PURPOSE & SCOPE


This chapter presents an outline of Quality Management System related to
realization of services and execution of projects by various SBUs of RITES.
The various services provided by SBUs have been covered under Chapter 2
and further elaborated with concerned SBUs.

II.

POLICY

1.

PLANNING OF SERVICE REALIZATION (Clause 7.1 of ISO 9001: 2008)

1.1 Major services provided by RITES through its various SBUs are as given
under Chapter 2, which shall be further, elaborated at SBU level through
suitable documentation. Processes needed for realization of these shall be
planned at SBU level in keeping with business requirements. Corporate /
Support processes shall be planned to provide services / discharge functions
in compatibility with other business processes.
A Process Flow chart for RITES as an organization is depicted at AnnexureA. Process Flow charts related to SBUs shall be documented at SBU level.
The flow charts shall provide the overall planning for realisation of various
services showing also the interfaces with other major processes within or
outside RITES.
1.2 In planning service realisation, for any existing / new area of service, new
project following issues shall be determined as appropriate:
-

Quality objectives and requirements for the service including customer


expectations.
The need to establish additional processes and documents and to
provide the resources specific to the service / project.
Required verification, validation, monitoring, measurement, inspection
and test activities specific to the service / project and criteria for service
acceptance.
Records needed to provide evidence that realisation processes and
resulting deliverables meet the requirements.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

SERVICE REALIZATION

Chapter No.: 7

(Clause 7 of ISO 9001 : 2008)

Page No.: 2 of 3
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

The output of this planning is consolidated in the form of Procedures, Work


Instructions, Check Sheets, Quality Plans etc and are made available for
usage by relevant personnel.
1.3 The major processes for product realisation are the following:
a.

Customer related processes including:


-

b.

Design and development including


-

c.

control over purchasing process


control over purchasing information
verification of purchase products/ services

Control over Service Provisions including


-

e.

design and development planning.


design and development inputs, outputs
design and development review, verification, validation.
control of design and development changes.

Purchasing including
-

d.

determination of requirement related to service.


review of requirements related to service.
customer communication.

control of project / service execution


process validation
identification and traceability
control over customer property
preservation of product

Control of monitoring and measuring equipment.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

SERVICE REALIZATION

Chapter No.: 7

(Clause 7 of ISO 9001 : 2008)

Page No.: 3 of 3
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

The above processes have been outlined under various subchapters


of Chapter 7.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008
Issue No.: 03
CUSTOMER RELATED
PROCESSES

Chapter No.: 7-A

(Clause 7.2 of ISO 9001 : 2008)

Page No.: 1 of 6
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

I.

OBJECTIVE & SCOPE:


This chapter provides RITES policy related to business development,
determination & review of service requirements and Customer
Communications. It applies to all areas of business of RITES, carried out
by any SBU or through Corporate level marketing activities.

II.

POLICY:

1.

This Policy shall be implemented by all SBU Heads through their project
co-ordinators, activity heads responsible for business development and
execution. At Corporate level, it shall be implemented by Head, M&CS.

2.

Business Development:

2.1

Focus on business development exists all through the organisation. Each


Division / SBU shall make efforts towards achieving targets for new
business development, turnover, operating ratio etc. laid down based on
Corporate direction given from time to time. In addition business
development activities shall also be pursued at corporate level from
Marketing & Client Services.

2.2

Opportunities for business development shall be identified through various


possible means such as newspapers, business letters, personal contacts,
Internet scan, references by customers, agents, funding agencies,
concerned ministries etc. Proactive marketing shall also be undertaken on
need basis through introductory letters, meetings and presentations. As
needed presentations / marketing brochures shall be developed at
Corporate / SBU level. Initial/preliminary information received by sources
as above shall be further consolidated/augmented through various means
including personal meetings at appropriate level, as may be required to
determine client requirements.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008
Issue No.: 03
CUSTOMER RELATED
PROCESSES

Chapter No.: 7-A

(Clause 7.2 of ISO 9001 : 2008)

Page No.: 2 of 6
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

2.3

As a result of above, initial proposal may be made covering basic


concepts and methodology of the project, relevant experience profile etc.
for clients perusal. This may be in the form of an expression of interest
(EOI).

2.4

Based on clients response to initial proposal / or directly after initial


interactions, as the case may require, an offer detailing terms of reference
and price offer shall be sent to the client along with other necessary
documents. In case of a tender the tender document shall be submitted to
client incorporating various details as may be required. Wherever any
specific formats are prescribed (e.g. In case of World Bank offers) the
same shall be complied with along with any underlying rules / regulations
applicable.

3.

Determination of Requirements Related to the Service: (Clause 7.2.1 of


ISO 9001: 2008)

All relevant requirements applicable to the service shall be determined


and considered including:
-

Requirements specified by the client, including requirements for


service delivery and post delivery activities.
Requirements not stated by the customer but necessary for to be
incorporated in the service to be executed for its stated or intended
use.
Statutory and regulatory requirements applicable to the service to
be provided.
Any additional requirement considered necessary by RITES.

Review of Requirements Related to the Service: (Clause 7.2.2 of ISO


9001: 2008)

4.1

Before submission of a tender / offer and/or the acceptance of contract /


order, the requirements related to the service / project to be executed,
shall be scrutinized and reviewed to ensure that:

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008
Issue No.: 03
CUSTOMER RELATED
PROCESSES

Chapter No.: 7-A

(Clause 7.2 of ISO 9001 : 2008)

Page No.: 3 of 6
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

a)

The requirements are adequately defined. Where no written


statement of the requirement is available for an enquiry / order
received by verbal means, it is ensured that requirements are
documented at receiving end. In all cases it shall be ensured that
requirements are agreed before acceptance

b)

Any differences between the tender, offer, contract agreement and


the order are brought out, reviewed, discussed at appropriate level
(if required with customers representative) and finally resolved to
the satisfaction of both, RITES & client.

c)

Before making any commitments, it shall be ensured that RITES


has the abilities to meet these requirements.

