Вы находитесь на странице: 1из 19

68440 Federal Register / Vol. 71, No.

227 / Monday, November 27, 2006 / Rules and Regulations

Dated: November 16, 2006. Before Commissioners: Joseph T. I. Background


Christopher A. Padilla, Kelliher, Chairman; Suedeen G. Kelly,
A. The Development of ISOs and RTOs
Assistant Secretary for Export Marc Spitzer, Philip D. Moeller, and
Administration. Jon Wellinghoff. 4. In both our Notice of Proposed
[FR Doc. 06–9414 Filed 11–24–06; 8:45 am] Rulemaking (NOPR) 3 and the Final
1. On July 20, 2006, the Commission Rule, we discussed the development of
BILLING CODE 3510–33–M
issued a Final Rule in this proceeding.1 Independent System Operators (ISOs)
In the Final Rule, the Commission and Regional Transmission
amended its regulations to require each Organizations (RTOs). In Order No. 888,
DEPARTMENT OF ENERGY transmission organization that is a the Commission found that undue
Federal Energy Regulatory public utility with one or more discrimination and anticompetitive
Commission organized electricity markets to make practices existed in the provision of
available long-term firm transmission electric transmission service in
18 CFR Part 42 rights that satisfy each of the guidelines interstate commerce.4 Accordingly, the
established by the Commission in this Commission required all public utilities
[Docket No. RM06–8–001; Order No. 681– Final Rule. We took this action pursuant that own, control or operate facilities
A] to section 1233 of the Energy Policy Act used for transmitting electric energy in
of 2005 (EPAct 2005), which added new interstate commerce to file open access
Long-Term Firm Transmission Rights transmission tariffs (OATTs) containing
in Organized Electricity Markets section 217 to the Federal Power Act
(FPA).2 The Final Rule required each certain non-price terms and conditions
November 16, 2006. transmission organization subject to its and to ‘‘functionally unbundle’’
AGENCY: Federal Energy Regulatory requirements to file with the wholesale power services from
Commission, DOE. Commission, no later than January 29, transmission services.5 In addition, the
Commission found in Order No. 888
ACTION: Order on Rehearing and 2007, either (1) tariff sheets and rate
that ISOs had the potential to aid in
Clarification. schedules that make available long-term
remedying undue discrimination and
firm transmission rights that satisfy each
SUMMARY: The Federal Energy accomplishing comparable access.6
of the guidelines set forth in the final 5. In light of the creation of ISOs and
Regulatory Commission is issuing an regulations, or (2) an explanation of how
order on rehearing and clarification of other changes in the electric industry,
its current tariff and rate schedules the Commission issued Order No.
Long-Term Firm Transmission Rights in already provide for long-term firm
Organized Electricity Markets, Order 2000.7 In that order, the Commission
transmission rights that satisfy each of concluded that traditional management
No. 681, 71 FR 43564 (Aug. 1, 2006).
the guidelines. A transmission of the transmission grid by vertically
The order on rehearing denies rehearing
organization approved by the integrated electric utilities was
and upholds Order No. 681 in all
respects, and grants certain limited Commission for operation after January inadequate to support the efficient and
clarifications. 29, 2007 will be required to satisfy the reliable operation of transmission
requirements of the Final Rule. facilities necessary for continued
DATES: Effective Date: Order No. 681 development of competitive electricity
became effective on August 31, 2006. 2. The guidelines adopted in the Final
Rule give transmission organizations the
FOR FURTHER INFORMATION CONTACT: Udi 3 Long-Term Firm Transmission Rights in
flexibility to propose designs for long- Organized Electricity Markets, Notice of Proposed
E. Helman (Technical Information),
term firm transmission rights that reflect Rulemaking, 71 FR 6693 (Feb. 9, 2006), FERC Stats.
Office of Energy Markets and Reliability,
regional preferences and accommodate & Regs. ¶ 32,598 (2006) (NOPR).
Federal Energy Regulatory Commission, 4 Promoting Wholesale Competition Through
888 First Street, NE., Washington, DC their regional market designs, while also
Open Access Non-discriminatory Transmission
20426, (202) 502–8080. ensuring that the objectives of Congress Services by Public Utilities; Recovery of Stranded
expressed in new section 217(b)(4) of Costs by Public Utilities and Transmitting Utilities,
Roland Wentworth (Technical Order No. 888, 61 FR 21540 (May 10, 1996), FERC
the FPA are met. The Commission
Information), Office of Energy Markets Stats. & Regs. ¶ 31,036 at 31,682 (1996), order on
allowed regional flexibility in setting
and Reliability, Federal Energy reh’g, Order No. 888–A, 62 FR 12274 (March 14,
Regulatory Commission, 888 First the terms of the rights, but required that 1997), FERC Stats & Regs. ¶ 31,048 (1997), order on
Street, NE., Washington, DC 20426, long-term firm transmission rights be reh’g, Order No. 888–B, 81 FERC ¶ 61,248 (1997),
order on reh’g, Order No. 888–C, 82 FERC ¶ 61,046
(202) 502–8262. made available with terms (and/or rights (1998), aff’d in relevant part sub nom. Transmission
Harry Singh (Technical Information), to renewal) that are sufficient to meet Access Policy Study Group v. FERC, 225 F.3d 667
Office of Enforcement, Division of the reasonable needs of load serving (D.C. Cir. 2000), aff’d sub nom. New York v. FERC,
entities to support long-term power 535 U.S. 1 (2002).
Energy Market Oversight, Federal 5 Under functional unbundling, the public utility
Energy Regulatory Commission, 888 supply arrangements used to satisfy is required to: (1) Take wholesale transmission
First Street, NE., Washington, DC their service obligations. services under the same tariff of general
20426, (202) 502–6341. applicability as it offers its customers; (2) state
3. In this order, the Commission separate rates for wholesale generation,
Jeffery S. Dennis (Legal Information), denies rehearing and upholds its transmission and ancillary services; and (3) rely on
Office of the General Counsel, Federal determinations in the Final Rule. We the same electronic information network that its
Energy Regulatory Commission, 888 also offer certain clarifications. transmission customers rely on to obtain
First Street, NE., Washington, DC information about the utility’s transmission system.
Id. at 31,654.
20426, (202) 502–6027. 6 Order No. 888 at 31,655; Order No. 888–A at
Heidi Werntz (Legal Information), Office 30,184.
1 Long-Term Firm Transmission Rights in
sroberts on PROD1PC70 with RULES

of the General Counsel, Federal 7 Regional Transmission Organizations, Order No.


Organized Electricity Markets, Order No. 681, 71 FR
Energy Regulatory Commission, 888 2000, FERC Stats. & Regs. ¶ 31,089 (1999), order on
43564 (Aug. 1, 2006), FERC Stats. & Regs. ¶ 31,226 reh’g, Order No. 2000–A, FERC Stats. & Regs.
First Street, NE., Washington, DC (2006) (Final Rule). ¶ 31,092 (2000), aff’d sub nom. Public Utility
20426, (202) 502–8910. 2 Pub. L. No. 109–58, § 1233, 119 Stat. 594, 957
District No. 1 of Snohomish County, Washington v.
SUPPLEMENTARY INFORMATION: (2005) (to be codified at 16 U.S.C. § 824q). FERC, 272 F.3d 607 (D.C. Cir. 2001).

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00010 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations 68441

markets,8 and opportunities for undue entities receive FTRs through either the reasonable needs of load-serving entities
discrimination continued to exist.9 As a direct allocation or through a two-step to satisfy the service obligations of the load-
result, the Commission adopted rules to process in which the load serving entity serving entities, and enables load-serving
facilitate the voluntary development of is first allocated auction revenue rights entities to secure firm transmission rights (or
equivalent tradable or financial rights) on a
RTOs. The Commission concluded that (ARRs) and then either uses those rights long-term basis for long-term power supply
RTOs would provide several benefits, to purchase FTRs, or has the ability arrangements made, or planned, to meet such
including regional transmission pricing, under the transmission organization needs.18
improved congestion management, and tariff to convert them to FTRs.13
more effective management of parallel Section 1233(b) of EPAct 2005
B. Interest in Long-Term Firm requires:
path flows.10
6. Most of the RTOs and ISOs now Transmission Rights
Within 1 year after the date of enactment
operate organized markets for energy 8. We noted in the Final Rule that in of this section and after notice and an
and/or ancillary services in addition to recent years, interest in long-term firm opportunity for comment, the Commission
providing transmission service under a transmission rights in organized shall by rule or order, implement section
single transmission tariff. Under the electricity markets has increased, 217(b)(4) of the Federal Power Act in
stemming in large part from a desire of Transmission Organizations, as defined by
definitions adopted in the Final Rule,
that Act with organized electricity markets.19
these RTOs and ISOs are transmission some market participants to obtain
organizations with organized electricity rights that replicate the transmission D. Notice of Proposed Rulemaking
markets subject to the regulations service that was available to them prior 11. On February 2, 2006, the
adopted in this proceeding. to the formation of the organized Commission issued a NOPR that
7. Most of the organized electricity electricity markets and remains proposed to amend its regulations to
markets operated by transmission available today in regions without require each transmission organization
organizations utilize a congestion organized electricity markets. The that is a public utility with one or more
management system based on principal concern of these market organized electricity markets to make
Locational Marginal Pricing (LMP). participants is the inability to obtain a available long-term firm transmission
Congestion is defined as the inability to fixed, long-term level of service under rights that satisfy guidelines established
inject and withdraw additional energy pricing arrangements that hedge the by the Commission.20 The NOPR
at particular locations in the network congestion cost risk that they face in the proposed eight guidelines, and sought
due to the fact that the injections and organized electricity markets.14 comments on various issues raised by
withdrawals would cause power flows 9. There are several important
the introduction of long-term firm
over a specific transmission facility to differences between transmission
transmission rights in the organized
violate the reliability limits for that service under the Order No. 888 pro
electricity markets.
facility. The market operator manages forma OATT and transmission rights in
congestion by scheduling and organized electricity markets that use E. Final Rule: Order No. 681
dispatching generators that can meet LMP and FTRs.15 However, the 12. As noted above, in the Final Rule
load in the presence of congestion. differences that are most relevant for the Commission adopted regulations
Financially, in LMP markets the price of purposes of the Final Rule concern the requiring public utilities that are
congestion is measured as the difference management of congestion, the recovery transmission organizations with
in the cost of energy at two different of congestion costs, and the availability organized electricity markets (as defined
locations in the network. When such of long-term service arrangements. in the Final Rule) to make available
price differences occur, a congestion These differences are discussed in the long-term firm transmission rights that
charge is assessed to transmission users Final Rule.16 satisfy each of the seven guidelines
based on their injections and C. Energy Policy Act of 2005 established by the Commission, which
withdrawals at particular locations. are set forth in the regulations. By
These price differences can be variable 10. On August 8, 2005, EPAct 2005 17
became law. As noted above, section adopting guidelines for the development
and difficult to predict. In order to of long-term firm transmission rights,
manage the risk associated with the 1233 of EPAct 2005 added a new section
217 to the FPA, which provides: the Commission gave transmission
variability in prices due to transmission organizations the flexibility to propose
congestion, these markets use various The Commission shall exercise the designs for long-term firm transmission
forms of financial transmission rights authority of the Commission under this Act
rights that reflect regional preferences
(FTRs),11 which enable market in a manner that facilitates the planning and
expansion of transmission facilities to meet and accommodate regional market
participants who hold the rights to designs, while ensuring that the
protect against such price risks. In most objectives of Congress expressed in new
Comments On Establishing Long-Term
cases, these FTRs have terms of one year Transmission Rights in Markets With Locational section 217(b)(4) of the FPA are met.21
or less.12 In general, load serving Pricing and Staff Paper, Long-Term Transmission
Rights Assessment, Docket No. AD05–7–000 (May 18 Pub. L. No. 109–58, § 1233, 119 Stat. 594, 958.
8 Order No. 2000 at 30,992–93 and 31,014–15. 11, 2005) (Staff Paper). There, the current FTR 19 Id. at 960. Transmission organization is defined
9 Id. at 31,015–17. situation was discussed. See id. at 1 (stating that, in EPAct 2005 as ‘‘a Regional Transmission
10 Id. at 31,024. as of the date of issuance ‘‘the longest term FTR Organization, Independent System Operator,
11 While ‘‘FTR’’ is sometimes used to refer to offered in any of the RTO or ISO markets is one independent transmission provider, or other
year’’). transmission organization finally approved by the
‘‘firm transmission rights,’’ in this Final Rule we 13 For a more detailed discussion, see NOPR at P
use this acronym to refer to the various forms of Commission for the operation of transmission
financial transmission rights that exist in organized 27. As we noted in the NOPR, ARRs confer the right facilities.’’ Pub. L. No. 109–58, § 1291, 119 Stat.
electricity markets. In some markets, these are to collect revenues from the subsequent FTR 594, 985. In the Final Rule, we adopted this
referred to as congestion revenue rights or auction. definition with slight modifications for the
sroberts on PROD1PC70 with RULES

14 See Staff Paper at 1–2.


transmission congestion contracts. purposes of the Final Rule.
12 In May 2005, the Commission released a Staff 15 A detailed discussion of transmission rights in 20 See supra note 3.

