Академический Документы
Профессиональный Документы
Культура Документы
A dissertation
Submitted to
By
CERTIFICATE
I have the pleasure to certify that Shri Brijesh Kumar Gupta has pursued his
research work and prepared the dissertation titled PPP In Indian Railways- A Case
Study of Pipavav Port Connectivity under my guidance and supervision. The
dissertation is the result of his own research and to the best of my knowledge, does
not contain any part of work, which has been submitted for the award of any degree
either in this university or any other University/Deemed University without proper
citation. This is being submitted to Punjab University, Chandigarh for the degree of
Master of Philosophy in Social Sciences (M. Phil) in partial fulfillment of the
requirements for the Advanced Professional Programme in Public Administration
(APPPA) of the Indian Institute of Public Administration (IIPA), New Delhi.
Acknowledgements
CONTENTS
Contents
Certificate
Page
Acknowledgements
Abbreviations
Chapter -1 Introduction
Chapter -2 Objectives & Methodology
Chapter -3 Literature Survey
Chapter -4 Private Investments
Chapter -5 Pipavav Port Rail Connectivity
Chapter -6 Analysis & Finding
Chapter -7 Conclusions
Annexure A
Annexure B
Annexure C
Annexure D
Annexure E
Bibliography
Abbreviations
BOT
BBO
BOO
BOOT
BLOT
CA
CAGR
CC
CONCO
R
DB
DBFO
DBFOT
DP
FDI
GDP
GOI
GPPL
MCA
MOR
NPM
O&M
PC
PFI
PRCL
PPP
RPF
RFQ
SPV
VGF
WB
Chapter 1
INTRODUCTION
Indian Railways, the worlds third largest railway network has suffered due to lack of
sufficient investment and populist policies of subsidising the fares. Lack of
investments has turned once a mighty system into a slow and congested network,
that crimps the economic growth. Indian Railways, an engine of economic growth of
the country requires continuous infusion of funds and technology for its infrastructure
and modernization.
tariff policy is also fixed by the Government. There is thus a need for separate
accounting for infrastructure and train operations for initiating any long term PPP
regulatory framework. 28. It would thus be seen that Ministerial, commercial, and
regulatory powers are vested with a single entity. While it is possible for other
infrastructure projects in ports, highways & airports to be an independent system
which could be operated and maintained independently of the existing system, the
same is not possible for Railways. Here any project has to be supplementary or an
extension to an existing larger railway network. Due to this historical perspective,
railway activities are not readily available to private sector which poses a new
challenge of building capacity with private sector through PPP
During the XI FYP, the share of the private investment in major infrastructure
sectors is: electricity (49%), telecom (80%), roads (20%), ports (81%) and airports
(64%). In contrast, share of the private investment in railways has been negligible
(5%).
1.2 Risks in PPP
A project under PPP mode may be subjected to a number of technical,
environmental, economic and political risks particularly in developing countries and
emerging markets. Financial institutions and project sponsors may occationally find
that the risks inherent in project development and operation are unacceptable. To
cope with these risks, projects in these industries (such as power plants or railway
lines) are generally completed by a number of specialist companies operating in a
network with each other that allocates risk in a way that is proportional to their
exposure to the project.
Infrastructure projects have at least three phases, namely preparation and
promotion, construction and operating phase. Thus, task of the project
management is to find a way to mitigate these phase specific risks . The key
issue of the promotion and preparation stage is the commercial and political
risks related to the procurement .The major risks in different infrastructure project
are summarized below in the table.
Phase name
Promotion and preparing
Primary risk
Commercial and political risk
Risk subgroups
Competitiveness risk,
phase
Construction phase
Operating phase
scope and objectives of the project is likely draw more attention among the private
sector actors than vague and unclear project description.
Moreover, the PPP project should have full support of government, without
political unity exists, problems are likely occur in the procurement process. Lack of
political support can cause legislative delays. For instance, difficulties may appear
while PPP company is applying for necessary legal permissions for the project from
various government offices.
In sum, the commercial and political risks are always present in the
preparation and promotion phase. Thus, the key behind the successful outcome of
this phase is governments strong political engagement and unity over project
objectives in procurement process, and competitive procurement.
may
partly
delay
construction
work
by
demanding
certain
assessments during the construction and halting the work. In sum, project
management is facing construction and political risks on construction phase. To
overcome these risks project management should avoid cost overruns and
delays.
1.2.3 Operating phase
Operating phase includes political and commercial risks. Here, the risks comprise
mainly technical, market and regulatory risks, which may effect on returns. The main
source of the revenue in railway partnerships is usually the operating payments;
passenger service fees, cargo tolls, license fees, provisions and government
subsidies. Cuts and disruptions in service are likely to effect negatively on the
revenue. Indeed, customers might change their type of transportation if they cannot
account on it.
Chapter 2
Objectives & Methodology
drafting of provisions for sharing windfall gains and losses will ensure building trust
and confidence among the various stakeholders of the PPP project, hence, these are
very important for the success of these projects undertaken by agencies from using
the public funds.
The process of the PPP project is often itself a learning process for many
organizations. Thus, it is important to look already established PPP projects under
magnifying class to identify potential pitfalls to avoid them in future. The aspect of
learning from PPP projects makes case studies very valuable for all governments
planning to reform railway sector . Study of PRCL rail connectivity project involves a
systematic approach for a better railway PPP mechanisms and methods, with the
expectation that these can improve future results.
Provisions of PRCL concessionaire agreement are scrutinized with an
objective to identify the most efficient ways of mitigating the risks and overcome
challenges specific to ppp projects .We try to identify
those mechanisms,
of
different
partnerships and relationships, which are not covered fully in the thesis. The paper
focuses on one particular case study of PPP JV model port connectivity
project,
within which the topic is analyzed .To get generalized conclusion it is pertinent
that results of numbers of PPP projects are studied , hence this is a limitation.
CHAPTER 3
LITERATURE SURVEY
It is widely acknowledged within the relevant literature that there is no clear
definition for PPP which would cover all aspects of different relationships that these
PPPs encompass (Daube, Vollrath, & Alfen, 2007; Hodge & Greve, 2007; OECD,
2008) and at the same time restricting it to a more narrow description. As
Weihe (2006) argues, the concept of PPP is nebulous it allows for great variance
across
parameters
such
as
time,
closeness
of
cooperation,
types
of
In order to understand the PPP concept fully, it is also useful to distinguish it from
the traditional procurement mode. The reason for this is that the boundaries
between the two modes are ambiguous. In order to remove this ambiguity the main
differences between the two modes are identified and explained.
First of all, the main differentiating point between PPP and traditional
procurement is that in PPPs risks are shared between the private and public
partners whereas in a conventional procurement most of the risks are retained by
the government4 (European Commission, 2005; OECD, 2008) . This is in line with
the functions included in the contracts. In a PPP different tasks are bundled together
and, as a result, private partner takes responsibility for the whole package of the
associated risks. In the conventional procurement, on the other hand, the government
usually purchases a single function from a private partner and, as a result, the
private partner is responsible only for the risks associated with this function.
