Вы находитесь на странице: 1из 43

New Zealand Electricity Commission - Wind

Generation Investigation Project

Stage 1 - Wind Generation Impact Studies


Final Report

prepared for

Transpower NZ LTD

DIgSILENT GmbH
Heinrich-Hertz-Strasse 9
D-72810 Gomaringen
Tel.: +49 7072 9168 - 0
Fax: +49 7072 9168- 88
http://www.digsilent.de
e-mail: mail@digsilent.de
Please contact
Koos Theron
Tel.: +64 3 9690 0081
e-mail: koos@digsilent.com.au
Team
Brad Henderson B.E
Dr.-Ing. Markus Poller

Published by
DIgSILENT GmbH, Germany
Copyright 2003. All rights
reserved. Unauthorised copying
or publishing of this or any part
of this document is prohibited.
May, 2007

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

Table of Contents

Table of Contents
1 Executive Summary........................................................................................................................... 5
1.1 Background .............................................................................................................................................. 5
1.2 Study Objectives....................................................................................................................................... 6
1.3 Study Results ........................................................................................................................................... 7
1.3.1 Voltage Sag Screening Results North Island........................................................................................ 7
1.3.2 Voltage Sag Screening Results South Island ....................................................................................... 7
1.3.3 Dynamic Simulation Results North Island............................................................................................ 7
1.3.4 Dynamic Simulation Results South Island ........................................................................................... 8
1.4 Conclusions and Recommendations............................................................................................................ 8
1.5 Study Assumptions ................................................................................................................................. 10
1.5.1 Scenarios .......................................................................................................................................... 10
1.5.2 Wind-farms ....................................................................................................................................... 11
1.6 Voltage Sag Screening ............................................................................................................................ 12
1.6.1 Voltage Sag Study Methodology.......................................................................................................... 12
1.6.2 North Island Power System Key Results............................................................................................ 13
1.6.3 South Island Power System Key Results ........................................................................................... 16
1.6.4 System Impact from Medium Voltage Faults (110 kV) .......................................................................... 18
1.7 Options to reduce wind farm tripping ....................................................................................................... 19
2 Dynamic Wind Impact Studies ........................................................................................................ 21
2.1 Study Assumptions ................................................................................................................................. 21
2.1.1 Wind-farms ....................................................................................................................................... 22
2.2 Dynamic Simulation of the NZ System...................................................................................................... 23
2.2.1 Dynamic Study Methodology............................................................................................................... 23
2.3 Summary of Dynamic results for the North Island ..................................................................................... 24
2.3.1 Wind Generation Tripping................................................................................................................... 24
2.3.2 Electrical frequency at Huntly ............................................................................................................. 25
2.3.3 Short term voltage instability, North Island.......................................................................................... 27
2.3.4 Interconnecting line flows, North Island .............................................................................................. 30
2.4 Summary of dynamic results for the South Island ..................................................................................... 30
2.4.1 Sudden Loss of Wind Generation ........................................................................................................ 30
2.4.2 Electrical frequency at Clyde............................................................................................................... 31
2.4.3 Short term voltage instability, South Island ......................................................................................... 33
2.4.4 Interconnecting line flows South Island ............................................................................................... 35
3 Concluding Remarks and Recommendations .................................................................................. 36

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

Table of Contents

4 References....................................................................................................................................... 37

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

1 Executive Summary

1 Executive Summary
1.1 Background
Transpower has engaged DIgSILENT to investigate the effects of the connection of large scale wind generation to
the NZ power system. This study is part of the Electricity Commission's Wind Generation Investigation Project
(WGIP).
The impact of large amounts of new wind generation on the stability of any power system can be significant,
especially if the wind generation is not equipped with Fault Ride Through (FRT1) capability. If wind generators
without FRT capability are widely used, a fault on the power system may cause voltage sags that can cause large
amounts of wind generation to disconnect from the power system. The consequences include fast frequency
drops, load shedding and voltage stability problems.
To investigate the impact of the of large scale wind generation on the New Zealand power system, ten
independent scenarios have been created for each of the North and the South Island systems. The scenarios
consist of five different wind generation levels (from 0-100% of installed wind generation capacity) and two
forecast load scenarios (high and low load) for the year 2016.
According to Electricity Commissions Scenario C, the peak installed wind generation capacity for the North Island
will be 1600 MW, while the system is forecast to have a peak demand of 5460 MW in 2016. In this extreme
situation with 1600 MW of wind generation and 960 MW supplied from the HVDC inter island link, only 50% of
the load will be supplied by other generation during some hours2. For light load conditions where forecast load
will be 2130 MW, only 25% of the load will be supplied by other generation.
The South Island power system is forecast to have a peak load of 2520 MW in 2016. With the assumptions of the
Electricitys Commissions Scenario C, which is a peak installed wind generation capacity of 700 MW, only 75% of
the load will be supplied by other generation. In light load conditions, this could drop to as low as 40%.
With such high levels of wind generation relative to other generation, a considerable impact of wind generation
on power system stability must be expected, especially if it is assumed that wind generation technology is without
FRT capability.

This study discusses FRT by the simulation of voltage dips. The term LVRT (Low Voltage Ride Through)
essentially refers to the same aspect but also includes post-fault wind generator behaviour, e.g. in the case of
slow voltage recovery. However, in literature, both terms are often used to describe the same behaviour.
2

In reality, max. 90% to 95% of installed wind generation capacity will be available simultaneously. Hence,
assuming 100% availability is a conservative study assumption.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

1 Executive Summary

1.2 Study Objectives


The Wind Generation Investigation Project (WGIP) is expected to involve several stages of analysis. For the stage
one study, the impact of wind generation on system stability is analyzed. In this stage of the study all wind
generators are without FRT capability.
For this stage of the study a two step approach has been taken:
Stage 1.1 of the study will establish the likely amount of wind generation that would trip off in each island in each
of the ten scenarios for faults at high voltage bus bars. The focus is on 220kV bus bars because it can be
expected that faults at the highest voltage level affect the largest areas. However, also faults at some 110kV bus
bars are studies for verifying this assumption. The studies will be performed using steady-state (short circuit)
analysis.
The key objectives for stage 1.1 are:

Assessment of the amount of tripped wind generation for a fault at each HV bus in the system under
worst case assumptions (no FRT-capability of any wind generator);

Identification of critical cases, by comparing the amount of lost generation with the normal spinning
reserve in each island (largest conventional unit);

Recommendations for reducing the amount of tripped wind generation;

It is important to emphasise that:

Wind generators in this study are fixed speed asynchronous machines without FRT capability and have
no fast acting reactive power compensation devices;

This is a transmission system impact study. Localised issues are not assessed. Some local issues must be
addressed in order to obtain sensible and consistent results, but these are not the focus of this study. It
is anticipated that any localised issues will be assessed in later stages of the study;

The primary purpose of the stage 1.1 studies is to determine the most severe faults - the faults causing
the greatest amount of tripped wind generation.

