DT Procedure

LTE Drive Test Procedure


for Single Site Verification

08.2015

2015-9-7

1 , 15

DT Procedure

Description
Description
The RF optimization phase focuses on optimiszation of distribution of radio signals in the
network.The main test mothods is drive test
Concentrate on the drive test,through which you can cllect radio signal data tested through the UE
for analyzing coverage,handover,and interference of outdoor signals.

Test Preparations
Preparaing Tools and Materials
Before DT,prepare necessary software,hardware and materials to guarantee smooth perpformance
of subsequent test and analysis tasks.
Software Preparation:
No.

Software Name

Function

GENEX Probe

Drive test

GENEX Assistant

DT data analysis

Google Earth

Display of geographic location and


Environment of an eNodeB,and
display of altitude

Remark

Hardware Preparation:
No.

Device Name

Content

GPS

Ordinary GRAMIN series GPS


Home-made BU353

Dongle

Probe dongle

Laptop

PM2.0G/1G/160G/USB/COM/Serial

Vehicle mounted inverter

DC to AC,over 300W

Car

Normal Car

Remark

Material Preparation:
No.
2015-9-7

Material Needed

Content

Remark
2 , 15

DT Procedure

Engineering Parameter List

Latest version

Mapinfo map

Traffic road layer,latest station layer

Google earth

Software installation
Before Drive Test, Make sure about necessary software and the hardware device have installed in
the laptop.Such as GENEX Probe& Assistant.
The Probe Operation Guide can refer to attachment

Device connection
After finished the hardware drive software,try to connect to Probe.
To configure hardware using Probe.perform the following steps:
Step1: Start GENEX Probe 2.3 software.
Step2:Choose configuation>Device Management>Device Config.

Step3:Click the icon highlighted in red below.

Step4:Add the UE adjust the interval at which the UE can connect.

2015-9-7

3 , 15

DT Procedure

Step5:Add the GPS device.

Step6:After configuring the hardware.click the connection icon.

If connection is successful,Probe will display the following

End
2015-9-7

4 , 15

DT Procedure

Importing eNodeB information


Step1:Importing eNodeB information

Step2:

2015-9-7

5 , 15

DT Procedure

End

Importing the electronic map layer

2015-9-7

6 , 15

DT Procedure

End

Producing a Test Plan


In the Configuration menu,Click System Config ,and then choose Test Plan.In this section we
decribe using the Test Plan functions.

2015-9-7

7 , 15

DT Procedure

FTP Upload

FTP Download:

2015-9-7

8 , 15

DT Procedure

End

Configuring Probe

2015-9-7

9 , 15

DT Procedure

Field test record

Afer Finishing all the above step. We can start the drive test.
Step1:Planning the test route. We can plan the test road in the map before testing.It can improve
our testing efficiency

Step2:Start Probe and build a new test project(or open the project you have saved)
Step3:Connecting the device and start the test plan
2015-9-7

10 , 15

DT Procedure

Step4:Record the data file around the test areas


Step5:Stop the test and export the test Log file to analysis

Drive Test Procedures

1.Coverage Test
Objective
The objective of this test is to check if there's swapped feeders and if the Radio Units and
Antennae are radiating as supposed to be.
Coverage Test radio parameters :
Radio Parameters

Remarks

RSRP

reference Signal Radio Power, the power of the UE received.

SINR

signal to interference plus noise ratio ,the quality of the signal in UE


received

RSRQ

reference signal received quality,show the quality of reference signal

PCI

physical cell identifier

1. Serving PCI
For SSV this parameter can indicate whether the PCI is configured correctly or not and
whether the antenna is connected correctly or not.
Procedure

Expected Result

The test is done by driving all the roads


around the sites in idle/active mode .

PCI served correctly in each sector as it


should be as planned

GENEX Probe will display the serving PCI


and record the log file.Check the PCI of
different cell .
Test result:

2-Serving RSRP
Procedure

2015-9-7

Expected Result

11 , 15

DT Procedure

The test is done by driving all the roads


around the sites in idle/active mode .
GENEX Probe will display the serving
RSRP and record the log file
GENEX Assistant can analyse the log file
and show the result on the map and
statistics .

Near a cell : RSRP>=-80 dBm, (Excellent)


in the middle of a cell :
-100 =< RSRP < -80 (Good)
at the edge of a cell :
110 =< RSRP <-100 (Fair)
-120 =< RSRP <-110 (Poor)
target: the minimum RSRP for UEs to camp on a
cell is -109 dBm.
The RSRP is greater than -110 dBm in 90%
areas at the cell.

Test result:

3-Serving RSRQ
Procedure

Expected Result

The test is done by driving all the roads


around the sites in idle/active mode .
GENEX Probe will display the serving RSRQ
and record the log file.
GENEX Assistant can analyse the log file
and show the result on the map and statistics
.

