Академический Документы
Профессиональный Документы
Культура Документы
DE-FC36-02GO12112
The views and conclusions contained in this document are those of the authors
and should not be interpreted as necessarily representing the official policies or
endorsements, either expressed or implied, of the Department of Energy or the
U. S. Government.
Final Report for the Period November 1, 2002 – March 31, 2007
Program Manager:
Dr. Michael Strasik
206-544-5389
Principal Investigator:
2002 – 2006 Art Day, Phil Johnson
2006 – 2007 Dr. John Hull
206-544-5803
Team Members:
1
Final report Cooperative Agreement No. DE-FC36-02GO12112
1. SUMMARY
The chief objectives for the Risk Management System Flywheel were to
(1) demonstrate its ability to protect a critical load such as a small data center
from swings in power availability, cost, and power factor and (2) show that the
RMS flywheel can perform these functions with reduced noise, emissions,
and operating costs when compared with non-HTS competitors including
batteries, diesel generators, and microturbines.
2
Final report Cooperative Agreement No. DE-FC36-02GO12112
This project was initially partially funded at a very small level and the main
focus was on the first three tasks of the proposed project. The Boeing
Company changed cost policy determination of the original proposal resulting
in doubling of the proposed labor rates on the project. As a result of that
financial reclassification from the original proposal, it was mutually agreed by
Boeing and DOE to put the project on hold until a successful renegotiation
would take place with the new rates. Therefore, the project was put on hold in
March 2003, less than a year after start of the contract, and this hold
continued until it was restarted in August 2006. Only very minimal work was
completed from August 2006 until the completion of the contract on March 31
2007, as only about $60K of funding was remaining when the project was
restarted in 2006. The project was never fully renegotiated between Boeing
and DOE, and therefore the original objective of the proposal was never
achieved, and only limited amount of accomplishments on the first three tasks
was completed. This report will summarize those accomplishments.
3
Final report Cooperative Agreement No. DE-FC36-02GO12112
The original Phase III effort was proposed while the Boeing team was in
the initial stages of Phase II development, prior to testing of the large 10-kWh
flywheel system. That design included an innovative but unproven composite
spoke system, chosen to give the flywheel a high energy density.
Unfortunately, it encountered a dynamic response during full integration
testing that resulted in damage to the flywheel system. As a result of this test
experience, the Boeing team used more conservative design approach when
designing the 5-kWh / 100-kW UPS for utility testing. A key element of this
conservative approach was proven by a successful full-speed spin test of the
redesigned metal hub and a composite rotor.
The power market has changed dramatically in the last several years and
will continue to evolve -- with both users and providers looking for smarter
strategies and technologies. Risk management will be much more
individualized, and a significant number of power users will need localized
solutions under their own control. With the advent of rolling blackouts on both
the West and East Coasts of the United States, reliability of power has
become even more critical. Meanwhile, peak prices are rising dramatically.
Inevitably, the greatest costs will be borne by those drawing during peak
hours, and unlike existing uninterruptible power supply (UPS) systems,
flywheels have the potential to store significant amounts of energy at a
reasonable cost.
4
Final report Cooperative Agreement No. DE-FC36-02GO12112
It was the aim of this program to develop the first flywheel electricity
systems that give power users and utilities a full-scale device to manage both
their cost and reliability risks. This development relies fundamentally on
advances in the capabilities of high-temperature superconducting (HTS)
materials. Principal reasons include the need for a system that can be cycled
tens of thousands of times, is easy to control and therefore reliable, has no
wear parts in critical mechanisms, and is far more efficient than flywheels with
non-HTS suspensions. Figure 1 shows the design for Boeing’s 5-kWh
flywheel system being developed under the Phase-2 cooperative agreement
between the Boeing team and DOE, which was the point of departure for this
new program.
5
Final report Cooperative Agreement No. DE-FC36-02GO12112
They are very interested in avoiding the costs and delays associated with
siting new transmission lines to accommodate the growing loads in urban
areas.
¢ ¥ ¡$ ¢ ¥ ¡¢
POWER INVERTER
AND CONDITIONER
FLYWHEEL MOTOR
CONTROLLER
FLYWHEEL
STORAGE UNIT
CUSTOMER
UTILITY
VAULT
Previous and ongoing flywheel work at Boeing and elsewhere has focused
on the potential use of flywheels to act as uninterruptible power systems
(UPS). This potential is growing, with the recent introductions of small
flywheels for immediate backup until on-site diesel generators come online.