Paper that provided background and solicited traditional and organized markets was presented in 21 The Commission discussed the possibility that

comments on whether long-term transmission rights the NOPR at P 15–33. the flexible regional approach adopted in the Final
16 Final Rule at P 7–10.
were needed in the ISO and RTO markets, and if Rule could create seams issues, and directed each
so, how to implement them. Notice Inviting 17 Pub. L. No. 109–58, 119 Stat. 594. Continued

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00011 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
68442 Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations

13. In adopting the Final Rule, the (2) The long-term firm transmission right Company (BP), Public Utilities
Commission explained that it sought to must provide a hedge against day-ahead Commission of the State of California
provide increased certainty regarding locational marginal pricing congestion (CPUC), California Department of Water
charges or other direct assignment of
the congestion cost risks of long-term Resources—State Water Project (DWR),
congestion costs for the period covered and
firm transmission service in organized quantity specified. Once allocated, the Midwest ISO Transmission Owners
electricity markets that will help load financial coverage provided by a financial (Midwest TOs), Modesto Irrigation
serving entities and other market long-term right should not be modified District (Modesto), New York
participants make new investments and during its term (the ‘‘full funding’’ Independent System Operator, Inc.
other long-term power supply requirement) except in the case of (NYISO), City of Santa Clara (Santa
arrangements. The Commission also extraordinary circumstances or through Clara), Sacramento Municipal Utility
stated that the guidelines adopted in the voluntary agreement of both the holder of the District (SMUD), and Transmission
Final Rule are designed and intended right and the transmission organization. Access Policy Study Group (TAPS).
(3) Long-term firm transmission rights 18. On September 13, 2006, Electric
primarily to ensure that the long-term
made feasible by transmission upgrades or
firm transmission rights that are made Power Supply Association (EPSA) filed
expansions must be available upon request to
available by transmission organizations any party that pays for such upgrades or supplemental comments, and PJM
that are subject to the rule have expansions in accordance with the Interconnection, L.L.C. (PJM) filed a
characteristics that will support long- transmission organization’s prevailing cost motion for leave to answer, as well an
term power supply arrangements.22 allocation methods for upgrades or answer. SMUD and Modesto both
14. Additionally, the Final Rule made expansions. moved to strike PJM’s answer, while
clear that, while it unequivocally (4) Long-term firm transmission rights APPA and TAPS submitted a joint reply
requires transmission organizations to must be made available with term lengths to PJM’s answer.
offer long-term firm transmission rights (and/or rights to renewal) that are sufficient 19. Rule 213(a)(2) of the
to meet the needs of load serving entities to Commission’s Rules of Practice and
with characteristics that will support hedge long-term power supply arrangements
long-term power supply arrangements, made or planned to satisfy a service
Procedure 25 prohibits an answer to a
in most cases, offering such rights obligation. The length of term of renewals request for rehearing unless otherwise
should not require major changes in may be different from the original term. ordered by the decisional authority. We
allocations or allocation procedures.23 Transmission organizations may propose are not persuaded to accept PJM’s
We noted that our intent with regard to rules specifying the length of terms and use answer, EPSA’s supplemental
the existing transmission system is that of renewal rights to provide long-term comments (which are in the form of an
load serving entities be able to request coverage, but must be able to offer firm answer), or the responses to those
and obtain transmission rights up to a coverage for at least a 10 year period. answers, and will, therefore, reject
(5) Load serving entities must have priority
reasonable amount on a long-term firm them.
over non-load serving entities in the
basis, instead of being limited to allocation of long-term firm transmission B. Requests for Rehearing and
obtaining exclusively annual rights.24 rights that are supported by existing capacity. Clarification and Commission
Moreover, we emphasized that offering The transmission organization may propose Conclusions
such rights should not force reasonable limits on the amount of existing
transmission organizations to provide capacity used to support long-term firm 1. Definition of Load Serving Entity and
rights to the existing system that are transmission rights. Service Obligation
infeasible, and that the Final Rule does (6) A long-term transmission right held by
a load serving entity to support a service 20. In the Final Rule, as proposed in
not necessarily guarantee that a load the NOPR, the Commission adopted the
obligation should be re-assignable to another
serving entity will be able to obtain entity that acquires that service obligation. definitions of load serving entity and
long-term firm transmission rights to (7) The initial allocation of the long-term service obligation exactly as Congress
hedge its entire resource portfolio or be firm transmission rights shall not require defined those terms in new section 217
able to obtain all the long-term firm recipients to participate in an auction. of the FPA. Specifically, the Final Rule
transmission rights it requests. defines load serving entity as ‘‘a
In the preamble to the Final Rule, the
15. The specific guidelines adopted distribution utility or electric utility that
by the Commission in the Final Rule, Commission discussed each guideline
in detail. has a service obligation.’’ 26 The term
which the long-term firm transmission
16. The Final Rule also required ‘‘service obligation’’ is defined as ‘‘a
rights offered by transmission
transmission organizations with requirement applicable to, or the
organizations must satisfy, are:
organized electricity markets to explain exercise of authority granted to, an
(1) The long-term firm transmission right how their transmission system planning electric utility under Federal, State, or
should specify a source (injection node or and expansion policies will ensure that local law or under long-term contracts
nodes) and sink (withdrawal node or nodes),
and a quantity (MW).
long-term firm transmission rights, once to provide electric service to end-users
allocated, remain feasible over their or to a distribution utility.’’ 27 The
transmission organization to explain in its
entire term. Additionally, it required Commission reasoned that using the
compliance filing how its proposal addresses each transmission organization subject definitions provided by Congress would
potential seams issues. Final Rule at P 107. to the rule to make its planning and most closely effectuate the intent of
22 Final Rule at P 16.
expansion practices and procedures Congress in enacting section 217(b)(4) of
23 As we discuss in more detail below, while we
publicly available, including both the the FPA. The Commission did, however,
do not believe major changes to existing allocation
procedures will be necessary, Congress did not actual plans and any underlying offer several clarifications. For example,
intend to protect existing or future allocation information used to develop the plans. the Commission clarified that non-
methodologies from the implementation of section public utilities are within the definition
217(b)(4) of the FPA. See new section 217(c) of the II. Discussion
of load serving entity, provided they
FPA, Pub. L. No. 109–58, § 1233, 119 Stat. 594,
A. Procedural Matters
sroberts on PROD1PC70 with RULES

958–959.
24 Capacity available would be limited to that 25 18 CFR 385.213(a)(2) (2006).
17. Timely requests for rehearing and/ 26 Final
which is generally available and excludes capacity Rule at P 44; 18 CFR 42.1(b)(2); section
that is the exclusive right of a participant, e.g., a
or clarification were filed by the 217(a)(2) of EPAct.
participant that paid for such capacity and obtained following entities: American Public 27 Final Rule at P 44; 18 CFR 42.1(b)(3); section

FTRs for that payment. Power Association (APPA), BP Energy 217(a)(3) of EPAct.

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00012 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations 68443

have a service obligation.28 The as described by Congress in section as a load serving entity.33 In the same
Commission also clarified that 217(g) of the FPA. vein, BP similarly requests the
industrial customers who self-supply 22. DWR explains that it has put into Commission to clarify that, like those
their own load are construed to be load place long-term transmission entities that self supply, entities that
serving entities under the Final Rule, entitlements used ‘‘to support its own enter into long-term obligations to sell
even though some of these entities may water pumping facilities’’ as provided in electric energy to load serving entities
not technically ‘‘sell * * * electric section 217(g). DWR states that, while it that have the option to self supply, be
energy.’’ The Commission stated that self-provides power to its own water similarly construed as load serving
this would ensure that Congress’ pumping facilities, it does not provide entities for purposes of the Final Rule.34
objectives under the FPA are fulfilled. electric service to end-users or to a
distribution utility, as it must to qualify Commission Conclusion
Rehearing Requests as a load serving entity under 18 CFR 24. With respect to the issue raised by
21. DWR states that the Commission 42.1(b)(3). Rather, DWR is a water DWR concerning whether water
erred in assuming that a water pumping agency whose pumping facilities pumping entities fall under the
entity under section 217(g) of the FPA provide flood management, water definition of load serving entities, we
necessarily has an electric service deliveries, and other water related grant clarification. While water
obligation as defined in section services to California. Therefore, DWR pumping entities do not come under the
217(a)(3) of the FPA and under 18 CFR asks the Commission to revise section definition of load serving entities, we
42.1. DWR asserts that the Final Rule 42.1 of the regulations to ensure clarify that, to effectuate Congressional
misapprehends the nature of water compliance with section 217(g) of the intent, water pumping entities as
pumping entities, who, unlike load FPA. described in section 217(g) of the FPA
serving entities, have no ‘‘service 23. BP also requests clarification of should be treated as load serving
obligation’’ as defined in section the scope of the Final Rule’s definition entities. As DWR points out, section
217(a)(3) of the FPA and the Final Rule. of a load serving entity. BP states that 217(g) of the FPA provides that the
DWR asserts that new regulatory it is concerned that the Final Rule does ‘‘Commission shall ensure that any
language in 18 CFR 42.1 is necessary to not consistently apply its definition of entity described in section 201(f) [of the
ensure compliance with section 217(g) a load serving entity eligible for long- FPA] that owns transmission facilities
of the FPA. Specifically, DWR argues term firm transmission rights allocation used predominately to support its own
that section 217(g) of the FPA expressly priority. BP argues that the Final Rule water pumping facilities shall have,
distinguishes water pumping entities discriminates against certain entities with respect to the facilities, protections
from load serving entities, stating: with binding contractual obligations to for transmission service comparable to
Water Pumping Facilities—The provide power to load serving entities, those provided to load-serving entities
Commission shall ensure that any entity by denying them load serving entity pursuant to this section.’’ 35 From this
described in section 201(f) that owns status, while granting load serving provision, it is evident that Congress
transmission facilities used predominately to entity status to other similarly situated
support its own water pumping facilities
intended water pumping entities, such
entities. BP points out that Manitoba as DWR, to be on par with load serving
shall have, with respect to the facilities, Hydro had argued that the priority
protections for transmission service entities with respect to protections for
comparable to those provided to load-serving
allocation of long-term firm transmission services. Consequently, we
entities pursuant to this section. transmission rights should extend to clarify that water pumping entities and
entities that, through agreement with a their obligation to provide water related
Id. (emphasis added). DWR argues load serving entity, have ‘‘provided the
that, while the Final Rule clearly services, as described in section 217(g),
transmission required by the load- should be construed as meeting the
intends to implement section 217(g), it serving entity to satisfy its service
does so in an erroneous fashion, by definition of ‘‘service obligation’’ in 18
obligation and agreed to assume CFR 42.1(b)(3), and should be treated as
conflating water pumping facilities— congestion risk.’’ 31 BP states that
which have no electric service load serving entities with service
Manitoba Hydro cited the Commission’s obligations for purposes of the Final
obligation—with load serving entities. assertion that it sought to help ‘‘other
DWR asserts that the Final Rule Rule. This should effectuate
market participants’’ as well as load Congressional intent that water
erroneously states that water pumping
serving entities make new investments pumping entities receive protections for
facilities, which are non-public utilities,
and other long-term power supply transmission service comparable to
already appear to be captured by the
arrangements. BP reiterates Manitoba those provided to load-serving entities.
definition of load serving entity,
Hydro’s example of a load serving entity 25. Next, we deny BP’s request to
‘‘provided of course, that they have a
unable to obtain transmission that construe entities that enter into long-
service obligation.’’ 29 DWR points out
utilizes another party’s transmission term obligations to sell electric energy to
that ‘‘service obligation’’ in the Final
rights in exchange for assumption of the load serving entities that have the
Rule is defined as ‘‘a requirement
congestion risk.32 BP states that option to self supply as load serving
applicable to, or the exercise of
Manitoba Hydro requested the entities. As we stated in the Final Rule
authority granted to, an electric utility
under Federal, State or local law or Commission to ensure that if a market (in the discussion of guideline (5)), we
under long-term contracts to provide participant other than a load serving cannot allow certain entities that do not
electric service to end-users or to a entity has a contractual obligation to a meet the strict definition of load serving
distribution utility.30 DWR argues that load serving entity to provide entity to come under the definition of
this regulatory language makes no transmission rights and to assume load serving entity and, consequently,
mention of the water pumping facilities associated congestion risk, it too should receive priority in allocation of long-
have priority access to long term firm
sroberts on PROD1PC70 with RULES

28 Final Rule at P 45. transmission rights in the same manner 33 Id. at 8 (citing Manitoba Hydro Comments

29 Request for Rehearing/Clarification of DWR at at 3–4).


5 (quoting Final Rule at P 48). 31 Request for Rehearing of BP at 7 (citing 34 Id.

30 Id. at 6 (citing 18 CFR 42.1(b)(3); section Manitoba Hydro Comments at 1). 35 EPAct 2005, Pub. L. No. 109–58, § 1233, 119

217(a)(3) of EPAct). 32 Id. (citing Manitoba Hydro Comments at 3). Stat. at 959.