Consequently, in the traditional procurement the private partner has no incentives to
incorporate decisions that may favour future operations as after completion of the
task, the private partner is no longer involved in the operations of the
asset/service. For instance, if the government proposed a tender to deliver a
package of services, such as design, build and maintain a facility, the private partner
involved would be incentivized from the very beginning to make decision that could
minimize the future risks associated with cost overruns. Such an example has been
identified in the international experience by Grimsey and Lewis (2004, p. 135),
where an innovative decision to construct 45-degrees windowsills in UK hospital
was proposed with an intention to save future cleaning costs. It is hardly likely that
such a decision would have been made in the conventional procurement case.
A government would propose a tender to design a facility with input requirements
already specified. The specific requirements can be seen as a frame from the
it
does
that
through
input
specification.
if it operates better than expected, it may be awarded by, for example, receiving
higher portion of additional profits. In a traditional procurement case, on the other
hand, private partner is not awarded for an extra value added to the task it was
responsible for, however, it might be penalized for the uncompleted function.
Considering all this, the private partner in a traditional procurement is not
encouraged to provide more than the government requested for, which means
some possible gains might be overlooked.
Fourthly, the relationships involved in both of the procurement modes
differ (OECD, 2008). In the traditional procurement, in order to deliver the services
and infrastructure required, the government acts as an intermediary on the one
side it deals with direct users of the services, taxpayers, and financial markets, and on
the other side with other private companies. The idea behind such a relationship
structure is that the government gathers financing directly from the users of the
service, taxpayers and financial markets, and uses it to remunerate the other side
the private companies for the capital goods provided to deliver the public service
and develope the infrastructure. If the project is handled through a public-private
partnership, the intermediary role of the government is decreased public authority
deals with the taxpayers and the single private operator only. The role of the
private operator, on the other hand, is enhanced: private operator becomes
responsible for the intermediary role it collects financing from the direct users of
the service and financial markets and remunerates the other side other private
companies for the capital goods provided.
public sector retains the responsibility for the financial risks involved. Using
this procurement mode, public sector sets the quality outputs required and by doing
so it ensures that the private sector brings the necessary efficiency gains as well as
the asset is maintained to the standards expected. This mode of procurement is
used in water and waste projects as it ensures incentivized management and
maintenance of the asset through the bundling of functions passed on to the
private partner (European Commission, 2005).
DBFO scheme7 is characterized by involving a private partner with
responsibilities (financing, designing, building, constructing, and operating the
asset/service) attached to it. Public sectors role is to set the specific output
requirements for the private partner, whereas private partners role is to fulfill
those requirements. The DBFO schemes are usually long term and involve bundling
of functions in order to provide private partners with the necessary incentives for it to
operate in the most efficient and innovative way. These schemes involve performance
linked payment mechanisms with an aim to ensure the presence of motivation for
the private partner to operate on its full capacity. The idea behind such schemes is
that the private partner designs, builds, operates and maintains the asset for the
agreed term. At the end of this term, the asset is either transferred back to the
government or is left under the ownership of the private partner depending on the
specific structure of the scheme chosen. For example, one of the most common
schemes under DBFO is concession. Concession is described as a PPP scheme,
where exclusive rights to operate an asset or provide certain services are granted to
a private company (usually a SPV8), which in return has to design, build, finance and
operate the asset/service for the time agreed upon. These exclusive rights usually
permit the private partners to collect the revenues from the direct users of the
asset/service. Concessionaires typically own the rights to the asset/service during
the time of concession, however, at the end of this period the ownership of the
asset/service is usually transferred back to the public sector (Deloitte Research,
2006; European Commission, 2005; IMF, 2006). Literature overview shows that
concession is usually assumed to be a form of PPP (Deloitte Research, 2006;
European Commission, 2004; IMF, 2006; Ng, Xie, Cheung, & Jefferies, 2007;
PwC, 2005), however, OECD (2008) argues the opposite. First of all, it states, that
the amount of risk transferred differs in PPPs and concessions: concessions
involve higher level of risks allocated to the private partner, compared to other
forms of PPPs. Secondly, it is usual for concessionaires to collect revenues from
the direct users of the asset/service and, according to OECD, this feature
differentiates concession from other PPP forms. As a result, OECD concludes that
concessions should not be treated as a PPP.
The international experience shows that most of the time DBFO schemes are
used in transport sector for building highways, bridges, railways, whereas
concessions are chosen for mobile phone services, toll roads or provision of
municipal water.
The similarities between the turnkey procurement and DBFO schemes are that
the activities involved are same in both of the schemes, differing only in the amount of
functions involved in the arrangements. What differentiates the two schemes is that
in the first one the majority of risks remains within the public sector, whereas in the
latter risks are shared between the partners, allowing for the possibility to transfer
the optimal amount of risks to the private partner.
questioning PPPs ability to deliver additional gains, one should consider the
qualitative benefits of PPPs whether they are achievable and whether they really
provide the benefits expected. It is essential therefore to check whether the private
partner is capable of bringing in skills that the government lacks and whether it has
the expertise and know-how necessary to operate more efficiently compared to the
government (PwC, 2005).
According to the literature review, further reasons that lie behind the use of
PPP as a procurement mode differ between countries depending on the
environment present. For example, the main aim of a PPP at the early stage of its
development in the United Kingdom was to finance the public infrastructure projects
(Grimsey & Lewis, 2004; IMF, 2006; Meidute & Paliulis, 2011). The issue at that time
consisted of a growing need for public infrastructure development (as it also is the
case in Hong Kong (Cheung, Chan, & Kajewski, 2009)) and a lack of available public
funds to finance this need. As a result, a new initiative took place Private
Finance Initiative (PFI) with the purpose to provide additional funds for
public infrastructure projects. On the other hand, countries like Australia do not
have such an issue. They are capable of financing projects by themselves,
however, they still choose to involve the private sector for the possibility of
achieving additional value (Cheung et al., 2009). Moreover, Hong Kong and
Australia involve a private partner into the procurement of public services with the
aim to ensure a better quality of services. This, on the other hand, does not
seem to be the prioritized reason for the PPP development in the United
Kingdom, which emphasizes the point that reasons to implement PPP
In many of the countries the choice for PPPs, however, is due to financial
reasons (such as lack of public funds and restricted public investment). This
reason is amplified when a tight fiscal environment following the development of
European Monetary Union (EIB, 2004, p. 4) is considered as due to this European
countries experience difficulties in organizing large investment sums to finance
public infrastructure projects from the public funds only.
All in all, in theory, the main reason to develop PPPs lies behind the
concept of value for money, creating additional benefits due to private partners
expertise, know-how, ability to operate efficiently and generate additional revenues.
Despite the theoretical foundations, it is evident that PPPs are also often used in
cases when there is a lack of public funds for the growing need for public
infrastructure.