The Boeing product concept includes this function, but also addresses the
emerging susceptibility of electricity to prolonged outages and exceedingly
high peak-demand price. Members of our User Advisory Group (SCE,
Clearwood Electric, Alaska Energy Authority, GE Power Systems, and Boeing
Facilities) have expressed a strong interest in flywheels to protect them from
the economic risk of these high peak prices. Finally, many customers now
require harmonic filtering and power factor correction. Rather than force
customers to solve all of these problems individually, the flywheel RMS will
use the enabling efficiency and storage capacity of flywheels with
superconducting bearings to meet the need for comprehensive power risk
management.
The Boeing system as initially introduced would consist of three units: (1)
a power inverter and conditioning unit that also houses the flywheel’s motor
controller, (2) the flywheel storage unit in a vacuum canister with integral
cryocooler, and (3) a customer utility vault for the flywheel storage unit.
6
Final report Cooperative Agreement No. DE-FC36-02GO12112
Eventually, fully qualified containers may become integral parts of the storage
units but early customers will prefer the assurance of below ground
installation.
In operation, the ac power unit will receive power from the utility grid and
transfer some part of this power to the flywheel storage unit through a
motor/generator and motor controller. Because the flywheel unit can store a
significant amount of energy (typically sized for 1 to 3 hour’s usage), it will
primarily draw power when grid demand and prices are low. When prices are
high, or when power is interrupted, the unit will deliver this power to the
customer at low cost. At all times, the integrated inverter/controller unit will
maintain good power quality and correct the power factor to the benefit of the
utility as well as the customer. The system itself will run continuously, with a
rated lifetime in excess of 20 years. Potential commercial uses of the Risk
Management System are numerous because power cost and reliability are
central to the operation of our economy.
SMES systems use the energy stored in the magnetic field generated by a
current in a superconducting coil. The SMES option might be used to provide
short bursts of power, but cannot compete with flywheels for ride-through
protection. Foreseeable SMES systems also have very large capital and
7
Final report Cooperative Agreement No. DE-FC36-02GO12112
operating costs associated with liquid helium usage. HTS versions seem far
in the future.
$10,000,000
Lead-Acid Batteries
- 5 year life/battery
- $1.60/Wh battery cost
$8,000,000 - includes O&M
- 56,000 lbs
Life Cycle Cost
$4,000,000
Gas turbines and microturbines are often used as points of reference for
storage system costs. While large gas turbines produce much of the original
power, they cannot directly help the thousands of commercial customers who
face poor power supply from the grid. Microturbines are being proposed and
tested as a way of providing distributed local generation, which would be
preferred by both customers and the utilities. SCE has several such units
under test but has found them to be highly inefficient (typically 24%).
Downfalls of the microturbines include noise, generation of emissions, and
monthly maintenance. Gas turbines are not solving the customer’s needs for
clean, uninterruptible power.
8
Final report Cooperative Agreement No. DE-FC36-02GO12112
replacement costs for customers than the proven Boeing HTS bearing design.
Only Active and Pentadyne have truly entered the market so far, with Active
Power having a usable but inefficient and very limited product. Figure 4
compares the energy losses for mechanical, electromagnetic, and Boeing
HTS bearing. The total bearing loss in the 10 kWh system tested in the Phase
II project met the DOE’s goal of HTS bearing loss of 0.1% per hour. The
figure shows that the HTS bearing is the only economical solution to long-
term storage and UPS service. Other factors supporting this conclusion
include wear of mechanical bearings and complex inductive coupling
limitations of electromagnetic bearings.
100
Battery
80
Energy Remaining (%)
Boeing Flywheel
superconducting bearings
60 (includes cryogenics)
40 Flywheel
electromagnetic
bearings
20 Flywheel
mechanical
bearings
0
0 50 100 150 200
Time (Hours)
Figure 4. Energy Remaining in Flywheel with Time for Various Bearing Systems.
9
Final report Cooperative Agreement No. DE-FC36-02GO12112
10
Final report Cooperative Agreement No. DE-FC36-02GO12112
The initial design concept for the 30-kWh flywheel unit, carried forward
from the 5-kWh / 100-kW prototype, is shown in figure 10, with some
features highlighted.