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00013 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
68444 Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations

term firm transmission rights.36 allocation.38 The load serving entity that the statute’s express references to
Extending the definition as BP requests could sell or otherwise transfer its long- financial transmission rights
would likely defeat the purpose of the term firm transmission rights to its (particularly in section 217(c)), and the
preference, which is to ensure that load supplier. As noted in the Final Rule, a fact that Congress was presumably
serving entities have sufficient generator or any other entity that has a aware of Commission orders finding
protection for transmission service. If, as contract with a load serving entity can such rights equivalent to firm
BP requests, we were to construe a structure its contract with the load transmission rights under Order No.
supplier of a load serving entity, such as serving entity as necessary to attain the 888, imply that Congress viewed these
a generator, to be a load serving entity, desired congestion cost risk sharing.39 existing financial rights as acceptable in
this could lead to a situation where their current form. NYISO also suggests
2. Commission Interpretation of EPAct
multiple load serving entities are that since section 217(b)(4) does not
2005
counting the same load as part of their define ‘‘long-term,’’ it is reasonable to
load serving obligation. 28. In several places in the Final Rule, assume that Congress was aware of the
26. Furthermore, we disagree with the Commission offered interpretations Commission’s pre-existing definition of
BP’s contention that the Final Rule does of new section 217(b)(4) of the FPA and one-year or longer. NYISO also claims
not consistently apply the definition of section 1233(b) of EPAct 2005. In that no legislative history exists to
load serving entity. In the Final Rule, particular, the Commission interpreted support the Commission’s
we construed large industrial customers these provisions as containing two interpretations. Further, NYISO
who self-supply their own load to be separate directives: (1) To exercise its describes as ‘‘unreasonable’’ the
load serving entities for purposes of the authority to facilitate planning and Commission’s ‘‘sweeping’’ inference
Final Rule, in order to ensure expansion of transmission facilities; and that section 1233(b)’s direction to
fulfillment of Congress’s objectives in (2) to enable load serving entities with implement section 217(b)(4) within one
section 217 of the FPA.37 While a large long-term power supply arrangements year amounts to a statement by Congress
industrial customer is not technically a used to meet their load serving that existing transmission organizations
‘‘distribution utility’’ or an ‘‘electric obligations to obtain long-term firm do not meet the requirements.
utility,’’ like a traditional load serving transmission rights. We also interpreted 30. NYISO contends that ‘‘[a] more
entity it provides electricity to serve its these statutes to require, when existing natural reading’’ of section 217(b)(4) is
‘‘load,’’ i.e., its industrial facilities, on capacity is limited, giving a preference that it only requires the Commission to
an ongoing basis from either its own to load serving entities vis-à-vis non- ensure that the financial transmission
generation or through a direct purchase load serving entities to obtain long-term rights offered by transmission
from another generator. Contrary to BP’s firm transmission rights from existing organizations provide load serving
assertion, large industrial customers capacity. Further, we disagreed with entities with a reasonable opportunity to
who self-supply their own load are not interpretations of section 217(c) of the meet their long-term service obligations,
similarly situated to entities, such as FPA suggesting that it immunizes and that the Commission ensure that
generators, with contractual obligations existing market designs and transmission organization planning
to serve load serving entities. Entities transmission rights allocations from the procedures adequately enable load
that enter into long-term obligations to effect of section 217(b)(4) of the FPA. serving entities to meet their reasonable
supply load serving entities are at least Also, we disagreed with contentions needs. In short, NYISO argues, section
one step removed from load serving that transmission organizations already 217(b)(4) leaves open the possibility that
entities, insofar as they have a provide long-term firm transmission transmission organizations already
contractual obligation to serve an entity rights consistent with section 217(b)(4), satisfy its requirements. It contends that
(the load serving entity) that or that this section contained no this reading is more in line with the
subsequently has the service obligation. requirement to offer transmission rights entirety of section 217 than the
Consequently, we deny BP’s request to with longer terms than those that Commission’s reading.
construe as load serving entities those already exist. 31. Further, NYISO asserts that the
entities that enter into long-term Commission’s interpretation of section
obligations to supply load serving Rehearing Requests
217(b)(4) of the FPA as requiring
entities. 29. NYISO argues that the
changes in existing transmission
27. While we reject BP’s requested Commission misinterpreted section
organization market design is erroneous
clarification, we nevertheless emphasize 217(b)(4) of the FPA and section 1233(b)
because it nullifies section 217(c) of that
that, even though suppliers of load of EPAct 2005. First, it contends that the
statute. Section 217(c) provides, in
serving entities are not treated as load Commission read section 217(b)(4) too
pertinent part:
serving entities under the statute, this broadly to establish that the existing
does not mean that they will be financial transmission rights offered by Allocation of Transmission Rights-Nothing
deprived of long-term firm transmission ISO/RTOs do not provide load serving in subsections (b)(1), (b)(2), and (b)(3) of this
section shall affect any existing or future
rights. On the contrary, consistent with entities with sufficient price certainty
methodology employed by a Transmission
section 217 of the FPA, once load and stability over a long enough term. Organization for allocating or auctioning
serving entities have received their NYISO asserts that nothing in section transmission rights if such Transmission
allocated long-term firm transmission 217(b)(4) or section 1233(b) states that Organization was authorized by the
rights, those rights and any additional the rules for existing financial Commission to allocate or auction financial
long-term firm transmission rights transmission rights are not sufficient or transmission rights on its system as of
available from existing system capacity explicitly requires changes to those January 1, 2005, and the Commission
can be offered to such non-load serving rules, and notes section 217(b)(4) in fact determines that any future allocation is just,
entities (as well as other load serving explicitly recognizes that ‘‘tradable’’ or reasonable, and not unduly discriminatory or
sroberts on PROD1PC70 with RULES

preferential. * * *
entities) through a secondary auction, ‘‘financial’’ rights can be equivalent to
bilateral trades or another method of firm transmission rights. NYISO argues 32. NYISO contends that the
Commission’s interpretation of section
36 See Final Rule at P 326. 38 See id. 217(b)(4) effectively reads section 217(c)
37 See id. 39 Id. out of the FPA because it nullifies the

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00014 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations 68445

protections that the latter provision believed the existing transmission rights it leaves open the possibility that
provides for previously-approved offered by transmission organizations transmission organizations already
transmission organization rules with organized electricity markets may comply.41 We disagree with NYISO’s
concerning the auction and allocation of not be of a sufficient length to be ‘‘long- reading that section 217(b)(4) only
transmission rights. As a result of this term’’ and support long-term power requires that we ensure that the current
conflict, NYISO posits, the Commission supply arrangements. Under this financial transmission rights give load
must abandon its premise that section direction, we concluded that the current serving entities a reasonable
217(b)(4) requires modifications to one-year financial rights offered by opportunity to meet their long-term
existing transmission organization transmission organizations, which are service obligations; the statute says
auction and allocation rules.40 subject to financial proration during directly that the Commission must
33. Given what NYISO views as the their term, did not meet the requirement exercise its authority in a manner that
Commission’s incorrect interpretation of of section 217(b)(4) that the Commission ‘‘enables load-serving entities to secure
section 217(b)(4), NYISO argues that the enable load-serving entities to secure firm transmission rights (or equivalent
Commission should revise the Final long-term firm transmission rights to tradable or financial rights) on a long-
Rule to eliminate certain features, support long-term power supply term basis for long-term power supply
including: (1) The requirement that arrangements. As a result, we acted in arrangements made, or planned’’ to
existing transmission capacity be set the Final Rule as directed by Congress meet service obligations.42 This
aside to create new long-term firm in section 1233(b) of EPAct 2005, and language in the statute does not comport
transmission rights different from issued regulations requiring with NYISO’s reading. We agree with
existing transmission rights; (2) the transmission organizations with NYISO, however, that section 217(b)(4)
preference to existing capacity for load- organized electricity markets to make leaves open the possibility that the
serving entities with service obligations; available long-term firm transmission transmission rights offered by an
(3) the prohibition on allocation of long- rights. existing transmission organization
term firm transmission rights by 35. The references to ‘‘equivalent already comply. The regulations
auction; (4) the requirement that long- tradable or financial rights’’ in section adopted in the Final Rule recognize this,
term firm transmission rights ‘‘follow 217(b)(4) and the references to financial in fact, and provide that a transmission
load’’ and that tradable rights be transmission rights in other parts of organization may submit a compliance
‘‘recallable;’’ and (5) any future section 217 do not lead to the filing explaining ‘‘how its current tariff
requirement under the Final Rule that conclusion that the existing financial and rate schedules already provide for
conflicts with section 217(c). Finally, transmission rights offered by long-term firm transmission rights that
NYISO argues that because the transmission organizations are satisfy each of the guidelines’’ set
Commission lacked a statutory mandate sufficient. These references only suggest forth.43 As we have noted elsewhere, the
to modify existing transmission that financial transmission rights can guidelines we adopted in the Final Rule
organization rules for financial satisfy the requirements of the statute if, are intended to ensure that long-term
transmission rights, it could only in this instance, they are sufficiently firm transmission rights will support
require such modifications on the basis long-term and sufficiently firm to long-term power supply arrangements
of substantial evidence under section support long-term power supply used to satisfy native load service
206 of the FPA. The Commission arrangements. This is particularly true obligations, as Congress directed. The
neither built a record to support its under section 217(b)(4), where Congress guidelines and the discussion of them in
requirements nor invoked section 206, referred to financial rights in the Final Rule focus on the current
NYISO concludes. comparison to ‘‘firm transmission short-term transmission rights
rights.’’ Moreover, we again reiterate predominately offered by transmission
Commission Conclusion that if Congress believed the existing organizations, but do not rule out the
34. We deny NYISO’s rehearing financial rights offered by transmission possibility that an existing transmission
request regarding our interpretation of organizations were sufficient, it is organization might currently offer rights
section 217(b)(4) of the FPA and section unclear why Congress would have made that already satisfy the guidelines.
1233(b) of EPAct 2005. NYISO argues such an explicit direction to the 37. NYISO also asserts that our
first that nothing in section 217(b)(4) or Commission to act within one year in reading of section 217(b)(4) nullifies
section 1233 states that existing transmission organizations with section 217(c). We disagree. First, we
transmission organizations’ financial organized electricity markets. Likewise, must reiterate that section 217(c)
transmission rights are deficient. While with regard to NYISO’s argument that expressly, and quite starkly, omits
NYISO is correct that these sections do Congress was surely aware of the reference to section 217(b)(4), while
not explicitly declare that existing Commission’s existing definition of referencing all other provisions of
transmission rights are insufficient, ‘‘long-term,’’ we are unclear why section 217(b). This express omission
Congress did direct explicitly that the Congress would have acted in the strongly suggests that Congress did not
Commission implement section manner it did and with specific intend for the protections of section
217(b)(4) within one year in direction to the Commission if it 217(c) to trump implementation of
transmission organizations with believed all the current transmission section 217(b)(4). Further, the Final
organized electricity markets. As we organizations offered sufficient Rule does not require that transmission
reasoned in the Final Rule, this explicit transmission rights to meet the organizations ignore the protections of
direction to a specific segment of the requirements of section 217(b)(4). section 217(c) or any other part of
industry strongly suggests that Congress 36. NYISO posits that a better reading section 217 when implementing section
of the statute at issue here is that it 217(b)(4), and repeatedly states the
40 NYISO notes that abandoning this ‘‘requires the Commission to ensure that Commission’s belief that section
sroberts on PROD1PC70 with RULES

interpretation would not nullify section 217(b)(4), the rules governing financial rights in 217(b)(4) can be implemented within
as some have claimed, because that section would [transmission organization] markets
still require the Commission to assess whether
transmission organizations were fulfilling their
provide [load serving entities] with a 41 Request for Rehearing of NYISO at 7–8.
planning obligations and adequately supporting reasonable opportunity to meet their 42 Pub.L. No. 109–58, § 1233, 119 Stat. 594, 958.
long-term power supply arrangements. ‘long-term’ service obligation,’’ and that 43 18 CFR 42.1(c)(1)(ii) (2006).

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00015 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
68446 Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations

existing allocation and auction 3. Seams Issues comments received, that transmission
mechanisms. The Final Rule 39. In the Final Rule, the Commission organizations would consider both types
appropriately recognizes, however, addressed comments on the NOPR that of potential seams. As we stated in the
Congress’s decision, in enacting section noted the potential for the flexible Final Rule, in both cases, transmission
217, to omit reference to section approach proposed by the Commission organizations should, in particular,
217(b)(4) when providing the to create seams issues both between explain how their proposals address
protections of section 217(c). As a transmission organizations, as well as seams issues with regard to the term of
result, we explained in the Final Rule between transmission organization the long-term rights offered and the
that if implementing long-term firm regions and non-transmission procedures and timelines for obtaining
transmission rights cannot be organization regions. The Commission such rights.47
accomplished without changes to agreed with commenters that 4. Full Funding of Long-Term Firm
existing allocation or auction transmission organizations should Transmission Rights
methodologies, section 217(c) does not consider these issues when complying
bar such changes. with the Final Rule, and directed each 42. As adopted in the Final Rule,
transmission organization to explain in guideline (2) provides in part that ‘‘once
38. For all of these reasons, we believe allocated, the financial coverage
our interpretation of section 217(b)(4) of its compliance filing how its proposal
addresses potential seams issues, provided by a financial long-term
the FPA is reasonable and comports transmission right should not be
particularly with regard to the term of
with Congress’s intent. Accordingly, we modified during its term (the full
the long-term rights offered and the
will not modify or eliminate the features funding requirement) except in the case
procedures and timelines for obtaining
identified by NYISO as conflicting with of extraordinary circumstances or
such rights.45 Concerning potential
its interpretation of the statute. through voluntary agreement of both the
seams between transmission
Moreover, we reject NYISO’s claim that organizations, the Commission directed holder of the right and the transmission
we have not acted in accordance with each transmission organization to organization.’’ 48 We determined that
the FPA in requiring transmission explain why it has or has not elected to the full funding requirement was
organizations to comply with the Final revise any seams agreement it has with necessary to satisfy Congress’ directive
Rule. Contrary to NYISO’s claim, the another transmission organization.46 in section 217(b)(4) that load serving
Commission is not overturning its entities with service obligations be able
existing precedents accepting Request for Rehearing to obtain ‘‘firm’’ transmission rights or
transmission organization allocation 40. APPA notes that the Commission, their equivalent on a long-term basis.49
and auction rules. Instead, we are in requiring transmission organizations We explained that full funding provided
requiring, consistent with the dictates of to address potential seams issues in one aspect of such firmness, increased
section 217(b)(4) of the FPA and section their compliance filings, primarily certainty in the revenue stream from the
1233(b) of EPAct 2005, that discusses seams between transmission rights over time. The Final Rule did not
transmission organizations offer long- organizations, within the context of require a particular method to provide
term firm transmission rights. The Final existing seams agreements between for full funding, thus allowing
Rule explains why certain existing transmission organizations. It states that transmission organizations and their
transmission organization rules for the Commission, in an apparent stakeholders discretion to determine
allocating transmission rights may not unintended oversight, makes no methods appropriate to regional
be compatible with long-term rights, but mention of seams issues arising between circumstances.50 However, we did note
does not find those rules (or the short- transmission organizations and non- that certain approaches could lead to
term rights that are currently available) transmission organizations. It asks the unreasonable outcomes, and we
unjust and unreasonable. It simply Commission to explicitly require discussed those approaches.51
explains what it will take to comply transmission organizations, in their
compliance filings, to address seams Requests for Rehearing and/or
with section 217(b)(4), now included in Clarification
the FPA (which it was not when the issues between transmission
current rules were approved), and organizations and non-transmission 43. Midwest TOs argue that the
establishes guidelines to ensure that organizations on their borders, in Commission erred first by interpreting
long-term firm transmission rights have addition to addressing seams between section 217(b)(4) to require that long-
properties that will allow them to neighboring transmission organizations. term firm transmission rights be fully
support long-term power supply funded, and second by then suggesting
Commission Conclusion
arrangements used to satisfy service that allocation of uplift to support full
41. In response to APPA’s seams funding could be done in ways that, in
obligations, as section 217(b)(4)
concerns, we clarify that each their view, violate cost causation
requires. Finally, we reiterate, as noted
transmission organization should principles. On the first issue, Midwest
above, that under the regulations
explain in its compliance filing how its TOs make several arguments. First,
adopted in the Final Rule, a proposal addresses potential seams
transmission organization may seek to Midwest TOs assert that the
issues between itself and neighboring Commission has not justified its
support its current allocation and non-transmission organization
auction rules as satisfying each of the interpretation of section 217(b)(4) as
transmission providers, as well as requiring full funding. Midwest TOs
guidelines in the Final Rule. The between itself and neighboring
regulations specifically allow a argue that the statutory language does
transmission organizations. While our not provide ‘‘absolute guarantees’’ for
transmission organization to explain discussion in the Final Rule focused in
‘‘how its current tariff and rate long-term firm transmission rights, but
particular on existing seams agreements
sroberts on PROD1PC70 with RULES

schedules already provide for long-term between transmission organizations, it 47 Id.


firm transmission rights that satisfy each was our intent, consistent with the 48 Id. at P 169.
of the guidelines’’ set forth.44 49 Id. at P 170.
45 Final Rule at P 107. 50 Id. at P 175.
44 Id. 46 Id. 51 See id. at P 171, 176–77.

