Академический Документы
Профессиональный Документы
Культура Документы
Kasanyangan
Pipe Size
O.D. (m)
I.D. (m)
Length (m)
100
0.12
0.10
1114.00
1114.00
For Concreting
Location
Kasanyangan
0.00
OP/Day
Qty
Dur.
11.20
11.20
1.08
2.71
0.10
0.24
TOTAL
Location
Kasanyangan
0.00
no. of
Drainage
2.00
7.00
0.34
36.00
Materials
Kasanyangan
Sand
Gravel
Tie Wire (2% of RSB)
Reinforcing Steel Bar, Grade 40
8.00
28.00
4.00
75.60
1.73
0.76
10.26
0.54
1.08
8.74
436.95
14.00
189.70
4.34
1.90
25.75
1.36
2.71
25.16
1258.02
Kasanyangan
12.53
0.67
0.67
0.03
0.04
5.94
Qty
1.00
2.00
4.00
Qty
1.00
1.00
1.00
2.00
Concrete
Cutting/dem
no of 2.5 x
olition and
2.5
excavation
fee 7.93
1.00
Kasanyangan
Kasanyangan
total
7.93
Transfer of Serviceline
Location
No. of serviceline
17.00
Kasanyangan
38.00
0
Valve Box
Location
Kasanyangan
Php
-
Inter-connection work
Location
Number of Assembly
Kasanyangan
6
Php
6
Hydrotesting
H2O ( cu.m.) Chlorine (kg)
8.74
0.46
8.74
0.46
Asphalt
2"
4"
6"
8"
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Size of
Pipeline
Total
Duration
OP/Day
Qty
Dur.
4.90
14.70
1440.00
1440.00
416.14
1198.11
0.29
0.83
TOTAL
Drainage Crossing
150mm D.I. Sleeve Type
Flexible Coupling, (D.I.)
100.00
-
1.12
0.39
1.07
1.46
Assorted
Plywood
CWN
(1/2" x 4' x (1kg./100
8") - 4 uses bdft. Of
75.60
1.73 Lumber)
0.76
Lumber,
Good - 4
uses
Cement
4.00
14.00
189.70
4.34
1.90
10.26
25.75
18.00
265.30
6.06
2.65
36.01
Asphalt Cutting
Concrete
Cutting
Asphalt
Breaking
Concrete Breaking
Trench Width
0.42
4.00
Sand
Gravel
0.54
1.36
1.08 8.74
2.71 25.16
1.90
3.79
Reinforcing
Steel Bar,
Grade 40
436.95
1258.02
33.90
1694.96
excava tion
(cu.m.)
1.73
0.00
Tie Wire
(2% of
RSB)
Area
1.73
total
12.53
0.67
0.67
0.03
0.04
5.94
Item 201
302a
310 2"
310 4"
310 6"
310 8"
Fire
Hydrant
-
0.60
0.000
0.60
0.000
Hydrotesting
Blow-off
Assembly
Duration
Gasoline (litres)
2.23
8.91
8.91
BREAKDOWN OF EXPENDITURES
I - ESTIMATED COST
A. DIRECT COST:
1. Mobilization/Demobilization . . . . . . . . . . . . . . . . . . . . .
2. Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3. Labor (including fringe benefits) . . . . . . . . . . . . . . . . . .
4. Equipment Expenses . . . . . . . . . . . . . . . . . . . . . . . . .
% OF
0.
61
25
3.
B. INDIRECT COST:
1. Overhead contingency Miscellaneous . . . . . . . . . . . . . .
2. Profit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3. Comprehensive All Risk Insurance . . . . . . . . . . . . . . . .
4. Value Added Tax (5% of EDC, OCM and Profit) . . . . .
5. Materials Testing 7% of 1% of OCM . . . . . . . . . . . . . .
C. ENVIRONMENTAL COMPLIANCE AND PERMITS
1. Concrete Cutting/Demolition & Excavation Fee
2. Certificate of Non Coverage (CNC)
S U B - T O T A L (CONTRACT COST)
8.
0.6
0.2
100
0.
III - CONTINGENCIES/RESERVED:
1. Physical (up to 5% of the Estimated Contract Cost) . . . . . .
2. Price Escalation (up to 12% of the Estimated
Contract Cost) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3. Preliminary Engineering . . . . . . . . . . . . . . . . . . . . . . . . . .
SUB-TOTAL
TOTAL ESTIMATED PROJECT COST
PREPARED BY:
0.0
100
CHECKED & SUBMITTED BY:
EDITO M. B
Officer-In
DESIGN
APPROVED BY:
ARNULFO A. AL
AGM-Technical Serv
of the Philippines
CITY WATER DISTRICT
t, Zamboanga City
% OF TOTAL
AMOUNT
0.90
61.78
25.03
3.44
14,334.26
981,247.02
397,546.64
54,632.09
8.00
127,048.90
0.6045
0.2518
100.00
0.00
0.00
100.00
CHECKED & SUBMITTED BY:
9,601.20
4,000.00
1,588,410.11
0.00
0.00
1,588,410.11
ARNULFO A. ALFONSO
AGM-Technical Services Group
INDIVIDUAL PROGRAM OF
PROJECT TITLE:
Proposed Laying of 100mm PVC Pipeline Extention at Sittio Canucutan, Brgy. Pasonanca
LOCATIONS:
Sittio Canucutan, Brgy.Pasonanca, Zamboanga City
CITY: ZAMBOANGA CITY
PROJECT CATEGORY:
PIPELAYING 100mm PVC PIEPLINE
PROJECT DESCRIPTION:
LENGTH:
Description
No.
1
1
1
1
SPL-1
MOBILIZATION/DEMOBILIZATION
% OF
TOTAL
0.99%
SPL-2
TEMPORARY FACILITIES
1.15%
SPL-3
1.50%
SPL-4
ITEM NO.
SPL-7a
DESCRIPTION
Page 20 of 298
12.80%
45.44%
SPL-5
SPL-6
SPL-7
6.18%
1.34%
VALVES/FITTINGS/INTER-CONNECTION WORKS
2.71%
SPL-8
SPL-9
SPL-10a
SPL-10
12.36%
7.98%
2.06%
5.49%
100.00%
PREPARED BY:
Officer-In-Charge
DESIGN DIVISION
DESIGN DIVISION
ARNULFO A. ALFONSO
AGM-Technical Services Group
Page 21 of 298
APPROVED FOR P
ic of the Philippines
A CITY WATER DISTRICT
eet, Zamboanga City
L PROGRAM OF WORK
29-May-15
(Date)
APPROPRIATE:
SOURCE OF FUNDS:
ISSUED OBLIGATED:
1,588,410.11
AUTHORITY RELEASED:
CALENDAR DAYS TO COMPLETE:
75 C.D.
UPON APPROVAL
CONTRACT / /
ADMINISTRATION / X /
Description
CONSTRUCTION FOREMAN
SAFETY OFFICER
1
1
SKILLED WORKERS
CARPENTER
PAINTER
PIPEFITTER
LABORERS
20
ST OF PROPOSED PROJECTS
DIRECT COST
TOTAL
UNIT COST
14,334.26
14,334.26
ADJUSTED
UNIT
14,334.26
UNIT
QTY.
LOT
1.00
EACH
1.00
16,674.00
16,674.00
18,174.66
LOT
1.00
21,771.27
21,771.27
21,771.27
CU.M.
483.52
185,328.00
383.29
417.79
LN.M.
1156.20
657,899.00
569.02
620.23
Page 22 of 298
LN.M.
ASSEMBLY
6.82
1.00
89,431.20
19,365.00
13,113.08
19,365.00
14,293.26
21,107.85
UNIT
1.00
39,266.18
39,266.18
42,800.14
UNITS
3.00
178,893.90
59,631.30
64,998.12
UNITS
2.00
115,464.20
57,732.10
62,927.99
LN.M.
1163.00
29,807.00
25.63
27.94
cu.m.
483.52
79,526.00
164.47
179.28
1,447,760.01
APPROVED BY:
Page 23 of 298
PROJECT
:
Project Cost
:
Project Duration :
Php
1,588,410.12
GANTT CHART
Particulars
SPL-1
SPL-2
SPL-3
SPL-4
SPL-7a
SPL-5
SPL-6
SPL-7
SPL-8
SPL-9
SPL-10a
SPL-10
MANUAL BACKFILLING & COMPACTION WORKS OF NATIVE MATERIALS
TOTAL PROJECT COST
CASH LAYOUT REQUIREMENT
TARGETED COMPLETION THIS PERIOD
COMMULATIVE COMPLETION TO DATE
PREPARED BY:
ARNULFO A. ALFONSO
AGM-Technical Services Group
Amounts
15
CALENDAR DAYS
45
30
13,601.20
###
###
###
###
###
###
###
14,334.26
###
###
###
###
18,174.66
###
###
21,771.27
###
###
###
###
###
###
202,007.52
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
717,109.91
###
###
###
###
###
###
97,480.01
###
21,107.85
42,800.14
194,994.35
125,855.98
32,489.63
86,683.34
1,588,410.12 Php
90,596.35 Php
90,596.35
5.70%
5.70%
108,218.31 Php
108,218.31
6.81%
12.52%
911,328.79
911,328.79
57.37%
69.89%
APPROVED B
ENGINEERING &
CALENDAR DAYS
45
60
75
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Php
911,328.79 Php
911,328.79
57.37%
69.89%
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
311,693.28 Php
166,573.38
311,693.28
166,573.38
19.62%
10.49%
89.51%
100.00%
APPROVED BY:
ITEM
NO.
DESCRIPTION
QUANTITY
UNIT
ESTIMATED
DIRECT COST
(1)
(2)
(3)
(4)
(5)
SPL-1
SPL-2
1.00
1.00
1.00
LOT
LOT
EACH
SPL-3
1.00
SPL-4
SPL-7a
SPL-5
SPL-6
MARK-UPS
IN PERCENT
OCM
PROFIT
(6)
(7)
13,601.20
14,334.26
16,674.00
0%
0%
9%
0%
0%
0%
LOT
21,771.27
0%
0%
483.52
CU.M.
185,328.00
9%
0%
1,156.20
LN.M.
657,899.00
9%
0%
6.82
LN.M.
89,431.20
9%
0%
1.00
ASSEMBLY
19,365.00
9%
0%
SPL-7
2.00
UNIT
39,266.18
9%
0%
SPL-8
3.00
UNITS
178,893.90
9%
0%
SPL-9
2.00
UNITS
115,464.20
9%
0%
Page 27 of 298
SPL-10a
SPL-10
1,163.00
LN.M.
29,807.00
9%
0%
483.52
CU.M.
79,526.00
9%
0%
TOTAL
1,461,361.21
PREPARED BY:
Officer-In-Charge
DESIGN DIVISION
ARNULFO A. ALFONSO
AGM-Technical Services Group
Page 28 of 298
APPROVED FOR P
Zamboanga City
Contract Duration: 75 Calendar Days
TOTAL MARK-UP
VAT
TOTAL
INDIRECT COST
TOTAL COST
UNIT
COST
0%
0%
9%
VALUE
(9)
(5)X(8)
0.00
0.00
1,500.66
(10)
0%((5)+(9))
0.00
0.00
0.00
(11)
(9)+(10)
0.000
0.000
1,500.660
(12)
(5)+(11)
13,601.20
14,334.26
18,174.66
(13)
(12)/(3)
0.00
14,334.26
18,174.66
0%
0.00
0.00
0.000
21,771.27
21,771.27
9%
16,679.52
0.00
16,679.520
202,007.52
417.79
9%
59,210.91
0.00
59,210.910
717,109.91
620.23
9%
8,048.81
0.00
8,048.810
97,480.01
14,293.26
9%
1,742.85
0.00
1,742.850
21,107.85
21,107.85
9%
3,533.96
0.00
3,533.960
42,800.14
21,400.07
9%
16,100.45
0.00
16,100.450
194,994.35
64,998.12
9%
10,391.78
0.00
10,391.780
125,855.98
62,927.99
%
(8)
Page 29 of 298
9%
2,682.63
0.00
2,682.630
32,489.63
27.94
9%
7,157.34
0.00
7,157.340
86,683.34
179.28
1,588,410.12
APPROVED BY:
Page 30 of 298
LOT
Designation
A.
No. P
Labor
N/A
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
N/A
Sub-Total for B
Total (A+B)
N/A
No. of
Qua
Fees
a.
b.
480
1
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
Amount
P
No. of Units
No. of Days
Daily Rate
Amount
Quantity
Unit
480.06
1
sq.m.
lot
Unit Cost
20.00
4,000.00
Amount
9,601.20
4,000.00
P
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
13,601.20
13,601.20
13,601.20
13,601.20
MOBILIZATION/DEMOBILIZATION
LOT
Designation
A.
No. P
Labor
N/A
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
N/A
Sub-Total for B
Total (A+B)
N/A
No. of
Mobilization/Demobilization
Note: Per D.O. 22 series 2015, Mobilization/Demobilization should not exceed
1% of estimated Direct Cost
Qua
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
Amount
P
No. of Units
No. of Days
Daily Rate
Amount
P
-
Quantity
Unit
Unit Cost
Amount
1,433,425.75
14,334.26
P
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
14,334.26
14,334.26
14,334.26
14,334.26
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
TEMPORARY FACILITIES
each/day
each
Designation
A.
