Вы находитесь на странице: 1из 64

BLOWOUT PREVENTER (BOP)

FAILURE MODE EFFECT CRITICALITY ANALYSIS (FMECA)-3


FOR
THE BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT

2650788-DFMECA-3-D2
2650788-DFMECA-3-D2

4
3

2650788-DFMECA-3-D2

2650788-DFMECA-3-D2

Report No.

Revision

Final Report
Issued to BSEE as Draft
Issued to industry participants
(IPs) as Draft for comments
Issued as Draft for internal
review and comments
Purpose of Revision

6/28/2013
3/25/2013
3/7/2013
2/20/2013
Date

June 2013
This work was performed by American Bureau of Shipping and ABSG Consulting Inc. for the Bureau of
Safety and Environmental Enforcement (BSEE) under the terms of BSEE contract number M11PC00027.

THIS PAGE INTENTIONALLY LEFT BLANK

ii

LIST OF CONTRIBUTORS:
ABS Consulting
Randal Montgomery
Darshan Lakhani
ABS
Harish Patel
David Cherbonnier
Bibek Das

iii

SUMMARY
As part of the Blowout Preventer (BOP) Maintenance and Inspection for Deepwater Operations study
(Bureau of Safety and Environmental Enforcement [BSEE] contract number M11PC00027),
American Bureau of Shipping (ABS) and ABSG Consulting Inc. (ABS Consulting) performed a
Failure Mode, Effect, and Criticality Analysis (FMECA) on specific BOP subsystems and
equipment. There were three FMECAs performed with three different teams of operator, drilling
contractor and original equipment manufacturer. This is the draft report of the FMECA conducted
with team-3 and represents the study deliverable associated with Task 6.2.2.1 as outlined in the
contract.
This report presents the objective and scope of the FMECA study, FMECA methodology, FMECA
worksheets and discusses major findings of the two workshops (Functional-level and Equipmentlevel) that were conducted on a Class VIII BOP (6R,2A) and a Class VI BOP (4R,2A) configuration.
Summary of Objective and Scope
The objectives of the FMECA analysis were to:
(1) identify the causes and effects of loss of BOP system functionality,
(2) identify the causes and effects of individual equipment failures,
(3) establish the relationship between a specific equipment failure and a loss of system
functionality,
(4) identify the current protection and monitoring/indication methods associated with the system
and equipment failures,
(5) identify and align the current maintenance, inspection, and test (MIT) practices and their
associated frequencies with each functional failure and the associated equipment failures, and
(6) identify the critical failures by using criticality- or risk-ranking methods.
The BOP system, sub-systems and components within the scope of this study are presented in
Appendix E of this report.
Summary of FMECA Approach
The FMECA was conducted in two phases, first a functional-level and then an equipment-level
FMECA. The functional-level (top-down) FMECA was conducted to identify the failures that could
degrade the BOP system functions. The equipment-level (bottom-up) FMECA was conducted to
identify the impact of major equipment and component failures on the BOP system performance by
evaluating equipment-level failure modes, identifying specific equipment-level causes, identifying
the safeguards to prevent or detect the failure modes, and ranking the failure modes risks. In
addition, the equipment-level FMECA was used to identify MIT activities associated with
equipment-level failure modes and specific equipment failures.

iv

The team identified the eight BOP functions in American Petroleum Institute (API) 53 Standard,
Section 7.1.3. During the workshop a few more functions were either added or broken down into
additional functions based on different operating conditions/logic. In total 13 BOP functions/systems
and their 56 associated functional failures were studied in the functional-level FMECA. Appendix A
presents the Functional-FMECA Worksheets.
For the equipment-level FMECA, the team identified and evaluated 3 major BOP subsystems
(surface control, subsea control and stack) and 50 major associated equipment categories. The list of
equipment is presented in the report. The definition of the sub-systems and equipment are presented
in Appendix E.

In order to establish the criticality of each equipment-level failure mode, the team used a Risk
Priority Number (RPN) scoring methodology based on severity, occurrence, and detection. The
definition of severity, occurrence and detection are presented in the report. Appendix B presents the
equipment-level FMECA Worksheets.
Summary of Assessment

Solenoid Valve Fluid End - Subsea


Control
Tubing and piping - Subsea Control
SPM Valve - Single acting - Subsea
Control
Rigid Conduit - Surface Control & Rigid
Conduit Manifold Valve Subsea Control
Remote hydraulic regulator (HKR) &
manual hydraulic regulators (MKR), Pilot
operated check Valve (POCV) - Subsea
Control

Top 25%

Double-acting SPM (Subsea PlateMounted) Valves - Subsea Control


Shuttle Valves
Choke & Kill Lines and Valves
Annular
Pipe Ram

Top 15%

Top 10%

Based on the criticality ranking, the following equipment and their failure modes were identified as
the top 25% of the critical items contributing to the BOPs potential functional failure:

The Double-acting SPM Valves were assessed as one of the top 10% of equipment whose failure
could potentially have a severe effect. This is owing to the fact that these valves are used in the
autoshear, where failure can lead to worst case consequences. The team assessed the double-acting
SPM valves to have mechanical damage (as a dormant failure not leading to leaks) every five years
to once in every ten years caused by damage to the piston rod, poppet, cage, seal plate or piston
housing or seal wear. Due to the nature of the Autoshear Hydraulic Circuit, such damage can only be
detected when the BOP is pulled for inspections. However, it is to be noted that these valves are
rebuilt or rotated every 18 months. The high RPN rating is also due to the occurrence of external and
internal leaks caused by seal wear and other mechanical damage discussed above. Such leak events
are assessed to occur once every two years. A high frequency of rebuilding the valves and a high
frequency of wear leading to leaks call for a detailed look at the maintenance practices followed
during the overhaul. It is also to be noted that a comparative assessment with the failure data
collected from the drilling contractor and the original equipment manufacturer (OEM) did not show
any failures of the double-acting SPM valves discussed above. Hence, this item will be discussed
with the IPs to verify the assessment results.
The Shuttle Valve external leaks were assessed as one of the top 10% of critical equipment failures.
Shuttle valves are evaluated as a single point of failure and depending on the function, the valve
failure may lead to worst case consequences. The team assessed external leaks caused by seal leaks,
fittings or O-ring leaks to occur less than twice a year to at least once every year. It is also to be noted
that these leaks will not be detected until the function is fired. A review of maintenance practices
shows that these valves are rebuilt or rotated every 18 months and checked for tightness of fittings on
every trip. A comparative assessment with the failure data collected from the drilling contractor and
the OEM did not show high failure occurrences. This could be attributed to the limited amount of
available failure data collected owing to the unavailable historical records reported during the data
collection phase. However, in the case of such uncertainties, the judgment based on the experience of
the team members from the operator, drilling contractor and OEM should be relied upon during the
assessment.
The inability to operate the Choke and Kill lines and valves when needed while closed on the drill
pipe or on an open hole by rams, or to circulate the wellbore, were assessed to be in the top 25% of
the criticality rankings. Such failures were attributed to mechanical failure of these gate valves owing
to spring failure, damage to the piston/operator cylinder, damage to the gate/seat, damage to the tail
rod, damage to the grease plate which prevents the gate from moving, or failure of connections and
bolts possibly due to over-torqueing during a recheck of the bolt torque. Such failures were assessed
by the team to occur less than twice a year to at least once every year. A review of the MIT practices
showed that the gate and seat are replaced every 18 months. The valves undergo an overhaul
schedule every three years and a hydraulic chamber test every year. It is to be noted that these valves
are cycled or function tested every shift (12 hours), which makes the failure detectability fairly high.
It is also to be noted that multiple choke and kill valves are available, depending on the ram that is
being functioned. Hence the team lowered the failure occurrence ranking by giving credit for the
redundancy. A comparative assessment with the failure data collected from the drilling contractor

vi

and the OEM did show occurrences of gate valve failures during surface tests, and some significant
downtime associated with its repair when such failures occurred during operation. The failure data
also showed external leaks from choke and kill lines being detected during surface tests.
The preliminary FMECA results show the Annular to be in the top 25% of the critical equipment
list. The possibility of mechanical damage to the annular body was assessed as once every 2 to 5
years. Such damages caused either by cutting/milling debris in the wellbore fluid, or wear of the
sealing element due to normal operation, or any corrosion or erosion issues specific to the well bore
chemical or sea-water environment, will only be detected during visual inspection of the body and
elements at the end of well. Such wear or damages, if kept unchecked, and other seal leaks (like
adapter seal, piston inner & outer seals, bonnet seal) will lead to external leak events. The annulars
are overhauled every five years. A comparative assessment with the failure data collected from the
drilling contractor and the OEM did show a couple of occurrences of annular upper element failures
with significant downtime associated with its repair.
The Pipe Ram was also assessed as one of the top 25% of the critical equipment, owing to the
severity of the failure of the functions associated with their operation. The failure of the poppet,
damage to the piston rod/cylinder/lock, ram housing, damage to the door lock/hinges/bolts, and worn
ram packers were assessed to have the likelihood of occurrence of once every 2 to 5 years. The
review of MIT practices showed that the ram doors are overhauled every 3 years and the body every
5 years. Additionally the ram doors are opened and an internal inspection is performed with changing
the rubber elements on every trip. In addition to that, the locks and the ram cavity are inspected every
year. The door hinges are greased between wells. Apart from weekly functional and bi-weekly
pressure tests, wellbore pressure tests are performed every month to detect leaks. However, a
comparative assessment with the failure data collected from the drilling contractor and the OEM
showed that external leaks associated with the pipe rams were found only during tests on surface.
The external leaks caused by damage to the ball/ball seat or O-ring and tubing failure of the Solenoid
valve fluid end, leaks caused by failure of the seals and elements of single-acting SPM valves and
associated tubing and piping in the subsea hydraulic fluid lines, and plugging due to external debris
and Teflon tape, place these equipment items in the top 15% of the criticality list. The solenoid valve
fluid end and single-acting SPM valves have a rebuild or rotation period of 18 months. The external
leaks can be detected either by surface/subsea flow meter indication or by remotely operated vehicle
(ROV) visual monitoring during the weekly functional tests or during operation. A comparative
assessment with the failure data collected from the drilling contractor and the OEM showed several
occurrences of external leaks in SPM valves and tubing, mostly during tests on surface. One
occurrence of a tubing leak on one pod during operation led to a significant downtime event.
Owing to the mechanical damage and subsequent failure, the HKR and MKR regulators, and the
Pilot operated check valves (POCVs) were assessed as one of the top 25% of critical equipment.
These equipment items are rebuilt or rotated every 18 months, and tested on the surface before
deployment. The external leaks in the Rigid Conduit (Surface Control) and Rigid Conduit

vii

Manifold Valve (Subsea Control) were also categorized under the top 25% of critical equipment
failures. A comparative assessment with the failure data collected from the drilling contractor and the
OEM did not show high failure occurrences. This can also be attributed to the limited amount of
failure data collected owing to the unavailable historical records reported during the data collection
phase. However, in the case of such uncertainties, the judgment based on the experience of the team
members from the operator, drilling contractor and OEM should be relied upon during the
assessment.
The RPN results are presented to reflect the criticality of the functions that were assessed during the
FMECA. Table 3-3 lists the top 25% of effects/functional failures with the highest average RPN for
all of the equipment failures associated with that functional failure. Another way is to calculate the
number of occurrences of each equipment level failure linked to a functional failure as presented in
Table 3-4. However, the reader is advised that tables 3-3 and 3-4, and the method of the average RPN
score depend on the categorization of functions, categorization of equipment and the level of detailed
analysis, and results may slightly differ for different studies. It is suggested that the reader should
review the system and equipment breakdown for this particular study before assessing Tables 3-3 &
3-4.
The FMECA will also support the RAM modeling as appropriate. Specifically, the FMECA may be
used to provide operational and maintenance information, as well as, identification of dominant BOP
failures and protections.
This preliminary FMECA analysis and assessment report is submitted for review by the IPs. The
final report may bear the modifications suggested during the review process.