In order to match the requirements of the project, RITES has opted the
approach of a flexible organisation. Technical and managerial capabilities
required for the project shall be given due consideration and planned. As
needed the expertise, resources needed may be planned to be provided
from various sources such as:
4.3

Within RITES (including other SBUs)


Indian Railways on Deputation
Other Govt. / Public Sector organisations on deputation
Open market on permanent basis / short term contract basis
Other organisations with whom RITES has MOUs / Agreements
Through joint ventures with other specialist organizations.

Amendments:
The amendment to any proposal/offer or agreement shall be reviewed in
the same manner as the original order/contract.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008
Issue No.: 03
CUSTOMER RELATED
PROCESSES

Chapter No.: 7-A

(Clause 7.2 of ISO 9001 : 2008)

Page No.: 4 of 6
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

After any amendment is agreed to, the relevant changes shall be


documented and information shall be passed on to all concerned promptly
through defined channels of communication / reporting.
4.4

Records of scrutiny, review & amendment shall be suitably maintained in


client / concerned project file etc.

5.

Necessary follow-up shall be kept for securing business at appropriate


level. As necessary negotiations shall be held, clarifications made and
amendments made to reach a mutually acceptable and technocommercially viable agreement resulting in a contract signed with the
client.

6.

Normally offers / contracts shall be made at the level of the co-ordinating


SBU / Division. However, in cases where multidisciplinary efforts are
needed, such offers may also be made through Marketing directly,
depending on the size / value / importance of the projects. Directions /
advice may be taken from other higher functionaries including Divisional
Heads / Functional Directors as needed in finalizing offers, accepting
contracts (specially in case of overseas projects), project approvals shall
be taken at appropriate level as per SOP.
While technical viability, methodology and logistics for the offer shall be
assessed at the level of concerned SBUs / senior level technical
functionaries, for commercial offers, detailed guidelines exist which
provide the basis for commercial offers. As may be necessary, offers shall
be subjected to financial vetting / concurrence by concerned Finance.

7.

On acceptance of the offer / bid and on award of work, a realistic work


plan shall be developed and potential impediments and risks on project
execution shall be identified and contours of contingency plan devised.
An inception report work plan / bar chart/ detailed methodology / resource
utilizations/ reporting schedule etc. as per requirement shall be presented
to the client.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008
Issue No.: 03
CUSTOMER RELATED
PROCESSES

Chapter No.: 7-A

(Clause 7.2 of ISO 9001 : 2008)

Page No.: 5 of 6
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

8.

The relevant mechanism for business development, contract review, etc


shall be covered in details in the Quality System Procedures relevant to
SBUs.

9.

Customer Communication: (Clause 7.2.3 of ISO 9001: 2008)


An organization exists because of its customers. Customer
Communication is of essence to Customer satisfaction. Hence effective
arrangements / means of Customer Communication shall be maintained.
All customer communication shall be treated with utmost care both at
Corporate Level and at SBU level to ensure timely and effective response
with necessary action.
-

All communications with respect to service profile, capabilities and


strengths are handled as a part of Business Development efforts.
Suitable Service Brochures, other publicity software / hardware
shall be developed and updated from time to time. RITES web site
shall also provide information on service profile of the organization.
All communications with respect to enquiries, contracts handling
and amendments shall be effectively handled at operational level
and responded in a timely manner through personal discussions,
letters, fax etc as suitable.
All communications relating to customer feed back/complaints shall
be effectively handled at the level of SBU Heads. These shall be
analyzed and examined for prompt action. These communications
can be made through personal meetings, in writing or through web
site of RITES.
All communications regarding modifications to contract shall be
suitably attended and are suitably documented.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008
Issue No.: 03
CUSTOMER RELATED
PROCESSES

Chapter No.: 7-A

(Clause 7.2 of ISO 9001 : 2008)

Page No.: 6 of 6
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

Proactive efforts to maintain customer communication for determination


of customer perception of the services shall be made through activities
such as Customer meetings, customer liaison, feedbacks and
questionnaires etc.
At Corporate level regular meetings are held with railway / other major
clients by Senior Officers including quarterly review meetings with
Railway Board which shall be used to maintain customer communication
and determine customer perception of our service. Any actions arising
from such interactions shall be communicated to concerned SBU head
who shall ensure its implementation to enhance customer satisfaction.

III.

REFERENCES:
SBU level contract review / marketing related procedures.
F & A Procedure for preparation of project estimates (Procedure order
No.3/2k dt. 26.12.2000, issued by COA)
Schedule of Powers (SOP)

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

Design and Development

Chapter No.: 7-B

(Clause 7.3 of ISO 9001 : 2008)

Page No.: 1 of 4
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

I.

OBJECTIVE & SCOPE:


This chapter describes the policy to ensure controls on all design and
development activities so as to fully meet client requirements along with
any other applicable requirements. This chapter covers all Design &
Development activities carried out by RITES SBUs including:

Rolling Stock Design


Railway Civil Engineering Design
Highways Design
Ports and Water Resources
Airports
Architecture & Planning
Signals & Telecommunication
IT
Training
Mass Transport
Urban Engineering
Ropeway & Industrial Engineering

II.

