Вы находитесь на странице: 1из 9

STEEL STRUCTURES

building construction

a case study
HOWRAH BRIDGE

abhishek behera
The following are some of the advantages of steel bridges
that have contributed to their :
• They could carry heavier loads over longer spans with
minimum dead weight, leading to smaller foundations.
• Steel has the advantage where speed of construction is
vital, as many elements can be prefabricated and erected
at site.
• In urban environment with traffic congestion and limited
working space, steel bridges can be constructed with
minimum disruption to the community.
• Greater efficiency than concrete structures is invariably
achieved in resisting seismic forces and blast loading.
• The life of steel bridges is longer than that of concrete
bridges.
• Due to shallow construction depth, steel bridges offer
slender appearance, which make them aesthetically
attractive. The reduced depth also contributes to the
reduced cost of embankments.
• All these frequently leads to low life cycle costs in steel
bridges

Classification based on the position of carriageway


The bridges may be
• Deck Type Bridge - The carriageway rests on the top of the main load carrying members. In the deck
type plate girder bridge, the roadway or railway is placed on the top flanges. In the deck type truss
girder bridge, the roadway or railway is placed at the top chord level

• Through Type Bridge - The carriageway rests at the bottom level of the main load carrying members.
In the through type plate girder bridge, the roadway or railway is placed at the level of bottom
HOWRAH BRIDGE flanges. In the through type truss girder bridge, the roadway or railway is placed at the bottom chord
level. The bracing of the top flange or lateral support of the top chord under compression is also
calcutta required.

• Semi through Type Bridge - The deck lies in between the top and the bottom of the main load
carrying members. The bracing of the top flange or top chord under compression is not done and part
of the load carrying system project above the floor level. The lateral restraint in the system is
obtained usually by the U-frame action of the verticals and cross beam acting together.
Classification based on the main structural system
Many different types of structural systems are used in bridges depending upon the span,
carriageway width and types of traffic. Classification, according to make up of main load
carrying system, is as follows:

(i) Girder bridges - Flexure or bending between vertical supports is the main
structural action in this type. Girder bridges may be either solid web girders or
truss girders or box girders. Plate girder bridges are adopted for simply supported
spans less than 50 m and box girders for continuous spans up to 250 m. Truss
bridges are suitable for the span range of 30 m to 375 m. Cantilever bridges have
been built with success with main spans of 300m to 550m.
(ii) Rigid frame bridges - In this type, the longitudinal girders are made structurally
Arched bridge
continuous with the vertical or inclined supporting member by means of moment
carrying joints. Flexure with some axial force is the main forces in the members in
this type. Rigid frame bridges are suitable in the span range of 25m to 200m.
(iii) Arch bridges - The loads are transferred to the foundations by arches acting as the
main structural element. Axial compression in arch rib is the main force, combined
with some bending. Arch bridges are competitive in span range of 200m to 500m.
(iv) Cable stayed bridges - Cables in the vertical or near vertical planes support the
main longitudinal girders. These cables are hung from one or more tall towers, and
are usually anchored at the bottom to the girders. Cable stayed bridges are
economical when the span is about 150m to 700m.
(v) Suspension bridges - The bridge deck is suspended from cables stretched over the
gap to be bridged, anchored to the ground at two ends and passing over tall towers
erected at or near the two edges of the gap. Currently, the suspension bridge is
best solution for long span bridges.
Cable stayed bridge
HOWRAH BRIDGE
calcutta

Suspension bridge
LOADS ON BRIDGES
Normal span ranges of bridge system
The following are the various
loads to be considered for the
purpose of computing
stresses, wherever they are
applicable.
• Dead load
• Live load
• Impact load
HOWRAH BRIDGE • Longitudinal force
calcutta •

Thermal force
Wind load
• Seismic load
• Racking force
• Forces due to curvature.
• Forces on parapets
• Frictional resistance of
expansion bearings
• Erection forces
The Rabridra Setu or more famously called the Howrah Bridge over the Hooghly is primarily a cantilever truss bridge, built in the year
1943. The bridge is completely made up of steel.

By the 19th century, Calcutta and Howrah had grown to be the most important economic and cultural centres, and a need for bridging the
Hooghly River arose.

A proposal to build a bridge over the Hooghly was made by the government of Bengal, but the following observations were made :

• The foundations for a bridge at Calcutta would be at a considerable depth because of the depth of the mud there.
• the structure would cause considerable hindrance to the shipping on the river
• The only feasible site was at a great distance.

The bridge was not built. The famous Floating Pontoon Bridge was built in 1874 by Sir Bradford Leslie.

