Вы находитесь на странице: 1из 94

Project Dwg. No: G101-25-1700.

01-MM56

Turbine Main Oil Pump


MECHANICAL MAINTENANCE MANUAL
PT PAITON ENERGY
PAITON EXPANSION PROJECT

Turbine Main Oil Pump Maintenance


Manual No. MM-M05.06
Revision 001

Note
This mechanical maintenance manual is intended to provide the Paiton Expansion Project
mechanical maintenance personnel with the basic understanding required to perform preventive,
routine, corrective and overhaul maintenance activities on the subject equipment.

No part of this document may be reproduced for use by parties other than Mitsubishi Heavy
Industries, Ltd. and Paiton Expansion Project.

Turbine Main
Oil Pump
Maintenance

Be sure to read this manual.


Contents
Safety

General

Specifications

Preventive Maintenance

Disassembly and Reassembly

Corrective Maintenance

Recommended Lubrication

Appendixes

Contents

Contents
Revision Record i
Important Informationii
Warranty v
Limitation of Liabilityvii
Copyrightix
Personnel to whom the Manual is Directed x
Contact Addressxi
Abbreviations xii
List of Vendor Manuals xiii
Arrangement of the System Maintenance Manualxiv

Chapter1

Safety ____________________________

1.1

Feature of Turbine Main Oil Pump Safety 1-1

1.2

Warnings Description 1-2


1.2.1

Definitions of Serious Injury, Minor Injury, Serious


Damage to Property, and Minor Damage to Property 1-3

1.2.2

Symbol 1-4

1.2.3

Hazard Warning Label 1-5

1.2.4

Hazard Area 1-7

1.3

Risk Assessment Standard 1-8

1.4

Safety Measures 1-10


1.4.1

Work Permit System (Lockout/Tagout) 1-10

1.4.2

General Cautions on Personnel in Working Area 1-11

1.4.2.1 Caution against Rotating Equipment 1-11


1.4.2.2 Cautions against High Voltage Section 1-11
1.4.2.3 Cautions against High Temperature Sections 1-12
1.4.2.4 Cautions for Steam Leak in the Plant 1-13
1.4.2.5 Cautions against Oil Leak in the Plant 1-13
1.4.2.6 Cautions against Chemicals 1-14
1.4.2.7 Cautions against Combustible Materials/Storage Areas 1-14
Rev.001

1.4.2.8 Cautions against Lack of Oxygen 1-15


1.4.2.9 Cautions against Lifting Heavy Object 1-16
1.4.2.10 Caution against Sharp Objects 1-16

MM-M05.06

1.4.2.11 Cautions using Fork Lift 1-16


1.4.2.12 Cautions using Crane 1-17
Turbine Main Oil Pump
Mitsubishi

Contents

Chapter1

Safety (Continued from previous page)


1.4.2.13 Disposal 1-18

1.5

Emergency Measure 1-19


1.5.1

Evacuation on Emergency Case 1-19

1.5.1.1 Evacuation Route 1-19


1.5.1.2 Evacuation of disabled persons who cannot move by
themselves 1-19
1.5.1.3 Evacuation from Power House 1-20
Fire Accident 1-21

1.5.3

Earthquake 1-22

1.5.4

Explosion Accident 1-22

1.6

Qualification and Training 1-23

Chapter2

General ___________________________

2.1

Purpose 2-1

2.2

References 2-1

2.3

Overview of the Turbine Main Oil Pump 2-2

2.4

Construction 2-6
2.4.1

Pump Casing 2-6

2.4.2

Impeller and Shaft Assembly 2-7

2.4.3

Impeller Seal Rings 2-8

2.4.4

Shaft Penetration Seal Rings 2-8

Chapter3

Specifications _____________________

Chapter4

Preventive Maintenance _____________

4.1

Prerequisites 4-1

4.2

4.3

MM-M05.06

Rev.001

1.5.2

Turbine Main Oil Pump


Mitsubishi

4.1.1

Scheduling 4-1

4.1.2

Departmental Interface/Notification 4-2

4.1.3

Isolation of Equipment 4-2

4.1.4

Safety Precautions 4-2

Routine Maintenance 4-3


4.2.1

Preparation 4-3

4.2.2

Inspection and Maintenance 4-4

Annual Outage Maintenance 4-7


4.3.1

Preparation 4-7

4.3.2

Inspection and Maintenance 4-8

Contents

Chapter5

Disassembly and Reassembly ________

5.1

Turbine Main Oil Pump Disassembly and Reassembly 5-1

5.2

Impeller Removal and Replacement 5-5

Chapter6

Corrective Maintenance _____________

6.1

Prerequisites 6-1

6.2

Preparation 6-2

6.3

Troubleshooting 6-2

Chapter7

Recommended Lubrication __________

Appendixes
Torque Chart A-1

Appendix B

Recommended Spare Parts B-1

Appendix C

Special Tools C-1

Appendix D

Coupling Alignment D-1

Appendix E

Applicable Vendor Drawings E-1

Appendix F

Instruction ManualF-1

MM-M05.06

Rev.001

Appendix A

Turbine Main Oil Pump


Mitsubishi

Contents

List Of Figures
Figure 1-1

Types of Hazard Warning Labels 1-6

Figure 1-2

Mapping for Hazard Areas 1-9

Figure 2-1

Main Turbine Lubricating Oil Flow Diagram 2-3

Figure 2-2

Overview and Location of Main Oil Pump 2-4

Figure 2-3

Isometric View of Turbine Main Oil Pump 2-5

Figure 2-4

Cutaway View of Turbine Main Oil Pump 2-9

Figure 2-5

Sectional View of Turbine Main Oil Pump 2-10

Figure 4-1

Turbine Main Oil Pump Clearance Drawing 4-15

Figure 5-1

Exploded View of Turbine Main Oil Pump 5-7

Figure B-1

Spare Parts for Main Oil Pump 1/2B-2

Figure B-2

Spare Parts for Main Oil Pump 2/2B-3

Figure E-1

Turbine Main Oil Pump Assembly (1/2)E-2

Figure E-2

Turbine Main Oil Pump Assembly (2/2)E-3

List Of Tables
Risk Assessment Standard 1-8

Table 3-1

Turbine Main Oil Pump 3-1

Table 4-1

Routine Maintenance Checklist 4-6

Table 4-2

Annual Outage Maintenance Checklist 4-12

Table 6-1

Troubleshooting Turbine Main Oil Pump 6-3

Table A-1

Torque Chart A-1

MM-M05.06

Rev.001

Table 1-1

Turbine Main Oil Pump


Mitsubishi

Revision Record
Page Number
General

Description of Revision
Revision record added and all
pages changed to rev. 0001

Revision Issue
Date

Date Revised

Pages
Inserted

2012/03/30

2012/03/30

DRS (drawing review sheet)


added.
Appendix F para. 7 modified.

MM-M05.06

Rev.001

F-1

Turbine Main Oil Pump


Mitsubishi

Important Information
Purpose of the Plant Usage
This plant is designed to generate electric power of 815 MW by the steam turbine
generator.
The plant is only used for the electric power generation purpose that supports stable
and reliable electric power supply to the power grid and supplying steam for auxiliary
equipment in the power station.

General
1.

To satisfy the purpose mentioned above the following points must be strictly
observed,
a)

The operation, maintenance and inspection of Equipment must be


performed by the persons who have basic technical knowledge and have
been trained concerning the hazard of the Equipment and the avoidance
of the hazard.

b)

The operators and maintainers must read and understand these manuals
before starting the operation, maintenance or inspection.
It is often experienced that serious damage to the equipment or personnel
have occurred by the unexpected action of operators or maintainers who
do not fully understand the equipment.

c)

The modification or change of operational specification must be performed


under MHI supervision or as per the written acceptances of MHI.
The modification or change of specification causes not only a decline in
performance but also a decline in safety for operation of the equipment.
The Customer is requested to contact MHI regarding any modification or
proposed changes before the work commences.

MM-M05.06

Rev.001

The address for MHI to be contacted is shown in this chapter.


2.

The operation and maintenance must be performed according to the applicable


laws and regulations at the location of the power station.

3.

Disposal from the power station must be treated to satisfy the local regulations.

Turbine Main Oil Pump


Mitsubishi

ii

4.

The copyright of software, drawings and other documents provided by MHI at


all times, is still reserved by MHI.

Use or copying of the whole or part of any information provided by MHI for
any purpose other than operation and maintenance of this plant without
written consent is strictly prohibited.

Important General Notice for Safety


1.

The operator and maintainer must have knowledge about the equipment to
maintain good operating condition and to avoid danger when using the
equipment and systems.

2.

The protection measures must satisfy all of the operational functions.

3.

The safety activity must be planned systematically as a Safety and Health


management system and operate continuously.
Safety and Health management system must include the following points,
a) Instruction for use and the maintenance of the personal protective
equipment issued to operators and maintainers
b) The establishment of a work management organization to make clear the
operation directives and work procedures
c) Implementation of training for operator and maintainer

4.

The Customer must train the operators and maintainers to act positively and
to prevent the occurrence of an accident by using their knowledge of the
power plant.

5.

The Customer must make the operators and maintainers understand that the
most important purpose of safety control is to protect all personnel from
accidents and also to maintain operation of the plant without troubles.

6.

To prevent accidents involving personnel and equipment, it is necessary to


observe the notices of this manual and to keep the correct operation
according to the description provided in this manual.

MM-M05.06

Rev.001

If the notices are not observed, the following dangers could occur to the
operator, and to the maintainer.

7.

a)

Risk of a fatal accident

b)

Danger to lose his health and fitness

c)

Danger of damage to the equipment

MHI can not forecast all possible dangers existing in the plant such as danger
due to human error and/or dangers caused by the operating environment.

Turbine Main Oil Pump


Mitsubishi

iii

As this manual and the alert label cannot cover all of the dangers, the
operators and maintainers have to pay their full attention to all general safety
notices.
8.

MHI can not be responsible for damages and injury caused by neglecting the
notices in this manual, and other necessary general notices.

Instruction of this Manual


This manual is provided for people familiar with the use of English. If some
person not familiar with English is going to operate the plant, the Customer
must train him specially.

2.

The warning labels are to be expressed in the English language.

3.

This manual contains optional matters.

4.

Some figures in this manual include internal parts of the equipment which
may not be obvious, when looking at the completed equipment drawing.

5.

MHI may change the content of this manual without notice.

6.

This manual is intended for the use by the operators and maintainers and it
must be accessible to them at all times.

7.

If the Customer needs more detailed information, please contact MHI local
office or MHIs official agent.

MM-M05.06

Rev.001

1.

Turbine Main Oil Pump


Mitsubishi

iv

Warranty

The provisions set forth in this section are in addition to all liability and warranty
disclaimers and limitations set forth in the Contract, whether arising under law
or from course of performance, course of dealing, or usage of trade.

Nothing in these provisions shall constitute or be deemed to constitute any


additional liability undertaking or warranty, express or implied, with respect to
the Plant. All capitalized terms used, but not defined in this Warranty
Limitations section shall have the respective meanings ascribed to them in the
Contract.

The Contract Warranties are subject to the construction, installation and


Customer works having been performed in full compliance with the
requirements stated in (a) the Contract, (b) all manuals provided by MHI,
including this manual, (c) all applicable rules, regulations and laws prevailing in
the location where the Plant has been installed and will operate, and (d) any
other instructions, if any, provided by MHI (collectively, Rules and
Requirements). The Contract Warranties will NOT cover any accidents, partial
or total failure of the Plant, losses or damages to personnel or property
(including, without limitation, the Plants components, parts, systems and other
equipment), or any other liability (collectively, Accidents and Damages) in the
case of any breach of the stated Rules and Requirements.

For the detailed terms and conditions of the warranty concerning the Works
and Project, refer to the Contract.

In addition to the foregoing, the Contract Warranties will NOT cover any of the
following Accidents and Damages:
Accidents and Damages caused by any deviation from the Rules and
Requirements;

MM-M05.06

Rev.001

Turbine Main Oil Pump


Mitsubishi

Accidents and Damages caused by the modification or re-installation of the


Plant after the original installation, or caused by operation of the Plant for a
purpose other than that for which it is designed;

Accidents and Damages caused by natural disasters or accidents during


transfer or related handling;

Accidents and Damages occurring after the term of the warranty has expired;

Accidents and Damages due to faulty operation or operation not in accordance


with the Rules and Requirements;

Accidents and Damages due to inappropriate maintenance or servicing


performed by the Customer, its personnel or any other party.

Accidents and Damages caused by any components, parts, systems or other


equipment other than those delivered by MHI;

Accidents and Damages caused by unidentifiable reasons including loss of the


damaged parts which is necessary to pinpoint a cause of the failure;

Accidents and Damages caused by referring to inadequate, or incorrect


references, data or information provided by the Customer;

Accidents and Damages or rust/corrosion due to inadequate handling and/or


storage by the Customer; or

Accidents and Damages due to handling, storage and/ or use of the Plant
under severe conditions or in an environment that does not meet the design
specification conditions.

MM-M05.06

Rev.001

Turbine Main Oil Pump


Mitsubishi

vi

Limitation of Liability
General

Nothing in this Limitation of Liability section or manual shall constitute or be


deemed to constitute any additional liability undertaking or warranty, express
or implied, with respect to the Plant. All capitalized terms used, but not defined
in this Limitation of Liability section shall have the respective meanings
ascribed to them in the Contract.

The contents of this manual are subject to change without prior notice and
without any obligation or liability to MHI.

Use and Disposal

Use of the Plant must be limited to the use specified by MHI, including without
limitation, use of the Plant in accordance with the Contract, this manual, all
Safety Manuals, all applicable laws and regulations, and any other instructions,
if any, provided by MHI. The Plant components, parts, systems and other
equipment (collectively, Equipment) must be appropriately disposed of in
accordance with the Contract, this manual, all Safety Manuals, all applicable
laws and regulations, and any other instructions, if any, provided by MHI.

