Вы находитесь на странице: 1из 2

Federal Register / Vol. 72, No.

216 / Thursday, November 8, 2007 / Notices 63173

Any person desiring to intervene or to DEPARTMENT OF ENERGY to serve a copy of that document on
protest in any of the above proceedings each person whose name appears on the
must file in accordance with Rules 211 Federal Energy Regulatory official service list for the project.
and 214 of the Commission’s Rules of Commission Further, if an intervenor files comments
Practice and Procedure (18 CFR 385.211 [P–349–134; P–2407–121] or documents with the Commission
and 385.214) on or before 5 p.m. Eastern relating to the merits of an issue that
time on the specified comment date. It Alabama Power Company; Notice of may affect the responsibilities of a
is not necessary to separately intervene Application for Temporary Amendment particular resource agency, they must
again in a subdocket related to a of License and Soliciting Comments, also serve a copy of the document on
Motions To Intervene, and Protests that resource agency. A copy of any
compliance filing if you have previously
motion to intervene must also be served
intervened in the same docket. Protests November 1, 2007. upon each representative of the
will be considered by the Commission Take notice that the following Applicant specified in the particular
in determining the appropriate action to hydroelectric application has been filed application.
be taken, but will not serve to make with the Commission and is available k. Description of Request: Alabama
protestants parties to the proceeding. for public inspection: Power is requesting a drought-based
Anyone filing a motion to intervene or a. Type of Application: Request for temporary variance to the Martin Project
protest must serve a copy of that drought-based temporary variance of the rule curve. The rule curve variance
document on the Applicant. In reference Martin Project rule curve and minimum would be from November 20, 2007 to
to filings initiating a new proceeding, flow releases at the Yates and Thurlow May 1, 2008, and would include: (1) A
interventions or protests submitted on Project. winter pool elevation 3 feet higher than
or before the comment deadline need b. Project Nos.: 349–134 and 2407– normal, at elevation 483 feet instead of
not be served on persons other than the 121. elevation 480 feet; (2) maintaining the
Applicant. c. Date Filed: October 23, 2007. winter pool elevation earlier than
d. Applicant: Alabama Power normal, on November 20th rather than
The Commission encourages Company. January 1st; (3) initiating the filling
electronic submission of protests and e. Name of Projects: Martin process earlier than normal, beginning
interventions in lieu of paper, using the Hydroelectric Project (P–349) and Yates January 15th instead of February 15th;
FERC Online links at http:// and Thurlow Hydroelectric Project (P– and (4) reaching and maintaining
www.ferc.gov. To facilitate electronic 2407). summer pool elevation earlier than
service, persons with Internet access f. Location: The Martin Dam Project is normal, on April 1st rather than May
who will eFile a document and/or be located on the Tallapoosa River in the 1st. In association with the Martin rule
listed as a contact for an intervenor counties of Coosa, Elmore and curve variance, the minimum flows
must create and validate an Tallapoosa, Alabama. The Yates and from the Thurlow reservoir (P–2407)
eRegistration account using the Thurlow Project is located on the would be temporarily modified as
eRegistration link. Select the eFiling Tallapoosa River in the counties of follows until May 1, 2008: (1) Discharge
link to log on and submit the Tallapoosa and Elmore Counties, would be no less than 350 cubic feet per
intervention or protests. Alabama. second (cfs) until the Martin Reservoir
g. Filed Pursuant to: Federal Power elevation reaches the existing rule
Persons unable to file electronically Act, 16 U.S.C. 791a–825r. curve; (2) when the reservoir elevation
should submit an original and 14 copies h. Applicant Contact: Mr. Jim Crew, is at or above the existing rule curve but
of the intervention or protest to the Alabama Power Company, P.O. Box below the temporary rule curve,
Federal Energy Regulatory Commission, 2641, Birmingham, Alabama 35291, Tel: Alabama Power would discharge the
888 First St. NE., Washington, DC (205) 257–4265. greater of 350 cfs or inflow at the
20426. i. FERC Contact: Ms. Andrea Claros, upstream Heflin gage; and (3) when
The filings in the above proceedings (202) 502–8171; e-mail: Martin Reservoir elevation is at or above
are accessible in the Commission’s andrea.claros@ferc.gov. the temporary rule curve, Alabama
eLibrary system by clicking on the j. Deadline for filing comments, Power would discharge no less than
appropriate link in the above list. They motions to intervene and protests: 1200 cfs from Thurlow.
are also available for review in the November 14, 2007. l. Location of the Application: The
Commission’s Public Reference Room in Please include the project numbers filing is available for inspection and
(P–349–134 and P–2407–121) on any reproduction at the Commission’s
Washington, DC. There is an
comments or motions filed. All Public Reference Room, located at 888
eSubscription link on the Web site that
documents (original and eight copies) First Street, NE., Room 2A, Washington,
enables subscribers to receive e-mail should be filed with: Kimberly D. Bose, DC 20426 or by calling (202) 502–8371.
notification when a document is added Secretary, Federal Energy Regulatory This filing may also be viewed on the
to a subscribed docket(s). For assistance Commission, 888 First Street, NE., Commission’s Web site at http://ferc.gov
with any FERC Online service, please e- Washington, DC 20426. using the ‘‘eLibrary’’ link. Enter the
mail FERCOnlineSupport@ferc.gov. or Comments, protests, and docket number excluding the last three
call (866) 208–3676 (toll free). For TTY, interventions may be filed electronically digits in the docket number field to
call (202) 502–8659. via the Internet in lieu of paper, see 18 access the document. You may also
Nathaniel J. Davis, Sr.,
CFR 385.2001(a)(1)(iii) and the register online at http://www.ferc.gov/
instructions on the Commission’s Web docsfiling/esubscription.asp to be
Acting Deputy Secretary. site under the ‘‘e-filing’’ link. The notified via e-mail of new filings and
rwilkins on PROD1PC63 with NOTICES