Labor
a.
Construction Foreman/Engineering Assistant
b.
Skilled Laborers
c.
Laborers
No. Person
1
2
6
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
Sub-Total for B
Total (A+B)
0.50
each
Materials
a.
4 pcs. - 2" x 4" x 8' (Coco Lumber)
b.
4 pcs. - 2" x 3" x 8' (Coco Lumber)
c.
20 pcs. - 2" x 2" x 10' (Coco Lumber)
d.
*12mm Thk x 1.20m x 2.40m Ordinary Plywood
e.
GA # 26 x 10' Corrugated G.I. Sheet
f.
3" C.W. Nail
* ALL SIZES REFERRED HEREIN SHOULD MEAN COMMERCIALLY AVAILABLE
MEASUREMENTS TOLERANCE OF 1mm
Sub-Total for E
F.
No. of Units
Quantity
21
16
67
6.00
6.00
2.00
G.
H.
I.
J.
k.
PRICE ANALYSIS
ROJECT
No. Person
No. of Days
Daily Rate
1
2
6
2.00
2.00
2.00
524.00
366.00
317.00
1,048.00
1,464.00
3,804.00
P
No. of Units
No. of Days
Amount
Daily Rate
6,316.00
Amount
P
6,316.00
Quantity
Unit
21
16
67
6.00
6.00
2.00
bd. ft.
bd. ft.
bd. ft.
pcs.
pcs.
kgs.
Unit Cost
Amount
20.00
20.00
20.00
950.00
410.00
59.00
426.67
320.00
1,333.33
5,700.00
2,460.00
118.00
10,358.00
16,674.00
1,500.66
18,174.66
18,174.66
DETAILED UNIT
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPL-3
LOT
N/A
1.00
LOT
Designation
A.
Labor
a.
Laborers
b.
Painter
c.
Carpenter
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
N/A
Sub-Total for B
Total (A+B)
N/A
Materials
Project Signage
a.
b.
c.
d.
e.
f.
d.
e.
f.
g.
h.
i.
j.
Page 44 of 298
a.
b.
c.
d.
e.
f.
g.
h.
Sub-Total for E
F.
G.
H.
I.
J.
k.
Page 45 of 298
OT
ation
No. Person
No. of Days
Daily Rate
2
1
1
6
6
6
317.00
366.00
366.00
Capacity
No. of Units
No. of Days
Daily Rate
ywood
y Plywood
Amo
b-Total for B
otal (A+B)
ecifications
3
2
2
P
b-Total for A
Amo
Quantity
Unit
Unit Cost
1
33
60
2
1
1
unit
bd.ft.
bd.ft.
shts.
kg.
kg.
787.50
20.00
20.00
800.00
59.00
58.00
1
1
70
2.00
bd.ft.
shts.
20.00
800.00
1
1
1.50
kgs.
59.00
Page 46 of 298
Amo
1.50
1
1
1
2
2
10
Page 47 of 298
kgs.
gal.
gal.
pcs.
pcs.
pcs.
ln.ft.
58.00
937.75
683.55
85.00
35.00
65.00
37.00
40
1
2
0.10
0.25
10
1
1
bd.ft.
kg.
bags
cu.m
cu.m
ln.ft.
gal.
gal.
20.00
51.00
280.00
1,000.00
1,000.00
37.00
937.75
683.55
b-Total for E
13
21
21
21
Page 48 of 298
rgy. Pasonanca
Amount
3,804.00
2,196.00
2,196.00
8,196.00
Amount
8,196.00
Amount
787.50
666.67
1,200.00
1,600.00
59.00
58.00
1,400.00
1,600.00
88.50
Page 49 of 298
87.00
937.75
683.55
85.00
70.00
130.00
370.00
Page 50 of 298
800.00
51.00
560.00
100.00
250.00
370.00
937.75
683.55
13,575.27
21,771.27
21,771.27
21,771.27
Page 51 of 298
FINAL STAKING/LAYOUTING
LN.M./DAY
LN.M.
Designation
A. Labor
a.
Construction Foreman
b.
Skilled Worker
c.
Laborer
No. Person
1
2
4
Sub-Total for A
Name and Capacity
No. of Units
B. Equipment
N/A
C.
D. Output per day
Sub-Total for B
Total (A+B)
500.00
LN.M.
Quantity
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. of Days
Daily Rate
2.23
2.23
2.23
524.00
394.00
317.00
1,167.47
1,755.66
2,825.10
P
No. of Days
Amount
Daily Rate
5,748.24
Amount
P
5,748.24
Unit
Unit Cost
Amount
P
10% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
5,748.24
574.82
6,323.06
5.68
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Designation
A.
Labor
a.
Construction Foreman
b.
Laborers
c.
Skilled Worker
No. P
1
1
1
Sub-Total for A
Name and Capacity
B.
C.
D.
No. of
Equipment
N/A
Sub-Total for B
Total (A+B)
363.10
LN.M./DAY
Qua
E.
Materials
N/A
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
1
1
2
2
2
524.00
317.00
366.00
1,048.00
634.00
732.00
P
No. of Units
No. of Days
Amount
Daily Rate
2,414.00
Amount
P
2,414.00
Quantity
Unit
Unit Cost
Amount
P
6% per D.O. 29 s 2011
8% per D.O. 29 s 2011
12% per D.O. 29 s 2011
2,414.00
144.84
193.12
330.24
3,082.20
4.24
CU.M./DAY
CU.M.
Designation
A.
No.
Labor
a.
Laborers
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Dump Truck (3 cu.m.)
Minor Tools (10%)
Sub-Total for B
Total (A+B)
24.00
CU.M./DAY
No.
Materials
N/A
Qu
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
Amount
Err:509
317.00
Err:509
Err:509
No. of Units
No. of Days
Daily Rate
Amount
Err:509
10,816.00
Err:509
Err:509
Quantity
Unit
Unit Cost
Err:509
Err:509
Amount
P
6% per D.O. 29 s 2011
0% per D.O. 29 s 2011
0% per D.O. 29 s 2011
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
CU.M./DAY
CU.M.
Designation
A.
No.
Labor
a.
Laborers
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Dump Truck (3 cu.m.)
Minor Tools (10%)
Sub-Total for B
Total (A+B)
24.00
CU.M./DAY
No.
Materials
N/A
Qu
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
317.00
Amount
P
No. of Units
No. of Days
Daily Rate
10,816.00
Amount
Quantity
Unit
Unit Cost
Amount
P
-
CU.M./DAY
CU.M.
Designation
A.
No.
Labor
a.
Laborers
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Dump Truck (3 cu.m.)
Minor Tools (10%)
Sub-Total for B
Total (A+B)
24.00
CU.M./DAY
No.
Materials
N/A
Qu
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
317.00
Amount
P
No. of Units
No. of Days
Daily Rate
10,816.00
Amount
Quantity
Unit
Unit Cost
Amount
P
-
LOT
Designation
A.
No.
Labor
a.
Laborers
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Boom Truck
Minor Tools (10%)
Sub-Total for B
Total (A+B)
N/A
No.
Materials
N/A
Qu
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
317.00
5,072.00
P
No. of Units
No. of Days
Daily Rate
7,698.00
Unit
5,072.00
Amount
15,396.00
507.00
Quantity
Amount
Unit Cost
15,903.00
20,975.00
Amount
P
6% per D.O. 29 s 2011
0% per D.O. 29 s 2011
0% per D.O. 29 s 2011
20,975.00
1,258.50
22,233.50
22,233.50
LOT
Designation
A.
No.
Labor
a.
Laborers
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Dump Truck (3 cu.m.)
Minor Tools (10%)
Sub-Total for B
Total (A+B)
N/A
No.
Materials
N/A
Qu
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
12
317.00
30,432.00
P
No. of Units
No. of Days
Daily Rate
12
10,816.00
Quantity
Unit
Amount
Unit Cost
30,432.00
Amount
259,584.00
3,043.00
262,627.00
293,059.00
Amount
P
6% per D.O. 29 s 2011
0% per D.O. 29 s 2011
0% per D.O. 29 s 2011
293,059.00
17,583.54
310,642.54
310,642.54
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
POTHOLING
CU.M./DAY
CU.M.
Designation
A.
Labor
a.
Construction Foreman
b.
Laborers
c.
Skilled Worker
No. P
1
6
1
Sub-Total for A
Name and Capacity
B.
C.
D.
No. of
Equipment
N/A
Sub-Total for B
Total (A+B)
5.40
CU.M./DAY
Qua
E.
Materials
N/A
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
6
1
0.59
0.59
0.59
524.00
317.00
366.00
311.49
1,130.63
217.57
P
No. of Units
No. of Days
Amount
Daily Rate
1,659.69
Amount
P
1,659.69
Quantity
Unit
Unit Cost
Amount
P
6% per D.O. 29 s 2011
8% per D.O. 29 s 2011
12% per D.O. 29 s 2011
1,659.69
99.58
132.78
227.05
2,119.09
660.15
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Locations
Kasanyangan
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
SPL-4
LN.M.
75.00
0.00
ASPHALT CUTTING
LN.M./day
LN.M.
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total Length
Designation
A.
Total
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
No.
Labor
a.
Construction Foreman
b.
Light Equipment Operator
Sub-Total for A
Name and Capacity
B.
Equipment
a.
Concrete Cutter
Minor Tools (10%)
No. o
C.
D.
Sub-Total for B
Total (A+B)
75.00
Materials
N.A.
Sub-Total for E
F.
G.
H.
I.
J.
k.
LN.M./day
Qu
IT PRICE ANALYSIS
No. Person
No. of Days
Daily Rate
1
2
0.00
0.00
524.00
394.00
Amount
P
No. of Units
No. of Days
Daily Rate
0.00
1,758.00
Amount
Quantity
Unit
Unit Cost
Amount
P
-
CONCRETE CUTTING
LN.M./day
LN.M.
Length of Concrete
1114.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total Length
Designation
A.
Labor
a.
Construction Foreman
b.
Light Equipment Operator
No. Pe
1
6
Sub-Total for A
Name and Capacity
B.
Equipment
a.
Concrete Cutter
Minor Tools (10%)
No. of
C.
D.
Sub-Total for B
Total (A+B)
150.00
LN.M./day
Materials
N.A.
Sub-Total for E
F.
G.
H.
I.
J.
k.
Quan
No. Person
No. of Days
Daily Rate
1
6
14.85
14.85
524.00
394.00
Amount
7,783.15
35,113.28
P
No. of Units
No. of Days
Daily Rate
14.85
1,758.00
42,896.43
Amount
78,336.48
4,289.64
Quantity
Unit
Unit Cost
82,626.12
125,522.55
Amount
P
9% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
125,522.55
11,297.03
136,819.58
61.41
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
101(4)b
SQ.M.
480.00
0.00
Length
Kasanyangan
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total Area
0.00
Designation
A.
Labor
a.
Construction Foreman
b.
Laborers
No. P
1
2
Sub-Total for A
Name and Capacity
B.
Equipment
a.
Backhoe w/ Pavement Breaker (0.80 cu.m.)
b.
Payloader (1.50 cu.m.), LX80-2C
c.
Dump Truck (10 cu.m.)
Minor Tools (10%)
No. of
1
1
1
C.
D.
Sub-Total for B
Total (A+B)
480.00
Materials
N.A.
Sub-Total for E
F.
G.
H.
I.
J.
k.
SQ.M./DAY
Qua
NG ASPHALT PAVEMENT
No. Person
No. of Days
Daily Rate
1
2
0.00
0.00
524.00
317.00
Amount
P
No. of Units
No. of Days
Daily Rate
1
1
1
0.00
0.00
0.00
12,296.00
13,864.00
9,016.00
Amount
Quantity
Unit
Unit Cost
Amount
P
-
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
101(4)a
SQ.M.
320.00
0.00
Location
Kasanyangan
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total Area
A.
Labor
a.
Construction Foreman
b.
Laborers
No. Person
1
2
Sub-Total for A
Name and Capacity
B.
Equipment
a.
Backhoe w/ Pavement Breaker (0.80 cu.m.)
b.
Payloader (1.50 cu.m.), LX80-2C
c.
Dump Truck (10 cu.m.)
Minor Tools (10%)
No. of Units
1
1
1
C.
D.
Sub-Total for B
Total (A+B)
=
320.00
Name and Specifications
E.
Materials
N.A.
Sub-Total for E
F.
G.
H.
I.
J.
k.
SQ.M./DAY
Quantity
No. of Days
Daily Rate
0.00
0.00
524.00
317.00
Amount
P
No. of Days
Daily Rate
0.00
0.00
0.00
12,296.00
13,864.00
9,016.00
Amount
Unit
Unit Cost
Amount
P
-
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Proposed Laying of 100mm PVC Pipeline Extention at Sittio Canucutan, Brgy. Pason
PIPELINE EXCAVATION
CU.M./DAY
CU.M.
Designation
A.
Labor
a.
Construction Foreman
b.
Laborers
No. Person
1
3
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Dump Truck (10 cu.m.)
b.
Backhoe (0.80 cu.m.)