For Documents and Safety Training

MM-M05.06

Rev.001

The Customers personnel must read, understand and abide by all documents
provided by MHI, including without limitation, the operation and maintenance
manuals, safety manuals, and instruction manuals (collectively, Safety
Manuals) and must have received all required and/or necessary safety
training prior to the start of their work. Persons who have not received such
safety training are not permitted to work on the installed Plant. This initial
training, however, is merely the minimum requirements prior to allowing any
personnel to work on the installed Plant. The Customer must, on a continual
and regular schedule, give up-to-date training to its personnel on safety
requirements, provide testing or other methods to confirm their understanding
of the safety training, and confirm that they have the physical and mental
capability to perform their respective roles. The Customers obligation for
safety training and personnel supervision is an ongoing obligation and must be
continuously performed and kept current throughout the operation of the Plant.
Accidents, partial or total failure of the Plant, damage to personnel or property,
loss, injuries, and other liability (collectively, Liability) caused by inadequate

Turbine Main Oil Pump


Mitsubishi

vii

safety training or the Customers personnels failure to abide by the documents


provided by MHI are expressly excluded from the coverage of any warranty
provided by MHI and are the sole and exclusive responsibility of the Customer.

MHI will NOT be liable for any Liability caused by modification or changes
made in Plant-related documents (including any Safety Manual) by anyone
other than MHI.

For Damage to the Plant

Accidents may occur by use of Equipment that is acquired from anyone other
than MHI or anyone not appointed by MHI to modify or repair this Plant. The
Customer shall not be permitted to modify or repair the Plant or change
Equipment of the Plant without MHIs prior written approval, under any
circumstance.

MHI will NOT be liable for any Liability resulting from any abuse, misuse,
misapplication of the Equipment supplied by MHI.

MHI will NOT be liable for any Liability caused by an act by the Customer in
violation of the Contract, this manual, any applicable law or regulation, or any
Safety Manual or any other instruction provided by MHI, including without
limitation, a change of the installation environment or the removal and
installation of any Equipment in a location different to that originally selected by
MHI.

MHI will NOT be liable for any Liability caused by a defect, imperfection, or fault,

MM-M05.06

Rev.001

in material or Equipment that was used during a repair, even when such repair
was performed by or under an instruction given by MHI.

Turbine Main Oil Pump


Mitsubishi

viii

Copyright
COPYRIGHT 2009, MITSUBISHI HEAVY INDUSTRIES, LTD. ALL RIGHTS
RESERVED. ANY REPRODUCTION IS EXPRESSLY PROHIBITED.

All of the content contained in this manual is protected by Japanese,


International and/or United States copyright laws.

All copyright, trade secrets, and other proprietary and intellectual property
rights in the documents provided by Mitsubishi Heavy Industries, Ltd.(MHI)
(including safety-and-instruction manuals) are at all times owned and reserved
by MHI. Subject to your compliance with the restrictions set forth below, MHI
grants to you a limited, non-exclusive license in the copyright for the sole
purpose of allowing you to use, operate, maintain and inspect the Plant.

Use, copying, other reproduction of the whole or part of the documents


provided by MHI (including safety-and-instruction manuals) for any purpose
other than the purpose described above without MHIs prior written consent is
strictly prohibited.

The act of rewriting, translating, modifying, revising, creating electronic copies,


uploading, selling, sublicensing, or otherwise disclosing the whole or part of the
manuals is strictly prohibited.

Except as specifically set forth above, no right, title or license to the documents

MM-M05.06

Rev.001

provided by MHI, whether arising from contract, implication, estoppel or


otherwise, is being granted or otherwise transferred.

Turbine Main Oil Pump


Mitsubishi

ix

Personnel to whom the


Manual is Directed
This Manual was prepared for all personnel who will participate in the operation and
maintenance of the plant, and the other related mechanical plant and equipment
installed.
In this Manual, MHI classifies personnel into the following two classes based on
their ability, experience and their attitude to the safety of personnel, and the plant
installed.
Only the personnel recognized by the Customer as trained personnel are allowed to
perform the operation and maintenance specified in the manuals.
Maintainers and Operators are required to have read and understood the contents
of the safety, operation, and maintenance manuals and sufficiently understand the
work procedures before actually starting their tasks.

Operator

Operators following the instructions of their supervisor or the Shift Charge Engineer
are permitted to handle materials to be used in the operation of the plant.
Operators are allowed to turn on the power supply, startup equipment, open up or
remove covers or panels on receipt of an instruction or authorization from their
superior.
Operators are permitted access to emergency stop devices following instructions
given by their superior when dangerous or hazardous situations are recognized.

Maintainer

MM-M05.06

Rev.001

Maintainers are permitted to perform maintenance on the plant. They will also
perform troubleshooting routine and periodical inspections of the installed
equipment. The maintainer will also work under the supervision of MHIs
supervisors during on-the-job training and annual maintenance and overhaul work if
MHIs supervisors are requested to witness periodical inspections, etc.
Maintainers MUST have attended the training programme initially provided by MHI
and subsequently by the Customer, and they must have obtained the necessary
knowledge and maintenance skills to understand the characteristics of their tasks
before actually starting their work.
Turbine Main Oil Pump
Mitsubishi

Contact Address
For any question or any clarification required, please do not hesitate to contact MHI
through the following address (es).

For Support before Operation:


MITSUBISHI HEAVY INDUSTRIES, Ltd.
Nagasaki Shipyard & Machinery Works
1-1, Akunoura Machi, Nagasaki 850-91

For Support after Commissioning and in an Emergency

MM-M05.06

Rev.001

(Later)

Turbine Main Oil Pump


Mitsubishi

xi

Abbreviations
Abb.

Expanded Form

Abb.

Expanded Form

Alternating Current

MOST

Mechanical Overspeed Trip

Gen End

Generator End

MSDS

Material Safety Data Sheet

Gov End

Governor End

NDE

Non-Destructive Examination

HP

High Pressure

OJT

On Job Training

IP

Intermediate Pressure

P&ID

Process and Instrumentation


Diagram

I&C

Instrumentation and Control

PPE

Personal Protective Equipment

LH

Left-hand

PTW

Permit to Work

LP

Low Pressure

RH

Right-Hand

MOP

Main Oil pump

TOP

Turning Oil Pump

MM-M05.06

Rev.001

AC

Turbine Main Oil Pump


Mitsubishi

xii

List of Vendor Manuals

MM-M05.06

Rev.001

NIL

Turbine Main Oil Pump


Mitsubishi

xiii

Arrangement of the System


Maintenance Manual
This manual is arranged as follows.

Chapter 1
Describes health and safety issues during maintenance, disassembly and reassembly
of the Turbine Main Oil Pump.

Chapter 2
Describes the construction, purpose, and function of the Turbine Main Oil Pump and
the associated parts.

Chapter 3
Describes the Turbine Main Oil Pump parts, using the relevant Data Sheets.

Chapter 4
Describes the Preventive, Routine, and Outage Maintenance.

Chapter 5
Describes the disassembly and reassembly procedures, necessary to obtain access
to internal parts for inspection and repair during Turbine Main Oil Pump overhaul.

Chapter 6
Describes the corrective maintenance procedures to be followed to investigate,
identify and remedy defects occurring during operation.

MM-M05.06

Rev.001

Chapter 7

Includes Torque Chart, Spare Parts, Special Tools and Vendor Drawings/Documents

Turbine Main Oil Pump


Mitsubishi

xiv

Chapter 1

Safety

C h a p t er

1 S af et y
1.1

Feature of Turbine Main Oil Pump Safety


The main oil pump is the equipment that rotates at the same speed of the main
turbine. The main oil pump when in service is subject to near constant discharge
oil pressure with high flow variations. The flow variations occur due to the
operation of the various turbine steam admission valves or when there is a
turbine trip.
The oil flow and hence pressure variations caused during the main turbine
operation are relieved by relief valves installed on the lubricating oil and control
oil piping. However, due to the sudden oil pressure fluctuation and ageing of
flange gaskets, the oil piping has a high risk of flange/pipe leakage. Leaked oil
from the oil piping can cause extensive damages in the vicinity of the turbine
and/or person working near, if it catches fire.
Oil lines supplying the control and lubricating oils to the main turbine are located
around the main turbine. Any oil leakage in the vicinity of the turbine could lead
to a fire which could damage the nearby components. All personnel should pay
strict attention and rectify any oil leakage at the first sight of leakage.
The main oil pump operates with close internal clearances and any disturbance
in the turbine rotor alignment can cause internal rubbing and damage to the
main oil pump components. All operators and maintainers should pay special
attention if any rubbing noise is observed near the HP pedestal where the Main
Oil Pump is installed.

MM-M05.06

Rev.001

All operators and maintainers must realize the danger and keep themselves
safe, following the recommendations written in this chapter.

Turbine Main Oil Pump


Mitsubishi

1-1

Chapter 1

1.2

Safety

Warnings Description
Safety of personnel working in the power plant is the most important matter and
all kinds of consideration to avoid dangerous conditions are studied and applied
to the design of the power plant. However, certain risks are unavoidable due to
the nature of the plant.
This manual classifies the severity and hazard level of such risks by two
categories, DANGER and CAUTION. Read and understand the indications
thoroughly before operation or maintenance of the plant.
The contents of wordings, DANGER and CAUTION are described as follows;
Kinds

Meaning of Warnings
DANGER indicates an imminently hazardous situation
during use of the Turbine Main Oil Pump, which, if not
avoided, could result in death or serious injury, or
serious damage to the property or environment.
CAUTION indicates a potentially hazardous situation

CAUTION

during use of the Turbine Main Oil Pump, which, if not


avoided, may result in minor injury, or minor damage to
the property or environment.

This manual also uses the following indicators in addition to the hazard level
indications described above.

Kinds

Meaning of Warnings
IMPORTANT describes the particular information or
items that personnel must know during operation and

IMPORTANT

maintenance of the Turbine Main Oil Pump, and that, if


not heeded, may result in an accident of an
in-assessable hazard level.
NOTICE describes useful information and tips for

Notice

operation and maintenance of the Turbine Main Oil

MM-M05.06

Rev.001

Pump.

Turbine Main Oil Pump


Mitsubishi

1-2

Chapter 1

Safety

1.2.1 Definitions of Serious Injury, Minor injury,


Serious Damage to Property, and Minor Damage to
Property
Serious Injury
This term describes injuries, which leave after effects such as loss of
eye sight, permanent disability, bone fracture or breakage, gas
inhalation, asphyxiation, electric shock, hospitalization or prolonged
hospital visits for treatment.

Minor Injury
This term describes injuries, which do not require hospitalization or
prolonged attention at a hospital (injuries other than the serious
injuries described above).

Serious Damage to Property


This term describes damages, which require a suspension of
productive activity for one day or more due to restoration of the
damaged property.

Minor Damage to Property

MM-M05.06

Rev.001

This term describes damage, which does not require any suspension
of productive activity due to restoration of the damaged property.

Turbine Main Oil Pump


Mitsubishi

1-3

Chapter 1

Safety

1.2.2 Symbol
In this manual, the following symbols are added for easy understanding
of the contents of warnings and are found next to DANGER,
CAUTION and indications.
These symbols are in compliance with ISO 3684.
Symbol

Description
This symbol indicates the possible presence of high voltage, and
warns of a hazard which may result in system shock, burn or
death by electric shock if safety precautions are neglected or the
system is handled incorrectly.
This symbol indicates a movable section that is inside a safety
cover or is exposed.
Movable parts may inflict laceration or bone fracture to body parts
such as a hand by pinching the hand and/or clothing.
This symbol indicates the presence of parts the surface of which
could be hot, and may cause a burn if handled incorrectly.
This symbol indicates that care should be taken where you place
your feet when moving around the area.
Risk of injury by tripping is present near this symbol due to
factors such as a location with an unstable surface, or
obstructions such as scaffolding, temporary pipe lines, or other
protrusions.
This symbol indicates the possible presence of gas(es) harmful or
asphyxiant to personnel.
Be sure to ventilate fully before work commences.
This symbol indicates caution against the handling of a heavy
object or working in an abnormal position.
Do not work in an abnormal posture which may damage your back
or waist.
This symbol indicates prohibited items or actions during the

MM-M05.06

Rev.001

operation and maintenance of the Turbine Main Oil Pump.

Turbine Main Oil Pump


Mitsubishi

1-4

Chapter 1

1.2.2

Safety

Symbols (Continued from previous page)

Symbol

Description
This symbol indicates that personnel must not touch since the
surface is hot.
Do NOT enter any area where this symbol is displayed.

This symbol indicates that the entry of personnel is prohibited.


Do NOT enter any area where this symbol is displayed.

This symbol indicates that physical contact is prohibited.


Do NOT touch or enter a location or enclosure where this symbol
is displayed.
This symbol indicates that the stated items or actions in the
warning notices relative to operation and maintenance of the
Turbine Main Oil Pump are mandatory.
This symbol indicates a movable section that is inside a safety
cover or exposed.
Do NOT touch any equipment where this symbol is displayed.

1.2.3 Hazard Warning Label


Hazard warning labels are applied where potential hazards are present
during operation and maintenance activities.
Hazard warning labels will be in appropriate sizes and colors that will
catch the eye and the attention of personnel. They also have symbols
that show the hazard types, in addition to the descriptions of warning
contents.

IMPORTANT
Personnel are requested to confirm the location of, and to read, and
thoroughly understand the contents of all hazard warning labels
labels peel off/wear out or become unreadable, install a new label in
the original location without delay.