Stage 1.2 of this study will build on the results gained from stage 1.1 and perform dynamic analysis on the
system for a selection of the most critical cases.
Stage 1.2 will look to identify the following key aspects:

Confirm the results of stage 1.1 studies with dynamic simulations;

Highlight the impact of tripped wind generation on frequency and voltage stability. In particular to
identify any cases where the automatic under frequency load shedding (AUFLS) frequency limits are
reached and observe any cases of inadequate voltage stability.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

1 Executive Summary

1.3 Study Results


1.3.1 Voltage Sag Screening Results North Island
High-wind scenario (Wind generation is 100% of installed wind generation capacity):

During high load for the majority of 220 kV system faults, more than 350 MW of wind generation will
trip. This exceeds the normal spinning reserve of 350 MW.

During light load, many system faults cause the entire wind farm capacity of the North Island
(1600 MW) to trip.

Low-wind scenario (Wind generation is 25% of installed wind generation capacity):

During high load, only one 220 kV system fault causes more than 350 MW of wind generation to trip.

During light load, over 50% of the 220 kV faults cause more than 350 MW of wind generation to trip.

1.3.2 Voltage Sag Screening Results South Island


High wind scenario (100% wind generation):

During high load for the majority of 220 kV system faults, more than 120 MW of wind generation will
trip. This exceeds the normal spinning reserve of 120 MW.

During light load, many system faults cause the entire wind generation capacity of the South Island
(700 MW) to trip.

Low wind scenario (25% wind generation):

During high load, the majority of 220 kV system faults cause less than 120 MW of wind generation to
trip.

During light load, a majority of the 220 kV faults cause more than 120 MW of wind generation to trip.

1.3.3 Dynamic Simulation Results North Island


The voltage sag screening identified 20 critical cases from the North Island for in-depth dynamic simulation. The
results of these studies confirm the results obtained by the voltage sag screening and show the under frequency
and voltage stability problems caused by excessive wind generation tripping.
The results of the dynamic analysis for the North Island can be summarized as follows:

For a majority of the 20 cases the predicted tripped wind generation from the static analysis agrees with
the observed results from the dynamic simulations.

In 10 of the 20 cases the block 1 AUFLS set point of 47.8 Hz was reached.

Short term voltage instability was observed in several of the light load cases where a large amount of
wind generation tripped for 4 of these cases it is unlikely that load shedding would act fast enough to
prevent a complete system collapse.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

1 Executive Summary

1.3.4 Dynamic Simulation Results South Island


The voltage sag screening identified 10 critical cases from the South Island for in-depth dynamic simulation. The
results of these studies confirm the results obtained by the voltage sag screening and show the under frequency
and voltage stability problems caused by excessive wind generation tripping.
The results of the dynamic analysis for the South Island can be summarized as follows:

With the exception of two of the 10 cases, the predicted tripped wind generation from the static analysis
agrees exactly with the observed results from the dynamic simulations.

For 2 of the 10 cases the block 1 AUFLS set point of 47.5 Hz was reached.

Short term voltage instability was observed in case S_026 and case S_028 where a large amount of wind
generation tripped. In case S_026 it is unlikely that load shedding would act fast enough to prevent a
complete system collapse, whereas in case S_028 the load shedding would probably act fast enough to
prevent the voltage instability.

1.4 Conclusions and Recommendations


The results of the voltage sag screening have shown that many (n-1) contingent events, such as faults on single
transmission circuits, can lead to widespread tripping of wind generation if wind generators are not equipped with
FRT capability.
Observations from the dynamic simulations show that widespread tripping of wind generation can drive the
system into frequency stability problems resulting in widespread load shedding, or into dynamic voltage stability
problems.
For avoiding widespread load shedding following a contingent event during high wind generation there are mainly
two options, increasing spinning reserve and system inertia or building all major wind farms with wind turbines
having FRT capability.
However, increasing spinning reserve and system inertia requires that almost all wind generators are backed up
by non-wind generators, which leads to enormous additional spinning reserve. Besides this, the network must be
able to transport any additionally required reserve power. In this study, a number of cases were identified, where
the available transport capacity is not sufficient and consequently, the network runs into dynamic voltage
collapse. For avoiding this, network reinforcements would be required or inter-area power transfer must be
limited.
The second option, only allowing wind generators with FRT-capability, is fairly easy to realize because this kind of
wind generator is standard technology. Consequently, for avoiding drastically reduced reliability of supply in the
New Zealand power system there is only one practical solution:

Only allowing the connection of wind generators with FRT-capability.

This has become an international standard for power transmission systems with high wind penetration, e.g. in
Germany, Denmark, U.K. or Australia.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

1 Executive Summary

When connecting wind generators with FRT capability, additional reserve power is only required for backing up
wind fluctuations but not for backing up wind generator trips.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

1 Executive Summary

Voltage Sag Screening

1.5 Study Assumptions


For each island, 10 predefined load and wind generation scenarios were created. A brief summary of these
scenarios is given below in Table 1-1 and 2-2. When wind generation increases from 0-100% of installed wind
generation capacity less other generation is dispatched, resulting in a weaker system (lower grid short circuit
level). For more detail on the methodology for the development of the generation scenarios and modelling of the
wind generator plant please refer to the modelling report [1].
It is assumed that faults are cleared after 120ms, based on first zone protection tripping time and maximum
breaker delays or transfer tripping delays.

1.5.1 Scenarios
Case

Load (MW)

Wind Generation (MW)

HVDC Import MW

High Load 100% Wind Generation

5459.2

1603.6

960

High Load 75% Wind Generation

5459.2

1237.8

960

High Load 50% Wind Generation

5459.2

886.8

960

High Load 25% Wind Generation

5459.2

519.4

960

High Load 0% Wind Generation

5459.2

153.6

960

Light Load 100% Wind Generation

2131.4

1603.6

Light Load 75% Wind Generation

2131.4

1237.8

Light Load 50% Wind Generation

2131.4

886.8

Light Load 25% Wind Generation

2131.4

519.4

Light Load 0% Wind Generation

2131.4

153.6

Table 1-1 - Wind generation scenarios, North Island

Case

Load (MW)

Wind Generation (MW)

HVDC Export MW

High Load 100% Wind Generation

2519.8

708.7

1040

High Load 75% Wind Generation

2519.8

544.1

1040

High Load 50% Wind Generation

2519.8

387.8

970

High Load 25% Wind Generation

2519.8

223.2

800

High Load 0% Wind Generation

2519.8

58.7

640

Light Load 100% Wind Generation

1218.6

708.7

Light Load 75% Wind Generation

1218.6

544.1

Light Load 50% Wind Generation

1218.6

387.8

Light Load 25% Wind Generation

1218.6

223.2

Light Load 0% Wind Generation

1218.6

58.7

Table 1-2 - Wind generation scenarios, South Island

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

10

1 Executive Summary

1.5.2 Wind-farms
There are three existing wind-farms greater than 10MW on the New Zealand system, Te Apiti, Tararua and White
Hill. In addition to these, nine new wind-farms are modelled to bring the total installed capacity for the North
Island to approximately 1600 MW and the installed capacity for the South Island to approximately 700 MW. Each
of the new wind farms is scaled from 0 to 100% of installed wind generation capacity to create five generation
scenarios for each island3.
Each wind-farm was modelled with generic fixed speed asynchronous machines with no built in FRT capability
and no fast acting reactive power compensation. Further, it was assumed that each generator had no
contribution to the short circuit level of the grid.
The wind-farms are shown in the tables below.
Wind-farm

