Академический Документы
Профессиональный Документы
Культура Документы
Keith Leitner
Sr. Lean Consultant
Optiprise, Inc.
(814) 414-6667
kleitner@optiprise.com
10/24/2002
Page 1
Just in Time
Continuous Flow
Produce only:
What
is needed,
When it is
needed
at Rate of
Customer
Consumption
Built in Quality
Culture
Pull System
Quick Change
Over & Lot
Size Reduction
Level Production
Flexible,
Capable,
Highly
Motivated
People
Standard Work
Error Proofing
Understanding
Value-Added
Separate Manual
from Machine
Time
Total Productive
Maintenance
Design for
Manufacturing
Elimination of
Variation
Problem Solving
Preventive Maintenance
Communications
Process Stability
Measurement/System
5 S & Organization
LEAN SHIPBUILDING
GOAL
WORLD CLASS SHIPBUILDING
JUST IN TIME
BUILT IN QUALITY
LEARNING
ORGANIZATION
DESIGNED AND BUILT
BY FLEXIBLE, CAPABLE,
HIGHLY MOTIVATED
PEOPLE
CONTINUOUS
IMPROVEMENT
ACCURACY CONTROL
LABOR-MACHINE BALANCING
IN-CONTROL PROCESSES
VISUAL CONTROL
WORKER SELF-QUALITY
CONTROL ERROR PROOFING
STABLE SHIPYARD
SHIPYARD PROCESSES
STABLE
PROCESSES
STANDARD
STANDARD
SYSTEMS
SYSTEMS
TOTAL
WORKPLACE
ORGANIZATION
(5S)
PRODUCTIVE
MAINTENANCE
AND SAFETY
ERGONOMICS
TOTAL PRODUCTIVE
MAINT.
OFAND
WASTE
ELIMINATION
ERGONOMICS
SAFETY
10/24/2002
Page 3
10/24/2002
Page 4
10/24/2002
Page 5
10/24/2002
Page 6
Process 1
Process 2
Process 3
Kaizen
Kaizen
Kaizen
10/24/2002
Page 7
Product Leadtime
Waiting
Casting
Transportation
Raw
Material
Assembly
Machining
Staging
Inspection
Time
= Value
Added Time
= Non-Value
Added Time
(WASTE)
Set-up
Finished
Parts
Traditional Results
Traditional Results of Manufacturing Improvement
Time
Time
Small Amount of
Time Eliminated
10/24/2002
Page 9
Lean Results
Focused on Non-Value Adding Items
Time
Large Amount
of Time
Eliminated
Time
10/24/2002
Page 10
Definition
What is the Value Stream:
All actions (VA & NVA)
Currently Required
Bring product through main flows essential to get
product to the customer
SUPPLIERS
PLANT OR COMPANY
10/24/2002
Page 11
Customer
Design
Concept
Launch
Administrative
Order-taking
Delivery
10/24/2002
Page 12
Flow Kaizen
(Value Stream Improvement)
Focus
Point Kaizen
(Elimination of Waste)
Front
Lines
Time
product family
current-state
drawing
future-state
drawing
work plan
10/24/2002
Page 14
Learning to See,
Mike Rother and John Shook
10/24/2002
Page 15
Objectives of
Value Stream Mapping
Visualize
current-state
drawing
future-state
drawing
work plan
10/24/2002
Page 17
Vendor
1X
Weekly
Sr. Mgt.
Fiber Prep
10/24/2002
Page 18
10/24/2002
Page 19
current-state
drawing
future-state
drawing
work plan
Understanding how
the work area
currently operates.
Designing a lean flow.
10/24/2002
Page 20
10
Modulator Fabrication
Material Flow
Suppliers
Customers
100/Day
(1/99)
1X Daily
Scheduled
Shipments
3 days
Shipping
Connector
Rifocs
Fiber Prep
15 - 30 days
2 days
.1 days
Wafer Fab
.5 days
A&T
I
20 days
I
Packing
1.5 days
.5 days
Package Prep
6 days
Push
3 days
10/24/2002
Page 21
Forecast
Meetings
100/Day
Order
Sr. Mgt.
