STV Construction, Inc.

DAILY CONSTRUCTION REPORT

Atlantic Yards

Date

4/21/2014

Location

B2

Weekday

Monday

Client

ESD

Report #

Contract #

6717

Weather

Project

299
Bright, Sunny, Cool Start

Project #
STV Representative:

2114659
Bill King

Temp. L/H
42/66
Wind Speed 11 mph gusting to 18 mph

Work hours

8:45-5:00

Precip

0"
117
930

93
0.126

1.3

Summary of Construction Activities


Module Fabrication - Ongoing at Navy Yard, presumably, still working on 6th floor mods with 142-man workforce. Draft 2-week lookahead by FCR stated that 6th floor installation won't start until May which calls into question progress on mfr of 6th floor mods and their state
of completeness. Were supposed to start installation 4/16/14 per latest (3/14/14) schedule. Only a half dozen completed mods were
observed sitting outside Bldg 293 at the Navy Yard on 4/16. New York Times article on 4/19/14 stated completion date pushed back to late
2015.
Tower Crane - Inactive for 5th day in a row
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 93 work
days = 1.3 mods per day so far. No more mods expected until May 2014.
MEP - Pipework and electrical conduit continued in basement levels, primarily upper level.
Foundation-related - Complete. Backfill done.
Other Additional New Observations:
New Information received:
New Information requested:
Information previously requested: 4/16/14 - Via email requested from Skanska's John Dolan and Bill Carson explanation for delay to
6th floor mods - no response.
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). Still no response. (Note: on 4/4, Skanska still discussing
internally.)
1/20/14 . No response. Will have to bring this up with them again. Skanska indicated on 3/5 that
no date has been set for the return of the SOFP contractor - temp must be at least 40 degrees and stay 40 degrees at night.

Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; possible quality issue with installed EPDM roof; possibility of mold in water-damaged
wallboard & floor boards.
Previous Information received: 4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Spray-on Fire-proofing (SOFP) to resume at ground floor and Dean St. transfer beam area this week or next according to draft 2-week lookahead. Must watch out that work areas contain dust from affecting other workers/the public. Looks l ke it won't start until next week at the
earliest.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. 3/4/15
TCO date projected, a 2-month slip.
1 of 2

STV Construction, Inc.


Previous observations: Front faade is 33-35' from the ped walkway. Flatbush faade is 12' from the edge of the sidewalk shed. Height
exceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
4/18/14: 8 holes cut in ceilings near faade walls of 3 Flatbush-facing apts on 5th floor. Similar holes cut in 3rd floor ceilings. Most of
fallen/torn down ceiling on 3rd floor removed. One more storage room to go on 2nd floor.
Special instruction(s) given:
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

Manpower on Site

15-20

Navillus
Civetta

4-6

Stearns

J SuporTrucking

Manpower figure is rough approximation by STV.

MEP trades
Other

Major Equipment on site (I = Inactive)


Potain Tower Crane (I)

8-10

Equip. Arr./ Departure-Observed

Materials Delivered other than Mods (Observed)

William King

4/21/2014

Prepared by Bill King

2 of 2

Date

STV Construction, Inc.


DAILY CONSTRUCTION REPORT

Atlantic Yards

Date

4/22/2014

Location

B2

Weekday

Tuesday

Client

ESD

Report #

Contract #

6717

Weather

Project

300
Sunny a.m., late p.m. Rain

Project #
STV Representative:

2114659
Bill King

Temp. L/H
51/71
Wind Speed 14 mph gusting to 27 mph

Work hours

9:30-6:15

Precip

.01"
117
930

94
0.126

1.2

Summary of Construction Activities


Module Fabrication - Ongoing at Navy Yard, presumably, still working on 6th floor mods with 142-man workforce. Draft 2-week lookahead by FCR stated that 6th floor installation won't start until May which calls into question progress on mfr of 6th floor mods and their state
of completeness. Were supposed to start installation 4/16/14 per latest (3/14/14) schedule. Only a half dozen completed mods were
observed sitting outside Bldg 293 at the Navy Yard on 4/16. New York Times article on 4/19/14 stated completion date pushed back to late
2015.
Tower Crane - Inactive for 6th day in a row
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 94 work
days = 1.2 mods per day so far. No more mods expected until May 2014.
MEP - Pipework and electrical conduit continued in basement levels, primarily upper level.
Foundation-related - Complete. Backfill done.
Other Additional New Observations:
New Information received:
New Information requested:
Information previously requested: 4/16/14 - Via email requested from Skanska's John Dolan and Bill Carson explanation for delay to
6th floor mods - no response.
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). Still no response. (Note: on 4/4, Skanska still discussing
internally.)
1/20/14 . Will have to bring this up with them again. Skanska indicated on 3/5 that
no date has been set for the return of the SOFP contractor - temp must be at least 40 degrees and stay 40 degrees at night.

Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; possible quality issue with installed EPDM roof; possibility of mold in water-damaged
wallboard & floor boards.
Previous Information received: 4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Spray-on Fire-proofing (SOFP) to resume at ground floor and Dean St. transfer beam area this week or next according to draft 2-week lookahead. Must watch out that work areas contain dust from affecting other workers/the public. Looks l ke it won't start until next week at the
earliest.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. 3/4/15
TCO date projected, a 2-month slip.
1 of 2

STV Construction, Inc.


Previous observations: Front faade is 33-35' from the ped walkway. Flatbush faade is 12' from the edge of the sidewalk shed. Height
exceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
4/18/14: 8 holes cut in ceilings near faade walls of 3 Flatbush-facing apts on 5th floor. Similar holes cut in 3rd floor ceilings. Most of
fallen/torn down ceiling on 3rd floor removed. One more storage room to go on 2nd floor.
Special instruction(s) given:
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

Manpower on Site

10-15

Navillus
Civetta

Stearns

J SuporTrucking

Manpower figure is rough approximation by STV.

MEP trades
Other

Major Equipment on site (I = Inactive)


Potain Tower Crane (I)

8-10

Equip. Arr./ Departure-Observed

Materials Delivered other than Mods (Observed)

William King

4/22/2014

Prepared by Bill King

2 of 2

Date

STV Construction, Inc.


DAILY CONSTRUCTION REPORT
Project

Atlantic Yards

Date

4/23/2014
Wednesday

Location

B2

Weekday

Client

ESD

Report #

Contract #

6717

Weather

301
Sunny, Blustery

Project #
STV Representative:

2114659
Bill King

Temp. L/H
45/62
Wind Speed 23 mph gusting to 45 mph late at night

Work hours

8:45-5:45

Precip

0"
117
930

95
0.126

1.2

Summary of Construction Activities


Module Fabrication - Ongoing at Navy Yard, presumably, still working on 6th floor mods with 142-man workforce. Draft 2-week lookahead by FCR stated that 6th floor installation won't start until May which calls into question progress on mfr of 6th floor mods and their state
of completeness. Were supposed to start installation 4/16/14 per latest (3/14/14) schedule. Only a half dozen completed mods were
observed sitting outside Bldg 293 at the Navy Yard on 4/16. New York Times article on 4/19/14 stated completion date pushed back to late
2015.
Tower Crane - Inactive for 7th day in a row
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 95 work
days = 1.2 mods per day so far. Advance draft 2-week look-ahead says mods won't restart until June. Skanska says June 2.
MEP - Pipework and electrical conduit continued in basement levels, primarily upper level.
Foundation-related - Complete. Backfill done.
Other - Con Ed on site - 2 trucks - installing permanent power.
Additional New Observations:
New Information received:
New Information requested:
Information previously requested: 4/16/14 - Via email requested from Skanska's John Dolan and Bill Carson explanation for delay to
6th floor mods - no response.
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). Still no response. (Note: on 4/4, Skanska still discussing
internally.)
1/20/14 y. No response. Will have to bring this up with them again. Skanska indicated on 3/5 that
no date has been set for the return of the SOFP contractor - temp must be at least 40 degrees and stay 40 degrees at night.

Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; possible quality issue with installed EPDM roof; possibility of mold in water-damaged
wallboard & floor boards.
Previous Information received: 4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Spray-on Fire-proofing (SOFP) to resume at ground floor and Dean St. transfer beam area this week or next according to draft 2-week lookahead. Must watch out that work areas contain dust from affecting other workers/the public. Looks l ke it won't start until next week at the
earliest.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. 3/4/15
TCO date projected, a 2-month slip.
1 of 2

STV Construction, Inc.


Previous observations: Front faade is 33-35' from the ped walkway. Flatbush faade is 12' from the edge of the sidewalk shed. Height
exceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
4/18/14: 8 holes cut in ceilings near faade walls of 3 Flatbush-facing apts on 5th floor. Similar holes cut in 3rd floor ceilings. Most of
fallen/torn down ceiling on 3rd floor removed. One more storage room to go on 2nd floor.
Special instruction(s) given:
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

Manpower on Site

10-15

Navillus
Civetta

Stearns

J SuporTrucking

Manpower figure is rough approximation by STV.

MEP trades
Other

Major Equipment on site (I = Inactive)


Potain Tower Crane (I)

8-10

Equip. Arr./ Departure-Observed

Materials Delivered other than Mods (Observed)

William King

4/23/2014

Prepared by Bill King

2 of 2

Date

STV Construction, Inc.


DAILY CONSTRUCTION REPORT
Project

Atlantic Yards

Date

4/24/2014
Thursday

Location

B2

Weekday

Client

ESD

Report #

Contract #

6717

Weather

302
Sunny, Blustery

Project #
STV Representative:

2114659
Bill King

Temp. L/H
42/61
Wind Speed 22 mph gusting to 44 mph late at night

Work hours

8:30-5:00

Precip

0"
117
930

96
0.126

1.2

Summary of Construction Activities


Module Fabrication - Ongoing at Navy Yard, presumably, still working on 6th floor mods with 142-man workforce. Draft 2-week lookahead by FCR stated that 6th floor installation won't start until May which calls into question progress on mfr of 6th floor mods and their state
of completeness. Were supposed to start installation 4/16/14 per latest (3/14/14) schedule. Only a half dozen completed mods were
observed sitting outside Bldg 293 at the Navy Yard on 4/16. New York Times article on 4/19/14 stated completion date pushed back to late
2015. Around a dozen completed mods appear to be sitting outside Bldg. 293 at the Navy Yard.
Tower Crane - Inactive for 8th day in a row
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 96 work
days = 1.2 mods per day so far.
MEP - Pipework and electrical conduit continued in basement levels, primarily upper level.
Foundation-related - Complete. Backfill done.
Other - Con Ed on site for 2nd day in a row - 2 trucks - installing permanent power.
Additional New Observations: Spray-on fire-proofing restarted in back area of Dean St. transfer beam area, adequately screened.
New Information received:
New Information requested:
Information previously requested: 4/16/14 - Via email requested from Skanska's John Dolan and Bill Carson explanation for delay to
6th floor mods - no response.
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). Still no response. (Note: on 4/4, Skanska still discussing
internally.)
1/20/14 . Will have to bring this up with them again. Skanska indicated on 3/5 that
no date has been set for the return of the SOFP contractor - temp must be at least 40 degrees and stay 40 degrees at night.

Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; possible quality issue with installed EPDM roof; possibility of mold in water-damaged
wallboard & floor boards.
Previous Information received: 4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Spray-on Fire-proofing (SOFP) to resume at ground floor and Dean St. transfer beam area this week or next according to draft 2-week lookahead. Must watch out that work areas contain dust from affecting other workers/the public. Looks l ke it won't start until next week at the
earliest.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. 3/4/15
TCO date projected, a 2-month slip.
1 of 2

STV Construction, Inc.


Previous observations: Front faade is 33-35' from the ped walkway. Flatbush faade is 12' from the edge of the sidewalk shed. Height
exceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
4/18/14: 8 holes cut in ceilings near faade walls of 3 Flatbush-facing apts on 5th floor. Similar holes cut in 3rd floor ceilings. Most of
fallen/torn down ceiling on 3rd floor removed. One more storage room to go on 2nd floor.
Special instruction(s) given:
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

Manpower on Site

10-15

Navillus
Civetta

Stearns

J SuporTrucking

Manpower figure is rough approximation by STV.

