Question: 1
What is the implication of having a direct link between a defect and a test?
A. The defect is directly linked to the related Test Run.
B. The defect is indirectly linked to the related Requirement.
C. The defect is indirectly linked to the related Test Set.
D. The defect is directly linked to the related Test Instance.
Answer: B
Question: 2
What are the potential subsequent states of a "Fixed" defect? (Select two.)
A. Closed
B. Reopened
C. Complete
D. New
E. Reviewed
Answer: A, B
Question: 3
By default, what does HP Application Lifecycle Management assign when a new defect is
created? (Select two.)
A. A unique defect id
B. The status created
C. A version number
D. The status new
E. A unique test set
Answer: A, D
Question: 4
Which options can be used to submit defects from HP Sprinter to HP Application Lifecycle
Management? (Select two.)
A. Smart Identification
B. Defect Checking
C. Smart Defects
D. Smart Defects Identification
E. Defect Reminder
Answer: C, E
Question: 5
Which annotation tools can be used to detect a defect during an HP Sprinter test run? (Select
two.)
A. Ruler tool
B. Step tool
C. Click tool
D. Guides tool
E. Align tool
Page 2 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Answer: A, D
Question: 6
Which tool can be used to store information about a defect in HP Sprinter without disrupting test
flow?
A. Defect Highlighter tool
B. Test Defect tool
C. Smart Defect tool
D. Defect Reminder tool
Answer: D
Question: 7
Which entities can be linked to a defect? (Select two.)
A. Cycles
B. Releases
C. Reports
D. Defects
E. Tests
Answer: D, E
Question: 8
A tester reports that when running a test, HP Sprinter is preventing him from attaching a movie of
the test run to the defect he is submitting. How can this problem be resolved?
A. By the user adjusting options in his hp sprinter user interface
B. By the user re-establishing his hp application lifecycle management connection
C. By the project administrator enabling the allow attaching movies to defects? Option on the
customization > hp sprinter page by the project administrator enabling the ?allow attaching
movies to defects? Option on the customization > hp sprinter page
D. By the project administrator enabling the allow attaching movies to defects? Option for the
appropriate user group on the customization >by the project administrator enabling the ?allow
attaching movies to defects? Option for the appropriate user group on the customization >
groups and permissions > Defects page
Answer: C
Question: 9
What is HP Sprinter?
A. An automated test environment for exploratory testers
B. A manual test environment for exploratory testers
C. A manual test execution environment
D. A manual test development environment
Answer: C
Question: 10
What does Risk-Based Quality Management enable you to do?
A. Determine which requirements to add to the application
B. Calculate the number of tests to be built per requirement
Page 3 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Page 6 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Question: 25
The ALM Synchronizer is a service that provides out-of-the box integration with which tools?
(Select three.)
A. Tasktop
B. Rational ClearQuest
C. Microsoft Project
D. CollabNet TeamForge
E. Rational ReqPro
F. Defects between two ALM Projects
Answer: B, E, F
Question: 26
In which fields of the Design Steps tab is it possible to use parameters? (Select two.)
A. Step Name
B. Expected Result
C. Parameters
D. Test Configurations
E. Description
Answer: B, E
Question: 27
Which HP Application Lifecycle Management command enables you to convert a Manual test to
an automated test type?
A. Convert Script
B. Create Script
C. Generate Script
D. Generate Script from manual test
Answer: C
Question: 28
How is a set of data defined in an Excel report?
A. SQL queries on the project database
B. SQL queries on the management database
C. Data Grid view from the Testing module
D. Data Grid view from the Dashboard module
Answer: A
Question: 29
In the Test Plan module, which graph enables you to correlate the number of tests and the
elapsed time interval?
A. Tests Summary graph
B. Tests Results graph
C. Tests Trend graph
D. Tests Progress graph
Answer: D
Page 7 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Question: 30
A company is using HP Quality Center (QC) 10 and HP Application Lifecycle Management (ALM)
11. During an upgrade, how should you install the clients?
A. Do not install HP QC 10 and HP ALM11 clients on the same machine; it will cause errors and
HP QC 10 will fail to start.
B. Do not install HP QC 10 and HP ALM11 clients on the same machine; it will cause errors and
HP ALM 11 will fail to start.
C. Install HP QC 10 and HP ALM11 clients on the same machine; do not start both clients
because it will cause errors.
D. Install HP QC 10 and HP ALM11 clients on the same machine; use both clients, side-by-side,
in different browser instances.
Answer: D
Question: 31
What the advantages are of clearly and correctly defining requirements at the front end of a
project? (Select three.)
