Вы находитесь на странице: 1из 47

Abdullah Sharrif

0945251

24/11/2010

UNIVERSITY OF EAST
LONDON

Engineering Surveying Field Scheme Bournemouth,


Dorset

CE2202- Engineering Surveying

Written by: Abdullah Sharrif

Student No: 0945251

Module Leader: Peter Lakin


1

Abdullah Sharrif

0945251

24/11/2010

Content
Introduction................................................................................
.............................5
Background..........................................................................................
..........5
Objectives............................................................................................
...........5
Scenario...............................................................................................
...........5
Methodology...............................................................................
..............................7
Task A:
Traverse.............................................................................................7
Task B: Volume
determination........................................................................8
Task C: Setting out
horizontal.........................................................................9
Task D: Setting out
vertical...........................................................................10
Findings......................................................................................
............................11
Introduction.........................................................................................
...........11
Task A:
Traverse...........................................................................................13
Task B: Volume
determination......................................................................16
Task C: Setting out
horizontal.......................................................................20
Task D: Setting out
vertical............................................................................24
2

Abdullah Sharrif

0945251

24/11/2010

Critical analysis of tasks.......................


.............................28
Introduction........................................................................
.........................28
Traverse.............................................................................
..........................29
Problems faced by team
members...............................................29
Precision achieved and if it was acceptable or
not.......................29
If I had to do it again, what I would do
diferently.........................29
An indication of time and budget constraint and how they
afected the
tasks.....................................................................................
.29
How team members adapted to the weather
conditions.............30
Conclusion............................................................................
.......30

Volume
determination.........................................................................
........31
Problems faced by team
members...............................................31
Precision achieved and if it was acceptable or
not.......................31
If I had to do it again, what I would do
diferently.........................31
An indication of time and budget constraint and how they
afected the
tasks.....................................................................................
..31
How team members adapted to the weather
conditions..............32
3

Abdullah Sharrif

0945251

24/11/2010

Conclusion............................................................................
........32
Setting out horizontal...........
..........................................33
Problems faced by team
members...............................................33
Precision achieved and if it was acceptable or
not.......................33
If I had to do it again, what I would do
diferently..........................33
An indication of time and budget constraint and how they
afected the
tasks.....................................................................................
..34
How team members adapted to the weather
conditions..............34
Conclusion............................................................................
........34
Setting out
vertical...............................................................................
......35
Problems faced by team
members..............................................35
Precision achieved and if it was acceptable or
not......................35
If I had to do it again, what I would do
diferently........................35
An indication of time and budget constraint and how they
afected the
tasks.....................................................................................
.35
How team members adapted to the weather
conditions.............36
Conclusion............................................................................
.......36
Overall
conclusion..........................................................................
..........36

Abdullah Sharrif

0945251

24/11/2010

Pictures
Picture
1.......................................................................................6
Picture
2.......................................................................................6
Picture
3.......................................................................................9
Picture
4.....................................................................................11
Picture
5.....................................................................................16
Picture
6......................................................................................21
Picture
7......................................................................................26

Figures
Figure
1.............................................................................................7
Figure
2.............................................................................................8
Figure
3...........................................................................................10
Figure
4...........................................................................................13
Figure
5...........................................................................................18
Figure
6............................................................................................20
.
Figure
7............................................................................................22
Figure
8............................................................................................23
Figure
9............................................................................................24
Figure
10..........................................................................................10
Tables
5

Abdullah Sharrif

0945251

24/11/2010

Table
1.......................................................................................11&1
2
Table
2..............................................................................................
13
Table
3..............................................................................................
14
Table
4..............................................................................................
15
Table
5..............................................................................................
15
Table
6..............................................................................................
17
Table
7..............................................................................................
19
Table
8..............................................................................................
21
Table
9:.............................................................................................
27