POLICY:

1.

This policy shall be implemented by SBU Heads through concerned


Project Co-ordinator and design personnel involved. Documented
procedures shall be implemented in all areas where design / development
activity is carried out.

2.

Design and development planning (Clause 7.3.1 of ISO 9001: 2008)


For every project involving design, the design activity shall be planned
bringing out planning for design to be undertaken such as the relevant
design stages, timeframe and requirements for verification, review &
validation; responsibilities and authorities for design & development
including involvement of consultants, experts and customer or his
representative(s) etc. The design / development plans shall be suitably

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

Design and Development

Chapter No.: 7-B

(Clause 7.3 of ISO 9001 : 2008)

Page No.: 2 of 4
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

documented, revised / modified and updated as the design evolves. It


shall be ensured that all design activities are assigned to competent
personnel, groups or agencies.
The design & development planning shall bring out organizational &
technical interfaces amongst design groups, SBUs, consultants, heads of
technical wings, project co-ordinators and if necessary concerned
contractors and customer and/or his representative(s), ensuring clear
responsibilities and effective communication so that necessary
documents/information is transmitted and regularly reviewed.
3.

Design & Development Input (Clause 7.3.2 of ISO 9001: 2008)


Design & development input requirements shall be established based on
contract review / further studies undertaken to establish the same. Design
& development input shall include functional & performance requirements
as applicable to the structure / infrastructure / facility / equipment / service
to be designed. In addition, designer shall take into consideration the
available previous data / information such as reports of survey relating to
geotechnical, seismic, hydrological, rock & structure/level, other historical
facts & other socio -environmental aspects and design input information /
data based on past experience for similar designs. Applicable statutory
legislation, regulations of the country concerned shall also be taken as
design inputs.
All available inputs shall be reviewed for adequacy, applicability and
conflicting or ambiguous requirements shall be resolved. This data /
information shall act as the basis for design activity and shall be recorded.

4.

Design & Development Output (Clause 7.3.3 of ISO 9001: 2008)


Design & development shall be carried out by competent technical
persons, well equipped with necessary data, information, equipment,
software etc. Design & development output shall be documented in
suitable fashion such as drawings, layouts, specifications, contracts,

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

Design and Development

Chapter No.: 7-B

(Clause 7.3 of ISO 9001 : 2008)

Page No.: 3 of 4
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

tenders etc, generated in a form that enables verification against design


inputs. Design output shall ensure the following:

Design & development input requirements are met


It contains / references relevant acceptance criteria.
Identification of critical design characteristics, for example, those
pertaining to safety & functional requirements.
Identification of characteristics of the product / service designed to
enable subsequent activities such as Purchasing / Tendering, project
execution and service provisioning etc.

All design & development documents, calculations etc. shall be reviewed


before release.
5.

Design & Development Review (Clause 7.3.4 of ISO 9001: 2008)


At appropriate phase of the design, review(s) of design & development
results shall be carried out as planned,

to evaluate the ability of the results of design & development to meet


requirements

to identify any problems and propose necessary action

Participants in these reviews shall include representatives from functions


concerned with design & development being reviewed. Results of design
review shall be recorded which shall address to practical difficulties likely
to be encountered, in completing the design and adequacy of full or a part
of design to meet design & development input requirements.
6.

Design & Development Verification (Clause 7.3.5 of ISO 9001: 2008)


Verification of design & development shall be carried out as planned to
ensure that design & development output meets the design &
development input requirements. Results of design verification shall be
recorded.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

Design and Development

Chapter No.: 7-B

(Clause 7.3 of ISO 9001 : 2008)

Page No.: 4 of 4
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

7.

Design & Development Validation (Clause 7.3.6 of ISO 9001: 2008)


Design & Development is required to be validated in accordance with
planned arrangements to provide confidence that final design conforms to
defined user needs and / or requirements at practical / site level.
Wherever practicable validation shall be completed before implementation
of the design / delivery of the product. For this, if required and practicable
a prototype / draft report shall be made and test checked in accordance
with agreed procedure and criteria. Client approval to design and
development shall be taken, as needed.
Records of design and development validation shall be maintained
bringing out the actions to be taken.

8.

Design & Development Changes (Clause 7.3.7 of ISO 9001: 2008)


The objective of design change control is to identify, document & manage
changes in the requirements, drawings, specifications etc. after initial
design has been authorized & released for implementation. The control
shall ensure that the need for change is identified and records of change
maintained. The change shall be reviewed, verified and validated, as
appropriate and approved before implementation. The review shall
include evaluation of the effect of change on other constituent aspects of
the designed entity.
Customer or his representative shall normally be involved when design
change is likely to affect functional performance.

III.

REFERENCES:
i)

SBU level relevant Design & Development control procedures.

QUALITY MANUAL

DOC :

RITES-QM-01

ISO 9001:2008

Issue No. 03

PURCHASING

Chapter No. 7-C

(Clause 7.4 of ISO 9001 : 2008)

Page No. 1 of 5
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date 15 Sept.,2009

I.

PURPOSE & SCOPE:


This chapter provides the policy to ensure that
materials / services
required for execution of services / projects of RITES, which are required
to be out sourced, are procured, conforming to specified requirements.
These shall include:

Hiring of experts / consultants / sub-consultants / advisors etc for


carrying out specific activities needed for execution of services and
projects.
Appointment of works contractors for project related works
Hiring of outside agencies for carrying out specific, specialized
assigned tasks / activities needed for execution of services and
projects.
Procurement of specific goods, materials, other items as per the
requirements of services / projects
Procurement of materials, equipment for office use.

