Академический Документы
Профессиональный Документы
Культура Документы
Pile foundation
Due to the fact that the good foundation soil is exceeded by the presence of the
underground car park, the foundation system must be changed from a general mat to pile
foundation.
A pile foundation consists of two components: Pile cap and single or group of piles. Piles
transfers the loads from structures to the hard strata, rocks or soil with high bearing capacity.
These are long and slender members whose length can be more than 15m.
Piles can be made from concrete, wood or steel depending on the requirements. These
piles are then driven, drilled or jacked into the ground and connected to pile caps. Pile foundation
are classified based on material of pile construction, type of soil, and load transmitting
characteristic of piles.
The use of pile foundations as load carrying and load transferring systems has been for
many years. Timber piles were used in early days, driven in to the ground by hand or holes were
dug and filled with sand and stones. The use of steel pile started since 19th century and concrete
piles since 20th century.
With the change in technology and industrial revolution, many advance systems have
been devloped for pile driving from the invention of steam and diesel pile driving machines.
The use of pile foundations is increasing day by day due to non-availability of land for
construction. Heavy multi-storyed building are being constructed, and load from these structures
can not be directly transferred to ground due to low bearing capacity issue and stability issues of
building during lateral load application. So, demand for use of pile foundations are increasing
day by day. Due to this demand for piles, there have been many improvements in piles and pile
driving technology and systems. Today there are many advanced techniques of pile installation.
There are three types of pile foundations according to their construction methods:
1. Driven piles;
2. Cast-in-situ piles;
NK [kN]
A
5064
4125
4973
5470
5734
4537
5860
3544
5120
3465
2842
2350
Availability of a full product inspection to ensure that no defects are present prior to
installation of the pile.
Precast piles are generally top driven into the ground using hydraulic drop hammers.
Sound levels from modern drop hammers are comparable to other piling systems such as
continuous flight auger (CFA). Noise during piling can be further reduced by shrouding the drop
hammer. The variety of segment lengths available, along with specialist piling equipment, makes
precast piles particularly suited to restricted access and low headroom sites.
Lnec= hV+ hA + hB+ 1 m Df + 0.25 m
= 0.5 + 1.6 + 6 + 1 1 + 0.25 = 8.1 m
Well choose PA-35-15.00
4 20+ 416 PC52
Mcap = 68.5kN*m
Qcap = 101.50kN
b) Resistance of thepile
b.1) Working alone
= 11640 kPa
Rb,k= 1425.9 kN
Rs,k= U * (li*qski)
, where U= 4*d = 1.4 m
For layer 1:
l1 = hA 0.3 = 0.8 m
D1 = hv+ hA l1/2 = 1.2 m and qsk1= 36.575 kPa
Rs,k,1= 1.4 * 0.8 * 36.575 = 40.964 kN
For layer 2:
Rs,k,2= U*l2*qsk2
l2 = 6 m
D2 = hV+ hA+ hB/2 = 4.6 m
qsk2 = 54.1 kPa
Rs,k,2 = 1.4*6*54.1 = 454.44 kN
For layer 3:
Rs,k,3= U*l3*qsk3
l3 = 8.2 m
D3 = hV+ hA+ hB+ l3/2 = 3.2 m
qsk3 = 63.15kPa
Rs,k,2 = 1.4*8.2*63.15 = 724.962kN
Rs,k= Rs,k,1 + Rs,k,2 + Rs,k,3 = 1220.366 kN
Rc,k = 2646.26 kN
U(liqski)
1.4(0.836.575+654.1+ 8.263.15)
Rt,k=
=
m
2.4
Rc,d=
Design approach D2
Rbk
Rsk
1425.9
+
=
b 1
s 1
1.1
Rc,d=
Rck
t
2646.26
1.1
Rt,d=
Rtk
st
508.49
=442.17 kN
1.15
= 2405.7 kN
1220.366
1.1
= 2405.7 kN
= 508.49 kN
Rc,d,g= mu * Rc,d
Rt,d,g= mu * Rt,d
, where mu = f(r/r0)
r = 3d = 1.05 m
r0 = li*tgi
' d
i =
and d=
4
1= 5.25
2 = 7
3 = 0
r01 = 0.074
r02 = 0.737
r03 = 0
r0 = 0.811
mu =0.837