Вы находитесь на странице: 1из 26

LECTURE 2

EARTHMOVING MATERIALS &


OPERATIONS
AUGUST 26, 2015

CHANG-SEON SHON, PH.D., ASSISTANT PROFESSOR


DEPARTMENT OF CIVIL ENGINEERING
NAZARBAYEV UNIVERSITY
ECE 404: Construction Technologies & Processes

Lecture 02

EARTHMOVING PROCESS
EARTHMOVING IS THE PROCESS OF MOVING SOIL OR ROCK
FROM ONE LOCATION TO ANOTHER AND PROCESSING IT SO
THAT IT MEETS CONSTRUCTION REQUIREMENTS OF LOCATION,
ELEVATION, DENSITY, MOISTURE CONTENT, AND SO ON

EARTHMOVING ACTIVITIES
Excavating / loading / hauling / placing (dumping and
spreading) / compacting / grading / finishing

FOR EFFICIENT EARTHMOVING PROCESS,


Accurate estimating of work quantities and job conditions
Proper selection of equipment
Competent job management
ECE 404: Construction Technologies & Processes

Lecture 02

EQUIPMENT SELECTION
CHOICE OF EQUIPMENT INFLUENCES ON THE EFFICIENCY &
PROFITABILITY OF THE CONSTRUCTION OPERATION

FACTORS THAT SHOULD BE CONSIDERED IN SELECTING


EQUIPMENT FOR A PROJECT

The ability of the equipment to perform the required work


Maximize the profit produced by the equipment
Achieve the lowest cost per unit of production

Possible future use of the equipment


Availability of parts and service
Effect of equipment downtime on other construction
equipment and operations
ECE 404: Construction Technologies & Processes

Lecture 02

PRODUCTION OF EARTHMOVING
EQUIPMENT
BASIC RELATIONSHIP FOR ESTIMATING THE PRODUCTION OF ALL
EARTHMOVING EQUIPMENT

Where,
Vol. per cycle average vol. of material moved per equipment
Cycles per hour the number of cycles actually achieved expected perhour

ECE 404: Construction Technologies & Processes

Lecture 02

PRODUCTION OF EARTHMOVING
EQUIPMENT (CONTD)
JOB EFFICIENCY FACTORS FOR EARTHMOVING OPERATIONS

(From TM 5-331B, U.S. Department of the Army)

ECE 404: Construction Technologies & Processes

Lecture 02

Lecture 02

EARTHMOVING MATERIALS:
GENERAL SOIL CHARACTERISTICS
TRAFFICABILITY
Ability of a soil to support the weight of
vehicles under repeated traffic
Function of soil type and moisture conditions
Factors impacting soil trafficability
Soil strength / Slipperiness / Stickiness / Slope
/ Stoniness

Drainage, stabilization of haul routes, or the


use of low-ground pressure construction
equipment may be required when poor
trafficability conditions exist
ECE 404: Construction Technologies & Processes

GENERAL SOIL CHARACTERISTICS


(CONTD)
LOADABILITY
Measure of the difficulty in excavating and loading a soil
E.g. Loose granular soils vs. compacted cohesive soils and rock

UNIT SOIL WEIGHT (LBS/YD3 OR KG/M3)


Used as measure of compaction
Factor in determining the capacity of a haul
Depend on soil type, moisture content, and degree of
compaction

MOISTURE CONTENT

100

ECE 404: Construction Technologies & Processes

Lecture 02

SOIL IDENTIFICATION AND


CLASSIFICATION
SOIL
Consist of gravel, sand, silt, clay, and organic materials

2mm

ECE 404: Construction Technologies & Processes

Lecture 02

SOIL CLASSIFICATION
SOIL CLASSIFICATION SYSTEMS
Two principal soil classification systems are used for design
and construction in the United States
Unified System
AASHTO System (American Association of State Highway and
Transportation Officials)
In both systems, soil particles 3 in. or larger in diameter are
removed before performing classification tests.