II.

POLICY:

1.

Following shall be responsible for various purchase activities


a)

Hiring of experts, consultants, sub-consultants etc. - Concerned


SBU / unit Head through P&A.

b)

Hiring of Services for projects and maintenance etc. Concerned


project co-ordinator / activity head through SBU Heads with
approvals as per SOP

c)

Selection and Appointment of works contractors for projects Concerned project co-ordinator through SBU Heads with approvals
as per SOP

d)

Purchase of stores for execution of services / projects Concerned


project co-ordinator through SBU Heads with approvals as per SOP

QUALITY MANUAL

DOC :

RITES-QM-01

ISO 9001:2008

Issue No. 03

PURCHASING

Chapter No. 7-C

(Clause 7.4 of ISO 9001 : 2008)

Page No. 2 of 5
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date 15 Sept.,2009

e)

2.

Purchase of Office Machinery, equipment, furniture, stationary etc. Concerned unit Head with approvals as per SOP directly or through
nominated agency.

Purchasing Process (Clause 7.4.1 of ISO 9001 : 2008)


Purchasing activities shall be carried out to ensure that purchased product
/ service conforms to the specified requirements, following a defined
system. Purchasing is largely done through any of the following methods:
a)
b)
c)

Single Tender
Limited Tenders
Open Tenders

The mechanism of procurement shall be dependent on its value,


requirements of the customers and requirements of funding agencies
involved. Approval of competent authority as per SOP shall be obtained
for all purchases.
As a policy the system of single tender shall be resorted to only in
exceptional circumstances following the existing guidelines.
2.1

Tenders shall be evaluated by duly constituted Tender Committees. The


criteria of evaluations and selection shall consist of considerations such
as:
-

Competence, Capability of tenderer to meet tender requirements


including Technical & financial capacity of the tenderers
Past Experience on similar Works
Technical & Financial Bids
Fulfillment of criteria laid down in the tender document including
pre-qualification, if any.
Technical Collaborations, if any as may be required.
Ability to deliver the product / service in time

QUALITY MANUAL

DOC :

RITES-QM-01

ISO 9001:2008

Issue No. 03

PURCHASING

Chapter No. 7-C

(Clause 7.4 of ISO 9001 : 2008)

Page No. 3 of 5
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date 15 Sept.,2009

Availability of necessary documents/ certificates as per the tender


requirement
Recommendations of client, consultant, statutory / regulatory
authorities, if applicable
Accreditation / Certification available as may be required.

If required site visits by members of tender evaluation committee or any


other person / team designated for the purpose, may also be made.
2.2

For procurement of laboratory services in case of Quality Assurance


Division for third party inspections, a system of approval of labs exists
based on the competence of the labs. The services of approved labs are
obtained as per the need without any further tendering etc.

2.3

Hiring of consultants, experts, advisors etc to carry out project related


work shall be done based on their competence, qualification & experience
against the project requirement through P&A. This shall be normally done
based on recommendations of hiring SBU / database available with P& A.

2.4

Controls on suppliers / service providers as applicable shall be dependent


on the final deliverables and may include some or all of the following :
1.
2.
3.
4.
5.
6.
7.
8.
9.

Approval of process / methodology / samples / examination of


services carried out
Examination of past credentials, references
Incoming inspection / verification of materials / services
Clearance of work stages / hold points.
Inspection & supervision of works and ensuring conformity to
specifications during execution of project
Identification of defects / non-conformities & rectification there of.
Monitoring the progress of works & corrective and preventive
actions.
Verification of measurements & bills
Control on products / services procured by sub-contractors / works
contractors ( e.g. procurement from suppliers approved by client /
RITES)

QUALITY MANUAL

DOC :

RITES-QM-01

ISO 9001:2008

Issue No. 03

PURCHASING

Chapter No. 7-C

(Clause 7.4 of ISO 9001 : 2008)

Page No. 4 of 5
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date 15 Sept.,2009

2.5

The Suppliers / service providers shall be re-evaluated as per the need


based on established criteria ensuring their continued suitability at the
time of renewal /revalidation etc. Records of evaluations, re-evaluations
and any actions arising from them shall be maintained in the form of file
notings /case files, etc.

3.

Purchasing Information (Clause 7.4.2 of ISO 9001: 2008)


The purchase orders / other relevant documents for purchase of materials
and procurement of services such as LOI/ LOA shall describe the
materials / services to be procured including, where appropriate:
a) Specification of the material / description of services to be procured
including requirements for approval of products, procedures,
processes, equipment as required
b) Requirements for Qualification of personnel as may be applicable.
c) Work Schedule / Delivery Schedules, if any.
d) Quality Management System Requirements including quality
assurance scheme / plan, standard to be followed.
Purchase orders / applicable purchase documents shall be reviewed for
adequacy before issue at defined level.

4.

Verification of Purchased Product (Clause 7.4.3 of ISO 9001: 2008)


Verification / inspection / examination of outsourced services / products
shall be done, as required, as per established procedures / project quality
plans etc to ensure their conformity to tender/ contract requirements.
Where it is specified to perform verification at suppliers premises, the
intended verification arrangements and methods of product approval shall
be established and communicated to the suppliers, appropriately.

QUALITY MANUAL

DOC :

RITES-QM-01

ISO 9001:2008

Issue No. 03

PURCHASING

Chapter No. 7-C

(Clause 7.4 of ISO 9001 : 2008)

Page No. 5 of 5
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date 15 Sept.,2009

5.