MM-M05.06

Rev.001

applied to this Turbine Main Oil Pump. If any of the hazard warning

Turbine Main Oil Pump


Mitsubishi

1-5

Chapter 1

WARNING

Safety

DO NOT COME
NEAR TO SHAFT
EXPOSED ZONE
WHEN IN
OPERATION

PINCH POINT

STEEP
DROP

DO NOT
ENTER

DO NOT
TOUCH

DO NOT
TOUCH

MM-M05.06

Rev.001

TB0001_A

FIGURE 1-1
Turbine Main Oil Pump
Mitsubishi

TYPES OF HAZARD WARNING LABEL

1-6

Chapter 1

Safety

1.2.4 Hazard Area

IMPORTANT
Only trained maintainers and operators are allowed to enter the
maintenance work area. Entry to the area by personnel untrained
could cause not only injury but also serious damage to the Turbine

MM-M05.06

Rev.001

Main Oil Pump.

Turbine Main Oil Pump


Mitsubishi

1-7

Chapter 1

1.3

Safety

Risk Assessment Standard


As prepared by the Design Section as per MIL STD822D.
TABLE 1-1

RISK ASSESSMENT STANDARD


Detailed Description of Impact on each Object

Category

Safety

- Death

- Harmful gas or oil leakage


- High pressure and
temperature material leakage
such as steam, water, air and
gas, oil etc.
- Low oxygen

Catastrophic

II

Critical

- Unit shutdown (can not be operated)


- Within 3 days for repairing

- Serious Injury

- Same as the above

III

Marginal

- Unit shutdown (can not be operated)


- Can be repaired by Customer

- Minor Injury
(with
hospitalization)

VI

Negligible

- Same as the above


- High temperature surface
- High elevation or unstable
- Not harmful and high
pressure & temperature
leakage
-Mechanical protected

- Minor Injury
(without
hospitalization)

RISK ASSESSMENT STANDARD (CONTINUED)

Definition

Description

Category

Detailed

(A)

Frequent

Repeating occurrence

1 time / 1 or 2 months

(B)

Probable

Known to occur, or, it has happened

1 time / 1 year

(C)

Occasional

Could occur

1 time / 5 years

(D)

Remote

Not likely to occur

1 time / 10 years

(E)

Improbable

Practically Impossible

1 or 2 times / total life

TABLE 1-1
Hazard
Categories
Frequency
of Occurrence
Rev.001

Environment

- Unit shutdown (unit cannot be


operated)
- More than 4 days for repairing

TABLE 1-1

MM-M05.06

Health

RISK ASSESSMENT STANDARD (CONTINUED)


I

II

III

VI

Catastrophic

Critical

Marginal

Negligible

(A)

Frequent

13

(B)

Probable

16

(C)

Occasional

11

18

(D)

Remote

10

14

19

(E)

Improbable

12

15

17

20

Turbine Main Oil Pump


Mitsubishi

1-8

Chapter 1

10
5
3
2

10
5
3
2

10
5
3
2

10
5
3
2

7
4
3

4
3 9
2 8
1 7

7
4
3

Safety

7
4
3
7
4
3

4
3

STAIR WAY

2
3
5
10

3
7
8

3
4
7

STAIR WAY

2
3
5
10

2
3
5
10

2
3
5
10

3
4
7

3
4
7

1 7
2 8
3 9
4

3
4
7
NOTES
WARNING LABELS SHOUD BE IN ARABIC.

GEN. SIDE

MM-M05.06

Rev.001

YELLOW

AVOID INJURY
WATCH YOUR STEP

YELLOW

FALL
WATCH YOUR STEP

MPTD-3-0314

YELLOW

RISK OF A ROTATING
A HAND

YELLOW

RISK OF A GEAR
PINCHING A HAND

GOV. SIDE

(*1)

YELLOW

RISK OF A CHAIN
PINCHING A HAND

YELLOW

PINCH POINT
KEEP HANDS AWAY

YELLOW

YELLOW

DO NOT TOUCH
HOT SURFACE

YELLOW

YELLOW

DISCONNECT
AUTOMATIC START.
ELECTRICAL POWER
KEEP HANDS CLEAR.
BEFORE SERVICING

RED

DO NOT SMOKE
IN THIS AREA.

10

RED

OPERATING PERIOD

(*1) THE MOST SUITABLE ONE WILL BE ADOPTED TO EACH PLACE.

FIGURE 1-2
Turbine Main Oil Pump
Mitsubishi

YELLOW

MAPPING FOR HAZARDOUS AREA

1-9

Chapter 1

1.4

Safety

Safety Measures
1.4.1 Work Permit System (Lockout/ Tagout)
Work permit system is applied when equipment is shutdown for
maintenance work, to complete the maintenance work under a safe
condition. The outline of the work permit system is as follows:

(2)

The Shift Charge Engineer passes the work permit form to the
operator to study and decide the isolation method from the line in
operation on the mechanical and electrical view point and then
report to the Shift Charge Engineer with the comments on the
hazard conditions for the work.

(3)

The Shift Charge Engineer gives work permit number and


prepares necessary tags to show the work permit number and
the situation of isolation by valves and power supply. He will then
instruct the operators to set the isolation condition following the
work permit form.

(4)

The operators will open the breaker and set the valves to the
specified condition, they will also drain and vent the equipment to
be worked on, and the breaker and the valves are to be locked.
The operators return the work permit to the Shift Charge
Engineer.

(5)

The Shift Charge Engineer checks the isolation and will issue the
signed work permit to the Maintainer, or his representative.

(6)

The Maintenance Engineer orders the start of the maintenance


work to the personnel nominated.

(7)

The Maintenance Engineer or his representative will then return


the signed work permit to the Shift Charge Engineer after making
sure the maintenance work is completed.

(8)

The Shift Charge Engineer will then send operators to release the
locks and return to the original situation.

(9)

The operators check the situation and report that the system is
now back to the normal condition when signing off the work
permit.

Rev.001

The Maintenance Engineer applies for the work permit clearly


indicating the content of the maintenance work that he wants to
do, and submits it to the Shift Charge Engineer.

(10) The Shift Charge Engineer makes sure that the work under the
permit is completed and files details in the log book.

MM-M05.06

(1)

The work permit system is to clarify responsibility for the works on each
step and to ensure that the work is performed safely.

Turbine Main Oil Pump


Mitsubishi

1-10

Chapter 1

Safety

1.4.2 General Cautions on Personnel in Working Area


1.4.2.1

Cautions against Rotating Equipment


All couplings on rotating machines are covered by the
coupling cover but whole parts of the shaft are not fully
covered. It is recommended that the following warning is
observed strictly.

Do not approach or operate the equipment where


protective covers have been removed. Get additional
supervisor assistance.

Make sure that the breaker for the motor is opened when
you are required to remove the cover.

Care must be taken of the exposed rotating parts,


especially in the area between the casing and the coupling.

All shafting, coupling and other rotating parts must be


guarded in order to prevent accidental contact.

1.4.2.2

Cautions against Electrical Equipment

MM-M05.06

Rev.001

The electrical equipment covered under this section


includes all the concerned plant equipment and the
maintenance tools like grinders, lamps, welding equipment
etc. Though live parts of the plant or maintenance tools
are insulated, be sure to observe the following cautions.
Failure to observe them may cause fatal accidents,
personal injuries and damage to the electrical equipment.

Turbine Main Oil Pump


Mitsubishi

Always, confirm that power supply is disconnected at the


up-stream side of power supply system and it is locked
according to the Work Permit.

Do not remove or open panels or doors labeled with high


voltage live part warning label not included in the Work
Permit.

Ensure the proper earthing is provided for all electrically


operated tools and equipment used for maintenance works.

In case of usage of lamps for internal inspection, ensure


that a low voltage system (24volts) is available.

Make sure that no materials or Parts remain in the Panels or


terminal box before closing them finally.

1-11

Chapter 1

1.4.2.3

Safety

Cautions against High Temperature Sections


Various equipment and pipelines contain high temperature
fluid and they are insulated on their surface. There are
however some pipe lines which are not insulated, and as
their temperature is very high and you could get burned,
please observe the following caution to avoid burn injury.

CAUTION
Suitable Personal Protective clothing is always available
and should always be worn, including gloves to avoid
direct contact to hot spots in the plant.

Level gauges of pressure vessels including connecting


pipes are not insulated to cool down the steam to drain.

Sampling piping is not insulated to cool down the steam to


a suitable temperature for the analyzer except at the places
located close to the work place.

All exhaust pipes of the safety valves and the exhaust pipe
of the boiler flush pipe are not insulated.

Always wear gloves.

MM-M05.06

Rev.001

Turbine Main Oil Pump


Mitsubishi

1-12

Chapter 1

1.4.2.4

Safety

Cautions for Steam Leak in the Plant


The steam leak especially from high temperature steam
may cause serious injury to the personnel and it must be
repaired at an early stage of the leakage. The following
pre-cautions must be followed to find leakage at an early
stage.

Water drips may occur at the insulated parts such as the


connected part of the lagging. The leaking point can be found
by removing insulation partially using great care.

As you approach the leakage the water will change to visible


steam. It is now too dangerous to remove the insulation.

Leakage of the superheated steam only makes whistling


noise without generating white steam. It is very dangerous to
approach the noise area.

Contact the Charge Engineer to obtain a Permit to Work to


ensure plant isolation before repairing the damage.

Be well aware of the steam. The steam could leak from the
water system containing water at 100C or higher even if it is
a low pressure type water system.

High temperature drain or steam could leak from the flush


pipe during start-up.

If not avoided, the steam or vapor can enter the inside of your
working wear through the small gap between the body and
the clothing.

1.4.2.5 Caution against Oil Leak in the Plant

MM-M05.06

Rev.001

CAUTION

Turbine Main Oil Pump


Mitsubishi

Oil leakage is very dangerous. It is a potential fire hazard.

Any oil spillage must be reported to the Shift Charge


Engineer.

Oil leaks make the area slippery and people are advised to
move around these areas carefully.

1-13

Chapter 1

1.4.2.6

Safety

Cautions against Chemicals


Pay attention to the items listed below to prevent any
accident related to the chemicals in the plant.

IMPORTANT
Precaution against chemicals:

Operate chemical injection systems by strictly following the


instruction of the chemist. The operator must use suitable
protective tools.

Disposal:

Observe the rules and regulation of the installation site.

Material Safety Data Sheet (hereafter MSDS):

Always understand the content of the applicable MSDS


before using , and observe the notified instructions when
handling the chemical.

Emergency response:

Solution against emergency must be thoroughly instructed


to all personnel involved so that the fullest measures can be
taken against any situation.

1.4.2.7

Cautions against Combustible Materials/


Storage Areas

IMPORTANT
Storage containers must be clearly marked to indicate the
content.

Bunding must be provided for bulk tanks.

Suitable fire protection must be provided for each area.

Do not store bulk combustible materials on the site.

Small quantities of combustible materials must be stored in


fire resistant cupboards.

Combustible materials must be segregated from other


equipment.

MM-M05.06

Rev.001

Turbine Main Oil Pump


Mitsubishi

1-14

Chapter 1

1.4.2.7

Safety

Cautions against Combustible Materials /


Storage Areas (Continued)

IMPORTANT

Leakage of gasoline has the risk of fire. Maximum storage


quantity of gasoline outside of the dispensing pump is five
liters.

Emergency response:

Personnel directly involved in combustible materials MUST


be properly trained and thoroughly instructed. Other
personnel in the vicinity must be aware of the dangers and
take precautions in all situations.

1.4.2.8

Cautions against Lack of Oxygen

Check that the oxygen content in the equipment vessel or in


the confined space is between 18~22% before entering, and
ensure sufficient ventilation.

Continue monitoring oxygen and ventilation during


inspection.

It is recommended that you do not enter the equipment,


vessel or confined space alone but if the situation demands
that you must enter, take the necessary preventive safety
measure provided, breathing system etc, and find a partner
who will wait for your return at the point of entry, keeping in
verbal contact throughout.

Make complete arrangements for rescue.

MM-M05.06

Rev.001

Turbine Main Oil Pump


Mitsubishi

1-15

Chapter 1

1.4.2.9

Safety

Cautions against Lifting Heavy Object


Be careful during the removal/installation of any
equipment during maintenance.

CAUTION

Do NOT attempt to move or lift equipment in an abnormal


posture. ALWAYS install/remove equipment, using a forklift
or a crane. A normal lift without mechanical aid should be
shared between two or more persons.

Failure to observe the above may cause injury due to


dropped equipment, back or waist injury or damage to the
equipment.

1.4.2.10 Cautions against Sharp Objects

CAUTION

Use leather gloves when handling parts with sharp edges.

1.4.2.11 Cautions using Fork Lift

MM-M05.06

Rev.001

CAUTION

Turbine Main Oil Pump


Mitsubishi

Do NOT permit anyone to stand below any item being lifted


under any circumstance.

Failure to observe this may cause fatal accidents.

When using a forklift, ALWAYS lift the objects parallel to


the ground while considering the center of gravity.

Otherwise, lifted objects may fall and serious damage


could occur.

A forklift is often used to transfer small machines. Check


fork insertion position for the forklift prior to use. Be
careful, as marks which indicate the fork insertion
positions are sometimes hidden by wraps or packing
materials.

1-16

Chapter 1

Safety

1.4.2.12 Cautions using Crane

CAUTION

A crane is often used to transfer heavy parts. Check for any


possible risks which could occur during hoisting and
transportation before operating the crane.

Check of the equipment:

Check the crane, the crane hook and all related items
before use. Use wire ropes which can withstand the weight
of the parts multiplied by a safety factor.

Inspect the shackles, eyebolts, jigs and wire ropes


provided for the hoisting work prior to the actual hoisting.

Perform periodical inspection (dye penetrant test) of


hoisting tools at least once a year.

Rigging / Slinging work:

Only authorized personnel can perform slinging work and


operation of the crane.

Work area:

Before hoisting, secure a working area around the part to


be lifted and prohibit the entry of unrelated personnel.

Hoisting method:

Hoist the part parallel to the ground while paying attention


to the center of gravity.

Do NOT permit any person to stand under the part being


lifted.

