Академический Документы
Профессиональный Документы
Культура Документы
I.
EARTHWORKS
Equipment
Backhoe
Labor
1 Foreman
3Skilled Labor
5 Laborers
Days
Total Cost
P1,800.00
P1,800.00
Days
Total Cost
2
2
2
P83.00
P74.00
P63.00
P1,328.00
P3,552.00
P5,040.00
TOTAL COST=P11,720.00
II.
12mm x 6m RSB
16mm x 6m RSB
#16 G.I. Tie Wire
Equipment
1 Bar Cutter
Labor
2 Foreman
10 Skilled Labor
6 Laborers
Quantity
Unit Cost
Total Cost
22 pcs
107 pcs
24 kgs.
P180.00
P340.00
P60.00/kg
P3,960.00
P36,380.00
P1440.00
Days
Total Cost
P150.00
P150.00
Days
Total Cost
1
1
1
P83.00
P74.00
P63.00
P1,328.00
P5,920.00
P3,024.00
TOTAL COST=P52,202.00
III.
CONCRETE WORKS
Materials:
Portland Cement
Sand
Gravel
Plywood
2x2x12 Lumber
2x3x12 Lumber
Common Wire Nail
3
2
1
Quantity
Unit Cost
Total Cost
75 bags
5 cu.m.
10 cu.m.
16 pcs.
16 pcs
80 pcs.
P220.00
P420.00
P730.00
P330.00
P40.00
P40.00
P16,500.00
P2,100.00
P7,300.00
P5,280.00
P640.00
P3,200.00
4 kgs.
7 kgs.
7 kgs.
P70.00/kg
P70.00/kg
P70.00/kg
P280.00
P490.00
P490.00
Equipment
1 Concrete Mixer
1 Concrete Vibrator
Labor
1 Foreman
6 Skilled Labor
12 Laborers
Days
Total Cost
2
2
P1,248.00
P1,224.00
P2496.00
P2448.00
Days
Total Cost
3
3
3
P83.00
P74.00
P63.00
P1,992.00
P10,656.00
P18,144.00
TOTAL COST=P71,816.00
IV.
Quantity
Unit Cost
Total Cost
W460 x 74
W250 x 89
W360 x 33
0.5m x 0.5m x 15mm Base Plate
20mm x 400mm Anchor Bolt
Welding Rod
Oxy-Acetylene Refill
Grinding Disc
Vulcract Deck Model
56m
15m
85m
4 pcs
48 pcs
10 box
10 sets
30 pcs
15 sets
74.4kg/m P75.00/kg
89.3kg/m P75.00/kg
32.7kg/m 75.00/kg
P1,400.00
P200.00
P3,020.00
P1,900.00
P150.00
P1,800.00
P312,480.00
P100,462.50
P208,462.50
P5,600.00
P9,600.00
P30,200.00
P19,000.00
P4,500.00
P27,000.00
Equipment
Days
Total Cost
3
5
5
2
P5,500.00
P400.00
P180.00
P150.00
P16,500.00
P4,000.00
P900.00
P300.00
Days
Total Cost
5
5
5
P83.00
P74.00
P63.00
P9,960.00
P41,440.00
P40,320.00
1 Crane
2 Welding Machine
Acetylene Tools
1 Bar Cutter
Labor
3 Foreman
14 Skilled Labor
16 Laborers
TOTAL COST=P830,725.00
V.
MASONRY WORKS
Materials:
Portland Cement
Sand
Gravel
150 x 200 x 400mm CHB
100 x 200 x 400mm CHB
10mm dia. x 6m RSB
16mm dia. x 6m RSB
#16 G.I. Tie Wire
Quantity
Unit Cost
Total Cost
799 bags
64 cu.m.
130 cu.m.
1311 pcs.
1613 pcs.
98 pcs
30 pcs
15 kgs.
P220.00
P420.00
P730.00
P12.00
P9.00
P125.00
P340.00
P60.00/kg
P175,780.00
P26,880.00
P94,900.00
P15,732.00
P14,517.00
P12,250.00
P10,200.00
P900.00
Equipment
3
Labor
5 Foreman
10 Skilled Labor
10 Laborers
Days
Total Cost
2
2
P3,500.00
P1,224.00
P7,000.00
P4,896.00
Days
Total Cost
6
6
6
P83.00
P74.00
P63.00
P19,920.00
P35,520.00
P30,240.00
TOTAL COST=P448,735.00
VI.