[FR Doc. E7–21900 Filed 11–7–07; 8:45 am] Commission strongly encourages issuances related to this or other
BILLING CODE 6717–01–P electronic filings. pending projects. For assistance, call 1–
The Commission’s Rules of Practice 866–208–3676 or e-mail
and Procedure require all intervenors ferconlinesupport@ferc.gov; for TTY,
filing documents with the Commission call (202) 502–8659. A copy is also

VerDate Aug<31>2005 16:54 Nov 07, 2007 Jkt 214001 PO 00000 Frm 00013 Fmt 4703 Sfmt 4703 E:\FR\FM\08NON1.SGM 08NON1
63174 Federal Register / Vol. 72, No. 216 / Thursday, November 8, 2007 / Notices

available for inspection and with the Commission and is available calling (202) 502–8371. This filing may
reproduction at the address in item (h) for public inspection: also be viewed on the Commission’s
above. a. Type of Application: Preliminary Web site at http://www.ferc.gov using
m. Individuals desiring to be included Permit. the ‘‘eLibrary’’ link. Enter the docket
on the Commission’s mailing list should b. Project No.: 12932–000. number excluding the last three digits in
so indicate by writing to the Secretary c. Date filed: August 6, 2007. the docket number field to access the
of the Commission. d. Applicant: FFP Project 47, LLC. document. For assistance, call toll-free
n. Comments, Protests, or Motions to e. Name of Project: Williams Point 1–866–208–3676 or e-mail
Intervene: Anyone may submit Project. FERCOnlineSupport@ferc.gov. For TTY,
comments, a protest, or a motion to f. Location: The project would be call (202) 502–8659. A copy is also
intervene in accordance with the located on the Mississippi River in New available for inspection and
requirements of Rules of Practice and Madrid County, Missouri and Lake reproduction at the address in item h
Procedure, 18 CFR 385.210, 385.211, County, Tennessee. The project uses no above.
and 385.214. In determining the dam or impoundment. m. Individuals desiring to be included
appropriate action to take, the g. Filed Pursuant to: Federal Power on the Commission’s mailing list should
Commission will consider all protests or Act, 16 U.S.C. 791(a)—825(r). so indicate by writing to the Secretary
other comments filed, but only those h. Applicant Contact: Mr. Dan Irvin, of the Commission.
who file a motion to intervene in FFP Project 47, LLC, 69 Bridge Street, n. Competing Preliminary Permit—
accordance with the Commission’s Manchester, MA 01944, phone (978) Anyone desiring to file a competing
Rules may become a party to the 232–3536. application for preliminary permit for a
i. FERC Contact: Robert Bell, (202) proposed project must submit the
proceeding. Any comments, protests, or
502–6062. competing application itself, or a notice
motions to intervene must be received
j. Deadline for filing comments, of intent to file such an application, to
on or before the specified comment date
protests, and motions to intervene: 60 the Commission on or before the
for the particular application.
days from the issuance date of this specified comment date for the
o. Any filing must bear in all capital
notice. particular application (see 18 CFR 4.36).
letters the title ‘‘COMMENTS’’, All documents (original and eight
‘‘PROTEST’’, or ‘‘MOTION TO Submission of a timely notice of intent
copies) should be filed with: Kimberly allows an interested person to file the
INTERVENE’’, as applicable, and the D. Bose, Secretary, Federal Energy
Project Number of the particular competing preliminary permit
Regulatory Commission, 888 First application no later than 30 days after
application to which the filing refers. Street, NE., Washington, DC 20426.
p. Agency Comments: Federal, State, the specified comment date for the
Comments, protests, and interventions particular application. A competing
and local agencies are invited to file
