Вы находитесь на странице: 1из 31

Monthly Report

This document was generated by

Environmental Department PTFI

Environmental Department
June 2013

Executive Summary

June 2013 operating cost was $ 1.5 M, or 7.8% ($ 110 K) higher than forecast. YTD
2013 spending was $8.3 M, or 5.9% ($ 522 K) lower than below the forecast.
Environmental Department achieved 4,293,520 man-hours worked without LTA
and RAC since April, 2005. YTD actual reportable injury rate in June 2013 was
0.0. One case of serious injury which resulted in caused fatality by CV. Keladingki
(Contractor under Environmental Department) occurred on June 17. was not
categorized as fatality incident.
Monthly Inspection Finding (MIF) index for June2013, based on inspection of 28
facilities, was 0.21, or does not meet the target of lower than the target of 0.11.
PTFI received a letter from Ibu Nelly on her response to our routine KepMen431
quarterly report. The letter questions the exceedance of the TSS level at K5
monitoring point in November 2012, the elevated mercury level in the Kamora
estuary, disagreement to our plan to discontinue the K5/P5 monitoring points, and
the high TSS in the estuary and effort to retain more tailings on land. PTFI has
responded to the letter accordingly.
PTFI met with the Minister of Environment on June 17 to update the Minister on the
Big Gossan incident and to remind him on the follow-up of KepMen431 revision. The
minister advised that discussion on the KepMen431 revision be on hold until the
inauguration of the new MoE Deputy sometimes in July 2013. Response of the letter
has been sent to MoE.
External law firm provided draft analysis on the legal review of the planned
placement of the PCon material in to the ModADA. The draft analysis indicated that
such placement is legally possible on the basis of broad designation of the Mimika
region as the backbone mining zone in the National Spatial Plan based on
Ggovernment Rregulation Number 26 year 2008.
The last meeting in May with MEMR indicated that PTFI Mine Closure Document was
technically complete, and awaiting approval from the Director General of Mineral
and Coal.
PTFI received a cCopy of the letter from the Provincial Papua Mining office in
Jayapura on a complaint was received. The letter is about a complaint from from the
East Coastal Community Forum related with on the sedimentation in the tailings
estuary area. PTFI plans to meet with Provincial Papua Mining Office in Jayapura to
explain about PTFI tailings management system in the AMDAL 300K which was
approved by GoI in 1997.
Land clearing and excavation works of Ajkwa alternative channel phase II has
reached 200 meters out of 600 meters total target length targeted. This project will
temporarily is required to provide access for local people from the East to cross
tailings Ajkwa Estuary during low tide.
PT. Freeport Indonesia receivedpt Indonesian Green Award for Biodiversity
Conservation Program Category that was held by La Tofi School of CSR.
Eight schools from Mimika District received the Adiwiyata Province Trophies during
the Environmental Day celebration that officially opened by Head of Mimika District
in Timika and Papua Governor in Jayapura.

Ten (10) plots of slope area in Blitar 4030L and in Tembagapura along the stream
affected by erosion or landslide have been reclaimed using hydro-seeding. A total
Total 172 of 282 reclamation monitoring plots as recommended by ENV were
completed.

Safety & Budget


Safety record and achievement for June 2013 were as follows:
One case speeding violation by Tom Weiskopf occurred on June 12, 2013 at MP 28,
when drive LV 01-3151.
One case minor accident of LV 01-3214 by Romen Rifian occurred on June 08, 2013
at SP 2 Lowland.
One case serious injury which resulted in caused fatality by CV Keladingki
(Contractor under Environmental Department) occurred on June 17, 2013 at Kuala
Kencana. The victim name is Musa Yowani (907784).
YTD reportable rate injury (LTA, RAC or NDL) was 0.0 (the ceiling is 0.0)
Environmental Department achieved 4,293,520 man-hours worked without LTA and
RAC since April, 2005.
Actual operating cost in June 2013 was $ 1.5 M, or 7.8% ($ 110 K) higher than forecast.
YTD 2013 spending was $ 8.3 M, or 5.9% ($ 522 K) lowerbelow than the forecast.

Highlight Issues
MoE Decree 431 on Tailings Management
PTFI received a letter from Nelly on her response to our routine KepMen431 quarterly
report. The letter questions the exceedance of the TSS level at K5 monitoring point in
November 2012, the elevated mercury level in the Kamora Estuary, disagreement to our
plan to discontinue the K5/P5 monitoring points, and the high TSS in the estuary and
effort to retain more tailings on land. Our response letter included the explanation that
the high TSS level has been anticipated and modeled; and has been discussed several
times with MoE. As indicated by modeling, it was not if this would occur, but whenthe
exceedance will soon occur and predict the TSS value of 24500mg/L on annual average.
The ability to accurately model and measure TSS over shorter periods was always
known to be an issue due to the limitations of even the best models to accurately
predict river deposition over short periods of time. A single flow event on November 5,
2012 associated with high rainfall was the main contribution to the high TSS value in
November 2012. As the event occurred naturally, it would not breach the environmental
law. P5 and K5 are located in the active deposition zone, and therefore are not
appropriate as monitoring points. This scientific argument was also presented by ITB
experts during meetings on August 10, 2010 and November 5, 2012 with the MoE. PTFI
will be willing to meet and re-discuss the workable revision of KepMen431 as already
conveyed in our recent letter to MoE on May 15. On the mercury level, our explanation
included providing a short report on the mercury trend on this estuary and explaining
that the high mercury concentration phenomena is naturally occurring from the

upstream river. It was explained also that the area is outside of our project area, and are
not flown by tailings.