STEEL WORKS
Materials:
Equipment
1 Welding Machine
Acetylene Tools
Labor
2 Foreman
4 Skilled Labor
4 Laborers
Quantity
Unit Cost
Total Cost
5 pcs
3 kgs.
10 pcs.
1 pc
1 set
P2,950.00
P630.00
P214.00
P150.00
P1,900.00
P14,750.00
P1,890.00
P2,140.00
P150.00
P1,900.00
Days
Total Cost
2
2
P400.00
P180.00
P800.00
P360.00
Days
Total Cost
2
2
2
P83.00
P74.00
P63.00
P2,656.00
P4,736.00
P4,032.00
TOTAL COST=P33,414.00
VII.
Equipment
1 Crane
Quantity
Unit Cost
Total Cost
3 sets
P4,500.00
P13,500.00
2 sets
P4,500.00
P9,000.00
42 sets
P6,000.00
P252,000.00
Days
Total Cost
P5,500.00
P5,500
Labor
1 Foreman
8 Skilled Labor
4 Laborers
Days
Total Cost
3
3
3
P83.00
P74.00
P63.00
P1,992.00
P14,208.00
P6,048.00
TOTAL COST=P302,248.00
VIII.
TILE WORKS
Materials:
C.R.
0.2m x 0.3m Tiles (Wall)
0.2m x 0.2m Tiles (Floor)
Lavatory
0.2m x 0.2m Tiles
Stairs
0.2m x 0.2m Tiles
Main Floor
0.4m x 0.4m Tiles
Tile Adhesive
Portland Cement
Sand
Labor
2 Foreman
6 Skilled Labor
10 Laborers
Quantity
Unit Cost
Total Cost
480 pcs
175 pcs
P27.00
P16.00
P12,960.00
P2,800.00
250 pcs.
P16.00
P4,000.00
385 pcs.
P16.00
P6,160.00
760 pcs
20 bags
49 bags
3 cu. m.
P70.00
P275.00
P220.00
P420.00
P53,200.00
P5,500.00
P10,780.00
P1,260.00
Days
Total Cost
10
10
10
P83.00
P74.00
P63.00
P13,280.00
P35,520.00
P50,400.00
TOTAL COST=P195,860.00
IX.
PLUMBING WORKS
Materials:
Quantity
Unit Cost
Total Cost
2 sets
P4,635.00
P9,270.00
2 sets
P4,944.00
P9,888.00
6 sets
2 pcs.
100 pcs
50 lit.
P275.00
P150.00
P15.00
P180.00
P1,650.00
P300.00
P1,500.00
P9,000.00
33 pcs.
20 pcs
43 pcs
12 pcs.
P80.00
P15.00
P12.00
P18.00
P2,640.00
P300.00
P516.00
P216.00
44 pcs
P300.00
P13,200.00
8 pcs.
P130.00
P1,040.00
2 pcs
8 pcs
P130.00
P50.00
P260.00
P400.00
Labor
3 Foreman
12 Skilled Labor
6 Laborers
18 pcs
8 pcs
4 pcs.
3 pcs.
1 pc.
P45.00
P85.00
P700.00
P120.00
P200.00
P810.00
P680.00
P2,800.00
P360.00
P200.00
1 pc.
P85.00
P85.00
27 pcs.
66 pcs.
36 pcs.
19 pcs.
P700.00
P120.00
P65.00
P120.00
P18,900.00
P7,920.00
P2,340.00
P2,280.00
Days
Total Cost
8
8
8
P83.00
P74.00
P63.00
P15,936.00
P56,832.00
P24,192.00
TOTAL COST=P183,515.00
X.
ELECTRICAL WORKS
Materials:
Pin Light
One-way switch
Three-way switch
5.5mm2 Copper Wire
15mm dia. Flexible Hose
Electrical Tape, Big
Labor
2 Foreman
8 Skilled Labor
6 Laborers
Quantity
Unit Cost
Total Cost
50 sets
4 pcs
4 pcs.
97m
300m
10 rolls
P375.00
P60.00
P90.00
P33.00
P12.00
P30.00
P18,750.00
P240.00
P360.00
P3,201.00
P3,600.00
P300.00
Days
Total Cost
7
7
7
P83.00
P74.00
P63.00
P9,296.00
P33,152.00
P21,168.00
TOTAL COST=P90,067.00
XI.
PAINTING WORKS
Materials:
Concrete Neutralizer
Latex Paint (White)
Semi-gloss Latex Paint
Acricolor
Paint Roller
Paint Pan
Paint Brush, 3
Paint Brush, 2
Paint Brush, 1
Quantity
Unit Cost
Total Cost
5 gal.
