20-Aug-15

Contents
1.

Overview
a)

2.

Decription of site

b)

Zoning Plan

c)

Pile Schedule

d)

Site Logistics

e)

Sequence of Work

Sequence of Piling Work


a)

Material and equipment

b)

Surveyor setting out

c)

Piling Barge Anchorage

d)

Pile Driving

e)

Pile jointing

f)

Pile cut off

g)

Pda Test

h)

Documentation

20-Aug-15

Overview
Description of site
Scope of Work:

4
5

1.
2.
3.
4.
5.
6.
7.

6
1

Walkway to Water Villa


3 Nos One Bed Water Villa
1 Nos Five Bed VIP Villa
Walkway to Restaurant
Kayuputi Restaurant
Pile Stacked
Walkway to Westin

Overview
Zoning Plan

Land Piling

Sea Piling

 Due to the access route on site, pile installation method have been separated into two which :
a)

Sea Piling (High Tide)

b)

Land Piling ( Low Tide)

 Working Plan also been arranged based on the two condition :


a)

Working Hour Average 6 hours per day depend on the tide

b)

Working zone Water depth >1m using sea piling and water depth <1m land piling being introduced.

20-Aug-15

Overview
Pile Description Schedule

Location

Pile Size

No of Pile

Penetration Length

Pile type

1) Walkway to Water Villa

300 mm

78

21 m

PFA Spun Pile Class C

2)3 Nos One Bed Water Villa

300 mm

93

18 m

PFA Spun Pile Class C

3) 1 Nos Five Bed VIP Villa

300 mm

55

18 m

PFA Spun Pile Class C

4) Walkway to Restaurant

300 mm

74

19.5 m

PFA Spun Pile Class C

5) Kayuputi Restaurant

300 mm

66

20 m

PFA Spun Pile Class C

6) Walkway to Westin

300 mm

10

10 m

PFA Spun Pile Class C

Total Number of Pile

376

Overview

Equipment & Resources


A.

List of Plant and Machinery used :


1.

Piling Barge
Land Piling
Rig

2 sets of 12m W x 36 m L x 1m D piling barge come with :

1 unit piling rig with 5 tons hydraulic hammer

1 unit of 20 50 tons crawler crane

1 unit of 10-25 KVA genset

3 units of 300SE welding set

1 unit 300 500 hp tug boat

1 unit 20 ft x 40 ft anchor boat

1 unit 40hp speed boat

6 sets of 5 tons winch & 2-5 tons anchor

1 unit of pile head diamond cutter

1 unit of mini concrete mixer

2 units of container & cabin

2.

1 unit of fiber boat

3.

1 unit of piling rig with 5 tons hydraulic hammer (Land

4.

1 unit of 35 tons mobile crane (Land Piling)

5.

1 unit of Crawler Crane (Land Piling)

Piling)

Mobile and crawler crane

20-Aug-15

Overview
Site Logistics

B
A

C
 A : After delivered to site, all piles been properly stacked at this area.
 B : Then, the required pile being lifted to the small barge using mobile crane
 C : Small barge transported all the piles to the piling barge and stacked properly.
 Note: All this lifting procedure can only be done during high tide for small barge to access at the
sea shore.

Overview
Sequence of Piling Work

1) Delivery of material
& equipment

6) Pile Jointing and


Splicing

7) Pile Cut off

2) Surveyor setting
out

5) Pile Driving

8) PDA Test

3) Piling Barge
Anchorage

4) Pile Positioning

9) Documentation

20-Aug-15

Sequence of Piling Work

1) Delivery of Material

The Precast spun pile shall be purchased externally and


for this project all piles supplied by Industrial Concrete

1.
2.
3.
4.
5.
6.

Company Innitial
Malaysian Standard
Pile size and Class
Date of Cast
Serial no & Factory
code
Pile Length & Type

Products Sdn Bhd (ICP).

When arrived at site, all piles been closely inspected for :


1.

Type of Pile : PFA Spun Pile

2.

Lengths of Pile : 12m

3.

Date manufactured

4.

Quality : MS 1314:Part 4:2004

5.

Straightness

6.

Support conditions during transportation

Once Accepted all piles been neatly and properly


stacked under designed support conditions and serially
code-numbered prior to its use.

Pile Stacked

Sequence of Piling Work


2) Surveyor Setting Out
 Surveyor shall locate all lines, level, coordinates and set out position of each pile as per
approved drawing
 Triangulation Method for three base stations and reduced level is used to guide the piling
barge to its required position
 The piles will be checked for verticality by using spirit level at two points perpendicular to
each other.