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00016 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations 68447

provides instead for ‘‘reasonable needs,’’ preferences or competitive advantages. such rights. Indeed, we expressly noted
which suggests no guarantee of full As a result, BP argues that the that such rights may command a
funding.52 Second, the Commission Commission acted arbitrarily and premium.57 Midwest TOs argue that we
concluded in the Final Rule that full capriciously and failed to engage in did not explain why we did not require
funding would assist in financing of reasoned decision-making by failing to additional payment for long-term rights,
generation investments,53 but Midwest mandate explicitly that stakeholders since, according to them, requiring such
TOs argue that there are other means of follow the Commission’s methodologies a premium would be consistent with
assisting in financing, such as for full funding of firm transmission cost causation. We conclude, however,
consumers hedging risks. Also, Midwest rights. BP asserts that, in the event that that requiring a premium may or may
TOs posit, the Final Rule provides no the Commission fails to grant its not be consistent with cost causation,
evidence that full funding is necessary requested clarifications, the depending on the source and scope of
to obtain financing. Third, Midwest TOs Commission erred in its Final Rule. the revenue insufficiency. For example,
insist that the Final Rule does not it would not be consistent with cost
Commission Conclusion
adequately address the potential causation principles to require load
negative incentives from full funding. 46. We disagree with Midwest TOs’ serving entities that hold long-term
Nor, in their opinion, does the Final assertion that the Commission rights to pay a premium to cover
Rule adequately reflect the difficulties incorrectly interpreted section 217(b)(4) revenue insufficiency caused by another
in planning for full funding of the rights to require full funding. As we noted in utility, such as by a transmission owner
over the long-term. Fourth, Midwest the Final Rule, while section 217(b)(4) that does not adequately maintain its
TOs argue that the full funding does not explicitly use the term ‘‘full transmission system. For this reason, we
requirement runs contrary to principles funding,’’ it does state that the long-term chose not to simply impose a blanket
of hedging energy costs, which are transmission rights must be firm.54 We premium payment requirement, but
reflected in LMP-based congestion considered what the equivalent of the rather pointed out that there could be
prices, and which require parties to pay term ‘‘firm’’ (in a physical rights justification for imposing such a
for a hedge. Midwest TOs state that the context) would mean in the context of premium, based on stakeholder
Final Rule did not explain why holders the financial transmission rights found agreement and consistency with
of long-term rights should not, therefore, in organized electricity markets, and regional preferences for transmission
be required to pay a premium for the found that it corresponded to (a) the pricing.58
rights. expectation that once allocated, the 48. Finally, with regard to Midwest
44. The Midwest TOs’ second general quantity of rights allocated would TOs’ concern that parties holding short-
argument is that the Final Rule violates remain constant for the term of the right, term rights could be unfairly exposed to
principles of cost causation because it and (b) the expectation that, once uplift charges that support full funding
does not also require full funding of assigned or acquired, transmission for long-term rights if both types of
short-term rights, and because it appears rights do not experience volatility in the rights are not put on equal footing with
to endorse the prospect that holders of actual financial coverage that they regard to full funding, we agree that,
long-term rights would not always be provide relative to congestion charges under some conditions, such concerns
fully responsible for all uplift charges associated with the same points of may be justified. This is one reason why
associated with full funding. Hence, injection and withdrawal (although in the Final Rule we encourage
holders of short-term rights could be there might be some volatility extension of full funding to both types
required to pay uplift to support full experienced in the uplift charges that of rights, even though section 217(b)(4)
funding of long-term rights that they do support full funding).55 Midwest TOs does not require it.59 Because section
not benefit from. This creates a have not offered an alternative 217(b)(4) and this rulemaking concern
substantial potential future exposure, as interpretation of section 217(b)(4)’s long-term transmission rights, however,
it is difficult to accurately project events requirement that the rights be firm. we believe this issue falls outside the
over the long term. Instead, they focus on section scope of this proceeding. Moreover,
45. BP supports full funding of long- 217(b)(4)’s requirement of ‘‘reasonable Midwest TOs have failed to capture in
term firm transmission rights and needs.’’ We have interpreted that their argument the fact that the Final
suggests that the methodology for such requirement in the Final Rule as Rule explicitly recognizes that the
funding should be set by stakeholder pertaining to the quantity of long-term question of fair allocation of full
groups. It also supports extension of full rights that a load-serving entity is funding uplift is a matter of degree, and
funding to short-term transmission entitled to receive, rather than relating hence must be evaluated by the
rights. However, it seeks clarification to their firmness.56 Hence, Midwest TOs Commission on a case-by-case basis.60
that the Commission’s findings in the have not provided an alternative While we did state that if only a small
Final Rule—that full funding of both interpretation of section 217(b)(4) that group of load serving entities holds
durations of firm transmission rights is considers both statutory requirements— long-term rights, assigning the full
permissible under the law, and that any firmness and reasonable needs—and we funding uplift directly to them would
shortfall should be uplifted to all firm do not find their argument sufficiently largely undercut the requirement of full
transmission rights holders—set a persuasive to merit granting rehearing funding,61 we also stated that ‘‘if most
baseline for what is fair, equitable, and and eliminating the full funding load serving entities in a region opted
nondiscriminatory, and that anything requirement. for long-term rights (up to their
less is impermissible and will be 47. Next, we disagree with Midwest eligibility), then the distribution of
rejected by the Commission. BP is TOs’ assertion that we did not consider uplift charges over the set of rights
particularly concerned that, due to the prospect of having parties that are holders would have a lesser impact and
biases in the stakeholder processes, any allocated long-term rights pay more for
sroberts on PROD1PC70 with RULES

uplift rules for full funding not result in 57 See id. at P 172.
outcomes that create subsidies, 54 Id. at P 170. 58 Id.

55 Id. 59 Id.at P 179.


52 Request for Rehearing of Midwest TOs at 7. 56 See 60 See id. at P 171–173.
id. at P 323 (discussing guideline (5)); see
53 See Final Rule at P 171. also id. at P 273 and 318. 61 See Final Rule at P 177.

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00017 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
68448 Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations

could be reasonable from all parties’ allocation methods. Furthermore, our 53. We noted that, as adopted,
perspective.’’ 62 Therefore, to know discussion of various options for guideline (5) neither requires nor
whether the full funding requirement allocating any uplift necessary to prohibits the consideration of power
would lead to unreasonable cost-shifts support full funding was not intended supply arrangements in determining the
unrelated to cost causation, we would to set a baseline for what the allocation priority for long-term firm
need to know, among other factors, Commission will find just and transmission rights; it only requires that
whether the organized market has opted reasonable, as BP suggests in its load serving entities have priority over
to cover both short- and long-term rights clarification request; our discussion was non-load serving entities. In this regard,
with full funding, and whether the size only intended to be illustrative of some we noted that the transmission
of the set of load serving entities of the options and the issues associated organizations must make long-term firm
expected to request long-term rights is with those options. transmission rights available to all
sufficient to restrict full funding uplift 50. Regarding concerns about biases market participants; the priority
to that set. For that reason, we reject in the stakeholder processes, as we established by guideline (5) serves only
Midwest TOs argument that the stated in the Final Rule, addressing any as a ‘‘tiebreaker’’ between load serving
provisions of the Final Rule inherently such alleged flaws in these processes is entities and non-load serving entities
violate cost causation principles and outside the scope of this rule.66 when existing transmission capacity is
deny rehearing of our determination 5. Allocation Priority for Load Serving limited. We also noted that eliminating
that we must evaluate each compliance Entities With Long-Term Power Supply the priority for load serving entities
filing on a case-by-case basis. Arrangements with long-term power supply
49. With respect to BP’s request, we arrangements makes it possible for the
disagree with its suggestion that the 51. Guideline (5), as proposed in the transmission organization to propose an
Final Rule did not state that the NOPR, stated that load serving entities allocation method that requires neither
allocation of uplift to support full with long-term power supply
the transmission organization nor the
funding should be just and reasonable arrangements to meet a service
load serving entity to verify that the
and nondiscriminatory. First, obligation must have priority over
load serving entity holds a qualifying
transmission organizations are required existing transmission capacity that
long-term power supply arrangement.
to make compliance filings to supports long-term firm transmission
rights requested to hedge such 54. We noted that, because of
implement the guidelines set forth in
arrangements. However, in the Final uncertainty regarding load growth,
the Final Rule, and there are legal
Rule, we revised this guideline to changes in power flows and other
criteria—including, importantly the just
eliminate the preference for load serving factors, the transmission organization
and reasonable standard—for approving
entities with long-term power supply may be reluctant to commit all of its
any compliance filing that comes before
arrangements and replaced it with a existing capacity to long-term firm
the Commission. Moreover, in the Final
general preference for load serving transmission rights. Also, commenters
Rule, we mentioned these requirements
several times. For example, we noted entities vis-à-vis non-load serving suggested that the principal need for
that for the allocation of uplift costs to entities. We also revised the guideline to long-term firm transmission rights is to
support full funding, ‘‘certain options allow the transmission organization to support long-term power supply
proposed by commenters could result in place reasonable limits on the amount of arrangements for base load generation,
unreasonable outcomes’’ and then existing transmission capacity that it not peaking or intermediate generation.
proceeded to evaluate some alternatives will make available for long-term firm Therefore, we concluded that the
in light of those concerns.63 We also transmission rights. transmission organization and its
stated that applying the full funding 52. In the Final Rule, we concluded stakeholders should have flexibility to
requirement to short-term rights as well that, although section 217(b)(4) of the determine the level at which a load
as long-term rights would be a FPA would support a preference for serving entity may nominate long-term
‘‘potentially reasonable approach,’’ with load serving entities with long-term firm transmission rights, as long as that
the implication that such a proposal power supply arrangements, it should level does not fall below the ‘‘reasonable
could be approved by the Commission not be construed to require that a needs’’ of the load serving entity.
as just and reasonable.64 Further, we preference be given to this class of load Rehearing Requests
concluded that, with respect to serving entities at the expense of load
allocation of such uplift to transmission serving entities that prefer short-term 55. The CPUC, TAPS and APPA state
owners, ‘‘the Commission will allow power supply arrangements, or are that the Commission erred in revising
regional discretion on these options and precluded from entering into long-term guideline (5) to eliminate the preference
will examine the reasonableness of such arrangements. We stated that a broader for load serving entities with long-term
proposals on a case-by-case basis.’’ 65 preference for load serving entities in power supply arrangements in the
Hence, we believe that we provided general vis-à-vis non-load serving allocation of long-term firm
sufficiently explicit criteria short of entities is fully supported by the statute transmission rights and to replace it
enumerating every possible uplift and better meets the needs of today’s with a general preference for load
allocation method and considering how organized electricity markets. Indeed, serving entities vis-à-vis non-load
they might be adapted to the existing we stated that we did not believe that serving entities. TAPS and APPA also
market designs in the organized Congress intended to disadvantage state that the Commission erred in
markets. Also, we believe that it is entities that prefer short-term power finding that although section 217(b)(4)
sufficiently clear that a reasonableness supply arrangements when it enacted supports a preference for load serving
standard is incorporated into our section 217 of the FPA, particularly entities with long-term power supply
criteria for evaluating possible uplift given the statute’s overall focus on arrangements in the allocation of long-
sroberts on PROD1PC70 with RULES

protecting the transmission rights of term firm transmission rights, ‘‘a


62 Id. load serving entities with service broader preference for load serving
63 See Final Rule at P 175. obligations. entities in general vis-à-vis non-load
64 Id. at P 177. serving entities is fully supported by the
65 Id. at P 178. 66 Id. at P 106. statute and indeed better meets the