5 gal.
7 gal.
5 lit.
3 pcs.
3 pcs.
5 pcs.
5 pcs.
5 pcs.
P103.00
P400.00
P495.00
P150.00
P85.00
P45.00
P70.00
P48.00
P32.00
P515.00
P2,000.00
P3,465.00
P750.00
P255.00
P135.00
P350.00
P240.00
P160.00
Labor
2 Foreman
8 Skilled Labor
10 Laborers
Days
Total Cost
12
12
12
P83.00
P74.00
P63.00
P15,936.00
P56,832.00
P60,480.00
TOTAL COST=P141,118.00
GANTT CHART
Phase
A
Task
1
2
3
4
5
6
7
B
8
9
10
11
12
13
14
C
15
16
17
18
19
D
20
21
22
23
24
25
26
27
28
Activities
Contracts
Supply Lot Sale Agreement
Supply Construction Agreement
Supply Contract Plans
Supply Contract Specifications
Supply Contract Site Plan
Secure Financing
Construction Loan Settlement
Document Review & Revision
Review & Finalize Plans
Review & Finalize Specifications
Review & Finalize Site Plan
Print Construction Drawings
Approve Revised Plans
Approve Revised Specifications
Approve Revised Site Plan
Bids & Contracts
Make Copies of Plans
Make Copies of Specifications
Distribute Plans & Specifications
Receive Bids
Review Bids
Building Permits
Schedule lot stake-out
Stake lot
File Building Permit Application
Walk Lot w/ Owner
Install Construction Entrance
Municipal Permit Process
Building Permit Approved
Pay Permit Fees and Taxes
Building Permit Issued
S
1
1
1
1
1
1
1
1
2
2
2
20
21
21
21
21
22
22
22
22
24
32
22
22
22
22
22
22
22
35
35
35
E
1
1
1
1
1
1
1
1
21
19
20
21
21
21
21
21
35
22
22
23
31
35
35
22
22
23
22
22
35
35
35
35
D Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10
1
1
1
1
1
1
1
1
20
18
19
2
1
1
1
1
14
1
1
2
8
4
14
1
1
2
1
1
14
1
1
1
Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17
E
29
30
31
32
F
33
34
35
36
37
38
39
40
41
G
42
43
44
45
46
47
48
49
50
51
52
H
53
54
55
56
57
58
59
Site Work
Clear Lot
Strip Topsoil & Stockpile
Stake Lot for Excavation
Excavate for foundation
Foundation
Layout footings
Dig Footings & Install Reinforcing
Footing Inspection
Lumber Delivery
Pour footings
Build Block Foundation
Fill Block Cores w/ Concrete
Steel Delivery
Set Lintels, Bolts, Cap Block
Carpentry
Set Steel
Basement Deck Framing
Basement Wall Framing
Ground Floor Deck Framing
Ground Floor Wall Framing
2nd Floor Deck Framing
2nd Floor Wall Framing
3rd Floor Deck Framing
3rd Floor Wall Framing
4th Floor Deck Framing
4th Floor Wall Framing
Concrete Slabs
Slab Preparation
Stair Preparation
Pour Basement Slab
Pour Ground Floor Slab
Pour 2nd Floor Slab
Pour 3rd Floor Slab
Pour 4th Floor Slab and Stair Slab
36
36
36
36
37
38
38
38
38
38
39
39
40
40
40
42
42
44
45
44
46
44
46
44
46
44
46
46
47
47
48
48
48
48
48
37
36
36
36
37
41
38
38
38
38
39
39
41
41
41
46
43
44
45
44
46
44
46
44
46
44
46
47
47
47
48
48
48
48
48
2
1
1
1
1
4
1
1
1
1
1
1
2
2
2
5
2
1
1
1
1
1
1
1
1
1
1
2
1
1
1
1
1
1
1
Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 17 Week 19
60
61
62
63
64
K
65
66
67
68
L
69
70
M
71
N
72
73
74
75
76
77
78
O
79
80
81
82
P
83
Q
84
85
H.V.A.C.