Minor Tools (10%)
2
1
Sub-Total for B
Total (A+B)
160.00
CU.M./DAY
Materials
N.A.
No. of Units
Quantity
Sub-Total for E
F.
G.
H.
I.
J.
k.
T PRICE ANALYSIS
at Sittio Canucutan, Brgy. Pasonanca
No. of Days
Daily Rate
0.01
0.01
524.00
317.00
5.67
10.29
P
No. of Days
Daily Rate
0.01
0.01
10,816.00
12,296.00
Unit
Unit Cost
Amount
15.95
Amount
233.95
132.98
1.60
368.53
384.48
Amount
P
6% per D.O. 29 s 2011
8% per D.O. 29 s 2011
12% per D.O. 29 s 2011
384.48
23.07
30.76
52.60
490.90
283.69
Unit of Measurement:
Output per day:
Quantity:
UNITS
50.00
26.00
UNITS/DAY
UNITS
Designation
A. Labor
a.
Construction Foreman
b.
Skilled worker
c.
Laborer
Sub-Total for A
Name and Capacity
B. Equipment
N/A
C.
D. Output per day
Sub-Total for B
Total (A+B)
=
50.00
UNITS/DAY
Name and Specifications
E. Materials
a.
10 pcs. - 2" x 1" x 10' Coco Lumber
b.
30 pcs. - 4" x 4" x 12' Coco Lumber
c.
4" C.W. Nail
d.
2 1/2" C.W. Nail
e.
3" Finishing Nail
f.
2 1/2" Finishing Nail
g.
#100 Nylon Chord
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
5
0.52
0.52
524.00
341.00
272.48
886.60
0.52
317.00
824.20
P
No. of Units
No. of Days
Daily Rate
Quantity
Unit
17
40
3.00
1.00
3.00
3.00
1.00
bd.ft.
bd.ft.
kgs.
kgs.
kgs.
kgs.
roll
Unit Cost
1,983.28
Amount
1,983.28
Amount
20.00
20.00
80.00
80.00
80.00
80.00
130.00
P
Amount
333.00
800.00
240.00
80.00
240.00
240.00
130.00
2,063.00
4,046.28
404.63
4,450.91
171.19
Unit of Measurement:
Output per day:
Quantity:
UNITS
50.00
343.00
UNITS/DAY
UNITS
Designation
A. Labor
a.
Construction Foreman
b.
Skilled worker
c.
Laborer
Sub-Total for A
Name and Capacity
B. Equipment
N/A
C.
D. Output per day
Sub-Total for B
Total (A+B)
=
50.00
UNITS/DAY
Name and Specifications
E. Materials
a.
70 pcs. - 2" x 1" x 10' Coco Lumber
b.
330 pcs. - 4" x 4" x 12' Coco Lumber
c.
4" C.W. Nail
e.
2 1/2" C.W. Nail
3" Finishing Nail
f.
2 1/2" Finishing Nail
g.
#100 Nylon Chord
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
5
6.86
6.86
524.00
341.00
3,594.64
11,696.30
6.86
317.00
10,873.10
P
No. of Units
No. of Days
Daily Rate
Quantity
Unit
117
440
20.00
15.00
20.00
20.00
6.00
bd.ft.
bd.ft.
kgs.
kgs.
kgs.
kgs.
rolls
Unit Cost
26,164.04
Amount
26,164.04
Amount
20.00
20.00
80.00
80.00
80.00
80.00
130.00
P
Amount
2,333.00
8,800.00
1,600.00
1,200.00
1,600.00
1,600.00
780.00
17,913.00
44,077.04
4,407.70
48,484.74
141.35
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPL-5a
LN.M.
48.00
39.00
Designation
A. Labor
a.
Construction Foreman
b.
Skilled worker
c.
Laborer
Sub-Total for A
Name and Capacity
B. Equipment
a.
Truck Mounted Crane
b.
Diesel Hammer
c.
Drop Hammer
C.
D. Output per day
Sub-Total for B
Total (A+B)
=
48.00
LN.M./DAY
Name and Specifications
E. Materials
N/A
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
5
0.81
0.81
524.00
341.00
425.75
1,385.31
0.81
317.00
1,287.81
P
No. of Units
No. of Days
1
1
1
0.81
0.24
0.81
Daily Rate
1,758.00
1,191.04
1,376.00
P
Quantity
Unit
Unit Cost
3,098.88
Amount
1,428.38
290.32
1,118.00
2,836.69
5,935.57
Amount
P
10% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
Amount
5,935.57
593.56
6,529.13
167.41
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPL-5b
LN.M.
48.00
514.50
Designation
A. Labor
a.
Construction Foreman
b.
Skilled worker
c.
Laborer
Sub-Total for A
Name and Capacity
B. Equipment
a.
Truck Mounted Crane
b.
Diesel Hammer
c.
Drop Hammer
C.
D. Output per day
Sub-Total for B
Total (A+B)
=
48.00
LN.M./DAY
Name and Specifications
E. Materials
N/A
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
5
10.72
10.72
524.00
341.00
5,616.63
18,275.47
10.72
317.00
16,989.22
P
No. of Units
No. of Days
1
1
1
10.72
3.22
10.72
Daily Rate
1,758.00
1,191.04
1,376.00
P
Quantity
Unit
Unit Cost
40,881.31
Amount
18,843.56
3,829.94
14,749.00
37,422.50
78,303.81
Amount
P
10% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
Amount
78,303.81
7,830.38
86,134.19
167.41
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPL-4
CU.M.
18.00
483.52
Designation
A.
Labor
a.
Construction Foreman
b.
Laborers
No. Perso
1
20
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
N.A.
Sub-Total for B
Total (A+B)
=
18.00
CU.M./DAY
Name and Specifications
E.
Materials
N/A
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. of Uni
Quantity
T PRICE ANALYSIS
ON (MANUAL EXCAVATION)
No. Person
No. of Days
Daily Rate
1
20
27
27
524.00
317.00
14,148.00
171,180.00
P
No. of Units
No. of Days
Daily Rate
Quantity
Unit
Amount
Unit Cost
185,328.00
Amount
185,328.00
Amount
P
9% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
185,328.00
16,679.52
202,007.52
417.79
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPL-7a
LN.M.
43.00
1,156.20
Designation
No. Person
A. Labor
a.
Construction Foreman
b.
Pipefitter
c.
1
2
Laborers
4
Sub-Total for A
Name and Capacity
No. of Units
B. Equipment
N.A.
C.
D. Output per day
Sub-Total for B
Total (A+B)
=
43.00
LN.M./DAY
Quantity
193
1
5
46
3
1
1
1
4
10
2
l.
m.
n.
Washed Sand
Gravel (G-1)
12mm. x 6.00m. Def. Reinforcing Steel Bar
Sub-Total for E
F.
G.
H.
I.
J.
k.
0.10
0.20
1
No. Person
No. of Days
Daily Rate
1
2
27
27
524.00
341.00
14,148.00
18,414.00
27
317.00
34,236.00
P
No. of Units
No. of Days
Daily Rate
Quantity
Unit
193
1
5
46
3
1
1
1
4
pcs.
pc.
pcs.
pcs.
pcs.
pc.
pc.
pc.
pcs.
10
2
kgs.
bags
Unit Cost
2,800.00
710.00
714.00
570.00
1,950.00
8,083.00
2,695.00
1,402.00
65.00
80.00
280.00
Amount
66,798.00
Amount
66,798.00
Amount
540,400.00
710.00
3,570.00
26,220.00
5,850.00
8,083.00
2,695.00
1,402.00
260.00
800.00
560.00
0.10
0.20
1
cu.m.
cu.m.
pc.
950.00
950.00
266.00
P
95.00
190.00
266.00
591,101.00
657,899.00
59,210.91
717,109.91
620.23
DETAILED
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Designation
A.
Labor
a.
Construction Foreman
b.
Laborers
c.
Pipefitter
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
N.A.
Sub-Total for B
Total (A+B)
4.43
Name and Specifications
E.
Materials
a.
Polyethelyne Warning Tape, "Attention Water Main", 3"W x 1000ft/rol
b.
150mm x 6.00m D.I. Push-on Pipe in Accordance with ISO 2531, Cla
150mm x 45 D.I. Bend, Push-On in Accordance with ISO 2531, Clas
c.
Plain Margarine
d.
e.
150mm D.I. Sleeve Type Flexible Coupling, (D.I.)
Sub-Total for E
F.
G.
H.
I.
J.
k.
PCS./DAY
PCS.
nation
No. Person
No. of Days
Daily Rate
1
15
1
28
28
28
524.00
317.00
341.00
P
ub-Total for A
d Capacity
No. of Units
No. of Days
Daily Rate
ub-Total for B
Total (A+B)
PCS./DAY
pecifications
pling, (D.I.)
Quantity
Unit
Unit Cost
2.38
122.03
2
3.39
2.18
rolls
pcs.
pcs.
kgs.
1,400
9,988.85
1756.32
70
pcs.
2,730.00
Sub-Total for E
6% per D.O. 29 s 2011
8% per D.O. 29 s 2011
Pasonanca
Amount
14,426.10
130,908.57
9,387.98
154,722.65
Amount
154,722.65
Amount
3,334.71
1,218,972.66
3,512.65
237.29
5,947.58
1,232,004.89
1,386,727.53
83,203.65
110,938.20
189,704.33
1,770,573.71
14,508.94
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Location
SPL-8
LN.M.
13.43
19.60
Kasanyangan
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
4.90
14.70
0.00
0.00
0.00
0.00
0.00
0.00
0.00
19.60
Total Length
Designation
A.
Labor
a.
Construction Foreman
b.
Pipefitter
c.
Skilled Worker
d.
Laborer
(mm)
150
150
150
150
150
150
150
150
150
No. Person
1
1
6
12
Sub-Total for A
Equipment
One Bagger Mixer
a.
b.
c.
d
e.
No. of Unit
1
1
1
1
1
Concrete Vibrator
Water Truck (1000 gal.)
Bar Cutter
Bar Bender
Page 128 of 298
f.
C.
D.
Sub-Total for B
Total (A+B)
=
13.43
LN.M./DAY
Quantity
Materials
a.
Kasanyangan
150mm x 11.25 D.I. Bend, Push-on Double Socket w/ Rubber Gasket
8.00
b.
c.
d.
e.
f.
g.
4.00
20
60
2.00
0.50
0.50
h.
i.
j.
k.
l.
m.
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
Sand
Gravel
#16 G.I. Tie Wire
12mm x 6.00m Deformed Rein. Steel Bar
16mm x 6.00m Deformed Rein. Steel Bar
10.00
0.54
1.08
9.00
7.00
4.00
0.00
150mm x 11.25 D.I. Bend, Push-on Double Socket w/ Rubber Gasket
28.00
Cement
14.00
53
138
5.00
1.00
1.00
26.00
1.36
2.71
26.00
21.00
10.00
Cement
Sand
Gravel
#16 G.I. Tie Wire
12mm x 6.00m Deformed Rein. Steel Bar
16mm x 6.00m Deformed Rein. Steel Bar
0.00
150mm x 11.25 D.I. Bend, Push-on Double Socket w/ Rubber Gasket
150mm D.I. Sleeve Type Flexible Coupling, (D.I.)
10 pcs. - 2" x 2" x 10' Coco Lumber
20 pcs. - 2" x 3" x 12' Coco Lumber
12mm thk x 1.20m x 2.40m Ordinary Plywood
2 1/2" C.W. Nail
4" C.W. Nail
0.00
33
120
0.00
1.00
1.00
0.00
0.00
0.00
0.00
1.00
0.00
Cement
Sand
Gravel
#16 G.I. Tie Wire
12mm x 6.00m Deformed Rein. Steel Bar
16mm x 6.00m Deformed Rein. Steel Bar
0.00
Page 130 of 298
0.00
a.
0.00
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
0.00
53
138
0.00
1.00
1.00
0.00
0.00
0.00
0.00
1.00
1.00
Cement
Sand
Gravel
#16 G.I. Tie Wire
12mm x 6.00m Deformed Rein. Steel Bar
16mm x 6.00m Deformed Rein. Steel Bar
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
0.00
150mm x 11.25 D.I. Bend, Push-on Double Socket w/ Rubber Gasket
150mm D.I. Sleeve Type Flexible Coupling, (D.I.)
2 pcs. - 2" x 2" x 10' Coco Lumber
5 pcs. - 2" x 3" x 12' Coco Lumber
12mm thk x 1.20m x 2.40m Ordinary Plywood
2 1/2" C.W. Nail
4" C.W. Nail
Sand
Gravel
#16 G.I. Tie Wire
12mm x 6.00m Deformed Rein. Steel Bar
16mm x 6.00m Deformed Rein. Steel Bar
0.00
7
30
0.00
0.50
0.50
1.00
0.00
0.00
1.00
0.79
0.00
0.00
150mm x 11.25 D.I. Bend, Push-on Double Socket w/ Rubber Gasket
0.00
Cement
Sand
Gravel
#16 G.I. Tie Wire
12mm x 6.00m Deformed Rein. Steel Bar
16mm x 6.00m Deformed Rein. Steel Bar
0.00
0.00
13
54
1.00
0.50
0.50
0.00
0.00
0.00
0.00
2.00
0.00
IT PRICE ANALYSIS
No. Person
No. of Days
Daily Rate
1
1
6
12
1.46
1.46
1.46
1.46
524.00
394.00
366.00
317.00
Amount
764.73
575.00
3,204.84
5,551.56
P
No. of Units
No. of Days
Daily Rate
1
1
1
1
1
0.34
0.34
0.03
1.12
1.12
1,376.00
1,191.04
8,520.00
1,758.00
2,812.00
Page 133 of 298
10,096.13
Amount
465.63
403.04
288.31
1,970.73
3,152.27
0.34
8,816.00
2,964.84
Unit Cost
9,244.82
19,340.95
Quantity
Unit
Amount
8.00
pcs.