viii

TABLE OF CONTENTS
Section

Page

SUMMARY ......................................................................................................................................... iv
LIST OF TABLES .............................................................................................................................. xi
LIST OF FIGURES ............................................................................................................................ xi
LIST OF ACRONYMS ....................................................................................................................xiii
1.0

INTRODUCTION .................................................................................................................... 1

1.1

Objectives ............................................................................................................................... 1

1.2

Analysis Scope........................................................................................................................ 1

1.3

FMECA Team Members and Workshop Schedule ................................................................ 4

1.4

Report Organization................................................................................................................ 5

2.0

ANALYSIS METHODOLOGY .............................................................................................. 7

2.1

Analysis Approach.................................................................................................................. 7

2.2.1

Functional Level (Top-Down) FMECA .......................................................................... 9

2.2.2

Equipment Level (Bottom-Up) FMECA ........................................................................ 12

2.2.3

Evaluation and Ranking of Equipment Failure Modes (Criticality/Risk Ranking) ...... 14

3.0

FMECA RESULTS & ASSESSMENT ................................................................................ 19

4.0

CONCLUSION ....................................................................................................................... 47

5.0

REFERENCES ....................................................................................................................... 49

Appendix A Functional-Level FMECA Worksheets ................................................................. A-1


Appendix B Equipment-Level FMECA Worksheets ................................................................. B-1
Appendix C Equipment Criticality Sorted by RPN ................................................................... C-1
Appendix D Functional Failure Sorted by Average RPN ......................................................... D-1
Appendix E BOP Sub-System and Equipment Definitions ....... E-1

ix

THIS PAGE INTENTIONALLY LEFT BLANK

LIST OF TABLES
Table
1-2
1-3
2-1
2-2
2-3
2-4
2-5
3-1
3-2
3-3
3-4
3-5

Description
Page
IP FMECA Team Members....................................................................................................... 5
ABS and ABS Consulting FMECA Team Members ................................................................ 5
Functions and Functional Failures........................................................................................... 10
General Equipment Failure Modes ......................................................................................... 12
Severity Ratings....................................................................................................................... 15
Occurrence Ratings ........................................................................................................................ 16
Detection Ratings .................................................................................................................... 17
Functional Failure Ranking ..................................................................................................... 19
Failure Modes with Highest RPN Sorted by RPN ............................................................... 27
Failure Modes with S = 10, O 3, and D 5 ......................................................................... 32
Functional Failures with Highest Average RPN ..................................................................... 36
Functional Failures with Greatest Occurrences Due to Equipment Failures........................... 43

LIST OF FIGURES
Figure
Description
Page
2-1
General FMECA Approach ....................................................................................................... 8
2-2
Functional-Level FMECA Procedure...................................................................................... 10
2-3
Equipment-Level FMECA Procedures.................................................................................... 13

xi

THIS PAGE INTENTIONALLY LEFT BLANK

xii

LIST OF ACRONYMS
ABS
ABS Consulting
API
BOP
BSEE
C&K
CCSV
DDV
EDS
ERA
FMECA
HKR
HPU
IP
LMRP
MIT
MKR
MUX
OEM
ROV
RPN
SEM
SPM
UPS

American Bureau of Shipping


ABSG Consulting Inc.
American Petroleum Institute
Blowout Preventer
Bureau of Safety and Environmental Enforcement
Choke and Kill
Compensated Chamber Solenoid Valve
Direct Drive Valve (solenoid valve)
Emergency Disconnect System
Electronic Riser Angle
Failure Mode, Effect, and Criticality Analysis
Remote Hydraulic Regulator
Hydraulic Power Unit
Industry Participant
Lower Marine-Riser Package
Maintenance, Inspection, and Test
Manual Hydraulic Regulator
Multiplex
Original Equipment Manufacturer
Remote Operated Vehicle
Risk Priority Number
Subsea Electronic Module
Subsea Plate-Mounted (valve)
Uninterrupted Power Source

xiii

THIS PAGE INTENTIONALLY LEFT BLANK

xiv

1.0 INTRODUCTION
As part of the Blowout Preventer (BOP) Maintenance and Inspection for Deepwater Operations study
(Bureau of Safety and Environmental Enforcement [BSEE] contract number M11PC00027),
American Bureau of Shipping (ABS) and ABSG Consulting Inc. (ABS Consulting) performed
Failure Mode, Effect, and Criticality Analysis (FMECA) on specific BOP subsystems and
equipment. There were three FMECAs performed with three different teams of operator, drilling
contractor and original equipment manufacturer. This is the draft report of the FMECA conducted
with team-3 and represents the study deliverable associated with Task 6.2.2.1 as outlined in the
contract.
This report presents the objective and scope of the FMECA study, FMECA methodology, FMECA
worksheets and discusses major findings of the two workshops (Functional-level and Equipmentlevel) that were conducted on Class VIII BOP (6R, 2A) and Class VI BOP (4R, 2A) configurations.

1.1

OBJECTIVES

The objectives of the FMECA analysis were to:


(1) dentify the causes and effects of loss of BOP system functionality,
(2) identify the causes and effects of individual equipment failure,
(3) establish the relationship between a specific equipment failure and a loss of system
functionality,
(4) identify the current protection and monitoring/indication methods associated with the system
and equipment failures,
(5) identify and align the current maintenance, inspection, and test (MIT) practices and their
associated frequencies with each functional failure and the associated equipment failures,
and
(6) identify the critical failures by using criticality- or risk-ranking methods.

1.2

ANALYSIS SCOPE

The scope of this effort was the analysis of a selected BOP and associated equipment that meets the
following criteria:

Operation Location Gulf of Mexico (majority of the operation and maintenance to be from
the Gulf of Mexico)
Operating Depth 5,000 Feet and Deeper
BOP Configurations:
o Class VI BOP, five ram configuration and single annular or a four ram and dual annular
o Class VII BOP, five ram configuration and dual annular or a six ram and single annular
o Class VIII BOP, six ram configuration and dual annular (ram configurations can consist
of a combination of blind/shear ram, non-sealing casing ram and pipe ram preventers)

Since the drilling contractor and the operator were operating rigs in Gulf of Mexico using both Class
VIII BOP (6R, 2A) and Class VI BOP (4R, 2A) configurations from the same original equipment
manufacturer (OEM), ABS decided to include both configurations in the analysis. As pointed out by
the OEM, apart from the obvious difference in the stack configuration, the BOP multiplex control
system for the rig BOPs had a few differences including the type of solenoid valve and the voting
logic/redundancy of programmed logic controllers. The analysis included the compilation of
information from the industry participatns (IPs), followed by the review and analysis of the selected
BOPs and associated control systems used by the drilling contractor.

Figure 1-1. Class VI BOP Configuration Used in


Study

Figure 1-2. Class VIII BOP Configuration Used in


Study

The team identified eight BOP functions in American Petroleum Institute (API) 53 Standard, Section
7.1.3. During the workshop a few more functions were either added or broken down into additional
functions based on different operating conditions/logic. For example, the FMECA team determined
that the shear the drill pipe and seal the wellbore function needed to be broken down into three
functions based on different operating condition/logic. In total 13 BOP functions/system and their
56 associated functional failures were studied in the functional-level FMECA.
The following 13 BOP functions/system were studied in the functional-level FMECA:
1.
2.
3.
4.
5.
6.
7.

Close and seal on the drill pipe and allow circulation on demand
Close and seal on open hole and allow volumetric well control operations on demand
Strip the drill string using the annular BOP(s)
Hang-off the drill pipe on a ram BOP and control the wellbore
Controlled operation Shear the drill pipe and seal the wellbore
Emergency Operation Auto-Shear Shear the drill pipe and seal the wellbore
Emergency Operation Emergency Disconnect System (EDS) Shear the drill pipe and seal
the wellbore

8.
9.
10.
11.
12.
13.

Disconnect the lower marine-riser package (LMRP) from BOP stack


Circulate the well after drill pipe disconnect
Circulate across the BOP stack to remove trapped gas
Connect BOP and LMRP at landing (not included API 53)
Secondary Acoustic (not included API 53)
Secondary remotely operated vehicle (ROV) (not included API 53)

Note: Item 12 and 13 are not functional failures, but they were evaluated during the functional-level
FMECA as the team considered these systems as a vital contributor for safe operation of the BOP
stack and drilling rig. Since these were considered as standalone systems and not analyzed in the
equipment-level FMECA, there are no links between these items and the equipment-level FMECA.
For the equipment-level FMECA, the team identified and evaluated 3 major BOP subsystems
(surface control, subsea control and BOP stack (LMRP & lower stack)) and 50 major associated
equipment categories. The list of equipment is presented below (the numbering system followed in
the FMECA Worksheets has been retained).
Subsystem 1: Surface Control System
1. Surface Control: Power & multiplex (MUX) Electrical
1.1. Power Uninterrupted Power Source (UPS)
1.2. CCU
1.3. Driller Control Panel/RMP/SEP
1.4. MUX Reel
1.5. Slip Ring
1.6. MUX Communication Fiber Optic Ring
1.7. Hydraulic Power Unit (HPU) Panel
1.8. MUX Cable/Connector
2. Surface Control: Hydraulic
2.1. Glycol and Soluble Oil Tank
2.2. Filter & Glycol and Soluble Oil Pump
2.3. MRU and Level Switches
2.4. Mixing Pump
2.5. HPU Pump & Suction Strainer
2.6. High Pressure Discharge Filter
2.7. Rigid Conduit
2.8. Hotline
2.9. Surface Accumulators
Subsystem 2: Subsea Control System
3. Subsea Control: MUX Electrical
3.1. Subsea Electronic Module (SEM)

3.2. Solenoid Valve


3.3. Well bore P/T Probe
3.4. Electronic Riser Angle (ERA)
3.5. LMRP P/T Probe
4. Subsea Control: Hydraulic
4.1. Subsea Plate-Mounted (SPM) Manifold
4.2. Compensated Chamber and Depth Compensated Bladder
4.3. HKR Regulator
4.4. SPM Valve Single Acting
4.5. SPM Valve Double Acting
4.6. Pilot Operated Check Valve (POCV)
4.7. Tubing and Piping
4.8. Compensated Chamber Solenoid Valve (CCSV)/Direct Drive Valve (DDV) (solenoid
valve) Fluid End
4.9. Manual Hydraulic Regulator (MKR)
4.10. Subsea Accumulator (POD)
4.11. Subsea Accumulator (LMRP)
4.12. Pilot Manifold and Pilot Filter
4.13. Inlet/Supply Manifold and Supply Filter
4.14. Rigid Conduit Manifold
4.15. Gripper Assembly
Subsystem 3: Stack
5. BOP Stack
5.1. Annular
5.2. Blind Shear Ram
5.3. Pipe Ram
5.4. Casing Shear Ram
5.5. Choke & Kill Lines & Valves
5.6. Choke & Kill Hose
5.7. LMRP Connectors
5.8. Well Head Connectors
5.9. Spools (not applicable for the stacks studied)
5.10. Shuttle Valve
5.11. Clamps for Choke & Kill Hot Connection
5.12. Function hose
5.13. Accumulator DCB/Autoshear

For the major equipment boundaries included in the study, refer to the definitions presented in
Appendix E of this report. The referenced manuals and drawings are presented in Section 5 of this
report.

1.3

FMECA TEAM MEMBERS AND WORKSHOP SCHEDULE

The FMECA workshop team members included personnel from three IPs, ABS, and
ABS Consulting. The IPs participating included one or more representatives from an OEM, a drilling
contractor, and an operator. These individuals provided knowledge of the design, engineering,

operation, and maintenance of the BOP being evaluated. Table 1-2 lists the functional positions for
the IP personnel who participated in this study.

