Вы находитесь на странице: 1из 6

Federal Register / Vol. 71, No.

144 / Thursday, July 27, 2006 / Rules and Regulations 42587

Appendix A
Note: The following Appendix will not be
published in the Code of Federal
Regulations.

LIST OF PETITIONERS REQUESTING REHEARING AND/OR CLARIFICATION


[Petitioner acronyms]

Acronym Name

APPA/NRECA ..................................................... American Public Power Association and the National Rural Electric Cooperative Association.
EEI ...................................................................... Edison Electric Institute.
NARUC ............................................................... National Association of Regulatory Utility Commissioners.
Occidental ........................................................... Occidental Chemical Corporation.
TAPSG ................................................................ Transmission Access Policy Study Group.

[FR Doc. E6–12047 Filed 7–26–06; 8:45 am] Before Commissioners: Joseph T. their open access transmission tariffs
BILLING CODE 6717–01–P Kelliher, Chairman; Nora Mead (OATTs) to include the pro forma SGIP
Brownell, and Suedeen G. Kelly; Order and pro forma SGIA. On November 22,
on Clarification 2005, the Commission issued Order No.
DEPARTMENT OF ENERGY 2006–A, which modified portions of
I. Introduction
Order No. 2006.4
Federal Energy Regulatory 1. This order grants a request for
Commission clarification of Order No. 2006–A II. Background
submitted by Southern California
2. Under Order No. 2006, if the
18 CFR Part 35 Edison (SoCal Edison).1 Order Nos.
proposed interconnection of the
2006 and 2006–A require that all public
utilities that own, control, or operate Interconnection Customer’s Small
[Docket No. RM02–12–002; Order No. 2006– Generating Facility with the
B] facilities used for transmitting electric
energy in interstate commerce 2 have on Transmission Provider’s Transmission
Standardization of Small Generator file with the Commission standard System does not qualify for review
Interconnection Agreements and generator interconnection procedures under the accelerated Fast Track Process
Procedures (pro forma SGIP) and a standard small or the 10 kW Inverter Process, it is
generator interconnection agreement evaluated using industry-standard
Issued July 20, 2006. (pro forma SGIA) for interconnecting interconnection studies. These studies—
AGENCY: Federal Energy Regulatory with the Transmission Provider’s the Feasibility Study, the System Impact
Commission, DOE. Transmission System any Small Study, and the Facilities Study—are
ACTION: Order on clarification. Generating Facility capable of performed by the Transmission Provider
producing no more than 20 megawatts under the pro forma study agreements
SUMMARY: The Federal Energy of power.3 Order No. 2006 requires that in the pro forma SGIP. These study
Regulatory Commission clarifies one all public utilities subject to it modify agreements, to be signed by the
issue regarding Order No. 2006–A. Transmission Provider and
Order Nos. 2006–A and 2006 require all 1 Standardization of Small Generator Interconnection Customer, are similar
public utilities that own, control, or Interconnection Agreements and Procedures, Order to, but less complex than, similar
No. 2006, 70 FR 34189 (June 13, 2005), FERC Stats. agreements for Large Generators
operate facilities for transmitting & Regs. ¶ 31,180 (2005) (Order No. 2006), order on
electric energy in interstate commerce to reh’g, Order No. 2006A, 70 FR 71760 (November 30,
contained in Order No. 2003. The
file revised open access transmission 2005), FERC Stats. & Regs. ¶ 31,196 (2005). Commission developed the pro forma
tariffs containing standard small 2 A public utility is a utility that owns, controls, SGIP and SGIA to offer a simple process
generator interconnection procedures or operates facilities used for transmitting electric for interconnecting Small Generating
energy in interstate commerce, as defined in section Facilities with the nation’s electric
and a standard small generator 201(e) of the Federal Power Act (FPA). 16 U.S.C.
interconnection agreement, and to 824(e) (2000). A non-public utility that seeks grid.5 To this end, the three pro forma
provide interconnection service under voluntary compliance with the reciprocity SGIP study agreements did not include
condition of an open access transmission tariff may boilerplate contract provisions
them to small generating facilities of no satisfy that condition by adopting these procedures
more than 20 megawatts. and agreement, or by filing interconnection rules
4 Comparable documents for generators larger
DATES: Effective Date: August 28, 2006. that substantially conform with, or are superior to,
the pro forma SGIP and pro forma SGIA. than 20 megawatts in size are set forth in Order No.
FOR FURTHER INFORMATION CONTACT: 3 Capitalized terms used in this order have the 2003 and are referred to as the LGIP and LGIA. See
Michael G. Henry (Legal Information), meanings specified in the Glossaries of Terms or the Standardization of Generator Interconnection
text of the pro forma SGIP or the pro forma SGIA. Agreements and Procedures, Order No. 2003, 68 FR
Office of the General Counsel, Federal 49845 (August 19, 2003), FERC Stats. & Regs.
Small Generating Facility means the device for
Energy Regulatory Commission, 888 which the Interconnection Customer (the owner or ¶ 31,146 (2003) (Order No. 2003), order on reh’g,
First Street, NE., Washington, DC 20426. operator of the Small Generating Facility) has Order No. 2003–A, 69 FR 15932 (March 26, 2004),
(202) 502–8532. requested interconnection. The utility with which FERC Stats. & Regs. ¶ 31,160 (2004) (Order No.
the Small Generating Facility is interconnecting is 2003–A), order on reh’g, Order No. 2003–B, 70 FR
Kirk F. Randall, Office of Energy 265 (January 4, 2005), FERC Stats. & Regs. ¶ 31,171
the Transmission Provider. A Small Generating
Markets and Reliability, Federal Energy (2005) (Order No. 2003–B), order on reh’g, Order
jlentini on PROD1PC65 with RULES