3.4. VALUE FOR MONEY
The allocation and valuation of projects risks is inherent in the value for money
concept (European Commission, 2003; Grimsey & Lewis, 2004; Nisar, 2006;
Sarmento, 2010). The aim of the risk transfer is to transfer only those risks that the
private partner could offset in a most efficient and least costly way(Grimsey &
Lewis, 2004; Harris, 2004; Nisar, 2006). Risk allocation produces highest value for
money once the optimal risk transfer point is identified: transferring too much or too
little risks results in either procuring an inefficient project or procuring a project with
excess costs incurred by the government (for example, if risks are transferred to
the private partner that it does not have control over or cannot control it at leastcost, then the private partner will require higher premium for these additional risks
assumed (Hodge, 2004)), consequently, producing lower value for money (Amekudzi
& Morallos, 2008).
Unfortunately, there is no universal solution regarding risks allocation for
every single project, however, there is a general agreement on how different risks
should be allocated. To begin with, risks in general are allocated to different
categories, such as, for example, proposed by OECD (2008): legal and political
risks in addition to the commercial ones. Categories are differentiated on the basis of
who takes the responsibility for the risks concerned private partner or the government
authority. For example, construction, supply and demand side risks lie under the
commercial risk category (market risk, project risk and internal risk) as they are
handled better by the private partner, whereas legal and political risks are assumed
to be handled better by the government. Other categorization is proposed by Li,
Akintoye, and Hardcastle (2001), who distribute risks into three levels: macro,
meso and micro. Macro level covers risks outside the project environmental,
political, legal risks that are concerned with national or industry level. Meso level
risks emerge within the projects implementation phase design, construction,
operation. Finally, the micro level risks concern risks that appear between the
partners involved, they rest on the idea that both of the parties have different
incentives and objectives, and therefore, risks due to power struggle, differences in
working methods and environment between the partners may emerge.
3.5. ADVANTAGES AND DISADVANTAGES OF P PP
As it has already been reviewed, the appropriately constructed PPPs entail the
advantage of delivering better value for money compared to the traditional
procurement approach. Delivering projects on time and on budget set (Meidute &
Paliulis, 2011) are two of the most important advantages that are hidden under the
concept of value for money. As study conducted by UKs National Audit Office
(2003) showed, from all conventionally procured projects, 70% were delivered late
and 73% with costs exceeding the initial budget (data of 1999), whereas only 22%
of PFI projects were late and only 24% delivered project in excess of the budget
(data of 2002). The reason for such a difference lies behind the risks transferred in
line with additional responsibility and accountability attached to the private partner in
the case of PPP, what incentivizes the private partner to operate in the most efficient
way. In addition, due to the long term characteristics of the partnerships, partners
involved tend to act in a more cooperative way to each other in this case creating
additional
synergy
benefits.
Private
partner
manages
complex
financial
the government from moving ahead if the project becomes inadequate. In addition,
such kind of initial discussions encourage the government to think about the project
with long term strategic goals in mind rather than focus on short term objectives.
Furthermore, PPPs ability to spread the costs of large investments
over the lifetime of the asset is seen as an attractive advantage for the public
sector. This eases the current debt of the government sector as it does not have to
incur large cash outflows immediately. It follows, that the government can get
projects financed even though in reality there are no public funds available. This
advantage could be considered from two points of view: first large investment
costs are spread out, and second private funds are considered as the new
financing opportunities for the government (Meidute & Paliulis, 2011). On the other
hand, this advantage should be considered with caution as sometimes the
government might be incentivized to prove better value for money for a PPP project
than it actually is just to guarantee the financing of the project.
Finally, from the private partners point of view, PPPs deliver opportunity
for the private sector to get involved in the new markets (telecommunication,
municipal water systems, energy, etc.) that otherwise would be closed for the private
sectors participation. In addition to this, the private partner involved in the new
markets has a support of the government, which may facilitate gathering the funds
required.
On the other hand, one of the main disadvantages of PPPs is large bidding
and contractual costs, which refer both to the government and the private
partner. Large bidding costs of the PPP projects act as a rejecting force for the
private parties as they are unwilling to invest heavily in the bidding process just
to be rejected later. What concerns government, large preparation costs consist
of feasibility studies, lawyers, etc. Moreover, PPP projects are highly complicated.
Usually, they involve more than two parties: public, private and banking sectors,
and all of these parties have their own contradicting aims. In order to construct a
unified agreement, a lot of time and capital needs to be invested on complex
negotiations.
Furthermore, PPPs are said to deliver benefits because they transfer a
significant amount of risks to the private partner. Nevertheless, it should be kept in
mind that even though most of the risks are transferred to the private partner, the
final entity that is responsible for providing services to the public is the
government. As a matter of fact, if the private partner goes bankrupt, solely the
government has to deal with the consequences and try to find other expedients how
to keep delivering the service to the public. This implies that even though the risks are
contractually transferred to the private partner, in practice, government retains a large
portion of them in case of the private partners failure.
Moreover, in a PPP agreement, government bounds itself to a single
private partner for a long term period and it agrees today for services/assets that will
be in use in further future. There is a certain amount of risk concerning the future
consumers need for the specific service. The idea behind the risks concerned is
that the partnership may end up delivering services that are no longer required by
the public. As a result, the partnership will appear to be less valuable than initially
expected.
Finally, PPPs work well only for specific projects, which are complex and
require specific private partners know-how, skills, and experience. Therefore,
advantages that are attached to PPPs are attained only if certain project
characteristics are met, whereas if the project is simple, executing it trough a PPP
implies higher preparation costs, and as a result, lower value for money.
Considering all of the above, the main idea behind the PPP option is to
have a project intricate enough that its complexity could justify additional
preparation and negotiation costs. Developing a project through a PPP usually
ensures additional benefits such as implementing the project on time and on
budget. Nevertheless, these benefits should be considered while keeping in mind
the risks involved in having the long term agreement between private and public
sectors for a certain service provisions.
3.6 CR I TIC ISM OF PPPS
Even though the majority of the international institutions seem to favour the PPP
option (EC, UK Treasury, OECD, IMF), some of the researchers see PPPs as a
language game in the politics PPP is regarded as another way of privatizing a
service/asset (Hodge & Greve, 2007). This point of view has been neglected by
many other researchers who represent arguments proving that PPPs differ from
the privatization (Grimsey & Lewis, 2004; Harris, 2004; Hong Kong Efficiency Unit,
2008; OECD, 2008). One of the first differences identified is the sale/transfer
concerned. PPP involves government granting a right to the private party to
develop and provide certain services/assets for a period of time, whereas
privatization, in general terms, involves the sale of the asset. This assents to the
amount of risks transferred. In PPP case, the amount transferred differs on the
type of PPP chosen. Concession is the mode of PPP that involves the largest
amount of risks transferred to the private partner; however, it still does not
encompass the transfer of all risks. On the other hand, privatization includes the
sale of the full package, which means the transfer of all associated risks. In this
case, government is left with no direct responsibility for the service provided/asset
developed, whereas in a PPP case, government is the one that retains the initial
control and responsibility for the service/asset (Harris, 2004). If the private partner
goes bankrupt, the service/asset is transferred back to the government. If the
private partner does not operate to the standard required, the government has a
right to intervene and punish the private partner. All in all, it is true that privatization
and PPP share some similarities, but the idea of PPP is that it shares some
superior features of the privatization as well as of the conventional procurement
mode as Grimsey and Lewis (2004) argue: PPP fills in the missing gap between
privatization and the traditional procurement approach.
