Академический Документы
Профессиональный Документы
Культура Документы
(393257-T)
DEVELOPMENT DEPARTMENT
MANUAL FOR MONITORING OF
CONSTRUCTION AND TAKING
OVER OF WATER SUPPLY SYSTEM FROM
DEVELOPERS
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 1 of 5
TABLE OF CONTENT
SECTION
CONTENTS
PAGE
6
1.0
INTRODUCTION
2 .0
SCOPE
3.0
GENERAL POLICY
3.1
3.1.i
3.1.ii
3.1.iii
3.1.iv
3.1.v
Role of Developer
8 -10
3.1.vi
Role of Consultant
10
3.2
General conditions
10 - 11
4.0
4.1
6 -7
A-1
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 2 of 5
TABLE OF CONTENT
SECTION
CONTENTS
PAGE
4.1.a
A-2 A-7
4.1.b
A-8 A-9
4.1.c
A-10 A-12
Form EPS 1
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
2
3
3A
4
5
6
7
7A
8
8A
9
10
10A
11
12
13
14
15
15A
16
16A
17
A-13
A-14
A-15
A-16
A-17
A-18
A-19
A-20
A -21
A -22
A -23
A-24
A-25
A-26
A-27
A-28 - A-30
A-31
A-32
A-33
A-34
A-35
A-36
A-37
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 3 of 5
TABLE OF CONTENT
SECTION
CONTENTS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
Form EPS
18
19A
19B
19C
19D
20
20A
21
PAGE
A-38
A-39
A-40
A-41
A-42 - A-43
A-44
A-45
A-46
4.2
B1
4.2 .a
4.2.b
B2 B3
B4
4.2.c
4.3
4.3.a
B5
B6
B7
B8
B9 B11
B12
B13
C1
Mechanical Works
C2 C10
FORM EPS/M&E 1
FORM EPS/M 1
FORM EPS/M&E 2
FORM EPS/M&E 3
C 11
C 12
C13
C 14
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 4 of 5
TABLE OF CONTENT
SECTION
4.3b
CONTENTS
PAGE
FORM EPS/M 2
FORM EPS/M&E 4
FORM EPS/M 3
FORM EPS/M&E 2
FORM EPS/M&E 5
FORM EPS/M 4
FORM EPS/M 5
FORM EPS/M 5a
FORM EPS/M 6
FORM EPS/M&E 6
FORM EPS/M &E 2
FORM EPS/M &E 7
FORM EPS/M&E 8
C15 C29
C 30
C 31
C 32
C 33
C 34
C 35
C 36
C 37
C 38
C 39
C 40
C 41
Electrical Works
C42 C49
C 50
C51
C52
C53 C62
C63 C 66
C67
C68
C69
C70 -C 76
C77- C80
C81
C82
C83
C84
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 5 of 5
TABLE OF CONTENT
SECTION
4.3c
CONTENTS
PAGE
C85
C86
C87
C88
Telemetry Works
FORM ESP / M&E 1
FORM EPS / T 1
FORM EPS / M&E 2
FORM EPS / M&E 3
FORM EPS / T 2
FORM EPS / M&E 4
FORM EPS / T 3
FORM EPS / M&E 2
FORM EPS / M&E 5
FORM EPS / M&E 6
FORM EPS / M&E 2
FORM EPS / M&E 7
FORM EPS / M&E 8
C89 - C96
C97
C98
C99
C100
C101 C 106
C107
C108
C109
C110
C111
C112
C113
C114
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 1 of 6
SUBJECT
1.0
2.0
INTRODUCTION
1.1
1.2
1.3
To facilitate the process of taking over the completed water supply systems
constructed by developers.
1.4
To ensure that completed water supply systems taken over are built according to
the approved plan and is of good quality.
SCOPE
2.1
The manual covers the quality control during construction stage followed by the
taking over processes for civil, mechanical & electrical and telemetry works as
follows :a)
b)
c)
3.0
GENERAL POLICY
3.1
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 2 of 6
SUBJECT
iii)
iv)
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 3 of 6
SUBJECT
Role of Developer
a. All construction works at site must be based on approved plan.
Developer is required to ensure no construction work shall commence
without the water supply system plans already approved by SYABAS.
b. To appoint Professional Engineer registered with Board of Engineers
Malaysia from SYABAS recommended list of consultants who are
familiar with SYABAS technical requirements on water supply system. (A
list of consultants is available from SYABAS office for reference).
c. To engage the same consultant to carry out design works and supervision
of work.
d. The developer must engage consultant supervisor to do supervision of
works based on the following category :i). Supervision for civil works on pipeline, reservoir and pump house
shall be as follows:For housing development in progress at any stage less than 100 units
or equivalent to 33,000 gallon per day intermittent supervision by
one full time technician.
For housing development in progress at any stage between 100 500
units or equivalent between 33,000 165,000 gallon per day full
time supervision by one full time technician.
For housing development in progress at any stage between 500
1,000 units or equivalent between 165,000 330,000 gallon per day
supervision by one full time civil engineer and one technician.
For housing development in progress at any stage more than 1,000
units or equivalent more than 330,000 gallon per day supervision
by one full time civil engineer and two technicians.
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 4 of 6
SUBJECT
ii). Supervision for works involving mechanical & electrical and telemetry
systems shall be by a qualified electrical or mechanical engineer and
be engaged when works are being carried out at project site.
e. Developer through its consultant must submit the curriculum vitae of
consultant supervisor who should have more than 5 years experience related
to water supply works and must be approved by SYABAS. Any works found at
site without the consultant supervisor as required, can be rendered as not
acceptable and lead to SYABAS not taking over the external water supply
system.
f.
To appoint a contractor registered with CIDB or PKK with relevant sub head
related to water supply works.
Developer is responsible to repair and make good any defects during the
defects liability period which in general is 36 months after the date of taking
over ( but is subjected to details in SYABAS s letter to REDHA ref. No(6201)
dlm.SYABAS 22/1/315 dated 8 November 2006 on the defect liability period .
Developer is also responsible to repair and make good any latent defects
which appear after defects liability period due to negligence, inferior quality of
materials and shoddy workmanship.
j.
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 5 of 6
SUBJECT
vi)
l.
Developers are required to allow access at their respective project site and
assist SYABAS staff to carry out site inspection on ongoing works as directed.
m.
The developer has to make sure that stealing of water does not take place
at project site.
Role of Consultant
a. To prepare a quality assurance plan
b. To supervise all works through its site representative
c. To ensure all works are built according to approved drawings and
specifications
d. To prepare bimonthly progress reports and works programmes.
e. Consultant shall take full responsibility for all proper study, design,
authority approval, specification, construction drawings, supervision,
material inspection, testing and commissioning.
f. Consultant will not be relieved of its design obligation and supervision
even after the water supply system is taken over by SYABAS.
3.2
General Conditions
a. The quantity of water for construction supply and testing purposes can be given
in 2 stages: Stage 1: For construction supply, the meter installed at site shall be small
(generally not more than 25 mm diameter). Water for construction supply
will be used for construction, leakage and pressure testing and general
cleaning purposes
Stage 2: For pump testing and flushing purposes, the meter can be
increased to full bore diameter, for example 100 mm diameter (generally)
depending on water requirement of the water supply system. Water for
sterilization and flushing and pumping system test shall be obtained after
connection to the existing mains has been carried out.
b. SYABAS will take over the permanent water supply system only if developers
have completed the said system according to the approved plans. For big
developments, the taking over can be done by phases of development provided
each phase of development has completed its entire water supply system.
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 6 of 6
SUBJECT
4.0
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 1 of 6
4.1. a
Action By
4.1.1
4.1.2
4.1.3
4.1.4
4.1.5
4.1.6
Manager,
Contractor, Consultant,
SYABAS Technician/ Technical
Supervisor, Head of Planning/
development Section.
/
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 2 of 6
4.1. a
Action By
4.1.7
4.1.8
Technician/
Supervisor
of
Development
section
4.1.9
4.1.10
4.1.11
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 3 of 6
4.1. a
Action By
4.1.12
4.1.13
4.1.14
4.1.15
4.1.16
4.1.17
Consultant / Developer
Head
Planning
/
Development,
Technical
Manager, Head of District,
secretary of works.
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 4 of 6
4.1. a
4.1.18
4.1.19
4.1.20
4.1.21
4.1.22
SYABAS district notifies the date for sterilizing / District Technical Manager,
flushing/ water quality using Form EPS 16A from Head of district
the date of application by contractor.
4.1.23
4.1.24
4.1.25
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 5 of 6
4.1. a
Action By
4.1.26
4.1.27
4.1.28
4.1.29
4.1.30
4.1.31
District technician of meter section updates the water District Technician water
data and activate the consumer account for billing meter section.
from the date of submission of water meter data by
plumber.
4.1.32
Plumber
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 6 of 6
4.1. a
Action By
4.1.33
4.1.34
District,
Page 1 of 2
4.1.b. Workflow Chart of Contruction and Post Construction of External Water Supply System
Ref.No.
Plumber
Contractor
Consultant
SYABAS
District
Approved Plan
<50,000 lpd
EPS 1
4.1.4
Head of district
notifies of product material
inspection
EPS 5
Head of District
HQ Development
HQ monitors and
conducts surprise
check at project
site.
4.1.12
4.1.13
4.1.14
EPS 6
Audit HQ
to carry out
independent
check
EPS 7
EPS 7A
4.1.10
4.1.11
EPS 3
EPS 3A
EPS 4
Head of planning /
Development informs
the result of inspection
to consultant
4.1.8
4.1.9
EPS 2
Check pipe material at site, water fitting/pipe material for testing and
water fittings inspection (except for pipes)
4.1.6
4.1.7
4.1.3
4.1.5
FORM
USED
Approved Plan
>50,000 lpd
Head of district
4.1.1
4.1.2
Developer
HQ
Contractor/consultant carries out pipeline / reservoir testing and witness by SYABAS district
Head of Planning/Development and Technical Manager
EPS 8
EPS 9
EPS 10
EPS 10A
EPS 11
EPS 12
IP 5
4.1.15
Confirmation of completion
of Internal Plumbing by
Technical Manager to HOD
4.1.16
Confirmation on
For big systems
completion of M & E, &
telemetry by M & E section (>150kw) and HT
to HOD
Continue to page 2 of 2
EPS /M&E 8
Page 2 of 2
4.1.b. Workflow Chart of Contruction and Post Construction of External Water Supply System
Ref.No.
Plumber
Contractor
Consultant
SYABAS
District
Developer
HQ
FORM
USED
From page 1 of 2
4.1.17
4.1.20
4.1.23
Contractor executes
sterilising and flushing
District technical
manager coordinates
EPS 16A
EPS 17
EPS 18
EPS 19 A
4.1.25
Head of district
approves and issues
letter of Taking Over
4.1.26
4.1.27
EPS 19 C
EPS 19 D
Licensed Plumber
applies for water meter(s)
EPS 20
Head of district
approves the issuance
of water meter(s)
Licensed Plumber
installs meter
District technician meter
section to update the
meter particulars and
activate the consumer
account
4.1.33
4.1.34
EPS 19 B
Head of district
distributes the taking
over document to
various sections
4.1.29
4.1.32
EPS 15
EPS 15A
4.1.24
EPS 14
EPS 16
4.1.22
4.1.31
4.1.21
4.1.30
4.1.18
4.1.28
EPS 13
Developer receives
unused BG
EPS 21
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 1 of 3
SUBJECT
4.1 c - Different Types of form to be used for External Permanent Water Supply System.
TYPE OF FORM
FORM EPS 1
TITLE OF FORM
APPLICATION BY CONSULTANT FOR SYABAS TO CHECK
PRODUCT/MATERIAL
FORM EPS 2
FORM EPS 3
FORM EPS 3A
FORM EPS 4
FORM EPS 5
FORM EPS 6
FORM EPS 7
FORM EPS 7A
FORM EPS 8
FORM EPS 8 A
FORM EPS 9
FORM EPS 10
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 2 of 3
SUBJECT
TYPE OF FORM
TITLE OF FORM
FORM EPS 11
FORM EPS 12
FINAL
JOINT
INSPECTION
(RESERVOIR/PUMPHOUSE)
FORM EPS 13
FORM EPS 14
FORM EPS 15
FORM EPS 16
FORM EPS 16 A
FORM EPS 17
FORM EPS 18
FORM EPS 19 A
CONFIRMATION
CONSULTANT
FORM EPS 19 B
FOR
HANDING
REPORT
OVER
BY
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 3 of 3
SUBJECT
TYPE OF FORM
TITLE OF FORM
FORM EPS 20
FORM EPS 20 A
FORM EPS 21
FORM EPS 1
APPLICATION BY CONSULTANT FOR SYABAS
TO CHECK PRODUCT MATERIAL
(To be filled in by Consultant)
To
Consultant
Name of Development
File Ref. No.