Facility is a device used for the production of


Regulatory Commission, 888 First electricity having a capacity of no more than 20 No. 2003–C, 70 FR 37661 (June 30, 2005), FERC
Street, NE., Washington, DC 20426. megawatts. The interconnection process begins Stats. & Regs. ¶ 31,190 (2005) (Order No. 2003–C);
when the Interconnection Customer submits an see also Notice Clarifying Compliance Procedures,
(202) 502–8092. application for interconnection (Interconnection 106 FERC ¶ 61,009 (2004).
SUPPLEMENTARY INFORMATION: Request) to the Transmission Provider. 5 See Order No. 2006 at P 1, 509.

VerDate Aug<31>2005 17:08 Jul 26, 2006 Jkt 208001 PO 00000 Frm 00021 Fmt 4700 Sfmt 4700 E:\FR\FM\27JYR1.SGM 27JYR1
42588 Federal Register / Vol. 71, No. 144 / Thursday, July 27, 2006 / Rules and Regulations

addressing issues such as waiver, Agreement. While this will increase the Transmission Provider must submit an
amendment, and governing law. length of each study agreement, the amendment to its pending filing.
increase in certainty justifies the Independent Transmission Providers
III. Request for Clarification
inclusion of additional legal boilerplate. that have been given an extension of
3. Previously, in its request for 6. We also clarify that section 4 of the time to make Order Nos. 2006 and
rehearing of Order No. 2006, SoCal pro forma SGIP (dealing with matters 2006–A compliance filings beyond the
Edison urged the Commission to adopt such as dispute resolution, effective date of this order must include
miscellaneous boilerplate contract confidentiality, record retention, etc.) the changes to their study agreements in
provisions in the pro forma study also applies to the interconnection that filing.
agreements. It proposed that the study process. These provisions, along 10. Any study agreements signed
Commission include in the pro forma with the contractual provisions being before the effective date of this order are
study agreements the miscellaneous added to the study agreements grandfathered and need not be revised
provisions contained in article 12 of the themselves, provide the parties with a to include the revisions set forth in this
pro forma SGIA. The Commission did way to resolve disputes and the order. All study agreements signed on or
not address this issue in Order No. necessary legal protections should a after the effective date of this order must
2006–A, and on rehearing of that order, dispute arise. include the revisions set forth in this
SoCal Edison repeats its request. order.
IV. Additional Changes to the SGIA
Commission Conclusion VI. Information Collection Statement
7. Finally, we note that articles 1.1
4. We agree with SoCal Edison that through 1.4 of the pro forma SGIA are 11. Order Nos. 2006 and 2006–A
the pro forma SGIP study agreements not listed in the pro forma SGIA’s Table contain information collection
should contain standard legal terms and of Contents. We will correct that here. requirements for which the Commission
conditions. Although these added The corrections to article 1 of the Table obtained approval from the Office of
provisions will lengthen the study of Contents are included as Appendix 4 Management and Budget (OMB). The
agreements, we conclude that their of this order. OMB Control Number for this collection
inclusion will benefit both generators
V. Compliance of information is 1902–0203. By
and Transmission Providers. Since the
clarifying the provisions of Order Nos.
period of time between when the study 8. As in Order No. 2006, the tariffs of 2006 and 2006–A, this order does not
agreements are signed and when the non-independent Transmission make substantive modifications to the
studies are complete is short, we expect Providers will be deemed to have been Commission’s information collection
that including standard legal protections modified to include the revised pro requirements and, accordingly, OMB
will clarify each party’s legal rights forma SGIP study agreements and SGIA approval for this order is not necessary.
under the study agreements and on the effective date of this order. The However, the Commission will send a
minimize disputes. non-independent Transmission Provider copy of this order to OMB for
5. We agree with SoCal Edison that is not required to make any additional informational purposes.
certain of the provisions in article 12 of filing before it is otherwise required to
the SGIA provide the necessary clarity do so by Order No. 2006.7 If a non- VII. Document Availability
and legal protections to the parties, and independent Transmission Provider 12. The Commission will publish the
will therefore adopt several of those seeks to modify the pro forma study full text of this document in the Federal
provisions, with some minor editorial agreements it must make an FPA section Register. Interested persons also may
revisions, into each study agreement. 205 filing explaining why its changes obtain this document from the
Specifically, we will add to each study are ‘‘consistent with or superior to’’ the Commission’s Public Reference Room
agreement articles 12.1 through 12.4 and Commission’s pro forma study during normal business hours (8:30 a.m.
12.6 through 12.8 (including provisions agreements.8 to 5 p.m. Eastern Time) at 888 First
on governing law, amendment, third- 9. Independent Transmission Street, NE., Room 2A, Washington, DC.
party beneficiaries, waiver, multiple Providers will be given an additional 60 This document is also available
counterparts, partnership, and days after the effective date of this order electronically from the Commission’s
severability); as well as articles 12.11 to make conforming changes. If the eLibrary system (http://www.ferc.gov/
and 12.12 (subcontractors and Commission has already acted on the docs-filing/elibrary.asp) in PDF and
reservation of rights).6 We will not independent Transmission Provider’s Microsoft Word format. To access this
include article 12.9 (security Order Nos. 2006 and 2006–A document in eLibrary, type ‘‘RM02–12’’
arrangements) or article 12.10 compliance filing by the effective date in the docket number field and specify
(environmental releases) since neither of of this order, the independent a date range that includes this
these provisions is relevant during the Transmission Provider must make a document’s issuance date. User
study phase of an interconnection new compliance filing to incorporate assistance is available for eLibrary and
project. Nor do we include article 12.5 the new provisions (or request the Commission’s Web site during
(entirety of agreement), since it suggests variation). If the Commission has not yet normal business hours from the
that the SGIP may not be used to acted on the independent Transmission Commission’s Help Line at 202–502–
interpret the parties’ obligations under Provider’s Order Nos. 2006 or 2006–A 8222 or the Public Reference Room at
the study agreements. The new compliance filings, the independent 202–502–8371 Press 0, TTY 202–502–
provisions will become articles 13
8659. E-mail the Public Reference Room
through 21 of the Feasibility Study 7 See Order No. 2006 at P 544 (stating that a non-