Other critiques concentrate on the idea that the government should be
fully responsible for the services provided as this is the role of the government and
not the private sector. However, as Harris (2004, p. 3) argues, the provision of public
services (such as free education, transportation or health) by the government is
comparatively recent development. So the question rises whether it is the actual
provision of the services or is it the regulation and control of the service provision
(what kind of services to deliver, what kind of standard should be kept, what policy
to follow, etc.) that is the role of the government? As Harris (2004) concludes the
role of the government is to ensure that a policy is being adopted. If delivering the
policy through the parties that are able to do that in the best possible way while
additionally creating value for money to the public means that the private partner
should be involved, then the advantages of private partners efficiency and
innovative skills should be utilized.
Further critique concerns the view that PPPs are a trendy politics. This
means that countries might favour PPPs over the conventional procurement due to
the lack of public funds available. Owing to this, the government is left with a
choice not between a PPP and a conventional procurement project but with a
choice between a project and no project at all as a government is unable to finance
the project from its own funds (Robinson, 2000; Shaoul, 2005). The problem of such
a preference for PPPs is that there is a high degree of possibility for approval of
projects that do not generate better value for money but are accepted for the
financial resources only getting a project procured while having debt off
governments balance sheet (Maski & Tirole, 2008). In addition to this, as value of
PPPs are most of the times assessed by using PSC, problems appear when
hypothetical risk-adjusted nature of the model is considered. The PSC depends
highly on the assumptions employed (Amekudzi & Morallos, 2008), one of the
most important one being the rate used to discount the cash flows of the PSC.
Furthermore, when risks allocation is performed, it is criticized that not all of the
risks may be identified and valued (Amekudzi & Morallos, 2008; OECD, 2008;
Shaoul, 2005), thus leading to inaccurate PSC estimate. As OECD (2008) argues
some of the risks may be left out and neither of the party initially agrees to take
responsibility for it, however, once the risk evolves, it is the government and the
public that have to bear the consequences and not the private partner, leaving
some element of value for money out of the initial estimate. Considering all this, the
value for money estimate may be easily adjusted in order to make the PPP proposal
more attractive, which is seen as a problem when the only reason for PPP project
implementation is the lack of public funds.
Moreover, it has been noted that an advantage of PPP is its ability to spread
out the huge initial investment costs throughout the years of the lifetime of the
asset. This means that the government avoids large investments today and is able
to incur them later on in smaller amounts. However, who may guarantee that the
government with increasing number of PPPs will be capable of financing these
payments in later years? Will it pass this contingent liability to the future taxpayers
(Harris, 2004)? In addition, who can be reassured that the same
service/infrastructure will be necessary in, for example, 30 years? In addition, will
the taxpayers be happy for paying taxes for the services that are unnecessary
anymore? These questions are especially relevant to the cases of PPPs where the
government contracts to pay availability payments for the services provided by the
private partner.
Overall, PPPs attract some significant critiques, however, it should be noted
that PPPs are not a magic solution for the conventional procurement issues. The true
experiences of PPPs have not been observed yet as it takes time to acknowledge
the full impact of each PPP, however, the initial stages of the PPP and the
theoretical foundations allow PPPs to be considered as a possible way to bring on
additional efficiency gains to the public sector.
Chapter 4
Private Investments
There is a growing demand for investment to improve the quality of public services.
Public sectors or governments worldwide are experiencing
significant
challenges as public resources are often insufficient to meet the increasing demand
principles and contractual commitment reflecting a balance between profit and the
need for regulation to ensure value for money in the use of public resources. Under a
PPP approach, public sector expertise are complemented by the strengths of the
private sector such as technical knowledge, greater awareness of commercial and
performance management principles, ability to mobilise additional investment,
innovation, better risk management practices, and knowledge of operating good
business models with high level of efficiency. In a developing country like India, the
model of this type has enormous opportunities in the upliftment of economy specially in
infrastructural and service sectors.
4.1 Evolution and Development of PPPs
Publicprivate partnerships have a long history in many countries, but grew
significantly more popular during the 1980s. At this point, private sector thinking was
introduced and used in the public sector, and market-based criteria were applied to
the delivery of public products and services. During the 1990s, New Public
Management (NPM) and market-based philosophies further influenced public
management in many countries. Because the degree of complexity of the problems
needing to be solved increased as a result of growing interdependencies between
assignments and parties involved, more partnerships between public and private
sectors were formed.
Publicprivate partnerships have the longest tradition in the USA. In the 1950s
and 1960s, PPPs in the USA were set out by the federal government as a tool
for stimulating private investment in intercity infrastructure and regional
economic development. They became an explicit instrument during President
Carters administration: the 1978 National Urban Policy and Urban Development
money and skills. However, there are major differences in the motives and
procurement rules in different forms of PPP between countries.
4.2 Types of PPP Models
There are various types of PPPs, established for different reasons, across a wide
range of market segments, reflecting the different needs of governments for
infrastructure services. Although the types vary, two broad categories of PPPs can
be identified: the institutionalised kind that refers to all forms of joint ventures
between public and private stakeholders; and contractual PPPs.
above-mentioned
elements:
namely
finance,
design,
construction,
management and maintenance. They are often financed by user fees (e.g. for
drinking water, gas and electricity, public transport etc. but not for social PPPs
e.g. health, prisons, courts, education, and urban roads, as well as defence).
risk of cost overruns is transferred to the private sector. (Many do not consider DBs
to be within the spectrum of PPPs and consider such contracts as public works
contracts.)
Operation License: A private operator receives a license or rights to operate a
public service, usually for a specified term. This is often used in IT projects.
4.2.3 PPP vs. Privatisation
The central question on governance from the perspective of PPPs is how to
organise the interaction between public and private sector. The main goal is to
improve efficiency, quality of public services and products, and legitimacy. The
question how to organise a PPP cannot be answered in general for every market,
and, in most cases even for every project, the answer has to be customised.
Confusion about the PPP concept is striking in the political and social discussion on
these governance questions. Often, PPP is used as a synonym for privatization.
Nevertheless, there are significant differences between PPP and privatisation. In
PPPs, public and private parties (actors) share costs, revenues and
responsibilities. Privatisation represents the transfer of tasks and responsibilities to
the private sector, with both costs and revenues being in private hands. The confusion
impedes a rational discussion about PPPs since all the disadvantages of
privatisation are imputed to PPPs.
