Вы находитесь на странице: 1из 62

CONSTRUCTION PROJECT

MANAGEMENT TECHNIQUES

Dr. Vanita Ahuja


1

Project Management Process Groups Mapped to


the Plan-Do-Check-Act Cycle
(Source: PMBOK)
2

POGRESSIVE ELABORATION

Process groups are not one time events


They are overlapping activities occurring at varying levels of
intensity throughout each phase of project
3

Process groups are linked by the results they produce.


Output of one becomes the input of another
Within each Process group, individual processes are linked
by their inputs and outputs.
Each process can be described in terms of its:
Inputs: documents or documentable items that will be acted
upon
Tools and Techniques: mechanisms applied to inputs to
create the outputs
Outputs: documents or documentable items that are result of
the process.
4

PROJECTS HAVE MULTIPLE PHASES

INITIAL PHASE

INTERMIDIATE PHASE(s)

FINAL PHASE

PROJECT PHASES AND PROCESSES

(Source: PMBOK)
6

FORMAL PROJECT MANAGEMENT

HENRY GANTT (1917)


Bar Chart
POLARIS (1958)
Programme Evaluation and Review Technique
(PERT)
DuPont Company (1960)
Critical Path Method (CPM)
1960s NASA Projects Apollo etc.
q Work Breakdown Structure
q Time and Cost Tracking

PLANNING TIME
1. What is to be done?
Define scope of work

4. When it is to be done?
Schedule work

2. What are the activities


involved?
Break down project work
into activities

3. How it can be done?


Develop network plans

WORK BREAKDOWN STRUCTURE


PROJECT
1.1 Sub Project 1

1.1.1 Work Package 1

1.1.1.1 Task 1

1.n Sub Project n

1.1.n Work Package n

1.1.1.n Task n

1.1.1.1a Activity 1
1.1.1.1n Activity n
9

CAMPUS PROJECT
1.1 SITE WORK

1.2 BUILDING 1

1.3 BUILDING 2

1.1.1 Layout

1.2.1 Layout

1.3.1 Layout

1.1.2 Earthwork

1.2.2 Excavation

1.3.2 Excavation

1.1.3 Paving

1.2.3 Foundations

1.3.3 Foundations

1.1.4 Landscaping

1.2.4 Structure
1.2.5 Services

1.3.4 Structure
1.3.5 Services

1.2.6 Finishes

1.3.6 Finishes

1.1.5 Site
Improvements
1.1.6 Utilities
1.1.7 Services

Location Based WBS


10

1.2.4 STRUCTURE
1.2.4.1 Basement Columns and Slab
1.2.4.2 G.Floor Columns and Slab
1.2.4.3 F.Floor Columns and Slab
1.2.4.4 T.Floor Columns and Slab
1.2.4.5 Fourth Floor Columns and Slab
1.2.4.6 Fifth Floor Columns and Slab
1.2.4.7 Sixth Floor Columns and Slab
1.2.4.10 Roof Works
1.2.4.11 Staircase

11

One WBS per project/program


q Deliverable-oriented
q Work not in the WBS is out-of-scope
q Each descending level represents more detail

Lowest level activities include


q Defined deliverable(s) or Scope of Work
q Timeframe for Completion
q Total cost (direct and indirect)

12

PLANNING TIME
1. What is to be done?
Define scope of work

4. When it is to be done?
Schedule work

2. What are the activities


involved?
Break down project work
into activities

3. How it can be done?


Develop network plans

13

ACTIVITY DURATION ESTIMATION

It is based on:
q Decision making structure in the organization
q Methodology adopted for executing the activity
q Resource availability and planning

Resource planning includes:


q Workers output norms
q Plant and Machinery output norms
q Materials quantity estimation and wastage norms

14

ONE TIME ESTIMATE DETERMINISTIC DURATION

Duration =

Quantity of Work
--------------------------------------------------------------------Output per unit of resource x Resources earmarked

CRITICAL PATH METHOD (CPM)

15

THREE TIME ESTIMATE


PROBABILISTIC ESTIMATION

Research projects
Limited previous data
Captures schedule (and implicitly some cost) risk
Conceptual stages of projects
Contractual arrangements like Design-Build/BOT etc.