Date
Approved Plan No.
:
:
:
:
:
:
Product Brand /
Name of
Supplier
SYABAS
Product
Certificate No.
Product/Material
Details
Location to be
used
Remarks by
district
Enclosed is a copy of receipt of site inspection fees and attached herewith are necessary
product/material brochures and technical specification (or any other supporting documents)
Please give a suitable date for the above products / materials to be inspected.
_________________________________
Consultant Signature, Name and PE No:
:__________________
: _________________
: Technical Manager
: _________________
Accepted by,
Signature
Name
Designation
Date
: _________________
: _________________
: Head of District
: _________________
FORM EPS 2
To,
Consultant
: ____________________________________________________
Address
: ____________________________________________________
____________________________________________________
Name of Development
: ____________________________________________________
File No.
: ____________________________________________________
Date
: ____________________________________________________
With reference to your application letter for site product/material inspection dated ,
SYABAS wish to inform the site material inspection shall be as follows :a).
Date
: _________________________
b).
Time
: _________________________
c).
Place to meet
: _________________________
Please ensure that all products/materials listed in your letter are ready for inspection on the above
date.
Signature
: ______________________
Signature
: ______________________
Name
: ______________________
Name
: ______________________
Date
Date
: ______________________
: ______________________
FORM EPS 3
SYABAS DISTRICT: .
PIPE MATERIAL INSPECTION REPORT
Name of Development
File No.
Developer
Consultant
Pipe Supplier / Manufacturer
Contractor Name
Instrument Used
Inspection Date
Location To Be Laid
Total number of pipes to be inspected
Delivery Order No
Type of Pipe /
Pressure
Diameter (mm)
Rating
:
:
:
:
:
:
:
:
:
:
:
Minimum
Body
Thickness
(mm)
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
___________________________________________________
Calipers / Ultrasonic Thickness Equipment / Micrometer
____________________________________________________
____________________________________________________
____________________________________________________
____________________________________________________
Pipe
No/ ID
Int.
Lining
Thickness
Thickness
Socket
End
Of
Pipe
Middle
(mm)
Spigot
End
Remark
Passed
(/)
Failed
(X)
Note: a. Thickness Measurement shall be at random check and not less than 20% of the number of pipes supplied in each
delivery order.
b. All new pipes and laid pipes must be end-capped.
a. Recommendation to be used
b. Recommendation to be rejected and removed from site
c. Other remarks: __________________________________
Inspected & measured by: (Consultant)
Name
: ___________________________ Post: ___________________ Signature: _______________ Date: ___________
_________________________________________________________________
: (SYABAS)
: ___________________________
: Technician / Technical Supervisor Planning/
Development section
: ___________________________
:____________________________
Witnessed By
Name
Post
Signature
Date
: (SYABAS)
:_______________________
: Head of Planning/
Development Section
: _______________________
:________________________
FORM EPS 3A
SYABAS DISTRICT: .
WATER FITTING/PIPE SAMPLE FOR TESTING
Name of Development
: ___________________________________________________________
File No.
: ____________________________________________________________
Developer
: ____________________________________________________________
Consultant
: ____________________________________________________________
Date
: ____________________________________________________________
We,.., the consultant hereby submit the following water fitting/pipe sample
as requested by SYABAS for testing and agree to pay testing charges as imposed by the testing body /agency.
Type of water
fittings/pipes
SYABAS
Sample
Units
Dimension
Certificate
No
Nos
Size mm
No.
Name of Supplier/
manufacturer
To be filled in by
SYABAS AFTER
RESULT
Pass (/)
Fail (x)
Note : a. The certified test result of the selected sample issued by accredited laboratories need to be attached
later.
We hereby agree to abide the outcome of the test result as follows: _
1. We accept the outcome of the test result of the sample submitted for testing.
2. We accept that any sample that does not pass any specified requirement will result in the whole batch
of materials to be rejected and removed from site at developer's own cost.
Agreed by
: (Consultant)
Name : ______________________
Signature : __________________
Designation : __________________
Date: ________________
Agreed by
: (Developer)
Name : ______________________
Signature : __________________
Designation : __________________
Date: ________________
Endorsed by : (SYABAS)
Signature
: ________________________
Name
: ________________________
Designation : Technician/ Technical Supervisor
District Planning/ Development Section
Date
: ________________________
Signature
Name
Designation
Date
: _______________________
: _______________________
: District Head of Planning/
Development Section
: _______________________
FORM EPS 4
SYABAS DISTRICT: .
WATER FITTINGS INSPECTION REPORT (Except for pipes)
Name of Development
Developer
Consultant
Inspection Date
File No.
Type of Fittings
:
:
:
:
:
Product Brand
_______________________________________________
_______________________________________________
_______________________________________________
_______________________________________________
_______________________________________________
SYABAS
Certificate No
Name of
supplier
Product Details
( Dimensions &
Sizes)
Remarks (Visual
Inspection)
Good / Fair / Poor
General Remarks :
____________________________________________________________
(If any defective product is detected, head of planning and development section will
report to SYABAS Standard, Material and Product Committee)
Witnessed by
: Supplier/Contractor
Witnessed by
Name
: _________________________
Name
: _________________________
Designation
: _________________________
Designation
: _________________________
Signature
: _________________________
Signature
: _________________________
Witnessed by : SYABAS
Witnessed by
: SYABAS
Name
: __________________________
Name
: __________________________
Designation
: Technician/Technical Supervisor
Planning & Development Section
Designation
Signature
: __________________________
Signature
: __________________________
Consultant
FORM EPS 5
Logo of
consultant
firm
Name of Development
: ____________________________________________________________
File No.
: ____________________________________________________________
Name of Consultant
: ____________________________________________________________
Address
: ____________________________________________________________
Name of Developer
: ____________________________________________________________
: ____________________________________________________________
Period of Reporting
: ____________________________________________________________
Content of report
1. Location plan (street map)
3. Contract details
4. Progress Summary Description with actual progress compare to planned progress (Fill where appropriate)
i) External Works
a. Pipe laying works
b. Suction tank
c. Pump house
d. Reservoir
e. Installation of Mechanical works
f. Installation of electrical works
g. Installation of telemetry system
h. Overall progress (actual/schedule)
ii) Internal Plumbing
a. suction tank
b. Storage tank
c. Pipe works
5. Quality control
a. Material inspection
b. Work inspection
c. Site testing
6. Progress photographs
Prepared by
Consultant Signature
Name
PE No.
Designation
Date
:
: ______________________
: ______________________
: ______________________
: ______________________
: ______________________
FORM EPS 6
SYABAS DISTRICT :
QUALITY MONITORING BY DISTRICT REPORT
(EXTERNAL WATER SUPPLY SYSTEMS)
Name of Development
File No.
Developer
Consultant
Overall Progress Description
Date of Site Visit
:
:
:
:
:
:
____________________________________________________
____________________________________________________
____________________________________________________
____________________________________________________
____________________________________________________
____________________________________________________
1.
2.
3.
Activity
Plan Approval and Product approval
Work Permit (Digging)
Traffic management
Acceptable
Unacceptable
Comments
4.
Safety Measurement
( Signboard etc)
5. Site cleanliness
6. Excavation
7. Road Cutting
8. Capping of pipe end before and after laying
9. Laying of pipe
10. Jointing of pipes/valves
11. Backfilling material
12. Road reinstatement
13. Pipe protection internal and external
before and after laying
14. Chamber construction / cover /marker
post
15. Quality Material at site
16. Slope condition
17. Drainage within/outside worksite
(Compliance to JPS/DOE)
18. Concreting works
19. Concrete tests/site tests
20. Others
Tick where relevant
Overall findings
: _________________________________
Site Instruction to Consultant / Developer : _________________________________
( To be followed up by letter )
Inspected by :
(SYABAS Signature) :
Name
:
Designation
:
Date
Acknowledged By :
(Consultant Signature) :
Name
:
Designation
:
Date
:
______________________
_______________________
Technician Planning
Development
______________________
______________________
______________________
______________________
______________________
Endorsed by
:
(SYABAS Signature) :
Name
:
Designation
:
Date
_________________________
_________________________
Technician Supervisor
Planning &Development Section.
_________________________
Acknowledged By :
(Developer Signature) : _________________________
Name
:
__________________________
Designation
:
__________________________
Date
:
__________________________
FORM EPS 7
APPLICATION BY CONSULTANT FOR SYABAS
TO CARRY OUT PIPELINE / RESERVOIR TESTING
(To be filled by Consultant)
To
Consultant
: _____________________________________________________
Name of Development
: _____________________________________________________
File No
: _____________________________________________________
Date
: _____________________________________________________
b)
Obtained approval for water source for purposes of pressure and leakage testing from
SYABAS
c)
d)
Visually inspected and repaired the external condition of the pipe/tank for any sign of
leakage
e)
f)
Request to increase the size of flow meter for testing purpose (from .. mm to ..
mm)
g)
Physical inspection internally (free from debris) for pipe size 700mm and above
h)
Communication pipes, ferrule connections and main pipes are ready for pressure
testing.
(Tick, where relevant)
Thank you.
Consultant Signature :
______________________________
Name
______________________________
PE No
______________________________
Designation
______________________________
Date
______________________________
FORM EPS 7A
NOTIFICATION OF PIPE / RESERVOIR TESTING
(EXTERNAL WATER SUPPLY SYSTEMS)
To,
Consultant
: ____________________________________________________
Address
: ____________________________________________________
____________________________________________________
Name of Development
: ____________________________________________________
File No.
: ____________________________________________________
Date
: ____________________________________________________
With reference to your application letter for pipeline / reservoir testing dated ,
SYABAS wish to inform the pipeline / reservoir testing shall be as follows :a).
Date
: _________________________
b).
Time
: _________________________
c).
Place to meet
: _________________________
Please ensure that the preparation works are ready for testing on the above date.
Signature
: ______________________
Signature
: ______________________
Name
: ______________________
Name
: ______________________
Date
Date
: ______________________
: ______________________
FORM EPS 8
HYDROSTATIC PRESSURE AND LEAKAGE
TEST REPORT FOR EXTERNAL PIPELINE
Name of Development
___________________________________________________________
Consultant
___________________________________________________________
Developer
___________________________________________________________
Contractor
___________________________________________________________
File No.
___________________________________________________________
Date
_______________________
Type of Pipeline
Size of Pipe
_______________________ mm
Pipe Material
_______________________
Pipe length
_______________________ m
RESULT
B) LEAKAGE TEST
Initial pressure
Final Pressure
(Approx. 24 hours)
Total make-up water
Total test duration
PASS
Pipe
Material
Pressure
Test (Bar)
Leakage
Test (Bar)
HDPE
(PN 12.5)
Steel
12.0
15.0
8.0
12.0
15.0
12.0
12.0
8.0
Ductile
Iron
ABS
(CL 12)
FAIL
:
:
__________________________ Bar
__________________________ Bar
:
:
__________________________ Liters
__________________________ Hours
Allowable Leakage : 0.34 liter x internal pipe dia.(mm)x pipe length(m) x Total test duration (hour) x Leakage Test (bar) (Liters)
10 x 1000 x 24 hr x 1 bar
=
=
RESULT
Tested by :
____________________
(Contractor Signature)
Name :
Designation :
PASS
________________ liters
FAIL
______________________ __________________
(Consultant Signature)
Head of Planning & Development Section
Name :
Name :
Designation :
Designation :
Witnessed by,
_________________
Technical Manager
SYABAS
Designation:
FORM EPS 8A
HYDROSTATIC PRESSURE TEST REPORT
TEST ON MAIN PIPE COMPLETE WITH FERRULE AND COMMUNICATION PIPE
Name of Development
_______________________________________________________
_______________________________________________________
Consultant
_______________________________________________________
Developer
_______________________________________________________
Contractor
_______________________________________________________
Plumber
_______________________________________________________
File No.
_______________________________________________________
Date
___________________________
___________________________
___________________________
___________________________
_______________________ mm
_______________________ m
PRESSURE TEST
Initial specified Pressure
: ___________bar
PASS
Communication Pipe
Material
Pressure Test
(Bar)
All type
6.0
FAIL
Note : The second pipe pressure test referred here shall include the main pipe, complete with ferrule
connection and communication pipe up to meter stand position.
