Академический Документы
Профессиональный Документы
Культура Документы
S DTIC
ELCTE
MAY2 7 1992
C
TILT-UP CONSTRUCTION
BY
RICHARD E. CROMPTON
A
"DiSMhUT1ON STATUM- -
rMstribution UnPrnated9
UNIVERSITY OF FLORIDA
SPRING 1992
TABLE OF CONTENTS
LIST OF FIGURES.......................
.
..
..... .. .. . ...
CHAPTER ONE - INTRODUCTION TO TILT-UP CONSTRUCTION..... .. ... 1
Definition of Tilt-up Construction.......
. .. .. .. ...
1
Advantages of Tilt-up Construction.......
. .. .. .. ...
1
History of Tilt-up Construction..............3
Typical Uses for Tilt-up Buildings.............3
CHAPTER TWO - PLANNING THE TILT-UP BUILDING ...........
5
When to Use Tilt-up Construction..............5
Will There be Enough Casting Space?............6
Other Considerations for Tilt-up..............10
CHAPTER THREE - THE FLOOR SLAB AND CASTING SURFACE.......12
The Concrete Floor Slab....................12
Cure Coats and Bondbreakers................12
CHAPTER FOUR - CONSTRUCTING THE TILT-UP PANELS.........16
Edge Forms.........................16
Reinforcement.....................
18
Sandwich Panels.....................18
Lifting Systems and Inserts................20
CHAPTER FIVE - ARCHITECTURAL TREATMENTS............25
Types of Architectural Treatments.............25
Exposed Aggregate Finishes.................25
Form Liners........................27
Rustication and Paint......................29
Stucco and Insert Decorative Rocks............30
CHAPTER SIX - RIGGING, LIFTING, AND PLACING TILT-UP ....... 33
Preplanning.........................33
Rigging for the Lift...................33
Making the Lift........................39
Plumbing Panels.....................41
Temporary Bracing.....................43
CHAPTER SEVEN - CONNECTIONS FOR TILT-UP CONSTRUCTION
. .
. .
48
Design Considerations....................48
Types of Connections....................49
Foundation Connections..................50
Panel to Panel Connections.................52
Roof and Floor Connections.................54
CONCLUSION...............................62
REFERENCES.............................63
BIBLIOGRAPHY.........................64
ii
LIST OF FIGURES
Figure
Figure
Figure
Figure
Figure
1:
2:
3:
4:
5:
Figure 6:
Figure 7:
Figure
Figure
Figure
Figure
Figure
Figure
Figure
8:
9:
10:
11:
12:
13:
14:
Figur . 15:
Figure 16:
Figure 17:
Figure 18:
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
19:
20:
21:
22:
23:
24:
25:
26:
27:
28:
29:
30:
.......
Panels Placed in Rows ..........
Footprint
Small
with
Casting Slab for Building
.......
Typical Panel Layout ...........
a
Panel
Edge
of
the
Form
How
to
of
Example
An
Sandwich Panels Have a Core of Insulation
.............. .
Surrounded by Concrete .....
Ground Release Hardware Before Attaching to
Panel ........
......................
7
8
9
17
22
. ...
19
22
AvO1&
,:D
1D
3 t.
For
l.
pec lal
oedes
CHAPTER ONE
INTRODUCTION TO TILT-UP CONSTRUCTION
1.1
construction
concrete construction.
is
special
form
of
precast
1.2
construction,
transportation
tilt-up
of
eliminates
building
the
components
need
for
from
the
factors
of
constructing
a tilt-up
building
skillful
erection sequence
panel
casting
layout
plans,
the
By
panel
are
an
Since
can be
left
not
In fact,
it
Tilt-up
since
1.3
as
for
the
railroad
crane
or
the
expense
of
construction
became
more
popular
construction
1.4
mid-rise building.
warehouses.
By
tilt-up.
By
applying
the
myriad
architectural
A few
mid-rise apartments,
condominiums,
hotels.
townhouses,
and
CHAPTER TWO
a building
is
influenced
by
several
factors.
typically
building's
will
not
construction
be
as
method
concerned
as
he
will
The
most
A building's
with
be
his
new
with
the
reinforced
concrete
structure.
