Академический Документы
Профессиональный Документы
Культура Документы
EARNED VALUE
IS:
A collection of management practices.
A structured method to:
Establish a Performance Measurement
Baseline
Measure and analyze performance
Scalable to all sizes of projects.
Industry Best
Practices
Government
Requirements
Criterion-based Management
Brief Statements of Attributes
Not How-To
Not a System
Minimum Acceptable Standard
EVM History
In mid-1990s, OMB search for best practices in US
Government led to The Pentagon
Department of Defense cooperative
relationship with industry
Integrated Product Teams
Integrated Baseline Reviews
Reporting processes
EVM Evolution
Key events in transformation from C/S to EVM
Accounting Considerations
6 criteria
Organizational Breakdown
Structure
T
e
s
t
C
o
m
p
a
n
y
E
n
g.
Fan
Fan
Assembly
D
e
s
I
g
n
Mech.
Design
P
l
a
n
Drafting &
Checking
Full Scale
Fan Ring
Case Assy
Rotor Assy
Stator Assy
Control
Account
Control
Account
Control
Account
Control
Account
Analytical
Design
M
f
g.
Compressor
Control
Account
Control
Account
Training
Turbine
Minor Fan
Ring
Control
Account
Control
Account
Control
Account
Control
Account
Accounting Considerations
9 Cost performance measurement at a suitable time
9 Recognized, acceptable costing techniques
? Obligation
? Accrual
? Invoice
9 Rational identification and accountability of all costs
PLANNED VALUE
PLANNED VALUE
$1,200,000
$1,000,000
$1,000,000
$800,000
$600,000
Planned Value
$575,000
$400,000
$200,000
N
ov
Ju
l
Se
p
N
ov
Ja
n
M
ar
M
ay
Ju
l
Se
p
ay
M
ar
M
Ja
n
$0
ACTUAL COST
The dollar amount actually spent to date.
(AC) or Actual Cost of Work Performed (ACWP)
ACTUAL COST
$1,200,000
$1,000,000
$800,000
$600,000
$400,000
$200,000
ct
O
Au
g
Ju
n
Ap
r
Fe
b
D
ec
ct
O
Au
g
Ju
n
Ap
r
Fe
b
$0
EARNED VALUE
EARNED VALUE
$1,200,000
$1,000,000
$800,000
$575K Planned Value
$600,000
$400,000
$475K Earned Value
$200,000
v
No
p
Se
l
Ju
ay
M
ar
M
n
Ja
v
No
p
Se
l
Ju
ay
M
ar
M
Ja
$0
EARNED VALUE
Several ways to Earn value:
9
9
9
9
% Complete
50/50 Rule
20/80 Rule
0/100 Rule
CALCULATING VARIANCES
$1,200,000
$1,000,000
$800,000
$600,000
PV = $575K
EV = $475K
$400,000
$200,000
Ju
l
Se
p
N
ov
Ju
l
Se
p
N
ov
Ja
n
M
ar
M
ay
ay
M
ar
M
Ja
n
$0
EVMS RESULTS
Cost
EAC
(Forecast)
Cost Overrun
BAC
(Total Budget)
ETC
Actual Costs
Schedule
Variance
SPI
Planned Value
(ACWP)
Spending
Variance
(BCWS)
Cost
Variance
CPI
Schedule
Slippage
Earned Value
(BCWP)
Time Now
Time
CALCULATIONS
Cost Variance:
Cost Performance Index:
Schedule Variance:
Schedule Performance Index:
Estimate to Complete:
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
ETC = BAC - EV
Estimate at Completion:
EAC = AC +
BAC - EV
CPI
PERFORANCE METRICS
Cost Performance
Cost Variance (CV)
Difference between earned value and actual cost
CV = BCWP ACWP (+ favorable; - unfavorable)
PERFORANCE METRICS
Schedule Performance
SV - Schedule Variance
Difference between earned value and planned value
SV = BCWP BCWS (+ favorable; - unfavorable)
PERFORANCE METRICS
VAC - Variance At Completion
Difference between the budget at completion and the estimate at
completion
VAC = BAC EAC (+ favorable; - unfavorable)
ESTIMATE AT COMPETION
PLANNED
WORK
$ 3M
$ 1M
$ 1M
EARNED
VALUE
$ 1M
COST OF
WORK
$ 2M
$ 1M
$ 1M
$ 1M
$ 1M
PLANNED
WORK
$ 3M
EARNED
VALUE
$ 1M
COST OF
WORK
$ 2M
SCHEDULE
VARIANCE
COST
VARIANCE
(66% behind)
$ 1M
$ 1M
$ 1M
$ 1M
(100% overrun)
$ 1M
$ 1M
Estimate at Completion:
$8M and 8 months late
Source: May 1997 GAO Report