PTFI met with the Minister of Environment on June 17. The purpose of the meeting is
to update the Minister on the Big Gossan incident and to remind him on the
follow-up of KepMen431 revision. The minister advised that discussion on the
KepMen431 revision be on hold until the inauguration of the new MoE Deputy
sometimes in July 2013.

PROPER
No new update. PTFI continues to be exempted from this year PROPER Audit. PJP
submitted self-assessment questioner in lieu of PROPER verification for site visit. The
document is being reviewed by MoE. Feedback is expected to be received in July.

Implementing New Regulations


MoE Deputy IV in charge of B3, B3 Wwastes and Dumping (Nelly) socialized the latest
draft version of the B3 wastes regulation which was dated May 23, 2013, which and
essentially does not change from the previous version. in which L large volume mining
and energy wastes, such as tailings and fly ash are still classified as Special B3 wastes.
As reported in the last month report, Indonesian Mining Association hold its position that
these mining and energy wastes should not be listed as B3 wastes, but suggest site
specific management insteadof these wastes. Nelly met with representative of
Indonesian Chamber of Commerce on June 10, and basically mentioned that the draft
regulation is final. The draft regulation continues to be on hold to be discussed with the
Ministry of Law and Human Right, until the industry concerns are addressed by MoE.

Reclamation/Mine Closure
MEMR invited PTFI and other mining companies on a workshop of reclamation and mine
closure plan. The purpose is to guide mine operators to prepare technical aspects of
mine reclamation and mine closure plan. About 180 representative mining companies
attended the workshop. Cost of reclamation and mine closure plans which is were based
on a Canadian standard which is stipulated in the Minister of Regulation Number
18:2008 was explained in detail.
Up to now, there was no update on PTFI Mine Closure Plantailings reclamation. The last
meeting was in May, in which MEMR indicated that PTFI Mine Closure Document was
was technically complete, and was awaiting approval from the Director General of
Mineral and Coal.

Pyrite Pond Project


External law firm provided a draft analysis on the legal review of the planned
placement of the PCon material into the ModADA. The draft analysis indicated that such
placement is legally possible on the basis of broad designation of the Mimika region as
the backbone mining zone in the National Spatial Plan based on government regulation
Number 26 year 2008. The law firm recommends further for PTFI to work with local
Mimika government to draft up the detailed spatial plan of the ModADA.

Environmental Complaint
PTFI received a Ccopy of athe letter from the Provincial Papua Mining office in Jayapura
was received. The letter is about a complaint from the East Coastal Community Forum
on the sedimentation in the tailings estuary area. The Provincial Mining office responded
to the letter and report that the location being referred by the community is not being
presented in enough detail in a form of a map, and asked the community to pinpoint the
exact location of their residence. We plan to meet with the Head of Papua provincial
office to update them on the chronology of tailings management and the current efforts
and dialog we have with MoE and the Provincial Environmental office.

Sedimentation at Estuary
The initial kick-off meeting with Happold and IPB to discuss the scope of the Coastal
Management Plan is being set on July, 30 in Bogor. There is a plan to conduct a wider
stakeholder kick-off meeting in Timika in August or September.
Phase 2 alternative channel excavation preparation is underway. During the month, the
local contractor completed 20075 meters of excavated channel completed out of 600
meters. It is estimated that the whole channel will be completed in August 2013 to
temporarily ease the community travel through tailings estuary. Two potential dredging
companies were invited to Site in order to provide them with an overview of the
sedimentation in the tailings channel and shipping channels to help them better
understand site condition.

External Audit
PTFI met with ITB to discuss preliminary plan to conduct triennial audit and plan to
overlap with the new requirement of mandatory environmental audit as stipulated in the
new Ministerial Decree Number 17 Year 2013 on the Environmental Audit. The external
audit is being planned for May 2014.

Environmental Support
Environmental Management System
Environmental Emergency System
There was no reportable spill recorded during the month. Below are the cumulative
reportable spills until end of June 2013 for 12-rolling-months.

Environmental Audits and Inspection


Environmental observation was conducted to KPI Marine and informed them related
with vessel garbage disposal policy. The observation was also took place in the MV.
Ammar Ship to en. This is to enssure that the ships crews understand regarding this
policy.

Figure 1 Environmental observation at MV. Ammar Ship (left) and our team
explaineding vessel garbage disposal policy (right)
During the month, the environmental inspections and observations were
conducted at several shops at Grasberg Mine Maintenance, Underground Mine
Maintenance, GMBL Warehouse, PJP Power Plant highland, Facilities
Management - lowland, several PHMC facilities, Portsite Clinic, Environmental
Biotic Monitoring Portsite, and AVCO.

Activities related with Audits and Inspection:

Received information from Geo-Hydrology associated with wells to be installed at


MP73 landfill to follow-up recommendation from External Audit. Currently, the
bidding is in process to select drillers for installing wells.
Conducted meeting with Contract Department to discuss 2012 FCX Audit finding
which is related with contractors performance evaluation. The finding still could
not be closed because the system has not yet been established. so that the
contractors evaluation has not been conducted.

Waste Management & Recycle Program


Discussion with Mahaka Lime Plant and Grasberg Engineering was conducted for
used oil generation and collection to ensure enough storage while Mahaka Lime
Plant and Dewatering Plant are in shut-down condition due to stoppage of no mining
operation or no dedicated manpower for transporting raw material to Mahaka Lime
Plant. After calculating used oil that are generated and the availability of storage
space, it was concluded that used oil storage was sufficient during this temporary
situation.