Suppliers
Customers
Acct Mgrs
Sales
Orders
Purchasing
Materials
Mgt
MRP
Modulator
Fabrication
Information Flow
(1/99)
Shipping
Connector
Rifocs
Fiber Prep
Wafer Fab
Dice & Polish
A&T
Packing
Package Prep
Info Flow
10/24/2002
Page 22
11
DMX
Ft. Wayne, IN
Part X
Supplier
Austin, TX
EDI Order to
Supplier ABC
10/24/2002
Page 23
Modulator Fabrication
Value Stream Map
(1/99)
Forecast
Meetings
100/Day
Order
Sr. Mgt.
Suppliers
Customers
Acct Mgrs
Sales
1X daily
Orders
Materials
Mgt
Purchasing
3 days
MRP
Scheduled
Shipments
I
Shipping
Connector
Rifocs
Fiber Prep
15 - 30 days
2 days
Wafer Fab
.1 days
I
20 days
.5 days
A&T
I
Packing
1.5 days
.5 days
Package Prep
I
6 days
I
3 days
Info Flow
Push
10/24/2002
Page 24
12
Supplier
Weekly
Fax
250 ft coils
30/60/90 day
Forecast
Production
Control
Daily
Order
MRP System
Mondays
40,000 pcs/mo.
-30,000 L
-10,000 R
Container= 50 pcs
Daily Ship
Schedule
Daily Requirements
Customer
2 shifts
4 coils
Stamping
500/Gon
Drill
300 T press
2 machines
3 shifts
12000 L
EPE = 2 weeks 4000 R C/T=36sec
Takt = 4.1 sec
C/T= 3 sec.
O.A. = 70%
FTQ = 98%
C/O = 4 hrs, 1X/wk
Scrap = 2%
Rework = none
# operators = 1/shift
Capacity = 22,000/day
V.A. = 3 sec
Shared:part # 123,ABC
250/Cart
Grind
I
4500 L
1500 R
100/Cart
Assemble
OP 10 20 30
3000 L C/T 19 20 19
1000 R C/0 10 8 8
50
/C
on
2x
daily
t.
Ship
4500 L
1500 R
Staging
General Information
- 20 days/month
- 7.2 hours avail./shift
- 2 shifts/day
10/24/2002
Page 25
Master Planning:
Issues a complete schedule
good for the life of the product
barring any major changes.
SOC 3 Block
1 day
Daily Pick
Ticket
Trade Work
As
Sched.
Inv. (Elec.)
7.5 days
Warehouse
Supprt. Work
(Electrical)
C/T: 15 days
Wait (PCI)
2.5 days
Inst. Vent
3 days
15 days
Post-Turn
Delivery
1 day
3 days
7.5 days
Turn Block
2.5 days
Paint
Wait (Svcs.)
0.5 days
0.5 days
2 days
Wait (Trade)
0.5 days
Inv. (Pipe)
3.5 days
0.5 days
3.5 days
2 days
Ins. Steam P.
Wait (Paint)
0.5 days
3 days
3 days
3 days
0.5 days
0.5 days
Erect
As Req.
0.5 days
0.5 days
4.5 days
Wait (PCI)
1 day
4.5 days
0.5 days
1 day
2 days
1 day
Paint
Wait (PCI)
0.5 days
3 days
Wait (Svcs.)
0.5 days
Test Pipe
Wait (P-Test)
1 day
7 days
Inst. Insul.
Scaffold
(for Erection)
1 day
0.5 days
Trade Work
(Pipe)
7 days
2 days
0.5 days
Wait (Svcs.)
0.5 days
3 days
0.5 days
Scaffolding
2 days
Supprt. Work
Insul. P-Pen.
3 days
Wait (Trade)
0.5 days
0.5 days
0.5 days
Wait (Svcs.)
0.5 days
3 days
Clean/Prep
(for Turn)
0.5 days
Wait (Paint)
0.5 days
2 days
0.5 days
Wait (PCI)
3 days
SOC 6
1 Block
1 day
0.5 days
Lead Time = 71.5 days
13
current-state
drawing
future-state
drawing
work plan
Designing a
lean flow.