PCC (bus)

Units

Total Capacity (MW)

Marsden

MDN220

91

150

Otahuhu

OTA220

182

300

Huntly

HLY220

61

100

Hawkes Bay

RDF220

182

300

Manawatu

BPE220

182

300

Wilton

WIL220

182

300

Te Apiti

WDV110

55

90.2

Tararua

BPE334

96

63.36

1031

1603.56

Total

Table 1-3 - North Island Wind-farms

Wind-farm

PCC (bus)

Units

Total Capacity (MW)

Blenheim

BLN110

31

50

Timaru

TIM220

182

300

Invercargill

INV220

182

300

White Hill

NMA33

Total

36

58.68

431

708.68

Table 1-4 - South Island Wind-farms

The three existing wind-farms of Tararua, Te-Apiti and White Hills were not scaled for each different generation
scenario. Therefore, even the 0% scenario has a small level of wind generation.
4

Actually, Tararua wind farm contains 51x660kW machines connected to BPE0331 and 52x660kW machines
connected to LTN033. For modelling purposes, Transpower assumes that all machines are connected to BPE. For
the study results, this simplification is not relevant.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

11

1 Executive Summary

1.6 Voltage Sag Screening


1.6.1 Voltage Sag Study Methodology
Voltage sag screening was performed for the 20 scenarios. The methodology is as follows:
Assumptions for wind generators:

Each wind generator is a generic fixed speed asynchronous machine with no built in FRT-capability and
no fast acting reactive power compensation.

It is assumed that each induction machine provides no contribution to the short circuit power of the grid
(no short circuit current)5.

Every wind generator is equipped with an under-voltage relay with a setting a 0.8 p.u and a delay of
50ms. This corresponds to standard settings of low-cost wind generators.

Voltage Sag Screening Methodology:

For each bus bar in the system, calculate a solid (0 Ohm) 3 phase short circuit using the IEC minimum
fault method. Initially, only faults in the 220 kV system were considered as these are expected to result
in the most widespread voltage depression. The IEC minimum method is chosen because it allows for
zero short circuit contributions from asynchronous motor/generators to the fault and hence calculates
the lowest and most conservative value for the post fault bus voltages.

For each faulted bus, identify the wind farms that would trip off due to low bus voltage, (defined as
< 0.8 p.u) and sum the active power for each of these to give a wind generation tripped value.

Repeat for each scenario.

In reality asynchronous machines do provide some short circuit contribution. However, as a worst case
assumption, it is assumed that this contribution is negligible. In the dynamic simulations this contribution is
naturally captured and considered.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

12

1 Executive Summary

1.6.2 North Island Power System Key Results


In Figure 1-1 the observed wind generation trip for each 220 kV bus fault in the North Island system is shown.
This is for 100% wind generation capacity with the normal spinning reserve of 350 MW highlighted by the
horizontal red line. High load cases are shown in light blue and light load cases in deep red.
Two key points to note are:

In the light load scenarios the amount of wind generation to trip is generally much larger than the
corresponding high load scenario. This is expected due to the displacement of more other generation by
wind generation and a subsequently lower short circuit level in the light load case.

In most of the cases, the total wind generation trip exceeds the normal spinning reserve of 350MW. In
some of the light load cases, all wind generators on the North Island would trip.
1800

wind power tripped (MW)

1600
1400
1200
1000

HL
LL

800
600
400
200

ALB220
ARA220
ATI220
BPE220
BRB220
BRK220
EDG220
GLN220
HAM220
HAY220
HEN220
HLY220
HPI_220_1
KAW220
LTN_220_1
MDN220
MTI220
NPL220
OHK220
OKI220
OTA220
OTC220
PEN220
PPI_220
RDF220
RPO220
SFD220
SPLC220
SVL220
SWN220
TAK220-1
TKU220-1
TMN220
TNG220
TRK220
TWH220
WHI220
WIL220
WKM220
WPA220
WRK220
WTU220-1

faulted bus

Figure 1-1 - wind power tripped by bus, North Island under high wind conditions

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

13

1 Executive Summary

Figure 1-2 shows the same chart as Figure 1-1 with the total wind generation at 25% of installed wind generation
capacity. The key change is that the total quantity of tripped wind generation has been significantly reduced in
comparison with the same faults in the 100% wind generation scenario. The reduction is caused for two reasons.
Firstly, there is less total wind generation in the system and therefore the maximum amount to trip is
correspondingly less. Secondly, because there is less wind generation, there is more other generation and the
short circuit power or system strength is increased across the system, resulting in less widespread voltage
depressions following a fault.

600

wind power tripped (MW)

500
400
HL
LL

300
200
100

ALB220
ARA220
ATI220
BPE220
BRB220
BRK220
EDG220
GLN220
HAM220
HAY220
HEN220
HLY220
HPI_220_1
KAW220
LTN_220_1
MDN220
MTI220
NPL220
OHK220
OKI220
OTA220
OTC220
PEN220
PPI_220
RDF220
RPO220
SFD220
SPLC220
SVL220
SWN220
TAK220-1
TKU220-1
TMN220
TNG220
TRK220
TWH220
WHI220
WIL220
WKM220
WPA220
WRK220
WTU220-1

faulted bus

Figure 1-2 - wind power tripped by bus, North Island, low wind conditions

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

14

1 Executive Summary

The example shown in Figure 1-3 demonstrates that as the wind generation % increases from 0-100% of
installed wind generation capacity, the amount of wind generation to trip after a fault rises approximately
proportionately. In this example, only the five 220 kV bus faults with the largest wind generation trip are shown.
At 25% of the installed capacity of 1600 MW, the total wind generation to trip will exceed the usual North Island
spinning reserve of 350 MW in three of the five fault cases. At a wind generation output of 100% of installed
wind generation capacity all five of these example faults cause greater than 350 MW of wind generation to trip.
The reason for the slight non-linearity is because of the displacement of other generation, which provides a
contribution to the short circuit level, by wind generation that does not. Here, the large difference between the
75% and 100% cases for the HLY220 and ATI220 faults is caused by some large generation relatively near to the
two faults being displaced by wind generation.

1800
1600

wind power tripped (MW)

1400
faulted bus

1200

MTI220
WKM220
TKU220-1
HLY220
ATI220

1000
800
600
400
200
0
0

25

50

75

100

wind generation %

Figure 1-3 wind power tripped by wind generation level, North Island high load

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

15

1 Executive Summary

1.6.3 South Island Power System Key Results


In Figure 1-4 the observed wind generation trip for each 220 kV bus fault in the South Island system is shown.
This is for 100% of wind generation capacity with the normal spinning reserve of 120 MW highlighted by the
horizontal red line. High load cases are shown in light blue and light load cases in deep red.
Two key points to note are:

For all but five locations, a fault in a light load scenario causes over 700 MW of wind generation to trip,
this significantly exceeds the normal South Island spinning reserve of 120 MW.