A. Sets clear expectations between stakeholders
B. Improves the automated test performance
C. Provides stakeholders with guidelines of what the priorities are
D. Cuts waste and eliminates unnecessary expenditure
E. Allows integration with external tools
F. Eases the association between test sets and cycles
Answer: A, C, D
Question: 32
You are the QA manager for a company, working on a new project. In the past, end users have
claimed that IT does not deliver what they ask for. For this release, you decide the end users will
sign off on all the requirements. Which feature enables the manager of an HP Application
Lifecycle Management project to define a snapshot of the requirements after they are signed off
by users?
A. Baseline
B. Traceability Matrix
C. Document Generator
D. Graph Wizard
Answer: A
Question: 33
What does HP Sprinter's Storyboard feature do?
A. Enhances test results with screen captures of the application under test, taken during the test
run
B. Enables testers to design tests by capturing, annotating, and assembling a sequence of screen
captures of the application under test
C. Provides a movie editing toolbox for extracting, annotating, and assembling a sequence of
screen captures after a test run
D. Enables testers to view a guiding sequence of annotated screen captures during their test run
via the storyboard sidebar
Page 8 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Answer: A
Question: 34
Coverage Progress and Outstanding Defects are two graphs for tracking progress and quality of
your releases. Which entities must be assigned to the release and cycle for these graphs to
provide the complete information for your release? (Select three.)
A. Tests
B. Components
C. Resources
D. Test Sets
E. Requirements
F. Defects
Answer: D, E, F
Question: 35
Which description applies to HP Application Lifecycle Management access?
A. Login credentials are required (Single Sign On Supported), access may be restricted by
project, and projects to which you have no access are not visible.
B. Login credentials are required (Single Sign On Supported), access may be restricted by project
or role, and projects to which you have no access are visible.
C. Login credentials are required (Single Sign On Not Supported), access may be restricted only
by role, and projects not accessible by your role are not visible.
D. Login credentials are required (Single Sign On Supported), access may be restricted only by
role, and projects not accessible by your role are not visible.
Answer: A
Question: 36
What is a prerequisite for using the Business Models module?
A. Models must be created in standard BPMN or EPC modeling tools.
B. Models must be created using RUP.
C. Models must be created in Excel.
D. HP Application Lifecycle Management Modeling Manager must be implemented.
Answer: A
Question: 37
Which HP Application Lifecycle Management module allows you to manage, view, and create
graphs?
A. Management
B. Dashboard
C. Reports
D. Business Objects
Answer: D
Question: 38
Which icon indicates a checked out entity?
A. A red lock
Page 9 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Page 10 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Answer: D
Question: 44
What are solutions for running manual tests? (Select two.)
A. HP QuickTest Professional
B. Manual Runner
C. Manual Test Runner
D. HP Sprinter
E. HP LoadRunner
Answer: B, D
Question: 45
When should tests be automated? (Select two.)
A. When tests are executed only once
B. When tests check a multi-user client/server system
C. When tests require immediate execution
D. When tests check how easy the application is to use
E. When tests check the stability of application basic functionality
Answer: B, E
Question: 46
What are execution statuses of a test instance? (Select two.)
A. OK
B. Completed
C. Not Completed
D. Blocked
E. Suspended
Answer: C, D
Question: 47
How would you leverage test configurations to cover multiple requirements and avoid unneeded
duplications?
A. By associating different test configurations in multiple tests with each requirement
B. By associating different test configurations in the same test with each requirement
C. By associating the same test configuration in the same test with each requirement
D. By associating the same test configuration in multiple tests with each requirement
Answer: B
Question: 48
As the project administrator of a project that is linked to a template project, what can you do?
A. Synchronize project customizations with the linked template project on demand
B. Roll back project customizations if problems are detected
C. Request suspension of template customizations being applied
D. Run verification prior to synchronization with the template project
Answer: C
Page 11 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Question: 49
DRAG DROP
Click the Task button. The process for Risk-Based Quality Management includes four steps.
Identify the valid steps and place them in the correct order of execution.
Answer:
Page 12 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Question: 50
Which type of data can be added to a Dashboard page?
A. Releases
B. Requirements
C. Reports
D. Graphs
Answer: D
Question: 51
What are supported test types out-of-the-box? (Select three.)
A. LOAD_TEST
B. CAPACITY_TEST
C. BLACK-BOX_TEST
D. LR-SCENARIO
E. QUICKTEST_TEST
F. MANUAL
Answer: D, E, F
Question: 52
Which condition best allows leveraging of test configurations?
