Let the size of brick be 230mm x 115mm

x 75mm
Vol. of brick( w/o mortar) = 0.00198 cum.
Thk. of mortar be 12mm.
vol. of brick with mortar = 242mm x
127mm x 87mm
= 0.00267 cum.
No. of bricks in 1 cum. with mortar =
1/0.00267
= 373.99
Say = 374 bricks.
Cement Mortar required = 1-( 374 x
0.00198)cum.
= 0.259 cum.
Say 0.26 cum

b.s.dev

Add 15% for frog filling and wastage


while execution.
Vol. of wet mortar = 0.299 cum.
Vol. of dry mortar( increase by 30% ) =
0.388 cum.
For CM of 1:6
Qty. of cement = 1/7 x (1440 x 0.388)
= 0.055 cum.
Qty. of sand = 0.055 x 6
= 0.330 cum.
Is This
Answer
Correct ?

144
Yes

Answer
#2

47 No

Let the size of brick be


230mm x 115mm x 75mm
Vol. of brick( w/o mortar) =
0.00198 cum.
Thk. of mortar be 12mm.
vol. of brick with mortar =
242mm x 127mm x 87mm
= 0.00267 cum.
No. of bricks in 1 cum. with
mortar = 1/0.00267

ar. g.s.
rehal

= 373.99
Say = 374 bricks.
volume of 374 bricks= 374 x
0.00198 = 0.74052cum
Cement Mortar required for
1cum = 1 - 0.74052cum.
= 0.259 cum.
Say 0.26 cum
Add 15% for frog filling and
wastage while execution.
.26 x 15/100 = 0.299 cum
Vol. of wet mortar = 0.299
cum.
Vol. of dry mortar( increase
by 30% ) 0.299 x 30/100
=0.0897
0.299 + 0.0897 = 0.388 cum.
For CM of 1:6 (1 + 6 = 7)
Qty. of cement for 1cum = 1/7
x 0.388
= 0.055 cum.
Qty. of sand for 1cum = 0.055
x6
= 0.330 cum.
Qty. of cement for 10cum =10
x 0.055
=0.55 cum.
Qty. of sand for 10cum = 10 x
0.330
= 3.30 cum.
Is This
Answer
Correct
?

Answer
#3

71
Yes

20
No

The size of brick be 230mm x


115mm x 75mm
Vol.of brick( w/o mortar) =

uday kiran

0.00198 cum.
Thk.of mortar be 12mm.
vol.of brick with mortar =
242mm x 127mm x 87mm =
0.00267 cum.
No.of bricks in 1 cum. with
mortar = 1/0.00267 = 373.99
Say = 374 bricks.
Cement Mortar required = 1(374 x 0.00198) cum= 0.259
cum.
Say 0.26 cum
Add 15% for frog filling and
wastage while execution.
Vol. of wet mortar = 0.299
cum.
Vol. of dry mortar (increase
by 30%) = 0.388 cum.
For CM of 1:6
Qty. of cement = 1/7 x (1440
x 0.388) = 0.055 cum.
Qty. of sand = 0.055 x 6 =
0.330 cum.
Is This
Answer
Correct
?

Answer
#4

26
Yes

8 No

mortar required for 10 cu.m


brick work
Dry mortar = 30% of brick
work = 3 cu.m
one part of
cement=3cu.m/sum of
proportion
(3/1+6)=0.428cu.m
cement required in
bags...0.428/vol. of one bag

jocky

of cement
(0.428/0.035) =12.23 bags
..take 13 bags of cement
sand = 0.428*6= 2.57 cu.m
Is This
Answer
Correct
?

Answer
#5

8 No

see CPWD ANALYSIS


480 BRICKS PER CUM I/C
WASTAGE
1.24 BAGS CEMENT/CUM
I/C WASTAGE
1.24*.035*6 = WILL BE THE
QTY OF C.SAND REQD/
PER CUM
Is This
Answer
Correct
?

Answer
#6

21
Yes

22
Yes

sudhir

13
No

The size of brick be 230mm x


115mm x 75mm
Vol.of brick( w/o mortar) =
0.00198 cum.
Thk.of mortar be 12mm.
vol.of brick with mortar =
242mm x 127mm x 87mm =
0.00267
cum.
No.of bricks in 1 cum. with
mortar = 1/0.00267 = 373.99
Say = 374 bricks.
Cement Mortar required = 1(374 x 0.00198) cum= 0.259
cum.

arvind
vyas

Say 0.26 cum


Add 15% for frog filling and
wastage while execution.
Vol. of wet mortar = 0.299
cum.
Vol. of dry mortar (increase
by 30%) = 0.388 cum.
For CM of 1:6
Qty. of cement = 1/7 x (1440
x 0.388) = 0.055 cum.
Qty. of sand = 0.055 x 6 =
0.330 cum
Is This
Answer
Correct
?