Tested by :
Tested by :
_________________ ____________
(Contractor Signature) (Plumber Signature)
Name :
Name :
Designation :
Designation :
Witnessed by:
_________________
_______________
(Consultant Signature) Head of Planning &
Name :
Development Section
Designation :
Name :
Designation:
Witnessed by:
________________
Technical Manager
SYABAS
Name :
Designation:
FORM EPS 9
WATERTIGHTNESS TEST REPORT FOR RESERVOIR
Name of Development
___________________________________________________________
Developer
___________________________________________________________
Consultant
___________________________________________________________
File No.
___________________________________________________________
Date
____________________________________________________________
Type of Reservoir
____________________________________________________________
Capacity of Reservoir
______________________________________________ml____________
Test Preparation
:
(If not satisfactory, please state details)
____________________________________________________________
Visual Inspection
____________________________________________________________
WATERTIGHTNESS TEST
A.
Water Level
Initial water level reading
B.
: ____________________
: ____________________
Evaporation
Tray size = L X B X H
Initial water level reading
= __________________
Date / Time
: ____________________
Date / Time
: ____________________
ALLOWABLE LEAKAGE
C=
mm
ACTUAL LEAKAGE
D=
Drop in water level (A) Drop in water level (B) Evaporation
( If D < C= PASS; D> C = FAIL )
RESULT
PASS
mm
FAIL
Tested by :
Witnessed by,
____________________
(Contractor Signature)
Name :
Designation :
______________________ ________________________
(Consultant Signature)
Head of Planning & Development Section
Name :
Name :
Designation :
Designation :
Witnessed by,
_________________
Technical Manager
SYABAS
Designation:
FORM EPS 10
APPLICATION BY CONSULTANT FOR SYABAS
TO CARRY OUT FINAL INSPECTION OF EXTERNAL SYSTEM
( to be filled in by Consultant)
To,
File No.
: ____________________________________________________
Consultant
: ____________________________________________________
Name of Development
: ____________________________________________________
We, the designer and supervising consultant, undertake to confirm the pipelines/reservoirs have been
completed
1. All water supply installation works are built according to approved plans and specification.
2. All fittings / Product used are approved type as in approved list
3. Pipelines/reservoirs are not constructed in private land.
4. Pipelines of 700mm and above are physical cleaned internally to be free from debris and
mud.
5. Take full responsibility for any non-compliance and deviations of the works.
Please inform us of a suitable date for inspection.
Applied by :
Acknowledged by :
Name
Name
: ______________________
: ______________________
Designation : ______________________
Designation : _____________________
PE No.
: ______________________
Date
Date
: ______________________
: ______________________
: __________________________________________________
Address
: __________________________________________________
__________________________________________________
Name of Development
: __________________________________________________
File No.
: __________________________________________________
Date
: __________________________________________________
Date
: _________________________
b).
Time
: _________________________
c).
Place to meet
: _________________________
Please ensure that all works are completed and ready for inspection on the above date.
Signature
: ______________________
Signature
: ______________________
Name
: ______________________
Name
: ______________________
Date
Date
: ______________________
: ______________________
FORM EPS 11
SYABAS DISTRICT : ..
FINAL JOINT INSPECTION REPORT (EXTERNAL PIPELINE)
( Valid for six (6) months prior taking over date )
Name of Development
File No.
Approved Plan No.
(Attach approved plan and as-built plan of pipeline)
Date of Site Visit
Phase / Name of location pipeline checked
Work Description
A) PIPELINES
Type of
pipe
: _____________________________________
: _____________________________________
: _____________________________________
: _____________________________________
: _____________________________________
Satisfactory
(tick relevant
Diameter
(mm)
Remarks
Unsatisfactory
Column)
Comments
Length
(m)
1) Main Pipes
2) Communication Pipes
Type
Nos
Size(mm)
3) Sluice Valves
4) Butterfly Valves
5) Scour Valves
6) Air Valve
7) Hydrants
8) Valve Chambers
9) Pipe Markers
10) Pressure reducing valves
11) Sampling Points
12) Zone Meters
13) Bulk meter with proper meter stand/filter
/ gate valves
14) Constant flow valve
15) Over crossing with/without supports /
Spike guards
16) Other items :
General Comments
Work done Satisfactory and acceptable to be taken over.
Work done Unsatisfactory for those items commented and need to be rectified and another inspection date to be arranged.
Others (Please specify)
Remarks :
Jointly Inspected by : Head of Planning/Development Section SYABAS
Signature
: _________________________
Name
: _________________________
Date
: _________________________
FORM EPS12
page 1 of 3
SYABAS DISTRICT : ..
FINAL JOINT INSPECTION REPORT(RESERVOIR / PUMPHOUSE)
( Valid for six (6) months prior taking over date )
EXTERNAL WATER SUPPLY SYSTEM
Development
:
File No.
:
Approved Layout Plan No.
:
Date of Site Visit
:
(Tick relevant column)
Work Description
Remarks
Capacity
Satisfactory Unsatisfactory
Comments
/size
(tick relevant column)
A) RESERVOIRS ( Suction or Service )
Nos
1) Type of tank (Ground/Elevated)
2) Make of tank (RC/Panel tank)
3) Capacity (ML)
4) Dimensions ( length x breadth x Height)
5) No visible Ground Settlement
6) Roof Condition
7) Wall Condition
8) Floor Condition
9) Column Condition
10) Ventilation Lantern
11) Inlet Pipe
12) Outlet Pipe
13) Overflow Pipe
14) Scour pipe
15) Bypass pipe
16) Inlet valve (altitude/ball)
17) Outlet valve
18) Overflow valve
19) Scour valve
20) Bypass pipe valve
21) Valve Chamber with step
ladder/cover/clean
22) Slope gradient
23) Setback
24) Guard rails (galvanized steel)
25) Internal Ladder (RC/Aluminium/stainless
steel)
26) External Ladder (RC/Aluminium/stainless
steel)
27) Ventilation door (Mosquito proof Monel
Metal Gauge)
28) Perimeter Drainage
29) Drain Manhole
30) Level Indicator
31) Reservoir Painting
32) RTU/Telemetry
33) Reservoir Information
TWL/BWL/Capacity
34) Flow meter
35) Other Comments
FORM EPS12
page 2 of 3
SYABAS DISTRICT : ..
FINAL JOINT INSPECTION REPORT(RESERVOIR / PUMPHOUSE)
( Valid for six (6) months prior taking over date )
EXTERNAL WATER SUPPLY SYSTEM
Development
:
File No.
:
Approved Layout Plan No.
:
Date of Site Visit
:
(Tick relevant column)
Work Description
Remarks
Capacity
Satisfactory Unsatisfactory
Comments
/size
(tick relevant column)
B) PUMPHOUSE
Nos
1) Location Dimension (length x Breath)
2) Roof type (RC/Steel)
3) Security Grilles
4) Gantry Crane
5) Fire Protection
6) Toilet facilities
7) Table and Chair
8) Painting works
9) Metal roller shutter door
10) Suction pipeline
11) Flowmeter
12) Valves (suction line)
13) Valves (delivery line)
14) Type of rosestrainer
15) Other Comments
Capacity
Satisfactory Unsatisfactory
Comments
/size
(tick relevant column)
Nos
C) EXTERNAL CIVIL WORKS
1) Access Road
2) Premix
3) Close Turfing
4) Security Fencing (Y- type)
5)Perimeter Barbed Wire (ground level)
6) Padlock
7) Boundary Markers
8) Signboard
9) Perimeter drainage system
10) Discharge point
11) Other Comments :
D)
1)
2)
3)
4)
5)
6)
7)
8)
Quarters
Floor area
Rooms
Kitchen
Roofing Material
Type of ceiling
Type of floor tile
Lighting points
Power points
Capacity
/size
Nos
Satisfactory Unsatisfactory
(tick relevant column)
Comments
FORM EPS12
page 3 of 3
SYABAS DISTRICT : ..
FINAL JOINT INSPECTION REPORT(RESERVOIR / PUMPHOUSE)
( Valid for six (6) months prior taking over date )
EXTERNAL WATER SUPPLY SYSTEM
Development
:
File No.
:
Approved Layout Plan No.
:
Date of Site Visit
:
(Tick relevant column)
9) Toilets
10) Water taps
11) Painting works
12) Perimeter drainage system
13) Septic tank
14) Other Comments:
General Comments
Work done Satisfactory and acceptable to be taken over.
Work done Unsatisfactory for those items commented and need to be rectified and another inspection date
to be arranged.
Others (Please specify)
Remarks :
Jointly Inspected by: Section Head of Planning
/Development SYABAS (District)
Signature
: ____________________
Name
: ____________________
Date
: ____________________
Acknowledged by Consultant :
Signature
: ____________________
Name
: ____________________
Designation
: ____________________
Date
: ____________________
Acknowledged by Developer :
Signature
: ____________________
Name
: ____________________
Designation : ____________________
Date
: ____________________
Signature
Name
Date
: ____________________
: ____________________
: ____________________
FORM EPS 13
SYABAS DISTRICT : ..
LETTER REQUESTING BANK GUARANTEE FOR DEFECT LIABILITY PERIOD
(EXTERNAL WATER SUPPLY SYSTEM)
Your Ref. :
Our ref. : Bil (
Date :
) dlm.SYABAS
(Developer Name )
Dear Sir,
Subject : ( Development Title )
BANK GUARANTEE FOR DEFECT LIABILITY PERIOD
With reference to your letter dated .. on the above matter and the final site inspection carried out in the
presence of representatives from your company, consultant, contractor and SYABAS on .. is referred.
2.
Before the letter to take over the water supply system is issued out, you are required to submit a bank
guarantee of amount RM.. ( Ringgit Malaysia ..) under the name of
Syarikat Bekalan Air Selangor Sdn. Bhd. and deliver to this office within fourteen (14) days from the date of this
letter.
3.
The said bank guarantee is a guarantee to ensure that the taken over water supply system is in good
condition and functioning well within the months of defect liability period.
4.
SYABAS has the right to exercise the said bank guarantee to do any repair works arising from civil or
mechanical or electrical or telemetry works during the defect liability period for the above development if the
developer fails to execute the repair works within the stipulated time frame as required by SYABAS.
5.
The balance of bank guarantee amount will be returned to the developer after deducting repair costs (if
any) borne by SYABAS.
Thank you.
.
SYABAS Head of District ______________
Name :
Date :
sk
1.
2.
3.
( Consultant )
Porting
FORM EPS 14
APPLICATION BY DEVELOPER FOR SYABAS
TO TAKE OVER EXTERNAL WATER SUPPLY SYSTEM
(to be filled in by Developer and Consultant)
To
Development
File No
Date
:
:
:
:
______________________________________
_______________________________________
_______________________________________
APPLICATION FOR SYABAS TO TAKE OVER SYSTEM
: ___________________________
: ___________________________
: ___________________________
: ___________________________
: ___________________________
Applied by
Developer Signature
Name
Designation
Date
:_____________________
: _____________________
: _____________________
: _____________________
: _____________________
FORM EPS 15
SYABAS DISTRICT: ..
(EXTERNAL WATER SUPPLY SYSTEM)
TO
FROM
: ___________________________________________________
..(name
of
contractor)
wish
to
apply
for
tapping
at
: ____________________________________________________
Address
: ____________________________________________________
____________________________________________________
Name of Development
: ____________________________________________________
File No.
: ____________________________________________________
Date
: ____________________________________________________
60 % SKP Receipt No
: ____________________________________________________
Date
: _________________________
b).
Time
: _________________________
c).
Place to meet
: _________________________
Please ensure that the preparation works are ready for tapping connection on the above date.
Signature
: ______________________
Signature
: ______________________
Name
: ______________________
Name
: ______________________
Date
: ______________________
Date
Copy to
: (Developer)
: ______________________
FORM EPS 16
SYABAS DISTRICT: .
(EXTERNAL WATER SUPPLY SYSTEM)
TO
FROM
: ___________________________________________________
Applied by:
..
(Contractor)
: ____________________________________________________
Address
: ____________________________________________________
____________________________________________________
Name of Development
: ____________________________________________________
File No.
: ____________________________________________________
Date
: ____________________________________________________
Date
: _________________________
b).
Time
: _________________________
c).
Place to meet
: _________________________
Please ensure that the preparation works are ready for sterilizing / flushing/ water quality on the above
date.
Signature
: ______________________
Signature
: ______________________
Name
: ______________________
Name
: ______________________
Date
: ______________________
Date
Copy to
: (Consultant)
: ______________________
FORM EPS 17
SYABAS DISTRICT: .