Figure 2 Observing used oil at Grasberg Maintenance (left) and MP74 (right)
There were 34 containers of hazardous waste were shipped outside jobsite for
further treatment with MV. Sawu Sea72AJ and MV. Flores Sea73AJ. Following are
statistics for Hazardous Material Authorization Forms which have been reviewed
until end of June 2013 and hazardous waste shipped.

Activities of Waste Management:

Inspected 8 shipping containers of hazardous waste at the point of originator


that have been approved to be sent to Temporary Hazardous Waste Storage
at MP32.
Facilitated PJP LIP in requesting pump truck to FM, in order to mobilize their
waste oil to Dewatering Plant.
Gathered information for current condition at Kokarfis tofu and soy cake
factory at MP38 and its process until production. Currently, this factory is not
operated at MP38 due to unsafe work location and had been relocated to
Timika area. However, due to water condition in Timika, this factory possibly
will be relocated to PTFIs work area. Theoretically, the wastewater from this
factory can be treated at Sewage Treatment Plant (STP) if the flow rate and
Biological Oxygen Demand (BOD) are not exceeded from determined quantity
due to STP has maximum level of capacity and concentration for treatment.
Communicated with PT. PPLI for the type of waste when disposing used
aerosol can and Safety Department for packaging them before shipping. The
empty used aerosol can is categorized as used rags and can be placed in the
used cube tanks and no ventilation is needed for shipment.
Met with Facilities Management WSW and SLD to review SOP E 09-09 Wood
Pallet Management and improving its handling. Several action plans will be
taken for revising this procedure.
Conducted non-hazardous solid waste disposal observation in GRS Koteka
Dump.
Observed new laundry facility at Ridge Camp area before hand-over to
Pangansari Utama. This laundry uses ozone technologies developed by OTEK
laundry system. Ozone is created via electrical discharge and gas injection
into the water line into the bottom of the washing machine. This new system
will reduce the wastewater and energy use. Several factors need to be
ensured by Pangansari Utama, such as piping and wastewater generated due
to STP at Ridge Camp is currently overloaded.
Discussed with SCM associated with shipping containers contains with bags of
iron powders to be placed above magazine warehouse Grasberg as partitions
to block falling rocks from the mountains. Several action plans will be
conducted to determine the environmental aspects and impacts before the
containers located at this warehouse.
Analyzed PCB for 38 samples of transformer oil from Concentrating
Department and Grasberg Maintenance. Until end of the week 81% of oil
transformer samples have been analyzed (164 of 202).

Attended a presentation and discussion of PTFI Biodiesel Utilization Plan


delivered by PT BNE (PT Berjaya Nusantara Energy) at Dewatering Plant
Porsite. Detailed proposal of biodiesel utilization plan at PTFI work areas will
be created and send to PTFI by first week of July. PT BNE team also visited to
PTFI Biodiesel Reactor Facility at MP21.
Collected 1 trash bag of used toner cartridge from MP68 Geotechnical Group.
Provided advices to:
1. Trakindo for managing their used toner/cartridges.
2. KPI Marine for OWS station for having silt trap installed in the drainage
and immediate fixing the broken pump at the location to support the OWS.
3. Responsible parties regarding permit for ship transporting hazardous
waste, as the permit will expired in next month. (July, 14 2013).
4. Trakindo to pack their used fluorescent tubes into one shipping container
with used rags or slop oil.

Activities of 3R Programs:

Conducted safety pre-check of 5R MP66 Integrated Workshop with Safety


Department. Forthcoming task is to hold re-check by Safety Department,
Industrial Hygiene, Facilities Management Fire Engineering Service and Project
Manager when the building progress reaches 90%. Overall progress of 5R
MP66 Integrated Workshop was 82%.
Collected 27,000 liters used cooking oil from several Mess Halls at Highland
area
Replaced element filter at Kawiki Shop Biodiesel Refueling Station.
Distributed 2 used cube tanks to MP72 Kenanga Mess Hall at Highland area to
support their used cooking oil storage.

The fFollowings are the volume of biodiesel and 3R souvenir produced until the
end of June 2013.

10

EMS Documents
Updates on Environmental Management System Documentations:

Conducted inspection on original copy of EMS documents.


Review and revised several EMS Documents:
1. SOP E 09-17 Oil-Water Separator Management to include visual observation by
permitted areas.
2. COP 16 Equipment Maintenance and Calibration and COP 19 Environmental
Audits and Inspections. These two documents have been finalized and signed by
Environmental Manager.
3. SOP E 15-01 Preliminary Notification for Corrective and Preventive Action from
Environmental Monitoring Data Validation with Environmental Monitoring Group
on Thursday, 20 June 2013 for items needs to be revised to improve SOP
implementation in the field.
4. SOP E 09-09 Wood Pallet Management which has been added for several
items for transportation

Legal and Other Requirements


As the vessel permit for transporting hazardous waste was due in July 14, 2013,
Environmental Department discussed with KPI Marine Agency to propose permit
renewal to Ministry of Transportation. The application of vessel permit for
transporting hazardous waste has been submitted to Ministry of Transportation.

