As some readers recall, Guofu also developed a HYSYS simulation with ConocoPhillips Optimized
Cascade LNG process. In that simulation, the same 5 million metric ton per year natural gas is liquefied
with a power consumption of about 191,600 kW. While with the APCI C3MR process, as you see, the
power consumption is about 179,900 kW. With this said, the C3MR process can save the liquefaction
power by about 6%, comparing against the ConocoPhillips Optimized Cascade process.
Thanks for watching this video, it is brought to you by +Guofu Chen ; more interesting topics can be found
atshowcase.guofuchen.com
For those who can't see the embedded video in this blog, please watch this video on youtube.com
at https://youtu.be/3sFCwP0zWuU