STERILIZING / FLUSHING / WATER QUALITY PIPELINE REPORT
Name of Development
File No.
Developer
Sterilizing
Agent
Date
Location of
Sterilizing
__________________________________________
__________________________________________
__________________________________________
__________________________________________
: __________________________________________
:
:
:
:
Pipeline
Length (m)
Pipeline
Dia. (m)
Volume of
Water (m3)
Chlorine
(kg)
Time start
Time
Finish
* End of 24 hour period the sterilizing mixture shall have a strength of at least 10ppm of chlorine.
Flushing
Date
:
Location of
Flushing
Time Start
Time Finish
Total Time
(min)
Pipeline
Length
(m)
Pipeline
Diameter
(m)
Non Revenue
Water (NRW)
(m3)
Chemical Parameter
Aluminium
Iron
Manganese
0.3 mg/l
0.1 mg/l
0.2 mg/l
Microbiological
E.Coli
T. Coliform
(Absent)
(Absent
Fail
If not satisfactory, please list the following actions required to be taken by contractor / consultant: ____________
Carried Out By : ___________________________
Contractor Signature)
Name
: ___________________________
Designation
: ___________________________
Date
: ___________________________
Supervised by : ___________________________
(Consultant Signature)
Name
: ___________________________
Designation : ___________________________
Date
: ___________________________
: ___________________________
(SYABAS Signature)
: ___________________________
: Technician Water Quality Unit
: ___________________________
Witnessed By : ___________________________
(SYABAS Signature)
Name
: ___________________________
Designation : Head of Unit Water Quality Unit
Date
: ___________________________
Witnessed By
Name
Designation
Date
FORM EPS 18
SYABAS DISTRICT: .
STERILIZING / WATER QUALITY RESERVOIR REPORT
Name of Development
File No.
Developer
Sterilizing
Agent
Date
: ___________________________________________
:____________________________________________
:____________________________________________
:____________________________________________
Reservoir
Type
Capacity
(mld)
Volume of
Water (m3)
Chlorine
Dosage (kg)
Time start
Time
Finish
Chemical Parameter
Microbiological
Aluminium
Iron
Manganese E.Coli
T. Coliform
0.1 mg/l
0.2 mg/l
0.3 mg/l
(Absent)
(Absent
Fail
If not satisfactory, please list the following actions required to be taken by contractor
/ consultant : ____________________________
Witnessed By : ___________________________
(SYABAS Signature)
Name
: ___________________________
Designation
: Technician Water Quality Unit
Date
: ___________________________
Witnessed By : ___________________________
(SYABAS Signature)
Name
: ___________________________
Designation : Head of Unit Water Quality Unit
Date
: ___________________________
Consultant
_____________________________________________________
Name of Development
_____________________________________________________
File No
_____________________________________________________
Date
_____________________________________________________
c)
completed all outstanding works and rectified all defects as per final joint inspection
report.
prepared three (3) set of master keys to be handed over for main gates of service
reservoir/ pump house/suction tank/manhole covers/ chambers)
Paid all outstanding TNB bills, a copy of which is enclosed.
d)
Others _______________________________________________________
b)
: _________________________________
Name
: _________________________________
PE No
: _________________________________
Designation
: _________________________________
Date
: _________________________________
______________________________________________
Address
______________________________________________
From
Date
______________________________________________
File No.
______________________________________________
Name of Development :
______________________________________________
____________________________________
b) Time
____________________________________
c) Place to meet
____________________________________
Please ensure that three (3) set of master keys for the gates, doors and padlocks, if applicable are ready to
be handed over on the above date.
Signature
_______________________
Signature
_____________________
Name
_______________________
Name
_____________________
Designation :
Technical Manager
Designation :
Date
_______________________
Date
______________________
FORM EPS 19 C
SYABAS DISTRICT: .
(EXTERNAL WATER SUPPLY SYSTEM)
LETTER FOR TAKE OVER SYSTEM
Your Ref :
Our ref : Bil (
) dlm.SYABAS
Date :
(Developer Name )
Dear Sir ,
Subject : (DEVELOPMENT TITLE)
Taking Over of Reticulation System/Pumping System/Reservoir
With reference to your letter (EPS 14) dated .. on the above matter and the water quality inspection
visit after flushing works were completed in the presence of representatives from your company, consultant,
contractor and SYABAS on .. is referred.
2.
Please be informed that SYABAS in principle has no objection to agree to take over the said reticulation
system/pumping system/reservoir from the date of this letter.
3.
The defect liability period is fixed at months effective from .. You are required to
repair all defects or damages during the defect liability period.
4.
The developer has submitted a bank guarantee amounting to RM.. and any repair cost borne by
SYABAS will be deducted from the bank guarantee if repair works are not carried out by developer.
5.
The end of defect liability period letter will be issued to the developer after the developer has repaired all
defects as notified by SYABAS
6.
With this letter the developer can proceed to apply for water meter after the water deposit has been paid.
7.
SYABAS in principle has no objection to supply water for the above development and the Local Authority to
issue the certificate of fitness.
Thank You.
Approved by,
Endorsed by,
Signature : _____________________________
SYABAS Head of District ________________
Signature : _________________________________________
SYABAS Secretary of Works District ____________________
Name :
Date :
Name :
Date :
sk
1.
2.
3.
4.
5.
6.
7.
Yang Dipertua
Majlis Perbandaran/District
General Manager, Development Department
General Manager, Operation and Maintenance Department
Assistant General Manager, Mechanical and Electrical Department
Unit Meter District ..
Unit Mechanical and Electrical District ..
( Consultant )
FORM EPS 19 D
Page 1 Of 2
SYABAS DISTRICT: .
(EXTERNAL WATER SUPPLY SYSTEM)
Distribution of Permanent Water supply System Handing Over Documents
To
Development Name
File No.
Date
: __________________________________________(Department Concerned)
: __________________________________________
: __________________________________________
: __________________________________________
Please be informed that the permanent water supply system has been completed by the developer and taken over by
SYABAS on .
Copies of permanent water supply system handing over documents for the above development are distributed to the relevant
departments as shown in the table below.
Item
Document
a.
Bound Copy
1
2
3
4
5
6
Development
Department
Planning and
Design
Department
Operation and
maintenance
Department
Mechanical and
Electrical
Department
District
FORM EPS 19 D
Page 2 Of 2
SYABAS DISTRICT: .
(EXTERNAL WATER SUPPLY SYSTEM)
Distribution of Permanent Water Supply System Handing Over Documents
Item
10
11
Required Document
Payment receipt
40% SKP dan 60%
SKP
Support Letter from
Mechanical and
Electrical section (if
applicable)
12
b.
Unbound Copy
13
14
15
16
Development
Department
Planning and
Design
Department
Operation and
maintenance
Department
Mechanical
and Electrical
Department
District
As-built plan
Mechanical, Electrical
and Telemetry
Additional As-built
plans (4 sets)
Operation /
Maintenance manual
for Zone Meter (2
sets)
Thank you.
__________________________________________________
Head of District :___________________________________
Name
: _________________________________________
Date
: _________________________________________
FORM EPS 20
SYABAS DISTRICT: .
(EXTERNAL WATER SUPPLY SYSTEM)
To
From
: __________________________________________________
Date
: __________________________________________________
Thank you.
Applied by Plumber :
Signature
: _____________________________
Name
: _____________________________
Designation
: _____________________________
: _____________________________
c.c.
i. (Developer)
ii. (Consultant)
: _________________________________________________
: _________________________________________________
DATE
: __________________________________________________
Recommended by ;
Approved by;
Signature
: ___________________________ Signature
:____________________________
Name
: ___________________________ Name
: ___________________________
: ____________________________ Date
: ___________________________
FORM EPS 21
SYABAS DISTRICT: .
Your Ref :
Our ref : Bil (
) dlm.SYABAS
Date :
(Developer Name )
Dear Sir,
Subject : (DEVELOPMENT TITLE)
End of defect liability period for Reticulation System/Incoming Main/Pumping System/Reservoir
With reference to the above matter, SYABAS is pleased to confirm that there are no more outstanding
defects for the above development. With this, SYABAS confirms that the end of defect liability period
for reticulation system/incoming main/pumping system/reservoir for the above development has
ended.
2. Enclosed herewith is the original copy of full/balance bank guarantee for the defect liability period
amounting to RM for your retention.
Thank You.
Recommended by :
Approved by :
Signature :______________________________
SYABAS Secretary of Works District
Name :_________________________________
Date : _________________________________
Signature :_________________________
SYABAS Head of District..
Name :____________________________
Date : _____________________________
sk
1.
2.
3.
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 1 of 2
4.2.2
4.2.3
M/E
consultant/architect
submits
the M/E consultant/architect
confirmation of product material used in
internal plumbing of the development project
using FORM IP 1.
4.2.4
4.2.5
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 2 of 2
4.2 a
Action By
4.2.6
4.2.7.
4.2.8
SYABAS
Technician,
Technical
Manager,
Consultant /architect /
licensed plumber
4.2.9
Licienced
Plumber
Consultant
SYABAS
Developer
District
HQ
4.2.1
Approved Plan
for others
4.2.2
District
4.2.3
4.2.4
FORM
USED
4.2.5
IP 2A
4.2.6
IP 2B
4.2.7
4.2.8
4.2.9
IP 3
Confirmation of
completion of
internal plumbing
by Technical
Manager to HOD
IP 4
IP 5
MANUAL REF.
PMD/D/SOP/1
DATE ISSUED
Nov. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 1 of 1
TABLE OF CONTENT
TYPE OF FORM
TITLE OF FORM
FORM IP 1
FORM IP 2A
FORM IP 2B
FORM IP 3
FORM IP 4
INTERNAL PLUMBING
TESTING REPORT
FORM IP 5
SELECTIVE
PRESSURE
FORM IP 1
CONFIRMATION OF PRODUCT
MATERIAL USED IN INTERNAL PLUMBING
(to be filled in by Consultant/Architect)
TO
FROM
: ____________________________________ (Consultant/Architect)
Name of Development
: ____________________________________
File No.
: ____________________________________
Date
: ____________________________________
CONFIRMATION OF PRODUCT
MATERIAL USED IN INTERNAL PLUMBING
Product
Brand
SYABAS
Product
Certificate No
Name of
supplier
Product
Details
Location to
be used
a. Pipes
b. Tanks
c. Type of Valves
d. Pumps
e. Motors
f. Water proofing materials
We confirm that the above mentioned materials will be checked and used at the project site. If any other
materials proposed to be used will be informed accordingly.
Prepared by :
___________________________
Consultant / Architect Signature
Name
Designation
Date
: __________________________
: __________________________
: __________________________
FORM IP 2A
COMPLETION OF INTERNAL PLUMBING
(To be filled by Licenced Plumber )
To
From
Name of Development
: _____________________________
File No.
: _____________________________
Date
: _____________________________
Thank you.
________________________
Licenced Plumber Signature
Name
: ___________________________
Designation
: ___________________________
: ___________________________
Date
: ___________________________
FORM IP 2B
CONSULTANT APPLIES FOR PIPE TESTING
(To be filled by Consultant/Architect)
To
From
____________________________________ (Consultant/Architect)
Name of Development
____________________________________
File No.
____________________________________
Date
____________________________________
consultant/architect responsible for the internal plumbing works hereby certify that we have completed
the installation of the internal plumbing system and that we have carried out pipe pressure tests on all
the units in the development. Enclosed are the test results.
2. We also certify that all material used are in accordance to SYABAS approved product list.
3. We now request SYABAS to carry out site inspection and selective pipe testing of the internal plumbing.
Thank you.