A. The test is configurable.
B. The test is manual.
C. The test is automated.
D. The test has parameters.
Answer: B, D
Question: 53
HOTSPOT
Click the Task button. Click on the entity where data hiding can be configured.
Page 13 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Answer:
Page 14 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Question: 54
Which application can you use to design a new Custom Report Template?
A. Microsoft Excel
B. Microsoft Word
C. HP Template Generator
D. ALM Template Manager
Answer: B
Question: 55
What can you do in the Configuration tab of a report?
A. Assign a report to a test step
B. Share reports
C. Link reports to test step
D. Select the report output format
Answer: D
Page 15 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Question: 56
What is required to create a Baseline Report?
A. The baseline must support the history template.
B. All report sections must support test configurations.
C. All report sections must support baselines.
D. The baseline must support the standard template.
Answer: C
Question: 57
Which integrations for HP Application Lifecycle Management are supported by the Free HP ALM
Mylyn Connector? (Select two.)
A. Microsoft TFS connector
B. Bugzilla
C. Collabnet connector
D. CVS
E. Rational ClearQuest
Answer: B, D
Question: 58
From which tabs in the Test Lab module can you add tests to a test set? (Select two.)
A. Testing Tree tab
B. Requirements Tree tab
C. Test Plan Tree tab
D. Releases Tree tab
E. Cycle Tree tab
Answer: B, C
Question: 59
What does assigning each Test Set folder to a Cycle enable you to do?
A. Group together test sets that will be run during the same cycle and analyze the progress of the
cycle as you run your tests
B. Separate test sets that will be run during the same cycle and analyze the progress of the cycle
as you run your tests
C. Group together test sets that will be run during different cycles and check the global
requirements
D. Separate test sets that will be run during the same cycle and check the global requirements
Answer: A
Question: 60
What happens if a team member tries to delete a representative requirement?
A. The deletion succeeds. The requirement coverage of the model entity is lost.
B. The deletion fails. The representative requirements are read-only and are therefore protected
from deletion.
C. The deletion fails. The representative requirement is automatically made read-only, and an
alert is optionally triggered.
D. The deletion succeeds. The representative requirement is moved to the Obsolete folder.
Page 16 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Answer: A
Question: 61
The business analyst team released a new version of the "Ship Product" Business Process
model. What does HP Application Lifecycle Management do when it re-imports the model file?
A. It unlinks all existing representative requirements associated with the model and activity
entities, and creates and links new ones.
B. It adds new path entities for any new alternate flows it detects.
C. It creates new model and activity entities if any new models or activities are detected in the
imported file based on name.
D. It creates duplicate representative requirements for any re-imported activities that have
different GUIDs than before.
Answer: D
Question: 62
What can you do by creating a new Requirement Type? (Select two.)
A. Define a new KPI
B. Define which fields are required
C. Associate the new requirement with a cycle
D. Define a rich text template
E. Define new requirement coverage status
Answer: B, D
Question: 63
What can you define by configuring the Traceability Matrix? (Select three.)
A. The source requirements
B. The tests linked to and from the test steps
C. The associated tests
D. The source releases
E. The associated cycles
F. The requirements linked to and from the source requirements
Answer: A, C, F
Question: 64
In HP Application Lifecycle Management 11, which learning aids are supplied with the client
install? (Select four.)
A. Feature movies
B. Tutorials
C. Support links
D. User documentation
E. FAQS
F. Certified partner integration documentation
G. Support chat window
H. Hp solutions integration Catalog
Answer: A, B, C, D
Page 17 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Question: 65
DRAG DROP
Click the Task button. Identify the phases that are embodied within HP Application Lifecycle
Management.
Answer:
Page 18 of 19
www.selfexamengine.com
Exam Name:
Exam Type:
Certification
Exam Code:
Total Questions:
HP0-M46
67
Question: 66
Which products are available for the HP Application Lifecycle Management (ALM) and HP Quality
Center (QC) 11.x release? (Select three.)
A. QC Starter Edition
B. QC Enterprise Edition for Site, Area, and Global Locations
C. ALM for Site, Area, and Global Locations
D. ALM Enterprise Edition for Site, Area, and Global Locations
E. ALM Starter Edition
F. QC Premier Edition for Site, Area, and Global Locations
Answer: A, B, C
.
Question: 67
Which Project Planning and Tracking feature allows you to analyze the KPI results?
A. Scorecard
B. Master Plan
C. KPI Report
D. Progress Report
Answer: A