ECE 404: Construction Technologies & Processes

Lecture 02

Lecture 02

10

SOIL CLASSIFICATION:
UNIFIED SOIL CLASSIFICATION SYSTEM (USCS)
STEP 1. DETERMINE ATTERBERG LIMITS
Plasticity index (PL) = Liquid limit (LL) - Plastic limit (PL)

ECE 404: Construction Technologies & Processes

SOIL CLASSIFICATION: USCS


(CONTD)
STEP 2. CONDUCT SIEVE ANALYSIS AND DETERMINE SOIL GROUP
ON THE BASIS OF PI AND R200

ECE 404: Construction Technologies & Processes

Lecture 02

11

SOIL CLASSIFICATION: USCS


(CONTD)
STEPS 3-6. DETERMINE R4 CONTENT AND GET RATIO OF
R4/R200. THEN, DETERMINE SOIL TYPE USING THE FOLLOWING
TABLES.

ECE 404: Construction Technologies & Processes

Lecture 02

12

SOIL CLASSIFICATION:
AASHTO SYSTEM
AASHTO SYSTEM OF SOIL CLASSIFICATION

Courtesy of BOMAC Americas

ECE 404: Construction Technologies & Processes

Lecture 02

13

Lecture 02

14

SOIL CLASSIFICATION: GRADATION CURVE

Typical gradation curves for coarse-grained soils. (U.S. Army Engineer School)

ECE 404: Construction Technologies & Processes

SOIL CLASSIFICATION:
FIELD IDENTIFICATION
UNIFIED SYSTEM OF SOIL CLASSIFICATION : FIELD IDENTIFICATION
in. (6mm) passing materials :
< 50% : gravel
50% : sand

Weight
passing

No.200 (75m) passing materials


< 10% : well or poorly graded
10% : High or low plasticity

ECE 404: Construction Technologies & Processes

Lecture 02

15

Lecture 02

16

SOIL CLASSIFICATION:
FIELD IDENTIFICATION (CONTD)
DRY STRENGTH TEST AND PLASTICITY

ECE 404: Construction Technologies & Processes

SOIL CLASSIFICATION:
FIELD IDENTIFICATION (CONTD)
SOIL SHAKING TEST
Place soil in palm of hand
Add water gradually and knead the soil until it
begins to get sticky
Form a ball about in. (19mm) in diameter
Hold the ball in one hand and tap the back of
the hand with the other
If the ball becomes wet and shiny, it is mostly
fine sand or silt
No reaction suggests clay

ECE 404: Construction Technologies & Processes

Lecture 02

17

Lecture 02

18

CONSTRUCTION CHARACTERISTICS
OF SOILS

ECE 404: Construction Technologies & Processes

EARTHWORK OPERATION
BASIC RULE OF EARTHWORKS OPERATION
Cut for the high
Fill for the low

ECE 404: Construction Technologies & Processes

Lecture 02

19

Lecture 02

20

EARTHWORK OPERATION : FILL & CUT

ECE 404: Construction Technologies & Processes

10

SOIL VOLUME-CHANGE
CHARACTERISTICS
TYPICAL SOIL VOLUME CHANGE DURING EARTHMOVING
Most excavated materials are found to increase in volume
after excavation (bulking or loosing)
When compacted in the in-situ volume, soils occupy less
volume (shrinkage)

ECE 404: Construction Technologies & Processes

Lecture 02

21

SOIL VOLUME-CHANGE
CHARACTERISTICS (CONTD)
SOIL CONDITIONS
Bank: Material in its natural state before disturbance. Often
referred to as in-place or in-situ. A unit volume is
identified as a bank cubic yard (BCY) or a bank cubic meter
(BCM).
Loose: Material that has been excavated or loaded. A unit
volume is identified as a loose cubic yard (LCY) or loose cubic
meter (LCM).
Compacted: Material after compaction. A unit volume is
identified as a compacted cubic yard (CCY) or compacted
cubic meter (CCM).

ECE 404: Construction Technologies & Processes

Lecture 02

22

11

SOIL VOLUME-CHANGE
CHARACTERISTICS (CONTD)
SWELL
% =

(
(

1 100

EXAMPLE
Find the swell of a soil that weight 1661 kg/m3 in its natural
state and 1186 kg/m3 after excavation.