Abdullah Sharrif

0945251

24/11/2010

INTRODUCTION:
Background
The purpose of this report is to focus on all aspects of surveying practical
field work that was carried out on the trip to Bournemouth during the five
days there (1st 5th of November 2010). Throughout the five days there all
the instruction were given on Monday and diferent tasks were set from
Tuesday to Friday carrying one task each day whilst noting the result and
calculating pertinent data to check the accuracy and precision of the task.
However the report will also emphasis on diferent aspect for example,
problem within the team, precision achieved and adequacy, practical
problems knowledgeable and how they were dealt with and never the less
weather conditions and time constraint and there efects.
Objectives
Working as part of a group of four students to carry out diferent
Civil Engineering surveying tasks
Ensuring that tasks are carried out to a high standard and limiting
amount of errors and misclosures.
Preparing calculations beforehand and sketching relevant figures
according to the task to be carried out the following day
Scenario
A developer wants to build a new leisure complex overlooking the sea on
the area currently grassed at the top of West Clif, and requires details of
the existing features in order to determine the how much material would
need to be removed in order to achieve a flat base.
The development will also extend onto the beach, where the developer
would like to build luxury beach houses for the clients and needs some
idea of how much space they would take up.
To avoid tidal drift of the sand, there is also the requirement to construct
new breakwaters on the beach at a constant interval between the existing
breakwaters, to protect the new beach houses.
To determine the requirements for the scheme, there are FOUR tasks that
need to be completed, as follows:
TASK
TASK
TASK
TASK

A: TRAVERSE
B: VOLUME DETERMINATION
C: SETTING OUT HORIZONTAL
D: SETTING OUT VERTICAL and LEVELLING

Abdullah Sharrif

0945251

24/11/2010

Picture 1: This is the plan view of the site where all tasks were carried
from.

Abdullah Sharrif

0945251

Picture 2: Welcoming of Bournemouth.

24/11/2010

Abdullah Sharrif

0945251

METHODOLOGY:

10

24/11/2010

Abdullah Sharrif

0945251

Task A: Traverse.

11

24/11/2010

The main aim of this exercise was to set up a control traverse around the
site at the top of west clif. The traverse has four diferent points around
the area given, and each student took three sets of angel at diferent
point. At each station the readings were taken carefully recorded and
making sure the instrument doesnt move or the bubble goes of set.
Finally the traverse was computed including information on partial
coordinates, misclosures, and linear errors and corrected (Bowditch) final
coordinates; however the measured angel had to be within tolerance of
+/-20.
020
32.

33.591

24/11/2010

Figure1: traverse

Task B: Volume Determination.


The main aim of this exercise was to determine the amount of soil needed
to be excavated at the area allocated as well as the volumes of soil
involved in grading the site
Before the task was carried out each and everyone in the team had to
sketch the area given and to determine the best suitable point to set up
the instrument were all the area can be best seen (visibility of whole
area) without distraction of trees and in our case (the beach house) that
was on the side of our working area. Square grids of 10X10 were set all
across the area using tape and flags to mark the points. Unequal areas
were then measured using ofsets and calculated separately at the end.
Each student then was able to take the readings and record data of
diferent points of height using the instrument (total station).

12

58.667

89
.05
0945251

Abdullah Sharrif

Abdullah Sharrif

0945251

24/11/2010

Figure2: Volume determination

Task C: Setting out horizontal.


The main aim of this exercise was to set out a beach house with bay
window overlooking the sea.
Time consuming was critical for this task hence why the instruction was
given to all students beforehand and required to do all the calculation and
sketch before arriving on site. After arriving on site before taken the
instruments had to be checked and insure all the equipment was doubled
checked as the area we were to undertake the task was far from where
the van is (where we collect equipment). The instrument was then set in
the middle of out point, then 3m ofset to the promenade was made and
point W1 is where the total station was set using the co-ordinates of
easting and northing to be 0.00. The line parallel to the promenade was
13

Abdullah Sharrif

0945251

24/11/2010

given a bearing of 2700 and to get the points of the beach house the total
station was used using the results already calculated beforehand.
Deflection angles and distances along the curve of the 2m intervals were
set using the total station and the tape measure. Base line at each point
and diagonals lines were also measured using total station. After
completing the task the group members checked each point to double
check the accuracy before calling a supervisor to measure and checked
its all correct.

Picture 3: Setting out horizontal


Task D: Setting out vertical.
The aim of this exercise was to set out a new breakwater line along the
beach. A perpendicular line was set up from the promenade, the ranging
rods were then placed 5m intervals from the promenade using Pythagoras
theorem.

14

Abdullah Sharrif

0945251

24/11/2010

15m
10m

5m

10m

5m

Figure 3: Setting out Vertical

After setting out the first three rods using Pythagoras theorem the other
two rods were then measured by tape from the 3rd one at 5m intervals
15

Abdullah Sharrif

0945251

24/11/2010

making sure there lining up with the rest. The group members were then
able to take the heights from benchmark to the point of start at the
promenade, transferred taking height of ranging rods as intermediate
sights. Knowing the gradient of 80 the height at 5m intervals was then
calculated and plotted using sliders to attach to the roads. After the
setting out on the beach exercise finished and checked by supervisor the
group members were then able to pack some equipment away and
worked our way up on to the zigzag way to take reading to the GPS point
which was set at the top of the west clif.