____________________________________
Consultant / Architect Signature
Name
______________________________
Designation
______________________________
Date
______________________________
FORM IP 3
Pg 1 of 3
b. Development Name
c. Architect/Consultant
d. Inspection Date
f.
k. Type of Premise
Terrace House
Shop
Factory
Semi-Detached
Bungalow
Apartment
:
l. No. of Storey
Please specify
1-s
Others
2-s
Please specify
MS
DI
Stainless Steel
Others
21/2-s
3-s
____________________________________
Remarks
d < 100mm
Others
HDPE
Please specify
Polysteel
__________________
Stopvalve
Ball Valve
PPR
Copper
d < 100mm
Others
Stainless Steel
Please specify
HDPE
ABS
____________________________________
Functioning
Not Functioning
PPR
Copper
d < 100mm
Others
Stainless Steel
Please specify
HDPE
ABS
____________________________________
R.Concrete
HDPE
< 100gsh
300gsh - 400gsh
FRP
Stainless Steel
100gsh - 200gsh
Others
Please specify
Good
Not Good
Good
Not Good
Yes
No
FORM IP 3
Pg 2 of 3
No(s)
Functioning
Remarks
Not Functioning
No
100% Watertight
Functioning
Not Functioning
No
Functioning
Not Functioning
No
Functioning
Not Functioning
No
f. Bib Tap
100% Watertight
g. Bidet
100% Watertight
Functioning
Not Functioning
No
7.0 KITCHEN
a. Stopcork for basin and Bib Tap
Functioning
Not Functioning
No
b. Basin Tap
100% Watertight
c. Bib Tap
100% Watertight
Yes
No
Yes
Yes
Yes
No
No
No
Yes
No
Yes
No
i) Electrofussion Clamp
Yes
No
Yes
No
Yes
No
e. For multi-layer meter stand, arrangement of meter should follow ascending order of
storeys
f. Meter Stand Position for fire hydrant
9.0 Others
a.Jointing for HDPE pipes
It is hereby confirmed that we have carried out site inspection on internal plumbing and all the installation works
are found to be satisfactory and comply to the required specification.
It is hereby confirmed that we have carried out site inspection on internal plumbing and noticed that some of the
installation works are not satisfactory completed.
FORM IP 3
Pg 3 of 3
Signature
Signature
Name
Designation
License No.
Date
Date
Signature
Signature
Date
Date
SYABAS IP 4
Note: If there is any failure of pressure test detected in any one of the building unit being tested, then 100% pressure testing need to be carried out to all building units.
for the above development.
Tested by
Witnessed by,
Witnessed by,
Signature (Plumber)
Signature(Consultant/architect)
Signature(SYABAS)
Signature(SYABAS)
Name
:
Plumber license No. :
Date
:
Name
:
Company Name :
Date
:
Name
Position
Date
Name
Position
Date
:
:
:
Technician
:
:
:
Technical Manager
FORM IP 5
SYABAS DISTRICT : .
To
Copy to
Date
Development Title
Please be informed that the internal plumbing system works for the above development has been checked
and the workmanship quality of the internal plumbing system is found to be satisfactory.
Enclosed herewith is the copy of Internal Plumbing Inspection Report (FORM IP 3) and Selective Pressure
Testing Internal Plumbing Report (FORM IP 4) which have been duly certified by the relevant parties for
your information.
Thank You.
Prepared by,
: _______________________________
Designation : _______________________________
Date
: _______________________________
4.3.
MECHANICAL
4.3b
ELECTRICAL
4.3c
TELEMETRY
MANUAL REF.
M&ED/PM/SOP/1
DATE ISSUED
Nov.2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 1 of 8
4.3a
Action By
4.3a.1
Consultant
4.3a.2
4.3a.3
4.3a.4
Consultant
4.3a.5
4.3a.6
Consultant
4.3a.7
Executive/Technician
a. M&E Units District
(motor <150kW)
b. M&E Unit HQ
(motor >150kW and HT)
4.3a.8
Consultant
a. To Head of District
(motor <150kW)
b. To Head of M&E HQ
(motor >150kW and HT)
MANUAL REF.
DATE ISSUED
M&ED/PM/SOP/1
Nov.2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 2 of 8
4.3a.
4.3a.9
Executive
M&E Unit, HQ /District
4.3a.10
Executive,
M&E Unit HQ/District
4.3a.11
4.3a.12
Executive,/ Technician
M&E Unit HQ/District
4.3a.13
Developer,
Consultant,
Main Contractors,
M&E Contractors,
Executive Technician
from M&E Unit HQ /District
4.3a.14
Executive/Technician
M&E Unit HQ/District
Head of M&E Unit HQ
/District
4.3a.15
Executive/Technician
M&E Unit HQ/District
Head of M&E Unit HQ
/District
Action By
MANUAL REF.
M&ED/PM/SOP/1
DATE ISSUED
Nov.2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 3 of 8
4.3a.
4.3a.16
4.3a.17
4.3a.18
Consultant
4.3a.19
4.3a.20
M&E Unit HQ/District carries out joint site re-inspection with Executive/Technician
M&E Unit HQ/District
consultant and contractor.
4.3a.21
Executive
M&E Unit HQ/District
Head of M&E Unit HQ/
District
4.3a.22
Consultant
4.3a.23
4.3a.24
Consultant
4.3a.25
Executive
M&E Unit HQ/District
Head of M&E Dept. HQ/
Head of District
4.3a.26
Action By
Head of M&E HQ/
Head of District
.
Developer/Contractors
MANUAL REF.
DATE ISSUED
M&ED/PM/SOP/1
Nov.2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 4 of 8
4.3a.
4.3a.27
Action By
Executive
M&E Unit HQ/District
4.3a.29
4.3a.30
Head of District,
Secretary of Works
MANUAL REF.
DATE ISSUED
M&ED/PM/SOP/1
Nov.2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 5 of 8
SUBJECT
Contractor
Consultant
SYABAS
DISTRICT
HQ
Approved Plan
Approved Plan
FORM
USED
Submission for
within 7 days.
HQ M&E
motor hp <150kW
motor hp >150kW,LV&HT
EPS/M&E 1
motor hp >150kW,LV&HT
within 3 days.
Consultant supervise
contractors works at site
Site monitoring
HQ monitor progress
EPS/E 1
EPS/E 2
motor hp >150kW,LV&HT
within 3 days.
Consultant and Contractor conduct Factory Test
for electrical Switchboard
Consultant and contractor
conduct testing on (MET) equipments and sistem at site
District M&E
HQ M&E
Witness and certified testing
EPS/E 3 or E 3a
MANUAL REF.
DATE ISSUED
M&ED/PM/SOP/1
Nov.2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 6 of 8
SUBJECT
Contractor
SYABAS
Consultant
DISTRICT
HQ
FORM
USED
A
EPS/M 1
EPS/E 4
EPS/T 1
EPS/M&E 2
motor hp >150kW,LV&HT
within 3 days.
Joint Inspection
within 3 days.
YES
District M&E
HQ M&E
motor hp <150kW
motor hp >150kW,LV&HT
EPS/M&E 3
EPS/M 2
EPS/E 5, E 6
EPS/T 2
EPS/M&E 4
EPS/M 3
EPS/E 7
EPS/T 3
Consultant applies
for re-inspection
EPS/M&E 2
motor hp >150kW,LV&HT
within 3 days.
Re-Inspection
District M&E
HQ M&E
motor hp <150kW
motor hp >150kW,LV&HT
EPS/M&E 5
MANUAL REF.
DATE ISSUED
M&ED/PM/SOP/1
Nov.2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 7 of 8
Contractor
Consultant
SYABAS
DISTRICT
HQ
FORM
USED
B
EPS/M 4
EPS/M 6
within 3 days.
EPS/M 5, M 5a
EPS/M&E 6
EPS/M&E 2
motor hp <150kW
motor hp >150kW,LV&HT
District M&E
motor hp <150kW
HQ M&E
motor hp >150kW,LV&HT
EPS/M&E 7
Copy Letter
EPS/M&E 8
within 3 days.
within 2 days.
Report on Mechanical, Electrical
and Telemetry System
ready to HOD
of Taking Over
To SYABAS M&E Dept. HQ
END
MANUAL REF.
M&ED/PM/SOP/1
DATE ISSUED
Nov.2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 8 of 8
TYPE OF FORM
TITLE OF FORM
FORM EPS/M&E 1
FORM EPS/M 1
FORM EPS/M&E 2
FORM EPS/M&E 3
FORM EPS/M 2
FORM EPS/M&E 4
FORM EPS/M 3
FORM EPS/M&E 2
FORM EPS/M&E 5
FORM EPS/M 4
FORM EPS/M 5
FORM EPS/M 5a
FORM EPS/M 6
FORM EPS/M&E 6
FORM EPS/M&E 2
FORM EPS/M&E 7
FORM EPS/M&E 8
FORM EPS/M&E 1
To
MECHANICAL
Consultant
Address
ELECTRICAL
TELEMETRY
:
Fail No.
Date
Name of Development:
2.
Where by, you can * (proceed / not to proceed) with the above developments
3.
Please refer to the above section for further clarifications. Thank You.
SYARIKAT BEKALAN AIR SELANGOR SDN BHD,
Recommended by,
Approved by,
..
Head of Department M&E, HQ/
..
Head of Division M&E, HQ/ Head of District
Name
Designation
FORM EPS/M 1
To
Consultant
Date
File Ref. No :
Name of Development;
Consultant Signature,
Name and
PE No.
Received by;
Name
:...
Designation :
Date
:
( SYABAS STAMP & receipt Date )
FORM EPS/M&E 2
To;
Inspection
Consultant :
Re-inspection
Address
Final Inspection
:
:
:
From
Date
File No
Name of Development:
Date
b)
Time
c)
Location
Please ensure that all works are ready for inspection on the above date.
FORM EPS/M&E 3
File No.
Name of Development
1 Developer
Address
:
:
Telephone No.
Name
:
:
2 Consultant
Address
:
:
Telephone No.
Name
:
:
3 Main Contractor
Address
:
:
Telephone No.
Name
:
:
4 Mechanical Contractor
Address
:
:
Telephone No.
Name
:
:
Signature
Signature
Signature
Signature
5 *Electrical/Telemetry Cont. :
Address
Telephone No.
Name
:
:
Signature
:
:
:
:
:
Signature
Signature
:
:
Signature
FORM EPS/M2
1 of 15
File No
Name of Development
1 PUMPHOUSE
i.
PUMPSET
No. of Pumpset
PUMP
Make
Type
Model
Capacity
Head
Efficiency
S/No.
:
:
:
:
:
:
:
nos.
No. 1
No. 2
No. 3
:
:
:
:
:
:
:
No. 4
:
:
:
:
:
:
:
:
:
:
:
:
:
:
Comply to design :
YES
NO
(please tick)
Comments;
MOTOR
Make
Type
Hp / kW
F/Load Current
Speed
S/No.
:
:
:
:
:
:
No. 1
If NO, comments
GOOD
No. 2
POOR
FAIR
No. 4
No. 3
:
:
:
:
:
:
(please tick)
:
:
:
:
:
:
:
:
:
:
:
:
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
POOR
FAIR
(please tick)
ii. INSTRUMENT
#
Pressure Gauges
SUCTION SIDE
No. of Gauges
Type
Make
Size
Range
*
:
:
:
:
:
nos.
DELIVERY SIDE
No. of Gauges
Type
Make
Size
Range
mm.
(FT.M) head of Water
:
:
:
:
:
nos.
mm.
(FT.M) head of Water
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
POOR
FAIR
(please tick)
FORM EPS/M2
2 of 15
Suction Pipe
Type
Size
:
:
MS
Comply to design :
YES
CI
DI
mm.
Others
NO
(please tick)
If NO, comments
GOOD
POOR
FAIR
(please tick)
Throttling Valve
No.
Pump No. 1
Type
Make
Size
Actuator
Make
Model
:
:
:
:
:
:
Sluice
Butterfly
mm.
No.
Pump No. 2
Type
Make
Size
Actuator
Make
Model
:
:
:
:
:
:
Sluice
Butterfly
mm.
Comply to design :
YES
NO
(please tick)
:
:
:
:
Foot Valve
Type
Make
Size
YES
If NO, comments
GOOD
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
NO
mm.
Comply to design :
YES
NO
(please tick)
:
:
:
:
Strainer
Type
Make
Size
YES
If NO, comments
GOOD
NO
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
FORM EPS/M2
3 of 15
Pumping Pipe
Type
Size
:
:
MS
Comply to design :
YES
CI
DI
mm.
Others
NO
(please tick)
If NO, comments
GOOD
POOR
FAIR
(please tick)
Check Valve
No.
Pump No. 1
Type
Swing
Make
Model
Size
:
:
:
Wafer
Spring
No.
Pump No. 2
Type
Swing
Make
Model
Size
:
:
:
Nozzle
Wafer
Spring
Nozzle
mm.
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
POOR
FAIR
(please tick)
Throttling Valve
No.
Pump No. 1
Type
Make
Size
Actuator
Make
Model
:
:
:
:
:
:
Sluice
Butterfly
mm.
No.
Pump No. 2
Type
Make
Size
Actuator
Make
Model
:
:
:
:
:
:
Sluice
Butterfly
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
POOR
FAIR
(please tick)
Control Valve
No.
Pump No. 1
Type
Make
Size
:
:
:
Sluice
Butterfly
mm.