As for the North Island system, a fault in the light load scenario causes more lost generation than the
high load scenario. Despite this, in all but two of the high load cases the amount of wind generation
tripped is greater than 300 MW, still about three times larger than the normal South Island spinning
reserve.
800

wind power tripped (MW)

700
600
500
HL
LL

400
300
200
100

ASB
AVI_220
BEN_220
BRY_220
CML_220A
CUT220-2
CYD_220
HWB_220
INV_220
ISL_220
KIK_220
LIV_220
MAN_220
NMA_220
NSY_220
OHA_220
OHB_220
OHC_220
Opihi_1
ROX_220
SDN_220
STK_220
TIM_220A
TIM_220B
TKB_220
TMH_220
TWI_220
TWZ_220
WTK_220
WTT220-2
WTT220-3

faulted bus

Figure 1-4 - wind power tripped by bus, South Island, high wind conditions

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

16

1 Executive Summary

Figure 1-5 shows the corresponding chart with the wind generation at 25% of installed wind generation capacity.
Despite the reduced wind generation, the amount of tripped wind generation still exceeds the normal spinning
reserve for a significant majority of the light load cases and several of the high load cases.

250

wind power tripped (MW)

200

150
HL
LL
100

50

ASB
AVI_220
BEN_220
BRY_220
CML_220A
CUT220-2
CYD_220
HWB_220
INV_220
ISL_220
KIK_220
LIV_220
MAN_220
NMA_220
NSY_220
OHA_220
OHB_220
OHC_220
Opihi_1
ROX_220
SDN_220
STK_220
TIM_220A
TIM_220B
TKB_220
TMH_220
TWI_220
TWZ_220
WTK_220
WTT220-2
WTT220-3

faulted bus

Figure 1-5 - wind power tripped by bus, South Island wind generation: 25% of installed wind
capacity

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

17

1 Executive Summary

As for the North Island cases, Figure 1-6 shows that the amount of wind generation that trips in the South Island
increases approximately proportionately as wind generation output increases from 0-100% of installed wind
generation capacity. Again, only the five 220 kV bus faults with the largest wind generation trip are shown.
Max of wind power lost (MW)

faulted bus (name)

Wind generation (in % of


installed wind power capacity)

TWZ_220

CML_220A

CYD_220

ROX_220

HWB_220

0%

58.7

58.7

58.7

58.7

25%

88.7

210.3

210.3

210.3

134.5

50%

177.5

362

362

362

210.3

75%

261.3

507

507

507

282.9

100%

708.7

658.7

658.7

658.7

358.7

Table 1-5 - wind power tripped by wind generation level, South Island high load

800
700

wind power tripped (MW)

600
Faulted Bus
500

TWZ_220
CML_220A
CYD_220
ROX_220
HWB_220

400
300
200
100
0
0

25

50

75

100

wind generation %

Figure 1-6 - wind power tripped by wind generation level, South Island high load

1.6.4 System Impact from Medium Voltage Faults (110 kV)


For the initial part of the study, the voltage sag analysis was limited to faults on the 220 kV system, as usually HV
faults will cause the most widespread voltage depression and hence the most tripped wind generation. However,

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

18

1 Executive Summary

a sensitivity analysis was performed to look at faults in the medium voltage (110 kV) system to see if faults here
could also cause large amounts of wind generation to trip.
Figure 1-7 shows the wind power tripped by bus fault for the 30 worst 110 kV system faults for the high wind
scenario (100% wind generation). Although the impact is not as severe as for 220 kV faults, the majority of these
faults still cause wind power tripping greater than the normal spinning reserve of 350 MW.
Therefore, it is true in general that 220 kV system faults will cause the most wind generation to trip. However,
there are still many 110 kV faults that will cause more than 350 MW of wind generation to trip.

1800

wind power tripped (MW)

1600
1400
1200
1000

HL
LL

800
600
400
200

BPE110
HAY110
TKR110
UHT110
WIL110
CPK110
GFD110
KWA_110_1
MLG110
NPL110
PNI110
SFD110
TAP-110
WDV110
HEN110
HEP110
LST110
OTA110
PAK110
PEN110
WIR110
CST110
MTN_110_1
ALB110
MNG110
ROS110
MDN110
WRU-110-1
GYT110-1
MST110

faulted bus

Figure 1-7 - wind power tripped by bus, North Island 100% wind power generation (110 kV)

1.7 Options to reduce wind farm tripping


The most effective method to reduce the tripped wind generation after a high voltage fault is to enforce FRT
capability for all connected wind farms. Then, wind farms will be able to remain connected to the grid for more
severe faults and keep the affected area of the fault small.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

19

1 Executive Summary

In this context, it is interesting to analyzed if full FRT capability, meaning that the wind farm can ride through
faults with a remaining voltage of 0p.u., is required or if it would be sufficient to ask wind generators to remain
connected for voltages above a certain minimum threshold voltage.
The results of a rough assessment about the minimum required trip voltage are depicted in Figure 1-8. In this
example the amount of tripped wind generation in case of a fault at the Whakamaru 220 kV bus (identified in
section 1.6.2 as one of the worst case faults in the North Island system) with different wind farm trip voltages is
shown. From this figure it can be derived that a trip voltage of 0.2 p.u would be required for ensuring that the
amount of lost wind generation does not exceed the normal North Island spinning reserve of 350MW.

1800
1600

wind power tripped (MW)

1400
1200
1000

HL
LL

800
600
400
200
0
0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

trip voltage (p.u)

Figure 1-8 wind power tripped for a fault at WKM220 bus, North Island wind generation: 100% of
installed wind generation capacity

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

20

2 Dynamic Wind Impact Studies

2 Dynamic Wind Impact Studies


Following the voltage sag screening, dynamic studies have been carried out with the purpose of:

Verifying the amount of tripped wind generation obtained by steady state voltage sag screening.

Analyzing the consequences of tripped wind generation.

2.1 Study Assumptions


The dynamic studies follow on from the voltage sag screening. From the voltage sag assessment 30 critical cases
were identified for in-depth dynamic simulation, 20 from the North Island and 10 from the South Island. These
are shown in Table 2-1.