Pay attention to and ensure that all persons are clear of the
equipment being lifted.

Hoisting point:

Do NOT hoist any parts from a position other than the


specified hoisting points.

Unpacking:
Do NOT unpack any part until it is located in the
designated location.

Protection of machine:

MM-M05.06

Rev.001

Turbine Main Oil Pump


Mitsubishi

Avoid any impact to the unpacked parts.

1-17

Chapter 1

Safety

1.4.2.13 Disposal
a)

Water disposal including oily drain


The water is disposed to the plant drain system. The water must
be carefully disposed according to materials contained in the
water. The water drain system is separated into three categories
that are rain water, chemical water and oily water.
The waste waters are treated and then discharged to the public
drain system.

b)

Chemical disposal
Chemicals must be handled following the instruction of the MSDS
and disposed to the chemical drain system.

c)

Solid disposal made by maintenance work.

MM-M05.06

Rev.001

For disposal from the site, observe the local legal regulations.

Turbine Main Oil Pump


Mitsubishi

1-18

Chapter 1

1.5

Safety

Emergency Measure
1.5.1 Evacuation on Emergency Case
1.5.1.1

Evacuation Route
Following items are considered on design and installation
of emergency evacuation.

IMPORTANT

Each building installed in the plant is provided with at least two


exits. A clear indication of the exits can be seen from anywhere
in the building as the exit sign is illuminated using the
emergency power supply.

Evacuation routes are indicated on each floor of the building,


directing personnel to the exits.

Keep the evacuation routes completely free from materials and


tools.

1.5.1.2

Evacuation of Disabled Persons Who Cannot


Move by Themselves
The following are necessary items, prepared for emergency
evacuation:

IMPORTANT
It is recommended to keep a stretcher available for
emergencies at the places selected as being secure at the
safety meeting.

If you find this kind of accident, inform the rescue team, and
attempt to bring the collapsed person to the first aid station.

MM-M05.06

Rev.001

Turbine Main Oil Pump


Mitsubishi

1-19

Chapter 1

1.5.1.3

Safety

Evacuation from Power House


Following are guidance for the evacuation from the power
house.

IMPORTANT

An evacuation place for personnel to gather in after


evacuation from the power house in an emergency must be
predetermined and explained beforehand in the emergency
training.

Evacuation directive must be given by the responsible


person such as Shift Charge Engineer, and all personnel
must be alerted in the power house repeatedly with an
available broadcast facility.

All people working in the power house must stop their work
immediately and leave the power house to the gathering
place.

When evacuated to the evacuation place, make sure


that there is no one missing.

MM-M05.06

Rev.001

Turbine Main Oil Pump


Mitsubishi

1-20

Chapter 1

Safety

1.5.2 Fire Accident

IMPORTANT
Clearly show the location of fire alarm push button and fire
extinguisher to make everybody take the first step at fire
protection.

Inform everyone concerned that a fire has now started if


you discover a fire.

Start fire fighting using the fire extinguisher located near


the fire site.

The operators must check the plant is ready for trip, and
wait for order from the responsible person.

The operator and other personnel must transfer the fire


fighting to the fire fighting team when they arrive at the fire
site and the operators must wait for instruction from the
Shift Charge Engineer. All other personnel must
immediately start evacuation.

If unit trip is decided, the operator must trip the plant


manually.

The operators must evacuate from the power house


according to the instruction of the responsible person
immediately after shutdown of the unit.

If the fire is extinguished successfully, the operators


should return to the power house as required by the Shift
Charge Engineer and start inspection of the equipment for
restart of the unit.

Based on the inspection, the responsible person should


decide whether to operate the unit again or shutdown for
repairing.

After the inspection or repair, and then checking the


equipment and/or system, start up the unit again.

MM-M05.06

Rev.001

Turbine Main Oil Pump


Mitsubishi

1-21

Chapter 1

Safety

1.5.3 Earthquake
In the case of an earthquake, the shift charge engineer or operator
must judge whether the unit trip is necessary according to the intensity
of the earthquake, and immediately trip the unit manually. If the unit is
tripped, all equipment must be carefully checked on its operation status
and tripped if abnormal phenomena are found.
In the local area, mechanical and/or thermal shocks may be given to
the equipment, piping, instruments and electrical panels. Be sure to
observe the following when completing the inspection.

Check that the lubricating oil pump is running. Bearings of


the equipment will be damaged if lubricating oil is not
supplied.

Check the piping and equipment for steam and water


leakage. The steam or high temperature water leakage may
cause serious injury to the personnel and it must be
repaired at an early stage of the leakage.

Check the pulverizers and/or coal silos for signs of a fire. If


a fire does start, make sure that the CO2 fire fighting system
is properly operated.

Check the position of boiler seismic stopper. Since the


boiler seismic stopper must be anchored at the original
position, the boiler cannot be re-started if the slippage is
found. If the stopper is not at the original position, please
contact MHI.

CAUTION

Check the piping and equipment for the breaking and the
dropping of insulation. Since the exposure of the hot
surface may cause burn injury, it must be repaired by a
worker fully dressed in Personal Protective Equipment.

MM-M05.06

Rev.001

1.5.4 Explosion Accident

Turbine Main Oil Pump


Mitsubishi

Do not use a fire in a hazardous area where the combustibles


(hydrogen gas, oxygen gas, coal, fuel oil, etc.) are stored or
handled. Use of a fire in a hazardous area could cause
serious injury to personnel and serious damage to
equipment due to an explosion.

1-22

Chapter 1

1.6

Safety

Qualification and Training


The system must be operated only by authorized operators & maintenance
supervisors.
The customer shall authorize all operators and maintainers, who are involved in
the operation and maintenance of this plant, either by the training course given
by Mitsubishi, or by customers own personnel assessment.
Operator and maintainer training course (both classroom training and On the
Job Training (OJT)) will be provided by Mitsubishi before the handing over of
this plant. The customer must train and assess new operators and maintainers
who join after the turn-over according to his own procedure and standard,
(Mitsubishi training course may still be available if required).

MM-M05.06

Rev.001

As a minimum, operator and maintainer must satisfy the following:

Operator and Maintainer can read and fully understand the description of
this manual.

Operator and Maintainer can understand the related P & ID, logic diagram.

Operator and Maintainer know the location of the system equipment


including pipe routes, valves and the various instruments.

Operator and Maintainer have fundamental knowledge of the function of


each equipment.

Operator can operate the equipment and the system manually at local
stations.

Operator can operate the system remotely using DCS system.

Operator can respond suitably for any kind of alarm.

Operator knows location of emergency exit on power house and is available


to provide first aid treatment.

Operator knows emergency communication system operation.

Operator and Maintainer know from their discussions with the Shift Charge
Engineer the isolation method for mechanical, electrical and instrumental
equipment to ensure safety for maintenance work during plant operation.

Maintainer must also be able to handle the maintenance tools provided by


the owner and those supplied by the manufacturer.

Turbine Main Oil Pump


Mitsubishi

1-23

Chapter 2

General

C h a p t er

2 General
2.1

Purpose
The purpose of this maintenance manual is to provide specific information to the
Paiton Expansion Project maintenance personnel regarding the maintenance of
the turbine main oil pump. Although this document will convey a good
knowledge and direction regarding maintenance of the turbine main oil pump, it
is recommended that in the event of a problem not covered in the document the
person responsible should seek assistance or instruction from the turbine
manufacturer.

References
a)

Turbine Sectional Assembly


MHI Dwg No: T3059AAAA001
Project Dwg No: P101-50-3-TB-TGO003.

b)

Control and Lubrication Oil System Diagram


MHI Dwg No: T3059AAAA210-1
Project Dwg No: P101-51-3-TB-LT0001.

c)

Control and Lubrication Oil System Diagram


MHI Dwg No: T3059AAAA210-2
Project Dwg No: P101-51-3-TB-LT0002.

d)

Control and Lubrication Oil System Diagram


MHI Dwg No: T3059AAAA210-3
Project Dwg No: P101-51-3-TB-LT0003.

e)

Main Oil Pump Assembly (1/2, 2/2)


MHI Dwg No: N26-T19-5054.

MM-M05.06

Rev.001

2.2

Turbine Main Oil Pump


Mitsubishi

2-1

Chapter 2

2.3

General

Overview of the Turbine Main Oil Pump


Refer to Figures 2-1 to 2-3.
The turbine main oil pump (MOP) is installed in the High Pressure (HP) pedestal
in front of the HP turbine and is located on the turbine operating floor level. It is
driven directly by the HP-IP turbine rotor extension stub shaft.
As the turbine reaches normal speed the MOP discharge pressure exceeds and
replaces the discharge pressure of the auxiliary oil pump (AOP) and the turning
oil pump (TOP). Hence, the oil from the MOP discharge side becomes the high
pressure protection oil for the turbine protective devices (HP oil) and low
pressure lubricating oil for the turbine and generator bearings (lube oil).
The turbine MOP starts, stops and operates as the main turbine does. During
normal operation it turns with the main turbine rotor shaft at 3000 rpm.
The MOP is of the horizontal, single stage, conventional double suction,
centrifugal type.
The MOP draws suction oil from the outlet of No. 1 oil ejector and provides the
protection and lubricating oil requirements for the main turbine. The MOP
discharges high pressure oil (HP oil) to the turbine protection system and motive
oil for the Nos. 1 and 2 oil ejectors. The No. 1 oil ejector serves as a MOP
suction booster and the No. 2 oil ejector as a booster for the lubricating oil flow
for the thrust and journal bearings of the turbine and the generator. The seal oil
back-up line to the generator seal oil system is provided from the turbine bearing
lubricating oil system.
The MOP has no self-priming function; therefore prior to startup, the MOP is
supplied with suction oil from the TOP. This oil is used to prime and purge air
continuously from the inside of the MOP through the air vent plugs installed on
the MOP casing cover.
The extension shaft, bolted directly to the end of the HP-IP rotor at the governor
end (Gov End), carries the impeller of the MOP.

Sealing of the impeller shroud to casing and of the shaft penetrations is


achieved using floating wind-back type sealing rings.

MM-M05.06

Rev.001

The stub extension shaft also carries the centrifugally activated mechanical
overspeed trip (MOST) device and a rotor position measurement plate. It also
has provisions for installing the pick-ups for the rotor speed, rotor eccentricity,
rotor position and phase detection devices.

Turbine Main Oil Pump


Mitsubishi

2-2

INSTRUMENT AIR

Chapter 2

PI
24
PIT
26

TRIP LEVER
TRIP
PIT
31

PS
31

PS
32

PS
33

PS
34

35

MANUAL TRIP DEVICE

General

SOLENOID VALVE
(TURBINE MASTER RESET)

TO ATMOSPHER

DRAIN

EH EMERGENCY TRIP OIL

RESET
RESET LEVER

FROM EH HP OIL

LIMIT SWITCH

S
S

OVERSPEED TRIP DEVICE


TEST LEVER

EMERGENCY
TRIP VALVE
S

TEST

DRAIN

PIT
25

DRAIN

EH DRAIN OIL
DRAIN

LIMIT SWITCH

MECHANICAL OVERSPEED TRIP DEVICE

AUTO STOP OIL

HP OIL

DIFFERENTIAL EXPANSION
PICK-UP
MAIN OIL PUMP

PIT
24

PI
22

PHASE DETECTOR
PICK-UP
NO1.BRG.

ROTOR ECCENTRICITY
PICK-UP

TE
4

TE
6

TE
8

NO3.BRG.

NO2.BRG.

TE
9

TE
10

NO4.BRG.

TE
12

TE
11

NO5.BRG.
TE
14

TE
13

SOLENOID VALVE
(GEAR DISENGAGE)

NO6.BRG.
TE
15

SOLENOID VALVE
(GEAR ENGAGE)

SOLENOID VALVE
OIL SUPPLY TO
TURNING GEAR

THR.BRG.

AIR

INSTRUMENT AIR

AC
M

TE
16

ATMOSPHERE

ENGAGE

TEST VALVE
TE
5

TE
23
TE
21

SHAFT POSITION
PICK-UP

PIT
21

MOP DISCHARGE OIL

MOP SUCTION OIL

MAIN
OIL PUMP

PI
25

TE
24

TE
22

TE
25
PI
1

TE
26
PI
2

TE
28

TE
27
PI
4

PI
3

DISENGAGE

COUPLING
SPRAY

HP CASING EXPANSION

COUPLING SPRAY

TE
7

COUPLING SPRAY

HP REDESTAL

LIMIT SWITCH
(GEAR ENGAGE)

TURNING GEAR ENGAGING SYSTEM


TO GENERATOR
TO GENERATOR

LUBE OIL

JACKING OIL

HP OIL
LEVEL GAUGE
VAPOUR
EXTRACTOR

PI
1

PI
5

PIT
11

PI
4

PI
21

PI
2

LUBE OIL
FILTER

OIL
RETURN
AC
M

AC

AC

LIMIT SWITCH
(GEAR DISENGAGE)

DC
M

AC
M

JACKING
OIL
PUMP(A)

AC
M
TE
3

PI
12

PI
11

3-WAY
VALVE

PIT
12

JACKING
OIL
PUMP(B)

AC
M

PIT
13

TI
3

400 Mesh.

LT
1

TURBINE OIL COOLER


TURNING
OIL PUNP

TE
1

Rev.001

TI
1

EMERGENCY
OIL PUMP

(A)

DPI
13

400 Mesh.
DPI
14

(B)

AUXILIARY
OIL PUMP
3-WAY VALVE

MOP SUCTION
EJECTOR

TURBINE LUBRICATION
EJECTOR

TE
2

MM-M05.06

MAIN OIL TANK

MPTD-3-0193

FIGURE 2-1
Turbine Main Oil Pump
Mitsubishi

MAIN TURBINE LUBRICATING OIL FLOW DIAGRAM

2-3

Chapter 2

General

MAIN STEAM
INLET
IP EXHAUST

REHEAT STEAM
INLET

GOV. SIDE

GEN.SIDE

NO.1 MAIN BEARING

NO. 2&3 BEARING


PEDESTAL

THRUST BEARING
NO.2 MAIN
BEARING

MAIN OIL PUMP

HP PEDESTAL

HIP TURBINE

OPERATING FLOOR

HP EXHAUST

MAIN STEAM
INLET

MPTD-3-0194

MM-M05.06

Rev.001

REHEAT STEAM
INLET

FIGURE 2-2
Turbine Main Oil Pump
Mitsubishi

OVERVIEW AND LOCATION OF TURBINE MAIN OIL PUMP

2-4

Chapter 2

D E S C R IP T IO N
P U M P C A S IN G C O V E R
P U M P C A S IN G B A S E
R O T O R P O S IT IO N IN D IC A T O R D IS C
T R IP O V E R S P E E D A S S 'Y
SHAFT

MM-M05.06

Rev.001

IT E M
1
2
3
4
5

General

FIGURE 2-3
Turbine Main Oil Pump
Mitsubishi

ISOMETRIC VIEW OF TURBINE MAIN OIL PUMP

2-5

Chapter 2

2.4

General

Construction
The MOP consists of the following major components:

Pump casing

Impeller and shaft assembly

Impeller seal rings

Shaft penetration seal rings.