Lean Transformation Plan
10/24/2002
Page 28
14
Takt Time =
Available Time
Unit Demand
10/24/2002
Page 29
Per Shift:
420min/400 = 1.05 min
or 63 seconds per piece
15
BLOCK
OUTFITTING
ALL OUTFIT
ASSEMBLY FOR
BLOCK
GRAND BLOCK
JOINING
GRAND BLOCK
ERECTION IN
DOCK
10/24/2002
Page 32
16
Capacity Analysis
10/24/2002
Page 33
Capacity Analysis
Effective Cycle Time Vs Takt Time
Stamping
Effective C/T:
Takt Time:
3sec
(.7)(1-.02-.025)
= 4.5 sec
3.9 sec
Drill
36 sec
(.85)(1-.005-.02)
= 43 sec
23 sec X 2 machines
= 46 sec.
Grind
Assemble
20 sec
(.75)(1-.02)
= 27.2 sec
20 sec
(.9)(1-.05)
= 23.9 sec
23 sec
23 sec
10/24/2002
Page 34
17
MANUAL
CUTTING PLATE
.90
MANUAL
MANUAL
PROFILE CUTTING
.85
PLATE JOINING
.90
MANUAL
STIFFNER WELDING
.90
N/C BURNING
MACHINE
.95
ROBOTIC
PROFILE CUTTING
.98
PLATE LINE
PLATE JOINING
.97
STIFFNER JOINING
.96
10/24/2002
Page 35
Quality
Use Statistical Process Control (SPC) at those stations where critical process
indicators demonstrate high degrees of variability.
Stiffener Length
UCL
X-bar
LCL
Out of Control
Condition
10/24/2002
Page 36
18
Supplier
250 ft coils
45,000 pcs/mo.
-30,000 L
-15,000 R
Container= 50 pcs
2 shifts
Drill
OP (2) Grind 10 20 30
300 T press
3 shifts
EPE = 1 day
C/T 36
C/0 10
20
10
Ship
19 20 19
10 8 8
Staging
General Information
- 20 days/month
- 7.2 hours avail./shift
- 2 shifts/day
10/24/2002
Page 37
SORTING
SORTING/
BUFFER
BLOCK
CONSTRUCTION
SORTING
SORTING/
BUFFER
STORAGE
BLOCK
CONSTRUCTION
10/24/2002
Page 38
19
10/24/2002
Page 39
20
10/24/2002
Page 41
Process 2
INV
Process 3
INV
Logistics/Expediting
Inventory Carrying Cost
Slower Feedback
Lengthens lead times
10/24/2002
Page 42
21
250 ft coils
MRP System
Daily
Milk Run
coil
Supplier
Batch
Stamping
300 T press
3 shifts
EPE = 1 day
45,000 pcs/mo.
-30,000 L
-15,000 R
Container= 50 pcs
50
Customer
Drill
OP (2) Grind 10 20 30
C/T 36
C/0 10
20
10
19 20 19
10 8 8
2 shifts
50
L
2x
daily
Ship
Staging
General Information
- 20 days/month
- 7.2 hours avail./shift
- 2 shifts/day
10/24/2002
Page 43
Using Sequencing
Plate Panel
Pallet
Jumbled
Must be sorted
BEFORE
Plate Panel
AFTER
Pallet
Sequenced
10/24/2002
Page 44
22
Supplier
coil
Daily
Milk Run
tote
Stamping
1 day
C/T 36
C/0 10
20
10
19 20 19
10 8 8
1 day
3 sec,
OXOX
Drill
OP (2) Grind 10 20 30
2 shifts
50
50
L
R
2x
daily
Ship
Staging
General Information
- 20 days/month
- 7.2 hours avail./shift
- 2 shifts/day
1 day
114 sec.
Customer
45,000 pcs/mo.