933.06
7,464.48
4.00
20
60
2.00
0.50
0.50
pcs.
bd.ft
bd.ft
shts.
kg.
kg.
2,730.00
20.00
20.00
950.00
80.00
80.00
10,920.00
400.00
1,200.00
1,900.00
40.00
40.00
Kasanyangan
10.00
0.54
1.08
9.00
7.00
4.00
bags
cu.m.
cu.m.
kgs.
pcs.
pcs.
28.00
pcs.
14.00
53
138
5.00
1.00
1.00
26.00
1.36
2.71
26.00
21.00
10.00
pcs.
bd.ft
bd.ft
shts.
kg.
kg.
bags
cu.m.
cu.m.
kgs.
pcs.
pcs.
0.00
pcs.
0.00
33
120
0.00
1.00
1.00
0.00
0.00
0.00
0.00
1.00
0.00
pcs.
bd.ft
bd.ft
shts.
kg.
kg.
bags
cu.m.
cu.m.
kgs.
pcs.
pcs.
265.00
1,000.00
1,000.00
70.00
192.00
330.00
2,650.00
540.00
1,080.00
630.00
1,344.00
1,320.00
933.06
26,125.68
2,730.00
20.00
20.00
950.00
80.00
80.00
265.00
1,000.00
1,000.00
70.00
192.00
330.00
38,220.00
1,066.67
2,760.00
4,750.00
80.00
80.00
6,890.00
1,355.00
2,710.00
1,820.00
4,032.00
3,300.00
0.00
0.00
933.06
2,730.00
20.00
20.00
950.00
80.00
80.00
265.00
1,000.00
1,000.00
70.00
192.00
330.00
0.00
Page 135 of 298
666.67
2,400.00
80.00
80.00
192.00
-
0.00
pcs.
0.00
53
138
0.00
1.00
1.00
0.00
0.00
0.00
0.00
1.00
1.00
pcs.
bd.ft
bd.ft
shts.
kg.
kg.
bags
cu.m.
cu.m.
kgs.
pcs.
pcs.
933.06
2,730.00
20.00
20.00
950.00
80.00
80.00
265.00
1,000.00
1,000.00
70.00
192.00
330.00
1,066.67
2,760.00
80.00
80.00
192.00
330.00
0.00
0.00
pcs.
0.00
7
30
0.00
0.50
0.50
1.00
0.00
0.00
1.00
0.79
0.00
pcs.
bd.ft
bd.ft
sht.
kg.
kg.
bags
cu.m.
cu.m.
kgs.
pcs.
pcs.
0.00
pcs.
0.00
13
54
1.00
0.50
0.50
0.00
0.00
0.00
0.00
2.00
0.00
pcs.
bd.ft
bd.ft
shts.
kg.
kg.
bags
cu.m.
cu.m.
kgs.
pcs.
pcs.
933.06
2,730.00
20.00
20.00
950.00
80.00
80.00
265.00
1,000.00
1,000.00
70.00
192.00
330.00
133.33
600.00
40.00
40.00
265.00
70.00
151.04
-
0.00
933.06
2,730.00
20.00
20.00
950.00
80.00
80.00
265.00
1,000.00
1,000.00
70.00
192.00
330.00
P
9% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
266.67
1,080.00
950.00
40.00
40.00
384.00
-
134,705.20
154,046.15
13,864.15
167,910.30
8,566.85
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPL-7b
LN.M.
144.00
0.00
Designation
No. Person
A. Labor
a.
Construction Foreman
b.
Pipefitter
c.
1
2
Laborers
8
Sub-Total for A
Name and Capacity
No. of Units
B. Equipment
a.
Steel Ladder
b.
A-Frame
c.
Dump Truck (10 cu.m.)
C.
D. Output per day
1
1
1
Sub-Total for B
Total (A+B)
=
144.00
LN.M./DAY
F.
G.
H.
I.
Quantity
36.00
2.00
22.00
J.
k.
Total Cost
Total Unit Cost
No. Person
No. of Days
Daily Rate
Amount
1
2
0.00
0.00
524.00
341.00
0.00
317.00
No. of Units
No. of Days
Daily Rate
1
1
1
0.00
0.00
0.00
300.00
300.00
9,016.00
Amount
Quantity
Unit
36.00
2.00
22.00
Unit Cost
rolls
pcs.
pcs.
kgs.
Amount
7,300.00
950.00
65.00
75.00
P
34,200.00
130.00
1,650.00
35,980.00
35,980.00
3,598.00
-
39,578.00
#DIV/0!
SAND ENVELOP
CU.M./DAY
CU.M.
Designation
A.
Labor
a.
Construction Foreman
b.
Laborers
No. P
1
2
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
N.A.
Sub-Total for B
Total (A+B)
12.00
CU.M./DAY
No. of
Materials
a.
Washed Sand
Qua
220
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
2
18.39
18.39
524.00
317.00
9,637.25
11,660.33
P
No. of Units
No. of Days
Amount
Daily Rate
21,297.58
Amount
P
21,297.58
Quantity
Unit
220.70
cu.m.
Unit Cost
1,000.00
Amount
220,700.33
P
10% per D.O. 29 s 2011
0% per D.O. 29 s 2011
0% per D.O. 29 s 2011
220,700.33
241,997.91
24,199.79
266,197.70
1,206.15
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Designation
A.
Labor
a.
Construction Foreman/Engineering Assistant
b.
Laborers
c.
Pipefitter
d.
Welder
Sub-Total for A
Name and Capacity
B.
Equipment
a.
A-Frame
C.
D. Output per day
Sub-Total for B
Total (A+B)
4.00
each/day
Materials
a.
b.
c.
d.
e.
f.
g.
50mm
50mm
50mm
16mm
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
6
1
1
0.50
0.50
0.50
0.50
524.00
317.00
394.00
394.00
Amount
262.00
951.00
197.00
197.00
P
No. of Units
No. of Days
Daily Rate
0.50
500.00
1,607.00
Amount
250.00
250.00
1,857.00
0
Quantity
Unit
pcs.
pc.
pcs.
pcs.
pcs.
kgs.
pc.
4
4
32
2
4
1
Unit Cost
3,795.00
1,100.00
1,250.00
60.00
1,402.00
140.00
4,340.00
P
Amount
7,590.00
4,400.00
5,000.00
1,920.00
2,804.00
560.00
4,340.00
26,614.00
28,471.00
2,847.10
31,318.10
15,659.05
Designation
A.
No. Person
Labor
a. Construction Foreman
b. Pipefitter
c. Skilled Worker
d. Laborers
3
4
Sub-Total for A
Name and Capacity
B.
Equipment
a.
Generator Set/ Welding Machine w/ complete accessories (w/ fuel)
Minor Tools (10%)
C.
D. Output per day
E.
No. of Units
Sub-Total for B
Total (A+B)
1.71
LN.M./DAY
Quantity
Materials
a. 100mm x 6.00m G.I. Pipe, Threaded Both Ends, (ASTM 53-90A- Heavy
Gauge)
b. 100mm. G.I. Coupling, (ANSI B16.3 Class 150 - Standard)
c. 6mm. Thk. x 50mm. x 6.00m MS Flat Bar
d. 12mm. x 250mm. MS Bolt with Nut and Washer
e. 100mm C.I. Sleeve Type Flexible Coupling, (PVC-G.I.)
f. 100mm C.I. Body Gate Valve, M/M, NRS
g. 100mm x 11.25 PVC Bend, Class 150, B/S w/ R.R.
h. 100mm x 22.5 PVC Bend, Class 150, B/S w/ R.R.
1
1
4
2
1
1
1
i.
j.
1
3
5
0.25
0.50
9
2
2
64
48
0.50
2
RICE ANALYSIS
No. Person
No. of Days
Daily Rate
524.00
2,096.00
341.00
1,364.00
3
4
4
4
366.00
317.00
4,392.00
5,072.00
P
No. of Units
No. of Days
Daily Rate
2,160.00
Amount
12,924.00
Amount
8,640.00
1,292.00
P
Quantity
Unit
Unit Cost
pcs.
18,565.00
1
1
4
2
1
1
1
pc.
pc.
pcs.
pcs.
pc.
pc.
pc.
500.00
865.20
100.00
4,726.00
8,083.00
570.00
714.00
9,932.00
22,856.00
Amount
37,130.00
500.00
865.20
400.00
9,452.00
8,083.00
570.00
714.00
1
3
kg.
pcs.
5
0.25
0.50
9
2
2
64
48
0.50
2
bags
cu.m.
cu.m.
pcs.
kgs.
shts.
bd.ft.
bd.ft.
kg.
kgs.
140.00
65.00
140.00
195.00
280.00
950.00
950.00
266.00
75.00
800.00
20.00
20.00
59.00
59.00
P
1,400.00
237.50
475.00
2,394.00
150.00
1,600.00
1,280.00
960.00
29.50
118.00
66,575.20
89,431.20
8,048.81
97,480.01
14,293.26
DETAI
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPL-6
ASSEMBLY
1
1
VALVES/FITTINGS/INTER-CON
ASSEMBLY/DAY
ASSEMBLY
Designation
A.
Labor
a.
Construction Foreman
b.
Pipefitter
c.
Laborers
e.
Skilled Worker
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Water Pump
Sub-Total for B
Total (A+B)
Output per day
1.00
Name and Specifications
E.
Materials
a.
b.
c.
d.
e.
100mm
100mm
150mm
150mm
f.
g.
h.
i.
Portland Cement
Washed Sand
Gravel (G-1)
12mm. x 6.00m. Def. Reinforcing Steel Bar
Sub-Total for E
F.
G.
H.
I.
J.
k.
Sub-Total for A
Name and Capacity
Sub-Total for B
Total (A+B)
ASSEMBLY/DAY
Name and Specifications
ent
CE ANALYSIS
No. Person
No. of Days
Daily Rate
1
1
2
1
1
1
1
1
524.00
341.00
317.00
366.00
P
No. of Units
No. of Days
Daily Rate
750.00
Amount
524.00
341.00
634.00
366.00
1,865.00
Amount
375.00
Unit Cost
375.00
2,240.00
Quantity
Unit
pc.
8,083.00
8,083.00
1
1
1
pc.
pc.
pc.
1,939.00
4,590.00
1,402.00
1,939.00
4,590.00
1,402.00
Amount
2
0.10
0.20
1
bags
cu.m.
cu.m.
pc.
280.00
950.00
950.00
266.00
P
560.00
95.00
190.00
266.00
17,125.00
19,365.00
1,742.85
21,107.85
21,107.85
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Designation
A.
Labor
a.
Construction Foreman
a.
Pipefitter
b.
Skilled Worker
c.
Laborer
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Generator Set/ Welding Machine w/ complete accessories (w/ fuel)
Sub-Total for B
Total (A+B)
0.66
Materials
a.
100mm x 100mm C.I. Tee, M/F, Flanged End in Accordance w/ ANSI B16.1 Clas
125
b.
c.
16mm x 88mm Stainless (Full Thread) Hex Bolt (Type 304) w/ Nut and Washer
d.
100mm C.I. Body Gate Valve,PN16, (NRS), F/F, Flanged End in Accordance w/ AN
B16.1 Class 125 w/ 2-units Steel Ring Flange Conforming to AWWA C207 Class EStandard, w/ 16 - Units of 19mm x 88mm Stainless, (Full Thread) Hex. Bolt (Type
304) w/ Nut and Washer
e.
f.
g.
h.
i.
j.
k.
l.
m.
n.
F.
G.
H.
I.
J.
k.
gnation
No. Person
No. of Days
Daily Rate
1
1
1
2
2
2
2
2
524.00
341.00
366.00
317.00
No. of Units
No. of Days
Daily Rate
2,160.00
Quantity
Unit
Unit Cost
pc.
4,000.00
pc.
373.00
pcs.
98.00
pc.
10,243.00
le Coupling, (PVC)
pc.
1,939.00
Sub-Total for A
d Capacity
Sub-Total for B
Total (A+B)
UNIT/DAY
Specifications
g Steel Bar
1
1
1
6
1
3
0.125
0.25
1
pc.
pc.
pc.
kgs.
pc.
bags.
cu.m.
cu.m.
kg.