11
Final report Cooperative Agreement No. DE-FC36-02GO12112
realistic factors of safety (typically two or more) and fatigue de-rating factors
to replicate the conditions of a commercial life.
Hybrid HTS/Permanent-Magnet Bearing. The energy losses associated
with mechanical and electromechanical bearings are prohibitively high for nearly
all potential flywheel applications. These losses are typically at least 3% to 10%
of the stored energy per hour. With hybrid superconducting bearings, we have
demonstrated that it is now possible to obtain losses that are as low as 0.1% per
hour - after imposing a cryogenic overhead factor FCOH of 20 – 30 at 77K. HTS
bearings possess other significant advantages such as dynamic stability,
simplicity, and reliability. The Boeing-patented bearing design (figure 11)
employs horizontally-polarized magnets to achieve a high magnetic stiffness
per unit area of superconductor.
Figure 10. RMS Unit Design, exclusive of Power Electronics and Cryocooler.
12
Final report Cooperative Agreement No. DE-FC36-02GO12112
Lift Magnet System. The system design uses permanent magnet rings to
carry most of the flywheel’s weight, significantly reducing the thrust
requirement on the HTS bearing. A small but inevitable amount of instability in
the lift system is counteracted with the HTS bearing. This approach has been
validated in systems built at Boeing and Argonne.
Cryogenic System. Compared with most potential HTS applications, the
Flywheel Risk Management System imposes relatively light requirements on
the cooling load and base temperature. Pulse-tube cooler technology now
promises to provide the most efficient, reliable cooling for this application.
Pulse-tube cooler designs eliminate moving parts from the cooler and do
away with sliding seals.
Motor/Generator (M/G). The flywheel transforms electrical energy to
mechanical and back again through a brushless permanent-magnet motor.
An unusual design requirement is that the motor magnets and laminations
must not destabilize the HTS bearing and flywheel. Team member Ashman
Technologies met this requirement in both 10-kW and 100-kW designs.
Motor Control and Power Conversion Electronics. A motor controller
unit transforms the variable speed motor output to an intermediate dc bus
level. Special algorithms have been developed through Ashman for efficient,
sensorless control of the flywheel M/G. From there, the power electronics for
the proposed system will be based very closely on commercial systems now
in use for battery UPS and renewable generation systems, typically
incorporating power factor correction. These systems are already very simple
to operate and have been developed with standby power requirements as low
as 50W.
13
Final report Cooperative Agreement No. DE-FC36-02GO12112
The first task in the original Phase 3 proposal was to transfer the 100 kW
UPS flywheel system, once testing was completed during Phase 2, to SCE
and carry out on-site testing. The system must then be capable of unattended
operation and will require a few upgrades to enhance stability and self-
monitoring. This task was never completed due to lack of funding in Phase 3
and the delay in completing Phase 2 tests, due to redesign of the rotor/hub
interface after previous instabilities described in the previous section.
The middle and outer rims have a 0.025” diameter interference fit. As with
previously performed flywheel analyses, the analysis includes load steps to
follow the assembly sequence. Contact surfaces are used to model the
interaction of bodies with each another. The composite rims are modeled with
orthotropic material properties.
14
Final report Cooperative Agreement No. DE-FC36-02GO12112
Model Attributes
¾31” ID
¾40” OD
¾0.025” Interference @
T700s/T800s Interface
S2-Glass
T700S
¾Contact surfaces
T800S
between each rim
¾ Central Hub is not
included
Load Steps
15.5” IR Step Description
1 T700s/T800s Press Fit
2 Spin to 20k RPM
20.0” IR
Figure 12. The 38 kWh Axisymmetric Spin Analysis. The FE model was created
with IDEAS and solved with ABAQUS.
5.2. Results
The results of the spin loads show that the rotor will experience
acceptable stress levels. The absence of a hub should be noted. The shear
stress levels will increase once this hardware is included. With that in mind,
the resulting max stress levels are presented in table 2. The table shows a
minimum Safety Factor of 1.6 on the hoop stress levels in the inner (S2-
Glass) and outer (T800s) rims.
15
Final report Cooperative Agreement No. DE-FC36-02GO12112
The hoop and radial stress distributions through the rotor thickness are
presented in figure 13. The discontinuities in the curve show the borders of
each rim.
