Академический Документы
Профессиональный Документы
Культура Документы
BUILDING STRONG
OUTLINE
INTRODUCTION
FOUNDATION PROBLEMS & PHOTOS
1970s GROUTING & WALL CONSTR.
SETUP FOR BARRIER WALL CONSTR
5-STEP BARRIER WALL
CONSTRUCTION
CONCLUSIONS
7/2/2013
INTRODUCTION
7/2/2013
Location of Site
7/2/2013
Embankment Plan
Toe of
Compacted
Fill
Downward Slope of
Cut Off Trench
Drainage Blanket
Embankment Profile
Elev. 773
Pool
Dam
Soil Foundation
Limestone Bedrock
5+00B
4+00B
3+00B
2+00B
Cutoff trench
1+00B
1+00A
2+00A
3+00A
4+00A
5+00A
7/2/2013
KARST
7/2/2013
Foundation Treatment
Original
Construction
in 1940s
Cave
Cave
Solution Features
Original
Construction
in 1940s
7/2/2013
Core Trench
Approx New
Wall
Location
Original
Construction
in 1940s
Pinnacle
Original
Construction
in 1940s
7/2/2013
Original
Construction
in 1940s
Approx
New Wall
Alignment
Original
Construction
in 1940s
7/2/2013
FOUNDATION PROBLEMS
IN 1960S
SWITCH
YARD
MUDDY
WATER
SHOW
WET AREAS
SINKHOLE 4-22-68 SINKHOLE
8-22-67
SINKHOLE 3-13-68
SPILLWAY
POWERHOUSE
Dam Embankment
7/2/2013
1968 Sinkhole
Switchyard
Sinkhole
10
7/2/2013
Solution Features
Concrete Monoliths
Grout Lines
RIVER
Concrete
Dam
Earth Emb
Grout Lines
Switchyard
11
7/2/2013
20 ft
M
O
N
O
L
I
T
H
12
7/2/2013
Follow-Up
Two barrier walls installed in Wolf Creek
after grouting was completed.
One along Crest
One at down-stream toe
13
7/2/2013
Full-face,
roller rock,
drill bit
14
7/2/2013
Project Geography
Working Platform
Contractor offices &
slurry plant area
Power house
USACE Resident office
Contractor Laydown
Disposal Area
15
7/2/2013
Layout of Wall
Technique Areas
Critical Areas
3800 linear feet total
THE REQUIREMENTS
Unit
Specification
Requirements
ft
ft
0.5
psi
2000
Lugeon
Description
Permeability (Maximum)
16
7/2/2013
WALL CONSTRUCTION
SEQUENCE
5-STEP PROCESS
5 Step Process
1. Pre-Grouting (2 lines either side of wall
and intensive grouting in Critical Areas)
2. PCEW (Panel wall embedded to bedrock)
3. Pilot hole drilling (to full depth)
4. Secant pile excavation & Combined
barrier wall (to full depth)
5. Verification coring to confirm quality (on
selected elements)
17
7/2/2013
Installation of upstream /
downstream grout courtain
High mobility grouting (HMG) to treat the
rock more than 5 ft below TOR.
Low mobility grouting (LMG) designed to
treat the rock, soft zones of soil, and
weathered rock.
2,000 grout holes, most 325 ft deep.
Over 1,000,000 gallons of grout (3.7million
liters).
18
7/2/2013
19
7/2/2013
PCEW Sequence
9-2
6 ft
5 min overlap
Embankment
Rock
20
7/2/2013
21
7/2/2013
Rock
22
7/2/2013
DD Overlap Analysis
Simulation of primary and secondary piles following pilot holes.
Starting point for pile installation
DD Deviation Charts
* More than 70% of the pilot holes installed reached a maximum
deviation of 2 to 3 inches at a depth of 282 ft.
23
7/2/2013
24
7/2/2013
P S
Embankment
Rock
Hydromill excavation
Overlapping 6 x 9 panels
Number of Panels Complete 245/431
57% Complete
25
7/2/2013
26
7/2/2013
27
7/2/2013
50 dia. piles
9.2-ft x 2.6-ft CBW panels
28
7/2/2013
29
7/2/2013
Barrier
Secondary
Primary
Wall installed
Piles in Cave and Core Trench Area
30
7/2/2013
31
7/2/2013
Wall Completed!
Last pile placed on March 6th, 2013
32
7/2/2013
Results
Quality:
1,197 piles + 52 Combined Barrier Wall elements
installed with only 2 remedial piles, les than 0.2%.
Barrier wall thickness, overlap between elements,
concrete strength, and permeability requirements
met, if not exceeded.
Schedule:
Construction of the Barrier Wall 11 months ahead
of schedule.
Safety:
1.3 million hours without a lost time injury.
33
7/2/2013
Conclusions
Wolf Creek Dam had serious foundation
problems due to Karst
The Corps chose a Cutoff Wall as the
permanent foundation repair
Treviicos-Soletache used an innovative
method of wall construction
Treviicos-Soletache exceeded the Corps
requirements for the cutoff wall.
34
7/2/2013
35