Figure 3 Discussion with KPI Marine at Coastal Environmental Office

11

A total of 49 analytical result reports from Timika Environmental Laboratory for


Oil-Water Separator (OWS) effluent sampling conducted on June 2013 were
reviewed. Six of the monitoring results are above the permit standard; they are
LIP Power Plant, MP74 Refueling Station, MP39 KPI Lube Shop, MP74 Power Plant
AB, MP74 Power Plant C and MLA LHD Shop. Corrective sampling hadve been
conducted before end of the month and the result met the permit standard.
Several samples were not taken for five OWS stations due to the security reason
(XC-9 Shop, XC-3 Shop and KPI East Levee Shop) and construction reason (MP66
Refueling Station and MP32 Refueling Station).
Activities related with legal compliance:

12

Conducted environmental investigation regarding the incompliance of the its


effluent:
1. OWS at LIP Power Plant was due to washing activities for parts after PM
Engine Check Unit # 4. The corrective sampling has been taken.
2. OWS at MP74 Refueling Station was due to fuel guns valve which was not
locked properly in the afternoon causing leaking of diesel fuel which flow
to drip pan first. However, since there was no employee working
afterwards, the drip pan cannot hold all the leaking causing then flow to
OWS. The OWS would be cleaned.
3. OWS at KPI Lube Shop MP39 was due to inappropriate practice, i.e., oil
collected in lube pit was pumped into drainage that reports to OWS and
there was no communication among shop mechanics, SHE
Representative, and supervisor regarding shops condition. The RCPA is
being drafted.
4. OWS at MP74 AB Power Plant and C Power Plant was due to the lack of
maintenance at these facilities due to the unsafe conditions at mine area.
5. OWS at MLA Shop owned by Underground Mine Maintenance effluent was
due to inadequate maintenance of OWS.
Conducted weekly OWS observation to permitted OWS facilities. The result of
observations has been communicated to area owner, such as:
1. SHE Representative at MP66 KPI HD Shop to update their weekly
inspection form.
2. Sandvik LIP to clean up their OWS due to turbid effluent that showed
during visual effluent observation.
3. LIP Electric Shop for no separation process (similar appearance at each
chamber). Samples from this station have been collected and sent to
Timika Lab for further investigation.
Conducted compliance permit audit for second quarter of 2013 at OWS of
Amole Besar Shop, Kasuang Shop, Kasuang Refueling Shop, Bukit Batu Shop,
MNK-Orica GRS Shop, Toraja Shop, Ambon Refueling Station, Sandvik Shop,
PJP Highland, MP66 KPI HD Shop, MP35 KPI Levee Maintenance, KPI Cargo
Dock, KPI-HD Shop Portsite, permit for three vessels in shipping hazardous
waste, Facilities Management Lowland area (five Sewage Treatment Plant
(STP), one Leachate Treatment Plant (LTP), three Temporary Hazardous Waste
Storages (THWS) and one permit related ground water utilization. Until end of
the month (second quarter of 2013), permit audit has been conducted 100%
and 89% permit findings have been closed.
Requested confirmation from PHMC and FM for the status of the Ministry of

Health Decree No.492/MenKes/Per/IV/2010 regarding Requirements on


Drinking Water Quality. It is confirmed that this regulation is used to monitor
drinking water quality in Jobsite and all the required parameters have been
monitored periodically; therefore, it can be registered as a required
regulation to PTFI.
Requested degreaser SISKEM quotation from Trakindo LIP and distributed to
the requestor.
Completed the list of all of environmental permits requirements, and has
been uploaded on internal website.
Evaluated several regulations:
1. Law No 4 Year 2009 (UU-4-2009) Mining and Coal Mining
2. Government Regulation No. 78 Year 2010 (PP-78-2010) Reclamation and
Post-Mining
3. Decree of Minister of Environmental No. 128 Year 2003 (KEP-MENLH-1282003) Technical Procedure and Requirement in Processing Petroleum
Waste and Contaminated Soil by Petroleum Product Biologically
4. Regulation of Minister of Transportation No. 52 Year 2011 (PER-MENLH-522011) Dredging and Reclamation
5. Three above regulations are required by PTFI except for Decree of
Minister of Environmental No. 128 Year 2003 which needs to be further
reviewed.

Completed the verification of five handbooks of environmental training


related with environmental compliance issues which would be conducted by
Quality Management Services.

Environmental Training

Facilitated TOT meeting to evaluate SOP E 09-28 Used Aerosol Can


Management on Tuesday, 4 May 2013.

Environmental Awareness and Education


Working with Schools
PTFI facilitated FKGPLH (Teachers Forum for Environment) members to started to
develop Environmental education syllabus which will be used in next semester at
elementary and middle schools. The draft was then discussed with Basic Education
and Culture Office of Mimika.

13

Figure 4 FKGLPH developed environmental education (left) and one staff of


Mimika Environmental Office introduced environmental program (right)
Activities of Working with School Program:

Facilitated one staff of Mimika Environmental Agency to visit SMAN 04 Entrop


Jayapura to introduce environmental program to the students.
Facilitated environmental education activities for SMPN 2 by giving 61 used
tires from workshop Stamford tires LIP and delivered 20 bags of Media Plant
TRUBUS for SDIT Permata Papua to support their Environmental Program.

Environmental Camp facilitation for 60 students and teachers of Yapis Junior


High School at MP21 Reclamation and Biodiversity Center.
Bird Watching facilitation to 40 students from Ebenezer Junior High School,
SMPN 3 Junior High School, Yosua Junior High School and ITB University at
Rimba Golf Yard.

Figure 5 Bird watching at Rimba Gold for ITB University (left) and several
Junior High Schools in Mimika District (right)

Environmental Youth Club


Environmental Prince and Princess visited several places in Jakarta from May 29 to
June 03, 2013. They attended the opening ceremony of Jakarta Environmental
Exhibition and Green Village Inauguration at Cakung Barat sponsored by United
Tractor, and visited Head Office of United Tractor and one Eco-school (SDN
Bantarjati 9) in Jakarta.
14

Figure 6 Environmental Prince and Princess with Minister of Environmental


(left) and with staff from United Tractor (right)

Working with Public Programs


We continued to supervise cCompost production by environmental cadres in Kuala
Kencana, Bringin Village and Inamco Camp were continue to be supervised. During
the month, 141 kg of organic compost was produced from Kuala Kencana.

