Академический Документы
Профессиональный Документы
Культура Документы
SPE/IADC 21900
Incentive Contract: A Contractor's Viewpoint
T. Geehan* and J.P. Rospide, Sedco Forex Schlumberger
*SPE Member
ABSTRACT
them to maintain a viable working system.Time -dependent costs range between 40% to 70% of the total well
costs (see Ref. 1), this applies both to the operator and
the drilling c~:mtractor, thus a reduction in the time spent
on the ,,:ell IS adv~~geous to both. As drilling is the
core busmess of drillIng contractors a large reservoir of
experience and knowledge resides in-house, a means to
utilize this drilling expertise and extensive knowledge is
through the vehicle of incentive drilling contracts. In todays market place with higher utilization resulting in improved daily revenue for the drilling contractor the operators are looking for ways to improve efficiency and control total drilling costs. Again the mechanism of contracts
based on perfoffilance will play an ever increasing role.
The direction taken by one major operator to encourage
the integration of services with acceptance of a broader
range of liabilities (Ref. 2) could, if successful tend to
direct the industry standard contract to be partly ~r wholly incentive based. The use of incentive contracts re-orientates the participating members in the project to become
as identified with the quality of the fmal product as with
the perfoffilance of the day rate service, the quality element of the service is emphasized.
During the last five years the oil industry has experienced
a renewed interest in contracts which include some element of perfoffilance related renumeration for the contractor.This is not a new idea as footage and turnkey were
the nOffilal mode of contracting 20 to 25 years ago. The
reason for the latest upsurge in interest being the depressed state of the drilling contract market which has
lead drilling contractor companies to participate in risk
sharing in order to increase the revenue per unit time and
in doing so allowed
References and illustrations at the end ofthe paper.
27
* Turnkey
* Modified turnkey
* Footage
* Modified footage
* Incentive modified footage
SPE/IADC 21900
Another aspect which becomes obvious on reviewing incentive contracts over the last 3 to 5 years is the increasing component of non-drilling activities included as fixed
price/ lumpsum payments. On land opemtions such items
include site prepamtion, rig moves, remedial treatment of
waste pits and site clean ups. Offshore rig moves and
running anchors have also been included in incentive
contmcts. H this trend continues and expands then
28
SPEI lADe
wan
29
would be the loss of an MWD tool, costing approximately 500 kUS$, insurance coverage is very expensive.
Under day rate contracts the operator carries insurance
coverage for such items. If the drilling contractor includes the contingency of loss of an MWD per well or a
fraction of a MWD per well then the overall cost will increase.
Example
This example is not a case history but it is used to
demonstrate the concepts raised and the operational techniques used to increase efficiencies.
In France a modified turnkey project was undertaken on a
field development in the Parisian basin. It included a total
of 11 wells each with a total depth of approximately 2500
meters. The contract used the standard drilling programme as defmed by the operator to defme the scope of
work. As the project proceeded refinements and adjustments were made to allow an increase in performance.
The casing, liner and related equipment were supplied by
the operator. All other consumables and services:
-Bits
- Mud products
-cement
- Waste treatments
- Wrreline logs
were also included in the total price submitted by the
drilling contractor. The rig moves between locations were
also on a lumpsum basis. The mud engineering and
solids control operations were undertaken by the contractor's in-house service, the supply of chemicals and mud
products were sub-contracted to a mud company. The
processing of the drilling waste and site clean up were
also included the package and sub-contracted to a company with local experience.
Full turnkeys, in which all consumables and services
were included (see Ref. 1.), were also undertaken supplying a cased hole to given depth, the completion of the
wells was undertaken on day rate.
To aid in the rig site management of incentive contracts a
monitoring system was introduced in the France district
to control three aspects of the drilling operation;
1 Tripping
2 Running casing
3 Making up and testing the BOP's
In Figure 2 the tripping times for the rig concerned have
been plotted for some wells in the Parisian basin. From
the spread of results the average tripping time per 100
meters was determined as was the optimum. Then using
the form, see Table 2, performance criterion were set for
each trip and the results reported. An improvement in the
performance was observed in each of the areas monitored.
1..-
SPE/IADC 21900
SPEI lADe
An integral part of incentive contracts, as in day rate contracts, is a safe and environmentally sensitive working
culture. Thus all incentive contracts contain a safety element, in that if there is a lost time accident then all or part
of the bonus payable to the rig crew is penalized. A
strong point can be made that efficiency is gained through
good planning and implementation not haste and omissions. The safety policy in use at the rig site is always
taken as the most stringent between the local governmental regulation, operator's requirements and the contractors
own. To the safety policy has also been added environmental audits to ensure compliance with environmental
regulations. The operation of incentive contracts must be
in such a manner as not to contravene safety and environmental policies.
ACKNOWLEDGEMENT
1?e auth.ors wish t~ thank all their colleagues for the asSIstance m preparatIon of this paper and to the rig crews
through whose effort incentive contracts have been successful. ~e authors wish to thank in particular both
Frank WIlliford and Alan Mckee of Sedco Forex for their
contributions to the discussion on incentive contracts.
REFERENCES
1 D.W. Marshall "Incentive Drilling Operations in
Remote Locations", SPE/IADC 18669, presented at the
SPE/ IADC Drilling Conference, New Orleans March
. '
1989.
ner.
31
SPE 21900
Table 1 Matrix to determine mode of operation
Incentive Rate
Day Rate
Ref
Operation
Drilling
Hole Opening
Running Casing
Cementing
Surveying
Coring
Logging
Completlonsl Testing
10
Well Abandonment
11
Repairs
12
Miscellaneous waiting
13
Remedial operations
14
x
x
x
x
Note: Each of the sections can be further divided to give a more detailed system
WELL NUMBER
REPORT NUMBER
DATE
RIG
CPERATION
1 TRIPPING
D D
D D
out in
5" 3 1/2"
Depth
Objective
hrs
mlns
Result
hrs
mins
Comment
2 CASING
D D
13318" 951S"
20" 13 318"
7"
Other
D
9518"
7"
Depth
Objective
hrs
mlns
hrs
mlns
hrs
mins
Result
hrs
mlns
hrs
mins
hrs
mins
Comment
3 BOP'S
13318 951S
D
41/2
N/U
NlD
Objective
Result
Comment
Name of Rig. Supt.
Signature
32
Other
SPE 21900
YES
CONTRACTOR
NO
PARTICIPATION
OFFSET
YES
I-DATA
AVAILABLE
'" DAYRATE
'" OTHER
INCENTIVE
PACKAGES
'" INCENTIVE
MODIFIED
FOOTAGE
< 100%
..--
" OTHER
INCENTIVE
PACKAGES
CONTRACTOR
CONTRACTOR
TO FURNISH
YES
TO FURNISH
,.--IALL SUPPLI ES
MOST SUPPLIES
NO & SERVICES
& SERVICES
..-NO
*
*
DEGREE OF
CONTRACTOR
100%
I.RESPONSIBILITY
FOR WELL PLANN ING
& CONTROL
i* FOOTAGE
INCENTIVE
MODIFIED
FOOTAGE
MODIFIED
FOOTAGE
* MODIFIED
TURNKEY
INCENTI VE SPECTRUM
INCREASING CONTRACTOR
PARTICIPA TlON
I
~ TURNKEY
WELL #3
o*
o
WELL #4-
.6.
WELL #1
WELL #2
00
o
c
*
"
AVERAGE
- - - - - -
"
FIGURE 2 RIG XX TRIPPING TIME: POOH
33
YES
~
OPTIMUM