-30,000 L
-15,000 R
Container= 50 pcs
5050
50
300 T press
3 shifts
EPE = 1 day
(at the press)
Takt = 3.9 sec
Change C/T= 3 sec.
over O.A. = 80%
FTQ = 98.5%
C/O = 4 hrs, 1X/day
Scrap = 1.5%
Rework = none
# operators = 1/shift
V.A. = 3 sec
Shared:part # 123,ABC
Daily
Order
MRP System
Batch
Coils
Production
Control
Daily
Fax
250 ft coils
Date:
30/60/90 day
Forecast
L.T. = 3 d
V.A. = 117 s
23
Production Smoothing
Leveled
Leveled Production
Production
Traditional Production
Production
Volume
Production
Volume
Monthly Production
Monthly Production
Level Production
Production
Volume
Monthly Production
10/24/2002
Page 47
10/24/2002
Page 48
24
Best Results:
Combination of All, Which Results in the
Least Amount of Waste
10/24/2002
Page 49
Produce
Next Appro.
Order
Warehouse,
Trade Shop,
& SOC 3
All Trades
On
Demand
Produce
Next Block
SOC 6
1 Block
C/T: 20 days
Clean/Prep
Shoot Pins
0.5 days
2 days
Paint
Turn Block
Scaffolding
1.5 days
20 days
0.5 days
2 days
1.5 days
1 day
1 day
Clean/Prep
Scaffold
1 day
Insulation
Paint
All Trades
0.5 days
Erect
3 days
3 days
7.2 days
0.5 days
1 day
3 days
3 days
7.2 days
25
PLATE
SUB
PROCESSING
STORAGE
ASSEMBLY
FLAT
SHOP
BLOCK
SHOP
CURVED
PLATE
PLATE
AND
STORAGE
PROFILE
STOCKYARD
FITTING
ASSEMBLY
CURVED
STORAGE
PROFILE
PROFILE
PROCESSING
STORAGE
PIPE
SHOP
CURVED
SHOP
OUT-
SHOP
SUB
STRAIGHT
BLOCK
PAINT
SHOP
PAINT
and
SHOP
GRAND
BLOCK
CONSTR
BLOCK
SHOP
BERTH
PROFILE
STORAGE
PAINT
FLAT BLOCK
SHOP
OUTFITTING
GRAND
PLATE
PROFILE
STOCKYARD
BLOCK
PIPE SHOP
SUB-ASSEMBLY
AND
BERTH
CONSTR-
PAINT
CURVED BLOCK
SHOP
OUTFITTING
UCTION
PARTS
PANEL
PARTS &
BUFFER
SUB-
BUFFER SUB-ASSEMBLY
ASSEMBLY
SHOP
BUFFER
BLOCK
CONSTRUCTION
BLOCK
PAINT
PIPE
BUFFER
SHOPS
SHOPS
PIPE
WORKER
FACILITES
PROFILE
PROCESSING
PROCESSING
BUFFER
BERTH
B
E
F
O
R
E
STOCK
YARD
SPACE FREED UP
FLAT BLOCK
PAINT
SUB-ASSEMBLY LINE
YARD
C.B. PAINT
BLOCK
PIPE
OUT-
OUT-
SHOP
FITTING
FITTING
SPACE
FREED UP
GRAND BLOCK CONST.
OFFICES
WORKER
FACILITES
FLAT
BLOCK
CURVED
A
F
T
E
R
BERTH
26
10/24/2002
Page 53
Improvements by
Moving to Future State
On-block inventory reduced from a total of
15 days to 2 days (82% reduction)
Lead Time vs. Value Added Time (VAR)
increased from 0.67 to 0.95
Reduced complexity in information flows
10/24/2002
Page 54
27
current-state
drawing
future-state
drawing
work plan
Lean Transformation
Plan
10/24/2002
Page 55
Item
PLANT-WIDE:
Develop Standard Work process, form & training
JIT Handbook Development
Problem Solving Process, Forms & Training
Visual Workplace-Form & Employee Rating Committee
TPM (method, training, OEE tracking)
Responsible
R. Soreno
Y. Kim
J. Jackson
G. Harrison
M. Thompson
23-Jun
2-Jul
20-Jul
15-Jun
20-Jun
1
2
3
4
5
ASSEMBLY:
Map Ass'y (and Other) box
TPM workshop
Develop Pull System from Table
Plan for 2 Shift Assembly
One-piece flow/Cell Design Workshop
B.