1,402.00
9,910.00
4,590.00
80.00
266.00
280.00
1,000.00
1,000.00
165.00
Sub-Total for E
9% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
anca
Daily Rate
524.00
341.00
366.00
317.00
Amount
1,048.00
517.00
555.00
961.00
P
Daily Rate
2,160.00
3,081.00
Amount
818.18
Unit Cost
818.18
3,899.18
Amount
4,000.00
4,000.00
373.00
373.00
98.00
784.00
10,243.00
10,243.00
1,939.00
1,939.00
1,402.00
9,910.00
4,590.00
80.00
266.00
280.00
1,000.00
1,000.00
165.00
P
22 s 2015
22 s 2015
22 s 2015
1,402.00
9,910.00
4,590.00
480.00
266.00
840.00
125.00
250.00
165.00
35,367.00
39,266.18
3,533.96
42,800.14
42,800.14
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
UNIT/DAY
UNITS
Designation
A.
Labor
a.
Construction Foreman
b.
Pipefitter
c.
Laborers
d.
Skilled Worker
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Generator Set/ Welding Machine w/ complete accessories (w/ fuel)
Sub-Total for B
Total (A+B)
Output per day
0.33
Name and Specifications
E.
Materials
a.
100mm x 50mm C.I. Tee, M/F, Flange end in accordance w/ ANSI B16.1 Class 1
1-unit Steel Ring Flange conforming to ANSI B16.5 Class 150, w/ 4-16mm. x 88m
Stainless (full thread) Hex. Bolt (type 304) w/ Nut & Washer
b.
c.
d.
e.
f.
h.
i.
j.
k.
l.
m.
n.
o.
p.
q.
r.
s.
t.
w.
x.
y.
z.
a'.
b'.
c'.
d'.
e'.
f'.
F.
G.
H.
I.
J.
k.
Hacksaw Blade
25mm Masking Tape
Concrete Neutralizer
Flat Latex Paint (Primer)
Gloss Latex Paint (Caterpillar Yellow)
Gloss Latex Paint (Black)
Portland Cement
Washed Sand
Gravel (G-1)
16mm x 6.00m Def. Reinforcing Steel Bar
10mm x 6.00m Def. Reinforcing Steel Bar
Quick Dry Enamel (Blue)
#16 G.I. Tie-wire
12mm. Thk. x 1.20m. x 2.40m. Ordinary Plywood
12 pcs. 2" x 2" x 10' Coco Lumber
2" C.W. Nail
3" C.W. Nail
3" Paint Brush
4" Paint Brush
Metal Primer
Sub-Total for E
Direct Cost (C+E)
Overhead, Contingencies & Miscellaneous
Contractor's Profit (CP)
Value Added Tax (VAT)
Total Cost
Total Unit Cost
Designation
No. Person
No. of Days
1
1
2
2
9
9
9
9
No. of Units
No. of Days
Quantity
Unit
pcs.
6
3
1
pcs.
pcs.
pc.
1
3
pc.
pcs.
20
3
rolls
Sub-Total for A
me and Capacity
Sub-Total for B
Total (A+B)
UNIT/DAY
e and Specifications
se Pressure Valve
pcs.
kgs.
m. Ordinary Plywood
6
24
1
2
2
2
15
1
2
12
5
2
2
2
40
4
2
2
2
2
pcs.
rolls
liter
gals.
gals.
gals.
bags
cu.m.
cu.m.
pcs.
pcs.
gals.
kgs.
shts.
bd.ft.
kgs.
kgs.
pcs.
pcs.
gals.
Sub-Total for E
9% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
nanca
Daily Rate
524.00
341.00
317.00
366.00
Amount
4,716.00
3,069.00
5,706.00
6,588.00
P
Daily Rate
2,160.00
20,079.00
Amount
6,480.00
P
Unit Cost
6,480.00
26,559.00
Amount
4,500.00
13,500.00
138.00
2,829.00
9,877.00
828.00
8,487.00
9,877.00
18,565.00
2,325.00
18,565.00
6,975.00
38.00
23,520.00
165.00
760.00
70,560.00
660.00
O. 22 s 2015
O. 22 s 2015
O. 22 s 2015
66.00
32.00
110.00
549.75
937.65
683.55
280.00
1,000.00
1,000.00
335.00
175.00
606.00
75.00
800.00
20.00
53.00
59.00
65.00
95.00
469.00
P
396.00
768.00
110.00
1,099.50
1,875.30
1,367.10
4,200.00
1,000.00
2,000.00
4,020.00
875.00
1,212.00
150.00
1,600.00
800.00
212.00
118.00
130.00
190.00
938.00
152,334.90
178,893.90
16,100.45
194,994.35
64,998.12
DETAILED
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
UNITS
0.33
2
UNIT/DAY
UNITS
Designation
A.
Labor
a.
Construction Foreman
b.
Pipefitter
c.
Laborers
d.
Skilled Worker
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Generator Set/ Welding Machine w/ complete accessories (w/ fuel)
Sub-Total for B
Total (A+B)
0.33
Materials
a.
150mm C.I. Valve Box Cover
b.
100mm x 75mm C.I. Tee, M/F, Flange end in accordance w/ ANS
unit Steel Ring Flange conforming to ANSI B16.5 Class 150, w/ 4-16
c.
Stainless (full thread) Hex. Bolt (type 304) w/ Nut & Washer
75mm Brass Fire Hydrant Head w/ 63mm Hose Connector
100mm C.I Sleeve Type Flexible Coupling, (PVC)
75mm x 6.00m G.I. Pipe, (ASTM A53-90A Heavy Gauge)
75mm x 90 G.I. Elbow, (ANSI B16.3 Class 150 - Standard)
150mm x 6.00m PVC Pipe, class 150, B/S, w/ R.R
25mm Teflon Tape
Page 172 of 298
j.
k.
l.
m.
n.
o.
p.
q.
r.
s.
t.
u.
v.
w.
x.
Portland Cement
Washed Sand
Gravel (G1)
*16mm x 6.00m Def. Reinforcing Steel Bar
*10mm x 6.00m Deformed Rein. Steel Bar
#16 G.I. Tie-wire
Hacksaw Blade
Concrete Neutralizer
Flat Latex Paint (Primer)
Gloss Latex Paint (Caterpillar Yellow)
Gloss Latex Paint (Black)
Red Oxide Metal Primer
Quick Dry Enamel (Red)
Paint Thinner
y.
z.
a'.
b'.
c'.
d'.
e'.
f'.
Sub-Total for E
F.
G.
H.
I.
J.
k.
NIT/DAY
NITS
ation
No. Person
No. of Days
Daily Rate
1
1
4
2
6
6
6
6
524.00
341.00
317.00
366.00
P
b-Total for A
Capacity
No. of Units
No. of Days
Daily Rate
2,160.00
P
b-Total for B
Total (A+B)
UNIT/DAY
ecifications
Quantity
Unit
2
2
pcs.
pcs.
1,402.00
4,288.00
pcs.
5,506.00
2
2
2
2
1
8
sets
pcs.
pcs.
pcs.
pc.
rolls
10,230.00
1,939.00
7,010.00
535.00
4,340.00
38.00
Unit Cost
t & Washer
ge end in accordance w/ ANSI B16.1 Class 125, w/ 2
l Bar
l Bar
18
kgs.
13
1
2
8
4
0.5
2
1
1
1
1
1
1
1
bags
cu.m.
cu.m.
pcs.
pcs.
kg.
pcs.
liter
gal.
gal.
gal.
gal.
gal.
gal.
140.00
280.00
1,000.00
1,000.00
335.00
175.00
75.00
65.00
110.00
549.75
937.65
683.55
427.00
655.20
332.00
4
1
20
2
1
2
2
2
Plywood
pcs.
sht.
bd.ft.
kgs.
kg.
kgs.
pcs.
pcs.
32.00
800.00
20.00
53.00
59.00
165.00
65.00
95.00
b-Total for E
9% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
Amount
3,175.76
2,066.67
7,684.85
4,436.36
17,363.64
Amount
13,090.91
13,090.91
30,454.55
Amount
2,804.00
8,576.00
11,012.00
20,460.00
3,878.00
14,020.00
1,070.00
4,340.00
304.00
Page 178 of 298
2,520.00
3,640.00
1,000.00
2,000.00
2,680.00
700.00
37.50
130.00
110.00
549.75
937.65
683.55
427.00
655.20
332.00
128.00
800.00
400.00
106.00
59.00
330.00
130.00
190.00
85,009.65
115,464.20
10,391.78
125,855.98
62,927.99
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPL-10a
LN.M.
500.00
1,163.00
Designation
A.
Labor
a.
Construction Foreman
b.
Pipefitter
c.
Laborers
No. Person
1
1
4
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Hydro Machine
Minor Tools (10%)
Sub-Total for B
Total (A+B)
500.00
LN.M./DAY
No. of Unit
Materials
a.
Chlorine Granules
b.
Potable Water
c.
100mm D.I. Mechanical End Cap
d.
100mm x 19mm C.I. Saddle Clamp w/ Stainless Bolt,
Nut & Washer & Rubber
e.
19mm Brass Corporation Cock, (ISO)
f.
19mm G.I. End Plug, (ANSI B16.3 Class 150-Standard)
g.
25mm Teflon Tape
Quantity
1
28
1
4
4
4
2
h.
F.
G.
H.
I.
J.
k.
1
10.00
IT PRICE ANALYSIS
No. Person
No. of Days
Daily Rate
1
1
4
6
6
6
524.00
341.00
317.00
3,144.00
2,046.00
7,608.00
P
No. of Units
No. of Days
Daily Rate
988.00
Unit
1
28
1
4
kg.
cu.m.
pc.
sets
4
4
2
pcs.
pcs.
rolls
12,798.00
Amount
5,928.00
1,280.00
P
Quantity
Amount
Unit Cost
7,208.00
20,006.00
Amount
250.00
54.00
2,695.00
414.00
250.00
1,512.00
2,695.00
1,656.00
518.00
20.00
38.00
2,072.00
80.00
76.00
1
10.00
roll
ltrs.
940.00
52.00
P
940.00
520.00
9,801.00
29,807.00
2,682.63
32,489.63
27.94
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPL-10b
LN.M.
500.00
0.00
Designation
A.
Labor
a.
Construction Foreman
b.
Pipefitter
c.
Laborers
No. Person
1
1
6
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Hydro Machine
Minor Tools (10%)
Sub-Total for B
Total (A+B)
500.00
LN.M./DAY
No. of Unit
Materials
a.
Chlorine Granules
b.
Potable Water
c.
50mm C.I. Mechanical End Cap
d.
50mm x 19mm C.I. Saddle Clamp w/ Stainless Bolt,
Quantity
1.00
0.00
6
4
F.
G.
H.
I.
J.
k.
4
4
4
2
1.00
IT PRICE ANALYSIS
No. Person
No. of Days
Daily Rate
1
1
6
0.00
0.00
0.00
524.00
341.00
317.00
Amount
P
No. of Units
No. of Days
Daily Rate
0.00
988.00
Amount
Quantity
Unit
1.00
0.00
6
kg.
cu.m.
pcs.
sets
Unit Cost
Amount
250.00
54.00
1,120.00
250.00
6,720.00
280.00
1,120.00
sets
280.00
1,120.00
4
4
2
1.00
pcs.
pcs.
rolls
ltrs.
518.00
20.00
38.00
43.00
P
2,072.00
80.00
76.00
43.00
10,361.00
10,361.00
1,036.10
11,397.10
#DIV/0!
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPL-13
UNIT
0.50
2.00
Location
Kasanyangan
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0
0
0
0
0
0
0
0
0
2
2
Total no.
Designation
A.
10
No. Person
Labor
a.
Construction Foreman
a.
Skilled Worker
b.
Laborer
Sub-Total for A
Name and Capacity
B.
Equipment
a.
One Bagger Mixer
b.
Concrete Vibrator
c.
Welding Machine
No. of Units
1
1
1
C.
D. Output per day
Sub-Total for B
Total (A+B)
=
0.50
UNIT/DAY
Quantity
Materials
0.00
a.
50mm. D. I. Body Gate Valve, PN16, NRS, F/F, with 2-Units Steel Ring Flange in
accordance w/ ANSI B16.5 Class 150 Standard w/ 8 pcs.- 16mm. x 75mm Stainless Steel
Bolt Head, Nut & Washer
b.
c.
d.
e.
f.
g.
h.
i.
j.
2
2
1
2
2
1
2
2
2
k.
l.
m.
n.
o.
2
2
2
22
26
p.
q.
r.
s.
t.
u.
4
2
24
8
4
32
v.
w.
x.
y.
z.
a.a.
a.b.
a.c.
a.d.
a.e.
a.f
a.g.
a.h.
a.i.
a.j.
a.k.
a.l.
a.m.
a.n.
a.o.
a.p.
a.q.
a.r.
a.s.
a.t.
a.u.
a.v.
a.w.
a.x.
32
16
16
16
16
16
16
16
16
7
7
0.16
0.32
10
1
1
2
1
2
6
4
8
4
1
8
5
4
67.00
100
a.y.
a.z.
b.a.
b.b.
b.c.
b.d.
F.
G.
H.
I.
J.
k.
2
2
2
2
2
2
10
No. of Days
Daily Rate
4.00
524.00
2,096.00
4.00
366.00
8,784.00
4.00
317.00
10,144.00
P
No. of Days
Daily Rate
4.00
4.00
4.00
1,248.00
800.00
2,160.00
Amount
21,024.00
Amount
4,992.00
3,200.00
8,640.00
Unit
Unit Cost
16,832.00
37,856.00
Amount
0.00
pcs.
