Академический Документы
Профессиональный Документы
Культура Документы
some cases the equipments are sized for operation at 47.5 Hz and
now this can be limited to 49 Hz.
Longevity and better performance of electrical equipments.
Reduction in outage of equipment leads to reduction in maintenance
cost an increase of productivity.
Reduction in auxiliary power consumption.
At lower frequency, reduction in performance of pumps, fans
etc.,. At higher frequencies increase of stress and wear
experienced.
Less chance of Turbine blade failures.
Avoids grid failures. Failure of Bearings due to oil starvation
during grid failure can be avoided.
Higher operational availability.
about the reason and duration of such operation. All governor shall have
a droop of between 3% and 6%
Section 6.2 (f)
Facilities available within load limiters, automatic turbine run up system,
turbine supervisory control, coordinated control system etc. Shall not
be used to suppress the normal governor action in any manner. No dead
band and / or time delays shall be deliberately introduced
Section 6.2 (g)
All generating units, operating at / up to 100% of their maximum
continuous rating (MCR) shall normally be capable of (and shall not in
any way be prevented from) instantaneously picking up five percent (%)
extra load for at least five (5) minutes or within technical limits
prescribed by the manufacturer when frequency falls due to system
contingency
Section 6.2 (h)
The recommended rate for changing the governor setting, i.e.
Supplementary control for increasing or decreasing the output
(generation level) for all generating units, irrespective of their type and
size, would be one (1.0) percent per minute or as per manufacturers
limits. However, if frequency fall below 49.5 hz, all partly loaded
generating units shall pickup additional load at faster rate, according to
their capability
Governor droop:
3. After this period the load value comes back to the original value in
a ramped fashion.
4. For frequencies more than 50.5 Hz and less than 49.0 Hz load
(limited to + 5%) is added to the load set point to form the final
load set point (Sigma Pr) going to load controller. This will increase
the load signal.
5. After the set point settling down to the new frequency value, the
error becomes zero. On sensing this, the integrator holding the
integral part of the frequency influence is set to zero after a
time delay. This process ensures that the increased value of load
is held for a period of about 5 minutes. While the load is brought
back to the original value a ramping circuit ensures that the load
change is gradual.
6. In the frequency range beyond FGMO limits i.e. blow 49.0 Hz &
above 50.5 Hz the frequency influence as per droop characteristic
will become effective and drives the frequency influence signal to
+ 10% (this limit can be decided as per site conditions).
7. While the frequency influence acts on turbine load set point a
signal is given to Boiler control to make changes in fuel firing with
a feed forward action for a quick response.
8. The pressure controller of EHTC in Limit Pressure mode ensures
that the load is reduced to maintain the boiler header pressure, in
the event of a sudden pressure drop more than set limit value
(10Kg/cm2 for 500MW unit).