2.4.1 Pump Casing


Refer to Figure 2-5.
The MOP casing is a casting made of cast steel (material SC450). It is
made in two halves, the lower half forming the pump casing base (2)
and upper half the pump casing cover (1). The pump casing is
supported from below on the base of the HP pedestal.
The pump casing is formed with integral suction and discharge ports.
The suction and discharge port stubs of the casing base are supported
and secured on matching flanges welded onto the HP pedestal base
using studs (13 and 14) and U-nuts (23).
O-rings (20 and 21) installed in slots machined in the support flanges
provide effective sealing for the flange joints. Accurate location of the
casing base is achieved by the use of a set of parallel pin (18, 34) and
bush (19, 35) in each flange. The bushes are tack-welded to the
flanges and to the parallel pins after installation.
The outlet pipe of No. 1 ejector is welded to the suction port in the HP
pedestal base and the MOP discharge pipe to the discharge port.
The pump casing is divided into three sections, two extreme sections
for the pump suction and the middle section for the pump discharge. Oil
flow across these three sections is minimized during operation by two
impeller oil seal rings (11) installed in slots machined in the pump
casing and operating with a fine impeller clearance.

MM-M05.06

Rev.001

The suction port of the casing base is provided with a splitter


arrangement which splits and supplies suction oil to both suction ends
of the pump casing.
The pump casing is split horizontally so that the casing cover can be
removed to facilitate HP-IP rotor and stub extension shaft (8) assembly
removal. The horizontal joint is assembled face to face (i.e. without a
gasket).
Turbine Main Oil Pump
Mitsubishi

2-6

Chapter 2

General

The two casing halves are located by two taper pins and nuts (16), and
secured by stud bolts (12 and 17) and U-nuts (22 and 24). The stud
bolts are screwed into the casing base and are tightened by the U-nuts
to secure the casing cover. The pump casing is provided with two
starting bolts (15) to facilitate removal of the casing cover during
maintenance.
Air vent plugs (27) are fitted to the casing cover, one on the discharge
section and one on each of the suction sections of the casing, to
release entrapped air.
Threaded blind holes are provided on the casing cover for the
installation of lifting eyebolts for handling purposes.
The pump casing base at the Gov End is provided with an extended
flange for mounting the mechanical overspeed trip (MOST) trigger
assembly.

2.4.2 Impeller and Shaft Assembly


The impeller (3) is made of stainless steel (material SCS1-T1) and is
keyed to the stub extension shaft with a fine clearance fit.
The axial position of the impeller in relation to the pump casing is
determined by a spacer ring (6) positioned between the impeller and a
shoulder on the extension shaft. An impeller nut (4), screwed onto a
thread machined on the extension shaft, secures the impeller. The
impeller nut is locked to the extension shaft in three positions radially at
120 apart by three sets of straight pins (25) and plugs (26).
Two vent holes are provided axially in the impeller hub and the impeller
nut to expel any entrapped air. These vent holes are interconnected by
an internal groove machined in the impeller nut. These vent holes
provide a continuous bleeding of oil/air from the pump suction casing
into the HP pedestal.
Two wear rings (5) are fitted to the impeller shroud, one on each end, to
provide a running surface for the two impeller seal rings (11). The
impeller wear rings are an interference fit on the shrouds and are
secured by grub screws (38).
The pump requires no dedicated bearings, the extension being sized

MM-M05.06

Rev.001

so that no deflection of the extension shaft occurs in normal operation.


The extension shaft is secured to the HP-IP rotor shaft with a flanged
rigid coupling. It is provided with a collar outside the pump casing
between MOP and No. 1 main bearing for locating the main turbine
thrust bearing. An overspeed trip device (33) and a rotor position disc
(7) are also installed on the extension shaft outside the pump casing at
the governor end (Gov End).
Turbine Main Oil Pump
Mitsubishi

2-7

Chapter 2

General

2.4.3 Impeller Seal Rings


The cast bronze impeller seal rings (11) (material LBC4) are
manufactured in halves. The seal ring halves are secured by pins and
locked by caulking.
Each seal ring has a spiral machined on its bore and is sized to a
thickness that allows it to float radially in its slot in the casing halves. A
radial clearance of 3 mm is provided between the top of the seal ring
and the pump casing. This arrangement accommodates the radial shaft
movement required by the clearances in the HP-IP rotor bearing while
maintaining acceptable shaft and impeller sealing.
The spirals machined into the rings fitted to the Gov End are machined
left-hand (LH) and those fitted to the generator end (Gen End) are
machined right-hand (RH). This ensures that, when the shaft rotates,
the spirals tend to wind back the oil to the high pressure discharge
side.

2.4.4 Shaft Penetration Seal Rings


The shaft penetrations are sealed by two shaft penetration seal rings
(10) (material LBC4). The construction of the shaft penetration seal ring
is similar to that of the impeller seal ring.
The floating shaft penetration seal rings are located in slots provided at
each end of the pump casing. Internal spirals tend to wind back the oil
into the suction area of the pump.

MM-M05.06

Rev.001

Since the complete pump is contained in the oil tight environment of the
HP pedestal casing, further sealing is not necessary.

Turbine Main Oil Pump


Mitsubishi

2-8

Chapter 2

ITEM
1
2
3
4
5
6
7
8
9
10
11
12
13

8
13

13

General

DESCRIPTION
PUMP CASING COVER
PUMP CASING BASE
IMPELLER
SLEEVE
WEAR RING
SPACER
ROTOR POSITION INDICATOR DISC
SHAFT
KEY
SHAFT PENETRATION SEAL RIMNG
TRIP OVER SPEED ASS'Y
IMPELLER SEAL RIMNG
AIR VENT PLUG

10

11

6
9
5

12
3

MM-M05.06

Rev.001

FIGURE 2-4
Turbine Main Oil Pump
Mitsubishi

CUTAWAY VIEW OF TURBINE MAIN OIL PUMP

2-9

Chapter 2

25

10

26

27

DETAIL A
A

24 17

27

General

DETAIL B

11
38

3
9
12 22

10
16

15

ITEM
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
33
34
35
38

DESCRIPTION
PUMP CASING COVER
PUMP CASING BASE
IMPELLER
SLEEVE
WEAR RING
SPACER
ROTOR POSITION INDICATOR DISC
SHAFT
KEY
SHAFT PENETRATION SEAL RING
IMPELLER SEAL RING
STUD BOLT
STUD BOLT
STUD BOLT
STARTING BOLT
TAPER PIN
STUD BOLT
PARALLEL PIN
BUSH
"O" RING
"O" RING
U-NUT
U-NUT
U-NUT
STRAIGHT PIN
PLUG
AIR VENT PLUG
SPRING RETAINING DISC
SPRING
SOCKET HEAD BOLT
TRIP OVER SPEED ASS'Y
PARALLEL PIN
BUSH
GRUB SCREW

33

ROTATION

29
CL OF ROTOR

28
OIL

OIL

30
8

2
2

13 23

19 18

10

INLET

23 14
34

11

CL OF PUMP

C
L O
FS

UC
TIO

C
L OF DISCHARGE

INLET

Rev.001

35

MM-M05.06

20

21

A-A

MPTD-3-0197

FIGURE 2-5
Turbine Main Oil Pump
Mitsubishi

SECTIONAL VIEW OF TURBINE MAIN OIL PUMP

2-10

Chapter 3

Specifications

C h a p t er

3 Specifications
TABLE 3-1

TURBINE MAIN OIL PUMP

Subject

Specifications

Equipment Number

03MAV02AP1

Quantity

Location

Enclosed within the HP pedestal at the Gov End of


the HP-IP cylinder

Manufacturer

Mitsubishi Heavy Industries (MHI)

Type

Horizontal, axially split, double suction volute,


centrifugal type, turbine shaft driven

Rotation

Clockwise (viewed from Gov End)

Fluid

Turbine oil ISO VG32

Fluid temperature

15C - 60C

Viscosity

15 - 120 cSt

Specific gravity

0.87 @ 15C

Lubrication

Not required (casing seal rings are lubricated by


the pumped oil)

Capacity

7600 litres/minute

Discharge pressure (at 3000 rpm)

2.35 MPa (g) [24 kg/cm2 (g)]

Suction pressure

0.18 MPa (g) [1.8 kg/cm2 (g)]

Speed

3000 rpm

Weight
37 kg

Casing Cover

193 kg

Casing Base

246 kg

MM-M05.06

Rev.001

Impeller assembly

Turbine Main Oil Pump


Mitsubishi

3-1

Chapter 3

Specifications

Continued from previous page

TABLE 3-1

TURBINE MAIN OIL PUMP

Subject

Specifications

Construction

Impeller diameter

438 mm (OD)

Impeller width

164 mm

No of vanes

Suction bore

204 mm

Discharge bore

152 mm

Bearing

None (overhung shaft)

Shaft coupling

Rigid flange coupling

Shaft seal

Floating ring (split in halves)

Material

Stainless Steel SCS1-T1

Casing

Cast Steel SC450

Impeller nut

Carbon Steel S35C

Impeller wear ring

Carbon Steel S35C

Seal rings

Cast Bronze LBC4

MM-M05.06

Rev.001

Impeller

Turbine Main Oil Pump


Mitsubishi

3-2

Chapter 4

Preventive Maintenance

C h a p t er

4 Preventive Maintenance
Preventive maintenance is carried out to avoid or minimize the possibility of failure or
deterioration of equipment performance. This requires a constant effort from
maintenance staff to ensure that the equipment is available on demand.
There are two categories of preventive maintenance, Routine Maintenance and Annual
Outage Maintenance. Routine maintenance helps to reduce the possibility of outage
and hence the downtime of machinery. Annual outage maintenance is required to
maintain the internal components of the installed equipment.
Though vendor/manufacturers recommendations provide a good basis for the
provision of a preventive maintenance schedule, the frequency and other details should
be updated from time to time based on practical experience and actual feedback
gathered through inspection and normal operation of the equipment/plant.
Consideration of these site related specific issues will make the preventive
maintenance more effective.

4.1

Prerequisites
The necessary prerequisites for the preventive maintenance of the turbine main
oil pump are as follows:

Scheduling is the first activity in the preparation of a preventive


maintenance program, the schedule is to include planning to attend all
operating equipment on a fixed regular basis. Initially, schedules will be
prepared based on vendor/manufacturers generic instructions, the
schedules will, however, be updated (frequency, nature of inspection,
etc.) as site specific data becomes available. Preventive maintenance
is to be co-ordinated with other concerned departments. In the case of
a major scheduled outage, maintenance personnel and other
concerned departments should jointly produce a plan of activities, well
in advance, to decide the inspection activities and other logistics (such
as the availability and supply of required equipment, spare parts, and
tools, etc.). The schedule should clearly identify the critical path.
Priority is to be assigned to specific tasks that also involve parallel
activities to reduce the equipment downtime and to complete the work
within the scheduled time.

MM-M05.06

Rev.001

4.1.1 Scheduling

Turbine Main Oil Pump


Mitsubishi

4-1

Chapter 4

Preventive Maintenance

4.1.2 Departmental Interface/Notification


Departmental communication is essential and interfacing between
departments is to be maintained to avoid any lack of communication
that may arise and adversely affect routine or annual outage
maintenance work. Prior to commencing preventive maintenance all
concerned persons (shift supervisor, operators, etc.) are to be made
aware of the schedule and the nature of the activities that are to take
place. If it becomes clear that there is a problem or a conflict of
interests in the schedule (e.g. the maintenance schedule interferes with
another groups work), this is to be resolved by mutual agreement
between the parties involved.

4.1.3 Isolation of Equipment


It is important that isolations are agreed and valid clearances and work
permits are obtained before any maintenance work is performed. The
isolation boundaries of the particular equipment to be taken under
maintenance are to be clearly identified.
In the case of an electrical isolation the power supply shall be
disconnected and/or the fuses removed. In the case of mechanical
isolation, the valves or other mechanical means of isolation, at the
isolation boundaries are to be closed and if possible locked closed. The
system within the isolation boundaries is to be depressurized.

4.1.4 Safety Precautions


Before the commencement of any maintenance work, the person in
charge of the work site is to perform a risk assessment and method
statement for the safe execution of the job scope activities, described
within the work permit. Risk assessment includes identifying,
recognizing and understanding the potential hazards associated with
the work. The method statement is to illustrate the safe working
practices in accordance with the safety manual and the manufacturers
instruction manual to prevent personal injury and/or equipment
damage.

and also use his own judgment to ensure that the equipment and the
prevailing working conditions are safe. During maintenance work,
every employee should follow the safe working procedures detailed in
the method statement.