ECE 404: Construction Technologies & Processes

Lecture 02

23

SOIL VOLUME-CHANGE
CHARACTERISTICS (CONTD)
SHRINKAGE
% = 1

(
(

)
)

100

EXAMPLE
Find the shrinkage of a soil that weight 1661 kg/m3 in its
natural state and 2077 kg/m3 after compaction

ECE 404: Construction Technologies & Processes

Lecture 02

24

12

SOIL VOLUME-CHANGE
CHARACTERISTICS (CONTD)
LOAD FACTORS

(
(

)
)

or

1
1+

SHRINKAGE FACTOR (COMPACTION FACTOR)

(
(

or

=1

ECE 404: Construction Technologies & Processes

Lecture 02

25

SOIL VOLUME-CHANGE
CHARACTERISTICS (CONTD)
LOAD AND SHRINKAGE FACTORS
EXAMPLE
A soil weighs 1163 kg/LCM, 1661 kg/BCM, and 2077 kg/CCM
Find the load factor and shrinkage factor for the soil
How many bank cubic meters (BCM) and compacted cubic
meters (CCM) are contained in 593330 loose cubic meters of
this soil?

ECE 404: Construction Technologies & Processes

Lecture 02

26

13

SOIL VOLUME-CHANGE
CHARACTERISTICS (CONTD)
TYPICAL SOIL WEIGHT AND VOLUME CHANGE CHARACTERISTICS*

ECE 404: Construction Technologies & Processes

SPOIL BANKS

OR

Lecture 02

27

PILES

WHEN PLANNING AND ESTIMATING EARTHWORK, IT IS


FREQUENTLY NECESSARY TO DETERMINE THE SIZE OF THE PILE OF
MATERIAL THAT WILL BE CREATED BY THE MATERIAL REMOVED
FROM THE EXCAVATION

If the pile of material is long in relation to its width, it is


referred to as a spoil bank.

ECE 404: Construction Technologies & Processes

Lecture 02

28

14

SPOIL BANKS

OR

PILES (CONTD)

DETERMINE THE DIMENSIONS OF SPOIL BANKS OR PILES


Convert the volume of excavation from in-place condition
(BCY or BCM) to loose conditions (LCY or LCM)

TRIANGULAR SPOIL BANK

ECE 404: Construction Technologies & Processes

SPOIL BANKS

OR

Lecture 02

29

Lecture 02

30

PILES (CONTD)

CONICAL SPOIL PILE

ECE 404: Construction Technologies & Processes

15

SPOIL BANKS

OR

PILES (CONTD)

TYPICAL VALUES OF ANGLE OF REPOSE OF EXCAVATED SOIL

ECE 404: Construction Technologies & Processes

SPOIL BANKS

OR

Lecture 02

31

PILES (CONTD)

EXAMPLE 1
Find the base width and height of a triangular spoil bank
containing 76.5 BCM if the pile length is 9.14 m, the soil's
angle of repose is 37, and its swell is 25%.

ECE 404: Construction Technologies & Processes

Lecture 02

32

16

SPOIL BANKS

OR

PILES (CONTD)

EXAMPLE 2
Find the base diameter and height of a conical spoil pile that
will contain 76.5 BCM of excavation if the soil's angle of
repose is 32and its swell is 12%.

ECE 404: Construction Technologies & Processes

Lecture 02

33

ESTIMATING EARTHWORK VOLUME


WHEN PLANNING OR ESTIMATING AN EARTHMOVING PROJECT,
IT IS OFTEN NECESSARY TO ESTIMATE THE VOLUME OF MATERIAL
TO BE EXCAVATED OR PLACED AS FILL

THE PROCEDURES TO BE FOLLOWED CAN BE DIVIDED INTO


THREE PRINCIPAL CATEGORIES:
Pit excavations (small, relatively deep excavations such as
those required for basements and foundations)
Trench excavation for utility lines
Excavating or grading relatively large areas