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00018 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations 68449

needs of today’s organized electricity term firm transmission rights with precluded from entering into long-term
markets.’’ 67 sources and sinks related to the arrangements.’’ 68 However, APPA
56. The CPUC requests rehearing of resources and loads that are part of the concludes that given the express
the Final Rule’s elimination of priority load serving entity’s long-term power language of FPA section 217(b)(4), it is
for load serving entities with long-term supply arrangements. As an alternative, difficult to argue, as a legal matter, that
power supply arrangements because, in TAPS states that the same result could any such discrimination is undue.
the CPUC’s view, it is contrary to EPAct be achieved by modifying guideline (1) 62. APPA argues that, if load serving
2005 and violates the FPA. The CPUC to clarify that the sources and sinks of entities that wish to enter into new long-
claims that, by allowing load serving any long-term firm transmission rights term power supply arrangements cannot
entities that do not have any obligation allocated under the Final Rule must be fully hedge with long-term firm
or contract to serve load to be allocated related to the resources and loads of the transmission rights the substantial risks
long-term firm transmission rights, the long-term power supply arrangements of of transmission congestion costs
Final Rule prevents load serving entities the requesting load serving entity, associated with their new long-term
with contracts or statutory obligations to whether in the transmission base load and renewable generation
serve load from being allocated those organization awarding the long-term resources, many of them will not be able
transmission rights. In the CPUC’s view, firm transmission right or its neighbor. to obtain the financing and bond ratings
such a result directly contradicts the 60. Second, TAPS states that required to support such projects. APPA
Commission’s duties under section guideline (5) and/or guideline (1) could adds that, if the Commission is
217(b)(4) of the FPA. be modified to restore the connection concerned about the ability of load
57. TAPS asserts that guideline (5) between long-term firm transmission serving entities to obtain long-term firm
and/or guideline (1) should be modified rights under the Final Rule and the transmission rights vis-à-vis non-load
to restore the connection between long- specific resources and loads of the load serving entities, it could specify on
term firm transmission rights allocated serving entity, but without requiring a rehearing that if there are insufficient
under the Final Rule and the specific long-term power supply arrangement to long-term firm transmission rights to
resources and loads of load serving qualify for a long-term firm transmission meet all requests, transmission
entities that seek such rights. TAPS right. At a minimum, TAPS states that organizations could distribute long-term
argues that, if the Commission were guideline (5) must be modified to limit firm transmission rights first to load
correct that the change in priority will the priority to load serving entities with serving entities that show such long-
not significantly affect load serving load located at the long-term firm term firm transmission rights would be
entities with long-term power supply transmission right sink (or, if the sink is used to support existing and new long-
arrangements, then there would be no a transmission organization border, on term power supply obligations needed
need for the Commission to eliminate the opposite side of the border). TAPS to meet their service obligations, then to
the NOPR’s proposed priority. Instead, argues that, although this solution does other load serving entities, and finally to
that priority could simply be not satisfy the full mandate of section non-load serving entities.
supplemented with a second-tier 217(b)(4), it does tie long-term firm 63. APPA also states that, because the
priority for load serving entities that transmission rights to the load serving Commission has expanded the universe
prefer to rely on short-term transactions entity service obligations that the statute of load serving entities eligible for long-
vis-à-vis non-load serving entities. was designed to protect. term firm transmission rights on a
58. TAPS adds that, in broadening the 61. APPA states that, with regard to preferred basis, its corollary decision to
language of guideline (5), the requiring a preference for load serving allow a transmission organization and
Commission has decoupled the entities with long-term power supply its stakeholders to place ‘‘reasonable
guideline’s priority from any specific arrangements, the statute could not be limits on the amount of existing
power supply arrangement, long-or clearer: the Commission is to exercise transmission capacity that it will make
short-term, and from the load serving its authority to enable load serving available’’ for long-term firm
entity’s obligation to serve load. TAPS entities to secure long-term firm transmission rights could unduly
states that, as adopted, guideline (5) transmission rights ‘‘for long-term discriminate against load serving
would allow load serving entities to power supply arrangements.’’ APPA entities with long-term power supply
nominate long-term firm transmission argues that the first two rationales that arrangements, and endanger their ability
rights completely unrelated to their the Commission cites for its decision to to obtain sufficient long-term firm
loads and power supply arrangements expand the class to all load serving transmission right allocations to support
and to use a generic load serving entity entities (i.e., avoiding the disruption of those arrangements. In addition, APPA
priority to obtain first preference to current firm transmission right is concerned that, given the strategic
those long-term firm transmission allocation mechanisms and obviating nomination and gaming activity that it
rights. TAPS claims that a load serving the need for transmission organizations claims now occurs in the current
entity that is located in a load pocket to verify the long-term power supply distributions of firm transmission rights,
and needs long-term firm transmission arrangements of load serving entities) the same problems will appear in the
rights to hedge the long-term power both are arguments of administrative distributions of long-term firm
supply arrangements it uses to meet its convenience. However, APPA asserts transmission rights.
service obligation could be crowded out that administrative convenience must 64. APPA concludes that the
by speculators attracted to the financial give way to implementation of Commission must reinstate in guideline
value of long-term firm transmission Congressional intent. According to (5) the preference for load serving
rights over the constrained interface. APPA, this leaves the Commission with entities with long-term power supply
59. TAPS states that there are several only its third rationale for revising arrangements needed to support their
ways to remedy this problem. First, guideline (5): That granting a preference service obligations, or at least take
sroberts on PROD1PC70 with RULES

TAPS’ preferred solution is to modify only to load serving entities with long- concrete steps to assure that load
the first sentence of guideline (5) to give term power supply arrangements would serving entities with such arrangements
priority to load serving entities for long- discriminate unduly against other load get the long-term firm transmission
serving entities that ‘‘prefer short-term
67 Final Rule at P 319. power supply arrangements, or are 68 Final Rule at P 322.

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00019 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
68450 Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations

rights they need. According to APPA, term basis for long-term power supply reasonable and not unduly
among the possible ways the arrangements made, or planned, to discriminatory,71 the Commission chose
Commission could do this would be to meet’’ service obligations.69 This in the Final Rule to adopt a broader
require load serving entities seeking language requires the Commission to preference in guideline (5). We
long-term firm transmission rights to enable load serving entities to secure a conclude that this approach will ensure
demonstrate that they: (1) will indeed reasonable amount of long-term firm just and reasonable outcomes for all
serve load at the delivery points covered transmission rights that will support users of the grid.
by their long-term firm transmission long-term power supply arrangements to 68. Second, we note that, historically,
rights and have power supplies meet their service obligations. We the cost of constructing and maintaining
committed to them at the requested satisfied this directive by adopting the grid has largely been borne by load
receipt points; and (2) have an guidelines in the Final Rule that require serving entities on an equitable basis
obligation to pay the embedded costs of each transmission organization with an without regard to the term of their
their transmission provider’s system, organized electricity market to design power supply arrangements. It is
thus signaling their commitment to pay and offer to customers long-term firm primarily for this reason that we believe
their allocated share of the transmission transmission rights with basic each load serving entity is entitled to an
system’s fixed costs. properties that will support specific equitable allocation of the firm
long-term power supply arrangements. transmission rights, whether short-term
Commission Conclusion or long-term, that are supported by
These basic properties include, but are
65. We deny the rehearing requests of not limited to, the specification of existing capacity.
the CPUC, TAPS and APPA to reinstate source, sink and MW quantity 69. We agree with APPA that the issue
in guideline (5) a preference for load (guideline 1), full funding (guideline 2), of priority takes on greater significance
serving entities with long-term power and sufficient term length (guideline 4). if the transmission organization
supply arrangements in the allocation of Guideline (5) is a measure to ensure that determines that, because of load growth
long-term firm transmission rights. We where existing transmission capacity is uncertainty and other factors, it must
retain the preference for load serving scarce, load serving entities will have limit the amount of existing
entities vis-à-vis non-load serving priority over non-load serving entities to transmission capacity that is committed
entities as adopted in the Final Rule. We secure long-term firm transmission to long-term firm transmission rights, as
reiterate that, in our view, a broader rights to satisfy their service obligations, guideline (5) permits it to do. However,
preference for load serving entities in as Congress intended. The language in the fact that a transmission organization
general vis-à-vis non-load serving new section 217(b)(4) 70 is sufficiently must limit the availability of long-term
entities is fully supported by the statute broad that it does not require, and does firm transmission rights in this manner
and will achieve the statute’s purposes. not prohibit, a narrower preference (like does not undermine our decision to
This feature of guideline (5), taken that proposed in the NOPR) for load provide a broader preference for load
together with the other guidelines in the serving entities with specific long-term serving entities vis-à-vis non-load
Final Rule, will enable load serving power supply arrangements, either serving entities. Indeed, as long as each
entities to obtain long-term firm made or planned. load serving entity receives a
transmission rights for long-term power 67. We believe that, as compared to ‘‘reasonable’’ allocation of long-term
supply arrangements to meet their the narrower preference proposed in the firm transmission rights (for example, a
service obligations, as section 217(b)(4) NOPR, the broader preference will quantity sufficient to hedge the load
requires. However, as explained below, equally enable load serving entities to serving entity’s needs at its base load
we clarify that, in cases where the obtain long-term firm transmission level), it arguably is receiving its fair
transmission organization must limit the rights to support long-term power share of long-term firm transmission
amount of existing capacity available for supply arrangements, while also taking rights, based on its historical cost
long-term firm transmission rights to a into account the countervailing responsibility.
level that cannot support the considerations discussed in the Final 70. While the Commission expects
‘‘reasonable needs’’ of all load serving Rule. These considerations include the that, in general, the transmission
entities, guideline (5) allows the burden on transmission providers to organization will be able to allocate
transmission organization to give verify long-term power supply sufficient long-term firm transmission
priority to load serving entities with arrangements, the potential for rights to hedge power supply
long-term power supply arrangements discrimination against load serving arrangements used to meet base load, a
in allocating the scarce capacity. entities that are prohibited from transmission system may temporarily
66. First, in response to TAPS’ and entering into long-term power supply not have enough capacity to provide
APPA’s argument that the Final Rule arrangements, and the need to simultaneously feasible, long-term firm
does not satisfy the mandate of section accommodate load serving entities in transmission rights to all load serving
217(b)(4) of the FPA, as we stated in the retail access jurisdictions. entities at this level. In such instances,
Final Rule, while this section can be Consequently, given new section a procedure is needed to allocate the
read to support a preference for load 217(b)(4)’s relatively flexible statutory scarce long-term firm transmission
serving entities with long-term power language, the countervailing rights among load serving entities. We
supply arrangements, it does not require considerations noted above, and the clarify that, in these circumstances,
that a preference be given to this class broader mandate of the FPA (under guideline (5) allows the transmission
of load serving entities at the expense of which we are required to implement organization to propose an allocation
those that prefer short-term power section 217(b)(4)) to ensure that rule that gives priority to load serving
supply arrangements. New section jurisdictional rates and services are just, entities with longer-term power supply
217(b)(4) of the FPA requires the arrangements to meet a service
sroberts on PROD1PC70 with RULES

Commission to exercise its authority 69 Pub. L. No. 109–58, § 1233, 119 Stat. 594, 958. obligation.72 In this regard, we note the
under the FPA ‘‘in a manner that * * * 70 E.g.,id. (‘‘* * * and enables load-serving methods currently used by some
enables load-serving entities to secure entities to secure firm transmission rights * * * on
a long-term basis for long-term power supply
firm transmission rights (or equivalent arrangements made, or planned, to meet such 71 16 U.S.C. 824d and 824e (2000).
tradable or financial rights) on a long- needs’’) (emphasis added). 72 See Final Rule at P 321.

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00020 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations 68451

transmission organizations for the initial 6. Allocation Priority for Load Serving especially at risk from this decision.
allocation of short-term firm Entities With Loads Outside the TAPS argues that restricting priority
transmission rights take explicit account Transmission Organization’s Boundaries access to long-term firm transmission
of a load serving entity’s current or 73. In the Final Rule, we stated that rights based on the transmission
historical loads and power supply long-term firm transmission rights organization’s footprint is unfair, given
arrangements. We believe that such should be made available first to those that it is the host transmission
methods offer a reasonable and entities that have an obligation to serve organization, not the transmission
appropriate solution to the problem of load within the transmission dependent utility, that makes decisions
allocating scarce long-term firm organization’s service territory and are about whether to join a transmission
transmission rights when the base load required to contribute to the embedded organization or whether to withdraw.
needs of all load serving entities cannot cost of the transmission organization’s TAPS states that it will also exacerbate
otherwise be met. Indeed, although we transmission system. We concluded that problems created by present and future
are providing flexibility to each any entity that has neither an obligation transmission organization seams,
transmission organization to propose to serve load on the transmission undermining, for example, the
allocation rules that are appropriate for organization’s transmission system, nor Commission’s efforts to foster a joint
its region, we expect that such rules will an obligation to pay the embedded costs and common market between PJM and
include adequate protections for load of that system, should not be given a MISO. TAPS concludes that the
serving entities with long-term power preference to acquire long-term firm Commission’s decision to exclude load
supply arrangements. transmission rights supported by the serving entities located outside the
71. In response to APPA’s argument system’s existing capacity. transmission organization from the
priority of guideline (5) should be
that guideline (5) would permit the Rehearing Requests reversed, and that an exception to the
same gaming activity that allegedly
74. APPA and TAPS state that the obligation to support the fixed cost of
occurs in the distribution of firm
Commission erred in holding that load the transmission organization issuing
transmission rights, the Commission
serving entities with long-term power the long-term firm transmission right
noted in the Final Rule that tying the supply arrangements, but with loads should be made where the Commission
allocation of long-term firm that sink outside a transmission has authorized elimination of pancaked
transmission rights to long-term power organization’s boundaries, should not be rates between transmission
supply arrangements could itself given any preference in the allocation of organizations (or transmission
influence market behavior long-term firm transmission rights organizations and adjacent utility
inappropriately. In particular, such a supported by the transmission control areas), as in the case of PJM and
priority may induce load serving organization’s existing transmission MISO.
entities to bias their supply portfolio capacity. In APPA’s view, it would be
unduly in favor of long-term power 76. Modesto also requests that the
unduly discriminatory to favor, in the
supply contracts (or, perhaps, enter into Commission clarify that load-serving
distribution of long-term firm
sham contracts) simply because they are entities will receive priority over long-
transmission rights, load serving entities
advantageous in the FTR allocation. term firm transmission rights if such
with loads sinking on the transmission
entities contribute to the embedded cost
72. In response to TAPS’ argument organization’s transmission system over
of the transmission organization’s
that guideline (5) would allow load load serving entities serving loads
transmission rates or have an obligation
serving entities to nominate long-term elsewhere. APPA asserts that FPA
to serve load within the control area of
firm transmission rights unrelated to section 217(b)(4) says nothing about
the transmission organization. Modesto
their loads and that speculators will where the loads of a particular load
argues that the language of the EPAct
crowd out others over constrained serving entity must be located, so long
2005 does not limit allocation of long-
paths, we note that most transmission as the load serving entity has long-term
power supply arrangements to meet a term firm transmission rights to load-
organizations now limit the flexibility serving entities located within the
that a load serving entity has to service obligation to those loads. APPA
states that if a load serving entity is control area of a transmission
nominate firm transmission rights on organization. In Modesto’s view, the
valuable transmission paths when those obligated to pay the embedded
transmission system fixed costs of the extension of the logic in the language of
paths do not include historical EPAct 2005 would not support
resources and loads of the load serving transmission organization from which it
obtains a long-term firm transmission distinctions among load-serving entities
entity. We expect that similar rules will along the lines indicated in the Final
be developed for long-term firm right under that transmission
organization’s Commission-approved Rule.
transmission rights. Also, the
rate design, and uses that long-term firm 77. SMUD asserts that the Final Rule
Commission expects that the entities
transmission right to support a long- properly concluded that transmission
that are most likely to be speculators
term power supply agreement needed to organizations must offer long-term
will be those that do not have a service
meet its service obligation to its own service to ‘‘all load serving entities that
obligation and, therefore, will not be
loads, then that should be sufficient to support the embedded costs of the
entitled to a preference under guideline
qualify for the preference. transmission system.’’ 73 SMUD asks the
(5).
75. TAPS asserts that priority should Commission to clarify that long-term
If it becomes apparent that load not be limited to load serving entities firm transmission service must be made
serving entities with long-term power within the transmission organization’s available whether or not the customer
supply arrangements are being crowded footprint. In TAPS’ view, transmission agrees to turn control of its transmission
sroberts on PROD1PC70 with RULES

out of the allocation of long-term firm dependent utilities, many of whom have facilities over to the transmission
transmission rights, or if a compliance loads and resources split between organization.
filing reveals the potential for such an transmission organizations and between
outcome, the Commission will take transmission organization and non- 73 SMUD Rehearing Request at 2 (citing Final

appropriate steps to address the issue. transmission organization regions, are Rule at P 321) (emphasis added by SMUD).