RSRQ >= -10 dB (Excellent)


-12 dB =< RSRQ <-10 dB (Good)
-14 dB =< RSRQ <-12 dB (Fair)
-16 dB =< RSRQ <-14 dB (bad)
target: The RSRQ is greater than -14 dB in
90% areas at the cell.

Test result:
3-Serving SINR

Procedure

Expected Result

The test is done by driving all the roads


around the sites in idle/active mode .
GENEX Probe will display the serving SINR
and record the log file.

2015-9-7

SINR >= 30 (Excellent)


20 dB =< SINR < 30 dB (Very good)

12 , 15

DT Procedure

GENEX Assistant can analyse the log file


and show the result on the map and statistics
.

10 dB =< SINR < 20 dB (good)


0 dB =< SINR < 10 dB (Fair)
20 dB =< SINR < 0dB (poor)
target : The SINR is greater than 0 dB in
90% areas at the cell.

Test result:

2. Throughput test
Description
1- For each cell we should find MID Point and FAR Point away from the site to do DL&UL test.
So we need to do 12 tests for a site (12 throughput screenshot pictures)
2- The throughput test is a static test just find a location in front of the sector where radio
conditions are the best near by the test point for each cell.
3- During test you make sure you are always camping on same PCI ( the one of the sector)
Throughput (DL&UL)
Single user throughput is a key performance indicator of LTE system to ensure customer experience.
This test case aims to check the single user downlink&uplink peak throughput performance when UDP
services are enabled.
Procedure

Expected Result

Start the UE tracing tool and monitor the following


items: DL RSRP/SINR, RLC throughput, and rank
or MIMO mode.
Use the NetMeter or netpersec to trace
throughput. and record the result of average
throughput.

Operation succeeded.

Power on the UE to initiate the attach procedure.

The INITIAL UE MESSAGE and the last


UPLINK NAS TRANSPORT messages in S1
interface tracing indicate that the attach
procedure is successful.

Adjust the attenuator or move the UE to the cell


center when do the peak throughput test.

The downlink SINR is greater than 25 db and


RSRP is greater than -80 dBm.

Cut the screen picture of throughput(DL&UL),


When we test in MID point (200m)&FAR point
(1000m) away from the site

For MID point target throughput :


DL:55Mbps, UL:25Mbps
For FAR point target throughput:

2015-9-7

13 , 15

DT Procedure

DL:15Mbps,UL:10Mbps
Start downlink&uplink UDP data transfer using the
Iperf tool.

Operation succeeded.

Record the logs of average RSRP, SINR, when you


do the throughput

The throughput is stable.

Restore the configuration.

Operation succeeded.

Test result:

3.The Latence Test


Test the latence
Latency is the key performance of LTE system to ensure customer experience and consists of control
plane latency and user plane latency.
This test case aims to test the ping 32/1000 bytes latency under the following scenarios: stationary,
target user on cell center, without load, pre-scheduled.
Procedure

Expected Result

Open command prompt from windows and ping the ip address


of the FTP server (10.10.19.148) on same location u where
doing the throughput test and take snapshot of the block
window.
We do it once per sector
Ping 32 bytes from the UE to the server for 50 times.
Obtain the average, maximum, minimum E2E user plane
latency and standard deviation for 32 bytes.
Command: ping n 50 l 32 10.10.19.148

The average time value is less than 35


ms

Test result:

4.Handover Test
The objective is to know if the HO is working between the 3 sectors of the site.
Handover Test
This test case involves the following elements: EPC, eNodeB , cell1,2,3, and UE
Procedure

Expected Result

HO test is done in dedicated mode


1. Power on the UE and enable it to access cell 1.
2. Enable the UE to log in to the FTP server and download
a file from the server.

The Target Value of Handover


Success Rate(Intra-Frequency) is
90%

2015-9-7

14 , 15

DT Procedure

3. Move the UE from the coverage of cell 1 to the


coverage of cell 2/3, or adjust the attenuator to make the
signal quality of cell 2/3 better than that of cell 1 to
trigger a handover for the UE.
4. After the handover is complete, check the status of the
FTP downloading task..
Remarks
1>. The following figure shows the message flow of intra-frequency handover procedure of intraeNodeB.
(1). The UE sends the Measurement Report message (A3 Event) to the eNodeB.
(2). The eNodeB sends the RRC Connection Reconfiguration message to the UE to indicate that the
radio resource configuration information for UE random accessing.
(3). The UE sends the RRC Reconfiguration Complete message to the target cell to confirm that the UE
attaches to the target cell successfully.
(4). The eNodeB sends the RRC Connect Reconfiguration message to the UE to indicate the
configuration of UE measurement and gets back the RRC Reconfiguration Complete (Handover
complete) message from the UE.

2015-9-7

15 , 15