The key differences between public-private-partnership and privatisation may
be summarised as :
Bombay (1874), and the power generation and distribution companies in Bombay
and Calcutta (now Kolkata) in the early 20th century are some of the earliest
examples of PPP in India. Since the opening of the economy in 1991 there have
been several cautious and tentative attempts at PPP in India. However, most
PPPs have been restricted to the roads sector. Large private financing in water
supply has so far been limited to a few cities like Visakhapatnam and Tirupur. Most
PPPs in water supply projects have been through municipal bonds in cities such
as Ahmedabad, Ludhiana, and Nagpur. West Bengal has recorded significant
success in housing and health sectors. For example, the housing projects coming
up on the outskirts of Kolkata City are a good example of what a PPP model can
deliver in terms of quality housing and quality living conditions to the lower
middle class and the middle class. Gujarat and Maharashtra have had success
especially in ports, roads, and urban infrastructure. Karnataka also has done well in
the airport, power, and road sector. Punjab has had PPPs in the road sector
A study conducted by the World Bank of 12 states and 3 central agencies in
2005 in India found only 86 PPP projects awarded by states and select central
agencies (not including power and telecom). Their total project cost is Rs 339.5
billion. An optimistic projection of PPPs growing by, say, five times between 2004 and
2006, in a country of Indias size, that is, around 500 projects, is not very
encouraging. The largest number of PPP projects is in the roads and bridges
sector, followed by ports, particularly Greenfield Ports. Apart from these two
sectors, there are very few PPP initiatives
Across states and central agencies, the leading users of PPPs by number
of projects have been Madhya Pradesh and Maharashtra, with 21 and 14
awarded projects, respectively, all in the roads sector, and the National Highways
Authority of India (NHAI), with 16 projects. The other states or central agencies
that have been important users of PPPs are Gujarat (9 projects) and Tamil
Nadu (7), Karnataka (4) and Ministry of Shipping, Road Transport and
Highways (MOSRTH) (4). However, looking at a breakdown by estimated
project size, we see that MP becomes significantly less prominent due to the large
number of relatively small-sized projects in its portfolio, falling to 3 percent of total
project costs.
States like Andhra Pradesh, Gujarat, and Punjab have legislation which
clearly defines what infrastructure is and how these infrastructure projects are going
to be executed by the private sector. Some other states have administrative
frameworks in place for decision-making. Despite these frameworks, in the last five
years the number of successful projects has not increased substantially. Madhya
Pradesh and Maharashtra have exhibited the possibility of developing a PPP
program in a single sector (roads) by building up capacities in line departments.
However, they have no PPPs in other sectors, possibly in part because of the absence
of platforms to transfer acquired skills to other departments. Gujarat, Andhra Pradesh,
and Punjab have developed cross-sectoral enabling legislation and dedicated
agencies but have not had a very successful track record in taking PPPs to the
market. Some other states, such as Tamil Nadu, have developed a few PPPs across a
wide range of sectors, without explicit cross-sectoral PPP units or legislation.
Rajasthan has a cross-sector policy/ regulatory framework and a project
development company but has concluded only one tourism project and a few road
projects. Therefore, there seems to be no clear link between institutional structure
and success of PPP. One possible reason for this is the non-availability of sufficient
skilled staff in the Government of India as well as in the states, who could
actually look at how PPP projects should be structured. This is one important
area where significant capacity building is required, both at the Centre and in the
states.
Various studies in developed and developing countries have shown that
there is a significant shortfall in infrastructure investment and lack of maintenance
resulting in a deteriorating stock of public infrastructure capital to support the
deliveryof core public services. Public-private partnership is an approach that is
increasingly adopted to facilitate the improvement of public services where there are
public sector budgetary constraints and there is a need for innovation by stimulating
private investment in infrastructure facilities such as health, education, transport,
defence and social housing, regeneration and waste management. The
alternative public-private partnership is a whole-life or integrated approach from
design to facilities management and service delivery aimed at addressing the
problems associated with the traditional approach by creating a shift in emphasis
from building contracting and lump sum payment to service contracting and
performance-based payment. However, it is important that appropriate policy,
strategic and implementation structures and processes are in place to address the
key objectives of the public sector in PFI/PPP projects. Another critical success factor
that should be added is sustainability to reflect the increasing need to balance
economic objectives with environmental and social obligations. putting
Typically, in larger countries, the national PPP units will not undertake the
projects but rather provide the policy, technical, legal and other support mechanisms
to local authorities and government ministries that have the responsibility of the
project together. Practically, it can help the relevant procuring authority more
confidently manage the whole process from the development of the initial project
design through to the bid evaluation process and post-financial close. In India, NHAI,
MOSRTH attracting PPP projects, is an example of such mechanism. Though
PPP is a relatively new approach to procurement, lessons could be drawn from the
experiences of developed and developing countries on the conditions for the success
of PPP. As a relatively late entrant in the PPP development process, India can learn
and benefit from these lessons.
Chapter 5
Pipavav Port Rail Connectivity
5.1 General
Port Pipavav is located at Latitude 20 54N and Longitude 71 30E on the west
coast of India, in the state of Gujarat. For decades the port was functioning as an
anchorage serving the then existing minor Port called Port Albert Victor. It is
protected by islands on either side, which act as a natural breakwater making the
port safe in all weather conditions. The presence of these islands also leads to the
tranquility in the harbor as well as ensures the wave height is less than 0.5m most of
the time.
In 1992, it was decided to develop the port as an all weather facility for
handling bulk, liquid and container cargo. A private limited company called Gujarat
Pipavav Port Limited (GPPL) was incorporated as a joint venture between Sea
King Infrastructure Limited and Gujarat Maritime Board, a state owned
organization.
General cargo handling operations at the Port commenced in November
1996 followed by container handling operations in 1998. Presently, the container
terminal offers direct services to Europe, US East Coast, China and the Far East.
Port Pipavav is today recognized as one of the principal gateways on the West
Coast of India.
The port is being developed for handling 19 million tonnes of cargo per
annum including 13 million tonnes of containerized cargo. APM Terminals is
making an investment of US$ 245 million to develop the facilities. With available draft
of 13.5 metres, the port is also able to handle Post-Panamax vessels.
5. 2 Connectivity
Initially, there was no rail connection to the port. The nearest railhead was
located at a distance of 18 km on the Rajula-Surendranagar metre gauge line of
Western Railway, beyond which the broad gauge rail network was available. In the
absence of a rail connection, the Port could not be adequately developed; hence
its keenness for a proper rail connectivity, preferably a broad gauge rail link.
Indian Railways had earlier sanctioned a project to convert the existing
Rajula-Surendranagar metre gauge line into broad gauge as a part of the
railways long-term plans for broad gauge network on the entire system.
However, financial constraints had prevented its timely execution. In the
2003. The table below shows the various contractual agreements and the dates of
their execution between different parties.
Table 1: Chronology of Agreements
Date
Sl.
No.