may be filed electronically via the preliminary permit application must
comments on the described application.
Internet in lieu of paper; see 18 CFR conform with 18 CFR 4.30 and 4.36.
A copy of the application may be
385.2001(a)(1)(iii) and the instructions o. Competing Development
obtained by agencies directly from the
on the Commission’s Web site under the Application—Any qualified
Applicant. If an agency does not file
‘‘e-Filing’’ link. The Commission development applicant desiring to file a
comments within the time specified for
strongly encourages electronic filings. competing development application
filing comments, it will be presumed to
Please include the project number (P– must submit to the Commission, on or
have no comments. One copy of an
12932–000) on any comments or before a specified comment date for the
agency’s comments must also be sent to
motions filed. particular application, either a
the Applicant’s representatives. The Commission’s Rules of Practice competing development application or a
q. Comments, protests and and Procedure require all intervenors notice of intent to file such an
interventions may be filed electronically filing documents with the Commission application. Submission of a timely
via the Internet in lieu of paper. See, 18 to serve a copy of that document on notice of intent to file a development
CFR 385.2001(a)(1)(iii) and the each person in the official service list application allows an interested person
instructions on the Commission’s Web for the project. Further, if an intervenor to file the competing application no
site at http://www.ferc.gov under the ‘‘e- files comments or documents with the later than 120 days after the specified
Filing’’ link. Commission relating to the merits of an comment date for the particular
Kimberly D. Bose, issue that may affect the responsibilities application. A competing license
Secretary. of a particular resource agency, they application must conform with 18 CFR
[FR Doc. E7–21916 Filed 11–7–07; 8:45 am] must also serve a copy of the document 4.30 and 4.36.
BILLING CODE 6717–01–P
on that resource agency. p. Notice of Intent—A notice of intent
k. Description of Project: The must specify the exact name, business
proposed project consists of: (1) 3,550 address, and telephone number of the
DEPARTMENT OF ENERGY proposed 20 kilowatt Free Flow prospective applicant, and must include
generating units having a total installed an unequivocal statement of intent to
Federal Energy Regulatory capacity of 71 megawatts, (2) a proposed submit, if such an application may be
Commission transmission line, and (3) appurtenant filed, either a preliminary permit
facilities. The FFP Project 47, LLC, application or a development
[Project No. 12932–000]
project would have an average annual application (specify which type of
FFP Project 47, LLC; Notice of generation of 310.98 gigawatt-hours and application). A notice of intent must be
Application Accepted for Filing and be sold to a local utility. served on the applicant(s) named in this
l. Locations of Applications: A copy of public notice.
rwilkins on PROD1PC63 with NOTICES

Soliciting Motions To Intervene,


Protests, and Comments the application is available for q. Proposed Scope of Studies under
inspection and reproduction at the Permit—A preliminary permit, if issued,
October 30, 2007. Commission in the Public Reference does not authorize construction. The
Take notice that the following Room, located at 888 First Street, NE., term of the proposed preliminary permit
hydroelectric application has been filed Room 2A, Washington DC 20426, or by would be 36 months. The work

VerDate Aug<31>2005 16:54 Nov 07, 2007 Jkt 214001 PO 00000 Frm 00014 Fmt 4703 Sfmt 4703 E:\FR\FM\08NON1.SGM 08NON1

Вам также может понравиться