Picture 4: Setting out the ranging rods.

FINDINGS
Introduction
All the results collected throughout the four days of the task (traverse,
volume determination, setting out horizontal and vertical) are shown
below with aid of sketch and explanation.

16

Abdullah Sharrif
POIN
T

A1

A2

A3

D1

D2

D3

C1

C2

C3

B1

0945251

FACE
LEFT

FACE
RIGHT

00 51
15
34 31
00

180 51
05
214 30
55

00 22
50
34 02
35

180 22
45
214 02
25

00 23
35
34 03
30

180 23
40
214 03
30

00 30
50
195 53
50

180 30
25
15 53
20

00 13
00
195 36
05

180 13
20

00 21
25
195 44
35

180 21
45

00 22
40
84 28
25

180 22
25
264 28
15

00 13
05
84 19
05

180 13
00
264 18
55

00 08
35
84 14
40

180 08
30
264 14
25

00 28
20

180 28
05

15 35 45

15 44 15

24/11/2010

AVERAGE

REDUCED

00 51 10

00 00 00

34 30 58

33 39 48

00 22 48

00 00 00

34 02 30

33 39 42

00 23 38

00 00 00

34 03 30

33 39 52

00 30 38
195 53
35

00 00 00

00 13 10
195 35
55

00 00 00

00 21 35
195 44
25

00 00 00

00 22 33

00 00 00

84 28 20

84 05 47

00 13 03

00 00 00

84 19 00

84 05 57

00 08 33

00 00 00

84 14 33

84 06 00

00 28 13

00 00 00

17

MEAN

33 39 48

195 22 57

195 22 51

195 22 45

195 22 50

84 05 55

Abdullah Sharrif

B2

B3

0945251

24/11/2010

47 20
15

227 20
15

47 20 15

46 52 02

00 19
00
47 11
00

180 18
50
227 11
10

00 18 55

00 00 00

47 11 05

46 52 10

00 20
20
47 12
20

180 20
05
227 12
15

00 20 13

00 00 00

47 12 18

46 52 05

46 52 06

''
36'09

131

11
6

13'
18'
'

4
5
3

296

1
3
'18
''

Task A: Traverse.
05
2'

Figure 4: TRAVERSE CALCULATION BEARINGS.


Line

Forward
bearing

Reverse
bearing

26234'11''

8234'11''

''
5
0
2'

''

4
5
Internal
21 angle

AB

3339'47''

18

26
2

3
4'1

1''

33.591

3
311

'
6'09'

Table 1: Results for traverse

Abdullah Sharrif

0945251

24/11/2010

BC
3542'05''

21542'05''

4652'06''

13136'09''

31136'09''

8405'56''

11613'18''

29613'18''

19522'51''

CD

DA

36000'40''

Table 2: Bearings readings


To calculate different in easting and different in northing the formula used
are
E=dsin
and
Line

AND

N =dcos

Hence computing

:
Bearing

AB

Distance

89.051

- 88.3032

- 11.5160

58.667

34.2358

47.6417

32.02

23.9436

- 21.2600

33.591

30.1342

-14.8420

213.329

0.0104

0.0237

26234'11''

BC
3542'05''

CD
13136'09''

DA
11613'18''

Table 3: Easting and Northing


19

Abdullah Sharrif

0945251

24/11/2010

After, the next stage was computing of the Bowditch adjustment using the
following formula below.
Eadj= Emisc