Agreement
1
2
3
4
17.04.2002
Operation &
Maintenance
Agreement
Transportation &
Traffic Guarantee
Agreement
15.01.2003
15.02.2003
Shareholders Agreement
28.03.2001
Parties to Agreement
MOR & GPPL
MOR (GOI) & PRCL
MOR (GOI) & PRCL
PRCL & Western
Railway (GOI)
20.01..2000
28.06.2001
28.06.2001
13.03.2002
administered by Railway Board. Indian Railways (IR), the fourth largest railway
network in the world, has a route length of 63,500 km. IR has 1.5 million
employees running over 8,000 passenger trains and 5,500 freight trains every day.
It moves over 17 million passengers and 2.0 million tones of goods daily. Its rolling
stock fleet includes some 8,300 locomotives, 4,400 coaching vehicles and
210,000 freight wagons.
Gujarat Pipavav Port Limited: Gujarat Pipavav Port Limited (GPPL) is one of the
first private sector ports in India. It was incorporated in 1992, as a joint venture
between Sea King Infrastructure Limited (SKIL) and Gujarat Maritime Board for
developing and operating an all-weather port for handling bulk, liquid and container
cargo at Pipavav, in Amreli district of Gujarat. The cargo handling operations had
commenced in 1998.
GPPLs principal shareholders are:
i.
iii.
iv.
v.
vi.
Pipavav Port
February 1992 GMB
Sea
June 1998 GMB divests its entire equity in favour of SKIL Group
Principles signed
September, 1998 Lead promoter SKIL licensed to develop, operate,
Maersk Sealand, the port operator, has started dedicated weekly service
between Pipavav and Salalah (Oman) and Jebel Ali (United Arab Emirates), which
has contributed to increase in container throughput at Pipavav port.
5.9 Shareholders Agreement
The basic structure of the company (PRCL) is defined in the Shareholders
Agreement (SHA). In addition, the other formalities like registration of the
Company, Memorandum of Articles of Association, registration with various
government revenue agencies like Sales Tax etc were also completed. The salient
features of the SHA are given in the table in Annexure - B.
5.10 Project Implementation Process
Project
Development
Phase:
The
gauge
conversion
of
the
different materials at various sites and a team of supply chasers was deployed at
important suppliers locations. These teams, working in tandem, kept WR informed
of the arrival dates to ensure inspection and certification. In the case of ballast,
several laboratories were approved for testing.
Labour contracts for track laying and signalling and telecom works were fixed
by WR including station buildings and staff quarters
5.11 Strengths of the Project
Both shareholders, namely, MOR and GPPL have gained substantially by
the Joint Venture arrangement of implementation.
Gains to MOR:
It would have completed the gauge conversion at its own cost in due
course of time as it was an approved work included in WRs works
programme. The WR would have incurred an expenditure of over Rs. 400
crore at present-day costs. With the JV arrangement, project was
completed with the total expenditure of only Rs. 98 crore which MOR
contributed as equity. The remaining funds came from other partner and
through debt from open market, servicing of which was not MORs
responsibility.
The project was completed in less than 2 years of contributing equity
MG line.
MOR was losing Rs. 20 crore per year on operating this un economical branch line. Losses of three years would wipe out the
Gains to GPPL
GPPL got rail connectivity to the port in time in fact, much before
port was ready for producing guaranteed traffic volumes of 3 MT.
-
Port connectivity cost to GPPL was only Rs. 98 crore. Otherwise, they
would have had to construct the entire line at their expense as a private
siding.
Early connectivity enhanced the share value of GPPL. - Port got traffic
clearance guarantee from MOR.
ii.
Procurement:
-
Materials to be inspected by WR
rails to Sabarmati in the WRs flash butt welding plant, unload, have three rail
panels welded, load on rail wagons, transport the panels to several sites on the
MG rail track, unload and stack them for laying on the formation. Other option was
to organize welding at a site on the line by using mobile welding plants. In 2002,
mobile welding plants were not easily available. Therefore, welding was organized
at Sabarmati. The plant had limited capacity and was overloaded with the pending
work of WR. It was, therefore, necessary to increase the capacity of the plant
which was done at PRCL cost.
O&M Agreement: The fixing of the elements of fixed costs to be paid to WR for
O&M of the line was the main concern. Each item of maintenance had to be
analysed and bench marked with the best practices. Help was taken from the
Konkan Railway to define the elements and put down norms and unit costs. Staff
costs being the major cost, tremendous efforts were required to set manning
norms at half of what is followed on IR. There were problems of redeploying
surplus staff. The process of redeployment was started early in 2001 and by 2004 it
was possible to relocate most of the surplus staff. Help of WR was invaluable in this
regard. This manning norm and practice became a benchmark for WR also for
their future projects.
5.15 Funding Arrangements
The Project line has been funded through a mix of equity and debt. The total
project cost of Rs. 373 crore, was met by equity of Rs.196 crore and a debt of Rs.173
crore. The completion cost was lower at Rs. 367 crore.
Table: Project Funding
Source
MOR equity
GPPL equity
Total Equity
Debt
Total
Amount in
Percentage
Actual
Percentage
98.00
crore
98.00
196.00
173.00
369.00
26.6%
26.6%
53.1%
46.9%
100.0%
95.66
amount
98.00
193.66
173.00
366.66
26%
27%
53%
47%
100%
5.16Means of Finance
PRCL being an equal partnership between MOR and GPPL, the capital cost
of Rs. 373 crore was financed by equity contribution of Rs. 196 crore on 50-50 basis
by the two promoters and the balance by raising debt from the open market. The
debt equity proportion was approved at 2:1 but actually it was maintained at
0.86:1. The means of finance are given in the table below:
Table : Means of Finance
Sl. No.
1.
(a)
(b)
2.
Particular
Amount (in
% of project cost
Equity
Ministry of Railways & its
GPPL & its Associates
PSUs
Debt from FIs and Banks
Total
100
100
173
373
27
27
46
100
IL&FS Investment have contributed their portion of the share capital, i.e., Rs.
98 crore. Until March 2005, GPPL was in default of not paying nearly Rs. 26 crore of
its share capital amount, which it has subsequently paid.
Debt funding: PRCL has availed long term loans amounting to Rs.173 crore
from various banks/financial institutions, details of which are set out in the table below.
PRCL had taken an initial loan of Rs.173 crore with a moratorium period ending on
31st March 2005 and repayment in 7 years starting from 1st April 2005. However, the
company had renegotiated with the lenders and got a further extension of
moratorium period from the lenders till 31st March 2007. Also, the lenders reduced
the interest rate to 8 percent instead of the original interest rates. Now this loan is
repayable in seven instalments starting from 1st April 2007. The lenders have also
agreed for deferment of interest on term loan for the period January 2005 to March
2007.This amount will be treated as Funded Interest on Term Loan (FITL) and
added to the loan amount which will be payable over the period of the loan term.
Apart from the above loans the company had taken a short-term loan of
Rs.25 crore from IRFC (Indian Railway Finance Corporation) due to delay in
receiving Railways share of equity, which was repaid during 2005-06. The total
debt is Rs. 204.70 crore inclusive of FITL and would be repaid in seven years
starting from FY08.