PROGRAM EVALUATION REVIEW TECHNIQUE (PERT)

16

A - optimistic time estimate


q
q

M - most likely task duration


q
q

Minimum time in which the task could be completed


Everything has to go right
Task duration under normal: conditions
Most frequent task durations based on past
experience

B - pessimistic time estimate


q
q
q

Time required under particularly bad circumstances


Most difficult to estimate, includes unexpected delays
Should be exceeded no more than 1% of the time
17

Duration =

A + 4M + B
6

18

ba
Activity Variance = =

Project Variance =
Sum of variance of activities on the Critical Path

If more than one Critical Path


Project Variance=
Sum of variance of activities on the longest Critical Path
19

LINKS/DEPENDENCIES
Finish Start (FS with 0 days lag)

Finish Start (FS with x days lag)

X days
Time
20

Start Start

(SS with x days lag)

X days
Finish Finish (FF with x days lag)

X days
Time
21

RISK ASSESSMENT PROJECT TIME

Probabilistic duration estimation helps in risk assessment for


time

Let calculated project duration = 45 days


Probability of completing the project in 50 days?
Variance of the schedule = 9
Standard deviation = SquRoot 9 = 3
Z = 50 45 = 1.67 standard deviations
3
It gives probability = 95.25%
(read from normal probability distribution table)
22

Probability =
shaded area of the curve corresponding to value of Z x 100
23

RESOURCE AND COST


SCHEDULING

24

PLANNING RESOURCES AND COST


1. What is the Resource
requirement schedule?
manpower
materials
equipment
Derived from Time schedule

3. Budget?
Direct cost from the total
resource requirement
Indirect
cost
from
organisation guidelines

2. What is the Resource


Procurement schedule?
Derived
from
Resource
schedule

4. Cash flow?
Derived from the Time
Schedule and Resource
Schedule
25

RESOURCES

WORK RESOURCES

MATERIAL RESOURCES

Manpower

Equipment

Material

26

Superimpose resource requirement for each type of


resource that is required to be planned/scheduled.

RESOURCE LOADING

27

Calculates total resource requirement


Resource usage pattern
Overallocated resources

28

Resource Leveling (Step 1)


Increase the duration of Activity 3 by 1 day and reduce resource requirement by 1
unit/day

RESOURCE LEVELING

29

Resource Leveling (Step 2)


Increase the duration of Activity 3 by 2 more days day and reduce resource requirement
by additional 0.5 unit/day

30

CUMULATIVE RESOURCE USAGE CURVE

cumulative requirement

resource 1
450
400
350
300
250
200
150
100
50
0

resource 1

time period

31

RESOURCE SCHEDULING OBJECTIVES

Validates the time objectives


Optimises the resources employed
Forecasts the input resources
Evaluates the implications of scheduling constraints
Establishes Target resource requirement with which the
actual resource usage would be compared

32

PLANNING RESOURCES AND COST


1. What is the Resource
requirement schedule?
manpower
materials
equipment
Derived from Time schedule

3. Budget?
Direct cost from the total
resource requirement
Indirect
cost
from
organisation guidelines

2. What is the Resource


Procurement schedule?
Derived
from
Resource
schedule

4. Cash flow?
Derived from the Time
Schedule and Resource
Schedule
33

RESOURCE PROCUREMENT SCHEDULE

Resource
requirement
date

Duration
for which
the
resource
can be
stored

Resource
receipt
date

Time
taken by
the vendor
for
supplying
resource
Time
taken to
organise
resource

Date of award
of work for
supplying
resource

34

PLANNING RESOURCES AND COST


1. What is the Resource
requirement schedule?
manpower
materials
equipment
Derived from Time schedule

3. Budget?
Direct cost from the total
resource requirement
Indirect
cost
from
organisation guidelines

2. What is the Resource


Procurement schedule?
Derived
from
Resource
schedule

4. Cash flow?
Derived from the Time
Schedule and Resource
Schedule
35

COST SCHEDULING OBJECTIVES

Establishes cost of each activity

Establishes cost of the project and cash flow pattern

Establishes Target cash flow pattern with which the


actual cash flow requirement would be compared

36

PROJECT COST/BUDGET

DIRECT COST

INDIRECT COST

Cost of Resources

Overheads and Infrastructure


Cost

37

Team Member Rate: Rs. 2,500.00/day

38

39

CRASHING THE SCHEDULE


Compute Cost/Time slope for each
Activity

CRASH
COST

Slope = Crash Cost Normal Cost


Crash Time Normal Time

NORMAL
COST
CRASH
TIME

Crash time leads to use of more


resources in less time and more cost

NORMAL
TIME

Apply Crash time to Critical


Activities
Recalculate the Critical path and
repeat the above steps
40

Crashing of Critical Tasks leads to increased Direct


Cost
Indirect Cost decreases as Project duration decreases
Minimise the sum of Direct Cost and Indirect Cost