No.
Pump No. 2
Type
Make
Size
:
:
:
Sluice
Butterfly
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
POOR
FAIR
(please tick)
MECHANICAL INSTALLATIONS
( Basic Information to be filled by Consultant/Contractor)
v. Bleeding Pipe
Materials
YES
NO
Comply to design :
YES
NO
(please tick)
If NO, comments
YES
GOOD
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
NO
Comply to design :
YES
NO
(please tick)
If NO, comments
YES
Type
Chequer Plate
Materials
MS
Aluminium
Drainage
GOOD
BAD
GOOD
NO
Expended Metal
Others
Conc.
Others
Comply to design :
YES
NO
(please tick)
viii.Drainage Pump
Type
Make
Size
:
:
:
:
YES
If NO, comments
GOOD
NO
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
FORM EPS/M2
5 of 15
YES
NO
Surge Vessel
a. Surge Vessel
Dimension
Plan No
Certificate No.
Test ed Date
Test Pressure
W. Pressure
:
:
:
:
:
:
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
Isolating Valve
Type
Make
Size
:
:
:
Sluice
Butterfly
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
Check valve
Type
Make
Size
:
:
:
Swing
Wafer
Nozzle
Spring
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
Orifice
Type
Make
Size
:
:
:
:
Sluice
Butterfly
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
Pipe Chambers
YES
NO
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
Chamber Cover
YES
Type
Chequer Plate
Materials
MS
Drainage
GOOD
FORM EPS/M2
6 of 15
NO
Expended Metal
Aluminium
Others
Conc.
Others
BAD
(For SYABAS use only)
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
Isolating Valve
Type
Make
Size
:
:
:
Sluice
Butterfly
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
Valve Chambers
YES
NO
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
Chamber Cover
YES
NO
Type
Chequer Plate
Materials
MS
Aluminium
Drainage
GOOD
BAD
Expended Metal
Others
Conc.
Others
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
FORM EPS/M2
7 of 15
No. of set
#
YES
NO
COMPRESSOR
Make
Model
Capacity
S/No.
:
:
:
:
MOTOR
Make
Hp / kW
Speed
S/No.
:
:
:
:
nos.
No. 1
No. 2
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
Overhead Crane
Type
Make
Capacity
YES
NO
:
:
:
Mono-rail
Parallel
Ceiling
tons
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
Hoist
Type
Make
Capacity
:
:
:
Manual
Electrical
tons
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
Floor Jack
Make
Capacity
:
:
:
YES
NO
tons
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
FORM EPS/M2
8 of 15
YES
NO
:
:
:
:
:
nos.
kgs.
Comply to design :
YES
NO
(please tick)
YES
NO
If NO, comments
GOOD
POOR
FAIR
(please tick)
FORM EPS/M2
9 of 15
TECHNICAL DATA
Type
Capacity
TWL
BWL
:
:
:
:
CRC
RRC
PS
MS
CI
DI
FRP
gallons/litres
Ft. / m
Ft. / m
GRP
SS Tank
Others
Others
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
Throttling Valve
Type
:
Make
:
Size
:
Actuator
Make
Model
:
:
:
Sluice
Butterfly
mm.
YES
NO
Comply to design :
YES
NO
(please tick)
If NO, comments
Control Valve
Type
Make
Size
Model
GOOD
:
:
:
:
Ball
Altitude
Modulating Valve
mm.
Comply to design :
YES
NO
(please tick)
Isolating Valve
Type
Make
Size
Model
If NO, comments
GOOD
:
:
:
:
Sluice
Butterfly
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
FORM EPS/M2
10 of 15
By-Pass Valve
Type
:
Make
:
Size
:
Sluice
Butterfly
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
Valve Chamber
Drainage
:
GOOD
BAD
Cover
YES
NO
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
MS
CI
DI
Others
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
:
:
MS
Comply to design :
YES
CI
DI
Others
mm.
NO
(please tick)
If NO, comments
GOOD
Isolating valve
Type
:
Make
:
Size
:
Sluice
Butterfly
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
FORM EPS/M2
11 of 15
Valve Chamber
Drainage
GOOD
BAD
Cover
YES
NO
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
MS
CI
DI
Others
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
Isolating valve
Type
:
Make
:
Size
:
Sluice
Butterfly
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
Valve Chamber
Drainage
:
GOOD
BAD
Cover
YES
NO
Comply to design :
YES
NO
(please tick)
vi. LADDER
# External
YES
NO
Type
MS
Aluminium
Internal
YES
NO
Type
MS
Aluminium
Comply to design :
YES
NO
If NO, comments
GOOD
Others
Others
If NO, comments
GOOD
FORM EPS/M2
12 of 15
YES
NO
Comply to design :
YES
NO
(please tick)
viii.MAINHOLE
# Inspection
YES
NO
YES
NO
MS
Aluminium
Maintenance
YES
NO
Cover
YES
NO
MS
Aluminium
Comply to design :
YES
NO
Cover
If NO, comments
GOOD
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
Others
Others
If NO, comments
GOOD
YES
NO
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
FORM EPS/M2
13 of 15
Capacity
TWL
BWL
:
:
:
:
CRC
RRC
Elevated
PS
FRP
GRP
SS Tank
Others
Ground
gallons/litres
Ft. / m
Ft. / m
MS
CI
DI
Others
mm.
Comply to design :
YES
NO
(please tick)
:
:
MS
Comply to design :
YES
CI
DI
If NO, comments
GOOD
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
Others
mm.
NO
(please tick)
GOOD
Throttling Valve
Type
:
Make
:
Size
:
Actuator
Make
Model
If NO, comments
:
:
:
Sluice
Butterfly
mm.
YES
NO
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
MS
CI
DI
Others
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
:
:
MS
Comply to design :
YES
CI
DI
Others
mm.
NO
(please tick)
If NO, comments
GOOD
FORM EPS/M2
14 of 15
Isolating valve
Type
:
Make
:
Size
:
Sluice
Butterfly
mm.
Comply to design :
YES
NO
(please tick)
If NO, comments
GOOD
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
POOR
FAIR
(please tick)
Valve Chamber
Drainage
:
GOOD
BAD
Cover
YES
NO
Comply to design :
YES
NO
(please tick)
vi. MAINHOLE
# Inspection
YES
NO
YES
NO
MS
Aluminium
Maintenance
YES
NO
Cover
YES
NO
MS
Aluminium
Comply to design :
YES
NO
Cover
If NO, comments
GOOD
Others
Others
vii. LADDER
# External
YES
NO
Type
MS
Aluminium
Internal
YES
NO
Type
MS
Aluminium
Comply to design :
YES
NO
If NO, comments
GOOD
Others
Others
viii.LEVEL INDICATOR
Type
:
Make
:
Model
:
Size
:
Range
:
Reading
:
String
:
YES
NO
mm.
If NO, comments
GOOD
FORM EPS/M2
15 of 15
Comply to design :
YES
NO
If NO, comments
(please tick)
GOOD
POOR
Signature
Signature
Name
Name
Designation
Designation
Date
Date
Signature
Signature
Name
Name
Designation
Designation
Date
Date
FAIR
(please tick)
FORM EPS/M&E 4
To,
Consultant
MECHANICAL WORKS
Address
ELECTRICAL WORKS
File No.
TELEMETRY WORKS
Date
Name of Development
Inspection Date
Referring to the above inspection, outstanding works/defects which require your action and make good are as
follows;-
Any delay in completing the above outstanding works and defects will delay the process of handing over.
Please notify us after all comments have been attended and completed for re-inspection.
Thank you.
.
Head of M&E, HQ/ Head of District, SYABAS
Name
:
Designation
:
Date
:
FORM EPS/M 3
APPLICATION FOR SITE RE-INSPECTION
(MECHANICAL WORKS)
( To be filled in by Consultant )
To
Consultant
Date
File Ref. No :
Name of Development;
Consultant Signature,
Name and
PE No.
Received by;
Name
:...
Designation :
Date
:
( SYABAS STAMP & receipt Date )
FORM EPS/M&E 2
To;
Inspection
Consultant :
Re-inspection
Address
Final Inspection
:
:
:
From
Date
File No
Name of Development:
Date
b)
Time
c)
Location
Please ensure that all works are ready for inspection on the above date.
FORM EPS/M&E 5
REPORT AFTER SITE RE-INSPECTION
*Please tick where applicable
To
MECHANICAL WORKS
Consultant
ELECTRICAL WORKS
Date
TELEMETRY WORKS
File Ref. No
Name of Development;
Location
General Remarks
If not completed, please list the following actions required to be taken by contractor / consultant.
Note: Any delay in completing the above outstanding works and defects will delay the process of
handing over.
* Delete where not applicable
Signature
:..
Signature
:..
Name
Designation
Date
:..
:..
:..
Name
Designation
Date
:..
:.
:..
Signature
:..
Signature
:..
Name
Designation
:..
:..
Name
Designation
:..
:..
Date
:..
Date
:..
FORM EPS/M 4
APPLICATION FOR WITNESS PUMP PERFORMANCE TEST
( To be filled in by Consultant )
To
Consultant
Date
File Ref. No :
Name of Development;
1).
Received by;
Name
Designation :
Date
:
( SYABAS STAMP & receipt Date )
Form EPS/M 5
Consultant
Name of Development
File No.
Date
RECORD SHEET NO
Pump No :
Test
No.
Start
( Ft. / M )
1
2
3
4
5
6
7
8
9
10
Reservoir
Level
Stop
( Ft. / M )
Level
Drop / Rise
( Ft. / M )
Throttling
Valve
Opening
Time
Start
Stop
Duration
( Hrs / Min.)
Form EPS/M 5a
PUMP PERFORMANCE TEST
RECORD SHEET
Pump Data
Pump House
Date
Motor Data
Formula (example)
Pump No.
Make
Total Head
Hd + Hs + Z
Make
Type
Type
Voltage
(V) .
Phase
Hertz
QH x 100
367 x Eff.
(M2.).
No. of Stage
(M2.).
Operating Data.
Difference in Level
between gauge (Z)
(M.).
Flow Rate
( l/s ).
( Amp ).
(M.).
( Amp ).
(M.).
Starting Current
( Amp ).
Speed
( rpm ).
Design Efficiency
(%).
Input in kW x Eff
0.746
Single - Phase in kW
V x A x Pf
1000
Time
Reservoir
Rise / Drop
Level
Flow Rate
Flow
Recorder
M3/h
Delivery
Gauge
Reading
( Hd )
M
Suction
Gauge
Reading
( Hs )
M
Total
Head
(H)
M
Pump
Output
Power
Volts
kW.
Amps
I
B
Av
x 100
Motor
Electrical
Input
Power
Watt
Meter
Reading
Motor
Output
Power
Pump
Efficiency
(Required)
Pf.
kW.
kW.
kW.
Tested By
Witnessed By
Signature
Signature
Signature
Contractor Name
Consultant Name :
Name
Designation
Designation
Designation
1.73 x V x A x Pf.
1000
( % ).
Pump Eff. (%)
No.
H.P. x 0.746
Eff.
Input of Motor in kW
FORM EPS/M 6
:
:
:
From
Date
File No
Name of Development:
Date
b)
Time
c)
Location
Please ensure that all equipments are tested and certified and ready to carry out the testing on
the above date.
FORM EPS/M&E 6
APPLICATION FOR FINAL INSPECTION
( To be filled in by Consultant )
To
Consultant
Date
File Ref. No
Name of Development;
Enclosed together;
1. Original approved drawing for Mechanical, Electrical and Telemetry works, respectively.
( 1 set )
( 1 set )
( 1 set )
4. A copy of Delivery order for handing over spare part and tools.
5. A copy of Delivery Order for handing over Operation Manual for the Pumping System
to Mechanical, Electrical and Telemetry Section.
Please inform us of a suitable date for inspection.
Applied by Consultant;
Signature
Name
Designation
PE No
Date
Received by;
M&E Unit, HQ/District
Acknowledged by;
Head of M&E Unit, HQ/District
Signature
:..
Signature
:..
Name
:..
Name
:..
Designation
:..
Designation
:..
Date
:..
Date
:..
FORM EPS/M&E 2
To;
Inspection
Consultant :
Re-inspection
Address
Final Inspection
:
:
:
From
Date
File No
Name of Development:
Date
b)
Time
c)
Location
Please ensure that all works are ready for inspection on the above date.
FORM EPS/M&E 7
To
File No
Date
MECHANICAL WORKS
ELECTRICAL WORKS
TELEMETRY WORKS
Name of Development;
Location
We confirm hereby that we have supervised the works and the facilities and confirmed it is in
fully in compliance to design and specification and works have been carried out on good
quality.