independent Transmission Provider wishing to at public.referenceroom@ferc.gov.


Agreement and the System Impact
adopt the pro forma SGIP and pro forma SGIA
Study Agreement; and articles 11 without modification may wait until it complies
VIII. Effective Date
jlentini on PROD1PC65 with RULES

through 19 of the Facilities Study with the Commission’s Electronic Tariff Filings 13. Changes to Order Nos. 2006 and
rulemaking); see also Electronic Tariff Filings,
6 The
revised study agreements (not including Notice of Proposed Rulemaking, 69 FR 43929 (Jul. 2006–A made in this Order on
unchanged attachments) are included as 23, 2004), FERC Stats. & Regs. ¶ 32,575 (2004). Rehearing will become effective on
Appendices 1–3 to this order. 8 See Order No. 2006 at P 546. August 28, 2006.

VerDate Aug<31>2005 17:08 Jul 26, 2006 Jkt 208001 PO 00000 Frm 00022 Fmt 4700 Sfmt 4700 E:\FR\FM\27JYR1.SGM 27JYR1
Federal Register / Vol. 71, No. 144 / Thursday, July 27, 2006 / Rules and Regulations 42589

List of Subjects in 18 CFR Part 35 Transmission Provider reserves the right to 12.0 The Interconnection Customer must
request additional technical information from pay any study costs that exceed the deposit
Electric power rates, Electric utilities, the Interconnection Customer as may without interest within 30 calendar days on
Reporting and recordkeeping reasonably become necessary consistent with receipt of the invoice or resolution of any
requirements. Good Utility Practice during the course of the dispute. If the deposit exceeds the invoiced
By the Commission. feasibility study and as designated in fees, the Transmission Provider shall refund
accordance with the standard Small such excess within 30 calendar days of the
Magalie R. Salas,
Generator Interconnection Procedures. If the invoice without interest.
Secretary. Interconnection Customer modifies its 13.0 Governing Law, Regulatory
Note: The following appendices will not Interconnection Request, the time to Authority, and Rules: The validity,
appear in the Code of Federal Regulations. complete the feasibility study may be interpretation and enforcement of this
extended by agreement of the Parties. Agreement and each of its provisions shall be
5.0 In performing the study, the governed by the laws of the state of
Appendix 1: Revised Feasibility Study Transmission Provider shall rely, to the llllllllll (where the Point of
Agreement extent reasonably practicable, on existing Interconnection is located), without regard to
Attachment 6 studies of recent vintage. The its conflicts of law principles. This
Interconnection Customer shall not be Agreement is subject to all Applicable Laws
Feasibility Study Agreement charged for such existing studies; however, and Regulations. Each Party expressly
THIS AGREEMENT is made and entered the Interconnection Customer shall be reserves the right to seek changes in, appeal,
into this lllday ofllllllll responsible for charges associated with any or otherwise contest any laws, orders, or
20ll by and new study or modifications to existing regulations of a Governmental Authority.
betweenllllllllllllll , a studies that are reasonably necessary to 14.0 Amendment: The Parties may amend
_llllllorganized and existing under perform the feasibility study. this Agreement by a written instrument duly
the laws of the State ofllllllllll , 6.0 The feasibility study report shall executed by both Parties.
(‘‘Interconnection Customer,’’) provide the following analyses for the 15.0 No Third-Party Beneficiaries: This
andllllllllllllll , a purpose of identifying any potential adverse Agreement is not intended to and does not
lllllll; existing under the laws of system impacts that would result from the create rights, remedies, or benefits of any
the State oflllllllll_ , interconnection of the Small Generating character whatsoever in favor of any persons,
(‘‘Transmission Provider’’). Interconnection Facility as proposed: corporations, associations, or entities other
Customer and Transmission Provider each 6.1 Initial identification of any circuit than the Parties, and the obligations herein
may be referred to as a ‘‘Party,’’ or breaker short circuit capability limits assumed are solely for the use and benefit of
collectively as the ‘‘Parties.’’ exceeded as a result of the interconnection; the Parties, their successors in interest and
6.2 Initial identification of any thermal where permitted, their assigns.
Recitals overload or voltage limit violations resulting 16.0 Waiver
WHEREAS, Interconnection Customer is from the interconnection; 16.1 The failure of a Party to this
proposing to develop a Small Generating 6.3 Initial review of grounding Agreement to insist, on any occasion, upon
Facility or generating capacity addition to an requirements and electric system protection; strict performance of any provision of this