Table 1-2: IP FMECA Team Members


IP Organization
Position/Expertise
BOP OEM
Engineering Director
Project Manager
Manager Pressure Control
Electrical Supervisor Pressure Control
Engineering Consultant Pressure Control
Drilling Contractor
Manager Subsea systems
Operator
Well Delivery Manager
Drilling Supervisor

ABS personnel provided knowledge of the overall BOP operations and class society and regulatory
requirements applicable to BOP design and operation. Table 1-3 lists the ABS and ABS Consulting
personnel who participated in this study.
Table 1-3: ABS and ABS Consulting FMECA Team Members
Name
Organization
Title
Bibek Das
ABS
Senior Engineer II (Risk &
Reliability), Corporate
Technology
Darshan Lakhani
ABS Consulting
Lead Engineer
Harish Patel
ABS
Manager, Corporate
Technology - Drilling and
Process

Study Role
Workshop Chair
Study Scribe
Project Manager

To prepare for the FMECA studies, ABS and ABS Consulting held a FMECA kickoff meeting with
the IPs on August 14 and 15, 2012. The purpose of the kickoff meeting was to discuss the FMECA
approach and the analysis scope for all participants to have the same level of understanding of the
FMECA procedures.
The functional-level FMECA workshop was conducted during full-day sessions held on
September 18 through 20, 2012. The equipment-level FMECA workshop was conducted during fullday sessions held on October 1 through 5, 2012.

1.4

REPORT ORGANIZATION

Section 1 of this report has provided the objectives, scope, FMECA team composition and workshop
schedules. Section 2 of this report provides an overview of the methodology used to analyze the
BOPs selected functions and equipment to determine the critical failure modes and their effects.
Section 3 discusses the results of the effort. Section 4 provides the concluding remarks. Section 5
presents the referenced documents and drawings used during the FMECA study. Appendices A & B

present the functional-level FMECA and the equipment-level FMECA worksheets respectively.
Appendices C & D present criticality rankings for equipment and functional failures respectively.
Appendix E presents the BOP sub-system and equipment definitions.

2.0 ANALYSIS METHODOLOGY


In order to evaluate BOP MIT practices, reduce the risk of failures and improve the reliability of
BOP performance, it is essential to identify the BOPs critical failure modes and their effects.
Therefore, ABS and ABS Consulting selected and employed both functional- and equipment-level
FMECA methodologies to evaluate BOP functions and identify specific subsystem and equipment
failures of interest as outlined in Section 1.2, Analysis Scope.
This analysis methodology was chosen because it provided a means to establish a relationship among
(1) BOP system functions, (2) BOP system equipment failures, and (3) BOP system MIT practices
by:
Identifying the potential effects resulting from deviations to BOP system functions (i.e.,
functional failures) and equipment-level failure modes causing the BOP system functional
failures
Identifying the potential functional failures resulting from BOP system equipment failure
modes and specific equipment failures causing the BOP system equipment failure modes
Linking specific equipment failures to BOP system functional failures
Identifying the safeguards (i.e., inspection, tests, protection/redundancy and maintenance)
currently provided for preventing specific equipment failures resulting in BOP system
functional failures and the associated potential end effects
Identifying and aligning MIT activities associated with specific equipment-level and failure
mode
Risk-ranking the equipment-level failure modes.

2.1

ANALYSIS APPROACH

A FMECA is an inductive reasoning approach that (1) considers how the functional failures of each
system function or the failure modes of each component could result in system performance
problems and (2) helps evaluate safeguards that are in place (including engineered protections &
monitoring systems, human actions, and maintenance activities) to prevent, detect or mitigate such
problems. The main focus of a FMECA is to establish the cause-and-effect relationship between
potential equipment failures, functional failures, and the end effect of those failures, and to evaluate
the criticality of the postulated functional failure/failure mode.
Figure 2-1 represents the general FMECA methodology used in evaluating the BOP system.
Specifically, this study employed both functional- and equipment-level FMECA approaches (see
Step 3) with the explicit purpose of transitioning the functional-level FMECA to a more detailed
level to better ensure the alignment of MIT activities with specific equipment failures and link the
specific equipment failures with their potential impact of BOP performance via functional failures.
This FMECA approach is very similar to the approach employed in many classical reliabilitycentered maintenance approaches, which have the overall objective of determining the optimal
maintenance strategy for preserving system functionality via detection and prevention of equipment
failures.

Figure 2-1. General FMECA Approach

2.2

ANALYSIS PROCEDURES

This section summarizes the procedures and specific tools used in performing the functional- and
equipment-level FMEAs. In addition, the risk priority number approach that was used to risk rank the
functional failure effects & equipment failure mode pairs is provided. More explanation on the
ranking method is given in section 2.2.3.
In preparation for the FMECA, ABS engineers identified potential functional failures and equipmentlevel failure modes to help guide the analysis team. Functional- and equipment-level FMECA
sessions were held with BOP subject matter experts from the OEM, drilling contractor, and operator.
ABS facilitated and documented the analysis using ABS Consultings Enterprise LEADER software
tool.
2.2.1

Functional Level (Top-Down) FMECA

The functional-level FMECA was performed by analyzing each function and its associated functional
failures. The functional-level FMECA process is illustrated in Figure 2-2. In executing this
procedure, the following operating modes were applied:

Normal Drilling

Kick Control

Emergency Operation (e.g., disconnect)

Riding the Storm

In addition, the following are consequences of interest for identifying end effects of interest during
the functional-level FMECA:
Safety Effects

Inability to control well or maintain well integrity

Potential release of hydrocarbon to the atmosphere resulting in potential fire, Explosion,


and/or exposure to toxic materials causing injury or worse

Environmental Effects

Inability to control well or maintain well integrity

Potential release of hydrocarbons to the environment resulting in a minor, significant,


(<1,000 bbl.), (1,000 to 10,000 bbl.), or large (>10,000 bbl.) spill/atmospheric release

Significant Downtime

Failures requiring pulling of the LMRP or BOP Stack

Downtime exceeding 5 days

In evaluating potential end effects, the team evaluated the severities based on worst-case end effects
assuming that available safeguards do not prevent or mitigate the end effects. Therefore, the end
effects represent the potential severity and conservatively overstate the expected consequences.

Figure 2-2. Functional-Level FMECA Procedure


During the functional-level FMECA, the analysis team evaluated these 13 BOP functions/systems
and their 56 associated functional failures. Each function and its associated functional failures were
evaluated in detail by identifying (1) the potential end effects resulting from the functional failure,
(2) equipment-level causes and failure modes potentially resulting in the functional failure, and (3)
safeguards used to prevent or detect the potential functional failure and its associated equipmentlevel causes. The equipment-level causes and failure modes were then studied in detail during the
equipment-level FMECA workshop.
Secondary systems (functions 12 & 13 below) were evaluated in a similar manner but were not
assessed in the equipment-level FMECA. Appendix A presents the Functional-FMECA Worksheets.
Table 2-1: Functions and Functional Failures
No.
Function
Functional Failure Modes
Failure to close on drill pipe through annular(s)
1
Close and seal on the drill
pipe and allow circulation
Failure to close on drill pipe through pipe rams
on demand
Failure to seal or partial seal on drill pipe through
annular(s)
Failure to seal or partial seal on drill pipe through
pipe rams
Unintentional closing / opening
Failure to open/close fail-safe valves to seal
Close too slowly
Loss of containment

10

Table 2-1: Functions and Functional Failures (contd)


No.
Function
Functional Failure Modes
2
Close and seal on open hole Failure to close on open hole through blind-shear
rams
and allow volumetric well
control operations on
Unintentional closing / opening
demand
Failure to open/close fail-safe valves
Close too slowly
Loss of containment
3
Strip the drill string using
Failure to close annular
the annular BOP(s)
Failure to maintain stripping pressure
Failure to seal
4
Hang-off the drill pipe on a Failure of hang-off ram to close
ram BOP and control the
Failure to maintain closing pressure
wellbore
Failure to maintain locking
5
Controlled Operation-Shear Failure to close
the drill pipe and seal the
Failure to shear the drill pipe
wellbore
Failure to seal the wellbore
Unintentional closing / opening
Close too slowly
Loss of containment
6
Emergency Operation-Auto Failure to arm
shear- Shear the drill pipe
Failure to close
and seal the wellbore
Failure to shear the drill pipe
Failure to seal the wellbore
Unintentional closing / opening
Close too slowly
Loss of containment
Failure to close
7
Emergency OperationEDS- Shear the drill pipe
Failure to shear the drill pipe
and seal the wellbore
Failure to seal the wellbore
Unintentional closing / opening
Close too slowly
Loss of containment
Failure to disconnect the LMRP
8
Disconnect LMRP/BOP
Failure to disconnect the LMRP/BOP
Unintentional disconnect of the LMRP/BOP
9
Circulate the well after drill Failure to circulate
pipe disconnect
Failure to circulate at desired flow rate
Failure to open/close fail-safe valves
Failure to seal wellbore after drill pipe disconnect
Loss of containment
10
Circulate across the BOP
Failure to circulate
stack to remove trapped gas Failure to circulate at desired flow rate
Failure to open/close fail-safe valves
Loss of containment

11

Table 2-1: Functions and Functional Failures (contd)


No.
Function
Functional Failure Modes
11
Connect BOP and LMRP at Inadequate BOP connection
landing
Inadequate LMRP connection
12
Secondary Acoustic
Failure to disarm
Failure to arm
13
Secondary ROV
Failure to perform ROV intervention
2.2.2

Equipment Level (Bottom-Up) FMECA

The equipment-level FMECA was performed by analyzing each major piece of equipment with its
associated components using equipment-level failure modes. The major equipment items were
identified in the functional-level FMECA as critical equipment whose failure contributed to the
failure of the function. Figure 2-3 outlines the equipment-level FMECA process. To evaluate each
equipment item, a list of the general failure modes was developed during the FMECA kick-off
meeting and is provided in Table 2-2. During the equipment-level FMECA, the analysis team
modified these general equipment failure modes to describe the means in which each major
component can fail.
Table 2-2: General Equipment Failure Modes
Mechanical Failures

Electrical/Electronics Failure

External leak/rupture

Loss of or degraded power

Internal leak

Fails with no output signal/no


communication

Plugged

Fails with low or high output signal

Mechanical failure (e.g., fracture, galling, fatigue)

Erratic output

Corrosion/erosion

Fails to respond to input

Loss of function (general)

Short

Wear/Mechanical Damage

Loss of function (general)


Processing error (e.g. calculation error,
sequence error)

12

Figure 2-3. Equipment-Level FMECA Procedures


During the equipment-level FMECA workshop, the analysis team evaluated each major equipment
item by first identifying potential equipment-level failure modes and then postulating on specific
equipment failure causes resulting in each failure mode. The team then identified the potential effects
resulting from each failure mode. The effects were then identified and classified into various BOP
functional failures. Based on this classification the equipment-level failure modes were linked to the
corresponding BOP functional failure. Once these links were established, the team identified any
safeguards that are currently in place to detect, prevent or mitigate the failure mode. Appendix B
presents the equipment-level FMECA Worksheets.

13

2.2.3

Evaluation and Ranking of Equipment Failure Modes (Criticality/Risk Ranking)

To provide a consistent means to evaluate the relative criticality of the BOP subsystem and
equipment failures and to help judge the adequacy of MIT activities performed to prevent and detect
the failures, a Risk Priority Number (RPN) ranking scheme based the following factors was
employed:

Frequency of Failure of the Equipment Failure Mode


Level of Redundancy to Prevent Specific Failure from Resulting in Complete Loss of Safety
Critical Functions
Ability to Detect and Prevent the Failure Mode via system monitoring and MIT practices
Severity of the End Effect for each BOP Functional Failure

A RPN ranking for each functional failure associated with an equipment-level failure mode was
based on the product of the following three independent factors:

Severity Rating This rating assesses the severity of worst-case end effect for a given
functional failure. (Note: The functional failure end effects documented in the functionallevel FMECA were used to determine this rating assuming no redundancies are present.). The
severity was rated for potential hazard to personnel on the rig, potential environmental
impact, and potential downtime.
Occurrence Rating This rating assesses the likelihood of the failure mode resulting in the
functional failure and its stated end effect. Such an assessment is made by evaluating the
causes listed for the failure mode. The presence of redundant components and systems is
explicitly considered in this rating.
Detection Rating This rating assesses the likelihood of the current applicable MIT activities
and system monitoring techniques to detect the failure mode before it results in the functional
failure.