PROCEDURES SUGGESTED FOR EACH OF THESE THREE CASES ARE


DESCRIBED IN THE FOLLOWING SECTIONS.
ECE 404: Construction Technologies & Processes

Lecture 02

34

17

ESTIMATING EARTHWORK VOLUME:


PIT EXCAVATIONS
SMALL, RELATIVELY DEEP EXCAVATIONS SUCH AS THOSE
REQUIRE FOR BASEMENTS AND FOUNDATION

Divide the horizontal area into a convenient set of


rectangles, triangles, or circular segments
Calculate total area (the sum of the segment areas)
Calculate the average depth
Calculate volume
=

ECE 404: Construction Technologies & Processes

Lecture 02

35

ESTIMATING EARTHWORK VOLUME:


PIT EXCAVATIONS (CONTD)
EXAMPLE
Estimate the volume of excavation required (bank measure)
for the basement shown. Values shown at each corner are
depths of excavation. All values are in meter.

ECE 404: Construction Technologies & Processes

Lecture 02

36

18

ESTIMATING EARTHWORK VOLUME:


TRENCH EXCAVATIONS
TRENCH EXCAVATION FOR UTILITY LINES
Calculate the trench cross-section area
Measure the linear distance along the trench line
Calculate volume
=

ECE 404: Construction Technologies & Processes

Lecture 02

37

Lecture 02

38

ESTIMATING EARTHWORK VOLUME:


TRENCH EXCAVATIONS (CONTD)
CROSS-SECTIONAL AVERAGE METHOD
+
2

1 +

2
2

1
6

+
2

+4

ECE 404: Construction Technologies & Processes

19

ESTIMATING EARTHWORK VOLUME:


TRENCH EXCAVATIONS (CONTD)
EXAMPLE
Find the volume (bank measure) of excavation required for
a trench 0.92 m wide, 1.83 m deep, and 152 m long.
Assume that the trench sides will be approximately vertical.

ECE 404: Construction Technologies & Processes

Lecture 02

39

ESTIMATING EARTHWORK VOLUME:


LARGE AREAS
EXCAVATING OR GRADING RELATIVELY LARGE & COMPLEX AREAS
Divide the area into a grid indicating the depth of excavation or
fill at each grid intersection
Assign the depth at each comer or segment intersection a
weight according to its location (number of segment lines
intersecting at the point)
Interior points : a weight of four
Exterior points : a weight of two
Corner points : a weight of one

ECE 404: Construction Technologies & Processes

Lecture 02

40

20

ESTIMATING EARTHWORK VOLUME:


LARGE AREAS (CONTD)
EXAMPLE

ECE 404: Construction Technologies & Processes

Lecture 02

41

Lecture 02

42

ESTIMATING EARTHWORK VOLUME:


LARGE AREAS (CONTD)
SQUARE PILLAR
ab
y1 y4 y3 y4
4
ab
V1 h1 h2 h2 h4
4
ab
V2 h2 h2 h3 h4
4

ab
h1 h2 h3 h4
4
ab
V h1 2 h2 3 h3 4 h4
4
V5

ECE 404: Construction Technologies & Processes

21

ESTIMATING EARTHWORK VOLUME:


LARGE AREAS (CONTD)
PRISM
ab
y1 y4 y3
6
ab
V1 h1 h4 h4
6
ab
V2 h3 h4 h4
6

ab
h1 h2 h4
6
ab
V h1 2 h2 3 h3 8 h8
6
V6

ECE 404: Construction Technologies & Processes

Lecture 02

43

ESTIMATING EARTHWORK VOLUME:


LARGE AREAS (CONTD)
EXAMPLE
Find the volume of excavation required for the area shown
in Figure. The figure at each grid intersection represents
the depth of cut at that location.

