Академический Документы
Профессиональный Документы
Культура Документы
Epoxy container
Rigger container
Methanol tank
Hypochlorite tank
From your experiences, do you see examples where pipe or cable penetrations through fire rated
decks or walls are not made properly?
Should check of such items not be part of the preventive maintenance (PPM), i.e. check of safety
critical items (SCE's)?
Around a tank with diesel oil (environment, max. temperature 40 C), is it required to make
hazardous area classification here?
For a closed, pressurized heating medium system (30% glycol, 70 water) with valves and flanged
connections, operating at 130C, should be make hazardous area classification here?
The exercise:
a) Calculate the number of air changes per hour for this case
b) Evaluate the number of air changes against IP 15 requirements
c) Is it OK or not?
Are there other possible future expansion options than those mentioned in the lesson, we should take
into consideration in initial design?
No. 6, Offshore Crane
An offshore crane rated for a SWL of 45 tons @ radius = 12 meter for internal platform lift, what can
that approximately take (SWL) from a supply boat at same lifting radius, when the significant wave
height H1/3 = 1,5 m?
What harm can a turbine exhaust or excessive heat from a flare do to the crane wires?
On your installation, how is wire change planned to take place (where should reels for old wire and
reels for new wire be placed)? Is there sufficient space for this operation?
From your own experience, do you always see that the crane driver has overview both to the supply
boat and to the laydown areas?
What is most likely to happen when/if we overstress a pipe spool "too much"? (what is weakest)
When putting a pipe spool into position (during construction) how accurate should the measures
approximately be of the spool (+/- 1 mm, +/-10 mm, +/-50 mm)?
What is the correct thing to do, if you experience that hook-up spools are not accurate enough?
In your daily work, do you see examples where they are installed incorrect?
Do you see examples where "people" forget to remove them after 6 month 12 months time?
Somebody who have experienced that a temporary strainer has been sucked into a compressor or
pump?
How are air intakes for ventilation and combustion air arranged?
Do you see risks that a gas leak could reach such air intakes?
No. 16, Workshop facilities and store
What would the appropriate size be for the two workshops on a process installation with 30 50
POB?
Is it required that fire pumps located in unclassified area on an accommodation platform are enclosed
in firerated enclosures?
Have you experienced a fire pumps that fails to start on demand? Or have you heard about such
cases? Please give examples.
Do you have ideas to better arrangements of the pumps and lifting equipment?
No. 20, API 14J layout exercise
See separate documents, following pages.