The severity, occurrence, and detection ratings are provided in Tables 2-3 through 2-5, respectively.
These ratings were then used to calculate a single RPN ranking for each functional failure effect &
equipment failure mode pair (i.e., RPN ranking for each functional failure associated with an
equipment-level failure mode) using the following equation:
RPN = Severity Rating X Occurrence Rating X Detection Rating
The individual RPN rankings provide a relative ranking of the risk associated with a given functional
failure effect-equipment failure mode pair. Thereby, providing a means to identify the most critical
equipment-level failure modes in overall BOP performance, as well as identifying the more critical
failure modes associated with a specific BOP functional failure.

14

Table 2-3: Severity Ratings


Severity Rank
Significance
Does not affect BOP
functionality; no
1
impact on safety and
environment.
Does not affect BOP
functionality but
2
needs to be corrected;
no impact on safety
and environment.
Partial loss of BOP
3
function; no loss of
well control.
Partial loss of BOP
function; no loss of
4
well control.

Personnel
No impact

Environment
Down Time
No impact
No downtime, repair can
be done while drilling
continues.

No impact

No impact

No impact

No impact

No downtime, repair can


be done at next
opportunity, drilling
continues.

Downtime of less than a


shift, stop drilling,
intervene and repair.
No impact No impact
Downtime between a
shift and 24 hours, stop
drilling, intervene and
repair.
Partial loss of BOP
No impact No impact
Downtime between 1 and
primary function if
7 days - stop drilling,
not corrected
intervene and repair
immediately.
(surface only).
Partial loss of BOP
Minor
Minor
Downtime between 8 and
primary function if
Injury; no
external
21 days - stop drilling,
not corrected
recordable subsea leak
intervene and repair
immediately.
lost time
(e.g., choke & (surface only).
kill [C&K]
connector
leak)
Loss of BOP primary Minor
Significant
Pulling LMRP only.
function.
Injury;
external
some lost subsea leak
time.
(e.g., major
connector
leak)
Loss of BOP primary Serious
<1000 BBL
Pulling LMRP/BOP
function.
Injury;
stack.
significant
lost time.
Loss of BOP primary Single
>1000BBL
Shut down of operations;
function.
Fatality;
drilling stopped and
multiple
major regulatory
serious
implications; changes to
injuries.
drilling schedule > 3
months.

15

Table 2-3: Severity Ratings (contd)


Severity Rank
Significance
Loss of BOP primary
function.
10

Personnel
Multiple
fatalities
and
injuries.

Table 2-4: Occurrence Ratings


Occurrence
Frequency/Rig Yr.
Ratings
10
>50+ events/ rig yr.
<50 events /rig yr. to 10 events /rig
9
yr.
8
<10 events /rig yr. to 4 events /rig yr.
7
<4 events /rig yr. to 2 events /yr.
6
<2 events /rig yr. to 1 event/yr.
<1 event /rig yr. to 1 event every 2 rig
5
years
<1 event every 2 rig years to 1 event
4
every 5 rig years
<1 event every 5 rig years to 1 event
3
every 10 rig years
<1 event every 10 rig years to 1 event
2
every 100 rig years
<1 event every 100 rig years
1

16

Environment
>10,000BBL
and severe
environmental
damage over a
large area.

Down Time
Shut down of
operations; drilling
stopped and major
regulatory implications;
total loss of asset.

Occurrence
Once a week or more often
Less than once a week to once a month
Less than once a month to once a quarter
Less than once a quarter to twice a year
Less than twice a year to once a year
Less than once a year to once every 2
years
Less than once every 2 years to once
every 5 years
Less than once every 5 years to once
every 10 years
Less than once every 10 years to 10%
chance every 10 years of operation
Less than 1% chance every 10 years of
operation

Table 2-5: Detection Ratings


Detection
Detection
Rating
Almost Certain
1

2
3
4
5
6
7-8
9
10

Likelihood of Detection

Very high probability of detection (>90% probability of


detection) by design controls (redundant or independent selfdiagnostic capability, independent alarms) will certainly detect
failures
Very High
High probability of detection (50 to 90% of detection) by
design controls (single device self-diagnostic capability, single
alarms, visual monitoring, leak monitoring, loss of fluid etc.)
will certainly detect failures
High
Probability of detection via weekly on-stream tests/inspections
will provide immediate detection of the failure
Moderately high
Probability of detection via monthly on-stream tests/inspections
will provide immediate detection of the failure
Moderate
Probability of detection via quarterly on-stream
tests/inspections will provide immediate detection of the failure
Low
Can only be detected during routine inspections/tests while the
BOP is pulled from the well
Very Low
Can only be detected during major PMs while the BOP is
pulled from the well
Remote
Can only be detected and/or corrected during major overhaul or
rebuilding-type activities
Absolute Uncertainty Currently no design controls or maintenance techniques in
place

17

THIS PAGE INTENTIONALLY LEFT BLANK

18

3.0 FMECA RESULTS & ASSESSMENT


This section summarizes the results of the FMECA analysisspecifically, the results of the
functional-level and equipment-level FMECAs which are provided in tabular format in
Appendices A and B, respectively. These appendices also include a description of the FMECA table
information.
The functional failures were ranked during the FMECA Workshop and the results are presented in
Table 3-1. The worst case ranking among the three groups was chosen as the severity ranking for
RPN calculations.
Table 3-1: Functional Failure Ranking
Severity
Function
1- Close and seal on the drill pipe and allow
circulation, on demand
No.:
Failure to close on drill pipe through
1.1.1
annular(s)
Failure to Provide Control Signal to Annular
1
or C&K Valves When Demanded
Failure to Supply Hydraulic Fluid &
Pressure to Annular & C&K Valves When
Demanded
2
3
Failure to Close Annular on Demand
4
Inability to Operate C&K Valves as Needed
5
Failure to open annular on demand
No.:
Failure to close on drill pipe through pipe
1.1.2
rams
Failure to Provide Control Signal to Pipe
1
Ram or C&K Valves When Demanded
Failure to Supply Hydraulic Fluid &
Pressure to Pipe Ram or C&K Valves When
Demanded
2
3
Failure to Close Pipe Ram on Demand
4
Inability to Operate C&K Valves as Needed
Failure to Open Pipe Ram on Demand (as
5
part of well control process)
No.:
Failure to seal or partial seal on drill pipe
1.1.3
through annular(s)
1
Failure of Annular to Seal on Demand
Failure to Maintain Adequate Sealing
2
Pressure on Annular ( high and low)
3
Partial seal - C&K Valves leaking

19

Personnel

Environment

Down
Time

8
1
1

8
8
1

8
8
8

10

10

10

10

10

10

10
1
1

10
10
1

10
10
8

8
8

8
8

8
8

Table 3-1: Functional Failure Ranking (contd)


Severity
Function
No.:
1.1.4

Failure to seal or partial seal on drill pipe


through pipe rams
1
Failure of Pipe Ram to Seal on Demand
Failure to Maintain Adequate Sealing
2
Pressure on Pipe Ram
3
Partial seal - C&K Valves leaking

No.:
1.1.5A
1
2
No.:
1.1.5B
1
2
No.:
1.1.6

Unintentional closing / opening - Annulars


Unintentional Closing
Unintentional Opening

Unintentional closing / opening -Pipe Rams


Unintentional Closing
Unintentional Opening
Failure to open / close Spring assisted valves
to seal
Failure to Actuate Under Failsafe
1
Conditions - NOT APPLICABLE
Failure to Adequately Seal Under Failsafe
2
Conditions-NOT APPLICABLE

No.:
1.1.7

Personnel

Environment

Down
Time

10
10

10
10

10
10

10

10

1
8

1
8

8
8

8
10

1
10

8
10

Closes too slowly - Annular


Actuates Too Slowly on Demand

Closes too slowly - Pipe Ram


Actuates Too Slowly on Demand

10

10

10

1
1

10
10

10
10

10

10

10

10

10

10

10
10

10
10

10
10

No.:
1.1.7
No.:
1.1.8

Loss of containment
1
External Leak
2
Rupture
2- Close and seal on open hole and allow volumetric
well control operations, on demand
No.:
Failure to close on open hole through blind
1.2.1
shear ram
Failure to Provide Control Signal to blind
1
shear ram or C&K Valves When Demanded
Failure to Supply Hydraulic Fluid & Pressure
to blind shear ram or C&K Valves When
Demanded
2
3
Failure to Close blind shear ram on Demand
Failure of blind shear ram to Seal on
4
Demand

20

Table 3-1: Functional Failure Ranking (contd)


Severity
Function

Failure to Maintain Adequate Sealing


Pressure on Blind shear ram ( high and low)
Inability to Operate C&K Valves as Needed
Unintentional closing / opening - Blind shear
ram
Unintentional Closing
Unintentional Opening
Failure to open / close Spring assisted valves
to seal
Failure to Actuate Under Failsafe Conditions
- NOT APPLICABLE
Failure to Adequately Seal Under Failsafe
Conditions-NOT APPLICABLE

Closes too slowly


Actuates Too Slowly on Demand

5
6
No.:
1.2.2
1
2
No.:
1.2.3
1
No.:
1.2.4

Personnel

Environment

10

10

Down
Time
10

10

10

10

10

10

10

10

10

1
1

10
10

10
10

1
1

1
1

8
8

No.:
1.2.5

Loss of containment
1
External Leak
2
Rupture
3- Strip the drill string using the annular BOP(s)
No.:
1.3.1
Failure to close annulars
Failure to Provide Control Signal to
1
Annulars When Demanded
Failure to Supply Hydraulic Fluid & Pressure
2
to Annulars
Failure to Close Annulars on Drill String on
3
Demand
No.:
1.3.2
Failure to maintain stripping pressure
Failure to Maintain Hydraulic Fluid &
1
Pressure to Annulars ( low and high pressure)
No.:
1.3.3
Failure to seal /lubrication
1
Failure of Annular to Seal on Demand
Failure to Maintain Adequate Sealing
2
Pressure on Annular ( high and low)

21

Table 3-1: Functional Failure Ranking (contd)


Severity
Function
4- Hang-off the drill pipe on a ram BOP and control
the wellbore
No.:
1.4.1
Failure of hang-off ram to close
Failure to Provide Control Signal to Hang-off
1
Ram When Demanded
Failure to Supply Hydraulic Fluid & Pressure
2
to Hang-off Ram
3
Failure to Close Hang off Ram on Demand
No.:
1.4.2
Failure to maintain closing pressure
Failure to Maintain Closing Pressure on
1
Hang-off Ram
No.:
1.4.3
Failure to maintain locking
1
Failure to Engage Lock on Hang-off Ram
No.:
Failure of hang-off ram to close in
1.4.4
preparation to Disconnect
Failure to Provide Control Signal to Hang-off
1
Ram in preparation to Disconnect
Failure to Supply Hydraulic Fluid & Pressure
to Hang-off Ram in preparation to
Disconnect
2
Failure to Close Hang off Ram in
3
preparation to Disconnect
5- Normal operation - Shear the drill pipe and seal
the wellbore
No.:
1.5.1
Failure to close
Failure to Provide Control Signal to Shear
1
Ram When Demanded
Failure to Supply Hydraulic Fluid & Pressure
2
to Shear Ram
No.:
1.5.2
Failure to shear the drill pipe
1
Failure to Shear Pipe
No.:
1.5.3
Failure to seal the wellbore
1
Failure of Shear Ram to Seal On Demand
Failure to Maintain Sealing Pressure on
2
Shear Ram ( failure to maintain seal)