Case

Faulted bus

Region

Load case

Wind %

S_001

WKM220

Edgecume

High Load

100

S_002

HLY220

Hamilton

High Load

100

S_003

BPE220

Bunnythorpe

High Load

100

S_004

HAY220

Wellington

High Load

100

S_005

SFD220

Taranaki

High Load

100

S_006

ALB220

North Isthmus

High Load

100

S_007

OTA220

Auckland

High Load

100

S_008

RDF220

Hawkes Bay

High Load

100

S_009

HLY220

Hamilton

Light Load

100

S_010

OTA220

Auckland

Light Load

100

S_011

WKM220

Edgecume

Light Load

100

S_012

WIL220

Wellington

Light Load

100

S_013

OTA220

Auckland

High Load

75

S_014

BPE220

Bunnythorpe

High Load

75

S_015

OTA220

Auckland

Light Load

50

S_016

BPE220

Bunnythorpe

Light Load

50

S_017

OTA220

Auckland

High Load

25

S_018

BPE220

Bunnythorpe

High Load

25

S_019

OTA220

Auckland

Light Load

S_020

BPE220

Bunnythorpe

Light Load

S_021

KIK220

Nelson

High Load

100

S_022

ISL220

Christchurch

High Load

100

S_023

TIM220A

Canterbury

High Load

100

S_024

TWZ220

Otago

High Load

100

S_025

ROX220

Southland

High Load

100

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

21

2 Dynamic Wind Impact Studies

S_026

TWZ220

Otago

Light Load

S_027

TWZ220

Otago

High Load

100
75

S_028

TWZ220

Otago

Light Load

50

S_029

TWZ220

Otago

High Load

25

S_030

TWZ220

Otago

Light Load

Table 2-1 Critical Cases for Dynamic Simulation


For more detail on the methodology for the development of the generation scenarios and modelling of the wind
generator plant please refer to the modelling report [1].

2.1.1 Wind-farms
Besides the three existing wind-farms Te Apiti, Tararua and White Hill, nine new wind-farms are modelled in the
North and South Island power systems.
It was assumed that least cost turbines will be used, which corresponds to fixed speed asynchronous generator
wind turbines with no FRT capability and no fast acting reactive power compensation.
The wind-farms are shown in the tables below.
Wind-farm

PCC (bus)

Units

Total Capacity (MW)

Marsden

MDN220

91

150

Otahuhu

OTA220

182

300

Huntly

HLY220

61

100

Hawkes Bay

RDF220

182

300

Manawatu

BPE220

182

300

Wilton

WIL220

182

300

Te Apiti

WDV110

55

90.2

Tararua

BPE33

96

63.36

1031

1603.56

Total

Table 2-2 - North Island Wind-farms

Wind-farm

PCC (bus)

Units

Total Capacity (MW)

Blenheim

BLN110

31

50

Timaru

TIM220

182

300

Invercargill

INV220

182

300

White Hill

NMA33

36

58.68

431

708.68

Total

Table 2-3 - South Island Wind-farms

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

22

2 Dynamic Wind Impact Studies

2.2 Dynamic Simulation of the NZ System


2.2.1 Dynamic Study Methodology
The methodology for the dynamic simulations is as follows:
Assumptions for wind generators:

Each wind generator is modelled by a generic fixed speed asynchronous machine with no FRT capability
and no fast acting reactive power compensation.

Every wind generator is equipped with an under-voltage relay with a setting of 0.8 p.u and a delay of
50 ms. This relay is located on the LV side of the wind generator unit transformer. This assumption
corresponds to typical under-voltage protection settings used in low cost wind turbines.

Aggregated models have been used for every wind-farm.

Assumptions for the power system:

Synchronous generator plants AVR and governor systems are as per the data provided in the
DIgSILENT cases by Transpower.

Several of the smaller units are without any control systems, AVR or governor as these were not
implemented in the model provided by Transpower. Therefore, they have constant excitation voltage
and constant turbine power.

Power system loads were represented by a constant current characteristic for the active part and
constant impedance characteristic for the reactive part.

The HVDC link was modelled as a constant current source/load for both active and reactive power.

Dynamic Simulation Methodology:

For each of the 30 critical cases perform a 5 second dynamic simulation with a 0 Ohm three phase fault
for 120 ms at the specified bus.

Record important variables such as total wind power, total synchronous generator power, key line flows,
bus voltages etc.

Repeat for each scenario.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

23

2 Dynamic Wind Impact Studies

2.3 Summary of Dynamic results for the North Island


2.3.1 Wind Generation Tripping
The loss of wind generation predicted in many fault cases by the static analysis is also observed in the dynamic
analysis.
Figure 2-1 shows a comparison of the predicted wind generation trip (steady state voltage sag screening) to the
wind generation trip observed with dynamic analysis for the North Island system. For the majority of the cases,
the estimate for the amount of wind generation to trip obtained by static analysis is confirmed by the dynamic
simulations.

1800

Wind Power Tripped (MW)

1600
1400
1200
1000
800
600
400
200

S_
00
1
S_
00
2
S_
00
3
S_
00
4
S_
00
5
S_
00
6
S_
00
7
S_
00
8
S_
00
9
S_
01
0
S_
01
1
S_
01
2
S_
01
3
S_
01
4
S_
01
5
S_
01
6
S_
01
7
S_
01
8
S_
01
9
S_
02
0

Case
Static analysis wind power tripped

Dynamic simulation wind power tripped

Figure 2-1 Static and dynamic analysis comparison, wind power tripped, North Island

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

24

2 Dynamic Wind Impact Studies

2.3.2 Electrical frequency at Huntly


The main consequence of the disconnection of large amounts of wind generation is large frequency drops.
According to part C of the New Zealand Electricity Governance Rules [2], the following automatic under frequency
load shedding (AUFLS) exists for the North Island:

Block 1, frequency <= 47.8 Hz within 0.4s

Block 2, frequency <= 47.5 Hz within 0.4s, or frequency <= 47.8 Hz for 15s

Each block is required to provide at least 16% of the total system load for automatic shedding giving a minimum
load shed of 32% if both block one and block two are activated.
Table 2-4 shows the dynamic simulation results and if the block one AUFLS trigger point is reached during the 5
second simulation.

Case

Faulted bus

Wind

Wind power

AUFLS block

Region

Load case

tripped in MW

one triggered
YES

S_001

WKM220

Edgecume

High Load

100

1513.36

S_002

HLY220

Hamilton

High Load

100

613.36

NO

S_003

BPE220

Bunnythorpe

High Load

100

753.56

YES

S_004

HAY220

Wellington

High Load

100

753.56

YES

S_005

SFD220

Taranaki

High Load

100

753.56

YES

S_006

ALB220

North Isthmus

High Load

100

450

NO

S_007

OTA220

Auckland

High Load

100

550

NO

S_008

RDF220

Hawkes Bay

High Load

100

300

NO

S_009

HLY220

Hamilton

Light Load

100

1603.56

YES

S_010

OTA220

Auckland

Light Load

100

1603.56

YES

S_011

WKM220

Edgecume

Light Load

100

1603.56

YES

S_012

WIL220

Wellington

Light Load

100

1603.56

YES

S_013

OTA220

Auckland

High Load

75

411.67

NO

S_014

BPE220

Bunnythorpe

High Load

75

601.91

NO

S_015

OTA220

Auckland

Light Load

50

796.6

YES

S_016

BPE220

Bunnythorpe

Light Load

50

456.86

YES

S_017

OTA220

Auckland

High Load

25

138.33

NO

S_018

BPE220

Bunnythorpe

High Load

25

305.21

NO

S_019

OTA220

Auckland

Light Load

63.36

NO

S_020

BPE220

Bunnythorpe

Light Load

153.56

NO

Table 2-4 Dynamic Simulation Results


Figure 2-2 shows an example from North Island case S_016 where the frequency drop exceeds the first AUFLS
block trigger point. Following a voltage sag, around 400MW of wind generation disconnects from the system.
Consequently, frequency drops below the first AUFLS load shedding stage. Because the actual AUFLS load
shedding scheme was not modelled in these simulations, it cannot be predicted if Block 2 will trigger as well.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