Confirmed by: (Consultant)
Signature
Signature
:..
Name
:..
Designation :..
Date
:..
:..
Name
:..
Designation :.
Date
:..
We have inspected all the facilities and confirm that works are generally completed and can be
taken over except the following minor/outstanding works.
Inspected by;
(Executive (M&E) Unit HQ/District
Endorsed by;
Head of M&E Unit, HQ/District
Signature
Name
Designation
Date
Signature
Name
Designation
Date
:..
:..
:..
:..
:..
:..
:.
:..
FORM EPS/M&E 8
Copy to:
Date
: ....................................................................................................................
Development title
: ....................................................................................................................
....................................................................................................................
....................................................................................................................
Dear Sir,
Taking Over Support For Mechanical, Electrical & Telemetry Systems
The final joint inspection for the above development carried out in the presence of representatives from
the consultant and SYABAS on .......................................... refers.
Please be informed that the installation works of mechanical , electrical and telemetry systems for the
above development has been satisfactorily completed.
We have no objection to recommed the taking over of the mechanical, electrical and telemetry
aquipment for the above development.
Thank you.
SYARIKAT BEKALAN AIR SELANGOR SDN. BHD.,
...
Section Head of M&E, HQ / Unit Head of District M&E
Name
: ........................................................
Designation
: .......................................................
Date
: .......................................................
Copy to
MANUAL REF.
M&ED/E/SOP/1
DATE ISSUED
NOV. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 1 of 7
4.3b
Action By
4.3b.1.
Consultant.
4.3b.2.
4.3b.3.
4.3b.4.
Consultant.
4.3b.5.
4.3b.6.
Consultant / Contractor
Electrical
4.3b.7.
4.3b.8.
Consultant
4.3b.9.
Consultant
4.3b.10
4.3b.11.
Consultant
SYABAS Representative
HT Chargeman M&E HQ
Head Of Dept. M&E HQ
MANUAL REF.
M&ED/E/SOP/1
DATE ISSUED
NOV. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 2 of 7
4.3b
Action By
4.3b.12.
Consultant
4.3b.13
4.3b.14.
4.3b.15.
4.3b.16.
Developer
Consultant
Main Contractors
M&E Contractors.
4.3b.17.
Developer
Consultant
Main Contractors
M&E Contractors.
4.3b.18.
4.3b.19.
M&E Unit using Checklist Form EPS/E 5 for LV, & EPS/E 6 for
HT.
4.3b.20.
MANUAL REF.
M&ED/E/SOP/1
DATE ISSUED
NOV. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 3 of 7
4.3b
4.3b.21
4.3b.22
Developer / Contractors
4.3b.23.
Consultant / Contractor
Electrical.
4.3b.24.
4.3b.25.
4.3b.26
Consultant
4.3b.27.
4.3b.28.
M&E Unit HQ / District organize final joint inspection at site Head of M&E Dept. HQ Head
with consultant, developer and electrical contractor. of District
Technical supervisor, electrical technician & charge man HT Secretary of Works
will check all the electrical system. Form EPS/M&E 7 will
use for report on electrical works after final site inspection.
4.3b.29.
4.3b.30.
Action By
MANUAL REF.
M&ED/E/SOP/1
DATE ISSUED
NOV. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 4 of 7
SUBJECT
Contractor
Consultant
SYABAS
DISTRICT
HQ
Approved Plan
Approved Plan
FORM
USED
Submission for
Mechanical, Electrical and
Telemetry Shop Drawing
District M&E
HQ M&E
motor hp <150kW
motor hp >150kW,LV&HT
motor hp >150kW,LV&HT
Site monitoring
HQ monitor progress
EPS/M&E 1
Consultant instructed
contractor to start works
Contractor commences
M, E and T works
Consultant supervise
contractors works at site
Consultant submit periodic
report (every 2 months)
EPS/E 1
EPS/E 2
motor hp >150kW,LV&HT
HQ M&E
District M&E
Witness and certified testing
EPS/E 3 or E 3a
MANUAL REF.
M&ED/E/SOP/1
DATE ISSUED
NOV. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 5 of 7
SUBJECT
Contractor
SYABAS
Consultant
DISTRICT
HQ
FORM
USED
A
EPS/M 1
EPS/E 4
EPS/T 1
EPS/M&E 2
motor hp <150kW
Joint Inspection
YES
District M&E
HQ M&E
motor hp <150kW
motor hp >150kW,LV&HT
EPS/M&E 3
EPS/M 2
EPS/E 5, E 6
EPS/T 2
EPS/M&E 4
EPS/M 3
EPS/E 7
EPS/T 3
Consultant applies
for re-inspection
Re-Inspection
EPS/M&E 2
motor hp >150kW,LV&HT
District M&E
HQ M&E
motor hp <150kW
motor hp >150kW,LV&HT
EPS/M&E 5
MANUAL REF.
M&ED/E/SOP/1
DATE ISSUED
NOV. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 6 of 7
SUBJECT
Contractor
Consultant
SYABAS
DISTRICT
HQ
FORM
USED
B
EPS/M 4
EPS/M 6
motor hp >150kW,LV&HT
EPS/M 5, M 5a
EPS/M&E 6
EPS/M&E 2
motor hp >150kW,LV&HT
District M&E
HQ M&E
motor hp <150kW
motor hp >150kW,LV&HT
EPS/M&E 7
within 2 days.
Report on Mechanical, Electrical
and Telemetry System
ready to HOD
Copy Letter
of Taking Over
To SYABAS M&E Dept. HQ
END
EPS/M&E 8
MANUAL REF.
M&ED/E/SOP/1
DATE ISSUED
NOV. 2006
ISSUE NO.
REVISION NO.
PAGE NO.
Page 7 of 7
TITLE OF FORM
FORM ESP/M&E 1
FORM EPS/E 1
FORM EPS/E 2
FORM EPS/E 3
FORM EPS/E 3a
FORM EPS/E 4
FORM EPS/M&E 2
FORM EPS/M&E 3
FORM EPS/E 5
FORM EPS/E 6
FORM EPS/M&E 4
FORM EPS/E 7
FORM EPS/M&E 2
FORM EPS/M&E 5
FORM EPS/M&E 6
FORM EPS/M&E 2
FORM EPS/M&E 7
FORM EPS/M&E 8
FORM EPS/M&E 1
To
MECHANICAL
Consultant
Address
ELECTRICAL
TELEMETRY
:
Fail No.
Date
Name of Development:
2.
Where by, you can * (proceed / not to proceed) with the above developments
3.
Please refer to the above section for further clarifications. Thank You.
Approved by,
..
Head of Department M&E, HQ/
..
Head of Division M&E, HQ/ Head of District
Name
Designation
FORM EPS/E 1
APPLICATION FOR WITNESS LV / HT EQUIPMENT PERFORMANCE TEST
( To be filled in by Consultant )
To
Consultant
Date
File Ref. No :
Name of Development;
1).
Received by;
Name
Designation :
Date
:
( SYABAS STAMP & receipt Date )
FORM EPS/E 2
NOTIFICATION FOR LV / HT EQUIPMENT PERFORMANCE TEST
(ELECTRICAL WORKS)
To;
Consultant :
Address
:
:
:
From
Date
File No
Name of Development:
Date
b)
Time
c)
Location
Please ensure that all works are ready for LV / HT Equipment Performance Test on the date.
Consultant
FORM EPS / E 3
PAGE 1/10
Name of Development :
File No
Date
CHECK DESCRIPTION
1.
NAME PLATE
2.
3.
PART LAYOUT
TYPE AND RATING OF EACH DEVICE
4.
COMPONENTS ARRANGEMENT
5.
GENERAL ASSEMBLY
6.
BUSBAR SIZES
7.
8.
WIRING
9.
LABELLING
10.
OTHERS
REMARKS
Others
: ___________________________________________________________________________________
___________________________________________________________________________________
___________________________________________________________________________________
Comments
: ____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
FORM EPS / E 3
PAGE 2/10
FRONT
PLAN
RESULT
TOLERANCE TABLE
0 mm
TO
999 mm
: 0.5 %
1000 mm TO
8000 mm
: 0.3 %
PAINTING CHECK
C
D
A
UNIT ( M)
A ( FRONT)
B ( REAR )
C ( RIGHT
SIDE )
D (LEFT SIDE )
E ( INTERNAL)
RESULT
: ___________________________________________________________________________________
___________________________________________________________________________________
___________________________________________________________________________________
Comments
: ____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
FORM EPS / E 3
PAGE 3/10
RESULT (MEGA-OHM)
AFTER DIELECTIRIC
R Y PHASE
Y B PHASE
B R PHASE
R N PHASE
Y N PHASE
B N PHASE
R E PHASE
Y EB PHASE
B E PHASE
N E PHASE
4.0
Others
: ___________________________________________________________________________________
___________________________________________________________________________________
___________________________________________________________________________________
Comments
: ____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
REMARKS
R Y PHASE
Y B PHASE
B R PHASE
RYB N PHASE
RYBN E PHASE
Others
: ___________________________________________________________________________________
___________________________________________________________________________________
___________________________________________________________________________________
Comments
: ____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
1.0
ITE
M
6.0
FORM EPS / E 3
PAGE 4/10
CIRCUIT/EQUIPMEN
T REFERENCE
INJECTE
D PHASE
INJECTE
D DC
AMP
MEASURE
D DCmV
CONTACTS
RESISTANC
E
REMARK
S
Others
: ___________________________________________________________________________________
___________________________________________________________________________________
___________________________________________________________________________________
Comments
: ____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
DESIGNATION
SERIES NO
TYPE
CLASS
RANGE
PHASE
Others
: ___________________________________________________________________________________
___________________________________________________________________________________
___________________________________________________________________________________
Comments
: ____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
FORM EPS / E 3
PAGE 5/10
PHASE
R
Y
B
N
SERIAL NUMBER
REMARKS
TEST SETTING
CURRENT SETTING
TIME SETTING
MEASURED SETTING
RELAY
CURRENT SETTING
TIME SETTING
RELAY
REMARKS
OC
EF
SERIAL NO :
MAKE :
MODEL :
TEST SETTING
REMARKS
OC
EF
SERIAL NO :
MAKE :
MODEL :
TEST SETTING
SERIAL NO:
CURRENT INJECTION
(A)
25 % 50 % 100 %
RANGE
RATIO
ACCURACY
B. VOLTMETER
DESIGNATION
Others
SERIAL NO:
RANGE
ACCURACY
: ___________________________________________________________________________________
___________________________________________________________________________________
___________________________________________________________________________________
FORM EPS / E 3
PAGE 6/10
:
____________________________________________________________________________________
____________________________________________________________________________________
8.1
DESIGNATION
SERIAL NO:
1.25
2.5
3.75
RANGE
RATIO
ACCURACY
B. VOLTAGE TRANSDUCER
DESIGNATION
SERIAL NO:
RANGE
ACCURACY
Others
: ___________________________________________________________________________________
___________________________________________________________________________________
___________________________________________________________________________________
Comments
: ____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
DESCIPTION
RESULT
Pass
Fail
Others
: ___________________________________________________________________________________
___________________________________________________________________________________
___________________________________________________________________________________
FORM EPS / E 3
PAGE 7/10
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
NO
TEST
DESCPIPTION
1.
Auto Start
2.
Auto Stop
3.
MCC Manual
Start
MCC Manual
Start
Remote PB
Manual Start
Remote PB
Manual Stop
Auto/Off/
MCC/RPB
4.
5.
6.
7.
SELECTOR
SWITCH POSITION
STOP
INDICATION OF MOTOR
RUN
TRIP
HEATER
STARTER
DESCRIPTION
Booster
Pump no.1
Booster
Pump no.2
Booster
Pump no.3
Booster
Pump no.4
Booster
Pump no.5
Booster
Pump no.6
Auto
Auto
MCC
MCC
RPB
RPB
Off
Others
: ___________________________________________________________________________________
___________________________________________________________________________________
___________________________________________________________________________________
Comments
: ____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
TEST
DESCPIPTION
1.
Auto Start
2.
Auto Stop
3.
MCC Manual
Start
MCC Manual
Start
Remote PB
Manual Start
Remote PB
Manual Stop
Auto/Off/
MCC/RPB
4.
5.
6.
7.