S2-Glass
T700S
T800S
290 ksi
Path-1
110 ksi
20.0” IR
Figure 13. The Rotor Radial & Hoop Stress vs. Rotor Thickness at 20K RPM.
16
Final report Cooperative Agreement No. DE-FC36-02GO12112
T800s OR S2-Glass IR
The XLRotor code was used to extrapolate from the 5 kWh design, based
on the rim concept discussed in the previous section (figure 15). Also, simple
scaling was used for the motor/generator to account for the new speed range
of nominally 10,000 – 20,000 rpm plus a modest increase in power output, to
150 kW. To get the power at the bottom of this speed range, the motor’s
magnet area must be increased by roughly a factor of 2.7 from the earlier
design. This was done by increasing the length by a factor of 1.5 and the
diameter by a factor of 1.8.
17
Final report Cooperative Agreement No. DE-FC36-02GO12112
Model Attributes
¾31” ID
¾40” OD
¾0.025” Interference @
T700s/T800s Interface
S2-Glass
T700S
¾Contact surfaces
T800S
between each rim
¾ Central Hub is not
included
Load Steps
15.5” IR Step Description
1 T700s/T800s Press Fit
2 Spin to 20k RPM
20.0” IR
The geometry of the scaled design is shown in figure 16. Note the thin rim
design. If the aluminum hub is to be used, the rim will have to get somewhat
thicker (smaller ID) which will increase weight. This will be one of many trades
in developing the working design.
FLYWHEEL DYNAMIC MODEL
25
28 30
6
15
Shaft Radius, in
5 10 12 14 1618
4 8 22
24
2 20 26
-5
-15
Axial Location, in
-25
-5 15 35 55
18
Final report Cooperative Agreement No. DE-FC36-02GO12112
The computed results for this model show a fairly stiff rotor (a benefit),
with a low speed bearing fundamental. However, there is a mode (shown as
the red line in figure 17) that closely follows the speed of the rotor. This would
lead to excessive vibration at most speeds of less than 5,000 rpm. It may be
possible to hold the rotor on auxiliary bearings through this speed range, but
a better strategy would be to reduce the moment ratio to some number
significantly less than 1.0. The key problem at present is that the transverse
and polar moments of inertia are nearly equal. Moving the hub lower on the
rim would also help, as was done on the 5 kWh design. The analysis
described here will show the need for fundamental adjustments prior to
establishing component requirements for designers.
Rotordynamic Damped Natural Frequency Map
FLYWHEEL DYNAMIC MODEL
200
180
Natural Frequency, Hz
160
140
120
100
80
60
40
20
0
0 5000 10000 15000 20000 25000
Figure 17. Critical speed map of the initial 38 kWh flywheel design.
19
Final report Cooperative Agreement No. DE-FC36-02GO12112
has been determined that the existing pit with the addition of the cement
barrier was the best solution and the analysis indicates that the existing pit is
sufficient to contain any potential failure and leave the second system intact.
The analysis has shown that the two tiers of cement ceiling blocks will not be
lifted clear of the nested interlock holding the blocks in place. With two layers
of blocks the energy rating is over 60 kWh. It should be noted that this
assumes that the momentum transfer takes place over a 10 ms period. The
rating decreases if the duration is shorter, as is shown in figure 19.
20
Final report Cooperative Agreement No. DE-FC36-02GO12112
Momentum Duration (Sec) 0.001 0.005 0.01 0.02 Energy Density Calculator
Effective Energy Ratio Ee/Et 75% 75% 75% 75% OD (in) 22.75
Load Factor fl 2.00 2.00 2.00 2.00 ID (in) 13.50
H (in) 13.50
Energy Density
ED Permissible Energy (KWh)
(KWh/#) 1st Layer of Bolocks Only Gama (#/in^3) 0.0530
0.01 1.50 7.51 15.01 30.02 RPM 24,000
0.02 2.12 10.61 21.23 42.46 W (lb) 188.43
0.022 2.23 11.13 22.27 44.53 I (#-Ft-Sec^2) 3.55
0.04 3.00 15.01 30.02 60.05 E (KWh) 4.23
0.06 3.68 18.39 36.77 73.54
0.1 4.75 23.74 47.47 94.94
0.15 5.81 29.07 58.14 ED (KWh/#) 0.022
Energy Density
ED Permissible Energy (KWh)
(KWh/#) 1st & 2nd Layer of Blocks Number of Blocks & Block Wieght Calculator
0.01 4.50 22.52 45.03 90.07 H (Ft) 3
0.02 6.37 31.84 63.69 d (Ft) 3
0.022 6.68 33.40 66.80 b (Ft) 1.8
0.04 9.01 45.03 90.07 L (Ft) 12.5
0.06 11.03 55.16 h (Ft) 2
0.1 14.24 71.21 p-concrete (lb/Ft3) 144
0.15 17.44 87.21 Ee/Et 75%
#DIV/0!