existing Small Generating Facility consistent and Agreement will not be considered a waiver
with the Interconnection Request completed 6.4 Description and non-binding estimated of any obligation, right, or duty of, or
by Interconnection Customer on cost of facilities required to interconnect the imposed upon, such Party.
_lllllllll ; and proposed Small Generating Facility and to 16.2 Any waiver at any time by either
WHEREAS, Interconnection Customer address the identified short circuit and Party of its rights with respect to this
desires to interconnect the Small Generating power flow issues. Agreement shall not be deemed a continuing
Facility with the Transmission Provider’s 7.0 The feasibility study shall model the waiver or a waiver with respect to any other
Transmission System; and impact of the Small Generating Facility failure to comply with any other obligation,
WHEREAS, Interconnection Customer has regardless of purpose in order to avoid the right, duty of this Agreement. Termination or
requested the Transmission Provider to further expense and interruption of operation default of this Agreement for any reason by
perform a feasibility study to assess the for reexamination of feasibility and impacts Interconnection Customer shall not
feasibility of interconnecting the proposed if the Interconnection Customer later changes constitute a waiver of the Interconnection
Small Generating Facility with the the purpose for which the Small Generating Customer’s legal rights to obtain an
Transmission Provider’s Transmission Facility is being installed. interconnection from the Transmission
System, and of any Affected Systems; 8.0 The study shall include the feasibility Provider. Any waiver of this Agreement
NOW, THEREFORE, in consideration of of any interconnection at a proposed project shall, if requested, be provided in writing.
and subject to the mutual covenants site where there could be multiple potential 17.0 Multiple Counterparts: This
contained herein the Parties agreed as Points of Interconnection, as requested by the Agreement may be executed in two or more
follows: Interconnection Customer and at the counterparts, each of which is deemed an
1.0 When used in this Agreement, with Interconnection Customer’s cost. original but all constitute one and the same
initial capitalization, the terms specified 9.0 A deposit of the lesser of 50 percent instrument.
shall have the meanings indicated or the of good faith estimated feasibility study costs 18.0 No Partnership: This Agreement
meanings specified in the standard Small or earnest money of $1,000 may be required shall not be interpreted or construed to create
Generator Interconnection Procedures. from the Interconnection Customer. an association, joint venture, agency
2.0 The Interconnection Customer elects 10.0 Once the feasibility study is relationship, or partnership between the
and the Transmission Provider shall cause to completed, a feasibility study report shall be Parties or to impose any partnership
be performed an interconnection feasibility prepared and transmitted to the obligation or partnership liability upon either
study consistent the standard Small Interconnection Customer. Barring unusual Party. Neither Party shall have any right,
Generator Interconnection Procedures in circumstances, the feasibility study must be power or authority to enter into any
accordance with the Open Access completed and the feasibility study report agreement or undertaking for, or act on behalf
Transmission Tariff. transmitted within 30 Business Days of the of, or to act as or be an agent or
3.0 The scope of the feasibility study Interconnection Customer’s agreement to representative of, or to otherwise bind, the
shall be subject to the assumptions set forth conduct a feasibility study. other Party.
in Attachment A to this Agreement. 11.0 Any study fees shall be based on the 19.0 Severability: If any provision or
jlentini on PROD1PC65 with RULES

4.0 The feasibility study shall be based on Transmission Provider’s actual costs and will portion of this Agreement shall for any
the technical information provided by the be invoiced to the Interconnection Customer reason be held or adjudged to be invalid or
Interconnection Customer in the after the study is completed and delivered illegal or unenforceable by any court of
Interconnection Request, as may be modified and will include a summary of professional competent jurisdiction or other
as the result of the scoping meeting. The time. Governmental Authority, (1) such portion or

VerDate Aug<31>2005 16:25 Jul 26, 2006 Jkt 208001 PO 00000 Frm 00023 Fmt 4700 Sfmt 4700 E:\FR\FM\27JYR1.SGM 27JYR1
42590 Federal Register / Vol. 71, No. 144 / Thursday, July 27, 2006 / Rules and Regulations