Construction Projects:
Detailed Guidelines for tendering for Construction Projects have been laid
down in Guidelines on Construction Project Management.
The
Guidelines cover all necessary steps including preparation of estimates,
preparation of tender documents and its publicity, standard forms for
tendering, sale of tender documents, receipt, opening and acceptance of
tenders, requirement of earnest money, performance guarantee and
security deposit, essential features of agreements /contracts, payment to
contractors, preparation, examination and verification of bills for passing,
etc. The Guidelines also includes various mandatory tests, inspections
and test procedure, frequency of testing, etc. thereof to be carried out on
raw materials received for construction projects as well as at various
stages during construction.

III.

REFERENCES:
Schedule of Powers
SBU level procedures on purchasing
Guidelines on Construction Project Management February 2009
General conditions of contract for works 2008
Guidelines of calling and accepting quotations instead of tenders
(Annexure 6.1 of Guidelines on Construction Project Management).
Procedure for calling and acceptance of single tender (Annexure 6.2 of
Guidelines on Construction Project Management).
Tender and Contract Document August 2009.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008
Issue No.: 03
CONTROL OF PROJECT /
SERVICE EXECUTION

Chapter No.: 7-D

(Clause 7.5.1 of ISO 9001 : 2008)

Page No.: 1 of 4
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

I.

OBJECTIVE & SCOPE:


This Chapter provides RITES policy to ensure that all projects and
services of RITES in all areas of operation including consultancy,
engineering, project management, export, procurement etc. are planned,
defined and executed under controlled conditions. This chapter covers
i)
ii)
iii)

All projects carried out by RITES for various clients.


All services executed by RITES for execution of various contracts
with clients.
Corporate and support processes needed for proper fulfillment of i)
& ii) above.

II.

POLICY:

All SBU Heads shall be responsible for execution of the requirements of


this chapter through concerned project coordinators / activity heads for
execution of projects / services to clients. Unit Heads providing internal
services within RITES shall be responsible for fulfillment of these
requirements within their areas of control.

All SBU Heads / unit heads shall ensure that projects / services under
them are planned and carried out under controlled conditions.

2.1

Planning for execution of all projects shall be carried through Project


Quality Plans, clearly bringing out details required such as:
a)
b)

c)
d)

Various project stages / sub-stages.


Controlling documents (drawings, specifications, standards, codes,
special instructions, work instructions, guidelines, check sheets
etc.) as applicable.
Responsibilities for RITES and contractors personnel.
Review / verification activities including customer verification along
with Acceptance criteria

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008
Issue No.: 03
CONTROL OF PROJECT /
SERVICE EXECUTION

Chapter No.: 7-D

(Clause 7.5.1 of ISO 9001 : 2008)

Page No.: 2 of 4
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009


e)
f)
g)

Records to be maintained, reports to be submitted to customer /


project management.
Completion schedules with identification of deliverables.
Resources to be deployed (personnel, equipment, machinery etc.).

2.2

In cases where services of non-project nature are to be provided, it shall


be ensured that the services to be provided are planned and defined
through documented procedures / work instructions / check sheets etc.

2.3

It shall be ensured that all service in the area of operation of RITES


including consultancy, engineering and project management provided to
external clients as well as internal services are executed under controlled
conditions meeting the laid down requirements. The controls shall
include:
a)

Availability of information that describes the nature and


requirements of the service to be provided i.e. Service deliverables
and service requirements.

b)

Availability of relevant documentation such as procedures / work


instructions / guidelines, etc. as necessary defining the manner of
execution of various project stages, service processes, at pertinent
locations.

c)

Maintaining compliance to the


supervision, monitoring activity.

d)

Use of suitable plant & machinery and equipment, software,


hardware & other resources for execution of project / service at
each stage as needed including their suitable maintenance.

e)

Availability & use of suitable monitoring & measuring equipment as


needed.

f)

Implementation of monitoring and measurements, of identified


important process parameters & service characteristics, ensuring

above,

through

appropriate

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008
Issue No.: 03
CONTROL OF PROJECT /
SERVICE EXECUTION

Chapter No.: 7-D

(Clause 7.5.1 of ISO 9001 : 2008)

Page No.: 3 of 4
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009


fulfillment of acceptance criteria, maintenance of records and
completion of projects and service processes as per time
schedules.

2.4

g)

Identification and planned & controlled implementation of release,


handover, delivery of project / service deliverables.

h)

Identification and planned, controlled execution of post delivery


activities.

i)

Compliance to applicable statutory / regulatory requirements such


as those relating to safety, hazards, fire, material handling and
movement / transfer, disposal etc. as well as administrative
requirements brought out through SOP, Personnel Manual and
internal circulars brought out from time to time.

Corporate processes which contribute for effective execution of services to


external clients by the SBUs include the following which shall be carried
out effectively and efficiently ensuring fulfillment of objectives:

Finance and accounts processes including budgetary controls: - These


activities shall be carried out as per the documented Quality
Management Systems of Finance. Guidelines shall be issued from
time to time to various accounts offices to ensure statutory and
budgetary controls based on these.
Personnel & administration processes: - These shall be carried out
with due controls as per laid down Quality Management System of
Personnel and Administration Groups.
Corporate planning: - Ten yearly Corporate Plan is developed under
the control of ED(CS) to provide management vision and overall
business directions for the organization which is reviewed periodically.
Annual target fixation: - Annual targets shall be fixed for organization
based on MOU targets finalized with Ministry of Railways at the
beginning of each financial year. SBU wise targets are fixed at the time
of budget finalization based on next years budget estimates submitted
by SBU in line with F&A procedures on the subject.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008
Issue No.: 03
CONTROL OF PROJECT /
SERVICE EXECUTION

Chapter No.: 7-D

(Clause 7.5.1 of ISO 9001 : 2008)

Page No.: 4 of 4
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

III.