MEP trades
Other

Major Equipment on site (I = Inactive)


Potain Tower Crane (I)

8-10

Equip. Arr./ Departure-Observed

Materials Delivered other than Mods (Observed)

William King

4/24/2014

Prepared by Bill King

2 of 2

Date

STV Construction, Inc.


DAILY CONSTRUCTION REPORT

Atlantic Yards

Date

4/25/2014

Location

B2

Weekday

Friday

Client

ESD

Report #

303

Contract #

6717

Weather

Sunny, Crisp

Project

Project #
STV Representative:

2114659
Bill King

Temp. L/H
44/61
Wind Speed 15 mph gusting to 24 mph

Work hours

9:00-5:00

Precip

1" late, after hours


117
930

97
0.126

1.2

Summary of Construction Activities


Module Fabrication - Ongoing at Navy Yard, presumably, still working on 6th floor mods with 142-man workforce. Draft 2-week lookahead by FCR stated that 6th floor installation won't start until May which calls into question progress on mfr of 6th floor mods and their state
of completeness. Were supposed to start installation 4/16/14 per latest (3/14/14) schedule. A dozen or so completed mods were observed
sitting outside Bldg 293 at the Navy Yard on 4/24.
Tower Crane - Inactive for 9th day in a row
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 97 work
days = 1.2 mods per day so far.
MEP - Pipework and electrical conduit continued in basement levels, primarily upper level.
Foundation-related - Complete. Backfill done.
Other - Con Ed on site for 3rd day in a row - 2 trucks - installing permanent power.
Additional New Observations: Spray-on fire-proofing still being applied in back area of Dean St. transfer beam area, adequately
screened.
No impact to construction day due to 1st game of Nets playoffs.

New Information received:


New Information requested: Requested info from FCR on punchlist-type items observed at building.
Information previously requested: 4/16/14 - Via email requested from Skanska's John Dolan and Bill Carson explanation for delay to
6th floor mods - no response.
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). Still no response. (Note: on 4/4, Skanska still discussing
internally.)
1/20/14 . Will have to bring this up with them again. Skanska indicated on 3/5 that
no date has been set for the return of the SOFP contractor - temp must be at least 40 degrees and stay 40 degrees at night.

Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; possible quality issue with installed EPDM roof; possibility of mold in water-damaged
wallboard & floor boards.
Previous Information received: 4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Spray-on Fire-proofing (SOFP) to resume at ground floor and Dean St. transfer beam area this week or next according to draft 2-week lookahead. Must watch out that work areas contain dust from affecting other workers/the public. Looks l ke it won't start until next week at the
earliest.
Are to 'uninstall' a few of the 5th floor mods in order to correct gasket allignment issues (haven't yet). No leaks noticed in western part of 5th
floor where mods are to be uninstalled.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt will be sufficient for production to keep ahead of
erection so there will be no downtime during mod erection at the B2 site.
The most recent project schedule is as of 3/14/14 and was transmitted to STV by FCR on 4/2/14; the one before that was 11/25/13. 3/4/15
TCO date projected, a 2-month slip.
1 of 2

STV Construction, Inc.


Previous observations: Front faade is 33-35' from the ped walkway. Flatbush faade is 12' from the edge of the sidewalk shed. Height
exceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
4/18/14: 8 holes cut in ceilings near faade walls of 3 Flatbush-facing apts on 5th floor. Similar holes cut in 3rd floor ceilings. Most of
fallen/torn down ceiling on 3rd floor removed. One more storage room to go on 2nd floor.
Special instruction(s) given:
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

Manpower on Site

10-15

Navillus
Civetta

Stearns

J SuporTrucking

Manpower figure is rough approximation by STV.

MEP trades
Other

Major Equipment on site (I = Inactive)


Potain Tower Crane (I)

8-10

Equip. Arr./ Departure-Observed

Materials Delivered other than Mods (Observed)

William King

4/25/2014

Prepared by Bill King

2 of 2