Figure 7 Organic composting observation at Inamco Camp (left) and collection


activity (right)
Other Working with the Public Programs:

15

Supported housekeeping activities by some residents.


Presentation of PTFI Environmental Management to 25 participants from
PNIEL Youth Evangelical organization and Global Warming to 47 participants of
YAPEDA organization.
Involved in environmental exhibition in Jayapura and displayed several 5R
materials, biodiesel information and several activities from Environmental
Department.

Figure 8 Exhibition booth (left) and explanation of 5R products to the Head of


Jayapura (right)

Environmental Event
Supported Environmental Day celebration in Graha Eme Neme Yauware Mimika
which was officially opened by Bupati (Regent) of Mimika and in Otonom Office
Jayapura which was officially opened by Governor of Papua. During the event, eight
schools from Mimika District received the Adiwiyata Province award.

Figure 9 Representatives received Adiwiyata for District Award (left) and for
Provincial level (right).

3R Program
Collected a total of 191 recycled materials from LIP Fabrication and United Tractor
and delivered to the approved contractor for recycling.

Environmental Monitoring
Timika Environmental Laboratory
During the month, TEL received 321 COC which included 1,098 samples and 12,788
analysis. TEL also published 342 Analytical Reports which consisted of 1,212
samples and 12,328 analysiis. Turn Around Time for the month was 90.6% less than
2.4 weeks. There were 2 AR revision for the month (0.6%).

16

Laboratory instrument availability status is 93% which included one instrument


under maintenance (automatic titrator), one unit ICP 3000 DV was waiting for
contract finalization for vendor to come to site and one unit LECO 432 which was
waiting for spare parts. New unit of TOC analyzer and FIMS installation was
completed.
MoE certification for environmental laboratory was on hold by KAN until
administration process was completed.

Sulfate sulfur project status is waiting for review from Contract Group and
Sucofindo which mostly related to the proposed price per sample. Material and
QC samples for this project have been collected and sent to Suciofindo.
Received samples categorized as Routine (59%), Special Project (20%),
Compliance (10%), LTEMP (9%) and QC (2%). Six major customers were TRMP
(33%), Environmental Abiotic (29%), Environmental Coastal (11%), DMQA
(9%), Facilities Management (8%) and Reclamation (4%).

17

Abiotic Monitoring
Forty three (43) from total 48 OWS facilities permitted were monitored on June
2013, while two OWSs were under construction (OWS-HLKBR-03 & OWS-LLKPI-17),
two OWSs with closed access/restricted area (OWS-HLUGAML-01 & OWS-HLUGAPT01) and one OWS has security issue (OWS-LLKPI-15).

Figure 10 Oil and Grease sampling from outlet of Underground OWS (left) and
outlet of Grasberg OWS (right)
Water quality monitoring included daily #57-Banti sampling, weekly DWP
Effluent, biweekly Lower Wanagon sampling, monthly RKL/RPL Highland-Lowland
rivers, monthly RKL/RPL Estuarine, monthly OWS effluents, monthly & weekly
tailing discharge at compliance point, monthly ARD-74 Plant sampling, monthly
Grasberg drainage, groundwater sampling at community wells, semi-annually
Alpine regional, semi-annually Tsinga Beanagong rivers, re-sampling at Kuala
Kencana domestic waste discharges and Golf course. Special projects sampling
comprised of weekly #57 Geo Chemistry composite, effluent OWS sampling at
AB Tunnel 2510, WDD discharge sampling, Mahaka flume sampling,
Tsinganogong water sampling and biweekly spill sampling at MA205.
Continuous ambient air quality monitoring at Ridge Camp, MP74 and Cargo Dock
stations included routine analyzer performance check and maintenance at Ridge
Camp, MP74 and Cargo Dock stations. The NO analyzer at MP74 station hass a
problem with cooling chamber and ozonator, while CO analyzer at Ridge Camp
and Cargo Dock showed unstable readings. Vendor is scheduled to visit to
resolve those issues.
Other air quality monitoring activities comprised of noise level monitoring at
Base Camp, Portsite, TPRA and Ridge Camp; dust fall monitoring at 4 locations

18

around ModADA; and particulates sampling using High Volume Air Sampler
(HVAS) at Amole M74, Ridge Camp, BMKG and Cargo Dock. There was no air
emission monitoring conducted during the month due to mine operation and
production were temporary stoppageed.
Meteorological activities included daily data updates and review, maintenance of
rainfall stations at Met-04 BMKG by fixing the power converter and network
communication link trial, and data collection from rainfall stations at Urumuka
HP01 & HP04. Data captured from existing meteorology and rainfall stations was
100%, except for Met-04 BMKG which only 90% captured.
Continuous ambient of mercury monitoring activities included routine
maintenance and calibration of Mercury analyzer (checked denuder, filter and
Argon gasses) with 100% data captured. Repair of lamp indicator of mercury
analyzer 2357AB is waiting lamp indicator part as no available stock. Mercury
survey in Timika using Lumex mobile analyzer was conducted with high mercury
concentrations observed was 43 ng/m3 at Gorong-gorong (Toko Mas Pak Haji) and
137 ng/m3 at Padat Karya Street (behind of Serayu Hotel).
Updates of some environmental abiotic monitoring projects were as follows:
Study-A project for river hydrology at Banti area (#56 and #57) comprised of
bed river profiling (twice a day), flow measurement (twice a day), daily data
updating, and water samples collection (4 samples a day).
Helipad and Wind-Sock project was still in material order process. Total
material in stock was 100% and the work would be started when condition isf
favorable.
Urumuka project comprised of removing monitoring teams and remobilization
security teams and important materials from HP 04 and HP 05; field data
updating (rating curve, automatic water level gauge, etc.) at HP-01; biweekly
data downloading and supplies delivery; and water sampling for suspended
solid tracking. During the month, there were six (6) visitors from MWH and
seven (7) visitors from Aurecon to conduct survey for transmission line and
water transportations for construction plan. Flow measurement recorded
were: minimum flow of 108m3/s, maximum of 460m3/s and average of
197m3/s. River profile measurements at HP 01 showed minimum water level
(WL) observed was 24 cm and maximum was 241 cm.
Continued isotope rainfall sampling as requested by BMKG - Columbia
University.
Total number of samples collected during the month was 390 and YTD highland
water quality monitoring sampling achievement was 41 % versus from 42 %
targeted.

