Академический Документы
Профессиональный Документы
Культура Документы
Manoj Barsaiyan
29 August 2012
Presentation Outline
Introduction
Bus arrangements
Bus protection techniques
network.
They can be open busbars in an outdoor switch yard, or
inside a metal clad cubicle restricted within a limited
enclosure with minimum phase-to-phase and phase-to
ground clearances.
They can be insulated as well as open
They form an electrical node where many circuits come
together, feeding in and sending out power
Introduction:
The requirements for good protection
Speed
Limit damage at fault point
Limit effect on fault stability
Selectivity
Trip only the faulted equipment
Important for busbars divided into zones
Stability
Not to operate for faults outside the zone
Most important for busbars
connected:
CT saturation often becomes a problem as CTs may not be
sufficiently rated for worst fault condition case
large dynamic forces associated with bus faults require fast
clearing times in order to reduce equipment damage
False trip by bus protection may create serious problems:
service interruption to a large number of circuits
(distribution and sub-transmission voltage levels)
system-wide stability problems (transmission voltage levels)
With both dependability and security important, preference is
always given to security
Bus arrangements :
Single bus - single breaker
ZONE 1
----
n-1
Bus arrangements :
Multiple bus sections - single breaker with bus tie
ZONE 1
ZONE 2
Bus arrangements :
Main and transfer buses
MAIN BUS
ZONE 1
TRANFER BUS
ZONE 2
ZONE 2
Breaker-and-a-half bus
ZONE 1
ZONE 2
Ring bus
L1
L2
TB1
B1
B2
TB1
L3
L4
51
Advantages
Simple
Low cost
Different ratios of CTs can be used with the help of Aux CT
Disadvantages
High operating time
All CTs must have equal ratio
Low sensitivity
Degree of CT saturation level to be very low
59
operates on voltage
developed across resistor
connected in secondary
circuit
Operating signal created
by connecting all CT
secondaries in parallel
VS
RCT
B
32
V = C x I ( C = 900 , = 0.25)
Advantages
It avoids the problem of unequal CT performances.
It uses high impedance voltage relay.
Highly sensitive and fast.
Disadvantages
All CTs must have equal Turns ratio
All CTs must have high Knee point voltage preferably
Percent Differential
87
51
52
DAU
52
DAU
DAU
CU
copper
fiber
installed in bays
Central Processing Unit (CPU)
processes all data from DAUs
Communications between DAUs
and CPU over fiber using
proprietary protocol
Sampling synchronisation
between DAUs is required
Perceived less reliable (more
hardware needed)
Difficult to apply in retrofit
applications
52
52
CU
copper
central processor
No communications, external
sampling synchronisation
necessary
Perceived more reliable (less
hardware needed)
Well suited to both new and
retrofit applications.
Isolators
Reliable Isolator Closed signals are needed for the
LBB PROTECTION
29 August 2012
53
LBB Protection
In EHV substations, reliability of fault detection is
enhanced by providing duplicated protections
(either main 1/main 2 or main and backup
protection)
The D.C. sources for protection are also duplicated
for better redundancy, circuit breakers are provided
with duplicated trip coils
All these measures, improve the reliability of fault
detection and isolation, however, the possibility of
mechanical failures of the switchgear or interrupter
flash over cannot be covered by these means
A failure of the breaker therefore, result, in spite of
correct operation of the protection and energisation
54
of trip coils
LBB Protection
Has
Protection
Operated?
No
Reset
Breaker
Failure
Protection
Normal
Operation
Yes
Yes
Start
Breaker
Failure
Protection
Wait for
Fault
Clearance
Fault
Cleared?
No
Trip
Main
Breaker(s)
Trip
Back-up
Breaker(s)
55
LBB Protection
This situation can be corrected by providing local breaker
Trip
Trip
Trip
LBB Protection
Typical setting range for the current check relay and follower
timer
Application
Generator Circuit
5-80%
All other circuits (TFRs 20-30%
/Lines /Bus Coupler
etc.)
5%
20%
0.1-1sec
0.1-1sec
0.2 sec
0.2 secs
61
LBB Protection
Fault
occurs
TIME- CHART
Current Detector
Dropout Time
Failed
Breaker
Breaker
Failure
Initiating
Margin
Back-up
Breaker
Interrupting
Breaker
Time
Failure
Tripping
62
THANK YOU
29 August 2012
63