This spreadsheet computs the energy #DIV/0!
necessary to lift one block due#DIV/0!
to the change #DIV/0!
in Block Weight (lb) 6,480
direction of the momentum flow. # 1st Layer Blocks 6.00 Actual Number Hit
# 2nd Layer Blocks 7 Actual Number Hit
Target Energy (KWh) 4.23 W-blocks-total (lb) 84,240
MS - 1 Block 4.02
MS - Both Rows of Blocks (3
total) 14.79
Figure 19. Boeing 15-08 building block lift Pit rating summary – Note that rating is
based on energy concentrated on only one 1st level block, the actual number of
1st and 2nd level blocks calculated in yellow for comparison.
21
Final report Cooperative Agreement No. DE-FC36-02GO12112
This project was on hold for over 3 years and was restarted in July 2006.
The primary objective in this task was to troubleshoot the current
motor/controller and system controller hardware and software to determine
optimum configuration for a commercial system that would be required for the
Power Risk Management System that would be deployed remotely in service
at a utility customer. This section summarizes our accomplishments and
conclusions.
22
Final report Cooperative Agreement No. DE-FC36-02GO12112
This SOW will address the design, build, delivery, and integration of the Motor
Controller for the Boeing Company’s 25 kW Flywheel Energy Storage System.
3. The motor controller will be required to operate the motor / generator in the
following modes of operation:
b. Normal (or Idle) Mode: The FESS is fully charged but is not
providing power to the load. This control method may utilize
23
Final report Cooperative Agreement No. DE-FC36-02GO12112
e. Normal Shut Down Mode: Used for normal shutdown of the FESS.
This control method will require idling or disabling the drive control
and manually loading the FESS with external loads.
4. The motor / generator controller design effort will be in coordination with the
Boeing team to insure compatibility with the FESS motor / generator. The
motor / generator is Tau connected and operated as Delta wound, e.g.
floating neutral.
6. Final engineering services with 100 days of receipt of contract will include
delivery of one motor / generator controller system as well as engineering
services to integration and tune the motor controller to the FESS motor /
generator. Final engineering services will include documentation such as
mechanical drawings, parts list, schematics, operating instructions, software,
and other test data used to verify the specifications outlined in Table 3.
SYSTEM SPECIFICATIONS
Table 3. Description of Inverter Characteristics.
24
Final report Cooperative Agreement No. DE-FC36-02GO12112
25 kWatts
Input Power Rating
Input Connection 2 wire plus ground
Input Voltage Range 500-670 Vdc
Input Current 60 Amps (RMS)
Input Power Factor 0.98 (at rated linear load)
Speed Range 0-20,000 rpm
Other
Packaging Commercial Grade
Operating Temperature 40F to 120F
Motor Poles 6
Motor Phases 3
25
Final report Cooperative Agreement No. DE-FC36-02GO12112
Generator (M/G) system, except for startup. Smooth operations under torque
control is limiting acceleration rate and is problematic. Thus, we have limited
our startup average current to 10 amps under Hall-Effect control and 20 amps
under Current-loop Sensor-less control. We expect better control and higher
acceleration under Speed-loop Sensor-less control.
26
Final report Cooperative Agreement No. DE-FC36-02GO12112
a single supplier is desired in the future. This will avoid some of the multiple
supplier integration issues encountered during our Phase 2 activities.
Software completion requires substitution of code to replace the ‘hard
switches’ currently used for startup, operation and shutdown. This code
needs developing, testing and implementation into firmware, and then loaded
into the microprocessor. Current software versions do not include this portion
of program code. Most of the basics blocks of code exist to test the
motor/controller functions, although some untested, but an integrated version
is not complete. This code addition is required for future integration of the
Power Risk Management System via the Can Bus interface in a commercially
deployed, autonomously operated flywheel system.
27