provision shall be deemed separate and Name (Printed): lllllllllllll Utility Practice during the course of the
independent, (2) the Parties shall negotiate in Title: llllllllllllllllll system impact study. If the Interconnection
good faith to restore insofar as practicable the Customer modifies its designated Point of
benefits to each Party that were affected by Appendix 2: Revised System Impact Interconnection, Interconnection Request, or
such ruling, and (3) the remainder of this Study Agreement the technical information provided therein is
Agreement shall remain in full force and Attachment 7 modified, the time to complete the system
effect. impact study may be extended.
20.0 Subcontractors: Nothing in this System Impact Study Agreement 5.0 A system impact study shall consist
Agreement shall prevent a Party from THIS AGREEMENT is made and entered of a short circuit analysis, a stability analysis,
utilizing the services of any subcontractor as into this lll day of llllllll a power flow analysis, voltage drop and
it deems appropriate to perform its 20ll by and between flicker studies, protection and set point
obligations under this Agreement; provided, llllllllllllll , a coordination studies, and grounding reviews,
however, that each Party shall require its lllllll organized and existing under as necessary. A system impact study shall
subcontractors to comply with all applicable the laws of the State of state the assumptions upon which it is based,
terms and conditions of this Agreement in llllllllll , (‘‘Interconnection state the results of the analyses, and provide
providing such services and each Party shall Customer,’’) and the requirement or potential impediments to
remain primarily liable to the other Party for llllllllllllll , a providing the requested interconnection
the performance of such subcontractor. lllllll existing under the laws of the service, including a preliminary indication of
the cost and length of time that would be
20.1 The creation of any subcontract State of llllllllll ,
relationship shall not relieve the hiring Party necessary to correct any problems identified
(’’Transmission Provider’’). Interconnection
of any of its obligations under this in those analyses and implement the
Customer and Transmission Provider each
Agreement. The hiring Party shall be fully interconnection. A system impact study shall
may be referred to as a ‘‘Party,’’ or
responsible to the other Party for the acts or provide a list of facilities that are required as
collectively as the ‘‘Parties.’’
omissions of any subcontractor the hiring a result of the Interconnection Request and
Party hires as if no subcontract had been Recitals non-binding good faith estimates of cost
made; provided, however, that in no event WHEREAS, the Interconnection Customer responsibility and time to construct.
is proposing to develop a Small Generating 6.0 A distribution system impact study
shall the Transmission Provider be liable for
shall incorporate a distribution load flow
the actions or inactions of the Facility or generating capacity addition to an
study, an analysis of equipment interrupting
Interconnection Customer or its existing Small Generating Facility consistent
ratings, protection coordination study,
subcontractors with respect to obligations of with the Interconnection Request completed
voltage drop and flicker studies, protection
the Interconnection Customer under this by the Interconnection Customer on
and set point coordination studies, grounding
Agreement. Any applicable obligation llllllllll ; and
reviews, and the impact on electric system
imposed by this Agreement upon the hiring WHEREAS, the Interconnection Customer
operation, as necessary.
Party shall be equally binding upon, and desires to interconnect the Small Generating
7.0 Affected Systems may participate in
shall be construed as having application to, Facility with the Transmission Provider’s
the preparation of a system impact study,
any subcontractor of such Party. Transmission System;
with a division of costs among such entities
20.2 The obligations under this article WHEREAS, the Transmission Provider has as they may agree. All Affected Systems shall
will not be limited in any way by any completed a feasibility study and provided be afforded an opportunity to review and
limitation of subcontractor’s insurance. the results of said study to the comment upon a system impact study that
21.0 Reservation of Rights: The Interconnection Customer (This recital to be covers potential adverse system impacts on
Transmission Provider shall have the right to omitted if the Parties have agreed to forego their electric systems, and the Transmission
make a unilateral filing with FERC to modify the feasibility study.); and Provider has 20 additional Business Days to
this Agreement with respect to any rates, WHEREAS, the Interconnection Customer complete a system impact study requiring
terms and conditions, charges, classifications has requested the Transmission Provider to review by Affected Systems.
of service, rule or regulation under section perform a system impact study(s) to assess 8.0 If the Transmission Provider uses a
205 or any other applicable provision of the the impact of interconnecting the Small queuing procedure for sorting or prioritizing
Federal Power Act and FERC’s rules and Generating Facility with the Transmission projects and their associated cost
regulations thereunder, and the Provider’s Transmission System, and of any responsibilities for any required Network
Interconnection Customer shall have the Affected Systems; Upgrades, the system impact study shall
right to make a unilateral filing with FERC NOW, THEREFORE, in consideration of consider all generating facilities (and with
to modify this Agreement under any and subject to the mutual covenants respect to paragraph 8.3 below, any
applicable provision of the Federal Power contained herein the Parties agreed as identified Upgrades associated with such
Act and FERC’s rules and regulations; follows: higher queued interconnection) that, on the
provided that each Party shall have the right 1.0 When used in this Agreement, with date the system impact study is
to protest any such filing by the other Party initial capitalization, the terms specified commenced—
and to participate fully in any proceeding shall have the meanings indicated or the 8.1 Are directly interconnected with the
before FERC in which such modifications meanings specified in the standard Small Transmission Provider’s electric system; or
may be considered. Nothing in this Generator Interconnection Procedures. 8.2 Are interconnected with Affected
Agreement shall limit the rights of the Parties 2.0 The Interconnection Customer elects Systems and may have an impact on the
or of FERC under sections 205 or 206 of the and the Transmission Provider shall cause to proposed interconnection; and
Federal Power Act and FERC’s rules and be performed a system impact study(s) 8.3 Have a pending higher queued
regulations, except to the extent that the consistent with the standard Small Generator Interconnection Request to interconnect with
Parties otherwise agree as provided herein. Interconnection Procedures in accordance the Transmission Provider’s electric system.
IN WITNESS WHEREOF, the Parties have with the Open Access Transmission Tariff. 9.0 A distribution system impact study, if
caused this Agreement to be duly executed 3.0 The scope of a system impact study required, shall be completed and the results
by their duly authorized officers or agents on shall be subject to the assumptions set forth transmitted to the Interconnection Customer
the day and year first above written. in Attachment A to this Agreement. within 30 Business Days after this Agreement
[Insert name of Transmission Provider] 4.0 A system impact study will be based is signed by the Parties. A transmission
upon the results of the feasibility study and system impact study, if required, shall be
lllllllllllllllllllll
the technical information provided by completed and the results transmitted to the
Signed: lllllllllllllllll
Interconnection Customer in the Interconnection Customer within 45 Business
Name (Printed): lllllllllllll
jlentini on PROD1PC65 with RULES