MM-M05.06

Rev.001

Prior to the commencement of actual work, the person carrying out the
work is to make a safety check based on the above method statement

Turbine Main Oil Pump


Mitsubishi

4-2

Chapter 4

4.2

Preventive Maintenance

Routine Maintenance
The purpose of routine maintenance is the implementation of the preventive
maintenance program on a day-to-day basis through a planned and correctly
executed inspection. The routine maintenance activities are very important in
that if they are properly carried out, they will enhance equipment reliability. As a
result, good routine maintenance activities may help in cost reduction in the long
run through minimization of equipment downtime.
Cleaning is an important and necessary maintenance activity to prevent the
ingress of foreign material. Other major points are as follows: (Summarized
major routine activities are also shown in Table 4-1).

4.2.1 Preparation
a)

Parts, Tools and Equipment


It is important to prepare the necessary parts, tools and
equipment before commencing actual work. Routine
maintenance generally requires a standard mechanical toolkit,
consumables, cleaning materials etc. Any shortages of these
items will affect the maintenance activity and may delay the
schedule. Personal Protective Equipment (PPE) is necessary for
maintenance staff at all times.
Upon completion of work, all tools and equipment should be
serviced and stored correctly to ensure availability for further use.

b)

Documentation

MM-M05.06

Rev.001

Documentation is an important part of any maintenance duty. All


findings should be noted on a comprehensive log sheet, reporting
all aspects of the equipment observed during the routine
inspection. The data recorded in these documents may be useful
in determining the root cause of equipment failure found during
annual outage/corrective maintenance work. Any abnormalities, if
observed, are to be immediately communicated to the concerned
department/personnel for rectification and are to be detailed in
the report.

Turbine Main Oil Pump


Mitsubishi

4-3

Chapter 4

Preventive Maintenance

4.2.2 Inspection and Maintenance

Beware of any noise inside the turbine enclosure when


inspecting the HP pedestal. There can be invisible superheat
steam leakage which can cause heavy burn injuries. Always
wear gloves.

Extreme care must be taken while inspecting near a hot steam


turbine. Hands and clothing can be burned by contact with the
steam turbine parts. Always wear gloves.

CAUTION
Wear ear protection and gloves when performing inspection
near a running machine.

a)

Piping
The oil piping external to the HP pedestal is to be inspected each
shift for evidence of leakage. Minor leakage of oil can lead to a
fire hazard and severe damage to the plant. Major leakage
reduces the ability of the oil system to meet the demands placed
upon it by the requirements of the main turbine.
Perform rectification of oil leakage with the topmost priority when
leakage is discovered.

b)

Rotating Components and Casing


The noise emanating from the HP pedestal is to be monitored. An

Rev.001

increase in the noise from the HP pedestal may indicate that the
pump rotating components are near failure or that they are
coming into contact with the casing.

MM-M05.06

The turbine is to be shut down for investigation and rectification


as required.

Turbine Main Oil Pump


Mitsubishi

4-4

Chapter 4

c)

Preventive Maintenance

Impeller and Shaft Penetration Seal Rings


The pump is located within the HP pedestal and is not readily
accessible. Hence the checks that may be performed are limited
to monitoring of the suction and discharge pressures. The suction
and discharge pressure indications are to be regularly recorded.
The records are to be reviewed periodically to trend the
performance of the pump.

MM-M05.06

Rev.001

If there is any abnormal reduction in suction and/or discharge


pressure, the pump should be shutdown and inspected for any
blockage or excessive internal clearance. The impeller wear rings,
the impeller seal rings and the shaft penetration seal rings are to
be inspected for excessive wear and replaced if abnormal wear
or excessive clearance is observed.

Turbine Main Oil Pump


Mitsubishi

4-5

Chapter 4

TABLE 4-1

No.

Description

Piping

Major Check Item

Oil Leakage

Check Method

No visible leakage

Preventive Maintenance

ROUTINE MAINTENANCE CHECKLIST

Check Reference

No leakage

(external to the HP
pedestal)

Action to be Taken
(if beyond acceptable limit)

Remarks

Shut down and replace piping gasket


/ O-rings

Rotating
Components

Rubbing

Audible

No abnormality

Shut down turbine and inspect pump


rotating components

Impeller

Wear

Permanent suction
pressure
instrument

Higher than normal


suction pressure
(Normal: 0.18 MPa)

Shut down turbine and inspect


impeller for abnormal wear or damage

Suction pressure
deterioration below
0.18 MPa

Shutdown and inspect No. 1 oil


ejector

Recommended
Maintenance
Frequency

Every Shift

Every Shift

Every Shift

Seal Rings

Wear

Permanent
Delivery pressure
discharge pressure below 2.35 MPa
instrument

Shutdown and inspect internal


clearances

Permanent suction
pressure
instrument

Shut down turbine and inspect shaft


penetration seal rings

Suction pressure
deterioration below
0.18 MPa

Beware of
rotating shaft
during
maintenance

Every Shift

Rev.001

Every Shift

MM-M05.06

Permanent
Delivery pressure
discharge pressure below 2.35 MPa
instrument

Turbine Main Oil Pump


Mitsubishi

Shut down turbine and inspect


impeller seal rings and wear rings

4-6

Chapter 4

4.3

Preventive Maintenance

Annual Outage Maintenance


The purpose of annual outage maintenance is the implementation of a
preventive maintenance program on a yearly basis through a planned and
correctly executed maintenance work program accompanying necessary
inspections. The annual outage maintenance activities are very important in the
sense that if properly undertaken these enhance the life and reliability of the
equipment.
Major activities related to annual outage maintenance are as follows:
(Summarized major activities for annual outage maintenance are also shown in
Table 4-2).

4.3.1 Preparation
a)

Parts, Tools and Equipment


Refer to Subsection 4.2.1 a), Parts, Tools and Equipment.
In addition, it will be necessary to identify and request the
provision of any spare part requirements.
Annual outage will, in certain cases, require the use of material
handling equipment.
Unused spare parts are to be returned for correct storage and
used spare parts are to be replaced.

b)

Documentation
Refer to Subsection 4.2.1 b), Documentation.
Records are to be maintained to record information regarding
spares and consumables used. These records will be used for
future reference and spare parts replacement.
On completion of annual outage maintenance work, the
equipment is to be monitored for correct operation and

MM-M05.06

Rev.001

maintenance data logging. This will help to determine the correct


intervals of preventive maintenance activities to ensure optimum
plant availability. The correct recording of findings during
inspection will build a valuable document for future reference.

Turbine Main Oil Pump


Mitsubishi

4-7

Chapter 4

Preventive Maintenance

4.3.2 Inspection and Maintenance


The turbine has to be shutdown and the turning gear stopped prior to
inspection of the turbine MOP. Normal rundown, cooling and isolation
procedures are to be followed. The lubricating oil system is to remain in
service until the turbine control stage outlet metal temperature is below
180C. Lubricating oil circulation is to be stopped before access to
MOP is permitted. Therefore access to the MOP is not possible until
this degree of cooling has taken place.
It should be noted that there is a manufacturer/vendor statement of
preference to keep the turning gear in operation whenever possible
when the turbine is shut down.
In the event that access to the turbine rotating parts is required quickly
from operating conditions, there are clear procedures that must be
followed.
The procedures for various shutdown situations are provided in
Appendix F, Turning Gear Operation During Shutdown. Operational
personnel will carry out the turbine shutdown with due regard to these
procedures.
Refer to Figure 4-1.

a)

Pump Casing
The pump casing is to be inspected for wear or deterioration that
has occurred during normal operation. Wear or deterioration can
restrict oil flow through the pump by the creation of turbulence.
The pump casing base and the casing cover are to be cleaned
using an approved solvent and lint-free cloth. Perform a visual
examination of each casing half, looking for erosion, pitting,
corrosion or cracks. Corrosion, pitting and cracks can propagate
leading to failure of the casing to contain the pumped oil and
possible destruction of the pump.

Rev.001

Carefully inspect the slots into which the impeller and shaft
penetration seal rings fit looking for fretting or wear. Sticking seal
rings cause unnecessary wear to the impeller wear ring, impeller
nut or shaft, and to the bore of the seal ring.

MM-M05.06

Measure the width of each slot and compare it to the thickness of


the respective seal ring. Replace parts to restore any clearance
that is not within the range specified in the annual outage
maintenance checklist table (Table 4-2).

Turbine Main Oil Pump


Mitsubishi

4-8

Chapter 4

b)

Preventive Maintenance

Impeller and Shaft


Thoroughly clean the impeller and shaft using an approved
solvent and lint-free cloth. Carefully examine the impeller and
shaft for corrosion or wear. Corrosion of the shaft can lead to
cracking and failure in service and lead to destruction of the
pump.
The impeller is to be manually checked for security on the shaft.
A loose impeller will move on the shaft causing considerable
internal damage to the pump. Ensure that the impeller nut is
properly tightened to the specified torque value and the lock pins
and plugs are properly secured.
The impeller is to be inspected for cracks. Minor cracks can
rapidly increase in size during service. Severe cracking leads to
failure of the impeller and destruction of the pump. Repair or
replace the impeller as necessary.
A suitably qualified and experienced person is to perform a
Non-Destructive Examination (NDE) of the impeller using the dye
penetrant method.
The surfaces on the shaft, the impeller nut and the impeller wear
rings upon which the seal rings bear are to be inspected for
scratches or ridges. Minor wear in the form of ridges and
scratches causes accelerated wear to the bore of the casing and
impeller oil seal rings. Minor imperfections are to be reduced or
removed by an oilstone.
Concentricity between the HP-IP rotor shaft and the extension
shaft is to be checked. A deterioration of concentricity will induce
excessive vibration. An extreme deterioration in concentricity will
cause impact between the rotating and stationary components of
the pump.
Any deterioration in concentricity exceeding the acceptable limit
as specified in the outage maintenance checklist table
(Table 4-2) is to be corrected. This correction will require that the
HP-IP rotor shaft to extension shaft coupling position be adjusted.

MM-M05.06

Rev.001

If the impeller has been removed from the extension shaft, a


check for cracks in the area normally concealed by the hub of the
impeller is to be performed. Cracks in the area normally
concealed by the impeller hub can rapidly propagate causing
failure of the extension shaft and destruction of the pump.
A suitably qualified and experienced person is to perform an NDE
of the extension shaft using the dye penetrant method.
Turbine Main Oil Pump
Mitsubishi

4-9

Chapter 4

c)

Preventive Maintenance

Impeller Seal Rings


The impeller seal rings are to be thoroughly cleaned using an
approved solvent and lint-free cloth. Each seal ring is to be
inspected for the formation of wear ridges and overall wear, on its
side faces, that has occurred during normal operation. Wear
ridges restrict the radial movement of the seal ring in the casing
and cause accelerated wear to the impeller wear ring and seal
ring bore. Excessive wear to the side faces of the impeller seal
rings causes leakage between the low pressure suction and high
pressure discharge sections within the pump causing a loss of
efficiency.
The bore of each impeller seal ring is to be inspected for damage
or excessive wear. Each impeller seal ring is to be assembled
and the bore measured. The bore size is to be compared to the
respective impeller wear ring OD (outer diameter). Replace parts
with new to restore any impeller seal ring clearance which is
greater than that specified in the annual outage maintenance
checklist table (Table 4-2).
The thickness of each impeller seal ring is to be measured. The
thickness of each ring is to be compared to the width of its
respective slot in both the pump casing base and the casing
cover. Replace parts with new to restore any clearance which is
greater than that specified in the annual outage maintenance
checklist table (Table 4-2).

d)

Shaft Penetration Seal Rings

Rev.001

The shaft penetration seal rings are to be thoroughly cleaned


using an approved solvent and lint-free cloth. Each ring is to be
inspected for the formation of wear ridges and overall wear, on its
side faces, that has occurred during normal operation. Wear
ridges restrict the radial movement of the seal ring in the casing
and cause accelerated wear to the extension shaft and/or the
impeller nut and the shaft penetration seal ring bore. Excessive
wear to the side faces of the shaft penetration seal rings causes
excessive leakage along the extension shaft causing a loss of
efficiency.

MM-M05.06

Each shaft penetration seal ring is to be reassembled and the


bore measured. The bore size of the Gen End shaft penetration
seal ring is to be compared with the shaft diameter and the bore
size of the Gov End shaft penetration seal ring is to be compared
with the impeller nut on which it runs.
Turbine Main Oil Pump
Mitsubishi

4-10

Chapter 4

Preventive Maintenance

Replace parts with new to restore any shaft penetration seal ring
clearance which is greater than that specified in the annual
outage maintenance checklist table (Table 4-2).

MM-M05.06

Rev.001

The thickness of each shaft penetration seal ring is to be


measured. The thickness of each ring is to be compared to the
width of its respective slot in both the pump casing base and the
casing cover. Replace parts with new to restore any clearance
that is greater that that specified in the annual outage
maintenance checklist table (Table 4-2).

Turbine Main Oil Pump


Mitsubishi

4-11

Chapter 4

TABLE 4-2
No.

Description

Casing

Major Check
Item

Wear, cracks

Check method

Visual

Casing seal
Visual
ring slot wear

Preventive Maintenance

ANNUAL OUTAGE MAINTENANCE CHECKLIST

Check Reference

Action to be Taken
(If beyond acceptable
limit)

Remarks

No visible wear or
cracks

Standard mechanical
casting recovery
methods

Performed by
specialists.