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00021 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
68452 Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations

Commission Conclusion whether a customer is located in the preferential access to additional long-
78. The Commission denies rehearing transmission organization’s control area term firm transmission rights would
on this issue. A load serving entity is or has agreed to cede control of its give it a windfall without serving any
entitled to a preference in the allocation transmission facilities to that useful policy purpose. NYISO states
of long-term firm transmission rights organization. Indeed, we have found in that, if the Commission denies the
within a transmission organization’s prior orders that, in allocating firm requested clarification, it should grant
region only to the extent that the transmission rights, it is not rehearing because granting additional
transmission organization plans and discriminatory for a transmission long-term firm transmission right
constructs its transmission system to organization to impose additional preferences would go beyond the Final
support the load of the load serving requirements on customers external to Rule’s stated goals.
the transmission organization’s control 84. Second, NYISO states that the
entity, and the load serving entity
area (external load) as a precondition to Commission should clarify that
contributes to the cost that the
receiving such rights.74 We decline, in transmission organizations may
transmission organization incurs for that
this rulemaking of general applicability, consider both the need to support state
purpose. It would be unreasonable to
to draw a broad conclusion that it may retail access programs and market
require a transmission organization to
never be reasonable to treat external participants’ desire for access to shorter-
provide a load serving entity with a
load differently from internal load for term transmission rights when deciding
preference in the allocation of firm
purposes of allocation of long-term firm what constitutes a ‘‘reasonable’’ amount
transmission rights for specific loads,
transmission rights. of existing transmission capacity to set
either long-term or short-term, when the
transmission organization has not 7. Miscellaneous Issues Regarding the aside for long-term firm transmission
planned and constructed its system to Allocation of Long-Term Firm rights. In the alternative, NYISO asks
accommodate those loads, and when the Transmission Rights the Commission to grant rehearing
loads have not contributed to the because it has not offered a reasoned
82. In the Final Rule, we noted that
system’s embedded costs. explanation of its reasons for
specifying and allocating long-term firm
79. We clarify, however, that in cases prohibiting the consideration of these
transmission rights supported by
where a load serving entity has an factors, and because such a prohibition
existing transfer capability will likely
existing agreement with the would be inconsistent with other
raise difficult issues that must be
transmission organization to pay a share statements in the Final Rule. NYISO
addressed by transmission organizations
of the embedded costs of the and their stakeholders. However, rather states that the Final Rule is not clear on
transmission system on a long-term than attempting to resolve in the Final the question of whether transmission
basis to support load outside the region, Rule all of these potential issues, we organizations may account for the needs
that load serving entity should be given adopted a non-prescriptive approach of state retail access programs when
a preference in the allocation of long- that gives each transmission determining how much capacity to set
term firm transmission rights for the organization and its stakeholders aside for long-term firm transmission
external load equal to the preference flexibility to design long-term firm rights. NYISO believes that, as a general
given to load serving entities with loads transmission rights that fit the matter, many load serving entities in
that lie within the transmission prevailing market design while also retail access states should be expected
organization’s region. Furthermore, in ensuring that the rights have certain to prefer shorter-term rights since the
response to TAPS, the preference fundamental properties necessary to amount of load that they serve may be
should apply in cases where pancaked achieve Congress’s objectives in section subject to frequent change. NYISO
rates between the transmission 217(b)(4) of the FPA. asserts that reserving too much capacity
organization and the other transmission for long-term firm transmission rights
provider have been eliminated, as long Rehearing Requests could become a serious barrier to market
as the agreement with the load serving 83. First, NYISO states that the entry if it prevented new load serving
entity provides for cost sharing in Commission should clarify that load entities from securing reasonable
accordance with the non-pancaked rates serving entities’ entitlement to receive transmission rights.
currently in effect. new long-term firm transmission rights 85. Third, NYISO states that the
80. We further clarify that, in cases should be reduced to the extent that Commission should clarify that the
where no such agreement exists, a load they already hold grandfathered transmission organization need not
serving entity with load that sinks transmission rights. NYISO explains allocate, or allow as many opportunities
outside the transmission organization’s that, under its system, load serving to reconfigure, long-term firm
region is entitled to receive long-term entities that have grandfathered rights transmission rights as it does for
firm transmission rights from existing already receive transmission service that shorter-term transmission rights. In the
system capacity to support that load to confers the same level of price certainty alternative, NYISO asks the Commission
the extent that capacity is available after and stability, and in many cases do so to grant rehearing because it has not
the needs of the load serving entities for a longer time, than the Final Rule offered a reasoned explanation why
whose loads are within the region have requires. NYISO argues that, to the long-term firm transmission rights and
been met. However, in such cases, we extent that a load serving entity’s needs shorter-term rights must be treated the
expect that the load serving entity are already satisfied by these same in this regard. NYISO states that
would be required to contribute, on a grandfathered rights, giving it it currently auctions transmission
long-term basis, toward the embedded congestion contracts twice a year and
74 See, e.g., New England Power Pool, 100 FERC
cost of the transmission system, by holds monthly reconfiguration auctions.
¶ 61,287, at P 85 (2002) (requiring external load to
paying either pancaked or non- pre-pay its transmission access charge in order to To avoid uncertainty and facilitate
sroberts on PROD1PC70 with RULES

pancaked rates, as applicable. receive FTRs); see also California Independent stakeholder compliance discussions,
81. We deny SMUD’s requested System Operator Corporation, 116 FERC ¶ 61,274 NYISO requests clarification that long-
clarification to prohibit a transmission at P 766 (2006) (stating that external load and term and short-term rights may be
internal load are not similarly situated with respect
organization from allocating long-term to their reliance on the transmission organization’s allocated, and adjusted, on different
firm transmission rights based on grid) (MRTU Order). timetables.

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00022 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations 68453

86. Finally, NYISO states that the obtain, at its option, a quantity of long- rights and for recovering the embedded
Commission should clarify that load term firm transmission rights sufficient costs of the transmission system from
serving entities that obtain long-term to hedge its long-term power supply those entities that receive, or are eligible
firm transmission rights must pay a fair arrangements at a base load level. We to receive, the rights. We expect that, in
share of transmission system costs. If emphasize that a load serving entity is most cases, the transmission
this was not the Commission’s intent, under no obligation to request its full organization will revise its current
NYISO asks that the Commission entitlement to long-term firm process as necessary to accommodate
reverse its position on rehearing. NYISO transmission rights. If the transmission the introduction of long-term firm
argues that making long-term firm capacity that is set aside for long-term transmission rights.
transmission rights available for free firm transmission rights remains
would be arbitrary and capricious unsubscribed at the conclusion of the 8. Use of an Auction to Allocate Long-
because it would be inconsistent with long-term firm transmission rights Term Firm Transmission Rights
relevant precedent and the Final Rule’s allocation process, the extra capacity 91. As adopted in the Final Rule,
stated goals. NYISO explains that must be made available to support the guideline (7) states that the initial
granting this clarification will facilitate requests of load serving entities that allocation of the long-term firm
the NYISO stakeholder process by prefer to hold short-term rights. The transmission rights shall not require
cutting off the possibility of a distracting Commission is confident that setting recipients of such rights to participate
debate over an issue that the aside capacity for long-term rights in (i.e., bid or offer) in an auction to obtain
Commission appears to view as this manner will achieve the result that the rights. We further explained that
unambiguously settled. NYISO seeks; that is, it will meet the guideline (7) does not preclude a
requirements of EPAct 2005 to make transmission organization from using an
Commission Conclusion
available long-term firm transmission auction subsequently to re-allocate long-
87. With regard to NYISO’s question rights to meet the reasonable needs of term firm transmission rights.
concerning the treatment of load serving entities that prefer such
grandfathered transmission rights, we Rehearing Requests
rights, while effectively reserving a large
note that, if such rights satisfy the portion of existing capacity for those 92. TAPS states that the language of
requirements of section 217(b)(4) of the entities that prefer shorter-term rights. guideline (7) is limited to the initial
FPA and satisfy each of the guidelines 89. NYISO asks the Commission to allocation of the long-term firm
in the Final Rule, they can be treated as clarify that the transmission transmission rights. TAPS therefore
the equivalent of the long-term firm organization need not provide as many requests clarification, or in the
transmission rights that the opportunities to allocate or reconfigure alternative rehearing, that the same
transmission organization must make long-term firm transmission rights as it restrictions on the use of mandatory
available under this rule, and may does for shorter-term transmission auctions for initial allocations will
substitute for such rights in the rights. We clarify that the transmission apply when long-term firm transmission
transmission organization’s allocation organization need not allow for the rights are renewed.
process. That is, they must qualify as allocation or reconfiguration of long-
long-term firm transmission rights (or Commission Conclusion
term firm transmission rights more
equivalent tradable or financial rights) frequently than once per year. Because 93. In response to TAPS’ request, we
that, for the load serving entities that most transmission organizations can clarify that the word ‘‘initial’’ is meant
hold them, meet their reasonable needs now readily accommodate annual to distinguish the award of long-term
to satisfy their service obligations. allocations of short-term rights, the firm transmission rights by the
However, we do not decide here Commission believes that a process that transmission organization to a load
whether the grandfathered rights held provides for the annual allocation and serving entity from any subsequent
by NYISO’s load serving entities satisfy reconfiguration of long-term firm resale of those rights by the load serving
these requirements. Should a transmission rights would be reasonable entity. Thus, guideline (7) precludes a
transmission organization believe that and appropriate. However, if the transmission organization from
its grandfathered rights satisfy each of transmission organization proposes to requiring a load serving entity to submit
the guidelines in the Final Rule, it allow allocations or reconfigurations a winning bid in an auction in order to:
should provide an explanation in its less frequently than once per year, we (a) Acquire long-term firm transmission
compliance filing, pursuant to 18 CFR clarify that it must fully support such a rights in the first instance; or (b) renew
42.1(c)(1)(ii). request in its compliance filing. those rights at a later date. However,
88. NYISO asks the Commission to 90. Finally, NYISO asks the guideline (7) does not preclude a holder
clarify that transmission organizations Commission to clarify that load serving of long-term firm transmission rights
may consider the needs of state retail entities that obtain long-term firm from reselling those rights in an auction
access programs and market transmission rights must pay a fair share process that may require the buyer,
participants’ preference for shorter-term of transmission system costs. We clarify which may be another load serving
transmission rights in determining how that, although the Final Rule does not entity, to submit a winning bid to
much existing transmission capacity to permit the use of an allocation process acquire them.
set aside for long-term firm transmission that requires load serving entities to
rights. As stated above, we expect the purchase long-term firm transmission 9. Transmission Planning and
transmission organization to make rights by bidding in an auction (see Expansion
available from existing transmission discussion below), we believe that load 94. In the Final Rule, we required that
system capacity sufficient long-term serving entities that are awarded such each transmission organization with an
firm transmission rights to meet the rights incur an obligation to contribute, organized electricity market implement
sroberts on PROD1PC70 with RULES

‘‘reasonable’’ needs of all of its load directly or indirectly, to the embedded a transmission system planning process
serving entities. In most cases, we costs of the transmission system that that will accommodate the long-term
believe that the reasonable needs of load supports those rights. Each transmission transmission rights that are awarded by
serving entities will be met if each load organization has in place a process for ensuring that they remain feasible over
serving entity is able to request and allocating short-term firm transmission their entire term. We noted that FPA