Survey Point 1

Pile Position
Survey Point 2

Triangulation method

20-Aug-15

Sequence of Piling Work


3) Pile Barge Anchorage

3
1

 Barge was equipped with four stockless 5 ton anchor and three winches
 Tug boat will drive the barge in desired location for piling and then
number1,2,3,4 anchor been dropped into the sea using barge crawler crane.
 Then using anchor winches, the crewmembers will set anchor number 1 & 2.
 Anchor number 3 & 4 will be adjusted to the required position under surveyor
instruction and then winches brakes are set.

2
4

Sequence of Piling Work


4) Pile Positioning

1.

Pile Lifting

Piles were lifted from its stacked position utilizing


its two designated lifting points and canvass
padded sling been used for spun pile.

2.

The toe end of the starter piles being planted to


its exact position manually by suspending the pile
form its driven end.

3.

When the toe position is fixed the required pile


inclination of pile then being adjusted to the
required angle while the guide rails and required
back support are firmly secured.

4.

Counter check being made through two survey


station at right angle to each other to confirm the

Surveyor point

position at the pile base and inclination of pile


shaft.

20-Aug-15

Sequence of Piling Work


4) Pile Driving
1.

Pile Driving shall utilize the most suitable hammer for the purpose of driving type to set without damage to the

2.

When driving commence the first few blows and meter of penetration been closely monitored to enable any

3.

Surveyor will keep monitoring the inclination and position if need forcible correction before inadequate to

pile head and for this project the static hammer being used.

initial deviation to be physically corrected.

change.

Surveyor monitoring
Pile Positioning

Hammer Blow

Sequence of Piling Work


4.Pile Driving
Land Pile Driving

1. Land piling being introduced for the area that cannot access by Piling barge as per zoning plan before.
2. This method only applicable during low water tide to accommodate the piling rig to the required position
3. The piling rig being supported by steel plate to avoid any uneven settlement during piling process which
can cause disposition of the required location and also provide access route for the Piling rig.
4. Method for Land pile driving being used is hydraulic hammer and using the same PFA Spun pile.

Land Pile Installation


Steel Plate for Support

20-Aug-15

Sequence of Piling Work


6. Pile Jointing and Splicing

1. Pile being driven continuously and jointed with extension pile to get set.
2. Pile jointing and splicing for extension being done using Shielded metal arc welding (SMAW) to weld all
splicing joints in accordance with manufacturer specifications as per Table 4.1 below.

SMAW welding
Table 4.1

Sequence of Piling Work


7. Pile Cut Off

1. When a pile has been driven to the required set of depth and after load test has been carried out, the he
ad of the pile shall be cut off to the level specified in the drawings. The length of the reinforcing bars
projecting above this level as specified in the Drawings (Fig 5.1).
2. A diamond blade cutter with an air compressor being used to cut the line of the required marking level.
3. Remnants of the cut section would be removed by crane onto the barge for subsequent disposal off the
site.

Figure 5.1

20-Aug-15

Sequence of Piling Work


8. PDA Test

Figure 6.1

Figure 6.2

Figure 6.3

Figure 6.4

1. Pile Driving Analyzer(PDA) test is cond


ucted to check the pile capacity, pile in
tegrity, driving stress and energy
transfer.For this project pile test been
conducted on the pile L10. Figure 6.1
2. Prior to testing two strain transducers
and two strain accelerometer were att
ached on the surface of the test pile
on both sides by using wall plugs.
Figure 6.2
3. After all hardware were checked and
fully functioned, the test pile's parame
ters were keyed in to the pile driving
analyzer. Figure 6.3
4. Few hammer blow were taken by using
appropriate drop height and the drop
hammer continuing until one good
signal was obtained.
5. All the signal taken were recorded in
pile driving analysis for further analysis
. Figure 6.4

Documentation
9. Document preparation
1. All documents being properly recorded and keep for future reference.
2. List of documents as below:
a) Surveyor Setting out form. Figure 1.1
b) Hiley formula calculation. Figure 1.2
c) Piling Record. Figure 1.3
d) As built drawing. Figure 1.4
e) Catalog and Sirim Certificate for spun pile. Figure 1.5

Figure 1.1

Figure 1.2

20-Aug-15

Documentation
9. Document preparation

Figure 1.4

Figure 1.3

Documentation
9. Document preparation

Figure 1.5

10