25

DIgSILENT

2 Dynamic Wind Impact Studies

2000.00

1800.00

1600.00

1400.00

1200.00

1000.00

0.00

1.25

2.50

3.75

[s]

5.00

2.50

3.75

[s]

5.00

NIPS: Generation, Active Power in MW


1000.00

875.00

750.00

625.00

500.00

375.00

250.00

0.00

1.25
WindFarms: Generation, Active Power in MW

51.00

50.00

49.00

48.00

Y = 47.800 Hz
Y = 47.500 Hz

47.00

0.00

1.25

2.50

3.75

[s]

5.00

HLY-UN1: Electrical Frequency in Hz

DIGSILENT

Transpower Wind Impact Study


3 phase fault at bus BPE220, cleared after 120ms

Pgen_sum

S_016_Light Load Wind Penetration 50%

Date: 9/28/2006
Annex: 16 /4

Figure 2-2 - Case S_016, example of excessive frequency drop due to tripped wind generation

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

26

2 Dynamic Wind Impact Studies

2.3.3 Short term voltage instability, North Island


Besides frequency collapse, the sudden disconnection of large amounts of wind generators can cause high branch
flows exceeding the voltage stability limit and finally leading to voltage collapse.
In the light load, high wind cases S_009-S_012 and S_015, short term voltage instability was observed. In case
S_015 this could probably be avoided by load shedding. However, in the other four cases the voltage collapse
occurs almost immediately after the tripping of the wind generation the load shedding would not operate in
time and a system collapse is inevitable.
Figure 2-3 shows an example from simulation S_012. This case shows how the initial voltage collapse initiates the
subsequent trip of more and more wind generators and finally drives the system into a complete collapse. Load
shedding would be initiated too late.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

27

DIgSILENT

2 Dynamic Wind Impact Studies

2400.00

2000.00

1600.00

1200.00

800.00

400.00

0.00

1.25

2.50

3.75

[s]

5.00

2.50

3.75

[s]

5.00

NIPS: Generation, Active Power in MW


2000.00

1600.00

1200.00

800.00

400.00

0.00

-400.00

0.00

1.25
WindFarms: Generation, Active Power in MW

60.00

50.00

47.800 Hz
Y = 47.500

40.00

30.00

20.00

10.00

0.00

1.25

2.50

3.75

[s]

5.00

HLY-UN1: Electrical Frequency in Hz

DIGSILENT

Transpower Wind Impact Study


3 phase fault at bus WIL220, cleared after 120ms

Pgen_sum

S_012_Light Load Wind Penetration 100%

Date: 9/28/2006
Annex: 12 /4

Figure 2-3 - Simulation S_012, example short term voltage instability

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

28

DIgSILENT

2 Dynamic Wind Impact Studies

1.10

1.00

0.90

Y = 0.800 p.u.

0.80

0.70

0.60

0.00

1.25

2.50

3.75

[s]

5.00

WGbus: Voltage, Magnitude in p.u.


WF2_G1: Voltage, Magnitude in p.u.
WF3_G3: Voltage, Magnitude in p.u.
WF4_G1: Voltage, Magnitude in p.u.
WF5_G1: Voltage, Magnitude in p.u.
TAPG(1): Voltage, Magnitude in p.u.
WF6_G1: Voltage, Magnitude in p.u.
TWF terminal: Voltage, Magnitude in p.u.

DIGSILENT

Transpower Wind Impact Study


3 phase fault at bus WIL220, cleared after 120ms

WG_voltage

S_012_Light Load Wind Penetration 100%

Date: 9/28/2006
Annex: 12 /2

Figure 2-4 - Simulation S_012, example short term voltage instability

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

29

2 Dynamic Wind Impact Studies

2.3.4 Interconnecting line flows, North Island


In cases, where power is imported into areas with high amounts of wind generation, there is a high risk of either
long term voltage collapse or thermal overload problems of interconnecting circuits. For a detailed analysis, PVcurve analysis based on subsequent load flow calculations or long-term simulations would have to be carried out
considering the post-contingency network state (considering the tripped wind generators).

2.4 Summary of dynamic results for the South Island


2.4.1 Sudden Loss of Wind Generation
The loss of wind generation predicted in many fault cases by the static analysis is also observed in the dynamic
analysis.
Figure 2-5 shows a comparison of the predicted wind generation trip (steady state voltage sag screening) to the
observed wind generation trip (dynamic analysis) for the South Island system. With the exception of cases S_024
and S_025, the dynamic analysis confirms exactly the results of the static estimate.

800

Wind Generation Tripped (MW)

700
600
500
400
300
200
100
0
S_021

S_022

S_023

S_024

S_025

S_026

S_027

S_028

S_029

S_030

Case
Static analysis wind power tripped

Dynamic simulation wind power tripped

Figure 2-5 - Static and dynamic analysis comparison, wind power tripped, South Island

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

30

2 Dynamic Wind Impact Studies

2.4.2 Electrical frequency at Clyde


In many of the simulations large frequency drops were observed due to the disconnection of large amounts of
wind generation. According to part C of the New Zealand Electricity Governance Rules [2], the following
automatic under frequency load shedding (AUFLS) exists for the South Island:

Block 1, frequency <= 47.5 Hz within 0.4s

Block 2, frequency <= 45.5 Hz within 0.4s, or frequency <= 47.5 Hz for 15s

Each block is required to provide at least 16% of the total system load for automatic shedding giving a minimum
load shed of 32% if both block one and block two are activated.
Table 2-5 shows the results from the dynamic simulations and whether AUFLS was triggered. Triggering of AUFLS
is observed less in the South Island than the North Island mainly because the ratio of wind generation to other
other generation is smaller - there is less wind generation relative to other types of generation.
Wind power

AUFLS block

Load case

Wind %

tripped

one triggered

Nelson

High Load

100

50.01

NO

Christchurch

High Load

100

350.01

NO

Canterbury

High Load

100

350.01

NO

TWZ220

Otago

High Load

100

350.01

NO

ROX220

Southland

High Load

100

358.68

NO

S_026

TWZ220

Otago

Light Load

100

708.69

YES

S_027

TWZ220

Otago

High Load

75

261.28

NO

S_028

TWZ220

Otago

Light Load

50

387.79

YES

Case

Faulted bus

S_021

KIK220

S_022

ISL220

S_023

TIM220A

S_024
S_025

Region

S_029

TWZ220

Otago

High Load

25

88.73

NO

S_030

TWZ220

Otago

Light Load

58.68

NO

Table 2-5 Dynamic Simulation Results, South Island


Figure 2-6 shows an example from a South Island case where the frequency drop will trigger AUFLS block one. As
mentioned in the North Island example, once this trigger point is reached any further results are meaningless
because AUFLS is not implemented in the model.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

31

DIgSILENT

2 Dynamic Wind Impact Studies

1400.00

1200.00

1000.00

800.00

600.00

400.00

200.00

0.00

1.25

2.50

3.75

[s]