R.
K.
V.
P.
7-Jul
15-Jul
11-Aug
30-Jul
23-Jul
Smith
Valentine
Masterson
Carrera
Gordon
Due Date
10/24/2002
Page 56
28
10/24/2002
Page 57
Approach to Lean
Transformation
Select Model Line (a major product line)
Identify Roles and Responsibilities for Lean
Enterprise Implementation
Develop a Current State Map and Future State
Map for Model Line
Develop Project Plan for Model Line
Transformation
Week by Week Transformation
Schedule for one-week Kaizen events as needed
JUST DO IT!
10/24/2002
Page 58
29
Customers
Modulator Fabrication
Material Flow
Suppliers
100/Day
1X Daily
(1/99)
3 days
S chedul ed
S hip ments
Customers
Acct Mgrs
Forecast
Meetings
Rifocs
Fiber Prep
Orders
Sales
15 - 30 days
2 days
Pu rchasing
Wafer Fab
Materials
Mgt
MRP
I
.1 days
Modulator
Fabrication
A &T
Information Flow
I
20 days
.5 days
Packing
(1/99)
1. 5 days
.5 days
Shipp ing
P ackag e P rep
Rifocs
6 days
1'-0"3
Fiber Prep
A &T
Packing
106'-0"
P ackage P rep
25'-0"
25'-0"
CI Plans
29 Griffin Road
Push South
Manufacturing Facility
days
10'-0"
Wafer Fab
Shipping
100/Day
Order
Sr. Mgt.
Suppliers
20'-0"
Loading
Dock
25'-0"
25'-0"
13'-0"
24'-0"
14'-6"
Info Flow
29'-0"
28'-0"
Bay 4a
14'-0"
4'-5 9/16"
Lunch Room
Bay 4b
Bay 3
Bay 2
Bay 1
Modulator Fabrication
Future State Map
Customers
Forecast
Meetings
100/ Day
Suppliers
Order
Sales
Orders
Current State
Pu rchasing
1'-0"
10'-0"
1X daily
Mat erials
Mgt
MRP
S chedul ed
S hip men ts
I
Pack/Ship
Fiber Prep
Continuous
Improvement
Process
25'-0"
Wafer Fab
Bay 4a
A &T
Rifocs
24'-0"
25'-0"
20'-0"
Loading
Dock
P ackage P rep
Info Flow
Material Push
Material Flow
Lunch Room
Bay 4b
Bay 3
Future State
10/24/2002
Page 59
30
Conclusions
Value Stream Mapping helps to:
visualize the product flow
show the links between the information and material
flows
identify the sources of waste in the system
establish a clear future vision for the value stream
prioritize improvement activities
focus attention on the key elements that will improve
the Lead Time and reduce the Total Cost of the
Product
10/24/2002
Page 61
References
Learning to See
by Rother & Shook
www.lean.org
Lean Thinking
by Womack & Jones
10/24/2002
Page 62
31
Single Plant
(Door to Door)
Multiple Plants
Across Companies
Learning to See
Rother & Shook
Lean Enterprise Institute
1999
Better Tool
Process
Level
Single Plant
(Door to Door)
Multiple Plants
Across Companies
and Delays
Receive
Part
Inspect
Accept
NO
Rework
YES
Move to
Machine
Machine
Machine
Part
Store
Building Lean Enterprise Excellence
Chart Symbols
Operation
- Indicates main steps in the process (usually VA).
- Part, material, process modified before proceeding.
Inspection
- Indicates inspection or check for quality.
- No modification to part, material or process.
Transport
- Indicates movement of manpower, materials,
equipment.
- Movement other than during operation (trucks,
benches, bins, conveyors).
Building Lean Enterprise Excellence
Chart Symbols
Permanent Storage
- Indicates controlled storage of material.
- Permanent storage requires authorization to remove.
- Temporary storage requires no authorization.
Temporary Storage or Delay
- Indicates a delay in the sequence of events
without record.