19

Coastal and Marine Monitoring


Land clearing and excavation works of Ajkwa alternative channel phase II has
reached 200 meters out of 600 meters total length targeted. This project is
required to temporarily provide access for local people from the East (Omawita,
Fanamo, Otakwa, Jilla, etc) and Government officer to cross Ajkwa Estuary during
low tide. It also provides temporary access for company to conduct environmental
monitoring activities at eastern areas.

Figure 11 Excavation of Ajkwa alternative channel phase II by PT. Ejore Amiete


Papua
The activities of aquatic biological monitoring included nekton sampling by trawl
net from 13 monitoring stations (EM330, EM332, EM275, EM276, EM281, EM270,
EM274, EM430, EM432, EM770, EM773, EM870 and EM871); estuarine benthos
sampling and sorting of 10 out of 15 stations; preparinged the benthos
sediment samples prior to analysis; completed the estuarine invertebrates
identification under supervising of invertebrate expert from Australia (John
Short); metals in tissue samples processing from routine samples and freshwater
fish from ModADA and SP1; and conductinged fish test acclimatization, acute
test at S255 (tailings river), cadmium test and drafted bioassay protocol for
organic matter testing.
Coastal Geomorphology monitoring comprised of bathymetry measurement in
the Ajkwa estuary and cross section 2 (CR2), while CR3 and CR4 could not be
reached by boat due to low tide condition; tide recording in three sites (Ajkwa,
Tipoeka and Cargo Dock); reviewed the high mercury concentration in sediment

20

from Kamora rivers system and collected the secondary data from exploration
study; and storm water samples collection.
Total samples collected during the month was 416 samples, with YTD coastal and
marine sampling progress at 1,837 or 56.7% from 47.5% of YTD target.

During the month, boat availability was 83 % with two boats were under
maintenance (Mawiro was in dry dock due to engine replacement and Kopero for
body repair). Boat utilization is 100% with total boat request in the month was 80
trips of boat requisitions served.

Updates of some environmental coastal and marine monitoring projects were as


follows:
Ninety two percent (92%) or equal with 46 hectares out of 50 hectares target
of dead trees at Mile 1517 area (Ajkwa Diversion Channel) have been cut by
PT. Srikandi Mitra Karya.
Continued area clearing, material pilling and channeling works which the total
channel length achieved was 200 meters out of 600 meters targeted.

Reclamation and Biodiversity


Highland Reclamation
Ten (10) plots of slope area in Blitar 4030L and in Tembagapura along the stream
affected by erosion or landslide have been reclaimed using hydro-seeding. The
21

materials used were GFM 200 bags, 100 bags of bactosoil, omega biosol 100 bags,
20 kg of vermonia vitex, 20 liters of vermonia vodria, 20 liters of wallichi schima, 5
bags nursery coats, 50 bags seed of Deschampsia klossii, and 50 bags of moss.

Figure 12 Hydro-seeding Activity in Blitar 4030L area (left) and Tembagapura


River (right)
During the month, there was no reclamation activitieswere no revegetation
activities in Grasberg Area due to no surface area available to be
planted.preparation for reclamation. YTD reclamation progress was 11.87
hectares (29.68%) out of 40 hectares as the internal 2013 reclamation plan
target.

In June, Highland Reclamation group propagated 3,400 clumps of Deschampsia


klossii grass and prepared of 3,700 coco-pots of propagation media in Grasberg
nursery. Total number of plant stocks in Grasberg Nursery wereNursery were
79,632 clumps of Deschampsia klossii grass and 4,390 seedlings of local subalpine shrub.
Fifty four (54) plots were monitored in June 2013 included of tens (10) plots in
OGD, fifteen (15) plots in Middle Wanagon, three (3) plots in Bali Area, two (2)
plots in Blitar Area, twenty (20) plots in Lower Cartensz, one (1) plot in Upper
Cartensz area and two (2) plots in Mega shop area. Total 172 of 282 reclamation
monitoring plots were completed.

Lowland Reclamation

22

Reclamation activities in double levee was re-activated at the 2 nd week of June 2013
by plantinged 200 sago palm seeds in 3.8 hectare and prepared 4.4 hectare
planting area. Meanwhile, Waii Island recalamation was re-started in 3rd week of
June by plantinged 27,000 propagules of Rhyzophora mucronata and collectinged
8,000 propagules and 1,300 seedlings of Avicennia marina.
Lowland reclamation programs included planting 3,280 seedlings of vegetables,
propagated 1,600 seedlings of agriculture crops and 891 seedlings of local tree
species in MP21 nursery, and harvestinged 420 kg agriculture crops that were
cultivated in the MP-21 tailings agriculture demonstration area.
Other lowland reclamation programs consisted of maintaining the reclamation
plants by cutting grass covered 18.6 hectares, planting legumes crop to cover
1.10 hectares for erosion control, fertilizinged 4,860 trees and maintained 118
trees inside double levee.
Cattle ranch activities were routine maintenance, planted 4.3 hectares of kinggrass in cattle ranch area (inside double levee). The existing cattle population is
66 head, with two of calves was born in the month.