22

Personnel

Environment

Down
Time

10

10

10

10

10

10

10

10

10

10

10

10

10

10

10

10

10

10

10

10

10

10
10

10
10

10
10

Table 3-1: Functional Failure Ranking (contd)


Severity
Function
No.:
1.5.4

Personnel

Environment

Down
Time

1
2

Unintentional closing / opening


Unintentional Closing
Unintentional Opening

8
10

1
10

8
10

Closes too slowly


Actuates Too Slowly on Demand

10

10

10

1
1

10
10

10
10

10

10

10

10

10

10

10

10

10

10
10

10
10

10
10

10

10

10

1
1

10
10

10
10

No.:
1.5.5
No.:
1.5.6

Loss of containment
1
External Leak
2
Rupture
6- Emergency Operation - Auto-Shear - Shear the
drill pipe and seal the wellbore
No.:
1.6.1
Failure to Arm
1
Failure to Provide Control Signal
No.:
1.6.2
Failure to close
Failure to Supply Hydraulic Fluid & Pressure
1
to Shear Ram
No.:
1.6.3
Failure to shear the drill pipe
Failure to Supply Hydraulic Fluid & Pressure
1
to Shear Ram
2
Failure to Shear Pipe
No.:
1.6.4
Failure to seal the wellbore
1
Failure of Shear Ram to Seal On Demand
Failure to Maintain Sealing Pressure on
2
Shear Ram
No.:
1.6.5
Unintentional closing / opening
1
Unintentional Closing
Unintentional Opening - NOT
2
APPLICABLE
No.:
1.6.6
Closes too slowly
1
Actuates Too Slowly on Demand
No.:
1.6.7
Loss of containment
1
External Leak
2
Rupture

23

Table 3-1: Functional Failure Ranking (contd)


Severity
Function
7- Emergency Operation - EDS - Disconnect and/or
Shear the drill pipe and seal the wellbore
No.:
1.7.1
Failure to close and/or disconnect
Failure to Provide Control Signal to Riser
1
connector when Demanded
Failure to Supply Hydraulic Fluid & Pressure
2
to Riser connector
3
Unintentional Closing
No.:
1.7.2
Failure to shear the drill pipe
1
Failure to Shear Pipe
No.:
1.7.3
Failure to seal the wellbore
1
Failure of Shear Ram to Seal On Demand
Failure to Maintain Sealing Pressure on
2
Shear Ram
No.:
1.7.4
Unintentional closing / opening
1
Unintentional Closing
2
Unintentional Opening
No.:
1.7.5
Closes too slowly
1
Actuates Too Slowly on Demand
No.:
1.7.6
Loss of containment
1
External Leak
2
Rupture
8- Disconnect the LMRP from the BOP stack
No.:
Failure to disconnect the LMRP from BOP
1.8.1
stack
Failure to Provide Disconnect Signal
1
(automatically or manually)
Failure of LMRP / BOP Connector to
2
Disengage
3
Failure of Hydraulic Fluid to Disconnect
4
Moves too slowly to disconnect
No.:
1.8.2
Unintentional disconnect of the LMRP
1
Spurious Disconnect Signal
2
Unintentional Manual Disconnect Signal

24

Personnel

Environment

Down
Time

10

10

10

10

10

10

1
1

10
10

10
10

10

10

1
1

10
10

10
10

1
1

1
1

8
8

10

10

Table 3-1: Functional Failure Ranking (contd)


Severity
Function
9- Circulate the well after drill pipe disconnect
No.:
1.9.1
Failure to circulate/seal the wellbore
Failure to Provide Control Signal (to open) to
1
C&K Valves when Demanded
Failure to Supply Hydraulic Fluid & Pressure
2
to C&K Valves
3
Inability to Operate C&K Valves as Needed
No.:
1.9.2
Failure to circulate at desired flow rate
Degraded Flow Pressure / Restricted Flow
1
Path
No.:
Failure to open / close fail-spring assist
1.9.3
valves to seal
1
Failure to close/partial close
No.:
Failure to seal wellbore after drill pipe
1.9.4
disconnect
Failure to Provide Control Signal to C&K
1
Valves when Demanded
Failure to Supply Hydraulic Fluid & Pressure
2
to C&K Valves
3
Inability to Operate C&K Valves as Needed
No.:
1.9.5
Loss of containment
1
External Leak
2
Rupture
10- Circulate across the BOP stack to remove
trapped gas
No.:
1.10.1 Failure to circulate
Failure to Provide Control Signal to C&K
1
Valves when Demanded
Failure to Supply Hydraulic Fluid & Pressure
2
to C&K Valves
3
Inability to Operate C&K Valves as Needed
No.:
1.10.2 Failure to circulate at desired flow rate
Degraded Flow Pressure / Restricted Flow
1
Path
No.:
Failure to open / close spring assist valves to
1.10.3 seal
1
Failure to close/partial close

25

Personnel

Environment

Down
Time

1
1

10
10

10
10

Table 3-1: Functional Failure Ranking (contd)


Severity
Function
No.:
1.10.4 Loss of containment
1
External Leak
2
Rupture
11- Connect BOP and LMRP at Landing
No.:
1.11.1 Inadequate BOP Connection
Failure of Wellhead Connector to Properly
1
Lock and Seal
2
Failure of Connector Integrity
Failure of Connector Integrity (during
3
operation)
No.:
1.11.2 Inadequate LMRP Connection
Failure of LMRP Connector to Properly
1
Lock and Seal
2
Failure of Connector Integrity
Failure of Connector Integrity (during
3
operation)
12- Secondary - Acoustic
No.:
1.12.1 Failure to disarm
1
Failure to provide Acoustic signal to disarm
No.:
1.12.2 Failure to arm
1
Failure to provide Acoustic signal to arm
13- Secondary - ROV
No.:
1.13.1 ROV Intervention
Failure to perform ROV intervention of
Riser connector/BOP stack function
Primary and secondary riser connector
1
unlock
2
Riser Connector gasket release
3
all stabs retract
4
Shear ram close
5
pipe ram close
stack connector primary and secondary
6
unlock
7
stack connector gasket release
8
stack connector gasket lock
26

Personnel

Environment

Down
Time

1
1

10
10

10
10

1
10

1
10

8
10

1
10

1
10

7
10

Not assessed in Equipment-level


FMECA RPN
1

1
1
2
Not assessed in Equipment-level
FMECA RPN

1
1
1
1
1

1
1
10
1
1

7
7
10
8
9

1
1

1
1

8
2

Table 3-1: Functional Failure Ranking (contd)


Severity
Function
9
10
11
12

Personnel

Environment

1
1
1
1

1
1
1
1

stack connector glycol injection


Visual inspection and monitoring
Shear Ram open
Pipe ram open

Down
Time
9
5
6
6

Table 3-2 shows the top 25% of equipment-level failure modes. These are considered to be the most
critical failure modes. RPN scores from the FMECA range from 1300, with the top 25% ranging
from 90300. Appendix C provides the complete table for these equipment-level failure modes based
on the RPN rankings. Note: The equipment/sub-system may be repeated in the table below for
different failure modes and functional failures.
Table 3-2: Failure Modes with Highest RPN Sorted by RPN
Equipment/
Subsystem
SPM Valve Double acting Subsea Control:
Hydraulic
Choke & Kill
Lines & Valves
- BOP Stack
SPM Valve Double acting Subsea Control:
Hydraulic
Choke & Kill
Lines & Valves
- BOP Stack
Pipe Ram BOP Stack
Pipe Ram BOP Stack
Annulars - BOP
Stack
Choke & Kill
Lines & Valves
- BOP Stack

Severity
(S)

Occurrence
(O)

Detection
(D)

RPN
(SxOxD)

# of Effects
(Functional
Failures)

External
Leak

10

300

Mechanical
Failure

270

Internal
Leak

10

240

240

10

200

10

200

192

192

Failure
Mode

Mechanical
Failure
External
Leak/
Rupture
Mechanical
Failure
Mechanical
Damage
Internal
Leak

27

Table 3-2: Failure Modes with Highest RPN Sorted by RPN (contd)
Equipment/
Subsystem

Failure
Mode

SPM Valve Double acting Subsea Control:


Hydraulic
Shuttle Valve BOP Stack

Mechani
cal
Damage/
Wear
External
Leak
External
Annulars - BOP
Leak/
Stack
Rupture
Mechani
Annulars - BOP
cal
Stack
Failure
Shuttle Valve External
BOP Stack
Leak
External
Tubing and piping Leak/
- Subsea Control: Mechani
cal
Hydraulic
Failure
CCSV/DDV
Fluid End Plugged
Subsea Control:
Hydraulic
External
Tubing and
Leak/
piping - Subsea
Mechani
Control:
cal
Hydraulic
Failure
CCSV/DDV
Fluid End Plugged
Subsea Control:
Hydraulic
External
Annulars - BOP
Leak/
Stack
Rupture
Mechani
Annulars - BOP
cal
Stack
Failure
Rigid Conduit Surface Control:
Hydraulic

Mechani
cal
Failure

Severity
(S)

Occurrence
(O)

Detection
(D)

RPN
(SxOxD)

# of Effects
(Functional
Failures)

10

180

10

180

160

160

154

10

150

17

10

150

13

135

135

128

128

10

120

13

28

Table 3-2: Failure Modes with Highest RPN Sorted by RPN (contd)
Equipment/
Subsystem

Failure
Mode

Severity
(S)

Occurrence
(O)

Detection
(D)

RPN
(SxOxD)

# of Effects
(Functional
Failures)

SPM Valve Single acting Subsea Control:


Hydraulic

External
Leak

10

120

17

SPM Valve Single acting Subsea Control:


Hydraulic

Mechani
cal
Failure/
Wear

10

120

13

Pilot operated
check Valve
(POCV) - Subsea
Control:
Hydraulic

External
Leak

10

120

Pilot operated
check Valve
(POCV) - Subsea
Control:
Hydraulic

Mechani
cal
Failure

10

120

Tubing and
piping - Subsea
Control:
Hydraulic

External
Leak/
Mechani
cal
Failure

120

10

Plugged

120

10

External
Leak

10

120

17

Mechani
cal
Failure/
Wear

10

120

13

Mechani
cal
Failure

108

CCSV/DDV
Fluid End Subsea Control:
Hydraulic
CCSV/DDV
Fluid End Subsea Control:
Hydraulic
Rigid Conduit
Manifold - SPM
valves - Subsea
Control:
Hydraulic
Rigid Conduit Surface Control:
Hydraulic

29

Table 3-2: Failure Modes with Highest RPN Sorted by RPN (contd)
Failure
Mode

Severity
(S)

Occurrence
(O)

Detection
(D)

RPN
(SxOxD)

# of Effects
(Functional
Failures)

External
Leak

108

Mechani
cal
Failure/
Wear

108

External
Leak

108

108

108

108

105

Plugged

105

External
Leak

10

100

17

External
Leak

10

100

17

HKR Regulator Subsea Control:


Hydraulic

Mechani
cal
Failure/
Wear

10

100

13

MKR Regulator Subsea Control:


Hydraulic

External
Leak

10

100

17

Equipment/
Subsystem
SPM Valve Single acting Subsea Control:
Hydraulic
SPM Valve Single acting Subsea Control:
Hydraulic
CCSV/DDV Fluid
End - Subsea
Control: Hydraulic
Rigid Conduit
Manifold - SPM
valves - Subsea
Control: Hydraulic
Choke & Kill
Lines & Valves BOP Stack
Choke & Kill
Lines & Valves BOP Stack
Tubing and piping
- Subsea Control:
Hydraulic
CCSV/DDV Fluid
End - Subsea
Control: Hydraulic
HKR Regulator Subsea Control:
Hydraulic
HKR Regulator Subsea Control:
Hydraulic