side lengt h
total perimet er

Nadj= Nmisc

side lengt h
total perimeter

Bowditch adjustment for A-B


Eadj=0.0104

Nadj=0.0237

89.051
=0.004
213.329

89.051
=0.01
213.329

Bowditch adjustment for B-C


Eadj=0.0104

Nadj=0.0237

58.667
=0.002
213.329

89.051
=0.007
213.329

Bowditch adjustment for C-D


Eadj=0.0104

Nadj=0.0237

32.02
=0.001
213.329

32.02
=0.004
213.329

Bowditch adjustment for D-A

20

Abdullah Sharrif

0945251

Eadj=0.0104

Nadj=0.0237

LINE

33.591
=0.001
213.329

33.591
=0.004
213.329

Adjustme
nt

Adjustme
nt
E

- 0.004

- 88.3072

BC
CD

88.3032
34.2358
23.9436

- 0.002
- 0.001

34.2338
23.9426

DA

30.1342

- 0.001

30.1332

AB

24/11/2010

11.5160
47.6417
21.2600
14.8420

Adjustme
nt

Adjustme
nt
N

- 0.01

- 11.526

- 0.007
- 0.004

47.6347
- 21.264

- 0.004

- 14.846

0.0002

-0.001

Table 4: Adjustment
Hence the final easting and northing are as follow:
LINE

Adjustment
E

Final Easting
(1000)

Adjustment
N

AB
BC
CD
DA

- 88.3072
34.2338
23.9426
30.1332

911.6928
945.9266
969.8692
1000.002

- 11.526
47.6347
- 21.264
- 14.846

Final
Northing
(2000)
1988.474
2036.1087
2014.8447
1999.9987

Table 5: Final Easting and Northing


In the end the final linear misclosure was calculated using the formula
listed below.
mE2 + mN2

(0.0104)2 + (0.0237)2 =

And for the fractional misclosure:


F.M =

213.329
0.0255

= 8236 i.e. 1: 8236


21

0.0259

Abdullah Sharrif

0945251

24/11/2010

Picture 5: Prism set up


Task B: Volume determination
To be able to remove soil in any land the volume of the land has to be
taken into account hence why we done this task to show that this is done
in everyday work force in order to have a flat land for a building or any
type of structure to be built on. As the land was not flat and had little hills
of ups and downs the better way for these problems, in this case this
exercise shows how to deal with such a condition.
22

Abdullah Sharrif

Points
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
24
25
26
27
28
29
30
31
32
33

Horizontal
angle
0000'00''
0000'00''
0000'00''
0000'00''
18001'20''
18000'58''
18000'30''
1851'27''
2831'20''
3738'40''
34351'20''
33656'45''
32155'44''
28254'28''
23104'07''
33200'38''
32337'50''
31615'55''
33901'30''
30205'28''
28807'25''
28454'20''
22001'33''
21310'10''
19151'30''
18156'45''
4854'50''
17051'28''
16601'20''
5854'50''
16051'28''
16151'38''

0945251

Distance(m
)
32.412
30.098
19.453
09.955
09.879
19.967
29.566
27.932
19.217
30.865
34.678
23.768
15.672
09.876
12.456
41.876
33.565
25.781
19.875
49.881
44.343
34,800
24.540
19.880
17.885
16.200
22.907
31,879
12.098
24.667
15.089
18.189

Height(
m)
-0.133
-0.123
-0.112
-0.013
-0.223
-0.076
0.167
0.057
-0.044
-0.350
0.434
0.151
0.127
-0.006
-0.023
0.756
0.524
0.216
0.387
1.299
1.250
0.734
0.535
0.167
0.298
-0.134
-0.116
-0.167
-0.403
-0.532
-0.881
-0.781

24/11/2010

Total
Height(m)
0.403
0.393
0.382
0.283
0.493
0.346
0.103
0.213
0.314
0.620
-0.164
0.119
0.143
0.276
0.293
-0.486
-0.254
0.054
-0.117
-1.029
-0.98
-0.464
-0.265
0.103
-0.028
0.404
0.386
0.437
-0.673
0.802
1.151
1.051

Table 6: Volume determination (angle, distance and height)

23

Abdullah Sharrif

0945251

24/11/2010

Figure 5: Volume area


Known that:
The height of prism = 1.2m
The height of total station = 1.47
.;. The total height can be sound using the formula:
Total height = Height of Instrument Height at point Height of prism.
To be able to find the area for each square grid of 10x10 point of each
corner had to be taken into consideration to add them up then divided by
the number in the grin in this case four to get the average height.
(FFl AH) x section area
Where FFL = finished floor level
AH = average height
24

Abdullah Sharrif

Section

A1
B1
B2
B3
C1
C2
C3
C4
C5
D1
D2
D3
D4
D5
D6
E1
E2
E3
E4
E5
E6
F1
F2
F3

0945251

Average
height
(m)
-1.12
0.259
0.208
0.101
0.155
-0.060
-0.058
-0.164
0.292
0.308
-0.071
-0.546
-0.262
0.144
0.443
0.598
0.184
-0.552
-0.3
0.156
0.322
0.244
0.116
-0.364