Examples are:
- work stacked on the floor,
- work waiting between operations,
- parts waiting to be put into store,
- letters waiting to be signed.
Building Lean Enterprise Excellence
Chart Symbols
Combined Activities
- Indicates activities performed simultaneously (ie.
operation & inspection).
- Should not be confused with Poka Yoke symbol.
Poka Yoke (mistake proofed operation)
-Indicates operation with mistake proof device fitted.
-Not an ASME Symbol.
10/24/2002
Page 1
10/24/2002
Page 2
10/24/2002
Page 3
10/24/2002
Page 4
Process Differences
The need for adaptation
VSM above shop floor
Traditional VSM
Physical Manufacturing
10/24/2002
Page 5
10/24/2002
Page 6
Version 2.2b
Version 2.1
E/C 1A 8C
Version 1
Designer
Structural Eng
Version 2.2b
Version 1
Weight Control
Version 1
ZZZ
Configuration Management
Scoping
10/24/2002
Page 7
Initial
Release
Milestone
Release I
January
February
WIP
Data
Final
Milestone
Release
Milestone
Release II
March
April
Hood Otr v8
Hood Inr v1.2
May
E/C Change
Requests
Engineering
10/24/2002
Page 8
PDN II Rel
Updated Timing
Recovery Plan
Ver I?
February
E/Cs
Program Mgmt
E/C Req 15
Structural Eng
WIP ver 14
Scoping
Major
Concern
Craft
Billing
10/24/2002
Page 10
10/24/2002
Page 11
10/24/2002
Page 12
2D Dwg Dev
Eng
3D Dwg Dev
Eng
3D Dwg Extr
Eng
Weight Control
Structural Models
Composites
Mach. Arrangement
Tech Check
Foundation Models
O&F Dwgs
Wireways Models
Wireways
CADM
Eng
Budgeting
IE
HVAC Models
Wire List
Piping Models
Cable Routing
Penetration Control
Foundation Dwgs
Structural Mfg Aids
10/24/2002
Page 13
Map Components
Work centers
Time line and scheduled events
Process boxes and activity levels
Data boxes
Primary data flows
Icons
Engineering Activity Logs
Tool Activity Tags
10/24/2002
Page 14
Work Centers
Primarily various functional disciplines
Layered and color coded
10/24/2002
Page 15
24
25
PDN 0 Release
23
PDN I
22
21
PDN II
20
FINAL
RELEASE
Clay Freeze
Body and Structures Engineering Data Release Milestones
10/24/2002
Page 16
Expedite / Overtime
Daily Loading
Task Time
(Value Added Activity)
Time in System
Changeover (if any)
Value Ratio
Definitions
Work center: Location where specific work or task is done
Time in System(Throughput Time): Time frame from
when a task is started within a work center until it leaves the
work center
Task Time: The total time it actually requires to complete a
task within a work center.
Value Ratio: Task time divided by time in system for a work
center or the sum of the task times divided by lead time for
the process
Lead Time: The time required for a single new product to
complete the entire process as defined
Time in Queue: Time a single unit spends in a specific
queue for instance a released product design waiting for a
processing resource.
10/24/2002
Page 20
10
10/24/2002
Page 21
Structural Elements
Lead Sheets
NVA-R
Discipline
Processing Throughpu
(HOURS)
t (Days)
CSI
NVA-R
Discipline
All
Processing Throughpu
(HOURS)
t (Days)
W ireways
Hot W ork
Machinery
Arrangement
Machinery
Grating
GT
Machinery
DG
Machinery
O&F
HVAC
10/24/2002
Page 22
11
Information Flow
(E/C Requests, directions, etc)
(Discussion)
(Meeting requests, data availability
notification, etc)
(Program management activity)
10/24/2002
Page 23
Activity Icons
Event Icons
12
C/D
WIP
Preliminary Level
Processing
I
Design
Phases
Level I
Level
I+
D
Level
II
C Level II
Rework
Level II
D
Level
II+
Update
To Final
C Level III
Process Chg
Rework
13
Waste Walk
Brainstorming
Visual Management
5-S
Diverse Workshop Team
Before Layout
Specific Goals
START:
ASSIGN
J.ob
Summary
DEVELOP
BUBBLE
CHART
8
INCORPORATE
COMMENTS
12
One JS Owner
.1
CONFIRM
W.B.S.