7,130.00
14,260.00
pcs.
pcs.
pc.
pcs.
pcs.
roll
pcs.
pcs.
pcs.
5,455.00
1,402.00
4,340.00
1,600.00
520.00
7,300.00
548.00
249.00
198.00
10,910.00
2,804.00
4,340.00
3,200.00
1,040.00
7,300.00
1,096.00
498.00
396.00
pcs.
pcs.
pcs.
pcs.
pcs.
176.00
155.00
136.00
124.00
104.00
352.00
310.00
272.00
2,728.00
2,704.00
pcs.
pcs.
pcs.
pcs.
kgs
rolls.
72.00
83.00
52.00
12.00
140.00
28.00
288.00
166.00
1,248.00
96.00
560.00
896.00
pcs.
pcs.
pcs.
pcs.
units
pcs.
pcs.
pcs.
pcs.
pcs.
bags.
cu.m.
cu.m.
pcs.
kg.
kg.
kgs.
kg.
kgs.
pcs.
shts.
pcs.
kgs.
pc.
pcs.
kgs.
shts.
bd.ft.
bd.ft.
23.00
85.00
60.00
57.00
1,300.00
5.00
437.85
360.00
250.00
192.00
265.00
1,000.00
1,000.00
65.00
80.00
80.00
80.00
80.00
80.00
852.00
1,500.00
65.00
160.00
25.00
130.00
70.00
950.00
20.00
20.00
736.00
1,360.00
960.00
912.00
20,800.00
80.00
7,005.60
5,760.00
4,000.00
1,344.00
1,855.00
160.00
320.00
650.00
80.00
80.00
160.00
80.00
160.00
5,112.00
6,000.00
520.00
640.00
25.00
1,040.00
350.00
3,800.00
1,340.00
2,000.00
gals.
gals.
gals.
gals.
pcs.
pcs.
937.65
792.00
260.00
332.00
35.00
20.00
P
1,875.30
1,584.00
520.00
664.00
70.00
40.00
127,546.90
165,402.90
14,886.26
180,289.16
90,144.58
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPL-13
UNIT
0.20
1.00
Designation
A.
No. Person
No. of Day
a. Construction Foreman
5.00
b. Skilled Worker
5.00
c.
5.00
No. of Units
No. of Day
1
1
1
0.12
0.12
0.12
Quantity
Unit
16.00
1.00
2.00
2.00
3.00
6.00
100.00
bags
cu.m.
cu.m.
pcs.
kgs.
shts.
bd.ft.
33.33
3.00
bd.ft.
kgs.
Labor
Laborer
Sub-Total for A
Name and Capacity
B.
Equipment
a. One Bagger Mixer
b. Concrete Vibrator
c. Welding Machine
C.
D. Output per day
Sub-Total for B
Total (A+B)
=
0.20
UNIT/DAY
Materials
a. Cement
b. Sand
c. Gravel
d. 16mm x 6.00m Stainless Steel Rod
e. #16 GI Tie wire
f. *12mm. thk. x 1.20m. x 2.40m. Ordinary Plywood
g. 20pcs. -2"x 3"x10 coco lumber
h. 10 pcs. -2"x2"x10 coco lumber
i. 4 C.W. Nail
j.
k.
l
m.
n.
o.
p.
2.00
0.50
4.00
18.00
1.00
2.00
1.00
kgs.
kgs.
pcs.
pcs.
pcs.
pcs.
pc.
Sub-Total for E
F.
G.
H.
I.
J.
k.
10%
0%
0%
T PRICE ANALYSIS
No. of Days
Daily Rate
5.00
524.00
2,620.00
5.00
366.00
7,320.00
5.00
317.00
6,340.00
P
No. of Days
Daily Rate
0.12
0.12
0.12
1,248.00
800.00
2,160.00
16,280.00
Amount
150.14
96.24
259.85
P
Unit
Amount
Unit Cost
506.23
16,786.23
Amount
bags
cu.m.
cu.m.
pcs.
kgs.
shts.
bd.ft.
265.00
1,000.00
1,000.00
2,214.45
70.00
950.00
20.00
4,240.00
1,000.00
2,000.00
4,428.90
210.00
5,700.00
2,000.00
bd.ft.
kgs.
20.00
80.00
666.67
240.00
kgs.
kgs.
pcs.
pcs.
pcs.
pcs.
pc.
80.00
396.00
65.00
330.00
192.00
130.00
255.00
P
per D.O. 22 s 2015
per D.O. 22 s 2015
per D.O. 22 s 2015
160.00
198.00
260.00
5,940.00
192.00
260.00
255.00
27,750.57
44,536.80
4,453.68
48,990.48
48,990.48
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Designation
A.
No. Person
Labor
a. Construction Foreman
b. Pipefitter
c. Skilled Worker
d. Laborers
3
6
Sub-Total for A
Name and Capacity
B.
No. of Units
Equipment
a. Generator Set/ Welding Machine w/ complete accessories (w/ fuel)
b. ICS Ductile Iron Pipe-Cutting Gas Chain Saw
C.
D. Output per day
Sub-Total for B
Total (A+B)
=
3.00
LN.M./DAY
Materials
a. 200mm x 6.0m D.I. Pipe, Flanged End
b. 6mm Thk x 50mm x 6.0m MS Flat Bar
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
1
1
Quantity
1.20
1.61
20.00
2.42
2.50
2.20
2.20
2.20
2.00
2.00
4.00
2.00
4.00
84.00
9.33
ICE ANALYSIS
No. Person
No. of Days
Daily Rate
Amount
0.00
524.00
0.00
341.00
3
6
0.00
0.00
366.00
317.00
No. of Units
No. of Days
1
1
0.00
0.00
Daily Rate
Amount
2,160.00
1,600.00
Quantity
Unit
1.20
1.61
20.00
2.42
2.50
2.20
2.20
2.20
2.00
2.00
4.00
2.00
pc.
pcs.
pcs.
pcs.
kgs.
gals.
gals.
gals.
pcs.
pcs.
pcs.
pcs.
Unit Cost
13,633.93
865.20
36.75
260.00
143.90
427.00
655.20
332.00
65.00
95.00
4,308.00
5,287.91
Amount
16,360.72
1,392.97
735.00
628.95
359.75
940.48
1,443.10
731.24
130.00
190.00
17,232.00
10,575.82
4.00
84.00
9.33
pcs.
pcs.
kgs.
5,333.33
62.76
140.00
P
21,333.33
5,271.84
1,306.67
78,631.86
78,631.86
7,076.87
6,290.55
11,039.91
103,039.19
#DIV/0!
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Designation
A.
Labor
a.
Pipefitter
b.
Skilled Worker
c.
Laborer
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
Sub-Total for B
Total (A+B)
0.50
Materials
a.
200mm
b.
200mm
c.
200mm
d.
100mm
e.
100mm
f.
100mm
g.
100mm
h.
100mm
i.
100mm
j.
k.
l.
m.
n.
o.
p.
F.
G.
H.
I.
J.
k.
gnation
No. Person
No. of Days
Daily Rate
1
3
6
0.00
0.00
0.00
524.00
366.00
317.00
No. of Units
No. of Days
Daily Rate
Quantity
Unit
Unit Cost
1
2
2
1
2
3
3
0.50
1
pc.
pcs.
pcs.
pc.
pcs.
pcs.
pcs.
pcs.
pc.
Sub-Total for A
d Capacity
Sub-Total for B
Total (A+B)
UNIT/DAY
Specifications
ed Spigot)
le Coupling, (D.I.)
on in Accordance w/ ISO 2531
10,205.00
5,287.91
4,308.00
12,879.00
4,000.00
3,965.93
2,730.00
9,988.85
1,402.00
. Steel Bar
0.42
56
10.67
0.27
2.62
0.10
0.21
pc.
pcs.
kgs.
pc.
bags
cu.m.
cu.m.
4,340.00
62.76
140.00
266.00
260.00
1,000.00
1,000.00
Sub-Total for E
9% per D.O. 29 s 2011
8% per D.O. 29 s 2011
12% per D.O. 29 s 2011
Daily Rate
Amount
524.00
366.00
317.00
P
Daily Rate
Amount
Unit Cost
10,205.00
5,287.91
4,308.00
12,879.00
4,000.00
3,965.93
2,730.00
9,988.85
1,402.00
Amount
10,205.00
10,575.82
8,616.00
12,879.00
8,000.00
11,897.79
8,190.00
4,994.43
1,402.00
4,340.00
62.76
140.00
266.00
260.00
1,000.00
1,000.00
P
29 s 2011
29 s 2011
29 s 2011
1,808.33
3,514.56
1,493.33
71.82
680.07
104.63
209.25
84,642.02
84,642.02
7,617.78
6,771.36
11,883.74
110,914.91
#DIV/0!
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
CU.M.
40.00
528.63
CU.M./DAY
CU.M.
Designation
A.
No. P
Labor
a.
Construction Foreman
b.
Laborers
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Tamper Rammer Machine
b.
Plate Compactor
c.
Payloader (1.50 cu.m.), LX80-2C
Minor Tools (10%)
Sub-Total for B
Total (A+B)
40.00
CU.M./DAY
Materials
Item 104
Qua
528
Sub-Total for E
F.
G.
H.
I.
No. o
J.
k.
Total Cost
Total Unit Cost
No. Person
No. of Days
Daily Rate
1
8
13.22
13.22
524.00
317.00
6,925.01
33,514.94
P
No. of Units
No. of Days
Daily Rate
2
2
1
13.22
13.22
13.22
1,000.00
984.00
13,864.00
Quantity
Unit
528.63
cu.m.
Unit Cost
40,439.95
Amount
26,431.34
26,008.44
183,222.06
4,044.00
239,705.84
280,145.79
Amount
350.00
P
10% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
Amount
185,019.39
185,019.39
465,165.18
46,516.52
-
511,681.70
967.95
DETAILE
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
UNITS/DAY
UNITS
Designation
A.
Labor
a.
Construction Foreman
b.
Skilled Worker
c.
Plumber
d.
Laborers
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
N.A.
Sub-Total for B
Total (A+B)
Output per day
2.00
Name and Specifications
E.
Materials
50mm x 50mm C.I. Tee, M/M
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
50mm
50mm
50mm
50mm
25mm
F.
G.
H.
I.
J.
k.
Designation
No. Person
No. of Days
1
2
2
8
11.50
11.50
11.50
11.50
No. of Units
No. of Days
Quantity
Unit
23.00
23.00
23.00
3.00
23.00
23.00
pcs.
pcs.
pcs.
rolls
pcs.
pcs.
69.00
23.00
pcs.
pcs.
Sub-Total for A
Name and Capacity
Sub-Total for B
Total (A+B)
UNITS/DAY
e Coupling, (P.E.)
SDR 11
46.00
23.00
23.00
23.00
23.00
pcs.
pcs.
pcs.
pcs.
pcs.
Sub-Total for E
10% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
onanca
L FAUCET
Daily Rate
524.00
366.00
394.00
317.00
Amount
6,026.00
8,418.00
9,062.00
29,164.00
P
Daily Rate
Unit Cost
52,670.00
Amount
52,670.00
Amount
1,850.00
950.00
650.00
7,300.00
520.00
110.00
42,550.00
21,850.00
14,950.00
21,900.00
11,960.00
2,530.00
300.00
800.00
20,700.00
18,400.00
50.00
1,050.00
25.00
90.00
20.00
P
per D.O. 22 s 2015
per D.O. 22 s 2015
per D.O. 22 s 2015
2,300.00
24,150.00
575.00
2,070.00
460.00
184,395.00
237,065.00
23,706.50
260,771.50
11,337.89
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Location
200
CU.M.
34.40
0.58
Kasanyangan
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.58
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.58
Total volume
Designation
A.
Labor
a.
Construction Foreman
b.
Laborers
No. Pe
1
8
Sub-Total for A
Name and Capacity
B.
Equipment
a.
Tamper Rammer Machine
b.
Water Truck (1000 gal.)
Minor Tools (10%)
No. of
2
2
C.
D.
Sub-Total for B
Total (A+B)
34.40
CU.M./DAY
Materials
Item 200 (Aggregate Subbase Course)
Sub-Total for E
F.
G.
H.
I.
J.
k.
Quan
0.5
No. Person
No. of Days
Daily Rate
1
8
0.02
0.02
524.00
317.00
Amount
8.83
42.72
P
No. of Units
No. of Days
Daily Rate
2
2
0.02
0.00
1,000.00
8,520.00
51.55
Amount
33.69
28.71
5.00
Quantity
Unit
0.58
cu.m.
Unit Cost
Amount
680.00
P
9% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
67.40
118.95
394.13
394.13
513.08
46.18
559.26
964.90
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Designation
A.
No. P
Labor
a.
Construction Foreman
b.
Laborers
c.
Carpenter
d.
Mason
e.
Light Equipment Operator
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Concrete Mixer
b.
Concrete Vibrator
c.
Water Truck (1000 gal.)