24/11/2010

FFL AH(m)
FFFL = 0.645

Area(m2)

Volume(m3)
(FFL-AH)xArea

1.765
0.386
0.437
0.544
0.490
0.705
0.703
0.809
0.353
0.337
0.716
1.191
0.907
0.501
0.202
0.047
0.461
1.197
0.945
0.489
0.323
0.401
0.529
1.009

67.5
100
93.75
37.5
100
100
100
75
18.75
100
100
100
100
96.5
54
100
100
100
92.5
52.5
23.625
87.5
60
22.5
TOTAL VOLUME

119.138
38.600
40.969
20.400
49.000
70.500
70.300
60.675
6.619
33.700
71.600
119.100
90.700
48.347
10.908
4.700
46.100
119.700
87.413
25.673
7.631
35.088
31.740
22.703
1231.304

Table 7: Final volume determination

25

Abdullah Sharrif

0945251

24/11/2010

Task C: Setting out Horizontal

Figure 6: Setting out horizontal


To calculate the chord length the formula
Given that: 4.53 + 4.53 + 10 = 19.06m
.;. 19.06 = 2 R sin 2 where R = 16m
19.06 = 2 (16) sin 2
19.06 = 32 sin 2
0.5956 = sin 2
Sin-1 (0.5956) = 2
3633'26'' = 2
= 7306'52''

26

2 R sin

was used.

Abdullah Sharrif

0945251

Known the length of the Arc:

Arc lengt h= R

24/11/2010

180

16 73.114
=20.417 m
180

Arc length = 20.417m

Chainage (l)

deflection ()
206265l /2 R
=
3600

TP1
0
2
334'52''
4
709'43''
6
1044'35''
8
1419'26''
10
1754'18''
12
2129'09''
14
2504'01''
16
2838'53''
18
3213'44''
20
3548'36''
20.42
3633'44''
Table 8: Angles of deflection

S
S=

0
3258'34''
2923'43''
2548'51''
2214'00''
1839'08''
1504'17''
1129'25''
754'33''
419'42''
0044'50''
0000'02''

27

Abdullah Sharrif

0945251

Picture 6: Instrument set up

28

24/11/2010

Abdullah Sharrif

0945251

24/11/2010

.63
21

21.63

10m

3m

29

PRO

Abdullah Sharrif

0945251

24/11/2010

Figure 7: Beach house set up


Pythagoras theorem and basic trigonometry were used to calculate the
length and the angle of this shape given.
1 = 5544'37''

3 = 0711'05''

2 = 6049'56''

4 = 0952'22''

As mentioned above the calculation for this task was done in advance
before undertaken the practical, from the result gathered was then enable
to set out the beach house, this was simply done by inputting the values
in the total station and using the prism to illuminate the exact point were
the total station was showing. After all the setting out was complete and
ready to be observed by the supervisor, all of the length, width and
diagonals were then double checked and recorded by the supervisor. The
values recorded by the team members were as followed:

30

Abdullah Sharrif

0945251

31

24/11/2010

Abdullah Sharrif

0945251

19.10m

.62
21

21.62

.14
14

32

24/11/2010

Abdullah Sharrif

0945251

24/11/2010

Figure 8: beach house distances


Task D: Setting out vertical
As the aim of the task was to set out new break water along the beach
10m
values taken were used to determine the slope of the promenade to the
beach shore line hence calculating the gradient of the slope into which the
break water will be placed along the beach.

Figure 9: Ranging rod gradient

2.769

2.827

2.293

2.497

2.073

PROMENA

5m

0.703

5m

1.405

Using the formula (Distance x tan

5m

2.108

5m

5 tan ( 8 = 0.703
10 tan ( 8 = 1.405
15 tan ( 8 = 2.108

20 tan ( 8

5m

in our case =8 ) enabled to work

out each poles position where the slider was attached to

2.811

= 2.811

33

Abdullah Sharrif

0945251

24/11/2010

Finding the height diference between ranging rods was calculated as


followed:

2.827
2.769
2.497
2.293

2.769
2.497
2.293
2.073

=
=
=
=

0.058
0.272
0.204
0.22

To find the height of the slider on the ranging rod was simply done
by the height of gradient which is 80 is subtracted with the height
diference of the rod
0.703
1.405
2.108
2.811

0.058 = 0.645
0.272 = 1.133
0.204 = 1.903
0.22 = 2.591

Figure 10: Slider positioned


The 1st rod near to the promenade could not be fitted with the slider
simply because the rod length itself which was around 2m 2.5m,

2.769

2.827

5m

0.703

2.293

2.497

5m

1.405
34

5m

2.108

2.073

5m

2.811

5m

Abdullah Sharrif

0945251

24/11/2010

the more you push the rod onto the sand the lesser the value you
end up with as a remain. The value 2.591m represent the gradient
which is over the maximum size for the rod hence it could not be
put on. After the completion on the task the exercise was then had
to be carried on and at each rough point the readings of back site,
fore site and intermediate had to be recorded all the way up the
zigzag until where the point of GPS was located.