No visible ridges

Remove using
carborundum stone

Performed by
specialist contractors

Inspection Date

Inspector

Results

Remachine slot
2

Impeller

Impeller key

Extension
shaft

Visual

No visible
wear/erosion

NDE (dye
penetrant)

No crack

Visual

No visible
wear/erosion

NDE (dye
penetrant)

No crack

Wear

Visual

No visible wear

Replace extension shaft

Crack

Visual

No crack

Replace extension shaft

Wear, cracks

Wear, cracks

Replace the impeller

Replace the key

MM-M05.06

Rev.001

NDE (if
impeller
removed)
Misalignment Measurement Deterioration in
to HP-IP rotor
concentricity
shaft
between HP-IP
rotor shaft and
extension shaft

Realign extension shaft


to HP-IP rotor shaft

Maximum: 0.05 mm

Turbine Main Oil Pump


Mitsubishi

4-12

Chapter 4

Preventive Maintenance

Continued from previous page

TABLE 4-2
No.

Description

Major Check
Item

Impeller seal Wear/ridging


ring
to side faces

Side face
wear

Check method

Visual

ANNUAL OUTAGE MAINTENANCE CHECKLIST

Check Reference

No wear or ridging

Action to be Taken
(If beyond acceptable limit)

Remarks

Inspection Date

Inspector

Results

Remove using fine file


and re-polish or change
seal ring

Measurement No excessive wear

Change seal ring when


Design clearance of clearance exceeds
seal ring to casing 0.20 mm
slot
0.06 mm 0.12 mm

Bore wear

Measurement No excessive wear

Change seal ring when


Design clearance of clearance exceeds
seal ring to impeller 0.30 mm
wear ring

MM-M05.06

Rev.001

0.14 mm 0.22 mm

Turbine Main Oil Pump


Mitsubishi

4-13

Chapter 4

Preventive Maintenance

Continued from previous page

TABLE 4-2
No.

Description

Shaft
penetration
seal ring

Major Check
Item

Check method

ANNUAL OUTAGE MAINTENANCE CHECKLIST

Check Reference

Wear/ridging
to side faces

Visual

No wear or ridging

Side face
wear

Measurement No excessive wear

Action to be Taken
(If beyond acceptable limit)

Remarks

Inspection Date

Inspector

Results

Remove using fine file and


re-polish or change ring

Change ring when


Design clearance of clearance exceeds
seal ring to casing 0.20 mm
slot
0.06 mm 0.12 mm

Bore wear

Measurement No excessive wear

Change ring when


Design clearance of clearance exceeds
0.30 mm
seal ring to shaft
(Gen End)
0.14 mm 0.22 mm
Design clearance of
seal ring to impeller
nut (Gov End)

MM-M05.06

Rev.001

0.14 mm 0.22 mm

Turbine Main Oil Pump


Mitsubishi

4-14

10.5+1
-

Preventive Maintenance

0.06~0.12

0.06~0.12

MM-M05.06

0.06~0.12
CLEAR.(TOTAL)

0.06~0.12
CLEAR.(TOTAL)

FIGURE 4-1
Turbine Main Oil Pump
Mitsubishi

CLEAR.ON DIA

CLEAR.(TOTAL)

0.14~0.22

CLEAR.ON DIA

Rev.001

0.14~0.22

CLEAR.(TOTAL)

MPTD-3-0198

CLEAR.ON DIA

0.14~0.22

CLEAR.ON DIA

0.14~0.22

3.04

4.5

10.5+1
-

4.5

Chapter 4

TURBINE MAIN OIL PUMP CLEARANCE DRAWING

4-15

Chapter 5

Disassembly and Reassembly

C h a p t er

5 Disassembly and Reassembly


Disassembly and reassembly are the activities to be conducted when internal parts of
the equipment are required to be accessed. An important part of the activities is the
preparatory work. This should identify the manpower, spares and tools that may be
required during the maintenance work. A shortfall of any of these may affect the
schedule and the operational status of the plant. The major steps associated with
disassembly and reassembly are as follows:

5.1

Turbine Main Oil Pump Disassembly and Reassembly

CAUTION
Prior to carrying out any maintenance, confirm all isolations are
in place and the equipment is shut down.

The removal and replacement of the HP-IP rotor falls outside the scope of this
document. Details of the procedure for opening the HP-IP cylinder, and for
rigging and removing the HP-IP rotor are fully explained in the mechanical
maintenance manual No. M-05.01, Main Turbine Maintenance.

a)

Preparation

MM-M05.06

Rev.001

If turbine main oil pump disassembly becomes necessary, all associated


equipment shall be mechanically and electrically isolated and an
authorized clearance and work permit shall be in place prior to the
commencement of work. The following points are also to be considered
when preparing for disassembly and reassembly.

Have all necessary drawings (assembly drawings, sectional drawings,


part details, etc.) and documents (log sheets, field record book, etc.)
ready prior to the start of work.

Prepare the necessary handling facilities to remove and store the


various parts of the equipment.

Co-ordinate with the Instrument and Control (I&C) Department to


remove all the attached instrumentation pick-ups before starting
disassembly work.

Turbine Main Oil Pump


Mitsubishi

5-1

Chapter 5

b)

Disassembly and Reassembly

Disassembly

CAUTION
When separating joints and flanges use jacking bolts and wooden
mallets. Never apply force with hammers, chisels or screwdrivers.

All data is to be recorded during disassembly. During disassembly, make


match marks on adjoining parts for ease of identification during
reassembly. The disassembly procedure is described as follows:

CAUTION

Remove the fasteners securing the front end cover from the HP
pedestal. Jack the cover away using the jack screws and transport it
to the lay-down area.

Remove the horizontal joint bolts securing the top cover of the HP
pedestal. Remove the HP pedestal cover and transport it to the
lay-down area.

Have the turbine instrumentation pickups and their associated


brackets removed in the vicinity of the main oil pump which may
hamper removal of the pump casing cover.

Remove the U-nuts (22) from the studs (12) and the U-nuts (24) from
the studs (17) securing the pump casing cover (1) to the casing base
(2).

Unscrew and remove the nuts from the taper pins (16), which locate
the casing cover to the casing base.

Using the starting bolts (15), separate the pump casing base (2) and
the casing cover (1).

Using the lifting equipment, slowly and carefully lift the pump casing
cover (1) away to the laydown area and cover it with a polythene
sheet.

MM-M05.06

Rev.001

Rigging and transportation of equipment must be carried out by


authorized persons. Care is to be taken where equipment weight
and center of gravity is to be considered. Care is to be taken to
protect machined surfaces.
Refer to Figures 2-5 and 5-1.

Turbine Main Oil Pump


Mitsubishi

5-2

Chapter 5

Disassembly and Reassembly

Note
Ensure that the pump casing cover is positioned so that the
wetted surfaces are available for inspection.

Remove the taper pins (16) from the casing base, if replacement is
essential.

Using a pin punch and small hammer, tap the oil seal ring joining pins
(32) from the shaft penetration seal rings (10) and impeller seal rings
(11) through their caulking. Remove the top half shaft penetration seal
rings and impeller seal rings. Match mark the seal ring halves and
their locations.

10 Match mark, then rotate and remove the bottom half shaft penetration
seal rings and impeller seal rings from the pump casing base.
11 Clean, inspect and refurbish or replace any damaged or worn parts.

Note
For normal annual MOP maintenance requirements
disassembly up to this point should be adequate if
inspections have confirmed that the shaft, impeller and
impeller wear rings are in a satisfactory condition.

CAUTION
Do not disconnect the extension shaft from the HP-IP rotor shaft
without due reason.

c)

Reassembly
The reassembly procedure is carried out in the reverse sequence to that
for disassembly. Install all parts in the same positions they were removed
from, referring to the match marks and checking that the clearances are
maintained as specified.

All contact surfaces are to be cleaned before starting reassembly and all
gaskets are to be replaced.

MM-M05.06

Rev.001

Ensure that all components are free from burrs and bruises, blending
away the defects using fine files, carborundum stones and emery cloth.

Turbine Main Oil Pump


Mitsubishi

5-3

Chapter 5

Disassembly and Reassembly

Refer to Figures 2-5 and 5-1.


1

Taking note of the markings made during disassembly, install the lower
half shaft penetration seal rings (10) and the impeller seal rings (11) in
the pump casing base (2).

Note
If new seals are being installed, those with a RH spiral go to
the Gen End and those with a LH spiral go to the Gov End.

Install the top half shaft penetration seal rings and impeller seal rings
in their respective positions. Fit the joint pins (32) in the seal ring
joints and caulk them in position using a prick punch.

CAUTION
Apply the anti-seize compound to the casing base and cover joint
sparingly, ensuring that none will be squeezed from the joint to
contaminate the oil.
3

Apply anti-seize compound onto the pump casing base (2) and cover
(1) horizontal joint surfaces.

Using lifting equipment, lift the pump casing cover and carefully lower
it into position on the pump casing base.

Install the taper pins (16), if removed during disassembly and locate
the casing cover on the casing base.

Lubricate, fit and tighten the stud bolts (17) if removed during
disassembly, then install and tighten the U-nuts (24).

Lubricate, fit and tighten the casing stud bolts (12), then install and
tighten the U-nuts (22).

Tighten all casing U-nuts (22 and 24) sequentially to the torque value
specified in Appendix A.

Arrange for the instrument pickups removed during disassembly to be


installed.

MM-M05.06

Rev.001

10 Using lifting equipment, lift and position the HP pedestal cover.


11 Fit and tighten the HP pedestal cover securing bolts.
12 Fit a new gasket if required, and lift the HP pedestal front end cover
into position and tighten the front end securing screws.

Turbine Main Oil Pump


Mitsubishi

5-4

Chapter 5

5.2

Disassembly and Reassembly

Impeller Removal and Replacement


Note
The impeller should not be removed from the extension shaft unless
repair or replacement is required.

a)

Preparation
If removal of the impeller from the shaft becomes necessary, all
associated equipment shall be mechanically and electrically isolated and
an authorized clearance and work permit shall be in place prior to work
commencement. The following points shall also be considered while
preparing for disassembly and reassembly:

b)

Have all necessary drawings (assembly drawings, sectional drawings,


part details, etc.) and documents (log sheets, field record book, etc.)
ready prior to start of work.

Prepare the necessary handling facilities (e.g. heating and extraction


equipment).

Removal
Refer to Figures 2-5 and 5-1.

MM-M05.06

Rev.001

With the HP-IP rotor removed from the HP-IP turbine cylinder and
temporarily located on the rotor stand proceed as follows:
1

Remove the holding spring (29) and remove the spring retaining disc
(28) from the rotor end of the extension stub shaft (8).

Remove the rotor position indicator disc (7) by removing the socket
head bolts (30).

Remove the plugs (26) and the straight pins (25) securing the sleeve
(4) to the shaft (8).

Unscrew and remove the sleeve (4).

If the impeller (3) is to be reused, clearly mark the Gov End.


Otherwise, note the impeller vane direction to aid the fitting of a
replacement impeller.

Using properly positioned pulling equipment withdraw the impeller


from the extension shaft (8).

Remove the impeller spacer ring (6) from the extension shaft.

Remove the impeller key (9), if the key requires repair or replacement.

Remove the set screws (38) and then remove the impeller wear rings
(5), if repair or replacement is necessary.

Turbine Main Oil Pump


Mitsubishi

5-5

Chapter 5

c)

d)

Disassembly and Reassembly

Checks Prior to Impeller Replacement (Original or New


Impeller)
1

Using a fine oil stone, fine emery cloth and crocus paper, remove any
ridges, scratches or rust from the section of the shaft where the
impeller is located.

Measure the diameter of the shaft 25 mm from each end at the


location where the impeller is mounted and at three points 120
displaced from each other.

Similarly, measure the bore of the impeller to be fitted.

Calculate the clearance and ensure that it is between 0.015 and


0.025 mm.

Replacement
1

Replace the impeller spacer ring (6) on the extension shaft (8).

Replace the impeller key (9) if removed during disassembly.

Slide the impeller (3) onto the shaft (8) such that the impeller key slot
engages the impeller key and push it until the impeller abuts the
spacer ring (6).

Note
Insertion of the impeller should be performed after ensuring
absolute cleanliness of the shaft. Any sticking debris may prevent
smooth insertion of the impeller and possibly stick on the way. This
will lead to undesirable withdrawal of the impeller and repetition of

MM-M05.06

Rev.001

the whole reassembly procedure.

Fit the sleeve (4) and tighten it to the torque value specified in
Appendix A.

Fit the sleeve-locking straight pins (25) and the plugs (26) and tighten
the plugs.

Install the impeller wear rings (5) in the locations they were removed
from during disassembly and secure them with the set screws (38).

Re-install the rotor position indicator disc (7) and secure it using the
socket head bolts (30).

Replace the spring retaining disc (28) and secure it to the shaft using
the holding spring (29).

Turbine Main Oil Pump


Mitsubishi

5-6

Chapter 5

Disassembly & Reassembly

31
ITE M
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38

27
37
36

15

D E S C R IP TIO N
P U M P C A S IN G C O V E R
P U M P C A S IN G B A S E
IM P E LLER
S LE E VE
W E A R R IN G
SPACER
R O TO R P O S IT IO N IN D IC A TO R D IS C
S H A FT
KEY
S H A FT P E N E T R A TIO N S E A L R IN G
IM P E LLE R S E A L R IN G
S TU D BO LT
S TU D BO LT
S TU D BO LT
S TA R T IN G B O LT
TA P ER PIN
S TU D BO LT
P A R A LLE L P IN
BUSH
"O " R IN G
"O " R IN G
U -N U T
U -N U T
U -N U T
S TR A IG H T P IN
P LU G
A IR V E N T P LU G
S P R IN G R E TA IN IN G D IS C
S P R IN G
S O C K E T H E A D B O LT
LIF TIN G LU G
JO IN IN G P IN
TR IP O V ER S P E E D A SS 'Y
P A R A LLE L P IN
BUSH
IN S TR U M E N T P IC K U P S
P IC K U P H O LD E R
GRUB SCREW

34
38

M P T D -3-0199

MM-M05.06

Rev.001

35

FIGURE 5-1
Turbine Main Oil Pump
Mitsubishi

EXPLODED VIEW OF TURBINE MAIN OIL PUMP


5-7

Chapter 6

Corrective Maintenance

C h a p t er

6 Corrective Maintenance
Corrective maintenance is the repair or replacement work undertaken for sudden failure of
any part or component of the equipment. Though a well-planned preventive maintenance
program tries to minimize the probability of occurrence of sudden failure of equipment,
provision for attending these unscheduled maintenance requirements is to be made.
Corrective maintenance work is to be given priority depending on the seriousness of the
problem faced and the impact on plant operations. The schedule for repair of any
equipment should be carefully planned to keep outage time to a minimum.
During such repair or replacement work, an inspection is to be carefully conducted to
determine why the equipment has failed. Good corrective maintenance requires, not only
the quick restoration of the failed equipment back into service but also demands every
effort to identify and record the root cause of the failure. The inspection results can be of
significant help in exploring the exact reason for the failure. The findings, along with
possible rectification proposals, are to be used as a feedback to update the preventive
maintenance procedures.