Mechani
cal
Failure/
Wear
External
Leak/
Rupture
Loss of
function
(general)
External
Leak/
Mechani
cal
Failure

30

Table 3-2: Failure Modes with Highest RPN Sorted by RPN (contd)
Equipment/
Subsystem
MKR Regulator Subsea Control:
Hydraulic
MKR Regulator Subsea Control:
Hydraulic
Rigid Conduit
Manifold - SPM
valves - Subsea
Control:
Hydraulic
Rigid Conduit Surface Control:
Hydraulic
SPM Valve Single acting Subsea Control:
Hydraulic
SPM Valve Single acting Subsea Control:
Hydraulic
CCSV/DDV
Fluid End Subsea Control:
Hydraulic
Rigid Conduit
Manifold - SPM
valves - Subsea
Control:
Hydraulic
Choke & Kill
Lines & Valves BOP Stack
HKR Regulator Subsea Control:
Hydraulic
HKR Regulator Subsea Control:
Hydraulic

Severity
(S)

Occurrence
(O)

Detection
(D)

RPN
(SxOxD)

# of Effects
(Functional
Failures)

10

100

13

10

100

External
Leak

10

100

17

Mechani
cal
Failure

96

10

External
Leak

96

10

Mechani
cal
Failure/
Wear

96

External
Leak

96

10

Mechani
cal
Failure/
Wear

96

10

External
Leak/
Rupture

96

External
Leak

90

Mechani
cal
Failure/
Wear

90

Failure
Mode
Mechani
cal
Failure/
Wear
Loss of
Function
(4th gen)

31

Table 3-2: Failure Modes with Highest RPN Sorted by RPN (contd)
Equipment/
Subsystem

Failure
Mode

Severity
(S)

Occurrence
(O)

Detection
(D)

RPN
(SxOxD)

# of Effects
(Functional
Failures)

MKR Regulator Subsea Control:


Hydraulic

External
Leak

90

MKR Regulator Subsea Control:


Hydraulic

Mechani
cal
Failure/
Wear

90

Rigid Conduit
Manifold - SPM
valves - Subsea
Control:
Hydraulic

External
Leak

90

Table 3-3 shows the equipment failure modes with a severity ranking of 10, an occurrence ranking
greater than or equal to 3 and a detection ranking greater than or equal to 5. These are the equipment
failures that occur most frequently and could result in the highest severity and are the hardest to
detect.
Table 3-3: Failure Modes with S = 10, O 3, and D 5
Equipment/
Subsystem
SPM Valve Double acting Subsea Control:
Hydraulic
SPM Valve Double acting Subsea Control:
Hydraulic
SPM Valve Double acting Subsea Control:
Hydraulic

Failure
Mode

# of Effects
Severity Occurrence Detection
RPN
(Functional
(S)
(O)
(D)
(SxOxD)
Failures)

External
Leak

10

300

Internal
Leak

10

240

Mechanical
Failure/Wear

10

180

32

Based on the criticality ranking, the following equipment and their failure modes were identified as
the top 25% of the critical items contributing to the BOPs potential functional failure:

Double-acting SPM Valves Subsea Control


Shuttle Valves
Choke & Kill Lines and Valves
Annular
Pipe Ram
Solenoid Valve Fluid End - Subsea Control
Tubing and piping - Subsea Control
SPM Valve - Single acting - Subsea Control
Rigid Conduit - Surface Control & Rigid Conduit Manifold Valve Subsea Control
HKR & MKR Regulators, Pilot operated check Valve (POCV) - Subsea Control

The Double-acting SPM Valves were assessed as one of the top 10% of equipment whose failure
could potentially have a severe effect. This is owing to the fact that these valves are used in the
autoshear application, where failure can lead to the worst case consequences. The team assessed the
double-acting SPM valves to have mechanical damage (as a dormant failure not leading to leaks)
every five years to once in every ten years caused by damage to the piston rod, poppet, cage, seal
plate or piston housing or seal wear. Such damage can only be detected when the BOP is pulled for
inspections. However, it is to be noted that these valves are rebuilt or rotated every 18 months. The
high RPN rating is also due to the occurrence of external and internal leaks caused by seal wear and
other mechanical damage discussed above. Such leak events are assessed to occur once every two
years. A high frequency of rebuilding the valves and a high frequency of wear leading to leaks call
for a detailed look at the maintenance practices followed during the overhaul. It is also to be noted
that a comparative assessment with the failure data collected from the drilling contractor and the
OEM did not show any failures of the double-acting SPM valves discussed above. Hence, this item
will be discussed with the IPs to verify the assessment results.
The Shuttle Valve external leaks were assessed as one of the top 10% of critical equipment failures.
Shuttle valves are evaluated as a single point of failure and depending on the function, the valve
failure may lead to worst consequences. The team assessed external leaks caused by seal leaks,
fittings or O-ring leaks to occur less than twice a year to at least once every year. It is also to be noted
that these leaks will not be detected until the function is fired. A review of maintenance practices
shows that these valves are rebuilt or rotated every 18 months and checked for tightness of fittings on
every trip. A comparative assessment with the failure data collected from the drilling contractor and
the OEM did not show high failure occurrences. This could be attributed to the limited amount of
available failure data collected owing to the unavailable historical records reported during the data
collection phase. However, in the case of such uncertainties, the judgment based on the experience of
the team members from the operator, drilling contractor and OEM should be relied upon during the
assessment.

33

The inability to operate the choke and kill lines and valves when needed while closed on the drill
pipe or on an open hole by rams, or to circulate the wellbore, were assessed to be in the top 25% of
the criticality rankings. Such failures were attributed to mechanical failure of these gate valves owing
to spring failure, damage to the piston/operator cylinder, damage to the gate/seat, damage to the tail
rod, damage to the grease plate which prevents gate from moving, or failure of connections and bolts.
Such failures were assessed by the team to occur less than twice a year to at least once every year. A
review of the MIT practices showed that the gate and seat are replaced every 18 months. The valves
undergo an overhaul schedule every three years and a hydraulic chamber test every year. It is also to
be noted that multiple choke and kill valves are available, depending on the ram that is being
functioned. Hence the team lowered the failure occurrence ranking by giving credit for the
redundancy. A comparative assessment with the failure data collected from the drilling contractor
and the OEM did show occurrences of gate valve failures during surface tests, and some significant
downtime associated with their repair when such failures occurred during operation. The failure data
also showed external leaks from choke and kill lines being detected during surface tests.
The preliminary FMECA results show the annular to be in the top 25% of the critical equipment list.
The possibility of mechanical damage to the annular body was assessed as once every 2 to 5 years.
Such damages caused either by cutting/milling debris in the wellbore fluid, or wear of the sealing
element due to normal operation, or any corrosion or erosion issues specific to the well bore chemical
or sea-water environment, will only be detected during visual inspection of the elements at the end of
well. Such wear or damages, if kept unchecked, and other seal leaks (like adapter seal, piston inner &
outer seals, bonnet seal) will lead to external leak events. The annulars are overhauled every five
years. A comparative assessment with the failure data collected from the drilling contractor and the
OEM did show a couple of occurrences of annular upper element failures with significant downtime
associated with its repair.
The pipe ram was also assessed as one of the top 25% of the critical equipment, owing to the severity
of the failure of the functions associated with their operation. The failure of the poppet, damage to
the piston rod/cylinder/lock, ram housing, damage to the door lock/hinges/bolts, and worn ram
packers were assessed to have the likelihood of occurrence of once every 2 to 5 years. The review of
MIT practices showed that the ram doors are overhauled every 3 years and the body every 5 years. In
addition to that, the locks and the ram cavity are inspected every year. The door hinges are greased
between wells. Apart from weekly functional and bi-weekly pressure tests, wellbore pressure tests
are performed every month to detect leaks. However, a comparative assessment with the failure data
collected from the drilling contractor and the OEM showed that external leaks associated with the
pipe rams were found only during tests on surface.
The external leaks caused by damage to the ball/ball seat or O-ring and tubing failure of Solenoid
valve fluid end, leaks caused by failure of the seals and elements of single-acting SPM valves and
associated tubing and piping in the subsea hydraulic fluid lines, place these equipment items in the
top 15% of the criticality list. The solenoid valve fluid end and single-acting SPM valves have a
rebuild or rotation period of 18 months. The external leaks can be detected either by surface/subsea

34

flow meter indication, by ROV visual monitoring during the weekly functional tests or during
operation. A comparative assessment with the failure data collected from the drilling contractor and
the OEM showed several occurrences of external leaks in SPM valves and tubing, mostly during tests
while on surface. One occurrence of a tubing leak on one pod during operation led to a significant
downtime event.
Owing to the mechanical damage and subsequent failure, the HKR and MKR regulators, and the
Pilot operated check valves (POCVs) were assessed as one of the top 25% of critical equipment.
These equipment items are rebuilt or rotated every 18 months. The external leaks in the Rigid
Conduit (Surface Control) and Rigid Conduit Manifold Valve (Subsea Control) were also
categorized under the top 25% of critical equipment failures. A comparative assessment with the
failure data collected from the drilling contractor and the OEM did not show high failure
occurrences. This can also be attributed to the limited amount of failure data collected owing to the
unavailable historical records reported during the data collection phase. However, in the case of such
uncertainties, the judgment based on the experience of the team members from the operator, drilling
contractor and OEM should be relied upon during the assessment.
The RPN results are presented to reflect the criticality of the functions that were assessed during the
FMECA. Table 3-4 lists the top 25% of effects/functional failures with the highest average RPN for
all of the equipment failures associated with that functional failure. The complete table is provided in
Appendix C. Another way of evaluating the data is to calculate the number of occurrences of each
equipment level failure linked to a functional failure as presented in Table 3-5. The complete table is
provided in Appendix D.
However, the reader is advised that Tables 3-3 and 3-4, and the method of the average RPN score
depend on the categorization of functions, categorization of equipment and the level of detailed
analysis, and results may slightly differ for different studies. It is suggested that the reader should
review the system and equipment breakdown for this particular study before assessing tables 3-3 &
3-4.