5.00

2.50

3.75

[s]

5.00

SIPS: Generation, Active Power in MW


500.00

400.00

300.00

200.00

100.00

0.00

-100.00

0.00

1.25
Windfarms: Generation, Active Power in MW

52.00

50.00

48.00

Y = 47.500 Hz

1.472 s

46.00

Y = 45.500 Hz

44.00

42.00

0.00

1.25

2.50

3.75

[s]

5.00

CYD_G1: Electrical Frequency in Hz

DIGSILENT

Transpower Wind Impact Study


3 phase fault at bus TWZ_220, cleared after 120ms

PGen_sum

S_028_Light Load Wind Penetration 50%

Date: 9/28/2006
Annex: 28 /4

Figure 2-6 - Case S_028, example of excessive frequency drop due to tripped wind generation

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

32

2 Dynamic Wind Impact Studies

2.4.3 Short term voltage instability, South Island


In the light load, high wind case S_026, a short term voltage instability was observed. This occurs almost
immediately after the tripping of the wind generation the load shedding blocks at 47.5 Hz and 45.5 Hz would
not operate in time and a system collapse is inevitable.
A voltage instability was also observed in simulation S_028 after 2 seconds simulation time. However, the first
load shedding block would have activated before this and probably prevented it from occurring.
Figure 2-3 shows an example from simulation S_026, in which the system loses synchronism immediately after
the disconnection of large amounts of wind generation.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

33

DIgSILENT

2 Dynamic Wind Impact Studies

1.10

1.00

0.90

0.80

0.70

0.60

0.00

1.25

2.50

3.75

[s]

5.00

PCC_BLN_WF: Voltage, Magnitude in p.u.


PCC_INV_WF: Voltage, Magnitude in p.u.
NMA_PCC: Voltage, Magnitude in p.u.
PCC_TIM_WF: Voltage, Magnitude in p.u.

DIGSILENT

Transpower Wind Impact Study


3 phase fault at bus TWZ_220, cleared after 120ms

PCC_Voltage

S_026_Light Load Wind Penetration 100%

Date: 9/28/2006
Annex: 26 /1

Figure 2-7 - Simulation S_026, example short term voltage instability

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

34

2 Dynamic Wind Impact Studies

2.4.4 Interconnecting line flows South Island


As for the North Island simulations, thermal overload problems can potentially occur during times in which power
is imported into areas with high amount of wind generation. Following the sudden loss of wind generation, the
power flow into this area is increased, leading either to voltage stability problems or thermal overloads of the
interconnecting circuits.
A detailed analysis either based on long-term simulations or on PV-curve analysis was beyond the scope of this
study.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

35

3 Concluding Remarks and Recommendations

3 Concluding Remarks and Recommendations


For analyzing the impact of increased levels of wind generation in New Zealand, detailed system impact studies
have been carried out.
In this first stage of the project, it has been assumed that least cost wind generators without fault ride-through
capability are used for all wind farms in New Zealand.
As a first step, the potential risk of widespread tripping of wind generation following single contingent events has
been assessed using steady state voltage sag screening. In a second step, the most critical cases have been
simulated dynamically to confirm the results of the voltage sag screening and to analyze the consequences of
widespread tripping of wind generation.
The voltage sag screening has shown that many single contingent events, such as faults on single transmission
circuits can lead to widespread tripping of wind generation if wind generators do not have the ability to ride
through voltage sags.
Dynamic simulations show that widespread tripping of wind generation can drive the system into frequency
stability problems causing load shedding or dynamic voltage stability problems.
However, increasing spinning reserve and system inertia requires that almost all wind generators are backed up
by non-wind generators, which leads to enormous additional spinning reserve. Besides this, the network must be
able to transport any additionally required reserve power. In this study, a number of cases were identified, where
the available transport capacity is not sufficient and consequently, the network runs into dynamic voltage
collapse. For avoiding this, network reinforcements would be required or inter-area power transfer must be
limited.
The second option, only allowing wind generators with FRT-capability, is fairly easy to realize because this kind of
wind generator is standard technology. Consequently, for avoiding drastically reduced reliability of supply in the
New Zealand power system there is only one practical solution:

Only allowing the connection of wind generators with FRT-capability.

This has become an international standard for power transmission systems with high wind penetration, e.g. in
Germany, Denmark, U.K. or Australia.
When connecting wind generators with FRT capability, additional reserve power is only required for backing up
wind fluctuations but not for backing up wind generator trips.

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

36

4 References

4 References
[1] Assessment of Potential Security Risks due to High Levels of Wind Generation in New Zealand - Stage 1,
Modelling Report.
[2] Electricity Governance Rules, Part C, Common Quality 8 June 2006

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

37

ANNEXES
Annexes

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

38

Annex A-1: Results of Voltage Sag Screening

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

39

Max of wind power lost (MW)

Wind Generation (in % of installed wind generation capacity)

faulted bus (name)

0%

25%

50%

75%

100%

ALB220

138.3

278.3

411.7

550

ARA220

75.8

151.6

224.2

663.4

ATI220

75.8

151.6

224.2

963.4

BPE220

153.6

305.2

456.9

601.9

753.6

BRB220

113.7

227.5

336.3

450

BRK220

153.6

305.2

456.9

601.9

753.6

EDG220

75.8

151.6

224.2

300

GLN220

138.3

278.3

411.7

550

HAM220

100.4

278.3

411.7

550

HAY220

153.6

305.2

456.9

601.9

753.6

HEN220

138.3

278.3

411.7

550

HLY220

138.3

278.3

411.7

1003.6

HPI_220_1

138.3

278.3

411.7

550

KAW220
LTN_220_1

300

153.6

305.2

456.9

601.9

753.6

113.7

227.5

336.3

450

MTI220

153.6

418.9

735.1

1013.6

1603.6

NPL220

153.6

305.2

456.9

601.9

753.6

OHK220

75.8

151.6

224.2

300

OKI220

75.8

151.6

224.2

300

OTA220

138.3

278.3

411.7

550

OTC220

138.3

278.3

411.7

550

PEN220

138.3

278.3

411.7

550

PPI_220

75.8

151.6

224.2

663.4

RDF220

75.8

151.6

224.2

300

RPO220

75.8

151.6

224.2

663.4

SFD220

153.6

305.2

456.9

601.9

753.6

SPLC220

153.6

305.2

456.9

601.9

753.6

SVL220

113.7

227.5

336.3

450

SWN220

138.3

278.3

411.7

550

TAK220-1

138.3

278.3

411.7

550

TKU220-1

1053.6

MDN220

153.6

381

608.5

826.1

TMN220

TNG220

153.6

229.4

305.2

377.7

753.6

TRK220

75.8

151.6

224.2

300

TWH220

24.6

202.5

299.6

400

WHI220

75.8

151.6

224.2

300

WIL220

153.6

305.2

456.9

601.9

753.6

WKM220

153.6

519.4

886.8

1237.8

1603.6

WPA220

75.8

151.6

224.2

600

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

40

WRK220

75.8

366.7

511.7

753.6

WTU220-1

75.8

151.6

224.2

300

Table 4-1 - Voltage Sag Results, North Island High Load


Max of wind power lost (MW)