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00023 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
68454 Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations

section 217(b)(4) requires the transmission rights). APPA asks the transmission scheduling, by reducing
Commission to exercise its authority Commission to clarify this point. the incidence of transmission loading
under the FPA in a manner that relief, or TLRs.80
Commission Conclusion
facilitates the planning and expansion
97. The Commission stated in the Rehearing Requests
of transmission facilities, and to enable
load serving entities to obtain long-term Final Rule that it was not, through the 99. Santa Clara seeks clarification or,
firm transmission rights. To implement long-term firm transmission rights in the alternative, rehearing on the
that section in a transmission regulations, imposing a new ‘‘obligation ‘‘physical attributes’’ of long-term firm
organization with an organized to build’’ that does not already exist transmission rights. Santa Clara asserts
electricity market, as required by section under Order No. 888.75 The this is necessary so that transmission
1233(b) of EPAct 2005, we concluded Commission also noted that it was organizations can meet what Santa Clara
that the transmission organization must considering issues concerning its interprets to be section 217(b)(4)’s
plan its system to ensure that allocated broader mandate to exercise its FPA mandate ‘‘that financial rights be
or awarded long-term firm transmission authority to facilitate planning and ‘equivalent to’ physical rights.’’ 81 Santa
rights are feasible. We stated that FPA expansion in both transmission Clara recognizes that the Final Rule
section 217(b)(4) itself, by including organization and non-transmission proposes several measures to support
both the requirement to facilitate organization regions in Docket No. the financial ‘‘firmness’’ of the long-
planning and expansion and the RM05–25–000, the Order No. 888 term firm transmission rights, including
requirement to provide long-term reform rulemaking.76 The nature of the full funding of the rights and fixing the
transmission rights, supports the general planning obligation in the quantity of the rights over time.
Commission’s authority to impose this OATT referred to by APPA here is However, Santa Clara argues that
requirement. under consideration in that docket. As additional attributes are needed,
95. The Commission stated that FPA a result, APPA’s request for clarification including ‘‘physical scheduling
section 217(b)(4) does not merely is outside of the scope of this attributes that enable LSEs to deliver
require the provision of long-term firm rulemaking proceeding, which concerns energy to native load.’’ 82 Santa Clara
transmission rights; it requires the only the obligation to plan and expand states that ‘‘financial rights do nothing
Commission to facilitate the planning the system as it relates to the provision for situations where service is denied to
and expansion of transmission facilities. of long-term firm transmission rights. a transmission-dependent user,’’
However, we noted that we were not including, in Santa Clara’s view,
requiring in the Final Rule any 10. Properties of Physical Versus
Financial Rights physical curtailment of transmission
‘‘obligation to build’’ or other obligation service.83 Hence, Santa Clara requests
that does not already exist under Order 98. In the Final Rule, we interpreted that holders of long-term firm
No. 888. We noted that we are section 217(b)(4) of the FPA to require transmission rights receive scheduling
considering issues concerning our that load serving entities be able to priority over other transmission users in
broader mandate to exercise our FPA obtain long-term firm transmission the event of curtailment. In addition,
authority to facilitate planning and rights, whether as physical rights or Santa Clara argues that financial rights
expansion (which applies to all regions) financial rights. While we left the choice do not support building new
in Docket No. RM05–25–000, the Order of specifying long-term rights as transmission capacity.
No. 888 OATT reform rulemaking. physical or financial rights to
transmission organizations and their Commission Conclusion
Rehearing Requests
stakeholders, we did not require that 100. We reject Santa Clara’s request
96. APPA asks the Commission to transmission organizations with existing for clarification or, in the alternative,
clarify that, while the Final Rule or approved designs for financial rehearing. First, we do not agree with
imposes no ‘‘obligation to build’’ transmission rights create a new long- Santa Clara that existing physical
transmission facilities that does not term physical right, such as an Order transmission rights have physical
already exist in Order No. 888, this does No. 888 network service right, upon scheduling attributes that are superior to
not mean there is no obligation for request of a load serving entity.77 In the scheduling rights that are available
transmission organizations to ensure addition, in our discussion of guideline in organized electricity markets with
that the transmission facilities necessary (2), we explained our interpretation of financial transmission rights. Currently,
to support long-term firm transmission the firmness requirement in a financial in organized markets with LMP, all
rights are constructed. In this regard, rights context as the right to hold a fixed physical transmission schedules are
APPA notes that the OATT imposes an (MW) quantity of long-term firm
equivalent obligation on individual honored subject to congestion charges
transmission rights over the life of the and physical feasibility. In general,
transmission providers, and rights and stability in the revenue
transmission organization transmission physical feasibility has not been a
stream from the right through full problem in such markets, as reflected in
providers must meet the ‘‘consistent funding.78 We observed that this
with or superior to’’ requirement for the very infrequent need to undertake
interpretation roughly parallels the physical curtailment of transmission
their own OATTs. APPA states that it features of quantity and financial
presumes this requirement will include through transmission loading relief.
stability of long-term physical Outside the organized markets, the
a showing that transmission transmission contracts.79 We further
organizations under their OATTs will frequency of transmission loading relief
noted that organized markets with can be much higher.
have obligations ‘‘consistent with or
locational marginal pricing generally 101. Moreover, we do not agree that
superior to’’ the obligations set out in
improve the firmness of physical long-term firm transmission rights
the OATT (as revised in Docket No.
sroberts on PROD1PC70 with RULES

RM05–25) to ensure the construction of 75 See Final Rule at P 21, n. 22 and P 453, n. 138. 80 Id.
new transmission facilities needed to 76 Id. at P 457. 81 Request for Clarification/Rehearing of Santa
support ongoing firm transmission 77 See Final Rule at P 120 and 474. Clara at 3.
service (including, in the transmission 78 See id. at P 170 and 473–74. 82 Id. at 6.

organization context, long-term firm 79 Id. at P 473. 83 Id. at 7.

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00024 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations 68455

warrant any additional physical Requests for Rehearing and/or that, while we do not interpret EPAct as
scheduling priority in the event of Clarification requiring hedging of marginal losses,
transmission curtailment. Under 104. SMUD argues that the this does not preclude future market
guideline (5), we have already accorded Commission properly concluded that design changes that allow hedging of
load serving entities priority in the under section 217(b)(4), a financial losses. Indeed, we encourage
allocation of long-term firm rights-based long-term firm transmission transmission organizations to explore
transmission rights. Granting physical service should provide a hedge to methods by which they can assist load
scheduling priority to holders of long- customers that allows them serving entities and others to obtain a
term rights would provide load serving ‘‘equivalent’’ protection to physical hedge for marginal losses.
entities that hold such rights with rights service, one that is ‘‘sufficient to 12. Compliance Procedures
greater claim over physical scheduling meet the needs of load serving entities 107. In the Final Rule, the
than load serving entities that do not to hedge long-term power supply Commission required transmission
hold such rights. We are concerned that arrangements.’’ 88 But, according to organizations subject to its requirements
distinguishing between long-term and SMUD, the Commission arbitrarily and to file compliance proposals within 180
short-term transmission rights holders illogically failed to require transmission days of the publication of the Final Rule
in this manner may not be just and organizations employing marginal loss in the Federal Register.91 The
reasonable and could be unduly charges to either: (1) offer long-term firm Commission specified that transmission
discriminatory. In fact, in our service customers a hedge against those organizations must file proposed tariff
conclusion on guideline (5) in the Final charges; or (2) exempt such customers sheets and rate schedules that would
Rule, we determined that EPAct 2005 from those charges. make available long-term firm
should not be construed to require Commission Conclusion transmission rights that satisfy each of
transmission organizations to give a the guidelines in the Final Rule. We
105. We stated in the Final Rule that
preference to load serving entities with noted that while the implementation of
we do not interpret section 217(b)(4) as
long-term rights at the expense of load long-term transmission rights would
addressing marginal loss charges.89 The
serving entities that prefer short-term present difficult issues and require
issue of hedging long-term marginal loss significant effort to prepare proposals
power supply arrangements.84 Santa charges is distinct from that of hedging
Clara has failed to persuade us that within 180 days, Congress had directed
marginal congestion charges. Congestion in section 1233(b) of EPAct 2005 that
changing this determination would charges arise in part due to transmission
yield a just and reasonable and non- the Commission act within one year of
grid constraints (or bottlenecks). For the legislation’s passage, evidencing its
discriminatory outcome. congestion charges, transmission intent that long-term transmission rights
102. Second, we disagree with Santa organizations allocate transmission be made available as soon as possible.
Clara’s assertion that we have provided rights to provide a hedge. Marginal
insufficient support for transmission losses are similar to congestion costs in Rehearing Requests
expansion to support long-term firm that they are a function of locational 108. NYISO objects to the 180-day
transmission rights. The Final Rule energy prices and line loadings. compliance deadline set forth in the
requires that transmission organizations However, the development of a financial Final Rule, arguing that this amount of
with organized electricity markets instrument or other means for hedging time is insufficient for transmission
establish a transmission system of marginal losses has not been organizations to collaborate with their
planning process that will accommodate accomplished to date in any of the stakeholders and prepare tariff revisions
the long-term transmission rights that organized electricity markets. addressing the issues raised by the Final
106. Section 217(b)(4) of the FPA Rule. According to NYISO, unlike other
are awarded by ensuring that they
requires the Commission to act in a transmission organizations, it must
remain feasible over their entire term.85 manner that ‘‘* * * enables load-
Santa Clara has not specifically make major changes to its existing
serving entities to secure firm systems for allocating and auctioning
addressed that requirement or explained transmission rights (or equivalent transmission rights, making its
why it is insufficient. tradable or financial rights) on a long- compliance burden more significant
11. Exemption From Marginal Loss term basis. The terms ‘‘firm than the Commission anticipates.
Charges transmission rights,’’ and ‘‘equivalent NYISO argues that the Commission
tradable or financial rights’’ are based its 180-day compliance deadline
103. We stated in the Final Rule that consistent with terminology on an expectation that ‘‘most’’
we do not interpret section 217(b)(4) as traditionally used to discuss hedging of transmission organizations would not
addressing marginal loss charges.86 In congestion, rather than marginal losses. require major changes in their financial
addition, we noted that the transmission Furthermore, we do not interpret EPAct transmission rights systems.92 NYISO is
organizations with organized electricity 2005 as requiring transmission different from the transmission
markets currently refund any marginal organizations to provide long-term firm organizations the Commission
loss surplus that they collect, and that transmission rights with properties that apparently had in mind, it asserts, for
those refund methods have been are fundamentally different from those several reasons, including the fact that
approved by the Commission on a case- of the short-term rights that they now it does not have an ARR allocation
by-case basis, reflecting regional offer. Consequently, we do not interpret system, does not currently have rules
preferences. Accordingly, we concluded the statute as requiring hedging of awarding incremental long-term firm
that we would not overturn those marginal losses.90 In addition, we note transmission rights for upgrades paid for
decisions in the Final Rule.87 by a market participant, does not have
sroberts on PROD1PC70 with RULES

88 SMUD Rehearing Request at 2 (citing Final

Rule at P 495). 91 The Final Rule was published in the Federal


84 Final Rule at P 319. 89 Id. at P 478.
Register on August 1, 2006, making compliance
85 See id. at P 453. 90 Transmission rights holders are nevertheless proposals due on January 29, 2007.
86 Id. at P 478.
free, of course, to contract with generators to hedge 92 Request for Rehearing of NYISO at 16 (citing
87 Id. losses. Final Rule at P 18).

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00025 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
68456 Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations

rules for mandatory re-assignments of Final Rule that transmission We remind NYISO and the other
transmission rights, and has substantial organizations file compliance proposals transmission organizations, however,
grandfathered transmission rights in by January 29, 2007 (180 days from the that they must file compliance
place. NYISO also argues that it must date of publication in the Federal proposals within 180 days, and may
take care to ensure that its long-term Register). While we appreciate that propose an individual effective date in
firm transmission rights design does not NYISO will need to work through many that filing that takes into account
harm New York’s successful retail issues during this time period, perhaps existing allocation schedules for
access program. even more than some other transmission transmission rights or the need to make
109. NYISO further contends that organizations, we believe that it is software or procedural changes to
nothing in section 217 of the FPA necessary to implement Congress’s implement long-term rights.95 The
requires the Commission to impose such mandate regarding provision of long- Commission will consider effective date
an aggressive compliance timeline. If term transmission rights in an proposals in light of Congress’s intent
anything, NYISO asserts, section 217’s expeditious manner. The that long-term firm transmission rights
references to financial transmission implementation of section 217(b)(4) and be implemented as soon as possible and
rights and explicit protection of existing the availability of long-term firm demonstrated constraints faced by the
transmission organization auction rules transmission rights in transmission transmission organization in
suggests that Congress did not believe organizations with organized electricity implementing long-term rights.96
there was a pressing need for change. markets is a directive from Congress in 114. We also decline to begin the 180-
Moreover, NYISO compares the EPAct 2005. As we stated in the Final day compliance period from the date of
Commission’s interpretation of the Rule, if implementing the rule requires this order on rehearing. We are not
necessary compliance requirements here NYISO or another transmission changing the Final Rule, so the work
with new section 215 of the FPA organization to reorder its market design transmission organizations and their
(concerning bulk electric system initiatives, it should do so, seeking stakeholders have accomplished to date
reliability and certification of an Electric approval from the Commission to reset will not be wasted.
Reliability Organization (ERO)); it deadlines as necessary.94 13. Implementation Date
argues that the Commission did not 112. Despite NYISO’s observation that
interpret that statute’s requirement that an expeditious implementation 115. In the Final Rule, the
an ERO be certified within 180 days as schedule is not explicitly required by Commission declined to prescribe
imposing deadlines on the ERO’s section 217 of the FPA and section effective dates for the tariff sheets to be
compliance with future Commission 1233(b) of EPAct 2005, we believe that filed 180 days after issuance of the Final
regulations. Congress would not have specifically Rule. We recognized that transmission
110. Accordingly, NYISO states that directed in section 1233(b) that the organizations may need to synchronize
the Commission is under no legal Commission act within one year to the availability of long-term firm
obligation to set a uniform compliance implement section 217(b)(4) within transmission rights with their existing
deadline, and should allow each transmission organizations with allocation schedules, and take
transmission organization to propose an organized electricity markets unless additional steps, such as making
individual compliance deadline that Congress believed that this directive necessary software or procedural
reflects what it must do to comply with would ensure presence of long-term changes, to implement their long-term
the Final Rule.93 This approach better firm transmission rights shortly firm transmission rights proposals.
comports with the Commission’s thereafter. The references to financial Consequently, we concluded that we
flexible approach, NYISO contends. If transmission rights in section 217 only would evaluate effective dates on a case-
nothing else, it argues that the suggest that such rights, if offered on a by-case basis, and in light of Congress’s
Commission should delay the start of long-term basis to support long-term intent that long-term firm transmission
the 180-day period for compliance power supply arrangements, can satisfy rights be implemented as soon as
filings until after it issues its order on the requirements of that section, not that possible.
rehearing. There is likely to be a large no change is required. NYISO’s 116. In addition, we explicitly
number of rehearing requests, some of reference to the Commission’s required CAISO, along with all existing
which may seek significant revisions to implementation of section 215 of the transmission organizations, to make
the Final Rule. As a result, NYISO FPA (concerning mandatory reliability proposals to comply with the Final Rule
states, the order on rehearing may not standards and certification of the ERO) according to the 180-day timetable.
issue until halfway through the is not relevant to our implementation of While we were sympathetic to CAISO’s
compliance period (if not later), which section 217(b)(4) of the FPA. Section concerns regarding its pending market
would waste the effort of stakeholders if 1233(b) of EPAct 2005 expressly redesign, we determined that we could
changes are required. Granting this directed that long-term firm not address in a rulemaking of general
request would not substantially affect transmission rights be implemented applicability any possible plans for
the actual effective date of the tariff within one year of its passage. The phase-in or delayed implementation of
revisions filed in compliance with the Commission has already granted as long-term firm transmission rights. We
Final Rule and would not delay much flexibility as we believe the further noted in the Final Rule that
technical implementation work, NYISO statute allows in providing a six month CAISO had not provided any timetable
argues. period after the one-year deadline to file in its comments for implementing long-
Commission Conclusion tariff sheets making long-term firm term firm transmission rights as
transmission rights available to market required by EPAct 2005. Accordingly,
111. We deny this rehearing request, participants. we directed CAISO to work with its
and maintain the requirement in the 113. Accordingly, we decline to stakeholders to develop and submit a
sroberts on PROD1PC70 with RULES

modify the Final Rule to allow compliance filing within the timetable
93 Specifically, NYISO states that each
transmission organizations to propose prescribed in the Final Rule. We also
transmission organization should be required to
submit a detailed compliance plan within 90 days individual implementation schedules.
95 Id. at P 493.
(after consultation with stakeholders), including
timetables for developing and filing tariff revisions. 94 Final Rule at P 491. 96 Id.

