Atlantic Yards
Date
4/21/2014
Location
B2
Weekday
Monday
Client
ESD
Report #
Contract #
6717
Weather
Project
299
Bright, Sunny, Cool Start
Project #
STV Representative:
2114659
Bill King
Temp. L/H
42/66
Wind Speed 11 mph gusting to 18 mph
Work hours
8:45-5:00
Precip
0"
117
930
93
0.126
1.3
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; possible quality issue with installed EPDM roof; possibility of mold in water-damaged
wallboard & floor boards.
Previous Information received: 4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Spray-on Fire-proofing (SOFP) to resume at ground floor and Dean St. transfer beam area this week or next according to draft 2-week lookahead. Must watch out that work areas contain dust from affecting other workers/the public. Looks l ke it won't start until next week at the
earliest.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. 3/4/15
TCO date projected, a 2-month slip.
1 of 2
Manpower on Site
15-20
Navillus
Civetta
4-6
Stearns
J SuporTrucking
MEP trades
Other
8-10
William King
4/21/2014
2 of 2
Date
Atlantic Yards
Date
4/22/2014
Location
B2
Weekday
Tuesday
Client
ESD
Report #
Contract #
6717
Weather
Project
300
Sunny a.m., late p.m. Rain
Project #
STV Representative:
2114659
Bill King
Temp. L/H
51/71
Wind Speed 14 mph gusting to 27 mph
Work hours
9:30-6:15
Precip
.01"
117
930
94
0.126
1.2
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; possible quality issue with installed EPDM roof; possibility of mold in water-damaged
wallboard & floor boards.
Previous Information received: 4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Spray-on Fire-proofing (SOFP) to resume at ground floor and Dean St. transfer beam area this week or next according to draft 2-week lookahead. Must watch out that work areas contain dust from affecting other workers/the public. Looks l ke it won't start until next week at the
earliest.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. 3/4/15
TCO date projected, a 2-month slip.
1 of 2
Manpower on Site
10-15
Navillus
Civetta
Stearns
J SuporTrucking
MEP trades
Other
8-10
William King
4/22/2014
2 of 2
Date
Atlantic Yards
Date
4/23/2014
Wednesday
Location
B2
Weekday
Client
ESD
Report #
Contract #
6717
Weather
301
Sunny, Blustery
Project #
STV Representative:
2114659
Bill King
Temp. L/H
45/62
Wind Speed 23 mph gusting to 45 mph late at night
Work hours
8:45-5:45
Precip
0"
117
930
95
0.126
1.2
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; possible quality issue with installed EPDM roof; possibility of mold in water-damaged
wallboard & floor boards.
Previous Information received: 4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Spray-on Fire-proofing (SOFP) to resume at ground floor and Dean St. transfer beam area this week or next according to draft 2-week lookahead. Must watch out that work areas contain dust from affecting other workers/the public. Looks l ke it won't start until next week at the
earliest.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. 3/4/15
TCO date projected, a 2-month slip.
1 of 2
Manpower on Site
10-15
Navillus
Civetta
Stearns
J SuporTrucking
MEP trades
Other
8-10
William King
4/23/2014
2 of 2
Date
Atlantic Yards
Date
4/24/2014
Thursday
Location
B2
Weekday
Client
ESD
Report #
Contract #
6717
Weather
302
Sunny, Blustery
Project #
STV Representative:
2114659
Bill King
Temp. L/H
42/61
Wind Speed 22 mph gusting to 44 mph late at night
Work hours
8:30-5:00
Precip
0"
117
930
96
0.126
1.2
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; possible quality issue with installed EPDM roof; possibility of mold in water-damaged
wallboard & floor boards.
Previous Information received: 4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Spray-on Fire-proofing (SOFP) to resume at ground floor and Dean St. transfer beam area this week or next according to draft 2-week lookahead. Must watch out that work areas contain dust from affecting other workers/the public. Looks l ke it won't start until next week at the
earliest.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. 3/4/15
TCO date projected, a 2-month slip.
1 of 2
Manpower on Site
10-15
Navillus
Civetta
Stearns
J SuporTrucking
MEP trades
Other
8-10
William King
4/24/2014
2 of 2
Date
Atlantic Yards
Date
4/25/2014
Location
B2
Weekday
Friday
Client
ESD
Report #
303
Contract #
6717
Weather
Sunny, Crisp
Project
Project #
STV Representative:
2114659
Bill King
Temp. L/H
44/61
Wind Speed 15 mph gusting to 24 mph
Work hours
9:00-5:00
Precip
97
0.126
1.2
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; possible quality issue with installed EPDM roof; possibility of mold in water-damaged
wallboard & floor boards.
Previous Information received: 4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Spray-on Fire-proofing (SOFP) to resume at ground floor and Dean St. transfer beam area this week or next according to draft 2-week lookahead. Must watch out that work areas contain dust from affecting other workers/the public. Looks l ke it won't start until next week at the
earliest.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. 3/4/15
TCO date projected, a 2-month slip.
1 of 2
Manpower on Site
10-15
Navillus
Civetta
Stearns
J SuporTrucking
MEP trades
Other
8-10
William King
4/25/2014
2 of 2