Академический Документы
Профессиональный Документы
Культура Документы
INTRODUCTION
The Central Saint Giles development is located in
the West End of London where future Crossrail
tunnels will be constructed. These tunnels will be
sufficiently close as to impact on the basement and
foundations for this new development.
Crossrail is a major proposed east-west railway
across London. Since 1990, the route alignment
has been safeguarded through the local authority
planning application process to ensure future
construction of Crossrail is not prejudiced by any
other development.
Crossrail construction is
planned to commence in 2010 with services
starting in 2017.
Through central London, fifteen kilometres of
seven metre diameter twin bored tunnel will weave
its way between existing railway and other tunnels,
sewers and building foundations. At Central Saint
Giles, the eastbound tunnel alignment passes
beneath the southern boundary of the site. The
tunnel crown is about 16.5m below ground level
with a 4m exclusion zone above and 3.5m either
side of the tunnel to allow Crossrail flexibility to
move the proposed tunnel during design.
It is mandatory that all new projects within the safe
guarded zone must consult Crossrail. At Central
Saint Giles consultation with Crossrail commenced
during concept design stage where tunnel location,
geometry, loading and settlement constraints were
advised by Crossrail for which the design of the
Central Saint Giles development had to address in
design. These constraints had a defining influence
over the foundation and substructure solution as
discussed below.
CENTRAL SAINT GILES DEVELOPMENT
Central Saint Giles is a striking new landmark in
Londons West End just east of Centre Point Tower
Figure 5: Diagrammatic
arrangement, PTP2
The PTP2 construction
summarised as follows:
cross
sequence
section
can
be
Pile
Diameter
(mm)
Pile
Length
(m)
Length
Sleeved *
(m)
Base
Grouted
1200
47
7 / 16
No
900
56
26 / 22
Yes
900
64
11 / 40
Yes
Kings Cross
1200
37
0 / 25
Yes
CTRL C105
* Pile length sleeved: air void (i.e. double sleeved) length /
bitumen coated length.
50
75
100
20
25
25
15
10
Central Saint Giles
Moorhouse
Pinnacle
King's Cross CTRL C105
Figure 6:
comparison
Test
pile
load
settlement
125
Displacement (mm)
0
10
20
30
40
50
60
20
Bitumen sleeve friction (kPa)
18
16
14
12
10
8
6
4
2
Day
1
Activity
Install 1860mm diameter temporary
casing into top of London Clay
Bore 1800mm diameter to the design
level for friction reduction bitumen
coated sleeving
Install 1560mm diameter bitumen slip
coated permanent sleeve to base of
open bore
Grout annulus between open bore and
permanent sleeve (stage 1)
Grout annulus between open bore and
permanent sleeve (stage 2)
Bore 1500mm diameter to bentonite
introduction level
Introduce bentonite
Bore under bentonite and clean pile
base
Exchange bentonite
Install reinforcement cage and concrete
tremmie
3
Concreting (approx. 78m )
Typical
duration
(hours):
0.75
0.75
2.00
0.50
0.50
1.75
1.00
0.75
Not
required
4.00
4.00
16
RETAINING WALLS
In recent times the demands on commercial and
residential basements at least in London, is for
increased space for mechanical and electrical
plant necessary to also meet sustainability and
planning requirements as well as commercially
optimising roof space and appearance, the
traditional location for some plant.
Hence
basement heights have been on the increase so
that the single level seven metre basement
height at Central Saint Giles to facilitate plant
items and their maintenance is now not
uncommon.
With the complexity and associated cost of the
cantilevered area of basement, the challenge
was to also maximise savings for the remaining
perimeter wall.
With large basements like
Central Saint Giles there is less pressure on
minimising wall size as there is on small
70
0.6%H
Key
Central Saint Giles data
+ C580 & St John et al (1992) data
60
50
0.4%H
40
30
0.2%H
20
10
0
CONCLUSIONS
10
12