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00026 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations 68457

concluded that we would consider any possible.’’ 102 SMUD expresses concern, reasonable to require all transmission
issues specific to CAISO in its based on its contact with CAISO and organizations, including CAISO, to
compliance filing for implementing CAISO’s track record on this issue, that include and justify in their compliance
long-term firm transmission rights in CAISO may not implement long-term proposals a timetable for
CAISO.97 firm transmission rights before its implementation of long-term firm
MRTU implementation date or even by transmission rights.
Rehearing Requests that date should its MRTU 122. Next, we deny SMUD’s request
117. SMUD states that the implementation schedule slip. SMUD for a blanket clarification that the
Commission properly concluded that asserts that CAISO’s promise to make a implementation of long-term firm
Congress intended transmission timely compliance filing, without a transmission rights must take priority
organizations to implement long-term corresponding commitment to propose over the implementation of new market
firm service offerings ‘‘as soon as any implementation date, much less a designs, if implementation of new
possible.’’ 98 Nevertheless, SMUD date ‘‘as soon as possible’’ after the market designs would delay availability
asserts that, given CAISO’s prior filing, could lead to further disputes. of long-term service. Instead, we find it
unwillingness to offer a timetable for 120. Santa Clara also requests reasonable to evaluate market design
implementation, the Commission erred clarification, or, in the alternative, priorities, including implementation of
in two ways. First, according to SMUD, rehearing concerning CAISO’s long-term firm rights, on a case-by-case
the Commission reached a conclusion obligation to comply with the Final basis. As in the Final Rule, and as
inconsistent with its factual findings in Rule. Citing the NOPR and the Final discussed above, see supra P 107, we
concluding that the details of CAISO’s Rule, Santa Clara argues that the urge transmission organizations to find
implementation plans could be Commission has found CAISO to be an ways to reorder their priorities to ensure
addressed when CAISO made a organized electricity market that is timely implementation of long-term firm
compliance filing.99 SMUD asks the required to submit a compliance filing transmission rights.
within the 180-day time frame.103 Santa 123. With respect to CAISO in
Commission to clarify that: (1)
Clara asks the Commission to clarify or particular, SMUD’s requested
compliance filings must propose a
grant rehearing and find that CAISO is clarification assumes CAISO cannot
timetable for implementation and
a transmission organization with concomitantly accomplish its market
include a timely implementation date;
organized electricity markets, and is redesign on schedule and devise and
and (2) the implementation of long-term
firm transmission rights must take currently subject to the requirements of timely implement long-term firm
the Final Rule. Santa Clara states that transmission rights. We decline to make
priority over the implementation of new
the Final Rule makes clear that it that assumption. As we recently
market designs, if implementation of
applies to organized electricity markets concluded, California’s market redesign
new market designs would delay
that include ‘‘auction-based day ahead and technology upgrade (MRTU) is
availability of long-term service include
and real time wholesale market[s],’’ that needed to prevent recurrence of the
a timely implementation date.
do not offer financial transmission California and Western power crisis of
118. Second, SMUD asserts that the instruments with terms longer than one 2000–2001. As the Commission
Commission acted arbitrarily in failing year.104 Asserting that CAISO ‘‘clearly explained in its acceptance of the tariff
to address SMUD’s comment that operates an auction based single price CAISO filed to implement MRTU,
transmission providers/organizations day-ahead and real-time market’’ and MRTU will fix a flawed market design,
unable to develop financial rights-based does not offer long-term rights with enhance reliability of the CAISO-
long-term firm service within a short longer than annual terms, Santa Clara controlled grid, and improve market
time after the date for the compliance asks the Commission to confirm its prior power mitigation.106 These
filing should be required to offer interim ruling that CAISO must comply with the improvements over the current market
plans, such as the use of physical rights Final Rule. Santa Clara explains that design will help protect California, and
service, until a financial rights service confusion has arisen, ostensibly based the rest of the West, from a repeat of that
can be implemented.100 on the Commission’s statement that crisis.107 Long-term firm transmission
119. SMUD explains that CAISO’s organized electricity markets do not rights are also a critical feature of
market redesign and technological include ‘‘Day 1’’ markets.105 MRTU’s improved congestion
upgrade (MRTU) will not be Commission Conclusion management system, in part because
implemented until at least November these rights will help shield load
2007, so that even if CAISO’s proposed 121. First, we grant SMUD’s requested serving entities from exposure to
‘‘priority renewal provisions’’ for clarification that compliance filings potentially volatile congestion costs.108
congestion revenue rights (CRRs) 101 must include implementation The Final Rule directed CAISO to work
offered a reasonable interim bridge, timetables. As we emphasized in the with its stakeholders to develop and
delaying implementation to coincide Final Rule, Congress intended the swift submit a compliance filing within the
with implementation of a new market introduction of long-term firm timetable prescribed in the Final
design will not meet the Congressional transmission rights. In the Final Rule, Rule.109 The MRTU Order similarly
and Commission directives that long- we declined to prescribe an effective
required CAISO to comply with the
term service be available ‘‘as soon as date for tariff sheets implementing long-
Final Rule concerning timely
term firm transmission rights, so as to
implementation of long-term firm
provide flexibility to the various
97 Final Rule at P 495. transmission rights.110 We understand
98 SMUD Rehearing Request at 2 (citing Final transmission organizations to effectuate
SMUD’s concerns, given CAISO’s
Rule at P 495). the Final Rule. Nevertheless, we find it
99 Id. at 2 (citing Burlington Truck Lines v. United
lackluster history of delay with respect
sroberts on PROD1PC70 with RULES

States, 371 U.S. 156, 168 (1962)). 102 SMUD Rehearing Request at 8 (citing Final
106 MRTU Order at P 3.
100 Id. at 2 (citing Noram Gas Transmission Co v. Rule at P 495).
103 Request for Clarification/Rehearing of Santa 107 Id.
FERC, 148 F.3d 1158, 1165 (D.C. Cir. 1990)); see
Clara at 5. 108 Id.
at P 9.
also id. at 6–7.
101 ‘‘FTRs’’ are called ‘‘CRRs’’ under California’s 104 See id. (quoting Final Rule at P 30). 109 FinalRule at P 493.
new market design, MRTU. 105 Id. (citing Final Rule at P 31). 110 MRTU Order at P 890 and 892.

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00027 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1
68458 Federal Register / Vol. 71, No. 227 / Monday, November 27, 2006 / Rules and Regulations

to providing long-term firm market where a single entity receives DEPARTMENT OF COMMERCE
transmission rights.111 However, now offers to sell and bids to buy electric
that Congress has weighed in on the energy and/or ancillary services from International Trade Administration
issue, we remain optimistic that CAISO multiple sellers and buyers and
will develop a plan, tariff sheets and determines which sales and purchases 19 CFR Part 351
implementation timetable to allow are completed and at what prices, based
provision of long-term transmission Antidumping and Countervailing
on formal rules contained in
rights at the inception of MRTU, Duties
Commission-approved tariffs, and
without delaying MRTU’s target where the prices are used by a CFR Correction
November 2007 implementation date.
transmission organization for In Title 19 of the Code of Federal
124. We also deny SMUD’s request
that, if implementation of financial establishing transmission usage Regulations, part 200 to end, revised as
long-term firm transmission rights charges.’’ 114 In the Final Rule, however, of April 1, 2006, on page 225, § 351.218
cannot be accomplished within a short we modified the first clause of the is corrected by removing and reserving
time after the date for the compliance definition to state that organized paragraph (d)(2)(iii).
filing, the affected transmission electricity market ‘‘means an auction
[FR Doc. 06–55530 Filed 11–24–06; 8:45 am]
organizations should develop interim based day ahead and real time
BILLING CODE 1505–01–D
plans, such as the use of physical rights wholesale market. * * * ’’ 115 We
service, until a financial rights service explained that the purpose of this
can be implemented. We expect that, modification was:
DEPARTMENT OF THE TREASURY
apprised of the importance of this to clarify the application of the Final Rule
matter to Congress, transmission and ensure that the definition captures the Alcohol and Tobacco Tax and Trade
organizations will make compliance transmission organizations with organized Bureau
proposals that fully comply with the electricity markets using LMP and FTRs to
Final Rule in a timely manner. It is which Congress directed the Commission to 27 CFR Part 9
premature and inappropriate to consider apply this Final Rule in section 1233(b) of
in this generic proceeding whether EPAct 2005.116 [T.D. TTB–56; Re: Notice No. 18]
interim plans, such as the provision of RIN 1513–AA57
physical rights, are needed. Similarly, 126. CAISO does not currently
we will not address in this rehearing of operate a day-ahead wholesale energy Establishment of the Chehalem
a rulemaking of general applicability market, although it will upon the Mountains Viticultural Area (2002R–
SMUD’s assertion that the CAISO’s inception of MRTU, scheduled to take 214P)
proposed priority nomination process, place in November 2007. While CAISO
or PNP, is discriminatory. As we currently has FTRs, their characteristics AGENCY: Alcohol and Tobacco Tax and
explained in the Final Rule, we will will change dramatically upon Trade Bureau, Treasury.
address the specifics of individual implementation of MRTU—e.g., they ACTION: Final rule; Treasury decision.
transmission organizations’ will be point-to-point and available to SUMMARY: This Treasury decision
implementation of the Final Rule in our load serving entities without establishes the 68,265-acre Chehalem
orders on compliance proposals.112 The participation in an auction, two features Mountains viticultural area in
compliance proposal process provides of long-term firm transmission rights Clackamas, Yamhill, and Washington
transmission organizations with the required by our guidelines. Given that Counties, Oregon. This new viticultural
opportunity to offer for comment the the nature of FTRs in CAISO is in area is entirely within the existing
proposals they have created after vetting transition, implementing long-term Willamette Valley viticultural area. We
issues through their stakeholder FTRs under the current market design designate viticultural areas to allow
process, and the comment process would be problematic. Nevertheless, we vintners to better describe the origin of
ensures the opportunity for thorough
clarify that CAISO must submit a their wines and to allow consumers to
and fair discussion of the proposals.
125. Finally, with respect to Santa compliance filing on January 29, 2007. better identify wines they may
Clara’s requested clarification/rehearing This will enable the Commission (and purchase.
concerning CAISO’s obligation to its staff) to monitor CAISO’s progress DATES: Effective Date: December 27,
comply with the Final Rule, section and ensure availability of long-term firm 2006.
1233(b) of EPAct 2005 requires the transmission rights when MRTU goes
FOR FURTHER INFORMATION CONTACT:
Commission to implement the FPA’s into effect.
N.A. Sutton, Regulations and Rulings
new statutory provision, section 217, By the Commission. Division, Alcohol and Tobacco Tax and
concerning long-term firm transmission Magalie R. Salas, Trade Bureau, 925 Lakeville St., No.
rights in transmission organizations 158, Petaluma, CA 94952; telephone
Secretary.
with organized electricity markets. 415–271–1254.
Significantly, as we pointed out in the [FR Doc. E6–19999 Filed 11–24–06; 8:45 am]
SUPPLEMENTARY INFORMATION:
NOPR, neither EPAct 2005 nor section BILLING CODE 6717–01–P

217 of the FPA defines ‘‘organized Background on Viticultural Areas


electricity market.’’ 113 In the NOPR, we TTB Authority
proposed to define ‘‘organized
electricity market’’ as ‘‘an auction-based Section 105(e) of the Federal Alcohol
Administration Act (the FAA Act, 27
sroberts on PROD1PC70 with RULES

111 See id. at P 891 (recounting CAISO’s history U.S.C. 201 et seq.) requires that alcohol
of procrastination concerning long-term rights beverage labels provide consumers with
development). 114 See id. adequate information regarding product
112 Id. at P 495.
115 See Final Rule at P 30 (emphasis added). identity and prohibits the use of
113 See NOPR at P 8. 116 Id. misleading information on those labels.

VerDate Aug<31>2005 16:30 Nov 24, 2006 Jkt 211001 PO 00000 Frm 00028 Fmt 4700 Sfmt 4700 E:\FR\FM\27NOR1.SGM 27NOR1

Вам также может понравиться