Interconnection Request. The Transmission Days after this Agreement is signed by the
Title: llllllllllllllllll
Provider reserves the right to request Parties, or in accordance with the
[Insert name of Interconnection Customer] additional technical information from the Transmission Provider’s queuing procedures.
lllllllllllllllllllll Interconnection Customer as may reasonably 10.0 A deposit of the equivalent of the
Signed: lllllllllllllllll become necessary consistent with Good good faith estimated cost of a distribution

VerDate Aug<31>2005 16:25 Jul 26, 2006 Jkt 208001 PO 00000 Frm 00024 Fmt 4700 Sfmt 4700 E:\FR\FM\27JYR1.SGM 27JYR1
Federal Register / Vol. 71, No. 144 / Thursday, July 27, 2006 / Rules and Regulations 42591

system impact study and the one half the agreement or undertaking for, or act on behalf [Insert name of Interconnection Customer]
good faith estimated cost of a transmission of, or to act as or be an agent or lllllllllllllllllllll
system impact study may be required from representative of, or to otherwise bind, the Signed: lllllllllllllllll
the Interconnection Customer. other Party. Name (Printed): lllllllllllll
11.0 Any study fees shall be based on the 19.0 Severability: If any provision or Title: llllllllllllllllll
Transmission Provider’s actual costs and will portion of this Agreement shall for any
be invoiced to the Interconnection Customer reason be held or adjudged to be invalid or Appendix 3: Revised Facilities Study
after the study is completed and delivered illegal or unenforceable by any court of Agreement
and will include a summary of professional competent jurisdiction or other
time. Governmental Authority, (1) such portion or Attachment 8
12.0 The Interconnection Customer must provision shall be deemed separate and Facilities Study Agreement
pay any study costs that exceed the deposit independent, (2) the Parties shall negotiate in
without interest within 30 calendar days on good faith to restore insofar as practicable the THIS AGREEMENT is made and entered
receipt of the invoice or resolution of any benefits to each Party that were affected by into this lll day of llllllll 20
dispute. If the deposit exceeds the invoiced such ruling, and (3) the remainder of this ll by and between
fees, the Transmission Provider shall refund Agreement shall remain in full force and llllllllllllll , a
such excess within 30 calendar days of the effect. lllllll organized and existing under
invoice without interest. 20.0 Subcontractors: Nothing in this the laws of the State of
13.0 Governing Law, Regulatory Agreement shall prevent a Party from llllllllll , (‘‘Interconnection
Authority, and Rules: The validity, utilizing the services of any subcontractor as Customer,’’) and
interpretation and enforcement of this it deems appropriate to perform its llllllllllllll , a
Agreement and each of its provisions shall be obligations under this Agreement; provided, lllllll existing under the laws of the
governed by the laws of the state of __(where however, that each Party shall require its State of llllllllll ,
the Point of Interconnection is located), subcontractors to comply with all applicable (‘‘Transmission Provider’’). Interconnection
without regard to its conflicts of law terms and conditions of this Agreement in Customer and Transmission Provider each
principles. This Agreement is subject to all providing such services and each Party shall may be referred to as a ‘‘Party,’’ or
Applicable Laws and Regulations. Each Party remain primarily liable to the other Party for collectively as the ‘‘Parties.’’
expressly reserves the right to seek changes the performance of such subcontractor. Recitals
in, appeal, or otherwise contest any laws, 20.1 The creation of any subcontract
relationship shall not relieve the hiring Party WHEREAS, the Interconnection Customer
orders, or regulations of a Governmental
of any of its obligations under this is proposing to develop a Small Generating
Authority.
Agreement. The hiring Party shall be fully Facility or generating capacity addition to an
14.0 Amendment: The Parties may amend
responsible to the other Party for the acts or existing Small Generating Facility consistent
this Agreement by a written instrument duly
omissions of any subcontractor the hiring with the Interconnection Request completed
executed by both Parties.
Party hires as if no subcontract had been by the Interconnection Customer on
15.0 No Third-Party Beneficiaries: This llllllllll ; and
Agreement is not intended to and does not made; provided, however, that in no event
shall the Transmission Provider be liable for WHEREAS, the Interconnection Customer
create rights, remedies, or benefits of any desires to interconnect the Small Generating
character whatsoever in favor of any persons, the actions or inactions of the
Interconnection Customer or its Facility with the Transmission Provider’s
corporations, associations, or entities other Transmission System;
than the Parties, and the obligations herein subcontractors with respect to obligations of
the Interconnection Customer under this WHEREAS, the Transmission Provider has
assumed are solely for the use and benefit of completed a system impact study and
the Parties, their successors in interest and Agreement. Any applicable obligation
imposed by this Agreement upon the hiring provided the results of said study to the
where permitted, their assigns. Interconnection Customer; and
16.0 Waiver Party shall be equally binding upon, and
shall be construed as having application to, WHEREAS, the Interconnection Customer
16.1 The failure of a Party to this has requested the Transmission Provider to
Agreement to insist, on any occasion, upon any subcontractor of such Party.
20.2 The obligations under this article perform a facilities study to specify and
strict performance of any provision of this estimate the cost of the equipment,
Agreement will not be considered a waiver will not be limited in any way by any
limitation of subcontractor’s insurance. engineering, procurement and construction
of any obligation, right, or duty of, or work needed to implement the conclusions
imposed upon, such Party. 21.0 Reservation of Rights: The
Transmission Provider shall have the right to of the system impact study in accordance
16.2 Any waiver at any time by either with Good Utility Practice to physically and
Party of its rights with respect to this make a unilateral filing with FERC to modify
this Agreement with respect to any rates, electrically connect the Small Generating
Agreement shall not be deemed a continuing Facility with the Transmission Provider’s
waiver or a waiver with respect to any other terms and conditions, charges, classifications
of service, rule or regulation under section Transmission System.
failure to comply with any other obligation, NOW, THEREFORE, in consideration of
right, duty of this Agreement. Termination or 205 or any other applicable provision of the
Federal Power Act and FERC’s rules and and subject to the mutual covenants
default of this Agreement for any reason by contained herein the Parties agreed as
Interconnection Customer shall not regulations thereunder, and the
Interconnection Customer shall have the follows:
constitute a waiver of the Interconnection 1.0 When used in this Agreement, with
Customer’s legal rights to obtain an right to make a unilateral filing with FERC
to modify this Agreement under any initial capitalization, the terms specified
interconnection from the Transmission shall have the meanings indicated or the
applicable provision of the Federal Power
Provider. Any waiver of this Agreement meanings specified in the standard Small
Act and FERC’s rules and regulations;
shall, if requested, be provided in writing. Generator Interconnection Procedures.
provided that each Party shall have the right
17.0 Multiple Counterparts: This 2.0 The Interconnection Customer elects
to protest any such filing by the other Party
Agreement may be executed in two or more and the Transmission Provider shall cause a
and to participate fully in any proceeding
counterparts, each of which is deemed an facilities study consistent with the standard
before FERC in which such modifications
original but all constitute one and the same Small Generator Interconnection Procedures
IN WITNESS THEREOF, the Parties have
instrument. to be performed in accordance with the Open
caused this Agreement to be duly executed
18.0 No Partnership: This Agreement Access Transmission Tariff.
by their duly authorized officers or agents on
shall not be interpreted or construed to create 3.0 The scope of the facilities study shall
the day and year first above written.
an association, joint venture, agency be subject to data provided in Attachment A
jlentini on PROD1PC65 with RULES