Wind Generation (in % of installed wind generation capacity)

faulted bus (name)

0%

25%

50%

75%

100%

ALB220

63.4

443.5

886.8

1237.8

1603.6

ARA220

153.6

481.4

886.8

1237.8

1603.6

ATI220

153.6

519.4

886.8

1237.8

1603.6

BPE220

153.6

381

659.3

1125.7

1453.6

BRB220

138.3

278.3

411.7

1303.6

BRK220

153.6

305.2

659.3

901.5

1453.6

EDG220

381

608.5

826.1

1453.6

GLN220

153.6

443.5

886.8

1237.8

1603.6

HAM220

153.6

519.4

886.8

1237.8

1603.6

HAY220

153.6

305.2

456.9

826.1

1053.6

HEN220

153.6

519.4

886.8

1237.8

1603.6

HLY220

153.6

519.4

886.8

1237.8

1603.6

HPI_220_1

153.6

443.5

886.8

1237.8

1603.6

290.8

608.5

826.1

1453.6

153.6

305.2

608.5

826.1

1453.6

KAW220
LTN_220_1

138.3

278.3

411.7

1603.6

MTI220

153.6

519.4

886.8

1237.8

1603.6

NPL220

153.6

305.2

456.9

901.5

1153.6

OHK220

153.6

519.4

886.8

1237.8

1603.6

OKI220

153.6

381

811

1237.8

1603.6

OTA220

153.6

519.4

886.8

1237.8

1603.6

OTC220

153.6

519.4

886.8

1237.8

1603.6

PEN220

153.6

519.4

886.8

1237.8

1603.6

PPI_220

153.6

519.4

886.8

1237.8

1603.6

RDF220

75.8

608.5

826.1

1053.6

RPO220

153.6

381

608.5

826.1

1053.6

SFD220

153.6

329.8

507.7

901.5

1453.6

SPLC220

153.6

329.8

507.7

901.5

1453.6

MDN220

138.3

735.1

1237.8

1603.6

SWN220

153.6

519.4

886.8

1237.8

1603.6

TAK220-1

153.6

519.4

886.8

1237.8

1603.6

TKU220-1

153.6

481.4

811

1237.8

1603.6

TMN220

153.6

305.2

456.9

677.3

853.6

TNG220

153.6

381

608.5

826.1

1053.6

TRK220

153.6

381

811

1237.8

1603.6

TWH220

153.6

443.5

886.8

1237.8

1603.6

SVL220

WHI220

75.8

608.5

826.1

1053.6

WIL220

153.6

305.2

456.9

826.1

1053.6

WKM220

153.6

519.4

886.8

1237.8

1603.6

WPA220

153.6

519.4

886.8

1237.8

1603.6

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

41

WRK220
WTU220-1

153.6

519.4

886.8

1237.8

1603.6

75.8

518.3

826.1

1053.6

Table 4-2 - Voltage Sag Results, North Island Light Load


Max of wind power lost (MW)

Wind Generation (in % of installed wind generation capacity)

faulted bus (name)

0%

25%

50%

75%

100%

ASB

88.7

177.5

261.3

350

AVI_220

88.7

177.5

261.3

350

BEN_220

88.7

177.5

261.3

350

BRY_220

88.7

177.5

261.3

350
658.7

CML_220A

58.7

210.3

362

507

CUT220-2

88.7

177.5

261.3

350

CYD_220

58.7

210.3

362

507

658.7

HWB_220

58.7

134.5

210.3

282.9

358.7

INV_220

58.7

134.5

210.3

282.9

358.7

ISL_220

88.7

177.5

261.3

350

KIK_220

12.9

25.8

37.1

50

LIV_220

88.7

177.5

261.3

350

MAN_220

58.7

134.5

210.3

282.9

358.7

NMA_220

58.7

134.5

210.3

282.9

358.7

NSY_220

OHA_220

88.7

177.5

261.3

350

OHB_220

88.7

177.5

261.3

350
350

OHC_220

88.7

177.5

261.3

Opihi_1

88.7

177.5

261.3

350

ROX_220

58.7

210.3

362

507

658.7

SDN_220

58.7

134.5

210.3

282.9

358.7

STK_220

12.9

25.8

37.1

50

TIM_220A

88.7

177.5

261.3

350

TIM_220B

88.7

177.5

261.3

350

TKB_220

88.7

177.5

261.3

350

TMH_220

58.7

134.5

210.3

282.9

358.7

TWI_220

58.7

134.5

210.3

282.9

358.7

TWZ_220

88.7

177.5

261.3

708.7

WTK_220

88.7

177.5

261.3

350

WTT220-2

88.7

177.5

261.3

350

WTT220-3

88.7

177.5

261.3

350

Table 4-3 - Voltage Sag Results, South Island High Load

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

42

Max of wind power lost (MW)

Wind Generation (in % of installed wind generation capacity)

faulted bus (name)

0%

25%

50%

75%

100%

ASB

223.2

387.8

544.1

708.7

AVI_220

58.7

223.2

387.8

544.1

708.7

BEN_220

58.7

223.2

387.8

544.1

708.7

BRY_220

88.7

387.8

544.1

708.7

CML_220A

58.7

223.2

387.8

544.1

708.7

CUT220-2

88.7

177.5

261.3

350

CYD_220

58.7

223.2

387.8

544.1

708.7

HWB_220

58.7

223.2

387.8

544.1

708.7

INV_220

58.7

223.2

387.8

544.1

708.7

ISL_220

223.2

387.8

544.1

708.7

KIK_220

88.7

177.5

261.3

350

LIV_220

58.7

223.2

387.8

544.1

708.7

MAN_220

58.7

223.2

387.8

544.1

708.7

NMA_220

58.7

223.2

387.8

544.1

708.7

NSY_220

58.7

223.2

387.8

544.1

708.7

OHA_220

58.7

223.2

387.8

544.1

708.7

OHB_220

58.7

223.2

387.8

544.1

708.7

OHC_220

58.7

223.2

387.8

544.1

708.7

Opihi_1

223.2

387.8

544.1

708.7

ROX_220

58.7

223.2

387.8

544.1

708.7

SDN_220

58.7

223.2

387.8

544.1

708.7

STK_220

88.7

177.5

261.3

350

TIM_220A

88.7

177.5

544.1

708.7

TIM_220B

88.7

177.5

544.1

708.7

TKB_220

58.7

223.2

387.8

544.1

708.7

TMH_220

58.7

223.2

387.8

544.1

708.7

TWI_220

58.7

223.2

387.8

544.1

708.7

TWZ_220

58.7

223.2

387.8

544.1

708.7

WTK_220

58.7

223.2

387.8

544.1

708.7

WTT220-2

88.7

177.5

261.3

350

WTT220-3

88.7

177.5

261.3

350

Table 4-4 - Voltage Sag Results, South Island Light Load

New Zealand Electricity Commission - Wind Generation Investigation Project

- Stage 1

43

Вам также может понравиться