The
designer
must
intention of having
method.
If
2.2
dependant considerations that must be weighed. A crowded jobsite in an area like New York City would not readily lend
itself to using tilt-up construction.
dimensions
small
in
footprint,
and
cannot
location
a crowded
a building
these
with
economically
be
One
figure
in
construction.
1.
The
safely
drawback of
bracing
the
this
system
panels
is
during
the
the
concrete casting slabs on the job site, and then use these
slabs for constructing the building's wall panels.
L -A
10
Door
4.,Opening
To
minimize
the
number
of
additional
casting
slabs
Til-up Panels
Building Slab
unnecessary
delays
and
to
provide
maximum
safety.
3 shows a typical
layout
A few items
lifted from the outside of the building, but usually the crane
will lift panels from the inside of the building to take
advantage of the firm operating surface of the floor slab.
Corner panels are usually stack cast on top of each other to
keep
them
close
as
possible
to
their
final
position.
F-1
1-1
2.3
are
many
items
that
must
on
either
the
floor
considered
addition to
be
site
when
location
slab
or
the
casting
bed,
forming process
is
poured.
almost always
The
project begins.
In addition
to
it
in a
until
the
panel
is
properly
braced.
Obviously,
proper
welded or cast into the buildings footer, and both the type of
connection and the timing of connecting the panels to the
footer must be considered.
The final items that need to be considered on a tilt-up
building are the connections between adjacent panels and the
design
of
the
buildings
particularly
important
building
structural
its
roof.
because
they
integrity.
These
both
two
items
give
a tilt-up
are
In particular, these
11
CHAPTER THREE
THE FLOOR SLAB AND CASTING SURFACE
3.1
and since the slab will become the form for the exterior face
of the walls, any faults or imperfections will be identically
reflected on the wall panels.
provide
non-sagging
support
for
the
"The subgrade
concrete
slab.
Because the floor slab must bear the weight of the heavy
panels and the mobile crane, it is important that it be well
supported at all points by a thoroughly compacted subgrade"
(4:15).
from five to
six
inches thick.
In addition to
strength
3.2
(3:16).
curing process
Properly curing the floor slab will prevent cracks and other
imperfections that may occur on the casting surface due to
Equally important as the use of
curing
compound
for
the
slab
is
the
use
of
The common
The American
bondbreaker
to
insure
"compatibility
between
these
limit
13
in moisture.
Once the
panel's reinforcing
steel
and
lifting
in,
Avoid
If it
over
application.
Do
not
spray
is
the
following
are
several
factors
that
need
to
be
14
panels
are
lifted, a curing
compound and
Once the
concrete
ask
has
been
poured,
it
assistance.
15
is
too
late
to
for
CHAPTER FOUR
CONSTRUCTING THE TILT-UP PANELS
4.1
Edge Forms
to fasten the forms to the floor slab to hold the forms firmly
in place.
Since a wooden
opening
that will be
16
cast
Doors, windows, or
into the
panel
are
is
Re
w d
OWood
Support
Block
Concrete Panel
U/dg
om
3/4-inch Chamfer
17
4.2
Reinforcement
Once
the
panels
are
formed
and
and
squared
the
Extra reinforcement is
Care must
4.3
Sandwich Panels
"Sandwich panels can be defined as panels which have an
(3:59).
fully
use
the
of
mass
the
concrete
in
x"
xx
x x
xxx
eS
x x)xe--. TSteel
x
X X
te
PLAN
Steel TieT
2"
Mnyffffffa/m
/"Concrete
SECTION
Figure 5:
19
tempering
The
panels.
If
in
doubt,
the
designer
should
use
is
In
therefore
should
only
be
done
20
by
qualified
(lifting
engineer.
A vast
most sophisticated
lifting
system
is the
ground
The advantage
ground
available
is
system
release
lifting
it
is
the
most
expensive
systems.
Ground Release
Un. Attaches
here
Figure
7:
Relearse
Ground
attached to panel
22
Hardware
of
all
The
The twist-lift
for
connecting
and
disconnecting
No tools are
the
twist-lift
twisted into the next panel, and since the crane lines are
still attached to the lifting hardware, the next panel is
ready to be lifted.