Answer
#7

6
Yes

1 No

Consumption & Rate analysis


Brick Masnory 230mm 1:6
Superstructure With
scaffolding
Providing and placing brick
work 230mm 1:6
Superstructure
With scaffolding
1.3Ref: use 1..3 standard
Proportion of materials
Cement 1
Sand 6
Total 7
Std constant(1.5) / Total of
proporttion(4)
0.186
1) Required volume of
cement for 1 cum.
1 Proportion of cement 0.19
Add wastage(2.50%) 0.005
Vol of cement for 1 cum
0.190
0.035 is cum of per 50kg of

bhupendr
a potpose

bags 5.44.
As per standard we assumed
that in 1cum of brick work
,the
quantity of mortor (Cement &
Sand )is consider in
quantity. (24%) 1.28
Cost of cement per bags 325
Total cost of 1.34 bags
415.39
2) Required volume of Sand
for 1 cum
2 Proportionof Sand 1.114
Add wastage(2.50%) 0.028
Vol of Sand for 1 cum 1.142
As per standard we assumed
that in 1cum of brick work ,
the quantity of mortor
(Cement & Sand )is consider
in
quantity.(24%) 0.268
Cost of sand per brass 875
Total cost of 0.284 cum sand
234.85

3)Required brick for 1 cum of


size 230x115x75mm
Actual Vol of one bricks is
0.00198cum,&
10 gap Allaround is become
0.00255
Nos of bricks in 1cum0.00255
1 392.16
Add wastage(10.00%) 39.22
Total Required brick for
1 cum 431.37
Cost of bricks 5.00
Total cost of brick 2156.86
A)Total material cost (1+2+3)
2807.10

4)Cost for Manpower


,Mixing ,Shifting ,
placing etc, Rs 15 / sftMumbai, 529.80
5) Cost for screeing,
cleaning ,of sand (10%)
333.69
6) Cost for Tools ,
Safety, curing etc(5%) 183.53
B) Cost of labour on
total material cost (4+5+6)
1047.02
C) Cost of Material & labour
(A+B) 3854.12
5)Add over head(5%) 192.71
6)Add profit on(15%) 607.02

D- Total of (C+5+6),Over
head & profit cost
P/A P230mm,1:6 Per Sqm.
4653.85
If the brick work is required to
.

convert into Sqmt


1) for 230mm ; 0.23 1070.39
2) for 115mm ; 0.115 535.19
Is This
Answer
Correct
?

Answer
#8

7
Yes

2 No

lets the take size of brick is .


230*.115*.075. now calculate
the quantity for 10 cum.

karan
bagga

Area of one brick without


mortar -0.00198375 Cum
No of brick in 10 cum=
10/0.00198375 (Area of
bricks).
=5041 nos of bricks.
now calc. the bricks quantity
in 10 cum with mortar.
lets take the mortar used
10mm in brickwork then
size of brick will be taken with
mortar is =.240*.125*.085=
0.00255 (Area of one brick
with mortar).
now in 10 cum brickwork no
of bricks calculated with
mortar
is=10/0.00255 =3922 nos
calculate the mortar in cum=
bricks without mortar- bricks
with mortar= 50413922=1119 nos
Now area of brick without
mortar is .
230*.115*.075*1119=2.22cum
now 15% for frog filling and
wastage taken in acc.
=2.22+2.22*15/100=2.55 cum
Dry volume is the 1/3rd of wet
volume of mortar=
2.55+2.55/1/3=3.40 cum.
now the ratio is 1:6=7
3.40*14%=.486 cum cement
3.40*86%= 2.92 Cum Sand
=.486/.0347= 14.01 bags/10
Cum

= 14.01*6=84.06 Bags/10
Cum
Is This
Answer
Correct
?

Answer
#9

2 No

you are given 3x4x9


standard size of bricks
After placing mortar it
became- 4x5x10 =
10.16cmx12.7cmx25.4cm
No of bricks are required=
10/.106x.127x.254=3069 nos
The size of brick without
mortar= 3x4x9=
7.62cmx10.1cmx22.8cm
Then net mortar required
=10-(3069*.076*.101*.228)
= 4.62cum
Due to frog filling, brick
bonding course and
wastage add 15%
Volume of wet mortar=
4.62+4.62x15%=5.30cum
When dry increase this qty.
by 1/3rd=
5.30+5.30x1/3=7.06cum
Ratio is =1+6=7 cement =
7.06/7= 1.06 = 29 bags
Sand= 7.06*6= 42.36cum
Is This
Answer
Correct
?

Answer
# 10

4
Yes

47
Yes

sjtbehera

51
No

No of bricks = 500
[5(Stredger face with 10mm
CM)*10(Header face with

muthu
kumaran

10mm CM)*10(Header face


with 10mm CM)]
Volume of mortar required =
1-500*0.19*0.09*0.09
= 0.2305 cubic metre
Cement required for 1:6 =
(0.2305*1440)/7
= 47.41 Kg (Approx. 48 Kg)
(Density of cement 1440
Kg/cu.m)
Sand required = 284.5 Kg
(Approx. 288 Kg)