Financial / Administrative sanctions of various types: - These shall be


provided by competent authority at various levels based on SOP and
further guidelines issued from time to time.
Corporate level policy directions, performance reviews, coordination
and control: - This shall be done as per laid down procedure on
corporate level review of performance.
Corporate marketing and Client services: - These shall be carried out
with due controls as per documented Quality System of M&CS.
Corporate communication: - This shall be carried out based on
documented procedure with M&CS on the subject ensuring effective
communication of organizational vision, policies, achievements etc. to
external and internal publics of RITES.

REFERENCES:
SBU level procedures on Process Control, Project, Service Execution.
Operational Procedures related to Personnel Group.
Operational Procedures related to Finance & Accounts Group.
Operational Procedures related to Administration Group.
Operational Procedure related to Marketing & Client Services Group.
Procedure for Performance Review.
Schedule of Powers
Guidelines for Construction Project Management.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

VALIDATION OF
PROCESSES

Chapter No.: 7-E

(Clause 7.5.2 of ISO 9001 : 2008)

Page No.: 1 of 2
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date : 15 Sept.,2009

I.

OBJECTIVE & SCOPE:


This chapter provides the policy to ensure that all processes for service
provision which can not be verified by subsequent monitoring or
measurement are pre- validated. This applies to all projects / services of
RITES where such processes may exist.

II.

POLICY:

This policy shall be implemented by concerned SBU Heads through


Project Co-ordinators / activity heads under them.

2.

All such processes, required for execution of any project or service, which
can not be verified by subsequent monitoring or measurement and as a
consequence, deficiencies will become apparent only after resulting
product / structure / service / document comes in use, shall be identified.
All such processes shall be validated. Validation shall demonstrate the
ability of these processes to achieve desired result even without
subsequent verification activities, by maintaining defined process controls.
As applicable, following shall be ensured for these processes:
a) Review and approval / validation of the process based on defined
criteria for the same
b) Approval of equipment and qualification of personnel to carry out the
process
c) Controlled operation of the process under defined control and
establishment of specific methods / work instructions for execution of
the process
d) Records of maintenance of defined controls
e) Revalidation of the process at defined frequency

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

VALIDATION OF
PROCESSES

Chapter No.: 7-E

(Clause 7.5.2 of ISO 9001 : 2008)

Page No.: 2 of 2
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date : 15 Sept.,2009

3.

Examples of such processes include concreting, welding, heat treatment,


etc for which RITES may be responsible as a part of project execution /
supervision etc.

III.

REFERENCES:
SBU level procedures on Process Control, Project / Service Execution.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No. 03

IDENTIFICATION &
TRACEABILITY

Chapter No.: 7-F

(Clause 7.5.3 of ISO 9001:2008)

Page No.: 1 of 3
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

I.

OBJECTIVE & SCOPE:


This chapter provides the policy to maintain identification/ traceability and
status of products, works and activities, during execution of services and
projects, meeting customer requirements, statutory / codal requirements
and RITES own requirements. It is applicable to all projects and services
of RITES.

II.

POLICY:

This policy shall be implemented by all SBU Heads through Project Coordinators / activity heads under them.

2.

Where appropriate and required identification and traceability of the


products, materials, documents etc. handled during the execution of any
project / service shall be maintained. Status of products, materials,
documents etc. shall be also maintained with respect to monitoring and
measuring requirements through out service realization process through
suitable means.

2.1

The requirements for identification & traceability and status during service
/ project execution shall be identified based on contract review and service
/ project requirements.

2.2

These may arise due to:


a) Customer Requirements
b) Statutory Requirements / applicable standard or codal requirements
c) Requirements found necessary for overall management and control of
project / service.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No. 03

IDENTIFICATION &
TRACEABILITY

Chapter No.: 7-F

(Clause 7.5.3 of ISO 9001:2008)

Page No.: 2 of 3
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

2.3

The mechanism for maintaining identification and traceability shall be


planned and decided. As needed identification & traceability shall be
maintained through reference members, markings, tagging, colour coding,
code numbering etc. to:
a) Prevent mix-up during handling, processing and usage
b) Ensure that only materials / documents / works which meet specifications
are used / cleared
c) Enable recalling / other suitable corrections on the defective material /
documents / works activities
d) Enable tracing back of defective material / consignments / documents /
process activities to their source wherever required contractually.

2.4

Traceability shall enable tracing back the history of the material /


documents / works through its records, markings, tagging, code
numbering etc. Traceability requirements shall include the extent of
traceability to be maintained. It shall be ensured that wherever traceability
is a requirement, unique identification is provided to each batch / unit of
material / document / work executed, for which records shall be
maintained.

2.5

Identification & traceability relating to various documents shall ensure that


they are be kept identified / traceable / filed in well-identified folders / files,
so that they are well connected, retrievable for usage. Various projects
executed by RITES shall also be given a unique code for financial and
administrative convenience.

2.6

The inspection & test status of inspected / tested / verified materials


handled shall be maintained through means such as stickers, markings,
tagging, storage in identified areas or accompanying records etc.
preventing any possibilities of loss of this status and mix up.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No. 03

IDENTIFICATION &
TRACEABILITY

Chapter No.: 7-F

(Clause 7.5.3 of ISO 9001:2008)

Page No.: 3 of 3
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

2.7

The Inspection & Test /Review status of works / service executed as


conforming / non-conforming / requiring modifications, repairs etc.
throughout the service realization cycle shall be brought out through the
relevant records in general. Where any specific
mechanism for
maintenance of this status is required, the same shall be included in the
relevant Plans / documented procedure.