relationship, or partnership between the [Insert name of Transmission Provider] to this Agreement.
Parties or to impose any partnership lllllllllllllllllllll 4.0 The facilities study shall specify and
obligation or partnership liability upon either Signed: lllllllllllllllll estimate the cost of the equipment,
Party. Neither Party shall have any right, Name (Printed): lllllllllllll engineering, procurement and construction
power or authority to enter into any Title: llllllllllllllllll work (including overheads) needed to

VerDate Aug<31>2005 16:25 Jul 26, 2006 Jkt 208001 PO 00000 Frm 00025 Fmt 4700 Sfmt 4700 E:\FR\FM\27JYR1.SGM 27JYR1
42592 Federal Register / Vol. 71, No. 144 / Thursday, July 27, 2006 / Rules and Regulations

implement the conclusions of the system than the Parties, and the obligations herein subcontractors with respect to obligations of
impact study(s). The facilities study shall assumed are solely for the use and benefit of the Interconnection Customer under this
also identify (1) the electrical switching the Parties, their successors in interest and Agreement. Any applicable obligation
configuration of the equipment, including, where permitted, their assigns. imposed by this Agreement upon the hiring
without limitation, transformer, switchgear, 14.0 Waiver Party shall be equally binding upon, and
meters, and other station equipment, (2) the 14.1 The failure of a Party to this
shall be construed as having application to,
nature and estimated cost of the Agreement to insist, on any occasion, upon
Transmission Provider’s Interconnection strict performance of any provision of this any subcontractor of such Party.
Facilities and Upgrades necessary to Agreement will not be considered a waiver 18.2 The obligations under this article
accomplish the interconnection, and (3) an of any obligation, right, or duty of, or will not be limited in any way by any
estimate of the time required to complete the imposed upon, such Party. limitation of subcontractor’s insurance.
construction and installation of such 14.2 Any waiver at any time by either 19.0 Reservation of Rights: The
facilities. Party of its rights with respect to this Transmission Provider shall have the right to
5.0 The Transmission Provider may Agreement shall not be deemed a continuing make a unilateral filing with FERC to modify
propose to group facilities required for more waiver or a waiver with respect to any other this Agreement with respect to any rates,
than one Interconnection Customer in order failure to comply with any other obligation, terms and conditions, charges, classifications
to minimize facilities costs through right, duty of this Agreement. Termination or
of service, rule or regulation under section
economies of scale, but any Interconnection default of this Agreement for any reason by
Customer may require the installation of Interconnection Customer shall not 205 or any other applicable provision of the
facilities required for its own Small constitute a waiver of the Interconnection Federal Power Act and FERC’s rules and
Generating Facility if it is willing to pay the Customer’s legal rights to obtain an regulations thereunder, and the
costs of those facilities. interconnection from the Transmission Interconnection Customer shall have the
6.0 A deposit of the good faith estimated Provider. Any waiver of this Agreement right to make a unilateral filing with FERC
facilities study costs may be required from shall, if requested, be provided in writing. to modify this Agreement under any
the Interconnection Customer. 15.0 Multiple Counterparts: This applicable provision of the Federal Power
7.0 In cases where Upgrades are required, Agreement may be executed in two or more Act and FERC’s rules and regulations;
the facilities study must be completed within counterparts, each of which is deemed an provided that each Party shall have the right
45 Business Days of the receipt of this original but all constitute one and the same
to protest any such filing by the other Party
Agreement. In cases where no Upgrades are instrument.
and to participate fully in any proceeding
necessary, and the required facilities are 16.0 No Partnership: This Agreement
limited to Interconnection Facilities, the shall not be interpreted or construed to create before FERC in which such modifications
facilities study must be completed within 30 an association, joint venture, agency IN WITNESS WHEREOF, the Parties have
Business Days. relationship, or partnership between the caused this Agreement to be duly executed