Minor Tools (10%)
Sub-Total for B
Total (A+B)
62.61
SQ.M./DAY
No. o
Materials
Curing Compound
Portland Cement
Washed Sand
Gravel (331A)
Qua
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
15
1
2
3
5
5
5
5
5
524.00
317.00
366.00
366.00
394.00
2,856.61
25,922.09
1,995.26
3,990.53
6,443.72
P
No. of Units
No. of Days
Daily Rate
1
2
1
5
5
5
1,376.00
1,192.00
8,520.00
Unit
Unit Cost
99
1051
42
63
ltrs.
bags
cu.m.
cu.m.
30.00
260.00
1,000.00
1,000.00
41,208.21
Amount
7,501.32
12,996.48
46,447.15
4,121.00
P
Quantity
Amount
71,065.95
112,274.16
Amount
2,969.43
273,324.25
42,049.88
63,074.83
P
6% per D.O. 29 s 2011
8% per D.O. 29 s 2011
12% per D.O. 29 s 2011
381,418.40
493,692.56
29,621.55
39,495.40
67,537.14
630,346.66
1,846.82
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Designation
A.
Labor
a.
Construction Foreman
b.
Skilled Worker
c.
Laborers
SQ.M.
No. P
1
6
1
Sub-Total for A
C.
D.
Equipment
a.
Asphalt Paver (80 Hp)
b.
Pneumatic Roller (10 m.t.)
c.
Tandem Steel Roller (10.1 m.t.)
d.
Dump Truck (10 cu.m.)
e.
Asphalt Batch Plant (60-80 TPH)
f.
Water Truck (1000 gal.)
g.
Payloader (1.50 cu.m.)
Minor Tools (10% of Labor)
Sub-Total for B
Total (A+B)
Output per day
=
1,370.40
SQ.M./DAY
Name and Specifications
E.
Materials
a.
Asphalt Cement (6.5%)
b.
Aggregates (93%)
c.
Mineral Filler (7%)
(w/ 5% wastage)
No. of
1
1
1
2
1
1
1
Qua
0.
5.
15
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
6
12
0.09
0.09
0.09
524.00
366.00
317.00
45.03
188.73
326.93
P
No. of Units
No. of Days
Daily Rate
1
1
1
2
1
1
1
0.09
0.09
0.09
0.09
0.09
0.09
0.09
14,664.00
4,424.00
13,216.00
10,816.00
9,717.84
8,520.00
13,864.00
P
Quantity
Unit
0.96
5.75
15.58
m.t.
cu.m.
bag
Amount
Unit Cost
50,775.00
1,000.00
245.00
560.69
Amount
1,260.27
380.21
1,135.82
1,859.12
835.18
732.24
1,191.51
56.00
7,450.36
8,011.05
Amount
48,976.99
5,750.43
3,817.55
58,544.97
66,556.02
3,993.36
5,324.48
9,104.86
84,978.73
721.53
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
311 (1)b
Unit of Measurement:
SQ.M.
1,680.00
0.00
Location
Kasanyangan
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
SQ.M./DAY
SQ.M.
Total Area
Designation
A.
Labor
a.
Construction Foreman
b.
Skilled Worker
c.
Laborers
No. Person
No. of Days
1
12
36
0.00
0.00
0.00
No. of Units
No. of Days
12
6
3
0.00
0.00
0.00
Sub-Total for A
Name and Capacity
B.
Equipment
a.
Transit Mixer (5 cu.m.)
b.
Concrete Vibrator
c.
Batching Plant (30 cu.m.)
Page 233 of 298
d.
e.
f.
C.
D.
Sub-Total for B
Total (A+B)
=
1,680.00
0.00
0.00
0.00
Quantity
Unit
SQ.M./DAY
3
3
3
Materials
a.
b.
c.
d.
Kasanyangan
1.00
0.00
0.00
1.00
Curing Compound
Washed Sand
Gravel (311-a)
Portland Cement
lit.
cu.m.
cu.m.
bags
0.00
a.
b.
c.
d.
Curing Compound
Washed Sand
Gravel (311-a)
Portland Cement
1.00
0.00
0.00
1.00
lit.
cu.m.
cu.m.
bags
1.00
0.00
0.00
1.00
lit.
cu.m.
cu.m.
bags
1.00
0.00
0.00
0.00
lit.
cu.m.
cu.m.
bags
0.00
0.00
0.00
0.00
lit.
cu.m.
cu.m.
bags
0.00
0.00
0.00
1.00
lit.
cu.m.
cu.m.
bags
1.00
0.00
0.00
1.00
lit.
cu.m.
cu.m.
bags
0.00
0.00
0.00
lit.
cu.m.
cu.m.
0.00
a.
b.
c.
d.
Curing Compound
Washed Sand
Gravel (311-a)
Portland Cement
a.
b.
c.
d.
Curing Compound
Washed Sand
Gravel (311-a)
Portland Cement
0.00
0.00
a.
b.
c.
d.
Curing Compound
Washed Sand
Gravel (311-a)
Portland Cement
0.00
a.
b.
c.
d.
Curing Compound
Washed Sand
Gravel (311-a)
Portland Cement
0.00
a.
b.
c.
d.
Curing Compound
Washed Sand
Gravel (311-a)
Portland Cement
a.
b.
c.
Curing Compound
Washed Sand
Gravel (311-a)
0.00
d.
Portland Cement
0.00
bags
0.00
0.00
0.00
1.00
lit.
cu.m.
cu.m.
bags
1.00
0.00
0.00
0.00
lit.
cu.m.
cu.m.
bags
0.00
a.
b.
c.
d.
Curing Compound
Washed Sand
Gravel (311-a)
Portland Cement
0.00
a.
b.
c.
d.
Curing Compound
Washed Sand
Gravel (311-a)
Portland Cement
Sub-Total for E
F.
G.
H.
I.
J.
k.
9% per D.O
0% per D.O
0% per D.O
No. of Days
Daily Rate
0.00
0.00
0.00
524.00
366.00
317.00
Amount
P
No. of Days
Daily Rate
0.00
0.00
0.00
10,232.00
1,191.04
9,664.24
Amount
0.00
0.00
0.00
13,864.00
4,360.00
8,520.00
Unit
Unit Cost
Amount
Kasanyangan
lit.
cu.m.
cu.m.
bags
28.00
1,000.00
1,000.00
265.00
28.00
265.00
0.00
lit.
cu.m.
cu.m.
bags
28.00
1,000.00
1,000.00
265.00
28.00
-
lit.
cu.m.
cu.m.
bags
28.00
1,000.00
1,000.00
265.00
lit.
cu.m.
cu.m.
bags
28.00
1,000.00
1,000.00
265.00
lit.
cu.m.
cu.m.
bags
28.00
1,000.00
1,000.00
265.00
lit.
cu.m.
cu.m.
bags
28.00
1,000.00
1,000.00
265.00
lit.
cu.m.
cu.m.
bags
28.00
1,000.00
1,000.00
265.00
lit.
cu.m.
cu.m.
28.00
1,000.00
1,000.00
265.00
0.00
28.00
265.00
0.00
28.00
-
0.00
0.00
265.00
0.00
28.00
265.00
0.00
bags
265.00
lit.
cu.m.
cu.m.
bags
28.00
1,000.00
1,000.00
265.00
lit.
cu.m.
cu.m.
bags
28.00
1,000.00
1,000.00
265.00
0.00
265.00
0.00
P
per D.O. 22 s 2015
per D.O. 22 s 2015
per D.O. 22 s 2015
28.00
1,758.00
1,758.00
158.22
1,916.22
#DIV/0!
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Location
302a
M.T./DAY
M.T.
Quantity of Emulsified
Asphalt (M.T.)
Kasanyangan
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Designation
A.
No.
Labor
a.
Construction Foreman
b.
Laborers
Sub-Total for A
Name and Capacity
B.
Equipment
a.
Asphalt Distributor
b.
Power Broom
Minor Tools (10%)
Page 241 of 298
No.
C.
D.
Sub-Total for B
Total (A+B)
2.40
M.T./DAY
Qu
Materials
Kasanyangan
a.
a.
0
0.00
0
0.00
a.
0.00
a.
a.
0
0.00
0
0.00
a.
F.
G.
H.
I.
J.
k.
IT PRICE ANALYSIS
No. Person
No. of Days
Daily Rate
1
3
0.00
0.00
524.00
317.00
Amount
P
No. of Units
No. of Days
Daily Rate
1
1
0.00
0.00
7,488.00
1,044.32
Amount
Unit Cost
Quantity
Unit
Amount
0.00
m.t.
44,000.00
0.00
m.t.
44,000.00
0.00
m.t.
44,000.00
Kasanyangan
0.00
0.00
0.00
0.00
m.t.
44,000.00
0.00
m.t.
44,000.00
0.00
m.t.
44,000.00
0.00
0.00
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
310(b)
SQ.M.
1,370.40
0.00
Location
Kasanyangan
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total Area
Designation
A. Labor
a.
Construction Foreman
b.
Skilled Worker
c.
Laborers
No. Person
No. of Days
1
6
12
0.00
0.00
0.00
No. of Units
No. of Days
1
1
1
2
1
1
1
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Sub-Total for A
Name and Capacity
B. Equipment
a.
Asphalt Paver (80 Hp)
b.
Pneumatic Roller (10 m.t.)
c.
Tandem Steel Roller (10.1 m.t.)
d.
Dump Truck (10 cu.m.)
e.
Asphalt Batch Plant (60-80 TPH)
f.
Water Truck (1000 gal.)
g.
Payloader (1.50 cu.m.)
Minor Tools (10% of Labor)
C.
D. Output per day
Sub-Total for B
Total (A+B)
=
1,370.40
SQ.M./DAY
Quantity
Unit
E. Materials
a.
b.
c.
Kasanyangan
0.00
0.00
0.00
m.t.
cu.m.
bags
Sub-Total for E
F.
G.
H.
I.
J.
k.
9% per D.O. 22
0% per D.O. 22
0% per D.O. 22
IT PRICE ANALYSIS
Daily Rate
Amount
524.00
366.00
317.00
Daily Rate
14,664.00
4,424.00
13,216.00
10,816.00
9,717.84
8,520.00
13,864.00
Amount
Unit Cost
Amount
Kasanyangan
50,775.00
1,000.00
245.00
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Location
Kasanyangan
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
310(b)
SQ.M.
685.20
0.00
Designation
A.
Labor
a.
Construction Foreman
b.
Skilled Worker
c.
Laborers
Sub-Total for A
Name and Capacity
B.
Equipment
a.
Asphalt Paver (80 Hp)
b.
Pneumatic Roller (10 m.t.)
c.
Tandem Steel Roller (10.1 m.t.)
d.
Dump Truck (10 cu.m.)
e.
Asphalt Batch Plant (60-80 TPH)
f.
Water Truck (1000 gal.)
Page 251 of 298
g.
Payloader (1.50 cu.m.)
Minor Tools (10% of Labor)
C.
D.
Sub-Total for B
Total (A+B)
685.20
SQ.M./DAY
Materials
Kasanyangan
a.
b.
c.
a.
b.
c.
0.00
0.00
a.
b.
c.
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
6
12
0.00
0.00
0.00
524.00
366.00
317.00
Amount
No. of Units
No. of Days
Daily Rate
1
1
1
2
1
1
0.00
0.00
0.00
0.00
0.00
0.00
14,664.00
4,424.00
13,216.00
10,816.00
9,717.84
8,520.00
Amount
0.00
13,864.00
Quantity
Unit
Unit Cost
Amount
0.00
0.00
0.00
m.t.
cu.m.
bags
50,775.00
1,000.00
245.00
0.00
0.00
0.00
m.t.
cu.m.
bags
50,775.00
1,000.00
245.00
Kasanyangan
0.00
0.00
0.00
0.00
0.00
m.t.
cu.m.
bags
50,775.00
1,000.00
245.00
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
310(b)
SQ.M.
456.80
0.00
Location
Kasanyangan
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Total Area
Designation
A. Labor
a.
Construction Foreman
b.
Skilled Worker
c.
Laborers
No. Person
No. of Days
1
6
12
0.00
0.00
0.00
No. of Units
No. of Days
1
1
1
2
1
1
0.00
0.00
0.00
0.00
0.00
0.00
Sub-Total for A
Name and Capacity
B. Equipment
a.
Asphalt Paver (80 Hp)
b.
Pneumatic Roller (10 m.t.)
c.
Tandem Steel Roller (10.1 m.t.)
d.
Dump Truck (10 cu.m.)
e.
Asphalt Batch Plant (60-80 TPH)
f.
Water Truck (1000 gal.)
Page 257 of 298
g.
Payloader (1.50 cu.m.)
Minor Tools (10% of Labor)
Sub-Total for B
C.
Total (A+B)
D. Output per day
=
456.80
0.00
Quantity
Unit
0.00
0.00
0.00
m.t.
cu.m.
bags
0.00
0.00
1.00
m.t.
cu.m.
bags
SQ.M./DAY
a.
b.
c.
0.00
0.00
a.
b.
c.
0.00
0.00
1.00
m.t.
cu.m.
bags
Sub-Total for E
F.
G.
H.
I.
J.
k.
9% per D.
0% per D.
0% per D.