The
least
sophisticated
lifting
system
is
simple
line
attaches
to
the
swiveling
shackle,
and
The
each
using
wrench.
The
basic
shackle
system
is
23
24
CHAPTER FIVE
ARCHITECTURAL TREATMENTS
5.1
architectural treatments
are
Today, however,
only limited
by
the
(3:3).
The earliest
couple
of
decades,
and
tilt-up
5.2
seeding
aggregate
the desired
25
into the
exposed
top
of
0
Concrete
Large Aggregate
Rebar
__
Faceup Method
Concrete
Rebar
Large Aggregate
Facedown Method
desirable).
(in
this
instance,
an
edge
lift
system
may
be
in the
face down method is the aggregate finish is not seen until the
panels are already lifted, and if their are any areas that
were
no
constructed
properly,
these
areas
will
not
be
Form Liners
can provide very unique sculptured surfaces on the final tiltup panels.
liner.
27
3/4"
(19ram)
I1-lie '3mm)
On Center
6"(152mm) increment
liners are
in today's tilt-up
very common
industry.
so they can be
simply
Additionally,
since plastic and rubber form liners are machine made, they
assure a uniform reproduction of the desired visual effect
over an entire building.
5.4
finishes.
Often, paint is
to achieve
pleasing
29
Rustication
Painted Areas
Rustication
Painted Area
Figure 10:
Rustication Used
to Highlight
Painted
Areas
5.5
Also,
the
Stucco finishes
decorative
rocks
are
similar
to
face
down
the flat stones are visible on the exposed side of the panel.
5.6
Trompe l'oeil
Trompe l'oeil, or fool the eye, is a technique that lends
itself well
to
tilt-up
construction.
"By
combining the
appear to
have depth"
(1:10).
It
is much more
cost
31
An
Example
of
32
a Panel
using
Troupe
CHAPTER SIX
RIGGING, LIFTING, AND PLACING TILT-UP
6.1
PreDlannin
As with any construction project, preplanning is critical
A well-
casting
layout
should
be
drawn
prior
to
detaching the
lift
lines, moving
the
crane,
and
The
6.2
crane
supervisor,
and
rigging
supervisor
should
make
and
the number
lifting inserts.
The
any
simple
seemingly
changes.
An
important
lifting configuration.
If sling
lengths are too short, they can cause excessive side pull on
the lifting inserts which may result in failed inserts or
cracked panels.
As an example, "the
to
top
of
the
panel
(a '2 hi'
configuration]
is
minimum
sling
lengths
are
three
times
the
34
Figure 12:
Across and 2 Rows High
Rows'
Rows
To Crane
With
in
It may be economical
rigging
configuration
before
changing
to
another
to
change
the
rigging
configuration,
the
simpler
between "3 hi" rigging to "2 hi" rigging, and figure 15 shows
how to change between "4 hi" rigging to "2 hi" rigging. Also,
it is important to attach all slings to an individual panel at
two or more points, and the slings should be run through
pulleys to balance the lifting stresses.
36
Spreader mr
ottem
Wa
g
Name_
3 HI RIGGINGA
ttm
pn
-1
el
Top o panel
HI TO 2 HI RIGGING CHANGE
Atmte
UdLIom
to
litPint-
tt*Caed to
otm9m
TodlaPin
37
Wk=
Thi" switch
2 BY 4 HI TO 2 BY 2 HI CHANGE
38
6.3
should
be
lifted with
the
These
solid
operations.
platform
for
operating
during
lifting
casting the panels may provide adequate operating room for the
crane.
the
panels
are
lifted
from outside of
39
labor to
attach the
40
6.4
the
Plumbing Panels
two
techniques
for
straightening
panels
There
during
the
erection process.
A second crane can be used to pull the panel into a
vertical position by using lines attached to edge lift points
in the top of the panel.
lift points.
The
vertical position.
42
Upright
6.5
Temporary Bracing
Once a tilt-up panel is set into position, it is not yet
a completed wall.