35

Table 3-4: Functional Failures with Highest Average RPN


Effects
Failure of Pipe Ram to Seal on Demand - Failure to
seal or partial seal on drill pipe through pipe rams Close and seal on the drill pipe and allow circulation,
on demand (linked to 1.1.4.1)
Failure to Maintain Adequate Sealing Pressure on
Pipe Ram - Failure to seal or partial seal on drill pipe
through pipe rams - Close and seal on the drill pipe
and allow circulation, on demand (linked to 1.1.4.2)
Partial seal - C&K Valves leaking - Failure to seal or
partial seal on drill pipe through annular(s) - Close
and seal on the drill pipe and allow circulation, on
demand (linked to 1.1.3.3)
Partial seal - C&K Valves leaking - Failure to seal or
partial seal on drill pipe through pipe rams - Close
and seal on the drill pipe and allow circulation, on
demand (linked to 1.1.4.3)
Failure to Close Annulars on Drill String on Demand
- Failure to close annulars - Strip the drill string using
the annular BOP(s) (linked to 1.3.1.3)
Inability to Operate C&K Valves as Needed - Failure
to circulate/seal the wellbore - Circulate the well after
drill pipe disconnect (linked to 1.9.1.3)
Failure to Close Annular on Demand - Failure to
close on drill pipe through annular(s) - Close and seal
on the drill pipe and allow circulation, on demand
(linked to 1.1.1.3)
Inability to Operate C&K Valves as Needed - Failure
to seal wellbore after drill pipe disconnect - Circulate
the well after drill pipe disconnect (linked to 1.9.4.3)
Inability to Operate C&K Valves as Needed - Failure
to close on drill pipe through pipe rams - Close and
seal on the drill pipe and allow circulation, on
demand (linked to 1.1.2.4)
Inability to Operate C&K Valves as Needed - Failure
to close on open hole through blind shear ram - Close
and seal on open hole and allow volumetric well
control operations, on demand (linked to 1.2.1.6)
Degraded Flow Pressure / Restricted Flow Path Failure to circulate at desired flow rate - Circulate
across the BOP stack to remove trapped gas (linked
to 1.10.2.1)

36

# of
Occurrence

Cumulative
FF RPN

Average
FF RPN

400

200

400

200

192

192

192

192

320

160

450

150

448

149

432

144

416

139

416

139

400

133

Table 3-4: Functional Failures with Highest Average RPN (contd)


Effects

# of
Occurrence

Cumulative
FF RPN

Average
FF RPN

Inability to Operate C&K Valves as Needed - Failure


to circulate - Circulate across the BOP stack to
remove trapped gas (linked to 1.10.1.3)
Inability to Operate C&K Valves as Needed - Failure
to close on drill pipe through annular(s) - Close and
seal on the drill pipe and allow circulation, on
demand (linked to 1.1.1.4)
Degraded Flow Pressure / Restricted Flow Path Failure to circulate at desired flow rate - Circulate the
well after drill pipe disconnect (linked to 1.9.2.1)
Failure of Annular to Seal on Demand - Failure to
seal or partial seal on drill pipe through annular(s) Close and seal on the drill pipe and allow circulation,
on demand (linked to 1.1.3.1)
Failure to Maintain Adequate Sealing Pressure on
Annular ( high and low) - Failure to seal or partial
seal on drill pipe through annular(s) - Close and seal
on the drill pipe and allow circulation, on demand
(linked to 1.1.3.2)
Failure to Supply Hydraulic Fluid & Pressure to
Shear Ram - Failure to close - Emergency Operation Auto-Shear - Shear the drill pipe and seal the
wellbore (linked to 1.6.2.1)
External Leak - Loss of containment - Close and seal
on the drill pipe and allow circulation, on demand
(linked to 1.1.8.1)
External Leak - Loss of containment - Close and seal
on open hole and allow volumetric well control
operations, on demand (linked to 1.2.5.1)
External Leak - Loss of containment - Emergency
Operation - EDS - Disconnect and/or Shear the drill
pipe and seal the wellbore (linked to 1.7.6.1)
External Leak - Loss of containment - Normal
operation - Shear the drill pipe and seal the wellbore
(linked to 1.5.6.1)
Failure to Supply Hydraulic Fluid & Pressure to Pipe
Ram or C&K Valves When Demanded - Failure to
close on drill pipe through pipe rams - Close and seal
on the drill pipe and allow circulation, on demand
(linked to 1.1.2.2)

400

133

516

129

504

126

832

119

832

119

41

3330

85

18

1486

83

19

1526

80

17

1240

73

17

1240

73

33

2260

73

37

Table 3-4: Functional Failures with Highest Average RPN (contd)


Effects
Failure to Supply Hydraulic Fluid & Pressure to
Shear Ram - Failure to shear the drill pipe Emergency Operation - Auto-Shear - Shear the drill
pipe and seal the wellbore (linked to 1.6.3.1)
Failure to close/partial close - Failure to open / close
fail-spring assist valves - Circulate the well after drill
pipe disconnect (linked to 1.9.3.1)
Failure to Supply Hydraulic Fluid & Pressure to
Shear Ram - Failure to close - Normal operation Shear the drill pipe and seal the wellbore (linked to
1.5.1.2)
Actuates Too Slowly on Demand - Closes too slowly
- Close and seal on open hole and allow volumetric
well control operations, on demand (linked to 1.2.4.1)
Actuates Too Slowly on Demand - Closes too slowly
- Emergency Operation - EDS - Disconnect and/or
Shear the drill pipe and seal the wellbore (linked to
1.7.5.1)
Actuates Too Slowly on Demand - Closes too slowly
- Normal operation - Shear the drill pipe and seal the
wellbore (linked to 1.5.5.1)
Failure to Supply Hydraulic Fluid & Pressure to
Hang-off Ram - Failure of hang-off ram to close Hang-off the drill pipe on a ram BOP and control the
wellbore (linked to 1.4.1.2)
Failure to Supply Hydraulic Fluid & Pressure to
Hang-off Ram in preparation to Disconnect - Failure
of hang-off ram to close- Hang-off the drill pipe on a
ram BOP in preparation to Disconnect (linked to
1.4.4.2)
External Leak - Loss of containment - Normal
operation - Shear the drill pipe and seal the wellbore
(linked to 1.5.6.1)
Failure to Supply Hydraulic Fluid & Pressure to Pipe
Ram or C&K Valves When Demanded - Failure to
close on drill pipe through pipe rams - Close and seal
on the drill pipe and allow circulation, on demand
(linked to 1.1.2.2)
Failure to Supply Hydraulic Fluid & Pressure to
Shear Ram - Failure to close and/or disconnect Emergency Operation - EDS - Disconnect and/or
Shear the drill pipe and seal the wellbore (linked to
1.7.1.2)

38

# of
Occurrence

Cumulative
FF RPN

Average
FF RPN

33

2260

73

33

2199

71

32

2120

71

31

2020

70

31

2020

70

31

2020

70

31

2020

70

31

2020

70

17

1240

73

33

2260

73

31

2020

70

Table 3-4: Functional Failures with Highest Average RPN (contd)


Effects
Actuates Too Slowly on Demand - Closes too slowly
- Emergency Operation - Auto-Shear - Shear the drill
pipe and seal the wellbore (linked to 1.6.6.1)
Failure of Annular to Seal on Demand - Failure to
seal /lubrication - Strip the drill string using the
annular BOP(s) (linked to 1.3.3.1)
Failure to Supply Hydraulic Fluid & Pressure to C&K
Valves - Failure to circulate/seal the wellbore Circulate the well after drill pipe disconnect (linked to
1.9.1.2)
Failure to Supply Hydraulic Fluid & Pressure to C&K
Valves - Failure to seal wellbore after drill pipe
disconnect - Circulate the well after drill pipe
disconnect (linked to 1.9.4.2)
Failure of Shear Ram to Seal On Demand - Failure to
seal the wellbore - Emergency Operation - AutoShear - Shear the drill pipe and seal the wellbore
(linked to 1.6.4.1)
Failure of Shear Ram to Seal On Demand - Failure to
seal the wellbore - Emergency Operation - EDS Disconnect and/or Shear the drill pipe and seal the
wellbore (linked to 1.7.3.1)
Failure of Shear Ram to Seal On Demand - Failure to
seal the wellbore - Normal operation - Shear the drill
pipe and seal the wellbore (linked to 1.5.3.1)
Failure to Close Pipe Ram on Demand - Failure to
close on drill pipe through pipe rams - Close and seal
on the drill pipe and allow circulation, on demand
(linked to 1.1.2.3)
Failure to Maintain Sealing Pressure on Shear Ram Failure to seal the wellbore - Emergency Operation Auto-Shear - Shear the drill pipe and seal the
wellbore (linked to 1.6.4.2)
Failure to Maintain Sealing Pressure on Shear Ram Failure to seal the wellbore - Emergency Operation EDS - Disconnect and/or Shear the drill pipe and seal
the wellbore (linked to 1.7.3.2)
Failure to Maintain Sealing Pressure on Shear Ram Failure to seal the wellbore - Normal operation Shear the drill pipe and seal the wellbore (linked to
1.5.3.2)

39

# of
Occurrence

Cumulative
FF RPN

Average
FF RPN

35

2210

67

34

2134

67

33

2037

66

33

2037

66

180

60

60

60

60

60

180

60

180

60

60

60

60

60

Table 3-4: Functional Failures with Highest Average RPN (contd)


Effects
Failure to Supply Hydraulic Fluid & Pressure to C&K
Valves - Failure to circulate - Circulate across the
BOP stack to remove trapped gas (linked to 1.10.1.2)
Failure to Maintain Adequate Sealing Pressure on
Annular ( high and low) - Failure to seal /lubrication Strip the drill string using the annular BOP(s) (linked
to 1.3.3.2)
Failure of Hydraulic Fluid to Disconnect - Failure to
disconnect the LMRP from BOP stack - Disconnect
the LMRP from the BOP stack (linked to 1.8.1.3)
Failure to Maintain Hydraulic Fluid & Pressure to
Annulars ( low and high pressure) - Failure to
maintain stripping pressure - Strip the drill string
using the annular BOP(s) (linked to 1.3.2.1)
Failure to Supply Hydraulic Fluid & Pressure to
Annulars - Failure to close annulars - Strip the drill
string using the annular BOP(s) (linked to 1.3.1.2)
Moves too slowly to disconnect - Failure to
disconnect the LMRP from BOP stack - Disconnect
the LMRP from the BOP stack (linked to 1.8.1.4)
Failure to Supply Hydraulic Fluid & Pressure to
Annular & C&K Valves When Demanded - Failure to
close on drill pipe through annular(s) - Close and seal
on the drill pipe and allow circulation, on demand
(linked to 1.1.1.2)
Actuates Too Slowly on Demand - Closes too slowly
- Close and seal on the drill pipe and allow
circulation, on demand (linked to 1.1.7.1)
Failure to Shear Pipe - Failure to shear the drill pipe Emergency Operation - Auto-Shear - Shear the drill
pipe and seal the wellbore (linked to 1.6.3.2)
Failure of Wellhead Connector to Properly Lock and
Seal - Inadequate BOP Connection - Connect BOP
and LMRP at Landing (linked to 1.11.1.1)
Failure of Blind Shear Ram to Seal on Demand Failure to close on open hole through blind shear ram
- Close and seal on open hole and allow volumetric
well control operations, on demand (linked to 1.2.1.4)
Failure to Close Blind Shear Ram on Demand Failure to close on open hole through blind shear ram
- Close and seal on open hole and allow volumetric
well control operations, on demand (linked to 1.2.1.3)

40

# of
Occurrence

Cumulative
FF RPN

Average
FF RPN

33

1824

59

29

1516

56

31

1622

56

31

1622

56

31

1622

56

31

1622

56

32

1638

55

33

1686

54

270

54

34

1718

54

100

50

100

50

Table 3-4: Functional Failures with Highest Average RPN (contd)


Effects
Failure of LMRP Connector to Properly Lock and
Seal - Inadequate LMRP Connection - Connect BOP
and LMRP at Landing (linked to 1.11.2.1)
Failure to Shear Pipe - Failure to shear the drill pipe Emergency Operation - EDS - Disconnect and/or
Shear the drill pipe and seal the wellbore (linked to
1.7.2.1)
Failure to Shear Pipe - Failure to shear the drill pipe Normal operation - Shear the drill pipe and seal the
wellbore (linked to 1.5.2.1)
Failure of Connector Integrity - Inadequate LMRP
Connection - Connect BOP and LMRP at Landing
(linked to 1.11.2.2)
Failure to close/partial close - Failure to open / close
fail-spring assist valves - Circulate across the BOP
stack to remove trapped gas (linked to 1.10.3.1)
External Leak - Loss of containment - Emergency
Operation - Auto-Shear - Shear the drill pipe and seal
the wellbore (linked to 1.6.7.1)
Failure of Connector Integrity - Inadequate BOP
Connection - Connect BOP and LMRP at Landing
(linked to 1.11.1.2)
Failure of LMRP / BOP Connector to Disengage Failure to disconnect the LMRP from BOP stack Disconnect the LMRP from the BOP stack (linked to
1.8.1.2)
Failure to Provide Control Signal to C&K Valves
when Demanded - Failure to circulate/seal the
wellbore - Circulate the well after drill pipe
disconnect (linked to 1.9.1.1)
Failure to Provide Control Signal to Hang-off Ram in
preparation to Disconnect - Failure of hang-off ram to
close - Hang-off the drill pipe on a ram BOP in
preparation to Disconnect (linked to 1.4.4.1)
Failure to Provide Control Signal to Hang-off Ram
When Demanded - Failure of hang-off ram to close Hang-off the drill pipe on a ram BOP and control the
wellbore (linked to 1.4.1.1)
Failure to Provide Control Signal to Pipe Ram or
C&K Valves When Demanded - Failure to close on
drill pipe through pipe rams - Close and seal on the
drill pipe and allow circulation, on demand (linked to
1.1.2.1)