Lender
Loan
amount
Funded
interest Total
loan
term
loan
Rate of
interest
50.00
9.16
59.16
8.00%
Indian Railway
30.00
5.50
35.50
8.00%
25.00
24.00
24.00
10.00
10.00
173.00
4.58
4.40
4.40
1.83
1.83
31.70
29.58
28.40
28.40
11.83
11.83
204.70
8.00%
8.00%
8.00%
8.00%
8.00%
As per the traffic projections, GPPL is required to pay the traffic guarantee amount
for FY06 and FY07. The traffic guarantee shortfall is to be calculated as follows:
Traffic shortfall for the year = Traffic guarantee - Actual traffic achieved
during the year.
The amount of traffic shortfall is calculated by multiplying traffic shortfall @
Rs. 0.74 per ton per km.
Any variable cost saving due to traffic shortfall is calculated based on the
variable cost per MT for the year.
Net traffic guarantee = Traffic shortfall amount Variable cost saving. The net traffic
guarantee so calculated is payable by GPPL as the base traffic.
Traffic Projections
In view of poor performance in the first three years of operation, GPPL revised the
traffic projections to make them more realistic. Traffic projections were based on
the port traffic projections given by GPPL. It was understood that the project line
would fully depend upon the port traffic. Some corrections were made to make the
projections more realistic by moderating and scaling them down.
Traffic Performance: The actual traffic on Pipavav Railway was 0.36 MT in the
first year of operation (2003-04) which went up to 0.88 MT in 2004-05. The
principal commodities moving on the corridor are containers, gypsum, coal,
foodgrains, salt, and fertilisers. The projected cargo for 2005-06 was estimated at
1.38 MT and 1.59 MT was achieved by the company for this period. The traffic
performance of the company for the first three years was rather poor as shown
below:
2003-04
0.26
0.13
0.39
2004-05
0.10
0.78
0.88
2005-06
0.55
1.02
1.57
There was a serious problem and delay in finalizing the order for
rails; first Railways agreed to supply, then withdrew the offer. There was
again a delay in finalizing an international tender for rails.
Subsequently, after 6 months of delay, Railways agreed to the supply of
rails from Bhilai steel plant.
The most serious weakness of the project was its inability to get the
projected traffic. Even guaranteed traffic of 1, 2 and 3 MT in the first
three years respectively did not materialize. This created a serious
problem of inability to service the debt. Failure to do so would have
rendered the Company as an NPA and could have resulted in
bankruptcy.
All this was due to the fact that GPPL went under restructuring and
replacing the original promoter SKIL with AP Moeller. The new
management of GPPL dithered in honouring the commitments made by
GPPL toward payment of traffic guarantees.
The port development was tardy and even bulk traffic like coal and
fertilizers could not be handled resulting in poor materialization of traffic.
The pace of port development is still slow till the writing of this
report.
Chapter 6
Indian Railways in fourth largest Railway network in the world in terms of route
kilometers. Against the total route length of 64640 Km. only 21034 Km. is electrified.
Considering the requirement of economy and size of country the expression of
railway network has been inadequate. Indian Railways here added 11864 km. of
new lines since independence. It has not been able to cover major areas in country.
Gauge conversion has been instrumental in adding capacity in the system despite
low addition of new line. The network needs extensive modernization of
infrastructure to meet the needs of rapidly growing economy.
It is estimated that during the 12 th plan period Rs. 519221 Crore investment is
required to achieve the plan objective visualized for this period. This include Rs.
194221 Crore of general budgetary support (GBS), 225000 from internal and extra
budgetary resource (IEBR) and reaming Rs. 1,00,000 Crore is expected from private
sector.
The concession agreement unbundles risks and costs and allocates them to
the party best suited to manage them. Throughout, it seeks to achieve a reasonable
balance between risks and rewards for all participants. The predictability of cost and
obligations will be a key factor in improving efficiencies and reducing costs.
Various provisions incorporated in PRCL concessionaire agreement are
examined below to evaluate their suitability for balancing the risk among the various
stake holder and also operation of the agreement during the period of concession. A
compression of these provisions is also made with the corresponding relevant
clauses in the newly issued model concession agreement for joint venture project
through PPP mode by Indian Railway.
6.1 Linking traffic variation with the Concession Period
From the scrutiny of PRCL Concessionaire Contract it is found that no provisions
are available in regard to linking of traffic variation with period of concession.
Important clauses linking the traffic variation with the period of concession are
reproduced below from latest MCA issued by Indian Railways.
24.1.1The Parties acknowledge that the total NTKM during the Concession
Period as [on October 1, 20__] is estimated to be ***** (the Target
Traffic)13.
24.1.2 In the event that, as on expiry of 25 th (twenty fifth) year after Appointed Date
the actual NTKM shall have fallen short of the Target Traffic by more than
[4% (four per cent) thereof or exceeded the Target Traffic by more than [4%
(four per cent) thereof, the Concession Period shall be deemed to be
modified in accordance with Clause 24.2. For the avoidance of doubt, in the
event of any Dispute relating to actual NTKM, the Dispute Resolution
Procedure shall apply.
24.2.1 Subject to the provisions of this Clause, in the event actual NKTM shall
have fallen short of the Target Traffic, then for every 2% (two per cent)
shortfall or part thereof as compared to the Target Traffic, the Concession
Period shall be increased by 6(six) months or part thereof; provided that
such increase in Concession Period shall not in any case exceed 5 (five)
years.
24.2.2 Subject to the provisions of Sub-clause 24.1.1 above, in the event actual
NKTM shall have exceeded the Target Traffic, then for every 2% (two per
cent) excess or part thereof as compared to the Target Traffic, the
Concession Period shall be reduced by 6(six) months or part thereof;
provided that such reduction in Concession Period shall not in any case
exceed 5 (five) years.
The Target Traffic shall normally be a number based on 5% (five per cent)
Cumulative Average Growth Rate over the base traffic assumed for the Rail
System. The target traffic shall be for the entire Rail System and not for
individual lines or sections of the Rail System.
During the initial period of concession actual traffic and targeted traffic as
stipulated in traffic guarantee agreement, is compared below.
Target Traffic
Year
Shortfall (MT)
guarantee (MT)
2003-04
2004-05
2005-06
2006-07
2007-08
0.39
0.88
1.57
2.28
2.18
1.0
2.0
3.0
3.0
3.0
0.61
1.12
1.43
1.72
1.82
PRCL entered into a Traffic Guarantee Agreement (TGA) with GPPL and MOR. As
per the terms of this agreement, GPPL has to provide 1 million tons (MT) of cargo in
the first year of operation (2003-04), 2 MT in the second year of operation and 3 MT
from the third year onwards. So, from 2005-06 GPPL would be required to provide
at least 3 MT cargo for the project line and MOR/WR as part of this agreement has
to provide sufficient rolling stock for evacuation of minimum guaranteed traffic
(MGT). In case there is any shortfall in the traffic, PRCL will be compensated for any
shortfall by GPPL. While Railways also at times defaulted in 100% evacuation, the
port traffic was continuously low over the years.