ECE 404: Construction Technologies & Processes

Lecture 02

44

22

EARTHWORK CALCULATION SHEET


(TABLE)
EARTHWORK CALCULATE SHEET (TABLE) IS REQUIRED TO DRAW
MASS DIAGRAM
Cutting of soil (Used in fiiling)
Station No. Distance

11
12
13
14
15
16

20
12.5
7.5
20
20

*Average
Area
Area (m2)
(m2)
21.6
29.4

25.5

**Vol. of
soil
(m3)

510.0

Filling of soil
Area
(m2)

8.3
1.3

Average
Area
(m2)

Vol. of
soil
(m3)

Compaction
factor
(C)

4.8

96.0

0.9

Revised
Vol.
(m3)

Calculated
Soil (m3)
Excess (+)
Short (-)

106.7

403.3

Cumulative 4Vol. (m3)


Vol.
horizontal
direction
(m3)

963.3
1366.6

106.7

Total
* Average area is the average of previously and currently measured areas
**Volume of soil = Average area x distance
1
Revised vol. of soil = vol. of soil / compaction factor
2
"+" means cutting of soil while "-" imply filling of soil
3
Cumulative vol. of soil
4
At the same station no, select small vol. of soil betwwen cutting and filling of soil

ECE 404: Construction Technologies & Processes

Lecture 02

45

Lecture 02

46

EARTHWORK CALCULATION TABLE:


HIGHWAY CONSTRUCTION

ECE 404: Construction Technologies & Processes

23

MASS (HAUL) DIAGRAM


IN ORDER TO MINIMIZE MATERIAL WASTE OR BORROW, IT IS
NECESSARY TO PRODUCE WHAT IS CALLED A MASS HAUL
DIAGRAM
A PLOT OF CUMULATIVE VOLUME OF SOIL AGAINST DISTANCE
ALONG THE ROAD

CUT VOLUMES ARE TAKEN TO BE POSITIVE AND FILL VOLUMES


TO BE NEGATIVE

COMMON IN ROADWAY OR AIRFIELD


PREPARED BY HIGHWAY AND AIRFIELD DESIGNERS TO ASSIST IN
SELECTING AN ALIGNMENT
ECE 404: Construction Technologies & Processes

Lecture 02

47

Lecture 02

48

MASS (HAUL) DIAGRAM (CONTD)

ECE 404: Construction Technologies & Processes

24

MASS (HAUL) DIAGRAM (CONTD)


THE VERTICAL COORDINATE OF THE MASS DIAGRAM CORRESPONDING TO
ANY LOCATION ON THE ROADWAY PROFILE REPRESENTS THE CUMULATIVE
EARTHWORK VOLUME FROM THE ORIGIN TO THAT POINT

WITHIN A CUT, THE CURVE RISES FROM LEFT TO RIGHT


WITHIN A FILL, THE CURVE FALLS FROM LEFT TO RIGHT
A PEAK ON THE CURVE REPRESENTS A POINT WHERE THE EARTHWORK
CHANGES FROM CUT TO FILL

A VALLEY (LOW POINT) ON THE CURVE REPRESENTS A POINT WHERE THE


EARTHWORK CHANGES FROM FILL TO CUT

WHEN A HORIZONTAL LINE INTERSECTS THE CURVE AT TWO OR MORE


POINTS, THE ACCUMULATED VOLUMES AT THESE POINTS ARE EQUAL.
THUS, SUCH A LINE REPRESENTS A BALANCE LINE ON THE DIAGRAM.
ECE 404: Construction Technologies & Processes

Lecture 02

49

CONSTRUCTION USE OF THE MASS


DIAGRAM (CONTD)
USING THE MASS DIAGRAM
The length and direction of haul within a balanced section
The average length of haul for a balanced section
The location and amount of borrow (material hauled in
from a borrow pit) and waste (material hauled away to a
waste area) for the project
Selection of type of equipment for accomplishing the work
Selection of construction
method

ECE 404: Construction Technologies & Processes

Lecture 02

50

25

CONSTRUCTION USE OF THE MASS


DIAGRAM (CONTD)
EXAMPLE
Figure 1 shows the mass
diagram of earthwork.
(1) What is the total amount of
soil (m3) between A and B?
(2) What is the average
distance (m) between A and B?

ECE 404: Construction Technologies & Processes

Figure 1. Mass diagram

Lecture 02

51

26

Вам также может понравиться