No. of Days
Daily Rate
0.00
0.00
0.00
524.00
366.00
317.00
Amount
No. of Days
Daily Rate
0.00
0.00
0.00
0.00
0.00
0.00
14,664.00
4,424.00
13,216.00
10,816.00
9,717.84
8,520.00
Amount
0.00
13,864.00
Unit
Unit Cost
Amount
0.00
m.t.
cu.m.
bags
50,775.00
1,000.00
245.00
m.t.
cu.m.
bags
50,775.00
1,000.00
245.00
0.00
245.00
0.00
m.t.
cu.m.
bags
50,775.00
1,000.00
245.00
P
per D.O. 22 s 2015
per D.O. 22 s 2015
per D.O. 22 s 2015
245.00
490.00
490.00
44.10
534.10
#DIV/0!
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
310(b)
SQ.M.
1,370.40
Err:509
Location
Designation
No. Person
A. Labor
a.
Construction Foreman
b.
Skilled Worker
c.
Laborers
1
24
48
Sub-Total for A
Name and Capacity
B. Equipment
a.
Asphalt Paver (80 Hp)
b.
Pneumatic Roller (10 m.t.)
c.
Tandem Steel Roller (10.1 m.t.)
d.
Dump Truck (10 cu.m.)
e.
Asphalt Batch Plant (60-80 TPH)
f.
Water Truck (1000 gal.)
g.
Payloader (1.50 cu.m.)
Minor Tools (10% of Labor)
Sub-Total for B
C.
Total (A+B)
D. Output per day
=
1,370.40
No. of Units
4
4
4
8
4
4
4
SQ.M./DAY
Quantity
Err:509
Err:509
Err:509
CE ANALYSIS
oanga City
No. of Days
Daily Rate
Amount
Err:509
Err:509
Err:509
524.00
366.00
317.00
Err:509
Err:509
No. of Days
Daily Rate
Amount
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
14,664.00
4,424.00
13,216.00
10,816.00
9,717.84
8,520.00
13,864.00
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Unit
m.t.
cu.m.
bags
Unit Cost
Amount
50,775.00
1,000.00
245.00
P
9% per D.O. 29 s 2011
8% per D.O. 29 s 2011
12% per D.O. 29 s 2011
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
Err:509
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
Designation
A.
Labor
a.
Construction Foreman
b.
Skilled Worker
c.
Laborers
No. P
1
4
4
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Concrete Mixer
b.
Concrete Vibrator
c.
Welding Machine
Minor Tools (10% of Labor)
1
1
1
Sub-Total for B
Total (A+B)
0.40
UNIT/DAY
No. of
Materials
a.
Cement
b.
Sand
c.
Gravel
d.
*16mm x 6.0 Reinforcing Steel Bar
e.
#16 GI Tie Wire
f.
*4mm thk. X 50mm x 50mm x 6mm MS Angle Bar
g.
*16mm x 6.00m Stainless Steel Rod
h.
150mm x 6.00m PVC Pipe, Class 150, w/ B/S & R.R.
i.
1m x 1.50m D.I. Rectangular Manhole Frame Double Cover, Light Series
Qua
3.
1.
2.
30
4.
1.
2.
1.
1.
j.
k.
l.
m.
n.
o.
p.
q.
r.
Sub-Total for E
F.
G.
H.
I.
J.
k.
1.
5.
150
3.
0.
3.
5.
17
1.
No. Person
No. of Days
Daily Rate
1
4
4
2.5
2.5
2.5
524
366.00
317.00
1,310.00
3,660.00
3,170.00
P
No. of Units
No. of Days
Daily Rate
1
1
1
2.50
2.50
2.50
1,376.00
1,192.00
3,128.00
P
Quantity
Unit
3.00
1.50
2.00
30.00
4.00
1.00
2.00
1.00
1.00
bags
cu.m.
cu.m.
pcs.
pcs.
pc.
pcs.
pc.
pc.
Amount
Unit Cost
260.00
1,000.00
1,000.00
337.00
75.00
1,045.00
2,325.07
4,609.50
71,500.00
8,140.00
Amount
3,440.00
2,980.00
7,820.00
814.00
15,054.00
23,194.00
Amount
780.00
1,500.00
2,000.00
10,110.00
300.00
1,045.00
4,650.14
4,609.50
71,500.00
1.00
5.00
150.00
3.00
0.25
3.00
5.00
17.00
1.00
kg.
sheets
bd.ft
kgs.
kg.
pcs.
pcs.
pcs.
pc.
144.00
950.00
20.00
80.00
340.00
56.00
266.00
130.00
260.00
P
6% per D.O. 29 s 2011
8% per D.O. 29 s 2011
12% per D.O. 29 s 2011
144.00
4,750.00
3,000.00
240.00
85.00
168.00
1,330.00
2,210.00
260.00
108,681.64
131,875.64
7,912.54
10,550.05
18,040.59
168,378.81
168,378.81
Designation
A.
No.
Labor
a.
Construction Foreman
b.
Laborers
c.
Pipefitter
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
Sub-Total for B
Total (A+B)
20.62
LN.M./DAY
Materials
a.
50mm. x 60m P.E. Tubing, SDR 11
Sub-Total for E
F.
G.
H.
I.
J.
k.
No.
Qu
IT PRICE ANALYSIS
No. Person
No. of Days
Daily Rate
1
8
1
5.82
5.82
5.82
366.00
317.00
341.00
2,130.12
14,759.52
1,984.62
P
No. of Units
No. of Days
Daily Rate
Quantity
Unit
rolls
Unit Cost
18,874.26
Amount
18,874.26
Amount
10,713.00
P
6% per D.O. 29 s 2011
8% per D.O. 29 s 2011
12% per D.O. 29 s 2011
Amount
21,426.00
21,426.00
40,300.26
2,418.02
3,224.02
5,513.08
51,455.37
428.79
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
BRIDGE CROSSING
LN.M.
LN.M.
Designation
A.
Labor
a.
Pipefitter
b.
Skilled Worker
c.
Laborer
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Generator Set/ Welding Machine w/ complete accessories (w/ fuel)
b.
Boom Truck
c.
Cut-off Saw
Sub-Total for B
Total (A+B)
3.00
Materials
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
m.
n.
o.
p.
q.
r.
s.
Portland Cement
Washed Sand
Gravel
16mm x 6.00m Deformed Reinf. Steel Bar
12mm Thk x 1.20m x 2.40m Ordinary Plywood
2" x 2" x 8' Coco Lumber
1-1/2" C.W. Nail
3" C.W. Nail
Sub-Total for E
F.
G.
H.
I.
J.
k.
ation
No. Person
No. of Days
Daily Rate
3
9
18
63.33
63.33
63.33
394.00
366.00
317.00
b-Total for A
Capacity
No. of Units
No. of Days
Daily Rate
3
3
3
63.33
63.33
63.33
2,160.00
9,600.00
200.00
b-Total for B
Total (A+B)
LN.M.
ecifications
MS Angle Bar
t & Washer
/day
Quantity
Unit
190.00
373.67
76
1520
95
28.5
19
26.6
26.6
13.3
6.65
ln.m.
pcs.
pcs.
pcs.
pcs.
kgs.
pcs.
gals
gals
gals
pcs.
Unit Cost
95,856.00
1,123.00
146.00
65.00
894.00
145.00
200.00
480.00
558.80
480.00
50.00
f. Steel Bar
inary Plywood
532
26.01
52.02
17472.00
128.00
5937.5
17.81
41.56
bags
cu.m.
cu.m.
kgs.
shts.
bd.ft.
kg.
kg.
240.00
1,000.00
1,000.00
45.50
750.00
20.00
65.00
65.00
P
ub-Total for E
6% per D.O. 29 s 2011
8% per D.O. 29 s 2011
12% per D.O. 29 s 2011
Amount
74,860.00
208,620.00
361,380.00
644,860.00
Amount
410,400.00
1,824,000.00
38,000.00
2,272,400.00
2,917,260.00
Amount
18,212,640.00
419,627.67
11,096.00
98,800.00
84,930.00
4,132.50
3,800.00
12,768.00
14,864.08
6,384.00
332.50
127,680.00
26,008.89
52,017.78
794,976.00
96,000.00
118,750.00
1,157.81
2,701.56
20,088,666.79
23,005,926.79
1,380,355.61
1,840,474.14
3,147,210.78
29,373,967.32
154,599.83
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPL-10
cu.m.
28.90
483.52
Designation
A.
Labor
a.
Construction Foreman
b.
Laborers
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Tamper Rammer Machine
Sub-Total for B
Total (A+B)
28.90
Materials
N.A.
Note: Native Materials will be used in backfilling works
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
10
17
17
524.00
317.00
8
53
otal for A
pacity
No. of Units
No. of Days
Daily Rate
17
984.00
62
Amount
16
otal for B
l (A+B)
Amount
16
79
cu.m./day
fications
Quantity
Unit
Unit Cost
Amount
ckfilling works
otal for E
9% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
79
7
86
Amount
8,908.00
53,890.00
62,798.00
Amount
16,728.00
16,728.00
79,526.00
Amount
79,526.00
7,157.34
86,683.34
179.28
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPLcu.m.
0.875
1.00
Designation
A.
Labor
a.
Construction Foreman
b.
Skilled Laborer
c.
Laborers
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Concrete Bagger Mixer
Sub-Total for B
Total (A+B)
0.875
Materials
a.
Portland Cement
b.
Washed Sand
c.
Gravel (G-1)
d.
16mm. x 6.00m. Def. Reinforcing Steel Bars
e.
10mm. x 6.00m. Def. Reinforcing Steel Bars
f.
#16 G.I. Tie-wire
g.
12mm. Thk. x 1.20m. x 2.40m. Ordinary Plywood
h.
20pcs. 2" x 3" x 10' Coco Lumber
i.
2" C.W. Nail
j.
4" C.W. Nail
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
2
4
1
1
1
524.00
366.00
317.00
52
73
1,26
P
otal for A
pacity
No. of Units
No. of Days
Daily Rate
1,376.00
2,52
Amount
1,37
otal for B
l (A+B)
Amount
1,37
3,90
cu.m./day
fications
Steel Bars
Steel Bars
dinary Plywood
otal for E
Quantity
Unit
11
0.50
1
4
7
1
6
100
2
2
bags
cu.m.
cu.m.
pcs.
pcs.
kg.
shts.
bd.ft.
kgs.
kgs.
Unit Cost
Amount
280.00
1,000.00
1,000.00
335.00
175.00
75.00
800.00
20.00
53.00
59.00
P
3,08
50
1,00
1,34
1,22
7
4,80
2,00
10
11
14,24
18,14
1,63
19,77
19,77
Amount
524.00
732.00
1,268.00
2,524.00
Amount
1,376.00
1,376.00
3,900.00
Amount
3,080.00
500.00
1,000.00
1,340.00
1,225.00
75.00
4,800.00
2,000.00
106.00
118.00
14,244.00
18,144.00
1,632.96
19,776.96
19,776.96
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPLln.m.
50.00
6.20
CONCRETE CUTTING
ln.m./day
ln.m.
Designation
A.
Labor
a.
Construction Foreman
b.
Skilled Laborer
c.
Laborers
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Concrete Cutter
Minor Tools (10% of labor cost)
Sub-Total for B
Total (A+B)
50.00
Materials
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
1
1
0.12
0.12
0.12
524.00
366.00
317.00
6
4
3
P
otal for A
pacity
No. of Units
No. of Days
Daily Rate
0.12
1,758.00
14
Amount
21
1
P
otal for B
l (A+B)
fications
Amount
22
37
ln.m./day
Quantity
Unit
Unit Cost
Amount
otal for E
9% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
37
3
40
6
Amount
62.88
43.92
38.04
144.84
Amount
210.96
14.48
225.44
370.28
Amount
370.28
33.33
403.61
65.10
PROJECT NAME:
PROJECT LOCATION:
Item No./Description:
Unit of Measurement:
Output per day:
Quantity:
SPLcu.m.
0.875
0.62
CONCRETE RESTORATION
ln.m./day
cu.m.
Designation
A.
Labor
a.
Construction Foreman
b.
Skilled Laborer
c.
Laborers
Sub-Total for A
Name and Capacity
B.
C.
D.
Equipment
a.
Concrete Bagger Mixer
Sub-Total for B
Total (A+B)
0.88
Materials
a.
b.
c.
Sub-Total for E
F.
G.
H.
I.
J.
k.
No. Person
No. of Days
Daily Rate
1
2
2
0.71
0.71
0.71
524.00
366.00
317.00
pacity
No. of Units
No. of Days
Daily Rate
0.71
1,376.00
1,34
Amount
97
otal for B
l (A+B)
fications
37
51
45
P
otal for A
Amount
97
2,31
ln.m./day
Quantity
Unit
Unit Cost
Amount
otal for E
9% per D.O. 22 s 2015
0% per D.O. 22 s 2015
0% per D.O. 22 s 2015
2,31
20
2,52
4,07
60*trench width*0.61*noofteam
Amount
0.62
372.04
519.72
450.14
1,341.90
Amount
Php
DURATION:\
976.96 22.28
976.96
2,318.86
Amount
2,318.86
208.70
2,527.56
4,076.71
328.21782
548.62
L:
A:
6.2
0.1681
1.04222
0.52111
no sand bedding:
0.2562
0.17
0.42
469.31732736