WITH
TEAM
PHASE
CUS PER
BUBBLE
CHART
2
PREP
S/C
PKG.
BUILD
CU
ASSYS
3
14
SHIP
CHECK
DEVELOP
ALL PHASES
F Phase
PRIORITY
90
TECH
REVIEW
CONTRACT
OR INHOUSE
30
.5
STATUS
ALL CU PH
TO PRL
.2
.5
APS /
ZM
REVIEW
.2
START
SCHEDULING
PROCESS
UPDATE
METRICS
& HISTORY
FILE
Product Line
History
START
REMAINING
JMLS
10
END PROCESS
START:
- LF TGI
- PACKAGING
12
3
XFER
1 LLTM
TO END USE
APPROVE
SUMM &
ALL CU PH
Self-Directed Reviews
FILE
STD.
PACKAGE
MATL
SPECALIST
COMPL JML
LLTM CU
PHASE
.2
1.5
MATL
SPECIALIST
ISSUE
LLTM
JML 1.5
10
MATL
PROCESS
After
Total Distance:
2,464 to 13,944 Ft.
Control Board
CU PHASES
JS ID
SUMMARY
HOLDER
SCOPING MTG
Actual
Y
514A0101
GUTIERREZ
75%
15
2/20/02
2/20/02
4/2/02
515AB103 LEITHEISER
97%
12
2/26/02
2/26/02
556AB102 GUTIERREZ
80%
59
2/25/02
2/25/02
556AD106 GUTIERREZ
80%
15
2/22/02
4/18/02
3/19/02
4/18/02
4/1/02
4/18/02
2/22/02
3/26/02
561AA103 GUTIERREZ
80%
585AF105
FERREIRA
0%
595AA101
FERREIRA
60%
4/18/02
29
2/22/02
2/22/02
48
3/12/02
3/12/02
Y
3/29/02
528A0101
OHMAN
99%
80
2/22/02
2/22/02
3/29/02
N/A
N/A
726 FSUM
Schedule
Actual
COMMENTS /
REMARKS
TECH REVIEW,
NOT BEING
WORKED
03/01/02
complete. Still
need BSPO
action &
submepp
03/08/02 04/26/02 authorization (no
NEED PROJECT
REVIEW
03/11/02
review on 4/18
ECD 4/22/
Returned to 260.3
for edit ECD 4/26
03/11/02
tech review ECD
WAS 4/15,
delayed man
power ECD 4/26
03/12/02
Hold up BSPO
Vancleef
clarrification
required
03/12/02
FINNEY Tech
Review ECD 4/29
03/14/02
Wheeler. ECD
3/31 Tech review
Ohman making
changes ECD
03/15/02
Goal Chart
WEEKLY
GOAL
WEEKLY
ACTUAL
CUMULATIVE
GOAL
CUMULATIVE
ACTUAL
3/3/02
10
11
68
79
3/10/02
12
80
81
3/17/02
15
86
96
3/24/02
28
114
104
3/31/02
120
105
WEEK
4/7/02
127
107
4/14/02
10
137
114
4/21/02
139
121
125
4/28/02
143
10
153
5/12/02
159
5/19/02
12
171
5/5/02
Workspace (Before)
After Picture
Workshop Results
Average Job
Summary
Current State
Potential
Improvement
Future State
15
20
35 MD
62
97
30,744
15
8
23 MD
3
26
0%
60%
34%
95%
73%
2,464 to 13,944
55 to 92%
Process Steps
70
23
67%
Hand-Offs
58
10
80%
Primary Actions:
Co-located, Cross-functional Team
Single Job Summary Owner
Self directed work and reviews (reduced management of work)
Standard processes and records
Results - Month 4
COST
DURATION
Potential Improvement
34%
73%
Improvement Goal
20%
50%
ACTUAL
16%
66%
Current JS Average
9.4 MD
33 Days
(11.2 MD Budget)