41

# of
Occurrence

Cumulative
FF RPN

Average
FF RPN

34

1472

46

220

44

220

44

77

39

106

35

100

33

96

32

58

19

29

540

19

28

480

17

28

480

17

28

480

17

Table 3-4: Functional Failures with Highest Average RPN (contd)


Effects
Failure to Provide Control Signal to Shear Ram When
Demanded - Failure to close - Normal operation Shear the drill pipe and seal the wellbore (linked to
1.5.1.1)
Failure to Provide Control Signal to Shear Ram when
Demanded - Failure to close and/or disconnect Emergency Operation - EDS - Disconnect and/or
Shear the drill pipe and seal the wellbore (linked to
1.7.1.1)
Failure to Provide Control Signal - Failure to Arm Emergency Operation - Auto-Shear - Shear the drill
pipe and seal the wellbore (linked to 1.6.1.1)
Failure to Provide Control Signal to Annulars When
Demanded - Failure to close annulars - Strip the drill
string using the annular BOP(s) (linked to 1.3.1.1)
Failure to Provide Control Signal to C&K Valves
when Demanded - Failure to seal wellbore after drill
pipe disconnect - Circulate the well after drill pipe
disconnect (linked to 1.9.4.1)
Failure to Provide Control Signal to Annular or C&K
Valves When Demanded - Failure to close on drill
pipe through annular(s) - Close and seal on the drill
pipe and allow circulation, on demand (linked to
1.1.1.1)
Failure to Provide Control Signal to C&K Valves
when Demanded - Failure to circulate - Circulate
across the BOP stack to remove trapped gas (linked to
1.10.1.1)
Failure to Provide Disconnect Signal (automatically
or manually) - Failure to disconnect the LMRP from
BOP stack - Disconnect the LMRP from the BOP
stack (linked to 1.8.1.1)
Failure to Open Pipe Ram on Demand (as part of well
control process) - Failure to close on drill pipe
through pipe rams - Close and seal on the drill pipe
and allow circulation, on demand (linked to 1.1.2.5)
Failure to Close Hang off Ram on Demand - Failure
of hang-off ram to close - Hang-off the drill pipe on a
ram BOP and control the wellbore (linked to 1.4.1.3)

42

# of
Occurrence

Cumulative
FF RPN

Average
FF RPN

28

480

17

28

480

17

29

444

15

28

414

15

29

405

14

28

386

14

28

384

14

28

384

14

40

13

12

Table 3-4: Functional Failures with Highest Average RPN (contd)


Effects
Failure to Close Hang off Ram on Demand in
preparation to Disconnect - Failure of hang-off ram to
close - Hang-off the drill pipe on a ram BOP in
preparation to Disconnect (linked to 1.4.4.3)
Failure to Engage Lock on Hang-off Ram - Failure to
maintain locking - Hang-off the drill pipe on a ram
BOP and control the wellbore (linked to 1.4.3.1)
Failure to Maintain Closing Pressure on Hang-off
Ram - Failure to maintain closing pressure - Hang-off
the drill pipe on a ram BOP and control the wellbore
(linked to 1.4.2.1)

# of
Occurrence

Cumulative
FF RPN

Average
FF RPN

12

Table 3-5: Functional Failures with Greatest Occurrences Due to Equipment Failures
# of
Cumulative Average
Occurrences
FF RPN
FF RPN

Effect
Failure to Supply Hydraulic Fluid & Pressure to Shear
Ram - Failure to close - Emergency Operation - AutoShear - Shear the drill pipe and seal the wellbore (linked
to 1.6.2.1)
Actuates Too Slowly on Demand - Closes too slowly Emergency Operation - Auto-Shear - Shear the drill pipe
and seal the wellbore (linked to 1.6.6.1)
Failure of Annular to Seal on Demand - Failure to seal/
lubrication - Strip the drill string using the annular
BOP(s) (linked to 1.3.3.1)
Failure of Wellhead Connector to Properly Lock and
Seal - Inadequate BOP Connection - Connect BOP and
LMRP at Landing (linked to 1.11.1.1)
Failure of LMRP Connector to Properly Lock and Seal Inadequate LMRP Connection - Connect BOP and
LMRP at Landing (linked to 1.11.2.1)
Failure to Supply Hydraulic Fluid & Pressure to Pipe
Ram or C&K Valves When Demanded - Failure to close
on drill pipe through pipe rams - Close and seal on the
drill pipe and allow circulation, on demand (linked to
1.1.2.2)

43

41

3330

85

35

2210

67

34

2134

67

34

1718

54

34

1472

46

33

2260

73

Table 3-5: Functional Failures with Greatest Occurrences Due to Equipment Failures (contd)
# of
Cumulative Average
Occurrences
FF RPN
FF RPN

Effect
Failure to Supply Hydraulic Fluid & Pressure to Shear
Ram - Failure to shear the drill pipe - Emergency
Operation - Auto-Shear - Shear the drill pipe and seal
the wellbore (linked to 1.6.3.1)
Failure to close/partial close - Failure to open / close
fail-spring assist valves - Circulate the well after drill
pipe disconnect (linked to 1.9.3.1)
Failure to Supply Hydraulic Fluid & Pressure to C&K
Valves - Failure to circulate/seal the wellbore - Circulate
the well after drill pipe disconnect (linked to 1.9.1.2)
Failure to Supply Hydraulic Fluid & Pressure to C&K
Valves - Failure to seal wellbore after drill pipe
disconnect - Circulate the well after drill pipe disconnect
(linked to 1.9.4.2)
Failure to Supply Hydraulic Fluid & Pressure to C&K
Valves - Failure to circulate - Circulate across the BOP
stack to remove trapped gas (linked to 1.10.1.2)
Actuates Too Slowly on Demand - Closes too slowly Close and seal on the drill pipe and allow circulation, on
demand (linked to 1.1.7.1)
Failure to Supply Hydraulic Fluid & Pressure to Shear
Ram - Failure to close - Normal operation - Shear the
drill pipe and seal the wellbore (linked to 1.5.1.2)
Failure to Supply Hydraulic Fluid & Pressure to Annular
& C&K Valves When Demanded - Failure to close on
drill pipe through annular(s) - Close and seal on the drill
pipe and allow circulation, on demand (linked to 1.1.1.2)
Actuates Too Slowly on Demand - Closes too slowly Close and seal on open hole and allow volumetric well
control operations, on demand (linked to 1.2.4.1)
Actuates Too Slowly on Demand - Closes too slowly Emergency Operation - EDS - Disconnect and/or Shear
the drill pipe and seal the wellbore (linked to 1.7.5.1)
Actuates Too Slowly on Demand - Closes too slowly Normal operation - Shear the drill pipe and seal the
wellbore (linked to 1.5.5.1)
Failure to Supply Hydraulic Fluid & Pressure to Hangoff Ram - Failure of hang-off ram to close - Hang-off
the drill pipe on a ram BOP and control the wellbore
(linked to 1.4.1.2)

44

33

2260

73

33

2199

71

33

2037

66

33

2037

66

33

1824

59

33

1686

54

32

2120

71

32

1638

55

31

2020

70

31

2020

70

31

2020

70

31

2020

70

Table 3-5: Functional Failures with Greatest Occurrences Due to Equipment Failures (contd)
# of
Cumulative Average
Effect
Occurrences
FF RPN
FF RPN
Failure to Supply Hydraulic Fluid & Pressure to Hangoff Ram in preparation to Disconnect - Failure of hang31
2020
70
off ram to close- Hang-off the drill pipe on a ram BOP
in preparation to Disconnect (linked to 1.4.4.2)
Failure to Supply Hydraulic Fluid & Pressure to Shear
Ram - Failure to close and/or disconnect - Emergency
31
2020
70
Operation - EDS - Disconnect and/or Shear the drill pipe
and seal the wellbore (linked to 1.7.1.2)
Failure of Hydraulic Fluid to Disconnect - Failure to
disconnect the LMRP from BOP stack - Disconnect the
31
1622
56
LMRP from the BOP stack (linked to 1.8.1.3)
Failure to Maintain Hydraulic Fluid & Pressure to
Annulars ( low and high pressure) - Failure to maintain
31
1622
56
stripping pressure - Strip the drill string using the
annular BOP(s) (linked to 1.3.2.1)
Failure to Supply Hydraulic Fluid & Pressure to
Annulars - Failure to close annulars - Strip the drill
31
1622
56
string using the annular BOP(s) (linked to 1.3.1.2)
Moves too slowly to disconnect - Failure to disconnect
the LMRP from BOP stack - Disconnect the LMRP
31
1622
56
from the BOP stack (linked to 1.8.1.4)
Failure to Maintain Adequate Sealing Pressure on
Annular ( high and low) - Failure to seal /lubrication 29
1516
56
Strip the drill string using the annular BOP(s) (linked to
1.3.3.2)
Failure to Provide Control Signal to C&K Valves when
Demanded - Failure to circulate/seal the wellbore 29
540
19
Circulate the well after drill pipe disconnect (linked to
1.9.1.1)
Failure to Provide Control Signal - Failure to Arm Emergency Operation - Auto-Shear - Shear the drill pipe
29
444
15
and seal the wellbore (linked to 1.6.1.1)
Failure to Provide Control Signal to C&K Valves when
Demanded - Failure to seal wellbore after drill pipe
29
405
14
disconnect - Circulate the well after drill pipe disconnect
(linked to 1.9.4.1)
Failure to Provide Control Signal to Hang-off Ram in
preparation to Disconnect - Failure of hang-off ram to
28
480
17
close - Hang-off the drill pipe on a ram BOP in
preparation to Disconnect (linked to 1.4.4.1)

45

THIS PAGE INTENTIONALLY LEFT BLANK

46

4.0 CONCLUSION

Solenoid Valve Fluid End - Subsea


Control
Tubing and piping - Subsea Control
SPM Valve - Single acting - Subsea
Control
Rigid Conduit - Surface Control & Rigid
Conduit Manifold Valve Subsea Control
HKR & MKR Regulators, Pilot operated
check Valve (POCV) - Subsea Control

Figure 4-1. Equipment RPN range


47

Top 25%

Top 15%

Top 10%

The initial assessment showed that based on the criticality ranking, the following equipment and their
failure modes were identified as the top 25% of the critical items contributing to the BOPs potential
functional failure:
Double-acting SPM Valves - Subsea
Control
Shuttle Valves
Choke & Kill Lines and Valves
Annular
Pipe Ram

Figure 4-1 shows the top equipment RPN ranking range, median (separated by purple and green
lines) and inter-quartile distribution. The top 10% of equipment by RPN, as discussed, are Doubleacting SPM Valves, Shuttle Valves, Choke & Kill Lines and Valves, Annular and Pipe Ram.
Figure 4-2 shows the top failure modes and their RPN range. The top failure modes were external
and internal leaks, mechanical damage & failure and plugging.

Figure 4-2. Equipment Failure Modes RPN range


The MIT data and the failure data provided by the drilling contractor and the OEM were reviewed
against the FMECA results. The findings are presented in Section 3 of this report.
This preliminary FMECA analysis and assessment report is submitted for review by the IPs. The
final report may bear the modifications suggested during the review process.

48

5.0

REFERENCES

API 53 Standard
Drillers Well Control Manual
OEM Equipment Drawings, P&IDs, PFDs
Driller/OEM Equipment Operation and Maintenance Manuals
Drillers Failure data
Driller MIT data
OEM Failure data

49

THIS PAGE INTENTIONALLY LEFT BLANK

50

Вам также может понравиться