Figure 13 Agriculture activities at MP-21 tailings agriculture demonstration


area
During the month, a total of 58,575 kg compost was produced, comprised of
1,200 kg of vermin compost from Borobudur Tembagapura, 3,375 kg compost
from MP-38 and 54,000 kg compost from MP-21.
In June 2013, the number of local plants species propagated in MP32 nursery for
Kuala Kencana Land remediation Program were 495 trees consisted of 375 iron
wood, 985 matoa, 132 trembesi, and 3 boat trees. Total stock in Nursery MP-32
were 38,796 trees consisted of 25,618 seedlings of iron-wood (Intsia bijuga);
6,400 seedlings of matoa-tree (Pometia piata); 3,837 seedling of trembesi-tree
(Samanea saman); 1,135 seedlings of milk-tree (Alstonia scholaris); 827 Cina-tree
(Podocarpus amara); 778 seedlings of boat-tree (Octomeles sumatrana); 93

23

seedlings of Lawang-wood (Cinnamomum cullilawan); 28 seedlings of Nem-wood


(Azadirachta indica) and 80 Buah Merah (Pandanus conoideus).
YTD reclamation achievement of Kuala Kencana Land Remediation was 4,806
trees which covers 12.02 ha out of 85 ha for the target of Phase III in 2013 (May
2013 to April 2014). Total maintenance was 30,189 trees which cover 75.5 ha
and YTD achievement in June 2013 was 33.12 % out of 365 ha as target.14 ha.

Biodiversity
PT. Freeport Indonesia represented by Andi Mukhsia, Vice President of
Environmental Department, receivedpt Indonesian Green Award for Biodiversity
Conservation Program Category that was held by La Tofi School of CSR.

Figure 14 VP Environmental Departprtment received Indonesia Green Award


(left) and Biodiversitys crew wrapped up charcoal into sacks for plant
maintenance (right).
During the month, other biodiversity activities were as follows:

24

Visited the Indonesian Science Institute (LIPI) and discussed about ecosystem
diorama re-construction.
Participated in training of GIS Analysis for Strategic Environmental
Assessment for Mimika Regency spatial plans held by IFAC-USAID and Mimika
Government.
Conducted fauna monitoring program in double levee with participated by 4
internship students from ITB on this work.
Monitored mammals, birds, reptiles, butterflies, insects and amphibians from
eleven (11) of monitoring locations.

Deepeneding of the lake in NSDP MP-21.5 to obtain water using excavator


was 50% complete.
Produced charcoal for orchid planting media by utilize dead trunk surrounding
MP-21.
Collected ornamental plant species from surrounding Kuala Kencana forest
and planting in Ornamental Plant Botanical Garden MP-21.
Discussions with Resit Sozer of PPSC Cikananga (West Java) with the topics
relating to the repatriation of animals of Papua
Bird-watching activity at Rimba Golf Kuala Kencana involving 3 junior high
school in Timika and attended by 30 students.

Jakarta Environmental Affairs


Participation on symposium/workshop/other event
Participated in the Environmental committee of IMA to discuss and prepared IMAs
position to the draft Ministerial Decree on Mining Effluent Standard and Air Emission.
Participated in the technical workshop on Reclamation and Mine Closure facilitated
by the Directorate General of Mineral and Coal Mining of MEMR.
Participated in the socialization meeting of PTFI 2013 budget to the Governor of
Papua, in Bali.

Reporting and Management System

Continued to compile and review the Q1-2013 RKL-RPL reports.


Updated 2012 environmental fact sheet that was requested by Corporate
Communication Department to be published on the External PTFI Web.
Prepared presentation materials for Tailing Communication Forum that will be
conducted at jobsite on 1-2 July 2013 in Timika.

External Meeting of Environmental Affairs

25

Title

Subject

GOI
Meetings

Mining Effluent
Standard, Stationary
Air Emission Standard
and Update on
the Latest B3 Wastes
Draft Regulation.

Description
Participated in the Environmental committee of
IMA to discuss and prepared IMAs position to
the draft Ministerial Decree.

Tailing Concrete Trials

Participated in the meeting with Road and Bridge


Research Centre, Ministry of Public Work ministry
to discuss the latest update on tailing concrete
trials.

Institutio
ns /
Universiti
es
Meetings

Review Draft Proposal


From PT LAPI ITB.

Participated in the meeting coordinated by


Govrel to review draft proposal from PT LAPI ITB
to assist PTFI on Long Term Plan of CoW B.

Tailing Concrete
National Standard

Met with Polymer Research Center of BPPT to


update the latest progress on tailing polymer for
Tailing Concrete National Standard.

Other
Meetings

Managing Used Tire


Wastes

Met with a potential vendor to discuss option for


managing used tire wastes. We requested that
the vendor provided a more workable proposal
for further review.

