Академический Документы
Профессиональный Документы
Культура Документы
24-July-2014 / 1
Agenda
1.
Introduction
Challenge 1
2.
3.
System Design
Challenge 3
4.
Summary
24-July-2014 / 2
Introduction
24-July-2014 / 3
24-July-2014 / 4
Improve reliability
Simpler rolling stock Fewer moving parts to go wrong
Greener
Less CO2 emissions and less noise pollution
Regenerative breaking benefit
Better journeys
More seats and faster journeys
24-July-2014 / 5
Welsh Valleys
Edinburgh to Glasgow
Electric Spine
Infill schemes
24-July-2014 / 6
Challenge 1
24-July-2014 / 7
Volume of Work
Biggest programme for a generation
Electrification Investment
4 Billion
260 Million
CP4
CP5
24-July-2014 / 8
Enablers
Rail electrification development group
24-July-2014 / 9
Rail Electrification
Systems
24-July-2014 / 10
Why AC?
Better efficiency
24-July-2014 / 11
BOOSTER
TRANSFORMER
RETURN CONDUCTOR
CONTACT WIRE
RAIL
FEEDER
STATION
24-July-2014 / 12
24-July-2014 / 13
Autotransformer System
AUTOTRANSFORMER
1.5 I
0.5 I
CONTACT WIRE
2I
0.5 I
0.5 I
0.5 I
RAIL
0.5 I
0.5 I
AUXILIARY FEEDER
FEEDER
STATION
24-July-2014 / 14
Autotransformer System
24-July-2014 / 15
AT / BT Impedance Profile
10
MPTSC
ATS
ATS
SATS
FS
ATS
ATS
ATFS / FS
-10
FS
ATS
ATS
MPATS
TSC
TSC
MPTSC
TSC
TSC
MPTSC
TSC
SATS
ATS
ATS
TSC
8
MPATS
Impedance [ohms]
10
MPTSC
12
0
-60
-50
-40
-30
-20
20
30
40
50
60
Distance [km]
24-July-2014 / 16
Challenge 2
24-July-2014 / 17
Energy Risk
Supply shortage leading to Brownouts
Electricity price rise
24-July-2014 / 18
Enablers
Largest single consumer of electricity in UK
24-July-2014 / 19
System Design
24-July-2014 / 20
Strategic view
24-July-2014 / 21
Technical Requirements
Technical Specifications for Interoperability
Voltage regulation
Energy loss
24-July-2014 / 22
24-July-2014 / 23
24-July-2014 / 24
Transformer utilisation
compliant.
Analysis supports capacity
headroom definition.
24-July-2014 / 25
24-July-2014 / 26
24-July-2014 / 27
24-July-2014 / 28
Fault Analysis
- Nominal fault level is 300 MVA (12 kA) [Network Rail Policy]
24-July-2014 / 29
Energy Loss
- Portion of active power provided by GSP not transferred to train pantographs
24-July-2014 / 30
Electromagnetic Induction
24-July-2014 / 31
24-July-2014 / 32
Challenge 3
24-July-2014 / 33
24-July-2014 / 34
Enablers
Need tools that well suited to future planning and option analysis
Technological innovation
24-July-2014 / 35
To identify better whole life cost options that may span multiple
control periods.
To move away from project by project timetable specific TP
enhancements.
To demonstrate to the regulator that our power projects are aligned to
the future needs of the railway.
To allow the Energy industry to have a better understanding of our
future energy needs.
To develop the fundamental system design early to allow projects to
focus on delivering and implementing the detailed design.
24-July-2014 / 36
Communication
IEC 61850
A standard architecture for communication
networks and systems in substations.
Marshalling
Rugged Ethernet Switch
A typical device (harden for use within a railway
substation environment) is shown which directs
Ethernet network traffic.
24-July-2014 / 37
24-July-2014 / 38
Summary
1.
2.
Challenges ahead
3.
24-July-2014 / 39