HVAC Layout & Measure
HVAC Set Indoor Units
Plumbing Rough-in
Plumbing Layout
Plumbing rough-in
Electric Rough-in
Set Electric Boxes
Install Electric Service Panel
Electrical Walk-through
Electrical Rough-wire
Exterior Finishes
Install Windows & Doors
Siding
Floor Finishes
Ceramic Tile
Paint
Prep Drywall for Prime Coat
Prime Paint Drywall
Prep Trim for Prime Coat
Prime Trim
Finish Coat Drywall
Caulk Exterior Windows & Door
Finish Coat Exterior Trim & Siding
Interior Trim
Interior Trim Delivery
Install Interior Doors
Install Interior Trim
Install Cabinetry
Plumbing Trim
Set Fixtures
Electrical Final Trim
Switch & Plug
Install Fixtures
49
49
52
49
49
52
55
55
55
56
56
55
55
55
57
57
57
57
59
61
62
64
67
69
67
67
68
68
71
70
70
71
71
71
56 8
51 3
56 5
54 6
51 3
54 3
60 6
55 1
55 1
56 1
60 5
60 6
57 3
60 6
66 10
66 10
69 13
58 2
60 2
61 1
63 2
67 4
68 2
69 1
72 6
68 2
68 1
70 3
72 2
70 1
70 1
71 1
71 1
71 1
Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19
R
86
87
88
89
90
Cleaning
Windows
Rough Clean
Final Clean
Final Walk-through
Move-in
71
71
71
73
75
75
75
72
72
74
75
75
5
2
2
2
1
1
PERT/CPM
ACTIVITY
Beginning
A
B
B
C
D
E
F
G
H
H
I
I
J
J
K
K
L
L
M
N
N
N
O
P
Q
Ending
B
C
D
E
E
F
G
H
I
J
M
N
K
L
M
N
M
N
O
O
P
Q
R
R
R
m
1
20
20
14
14
2
4
5
2
2
8
8
6
6
2
2
2
2
10
10
13
14
4
1
1
b
1.5
30
30
16
16
3
7
10
4
4
10
10
8
8
3
3
3
3
15
12
14
16
5
2
2
PATH
A-B-C-E-F-G-H-I-M-O-R
A-B-C-E-F-G-H-I-N-O-R
A-B-C-E-F-G-H-I-N-P-R
A-B-C-E-F-G-H-I-N-Q-R
A-B-C-E-F-G-H-J-K-M-O-R
A-B-C-E-F-G-H-J-K-N-O-R
A-B-C-E-F-G-H-J-K-N-P-R
A-B-C-E-F-G-H-J-K-N-Q-R
A-B-C-E-F-G-H-J-L-M-O-R
A-B-C-E-F-G-H-J-L-N-O-R
A-B-C-E-F-G-H-J-L-N-P-R
A-B-C-E-F-G-H-J-L-N-Q-R
A-B-D-E-F-G-H-I-M-O-R
A-B-D-E-F-G-H-I-N-O-R
A-B-D-E-F-G-H-I-N-P-R
A-B-D-E-F-G-H-I-N-Q-R
A-B-D-E-F-G-H-J-K-M-O-R
A-B-D-E-F-G-H-J-K-N-O-R
A-B-D-E-F-G-H-J-K-N-P-R
A-B-D-E-F-G-H-J-K-N-Q-R
A-B-D-E-F-G-H-J-L-M-O-R
A-B-D-E-F-G-H-J-L-N-O-R
A-B-D-E-F-G-H-J-L-N-P-R
A-B-D-E-F-G-H-J-L-N-Q-R
+4 +
6
Where:
a= most optimistic time for an activity
b= most pessimistic time for an activity
m=most likely time for an activity
te=expected completion time
CRITICAL PATHS:
A-B-C-E-F-G-H-J-K-N-Q-R
A-B-C-E-F-G-H-J-L-N-Q-R
A-B-D-E-F-G-H-J-K-N-Q-R
A-B-D-E-F-G-H-J-L-N-Q-R
46.5
49.5
49
51
46.5
49.5
47
51
46.5
49.5
49
51
46.5
49.5
49
51
45.5
48.5
48
51
46.5
49.5
49
51
70
70
70
71
70
70
70
71
70
70
70
71
70
70
70
71
70
70
70
71
70
70
70
71
101.5
98.5
97.5
99.5
102.5
99.5
98.5
100.5
102.5
99.5
98.5
100.5
101.5
98.5
97.5
99.5
102.5
99.5
98.5
100.5
102.5
99.5
98.5
100.5
te
71.33333
71.33333
71.08333
72.41667
71.5
71.5
70.91667
72.58333
71.5
71.5
71.25
72.58833
71.33333
71.33333
71.08333
72.41667
71.33333
71.33333
71.08333
72.58833
71.5
71.5
71.25
72.58833