Visitor

26

USAID and IFACS visited jobsiteonsite for Carbon stock inventory project. The
aims are to establish collaborative natural resource management in southern
Papua wetlands that include the second largest contiguous block of mangroves in
the world. Scope of work is to reduce deforestation and Green House Gases
emission
John Short, a crustacean expert from Australia, conducted crustacean specimen
re-identification from 2011 2013 samples and held crustacean identification
training for Coastal staffs.
Engineer representative of Magna Sardo (M. Fadhil) is on site for LECO 632 repair
and maintenance.
MWH & FCX team visited to Urumuka Hydropower project site
Happold Consulting team visited jobsite for presenting work plan of Coastal
Management Plan project and to discuss baseline design of tailings reclamation
area.
Tiga Macan and Rukindo company representatives were invited to jobsite for
introduce company profile, to conduct field observation and to discuss dredging
work plans for shipping channel and tailingsAjkwa Estuary.
PT BITA Bandung visited to jobsite for baseline of air and water quality sampling
in association with the AMDAL of Water Treatment Plant for Mimika Regency.
Mr. Shaun Levine from Global Political Consulting Firm of Eurasia Group visited
MP-21 area.
Mr. Cyprianus Anto Saptowalyono and Mr.Erwin Edhi Prasetyo from Kompas
visited MP-21 area.
Wahyu Utami (Deputishipi III, KLH/Environmental Ministry), La-Ode Syamsul
Imam (IPB/ITSL), Kadoarjuna (BPSDLAH PROV) and Yohanes Laurens (BLH, Kab.
Mimika) visited MP-21 area.

Figure 15 Tumpal Sinaga presented Reclamation & Biodiversity activities (left)


and Barnabas Murib presented Reclamation & Biodiversity activity (right).

Environmental Project Status


Project
Title

27

Project
Description

Status June 2013

28

ARD
Management

Managed, collected and Target has been achieved. Flow from WDD
is significantly influenced by rainfall and
treated ARD.
varied from 6,500 to 7,000 gpm last
month.
24 HDPE installation progress last month
was 50.57%, slow progress as the project
is suspended associated with Big Gossan
incident

Lower Wanagon
Overburden
Management

Safely and effectively


managed overburden
placement

Cumulative progress Wanagon project


productivity was 30.04% below from plan
of 50.04%. MW4150 unloading continued
at 4045L and productivity at MW4150
was about 17Ktpd (Load&haul 13Ktpd
and dozing 4 Ktpd), excavator continued
project grading of final slope to 26
degree at 4105-4060L with update
progress resloping = 0.7 ha from target
= 4.10 ha. At LW3845 project, continued
dozing/unloading at 3775L to 3760L at
south side LWU resloping project.
June'13 productivity was about 595Kt
(26Ktpd). Shovel productivity was 13Ktpd
and 8Ktpd for dozing.
A construction and installation of 4ea
HDPE pipe 24 to drain clean water at
berm#3 has been completed. Installation
of 3ea HDPE 24" pipeline at berm#1 was
continued.
Continued dumping material at berm#2
from sh#03 or excavator to leveling
berm height until meet design at east
side of berm, remaining material
required for final construction berm#2
approximately about 6Kt.

Tailing
Management

Safely and effectively


managed tailings
deposition in the
ModADA.

Completed levee construction by 1.6


million m3 of loose material at an effort
rating of 36.4 million m3km.
Planting 17.4 ha on bio-retention for the
area within 100 meters of the Levee
Embankment.
Planting 1 ha of vegetation on the
upstream slope of the Levee
Embankment.
Build 9.2 km of series of stream deflection
channels to increase tailing retention at
ModADA in order to meet with KepMen
431 associated with total suspended
solid parameter.

29

Kwamki Lake
System Drainage
Enhancement

Minimized the impact of


water from the ModADA
on sulfate concentration
in groundwater for
drinking waters
downstream and
surrounding ModADA.

Ongoing, water level and water quality data


are being incorporated into the model.

Improvement of
Dewatering
Plants Effluent
and Drainage
System

Quantified, evaluated
and mitigated where
necessary high TSS
discharge from
Dewatering Plant in
Portsite and to improve
drainage system of
Dewatering Plant

Piling delivery and piling preparation for


welded connection are on-going. Piling
contractors are on site and driving piles
(131 started, 28 completed). Engineering,
site survey, and old concrete demolition
are on-going.
Q2 = 540 m3
13 YTD = 904 m3
PTD = 7,335 m3
Area 3C concrete completed.
Area 4A excavation in progress.

Tailing Utilization

Increased tailing
utilization at PTFI work
areas and Province
Papua in order to
support infrastructure.

The standard concrete cube trial is


continued with the newest best
performance polymer formulized by STPBPPT with the compressive strength of
concrete: 20 MPa, 25 MPa, 30 MPa, and
35 MPa respectively. The trials need 28days for every tailing concrete tested.
The phase of work with BPPT and Public
Work to obtain SNI on tailing concrete
from Indonesian National Standard body
will be initiated once the trials have been
completed. Service contract is being
considered to other consultant option.

Energy
Efficiency and
Conservation
Plan

Continued development
and implementation of
a site energy efficiency
and conservation plan.

Meetings had been conducted and Energy


Manager had also been appointed but there
is still no progress on the specific item.

Sedimentation in
the Ajkwa
Estuary

To ensure that there are


available transportation
alternatives between
the east side of the
Ajkwa estuary and the
Timika area, even
during low tide.

Ajkwa channel project phase-2 has been


started. Conduct Ajkwa channel dredging
as long as 150 meter from 600 meter have
targeted.

Oil Water
Separator (OWS)
Improvement

To achieve greater
consistency of effluent
quality standard that
conforms to the permit
requirements. The
permit requirement that
applies has been

Contract to have consultant (Nusantara


Water Centre) to review 45 OWS facilities at
jobsite has been approved by Management.

mg/L of Oil and Grease


in the effluent.
Resolution of
NOx Emissions
from Diesel
Power Plants

Map

30

To resolve NOx
emissions from dieselfueled generator plants
to meet GoI regulation
standard.

Proposals from two vendors have been


received. The decision will be made in July.

31

Вам также может понравиться