The Floating Pontoon Bridge was built using timber on pontoon. The bridge was opened to let river traffic through. The bridge had hinged
shore spans since Hooghly River is subjected to tides. During high tides these became very steep. It was also feared that the floating
bridge could affect river currents and cause silting problems. With time the bridge became too inadequate for the ever increasing traffic.

HOWRAH BRIDGE
calcutta

The old pontoon bridge


Construction of the New Howrah Bridge was started on 1937. The Cantilever Era was prevailing at that time, and engineers felts that
Cantilever bridges were more rigid than suspension bridge. This bridge is one of the finest Cantilever bridges in the world - left to India by
the British engineers.

Considering various aspects like navigational, hydraulics, tidal conditions of the river and the projected traffic conditions, Rendel Palmer &
Tritton came up with a design for a Cantilever bridge of 1500 feet, with a 71 feet wide roadway and two 15 feet wide cantilever footways.

The contract was awarded to Cleveland Bridge & Engineering Co. Ltd of Darlington with a strong recommendation that they use Indian-
made steel, which they agreed to do. Out of the total 26,500 tons of steel used, Tata Iron and Steel Company supplied 23,500 tons of steel
and fabrication was done by Braithwaite, Burn and Jessop Co. at four different shops in Calcutta.

The two huge caissons which was sunk (on the first stage of construction) is still the biggest ever sunk caisson on land.

To keep the water out at depth of around the foundations so that construction can be done, around 500 people were employed on the
compressed air operation. The air pressure maintained was about 40 lbs per square inch (2.8 bar).. By the end of 1940 the erection of the
cantilever arms was commenced and was completed in mid-summer of 1941.

The two halves of the suspended span, each long and weighing 2,000 tons, were built in December 1941. 16 hydraulic jacks, each of 800
ton capacity were pressed in to service for joining the two halves of the suspended span.

After completing the steel work of the deck and concreting of roadway. the New Howrah Bridge was finally opened to traffic on February
1943.

Howrah bridge under


HOWRAH BRIDGE construction

calcutta
325 feet 1500 feet 325 feet

280 feet

• Central span 1500 ft between centres of main towers 15 ft wide footpath on either sides of the bridge
• Anchor arm 325ft each
• Cantilever arm 468ft each
• Suspended span 564ft
• Main towers are 280ft high above the monoliths and 76 ft apart at the top
• Bridge deck width 71 ft with two footpaths of 15 ft either side

HOWRAH BRIDGE
calcutta

71ft wide bridge deck or road –


deserted on a bandh in Calcutta
Other features of the Bridge

• All members of the super structure comprise built


up riveted sections with a combination of high
tensile and mild steel
• Between towers bridge deck hangs from panel
points in the lower chord of the main trusses with
a series of hungers (39 pairs)
• Road way beyond the tower is supported on
ground leaving anchor arm free from deck loads
• Bridge deck comprises 71 ft carriage way and 15
ft footway projecting either side of the trusses
and braced by a longitudinal fascia girder.

More about the Bridge

• The deck system consists of cross girders hung


between pairs of hungers with pinned
connection.
• Six rows of longitudinal stringer girders span
between cross girder.
• Floor joists supported transversely on top of
stringers.
• They support a continuous pressed steel
troughing system.
• Over which deck concrete is laid out.

Joint System of Bridge (Expansion Joints)

• Longitudinal expansion and lateral sway movement of the


deck are taken care of by expansion and articulation joints.
• There are two main expansion joints, one at each interface
between the suspended span and the cantilever arms.
HOWRAH BRIDGE • There are expansion joints at the towers and at the interface
of steel and concrete structures at both approach.
calcutta
Articulation Joints

• There are total 8 articulation joints.


• 3 at each of the cantilever arms.
• 2 in the suspended portions.
• They divide the bridge into segments with vertical pin
connection between them to facilitate rotational movements
of the deck.
Camber and Traffic clearance

• Bridge deck has longitudinal ruling gradient of 1 in 40 from either end


• They are joined by a vertical curve of radius 4000 ft.
• Cross gradient of deck is 1 in 48 between kerbs and central 4.9mtr.
is level to provide tramway housing channel in between troughing.

Foundation

• The main tower is founded with single monoliths which are 55.31 x 24.8m
in plan with 21 chambers
• Monoliths at Calcutta and Howrah side are founded 31.41 m and 26.53 m
in below ground level respectively.
• Minimum headroom in carriageway is 5.8 m
• Freeboard for river traffic is 8.8 m

HOWRAH BRIDGE
calcutta

Вам также может понравиться