Also, wind
is
Local conditions
As shown
19
figure
on
the
following page,
a tilt-up
brace
is
right after the panel is set into its final position, and this
technique
allows all
temporary bracing
in
connections
to be
inches.
For taller
Knee bracing by
Figure 20
44
HEAVY
DUTY
PIPE
STANDARD PIPE
45
~
mm
~
gu.Cthm~IK
IiI~20: mno*
Bracing
rS~h
and
Latera I racing#
46
na
could
personal injury.
over
cause
and
significant
damage
and
joint
construction joint to
or
prevent
located
at
the middle
point
of
the main
brace,
and the
47
CHAPTER SEVEN
Design Considerations
is
the
connections
for
the
foundation,
the
are
determined
based
on
"strength,
ductility,
best
reducing
number
of
the
components
simplest
for
Usually,
ones.
"By
connection,
For example, if
No. 4 bar
Anytime the
reduce
congestion
in
the
connections.
steel and
During
threaded
7.2
TvDes of Connections
Tilt-up
panels
must
not
only
serve
as
a building's
carry
imposed
loads,
the
panels
must
be
relieve
cracking.
seismic
stresses,
and
to
minimize
cosmetic
Cast-in-
attention
an anchored embedded
49
steel plate
or angle
cast
are they eliminate the requirement for field welding, and the
drilled-in inserts can be used to conveniently correct any
slight errors in alignments.
connections
[connections]"
"are
the
(3:12).
cheapest
but
least
reliable
7.3
Foundation Connections
There are many variations for tilt-up panel foundations
and connections.
Welded Connection
Final
Grade
Continuous Strip
Footing
51
Slab In fill
Floor Slab
Tilt-up Panel
Steel
Figure 22:
7.4
Concrete Foolng
The
These welded
intensive labor
they
were
in
earlier
tilt-up
buildings.
The
one
Cast in Place
Column
Non-rigid Connection
connection
IRigid
v 1/
Panel
Panel
Felt Strip
Rebar
53
mbedde
WELD
PLALTE WELDED TO
EMBEDDED ANGLES
7.5
tilt-up
panels
and
the
upper
floors
(in
multi-story
Two
common
roof
connections
are
shown
is
Both of these
In
system
can
be
installed.
One
important
similarity
f~~
Rebar Ties
Angle Seat w/Joist
Connected by Field
Weld or Bolts
Welded to
Angle Seat
55
Chord Angle
Welded to Joist
Embedded Plate
w/Stud Anchors
Steel Angle Seat.
Joist Connected
by
or Field
Bolts Weld
For
buildings
that
will
use
wood
roof
or
floor
In figure 27, a
The
shown.
It is
Strap Tie
Nailed Throug
PI 0Deck&W
57
Plywood
Figue
Woo
28 Den Suport
58
eei
Suppor Shoe
For
buildings
designed
to
sustain
substantial
floor
29
on
the
following
page
is
required.
In
this
Figure 30 on
For
figure 30, the embedded rebar used to tie in the top of the
precast beam can get in the way during the placement of the
beam, so extra care
this system.
59
.Chord
I'D. /
*"I1'*
Angle
Steel Decking
I!
Wall Panel
ReinforcingI
II
'I
Steel Be
I|
Slot Bolt in Beam
to Allow Temporary
Movement
It
Rebar Ties
Welded to
Angle Seatn
Angle Seat
Closed Ties
Around Bolts
-I
60
Shear Plane
Line of Failure
Reinforced Concrete
Figure30*
Duble
ee onConTotepLe
Neopren
ge
CHAPTER EIGHT
CONCLUSION
"With Adequate planning and proper procedures, tilt-up
can
be
an
efficient,
safe
method
of
erecting
structural
The key to
tilt-up's economy
is
to effectively
speed up the
job.
Tilt-up
construction's
62
REFERENCES
1.
2.
3.
4.
5.
63
BIBLIOGRAPHY
Construction,
ACI
Cement
Tilt-up
Association, Tilt-up
for Tilt-up
Concrete
Load
Wall
Buildings,
Bearing
Walls,
64