41

TYPICAL COST PATTERN

42

TRACKING AND MONITORING


OF PROJECTS

43

PERFORMANCE PARAMETERS TO BE
CONTROLLED

Time Progress Control


Resource Productivity Control
Resource Mobilisation Control
Direct Cost Control
Budgeted Cost Control
Earned Value Control

44

VARIANCE ANALYSIS
q

Backward Looking

TRENDS FORECASTING
q

Provides a tool for forecasting future requirements


of resources

45

TIME PROGRESS CONTROL

46

VARIANCE ANALYSIS - TIME

47

VARIANCE ANALYSIS - WORK

48

VARIANCE ANALYSIS - COST

49

TRENDS FORECASTING EARNED VALUE ANALYSIS

Measures a projects progress

Forecasts its completion date and final cost

Provides schedule and budget variances

50

EARNED VALUE CALCULATIONS


BCWS - Budgeted Cost of Work Scheduled
Planned cost of the total amount of work
scheduled to be performed by the status date.
ACWP - Actual Cost of Work Performed
Cost incurred to accomplish the work that has
been done to date.
BCWP - Budgeted Cost of Work Performed
The planned (not actual) cost to complete the work
that has been done.
51

BCWS

ACWP

52

/ETC

53

DERIVED INDICES
SV: Schedule Variance (BCWP-BCWS)
q A comparison of amount of work performed during a
given period of time to what was scheduled to be
performed.
q A negative variance means the project is behind
schedule
CV: Cost Variance (BCWP-ACWP)
qA
comparison of the budgeted cost of work
performed with actual cost.
q A negative variance means the project is over
budget.
54

SPI:

Schedule Performance Index (BCWP/BCWS)


SPI<1 means project is behind schedule

CPI:

Cost Performance Index (BCWP/ACWP)


CPI<1 means project is over budget

55

CPI: Cost Performance Index (BCWP/ACWP)


CPI<1 means project is over budget
CPI:

Budgeted Cost of Remaining Work


Estimate to Complete (ETC)
Budgeted at Completion (BAC) BCWP
ETC
ETC: BAC BCWP
CPI
EAC (Estimate at Completion): ETC + ACWP
56

EXAMPLE
120000

BAC = 102000

100000
80000

BCWS

56000
60000

BCWP

55000
49000

40000

ACWP

20000
Dec-03

Nov-03

Oct-03

Sep-03

Aug-03

Jul-03

Jun-03

May-03

Apr-03

Mar-03

Feb-03

Jan-03

57

Schedule Variance = BCWP-BCWS = 49,000 55,000 = -14,000


Cost Variance

= BCWP-ACWP = 49,000 56,000 = - 7,000

SPI = BCWP/BCWS = 49,000/55,000 = 0.891


CPI = BCWP/ACWP = 49,000/56,000 = 0.875
ETC = (BAC BCWP)/CPI = (102,000 49,000)/0.875 =
60,571.42
EAC = ETC + ACWP = 60,571.42 + 56,000 = 116,571.42
Cost Variance = EAC BAC = 108,571.42 102,000 = 6,571.42
58

DIFFERENCE BETWEEN TIME CHAINAGE


CHART AND BAR/GANTT CHART
Gantt chart displays time horizontally and a list
of tasks vertically. The spacing of task lines
vertically is not related to any physical location.
A time chainage chart provides a second
dimension to an event by adding the start and
end measurements to the start date, end date
and duration.
This additional dimension makes it is easier to
visualise what is happening at a given location
at any time and what processes are passing
through any position.
59

60

61

QUESTIONS
AND
DISCUSSION

vanita_ahuja@yahoo.com
62

Вам также может понравиться