6.1

Prerequisites
The necessary prerequisites for the corrective maintenance of the MOP are as
follows:

a)

Scheduling
Unlike preventive maintenance, scheduling activity only starts after failure of
the equipment. Depending on the severity of the problem, the importance of
the service provided by the failed equipment and availability of manpower to
attend to the problem, a contingency schedule is to be prepared to solve the
problem at the earliest opportunity. The schedule should clearly indicate the
critical path activity and assign the priority for different parallel activities.
Finally, once the schedule is agreed, strict adherence to it is to be maintained
to ensure timely completion of the maintenance activity.

b)

Departmental Interface/Notification
Refer to Section 4.1.2, Departmental Interface/Notification.

MM-M05.06

Rev.001

c)

Isolation of Equipment
Refer to Section 4.1.3, Isolation of Equipment.

d)

Safety Precautions
Refer to Section 4.1.4, Safety Precautions.

Turbine Main Oil Pump


Mitsubishi

6-1

Chapter 6

6.2

Corrective Maintenance

Preparation
a)

Parts, Tools and Equipment


Refer to Subsection 4.2.1 a), Parts, Tools and Equipment.

b)

Documentation
Refer to Subsection 4.2.1 b), Documentation.

6.3

Troubleshooting

MM-M05.06

Rev.001

This section provides information about carrying out troubleshooting and servicing
for the turbine MOP, pertaining to mechanical maintenance staff. Tables of faults,
possible causes and remedies have been provided to assist in troubleshooting by
qualified users. If any new kind of problem is encountered which is not listed in the
following table, contact the manufacturer for assistance.

Turbine Main Oil Pump


Mitsubishi

6-2

Chapter 6

TABLE 6-1
Fault
Discharge pressure or
flow is low

Corrective Maintenance

TROUBLESHOOTING TURBINE MAIN OIL PUMP


Possible Cause

Remedy

Impeller worn or damaged

Check impeller and


repair/replace if required

Oil seal rings worn

Check clearance and


replace as required

No. 1 ejector plate is stuck

Overhaul No. 1 ejector

Oil leakage inside HP


pedestal

Shut down turbine and


repair oil leakage

Suction pressure at
start-up is low

Priming is insufficient

Adjust the turning oil pump


supply

Noise is
abnormal/excessive

Cavitation

Perform frequency analysis


and repair/replace
components as required

Internal contact

Investigate and repair

HP-IP rotor/extension shaft


joint loose

Overhaul to correct fault and


rebalance rotor

HP-IP rotor/extension shaft


misalignment

Realign

Internal rubbing between


pump rotary and stationary
components

Check and replace defective


components, and readjust
clearance

MM-M05.06

Rev.001

Vibration is abnormal
or excessive

Turbine Main Oil Pump


Mitsubishi

6-3

Chapter 7

Recommended Lubrication

C h a p t er

7 Recommended Lubrication
Since the turbine MOP is supported by a shaft overhung from the HP-IP rotor, there are no
bearings. The impeller and shaft penetration seal rings are the only wearing surfaces and
these are lubricated by the pumped medium turbine lubricating oil.
Therefore there are no specific recommendations regarding lubrication.

MM-M05.06

Rev.001

For details of the turbine lubricating oil pumped by the main oil pump, refer to the
mechanical maintenance manual No. M-05.08, Turbine Main Oil Tank and Auxiliary Pumps
Maintenance.

Turbine Main Oil Pump


Mitsubishi

7-1

Appendix A

A p p en d i x

A Torque Chart
TABLE A-1
Description
Impeller nut

Bolt Size

Quantity

Special thread

TORQUE CHART
Torque

Remarks

29010% (261~319) kg.m (OR)


284410% N.m (2560 ~ 3128 N.m)
Normal tightening torque

Suction flange nuts


(23)

M20

Discharge flange
nuts(23)

M20

12

32 (29 ~ 35) kg.m (OR)


310 (280 ~ 340) N.m

Casing cover nuts


(22)

M20

17

Casing cover nuts


(24)

M20

Add U-nut
friction to the
above normal
tightening
torque

Note
Perform the following steps in sequence.

Apply anti-seize compound to bolts.

Measure torque required to overcome U-nut friction.

Calculate final torque requirement.

Tighten nuts 20% of the calculated torque in a cross-diagonal sequence.

Following the sequence, tighten the nuts to 80% of calculated torque.

Following the sequence, tighten the nuts to 100% of calculated torque.

MM-M05.06

Rev.001

Turbine Main Oil Pump


Mitsubishi

A-1

Appendix B

Recommended
B Spare Parts

A p p en d i x

OPERATING SPARE PARTS LIST


Item no.

Description

Part No.

Dwg. No.

Oil seal

Mark-A01

TE60E-00003-A

Oil seal

Mark-A02

TE60E-00004-A

Oil seal

Mark-A04

TE60E-00004-B

Oil seal

Mark-A03

TE60E-00003-B

MM-M05.06

Rev.001

Turbine Main Oil Pump


Mitsubishi

B-1

Appendix B

MM-M05.06

Rev.001

SPARE PARTS

FIGURE B-1

Turbine Main Oil Pump


Mitsubishi

SPARE PARTS FOR MAIN OIL PUMP 1/2

B-2

MM-M05.06

Rev.001

Appendix B

FIGURE B-2
Turbine Main Oil Pump
Mitsubishi

SPARE PARTS MAIN OIL PUMP 2/2

B-3

Appendix C

A p p en d i x

C Special Tools

MM-M05.06

Rev.001

The main oil pump is shop-built and supplied as an assembly with the HP-IP turbine rotor shaft.
Therefore, no specific tools are recommended.

Turbine Main Oil Pump


Mitsubishi

C-1

Appendix D

A p p en d i x

D Coupling Alignment

MM-M05.06

Rev.001

The oil pump is shop-built and supplied complete with the HP pedestal. The main oil pump shaft is
an extension of the HP-IP turbine rotor shaft. Therefore, no specific alignment procedure is
applicable to this equipment.

Turbine Main Oil Pump


Mitsubishi

D-1

Appendix E

A p p en d i x

MM-M05.06

Rev.001

E Applicable Vendor Drawings

Turbine Main Oil Pump


Mitsubishi

E-1

MM-M05.06

Rev.001

Appendix E

MPTD-3-0334

FIGURE E-1
Turbine Main Oil Pump
Mitsubishi

TURBINE MAIN OIL PUMP ASSEMBLY (1 OF 2)


E-2

MM-M05.06

Rev.001

Appendix E

MSD-3-0335

Turbine Main Oil Pump


Mitsubishi

FIGURE E-2

TURBINE MAIN OIL PUMP ASSEMBLY (2 OF 2)

E-3

Appendix F

A p p en d i x

F Instruction Manual
Turning Gear Operation During Shutdown
The turbine-generator rotor is driven by turning gear at a nominal speed of 3 rpm.
Following a shutdown, the turbine-generator unit turning gear will engage automatically as soon
as the unit stops rolling. The operator should verify that the turning gear is rolling the turbine. In
order to facilitate restating the unit, it is recommended that it be rolled by the turning gear
throughout the shutdown period. Continuing turning gear operation after the turbine is
comparatively cool, greatly increases the likelihood that eccentricity will be within acceptable
limits for start up by preventing bowing of the rotors if steam should leak into the turbine during
the shutdown period.
Normally the turbine should remain on turning gear following a hot shutdown until the rotors have
cooled to between 150C to 200C.
Maintaining turning gear operation for this duration will prevent a rotor bow and assure the
availability of the turbine for start up without delay.
The rate of heat conduction through the gland ends of the turbine rotors to the journals is low.
The normal oil circulation around the journals is sufficient to keep the journals cool whether the
unit is at rest or on turning gear. If lubricating oil is shut off, the journal temperatures will rise at a
rate depending on the turbine internal temperatures. When there is no oil circulation, a journal
temperature in excess of 135C may cause damage to the bearing Babbitt.
Bearing metal temperatures should be closely monitored during this time and oil circulation
restored if excessive temperatures result.
If the turbine is hot, that is the control stage outlet metal temperature is between 200C to 450C,
and the turbine turning gear motor is not available for some reason, oil system maybe shutdown
for about 2 to 3 hours. By this time the motor problem can be rectified. During this period take
care that the journal bearing metal temperature does not exceed the permissible limits. If the
control stage temperature is less than 200C, the stoppage can be extended to 10 hrs. However,
if the control stage temperature is more than 450C continue the lube oil until the temperature
comes to less than 450C for carrying out any maintenance on the turning gear motor.

MM-M05.06

Rev.001

When it can be arranged without delaying work schedules, the turning gear and the oil circulation
system should be kept in operation for not less than 48 hours after shutdown.
If continuous rolling during shutdown is not practical, the turning gear should be restarted and
remain in operation for a sufficient length of time before admitting steam to the turbine to allow
rotor straightening as determined by stable eccentricity within the limits mentioned in the Chapter
4 in the mechanical maintenance manual M-05.01, Main Turbine Maintenance.

Turbine Main Oil Pump


Mitsubishi

F-1

Appendix F

1.

The turbine is to be dismantled


The turning gear should be kept in operation until the dismantling program requires
that it be stopped. If an emergency necessitates it, the turning gear may be shutdown
immediately, however, it must be recognized that this may subject the rotor to severe
bowing. Lubricating oil circulation must be maintained after shutdown to protect the
bearings against overheating. The minimum circulation period should be 24 hours
after shutdown. During this period, the oil temperature leaving the coolers should be
held between 20C and 35C, if possible.

2.

Shutdown for extensive repair or adjustment


Both the turning gear and the lubricating oil circulation system should be kept in
operation for a minimum of 24 hours. Oil temperature from the cooler should be
maintained between 20C and 35C, if possible. Both the turning gear and the oil
circulation may then be shutdown. When operation is to be resumed, the unit should
be placed on turning gear prior to turning on gland steam and establishing vacuum,
and can be rolled with steam upon attaining stable eccentricity conditions within
acceptable limits.
These recommendations also apply to the situation where rotor bearings are to be
inspected or repaired and it is necessary to shut off oil circulation. Metal temperatures
at all the bearings should be monitored during this period. To avoid overheating the
bearings, restore oil circulation as soon as possible.

Shutdown for minor repair or adjustment


Depending upon the nature of the work to be done, the following schedule may be
adopted:
a) Keep the turning gear and the bearing oil circulation system in operation for a
minimum of 3 hours. Both may then be shut off for a period of not more than 15
minutes. If practical, however, oil circulation should be maintained.
b) Following the 15 minute shutdown period in (a) above, roll the turbine on turning
gear for 2 hours or until stable eccentricity conditions exist, whichever occurs first.
Both turning gear and oil circulation may then be stopped for not more than 30
minutes: however, 15 minutes after stopping, the rotor is to be turned 180 with

MM-M05.06

Rev.001

the turning gear. Oil circulation should be on during the 180 turns to lubricate the
bearings.
c) Following the 30 minutes shutdown period in (b) above, the turbine should again
be rolled on turning gear with oil circulation for 2 hours or until stable eccentricity
conditions exists, whichever occurs first. The system may be shutdown indefinitely,
provided that the rotor is turned 180 at 30 minutes intervals for the next 6 hours.
Oil circulation should be on during the 180 degrees turns to lubricate the bearings.

Turbine Main Oil Pump


Mitsubishi

F-2

Appendix F

Emergency turning gear operation


If for any reason the turbine unit is tripped and the rotor comes to rest, the unit should
be placed on turning gear operation immediately. If turning gear operation is
impossible because of interference between internal rotating and stationary parts due
to thermal shock and consequent distortion, try jogging the turning gear motor after a
one hour interval. If unsuccessful, repeat the attempt after another one hour interval. If
unsuccessful after the second attempt the rotor may be bowed and/or stationary parts
distorted to the extent that one or two days soaking in the arrested condition may be
necessary before making another attempt to break the rotor loose by turning gear
operation.

Under no circumstances should an attempt be made to free the


rotor by admission of steam to the unit or by use of a crane. Such
an attempt could have disastrous results such as increased blade
seal strip clearances, shroud or rotor gouging, broken blades, etc.
If turning gear power is not available and the rotor remains at rest, a rotor bow can be
expected. Experience indicates, however, that a one to two hours period on turning
gear prior to start-up will roll the rotors straight. By turning the rotors 180 degrees in 15
to 20 minutes intervals, the severity of the bow can be reduced and thus reduce the
required turning gear operating time period to start-up. In cases such as a water
incident where both rotor and cylinder might be bowed, cranking must not be
attempted in order to break bound parts loose.
5

Removal of insulation

MM-M05.06

Rev.001

The cylinder insulation should not be removed from the turbine elements until they
have cooled for 24 hours or longer. This delay is necessary to avoid thermally
stressing the cylinders, locally cooling and deforming the cylinders, and exceeding the
allowed differential cooling of the cylinder parts relative to the rotor.

Turbine Main Oil Pump


Mitsubishi

F-3

Вам также может понравиться