In the latest MCA Provision of variation of traffic at the rate of 5% growth
from base year is kept and concession period if to be modified on the basis of
available actual traffic in comparison to estimated traffic used for deciding the
concession. To address the issue of windfall gains the Agreement providers a
review of concession in terms of traffic materialization after a period of 25 years
from signing of concession agreement. The concession period of 30 years will
be reduced or extended symmetrically depending upon traffic exceeding/going
below a Projected NTKM threshold. For this purpose the traffic will be measured
after a period of 25 years from signing of concession agreement. However, the
concession period shall not be less than 25 years or extend beyond 35 years.
However review of concessionaire period is to be done only after 25
years from the appointed date which may not likely to satisfy private
concessionaire. Due to this private concessionaire may not get adequate
confidence in regard to availability of projected traffic and corresponding
projected revenue.
6.2 Selection of Concessionaire
the
PRCL project
Indian
Railway
is
playing
both
the
roles
4.3 (c) without the prior approval of MOR, not to assign or crate any lien or
encumbrance on the Concession hereby granted except as permitted in this
Agreement
(d) without the prior approval of the MOR, not to assign the whole or any part
of the Project nor transfer, lease or part possession therewith except as
permitted in this Agreement.
Agreement,
the
Nominated
Company
substituting
the
this Agreement on the date of such substitution, MOR shall by notice grant a
Cure Period of 120 (one hundred and twenty) days to the Concessionaire for
curing such breach.
33.4 Assignment by MOR
Notwithstanding anything to the contrary contained in this Agreement, MOR
may, after giving 60 (sixty) days notice to the Concessionaire, assign and/
or transfer any of its rights and benefits and/or obligations under this
Agreement to an assignee who is, in the reasonable opinion of MOR,
capable of fulfilling all of MOR s then outstanding obligations under this
Agreement.
From private partners point of view, the project assets may not constitute
adequate security for lenders. It is the project revenue streams that constitute the
mainstay of their security. Lenders would, therefore, require assignment and
substitution rights so that the concession can be transferred to another company in
the event of failure of the Concessionaire to operate the project successfully. The
MCA accordingly provides for such substitution rights.
DRV if the default occurs after 15 years but within 25 years of COD.
The Depreciated Replacement Value (DRV) of such Assets if the default
Transfer fees and charges, if applicable and other incidental expenses incurred at
the time of Termination or Normal Transfer shall be borne by the MOR and PRCL
in the following proportion.
S.No.
Head of Charge
Onus
1.
2.
agreement by MOR
3.
4.
(management
time,
cost
Shared by both
be
borne
by
each
Party
of respectively
(b) 70% (seventy per cent) of the amount representing the Additional
Termination Payment:
Provided that if any insurance claims forming part of the Insurance Cover
are not admitted and paid, then 80% (eighty per cent) of such unpaid claims shall
be included in the computation of Debt Due.
For the avoidance of doubt, the Concessionaire hereby acknowledges that no
Termination Payment shall be due or payable on account of a Concessionaire
Default occurring prior to COD.
30.3.2 Upon Termination on account of a MOR Default, MOR shall pay to the
Concessionaire, by way of Termination Payment, an amount equal to:
(a)
Debt Due;
(b) 150% (one hundred and fifty per cent) of the Adjusted Equity;
and
(c)
Chapter 7
Conclusions
Concession agreement which consists of matrix of risk and rewards to
stakeholder is one of the important instrument of final outcome of delivery
objective of the project. Various provisions incorporated in concession
agreement to balance risks and responsibilities among the stakeholders are
examined and compared with the available provisions of latest MCA .Role of
various provisions of PRCL concessionaire agreement is also evaluated during
the actual construction and operation of project.
7.1Proper partner
Partner selection for PRCL project was contextually (strategically), rather through
open system of calling of EOI along with technical details. Hence element of
competition was completely absent in the process for selection of partner for this
project. GPPL, the chosen partner was not having any experience in dealing with
construction and operation of a railway project, hence GPPL was not suitable to
take these risk in such a complex project. Hence during the operation phase,
instead of applying innovativeness within the concessionaire agreement GPPL
demanded number of modification in concessionaire and other subsidiary
agreements. These are given in annexure- 99
7.2 Same regulator and operator
In the PRCL Rail connectivity project IR has assumed the role of a licensor,
regulator and operator (being 50% partner in PRCL). This is against the basic
principle of natural justice (player cannot also be umpires). The principle of
checks and balances aiso prohibits both roles to one authority as there will be
conflict of interest and level playing will field not be available to private player.
It is unrealistic to expect from one partner to forgo their power and
priveleges particularly when these are related to contracts and fiefdoms. It is in
vain to anticipate the progress when fundamental principle of human behavior
are violated.For any PPP framework reform to success it is necessary that
decision making is vested in institutions that are free from any conflict of interest.
In the PRCF project which is being studied, Railway had played all the
three roles i.e. licenser, regulator and operator. In other sector live telecom till the
conflict of interest is removed success of PPP could not be achieved in JV
projects.
Role of Railway Ministry as a regulator and operator has delayed the execution
of various partnership agreements in this project.
7.3 Risk transfer
Obligations of various stakeholders and subsequent action in their default, are
not properly incorporated in concessionaire agreements. It is observed that only
risk which GPPL was to bear was guarantee for availability of minimum
aggregate cargo of 1, 2, 3 million tonnes in first three years respectively. All the
risks in regard to construction and operation of railway line were to be borne by
Indian Railway. Hence inspite of signing so many complex agreement major
risks of construction and operation remained with Indian Railway and could not
be transferred to other partner. Ideally concessionaire agreement should
unbundle the risks in the project and these are to be allocated to party which is
capable to manage these easily. But GPPL was not capable of neither
construction nor operation of the project. Hence the selection of the partner were
not as per the accepted principles of PPP.
7.4 High debt cost for private sector
With JV arrangement Indian Railway could complete project (including gauge
conversion) total equity capital of 98 Crore which IR contributed its share of equity to
PRCL. The remaining funds came from other partner and through open market. As
per the recent study by Sh. Ajmer Singh it is reported that for a highway project cost
of debt to private sector is higher in comparison to cost of debt to public sector. In the
study it is brought out that due to higher cost of raising debt for private sector over
public sector has resulted in 60% higher unit cost for highway projects in BOT. From
the above it is observed basic purpose of project partner( i.e. GPPL) in this project is
to provide additional finances and to enable creation of an instrument for arranging
finance from the market, but as seen above that involving a private partner just for
arranging the finance for the project is likely to cause higher cost of financing to the
project.
7.4 Provisions for uncertainties
No provision is available in concession for dealing with uncertainties which was
one of important reason for many problems in construction and operation of
project. Government can compensate private sector loss via different kinds of
compensation mechanisms such as direct subsidy payments, availability
payments, demand guarantees, loan guarantees and viability gap funding.
Government should carefully consider which compensation mechanism to apply in
the PPP and take account dilemma always attached to it. Indeed, government