8.0 Once the facilities study is completed, Parties or to impose any partnership by their duly authorized officers or agents on
a facilities study report shall be prepared and obligation or partnership liability upon either the day and year first above written.
transmitted to the Interconnection Customer. Party. Neither Party shall have any right, [Insert name of Transmission Provider]
Barring unusual circumstances, the facilities power or authority to enter into any
study must be completed and the facilities agreement or undertaking for, or act on behalf lllllllllllllllllllll
study report transmitted within 30 Business of, or to act as or be an agent or Signed: lllllllllllllllll
Days of the Interconnection Customer’s representative of, or to otherwise bind, the Name (Printed): lllllllllllll
agreement to conduct a facilities study. other Party. Title: llllllllllllllllll
9.0 Any study fees shall be based on the 17.0 Severability: If any provision or [Insert name of Interconnection Customer] l
Transmission Provider’s actual costs and will portion of this Agreement shall for any lllllllllllllllllllll
be invoiced to the Interconnection Customer reason be held or adjudged to be invalid or Signed: lllllllllllllllll
after the study is completed and delivered illegal or unenforceable by any court of
Name (Printed): lllllllllllll
and will include a summary of professional competent jurisdiction or other
Title: llllllllllllllllll
time. Governmental Authority, (1) such portion or
10.0 The Interconnection Customer must provision shall be deemed separate and Appendix 4: Revised Table of Contents
pay any study costs that exceed the deposit independent, (2) the Parties shall negotiate in for Article 1 of the SGIA
without interest within 30 calendar days on good faith to restore insofar as practicable the
receipt of the invoice or resolution of any benefits to each Party that were affected by Table of Contents
dispute. If the deposit exceeds the invoiced such ruling, and (3) the remainder of this Page No.
fees, the Transmission Provider shall refund Agreement shall remain in full force and
Article 1. Scope and Limitations
such excess within 30 calendar days of the effect.
of Agreement ............................ 1
invoice without interest. 18.0 Subcontractors: Nothing in this
11.0 Governing Law, Regulatory Agreement shall prevent a Party from 1.1 Applicability .................... 1
Authority, and Rules: The validity, utilizing the services of any subcontractor as 1.2 Purpose ............................ 1
interpretation and enforcement of this it deems appropriate to perform its 1.3 No Agreement to Pur-
Agreement and each of its provisions shall be obligations under this Agreement; provided, chase or Deliver Power ........ 1
governed by the laws of the state of however, that each Party shall require its 1.4 Limitations ....................... 1
llllllllll (where the Point of subcontractors to comply with all applicable 1.5 Responsibilities of the
Interconnection is located), without regard to terms and conditions of this Agreement in Parties ................................... 2
its conflicts of law principles. This providing such services and each Party shall 1.6 Parallel Operation Obli-
Agreement is subject to all Applicable Laws remain primarily liable to the other Party for gations ................................... 2
and Regulations. Each Party expressly the performance of such subcontractor. 1.7 Metering ........................... 3
reserves the right to seek changes in, appeal, 18.1 The creation of any subcontract 1.8 Reactive Power ................ 3
or otherwise contest any laws, orders, or relationship shall not relieve the hiring Party
regulations of a Governmental Authority. of any of its obligations under this [FR Doc. E6–11989 Filed 7–26–06; 8:45 am]
12.0 Amendment: The Parties may amend Agreement. The hiring Party shall be fully BILLING CODE 6717–01–P
this Agreement by a written instrument duly responsible to the other Party for the acts or
executed by both Parties. omissions of any subcontractor the hiring
jlentini on PROD1PC65 with RULES

13.0 No Third-Party Beneficiaries: This Party hires as if no subcontract had been


Agreement is not intended to and does not made; provided, however, that in no event
create rights, remedies, or benefits of any shall the Transmission Provider be liable for
character whatsoever in favor of any persons, the actions or inactions of the
corporations, associations, or entities other Interconnection Customer or its

VerDate Aug<31>2005 16:25 Jul 26, 2006 Jkt 208001 PO 00000 Frm 00026 Fmt 4700 Sfmt 4700 E:\FR\FM\27JYR1.SGM 27JYR1

Вам также может понравиться