Picture 7: Taking Vertical readings

The results are shown as follow:

35

Abdullah Sharrif

BS
0.998
1.654
1.545
1.551
1.554
1.671
1.558

0945251

IS

FS

Rise

1.740
1.620
1.529
1.541
1.619
1.669

Fall
0.742

0.034
0.016
0.01
0.065
0.002

2.037
2.293
2.497
2.769
2.827
1.591
1.739
3.175
3.710
4.568
3.159
3.319
2.334
4.899
4.389
2.034
1.944

24/11/2010

0.515
0.22
0.204
0.272
0.058
1.462
1.120
0.329
0.074
0.414
0.105
0.091
0.252
0.247
0.677
0.793
1.403
1.014
=

1.365
0.471
1.410
3.101
3.296
4.463
3.068
3.067
2.087
4.222
3.596
0.631
0.93
=

47.392
17.699
Table 9: Results for levelling

31.769

=
2.076

Checks:
Bs

Fs = 47.392 17.699 = 29.693

RF= 31.769-2.076 = 29.693

Observed end known start 33.613 3.920 = 29.693


Known end known start = 29.63
Misclosure = 29.693 29.63 = 0.063
CRITICAL ANALYSIS OF TASKS
36

RL
3.920
3.178
3.212
3.228
3.238
3.173
3.175
2.66
2.44
2.236
1.964
1.906
4.906
5.377
6.787
9.888
11.549
16.032
19.1
22.167
24.254
28.476
32.072
32.703
33.613
33.55

Remarks
BM
CP1
CP2
CP3
CP4
CP5
CP6
CP7
CP8
CP9
CP10
CP11
CP12
CP13
CP14
CP15
CP16
CP17
CP18
CP19
CP20
CP21
CP22
CP23
CP24
BM

Abdullah Sharrif

0945251

24/11/2010

Introduction
Critical analysis of task will cover all diferent tasks that was carried out in
Bournemouth, and in detailed few points will be elaborated in more
details.
Problems within the team
The precision achieved and if it was acceptable or not
Any technical problems faced and how they were overcame
Given an opportunity to do the tasks again, how diferently would
they be done
An indication of time and budget constraint and how they afected
the tasks
How team members adapted to the weather conditions
Conclusion: what i have learnt from the task, including how i see
myself using them in the future.

Picture 8: Beautiful view of the beach


Task a: Traverse
37

Abdullah Sharrif

0945251

24/11/2010

This task was one of the best task that we all liked as every group
member had to take readings at one point and been observed by the
supervisor, this task went really well and we got there and got on with it
with no problem however, the diference in angle was 40 which was very
good as it was within the acceptable tolerance.
Problems faced by team members
From my opinion, this task went really well all the team member
contributed with the work fairly and we all got on really well, at start the
group was going bit slow but it eventually speeded the process up and
were then able to get on and finish the task with no problem.

Precision achieved and if it was acceptable or not:


The angle diference achieved at the end of the task was 40 which was
acceptable; however the misclosure was a bit more than expected this
was simply because of the clear vision due to the presence of the beach
shed (sitting area) and the trees as we was given one of the hard area to
work on. Cautious had to be taken into consideration while setting up the
total station due to the fact that the ground was not flat and also when
holding the prism, to ensure clear visibility whilst taking the readings
however some of error accrued when the reading was taken and it was
blurry vision due to the weather condition.
If I had to do it again, what I would do diferently:
If I had the opportunity to do the tasks again I would make sure I have
printed of all the relevant notes to take with me and i would also make
sure I revise and go through the task the day before i carried out the task,
I would also print all the calculation sheets that are required to take the
results in this will reduce the error of miss writing the numbers. Another
thing that I would do is not to stay with friends up all night and talk but to
try and have early sleep which will defiantly help me to be more awake
and concentrate more and also to have breakfast before coming to site.
An indication of time and budget constraint and how they
afected the tasks
Luck of preparation has afected the start of the task and also not having
the right sheet to record our result in meaning when the group got there
first thing we did was to sketch and made a table up using line paper,
38

Abdullah Sharrif

0945251

24/11/2010

however debating and talking was also one of the things helped to waste
time instead of getting on with the task and do it.