III.

REFERENCES:
i)
ii)

SBU level relevant procedures on Identification & traceability and


Status.
F&A Procedure on project coding.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

CUSTOMER PROPERTY

Chapter No.: 7-G

(Clause 7.5.4 of ISO 9001: 2008)

Page No.: 1 of 2
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

I.

OBJECTIVE & SCOPE:


This chapter provides the policy to ensure that customer property received
for execution of projects / service are controlled with respect to their
verification, storage, maintenance, etc. Customer property includes:
a)
b)
c)
d)
e)

Equipment, and machinery required to be installed, supplied by


customer.
Machinery, instrumentation, material handling equipment and
laboratory facilities etc. made available for execution of the project.
Infrastructural support facilities / services such as office
accommodation, logistics, transportation and other related services.
Documents and intellectual property such as drawings, layouts,
reports, survey data etc.
Representations, requests, Certificates, Bills, etc. received from
employees by Personnel, F&A and other internal services.

II.

POLICY:

1.

The policy shall be implemented by all SBU Heads through Concerned


Project Coordinator / activity heads in line with their procedures on the
subject.

2.

All customer property including intellectual property received for the


execution of any project / service shall be suitably identified, preserved,
protected and safeguarded to ensure their correct usage.
All customer property items required for execution of a service / project
shall be identified as a result of contract review and during planning stage.

2.1

It shall be ensured that all customer property items which are directly
responsible for / related to the quality of service are controlled with respect
to the following:

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

CUSTOMER PROPERTY

Chapter No.: 7-G

(Clause 7.5.4 of ISO 9001: 2008)

Page No.: 2 of 2
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

a)

All such items on receipt are verified to ensure their conformity to


the specifications, suitability / adequacy for the use and the
quantities involved.

b)

They are identified to maintain their status as customer property


items. Appropriate records of receipt are maintained.

c)

Any such item which does not meet the specifications, suitability /
adequacy / quantity requirements as needed are brought to the
notice of the customer and necessary records are maintained.
Mechanism for further disposal / use of any such item is decided.

d)

Proper storage, maintenance and usage of customer property items


is ensured so that any damage, deterioration, loss of the same is
avoided and the quality of the same is maintained. In case of any
non-conformity occurring to the same, corrective / preventive action
is identified and as required the same is informed to the customer.
Appropriate records are maintained.

e)

In case of items such as machinery, material handling equipment,


instrumentation and facilities such as workshop facilities supplied
by the customer for executing the project, proper maintenance and
suitability of the same is ensured before usage of the same.

f)

In case of infrastructural facilities provided by the customer, at the


time of their handing over by the customer their suitability and
adequacy is examined to ensure that they will serve the intended
purpose during the project duration.

2.2

Responsibilities shall be designated and mechanism developed for usage


of customer property in line with service / project requirements under
appropriate controls at SBU level.

III.

REFERENCES:
i)

SBU level relevant procedures on control of customer property.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

PRESERVATION OF
PRODUCT

Chapter No.: 7-H

(Clause 7.5.5 of ISO 9001 : 2008)

Page No.: 1 of 3
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009


I.

OBJECTIVE & SCOPE:


This chapter provides the policy to ensure appropriate preservation of
materials, products, documents during the execution of projects/ services.
It applies to products / materials / documents needed for execution of
projects & services which directly affect the quality of work and are under
the custody / supervision of RITES such as:
a)
b)
c)
d)

Construction material and other products directly used as project


requirements.
Other products like Plant, Machinery, Components etc. to be fitted /
installed / commissioned / supplied.
Work in progress at project.
Documents such as reports, training course material etc. needed
for execution of consultancy projects.

II.

POLICY:

1.

This policy shall be implemented by Concerned SBU Heads through


Project Coordinators / activity heads. These activities may involve
activities carried out by RITES directly or through appointed contractors,
as planned, for execution of project /service.

2.

At various stages of execution of a project or service all materials,


products, equipment, machinery, components, documents, reports etc
needed during the execution of any project / service shall be suitably
preserved to maintain their fitness & suitability and prevent any damage /
deterioration, through activities like identification, handling, storage,
packaging & protection etc. as applicable, thereby ensuring their
conformity to specified requirements.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

PRESERVATION OF
PRODUCT

Chapter No.: 7-H

(Clause 7.5.5 of ISO 9001 : 2008)

Page No.: 2 of 3
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

2.1

Identification:
All materials, products, equipment, machinery, components, documents
etc. needed to be handled / considered during the execution of any project
/ service shall be maintained well identified & accounted ensuring their
correct utilization.

2.2

Handling:
It shall ensured that adequate means & methods are used and provided
for safe and secured handling of products / materials etc. so that no
damage / deterioration to the same or to works takes place, safety in
operations is maintained. As needed, project specific guidelines, work
instruction or other documents shall be documented, suitable material
handling equipment shall be provided and competent personnel deployed
to use the same. Adequate supervision / monitoring shall be carried out
during execution of Projects, activities of RITES to ensure proper
handling.