Others
SELECTOR
SWITCH POSITION
Auto
Auto
MCC
MCC
RPB
RPB
STOP
INDICATION OF MOTOR
RUN
TRIP
HEATER
STARTER
DESCRIPTION
Booster
Pump no.1
Booster
Pump no.2
Booster
Pump no.3
Booster
Pump no.4
Booster
Pump no.5
Booster
Pump no.6
Off
: ___________________________________________________________________________________
___________________________________________________________________________________
___________________________________________________________________________________
FORM EPS / E 3
PAGE 8/10
11.
: ____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
TEST
DESCPIPTION
1.
STOP
INDICATION OF MOTOR
RUN
TRIP
HEATER
Fault
Alarm
Indicate
Sound
Alarm Accept
Manual
Auto
2.
6.
AC Control Supply
Failed
Overcurrent / Earth
Fault
Resistor Bank Temp.
High
Starting Incomplete
7.
8.
9.
3.
4.
5.
10.
11.
12.
13.
14.
15.
16.
Others
: ___________________________________________________________________________________
___________________________________________________________________________________
___________________________________________________________________________________
Comments
: ____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
FORM EPS / E 3
PAGE 9/10
12.
:
:
Signal Injected
Calculated Position
Display Position
P1
4 mAmp
0 % Opened
8 mAmp
25 % Opened
12 mAmp
50 % Opened
16 mAmp
75 % Opened
20 mAmp
100 % Opened
P2
P3
P4
P5
:
:
Shorting Terminal
Pump 1
Yes
No
Pump 2
Yes
No
Pump 3
Yes
No
Pump 4
Yes
No
Pump 5
Yes
Motor Overload
Earth Fault
Others
: ___________________________________________________________________________________
___________________________________________________________________________________
___________________________________________________________________________________
Comments
: ____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
GENERAL REMARKS
_____________________________________________________________________________________________________
_____________________________________________________________________________________________________
_____________________________________________________________________________________________________
_____________________________________________________________________________________________________
_____________________________________________________________________________________________________
_____________________________________________________________________________________________________
_____________________________________________________________________________________________________
_____________________________________________________________________________________________________
No
FORM EPS / E 3
PAGE 10/10
Acknowledgment by Consultant.
I, _____________________________ hereby acknowlege the testing and measurement of the
above LV equipment performance test.
Signature
Name
Designation:
PE No
Date
Witnessed By : (SYABAS)
Signature
: ___________________________
Name
Designation
Date
: ________________________________
__________________________
Witnessed By : (SYABAS)
Signature
: ___________________________
Name
Designation
Date
: ________________________________
__________________________
FORM EPS/E 3a
Page 1/4
To
File No.
Date
Consultant
Name Of Development
:
:
:
:
:
NO
PHASES
1.
M ohm
M ohm
2.
M ohm
M ohm
3.
M ohm
M ohm
4.
M ohm
M ohm
:
________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Comment:
________________________________________________________________________
_____________________________________________________________________________________
Others
______________________________________________________________________________
______________________________________________________________________________
2.
CURRENT LEAKAGE
a.
______ mAmp
b.
______ mAmp
c.
______ mAmp
d.
Across Contact With One Side Earthed and Circuit Breaker is at Open Position
______ mAmp
Others :
________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Comment:
________________________________________________________________________
_____________________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
FORM EPS/E 3a
Page 2/4
3. PROTECTION RELAY.
Over Current & Earth Fault
a.
Make/Model
________________
b.
Current Rating
_______________
c.
Serial No
________________
d.
Aux Supply
_______________
Tripping Test
a. R Y
:-
: ______________
Stability Test
:-
INJECT
: Primay
Secondary
b. Y B
: ______________
c.
RB
: _______________
: ______________ Amp
: ______________ Amp
________________________________________________________________________
Others :
_____________________________________________________________________________________
_____________________________________________________________________________________
Comment:
________________________________________________________________________
_____________________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
4.
CURRENT TRANSFORMER.
a.
PROTECTION CORE
Type : ___________________
CTs No.
b.
Ratio
R _________________
: _________
VA
: _________
Y _________________
Class
: ____________
B ___________________
RATIO CHECK
PHASES
PRIMARY
SECONDARY
REMARKS
R
Y
B
c.
METERING CORE
Type : ___________________
Serial No
Ratio
R _________________
: __________
VA
: ___________ Class
Y _________________
: ____________
B ___________________
FORM EPS/E 3a
Page 3/4
d.
RATIO CHECK
PHASES
PRIMARY
SECONDARY
REMARKS
R
Y
B
AMMETER
: Full Scale
: _______________ Amp.
Others :
________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Comment:
________________________________________________________________________
_____________________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
5. POTENTIAL TRANSFORMER.
Type : ___________________
Ratio
Serial No
R _________________
VOLTMETER
: Full Scale
: _________
VA
: _________
Y _________________
: _______________ Amp.
Class
: ____________
B ___________________
PRIMARY
SECONDARY
REMARKS
R-Y
Y-B
B-R
NO
6.
7.
8.
9.
Others :
DESCRIPTION
RESULT
PASSED
FAILED
________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Comment:
________________________________________________________________________
_____________________________________________________________________________________
FORM EPS/E 3a
Page 4/4
______________________________________________________________________________
______________________________________________________________________________
General Remarks :
_____________________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
Acknowledgment by Consultant.
I, _________________________________________ hereby acknowledge and certified the testing and
measurement of the above HT equipment performance test are in order.
Signature
: ___________________________________
Name
: ___________________________________
Designation
: ___________________________________
PE No.
: ___________________________________
Date
: ___________________________________
Witness by SYABAS :
Signature
Name
Designation
: HT Chargeman M&E HQ
Date
Signature
Name
Designation
Date
FORM EPS/E 4
APPLICATION FOR SITE INSPECTION
(ELECTRICAL WORKS)
( To be filled in by Consultant )
To
Consultant
Date
File Ref. No :
Name of Development;
Consultant Signature,
Name and
PE No.
* Delete where not available.
( For SYABAS use only )
Received by;
Name
:...
Designation :
Date
:
( SYABAS STAMP & receipt Date )
FORM EPS/M&E 2
To;
Inspection
Consultant :
Re-inspection
Address
Final Inspection
:
:
:
From
Date
File No
Name of Development:
Date
b)
Time
c)
Location
Please ensure that all works are ready for inspection on the above date.
FORM EPS/M&E 3
File No.
Name of Development
1 Developer
Address
:
:
Telephone No.
Name
:
:
2 Consultant
Address
:
:
Telephone No.
Name
:
:
3 Main Contractor
Address
:
:
Telephone No.
Name
:
:
4 Mechanical Contractor
Address
:
:
Telephone No.
Name
:
:
5 *Electrical/Telemetry Cont.
Signature
Signature
Signature
Signature
Address
Telephone No.
Name
:
:
Signature
:
:
:
:
:
Signature
Signature
:
:
Signature
FORM EPS / E 5
PAGE 1 / 7
To
Consultant
Name of Development
File No
Date
PUMP HOUSE
MOTOR 1
nos.
MOTOR 2
MOTOR 3
MOTOR 4
MOTOR 5
MOTOR 6
BRAND
KW / HP
AMPS
SPEED
FRAME
S / NO:
BEARINGS
NO
(please tick)
if NO comments : _________________________________________
FAIR
POOR
(please tick)
__________________________________________________________________________________________________________
FORM EPS / E 5
PAGE 2 / 7
MOTOR 1
nos.
MOTOR 2
MOTOR 3
MOTOR 4
MOTOR 5
MOTOR 6
BRAND
KW / HP
AMPS
ROTOR VOLT
ROTOR AMPS
SPEED
FRAME
S / NO:
BEARINGS
NO
(please tick)
if NO comments : _________________________________________
FAIR
POOR
(please tick)
__________________________________________________________________________________________________________
INCOMING
ACB
FUSE SWITCH
C/W HRC FUSE
MCCB
ESP C/W MCCB
E/F & O/C
BRAND
MODEL
AMPS
KA
EXP. DATE
NO
(please tick)
if NO comments : _________________________________________
FAIR
POOR
(please tick)
__________________________________________________________________________________________________________
FORM EPS / E 5
PAGE 3 / 7
LINE / MAIN
CONTACTOR
BRAND
AMPS
TC / ROTOR
CONTACTOR
SC / STP 1,2,3
CONTACTOR
AMPS
AMPS
MCCB
D.O.L.
AUTO
TRANSFORMER
ROTOR
RESISTANCE
NO
(please tick)
if NO comments : _________________________________________
FAIR
POOR
(please tick)
__________________________________________________________________________________________________________
DESCRIPTION
1.
2.
OVERLOAD RELAY
3.
PROTECTION TIMER
4.
SINGLE PHASING
5.
THERMISTER
6.
7.
UNDER CURRENT
8.
9..
10..
11.
12.
13.
14.
M1
M2
M3
M4
M5
M6
YES
NO
NO
(please tick)
if NO comments : _________________________________________
FAIR
POOR
(please tick)
__________________________________________________________________________________________________________
FORM EPS / E 5
PAGE
CHECK LIST OF SITE INSPECTION
ON4 / 7
LV ELECTRICAL INSTALLATION
(Basic Information to be filled by Consultant)
DESCRIPTION
M1
1.
2.
M2
M3
M4
M5
M6
YES
NO
NO
(please tick)
if NO comments : _________________________________________
FAIR
POOR
(please tick)
__________________________________________________________________________________________________________
Bil.
( READING IN AMPS)
( READING IN AMPS)
OVERLOAD
DESCRIPTION
1.
M1
2.
M2
M3
4.
M4
M5
6.
M6
YES
NO
NO
(please tick)
if NO comments : _________________________________________
FAIR
POOR
(please tick)
__________________________________________________________________________________________________________
FORM EPS / E 5
PAGE 5 / 7
CHECK LIST OF SITE INSPECTION ON
LV ELECTRICAL INSTALLATION
(Basic Information to be filled by Consultant)
( Reading in Ohm )
BIL.
DESCRIPTION
C1
1.
EARTH CONTINUITY
2.
C2
C3
C4
C5
TOTAL
( C1 + C2 + C3 + C4 + C5 )
YES
NO
NO
(please tick)
if NO comments : _________________________________________
FAIR
POOR
(please tick)
__________________________________________________________________________________________________________
BIL
.
DESCRIPTION
1.
SUCTION
RESERVOIR
SERVICE
RESERVOIR
2.
E1
-E
E2
-E
E3
-E
E4
-E
E5
-E
E6
-E
E1
E2
E1
E3
E1
E4
E1
E5
E1
E6
E2
E3
E2
E4
E2
E5
E2
E6
E3
E4
E3
E5
E3
E6
E4
E5
E4
E6
E5
E6
NO
(please tick)
if NO comments : _________________________________________
FAIR
POOR
(please tick)
__________________________________________________________________________________________________________
FORM EPS / E 5
BIL.
8.0
9.0
10.0
11.0
12.0
13.0
14.0
15.0
16.0
DESCRIPTION
AUTOMATIC CABLE MARKER C/W PILLER
ORIGINAL CALIBRATION CERTIFICATE FOR EARTH FAULT
ORIGINAL CALIBRATION CERTIFICATE FOR OVER CURRENT RELAY
ORIGINAL CALIBRATION CERTIFICATE FOR MOTOR PROTECTION RELAY
SPEM
ORIGINAL CALIBRATION CERTIFICATE FOR MOTOR PROTECTION RELAY
SPAM
ORIGINAL CALIBRATION CERTIFICATE FOR MOTOR PROTECTION RELAY
P&B GOLD RELAY
DRAWING FOR CONTROL CIRCUIT FRAME & HANG AT PUMP HOUSE.
DRAWING FOR LOCATION OF AUT O CABLE FRAME & HANG AT PUMP
HOUSE.
RUBBER MATE FOR SWITCH BOARD
YES
NO
NO
(please tick)
if NO comments : _________________________________________
FAIR
POOR
(please tick)
__________________________________________________________________________________________________________
FORM EPS / E 5
GENERAL REMARKS:
__________________________________________________________________________________________________________________
__________________________________________________________________________________________________________________
__________________________________________________________________________________________________________________
__________________________________________________________________________________________________________________
__________________________________________________________________________________________________________________
_______________________________________________________________________________________________________________
Signature
: ___________________________
Signature
: ________________________________
Name
: ___________________________
Name
: ________________________________
Designation
: ___________________________
Designation
: ________________________________
Date
: ___________________________
Date
: ________________________________
Signature
: ___________________________
Signature
: ________________________________
Name
: ___________________________
Name
: ________________________________
Designation
: ___________________________
Designation
: ________________________________
Date
: ___________________________
Date
: ________________________________