How team members adapted to the weather conditions


The group adapted to the weather quite well as all group member had
warm clothes to wear for example, gloves, hats, jumpers and even water
proof jackets and high visibility jackets as required at all times.
Conclusion
Overall the task went really well everyone put efort into it and wanted to
get the task over and done with but as accurate as possible, this task
teaches us how to set up instrument when wanting to undertake a task or
a project as angle and distance are vital information to have before
starting any construction. This exercise given to us is very useful in the
future time as we graduate and hope to get a job we can end up in any
construction company which are involve in surveying and knowing this
now can really help when it comes to real outside world i.e. work as this
task was carried out will be nearly enough the same as the one the
employer would ask you to do. I have really enjoyed traverse and I can
also see myself doing surveying as a career.

39

Abdullah Sharrif

0945251

24/11/2010

Task B: Volume determination:


This task was definitely the most challenging task for our group, as the
arear given was a complex type and objects blocking the view it was very
difficult to get clear of the whole view of the land.
Problems faced by team members
Having no knowledge of the task undertaken the group members have
struggled to set this task for the first hour or so, however as it was the
first time for group members to use the instrument this also took time in
start taking our readings, at one point the instrument did not pick up any
signal at all until the supervisor came to check it out and also gathered to
know that there was a faulty with the instrument hence why another
instrument was provided.
Precision achieved and if it was acceptable or not:
As this task did not have a limit tolerance set by the lecturer the volume
had to be compared by other group member who work on the same spot
in our case the green point to whether or not the volume at the end of
calculation were near enough the same or not, in this case as the result
were compared the result were nearly the same with other group which
indicated that it was correct.
If I had to do it again, what I would do diferently:
Given an opportunity to do the task again, the team have to be more
prepared and to also come on time, the total station would be one thing
that the team should check to see if any faults can be picked up, less
talking and more working and concentration would probably the best
solution to get on with the task.
An indication of time and budget constraint and how they
afected the tasks

40

Abdullah Sharrif

0945251

24/11/2010

The total station had a big impact on the task and really postponed the
completion of the task having weak signal and not able to pick up any
signal at all after setting up the total station it had then have to be
removed and placed it with a diferent one which then it also had to be
sated up second time. However, the weather also delayed the group
progress as it was windy and showers

How team members adapted to the weather conditions


The group adapted to the weather quite well as all group member had
warm clothes to wear for example, gloves, hats, jumpers and even water
proof jackets and high visibility jackets as required at all time as it was so
windy and showers of rain.
Conclusion
As last year student done assignment for construction method and one of
the criteria was to explain about excavation, when did the assignment it
did not really go to my head completely, but as i have done the practical
side this really gave me a big knowledge of how this process works, as
now understanding of filling and excavation is a bigger knowledge it can
also be applied to a work environment.

41

Abdullah Sharrif

0945251

24/11/2010

Task C: Setting out horizontal


This task didnt really go the way the group wanted it to go, even though
the calculation and sketch was done before hand few problems accrued
during the task.
Problems faced by team members
Problem within the team has coursed a major difficulty as a group work
and efected some task that was carried out, few points that shows this is
the case were:
Some group members were always turning up late therefore we
start late and finish late.
Some group members were not putting efort into the work leaving
few people to do the work instead of all as a group.
Some group members were on the phone or talking to friends during
the task.
Arguments during tasks which lead to time wasting.
Weather condition was also a major part to the group as it increases
the result error by significant amount.
Precision achieved and if it was acceptable or not:
From looking at the result done in advance and note down on the paper,
and comparing it with the task done at the practical side we can see that
the results are exactly the same therefore the results achieved in this task
was well done, on other hand the curve accuracy was definitely within the
satisfactory boundary thus the task went well.
If I had to do it again, what I would do diferently:

42

Abdullah Sharrif

0945251

24/11/2010

If the task was given again I would go over the lecture notes over and
over again until I was 100% sure of what to expect and if theres any
chance of error occurring how I would coupe with it. Doing the calculation
more once also builds up my confidence of doing any task so I would do
the calculation twice. Doing this task with less wind will definitely reduce
error from happening. Also taking more care and time with doing the work
will help achieve more accurate result. I would strongly recommend for
anyone to have some sort of glasses to stop sand blowing in their eyes
this has gave me a major problem as it was windy and sand flies
everywhere.