2.3

Storage:
Appropriate maintenance of stores, whether the stores are maintained by
RITES or by appointed contractors, shall be ensured through supervision /
monitoring activities. Materials / products at various stages shall be
provided suitably safe, secured storage so that no damage / deterioration
to quality takes place, safe custody and accountals are maintained.
Verification of quantities, quality on receipt shall be ensured. Material
storage with appropriate storage conditions shall be ensured. Material
receipt, issue activities shall be controlled and records maintained, as
necessary.
Identification, traceability during storage as per the
requirements shall be maintained.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

PRESERVATION OF
PRODUCT

Chapter No.: 7-H

(Clause 7.5.5 of ISO 9001 : 2008)

Page No.: 3 of 3
Approved By

Managing Director
Page Rev. No. : Nil

th

Effective Date:15 Sept.,2009

2.4

Packaging:
Any requirements for Packaging, Markings etc. required e.g. in case of
export of materials etc shall be identified and implemented to fully meet
contractual / internally identified requirements. Supervision / monitoring
activity shall ensure effective fulfillment of requirements.

2.5

Protection:
Protection of materials, products shall be carried out on need basis to
maintain them against deterioration. The need for protection and the
extent shall be identified during project planning stage and work
instruction / guidelines shall be developed as per the specific requirements
for compliance by RITES personnel / contractors. Monitoring, supervision
activities shall ensure compliance to laid down requirements. It shall be
ensured that work in progress at various stages is protected / maintained
with adequate care during in-process stages so that quality is maintained.

2.6

Preservation of Documents, Reports etc.:


Various documents needed for execution of projects like training
materials, reports etc. shall be handled, stored, protected, packaged with
due care ensuring that they are kept safe, secured, identifiable and are
prevented from being lost, damaged or spoiled during above activities.

III.

REFERENCES:
SBU level relevant procedures on Preservation and related aspects.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

CONTROL OF
MONITORING &
MEASURING EQUIPMENT

Chapter No.: 7-I

(Clause 7.6 of ISO 9001 : 2008)

Page No.: 1 of 3
Approved By

Managing Director
Page Rev. No. : Nil

Effective Date:15th Sept.,2009

I.

OBJECTIVE & SCOPE:


This Chapter brings out the policy related to control, calibration &
maintenance of all monitoring and measuring equipment used during the
execution of project / service for monitoring and measurement of identified
product / process characteristics. This includes all such equipment
whether owned by RITES, on hire or belonging to contractors used for the
purpose of the execution of project / service and affecting the quality of
project / service deliverables.

II.

POLICY:

1.

All SBU Heads shall be responsible to implement this policy through


concerned Project Co-ordinators / Activity Heads in line with their own
procedures on the subject. Monitoring and measurements to be
undertaken as a part of the project / service, shall be determined along
with the equipment required for the same.

2.

The measurements / monitoring to be undertaken, during the execution of


any project / service, shall be determined and suitable Monitoring &
Measuring Equipment shall be made available for providing evidence of
conformity to the identified product / process requirements.

2.1

Depending on the project / service requirements the monitoring and


measuring devices used may be:
a)
b)
c)
d)

owned by RITES.
owned by suppliers / service providers such as instruments in site
laboratory maintained by contractor.
made available by the client.
hired.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

CONTROL OF
MONITORING &
MEASURING EQUIPMENT

Chapter No.: 7-I

(Clause 7.6 of ISO 9001 : 2008)

Page No.: 2 of 3
Approved By

Managing Director
Page Rev. No. : Nil

Effective Date:15th Sept.,2009

2.2

Controls shall be exercised on all monitoring and measuring equipment


used to ensure the following:
a)

Monitoring and measuring equipment / Instruments used shall be


capable of making measurements consistent with the required
measurement capabilities. They shall be selected and used based
on their accuracy and precision vis-a-vis required measurement
capabilities.

b)

In case where calibration responsibility rests with RITES (e.g. for


instruments owned by RITES) the process of calibration shall be
established with defined acceptance criteria, calibration
frequencies, calibration method. In all such cases monitoring and
measuring equipment shall be calibrated or verified or both at
specified intervals or prior to use.

c)

Monitoring and measuring equipment used shall be identifiable to


their calibration / verification records. Before use it shall be ensured
that Monitoring and measuring equipment to be used are within
their valid calibration period. All calibrations shall be traceable to
national / international standards, where no such standards exist,
the basis used for calibration shall be recorded.

d)

Calibration status of the Monitoring and measuring equipment shall


be maintained / available through suitable indicator or shall be
verifiable through record of calibration and identification.
Calibration status shall be ensured before usage.

e)

Calibration records shall be maintained / kept available / and


verified by project personnel as needed.

QUALITY MANUAL

DOC: RITES-QM-01

ISO 9001:2008

Issue No.: 03

CONTROL OF
MONITORING &
MEASURING EQUIPMENT

Chapter No.: 7-I

(Clause 7.6 of ISO 9001 : 2008)

Page No.: 3 of 3
Approved By

Managing Director
Page Rev. No. : Nil

Effective Date:15th Sept.,2009

f)

Environmental condition required for calibration, inspections


measurements shall be maintained at the time of their calibration or
usage.

g)

Handling, preservation & storage of instruments shall be done in


such a way that their accuracy & fitness for use are maintained.

h)

Security of setting / adjustments & safeguard against wrong,


unauthorized use shall be ensured, verified before usage.

i)

Where instruments are found out of calibration, assessment of


validity of previous measurements done with them shall be done.

j)

When used in the monitoring and measurement of specified


requirements, the ability of computer software to satisfy the
intended application shall be confirmed. This shall be undertaken
prior to first usage and re-confirmed as necessary.

2.3

Wherever services of outside labs are taken for tests / evaluations, such
labs shall be evaluated ensuring control and calibration of instruments &
validity of measurements.

III.

REFERENCES:
SBU level relevant procedures on Control of monitoring and measuring
devices / inspection, measuring & test equipment.