An indication of time and budget constraint and how they


afected the tasks
The total station had bit of a problem picking up signal from the prism it
read weak signal this was due to the bad weather condition, IF the
student were provided with weather proof equipment such as the total
station this will speed up setting out and also give very accurate reading,
however the cost of weather proof instruments are taken into
consideration hence we dont have them at university.
How team members adapted to the weather conditions
The group adapted to the weather quite well as all group member had
warm clothes to wear for example, gloves, hats, jumpers and even water
proof jackets and high visibility jackets as required at all time as it was so
windy at the beach. This teaches us on what to expect while working for a
company and to get the job done no matter the weather condition and to
make sure there is no excuse for result error, as elaborated no check no
cheque
Conclusion
Overall the task went well everyone in the group member ended up in
putting the efort in to avoid big error, time was tackled really well as the
calculation was done the day before, however the result werent as we
wanted them to be this was due to a very windy day this had impact in
overall result. This task has really gave the taste of how its like to set up
the beach house or even any other structure possible as it would be same
procedure, communication with neighbour group and borrowing
equipment such as tape measure has really helped in getting the work
43

Abdullah Sharrif

0945251

24/11/2010

done quickly and efectively. There is defiantly a big lesson learnt from this
task in many diferent ways. This task will come in hand in many diferent
construction engineering such as tunnelling and highways.

Task D: Setting out vertical


The final task that the group undertake was the setting out vertical, this
task was very skilful and handy to know, and Pythagoras theorem was
used to determine the distance and the straightness of the break water,
this was very critical to get it as straight as possible.
Problems faced by team members
As always team member turning up late was one of the problems with
getting the task started on time, but once the task began all team
member were motivated and started to enjoy taking reading, the problem
that stressed the team the most was the wind as by taking the result from
the zigzag the staf had to be opened all the way reaching about 5m,
when it was all extended the staf kept moving, hence we had to rock it
backs and forwards and take the lowest reading. However, after all the
team worked extremely hard with great enthusiasm
Precision achieved and if it was acceptable or not:
Final misclosure was 63mm this was not within the tolerance required,
however due to lack of time and very strong windy condition we were
advice by the lecturer and were explained the reason for how it might
have been slightly of, taking into consideration the GPS finish point was
itself an error of 3to4mm out.

44

Abdullah Sharrif

0945251

24/11/2010

If I had to do it again, what I would do diferently:


If the opportunity was there to have another chance of doing the task I
would defiantly make sure that the task was started on time with much
knowledge about the task, holding the staf at exactly 90degree is very
critical in this case as every error obtained in one reading adds on and this
builds up to a bigger error of misclosure. Another thing that I would
definitely do is using change plate all the way through as I think this will
reduce the error.
An indication of time and budget constraint and how they
afected the tasks
Weather condition had a really big direct impact in our task, the wind was
very strong and blew the staf side to side so therefore at some point the
team had to wait a bit for wind to reduce its pressure and carried on in
taking the readings.

How team members adapted to the weather conditions


The group adapted to the weather quite well as all group member had
warm clothes to wear for example, gloves, hats, jumpers and even water
proof jackets and high visibility jackets as required at all time as it was so
windy at the beach and throughout the zigzag pathway.
Conclusion
Overall the task went really well, the skilled learn from this task was very
helpful to use in university practical classes and even in the real world of
work. This exercise can be related when setting out drainage systems
which use the same process of finding the gradient.

Overall Conclusion:
Everyday practical classes for surveying are done at the university site,
the areas where the task are carried out are not significant and having the
building surroundings the weather is not as strong as an open field thus
why not enough knowledge is gain, nevertheless the Bournemouth
45

Abdullah Sharrif

0945251

24/11/2010

surveying field trip has really teaches and show each and everyone how it
feels to work in real life work. All four task that were taken by student
were really useful skills to have in the future not only did it teach student
surveying but it also teach us so many diferent aspects such as; Working
in a team, communication skill, time management, leadership skill and
many more. This trip will be recommended to any student studying
engineering

46

Abdullah Sharrif

0945251

47

24/11/2010

Вам также может понравиться