Вы находитесь на странице: 1из 39

Railway Electrification Programme - The System Design Challenge

Railway Electrification Programme


- The System Design Challenge

24-July-2014 / 1

Railway Electrification Programme - The System Design Challenge

Agenda
1.

Introduction
Challenge 1

2.

Rail Electrification Systems


Challenge 2

3.

System Design
Challenge 3

4.

Summary

24-July-2014 / 2

Railway Electrification Programme - The System Design Challenge

Introduction

24-July-2014 / 3

Railway Electrification Programme - The System Design Challenge

Network Rail Who we are


Britain relies on rail

We own and operate Britains railway infrastructure

We are constantly maintaining and improving the railway for


customers

We aim to provide a safe, reliable and efficient railway

24-July-2014 / 4

Railway Electrification Programme - The System Design Challenge

Why Electrify the Railway?


Reduce long term costs
Rolling stock is cheaper to run and maintain
Lighter rolling stock so less damage to the track

Improve reliability
Simpler rolling stock Fewer moving parts to go wrong

Greener
Less CO2 emissions and less noise pollution
Regenerative breaking benefit

Better journeys
More seats and faster journeys

24-July-2014 / 5

Railway Electrification Programme - The System Design Challenge

Railway Electrification Programme


Great Western

North West & Trans-Pennine

Welsh Valleys

Edinburgh to Glasgow

Electric Spine

Infill schemes

24-July-2014 / 6

Railway Electrification Programme - The System Design Challenge

Challenge 1

24-July-2014 / 7

Railway Electrification Programme - The System Design Challenge

Volume of Work
Biggest programme for a generation

Electrification Investment
4 Billion

260 Million

CP4

CP5

24-July-2014 / 8

Railway Electrification Programme - The System Design Challenge

Enablers
Rail electrification development group

Addressing skills, resources and other issues

Sharing good practice and building a collaborative electrification


community

24-July-2014 / 9

Railway Electrification Programme - The System Design Challenge

Rail Electrification
Systems

24-July-2014 / 10

Railway Electrification Programme - The System Design Challenge

Why AC?
Better efficiency

Supports faster and high density traffic

Lower capital, operating and renewal costs

24-July-2014 / 11

Railway Electrification Programme - The System Design Challenge

Booster Transformer System

BOOSTER
TRANSFORMER

RETURN CONDUCTOR

CONTACT WIRE

RAIL
FEEDER
STATION

24-July-2014 / 12

Railway Electrification Programme - The System Design Challenge

Booster Transformer System

24-July-2014 / 13

Railway Electrification Programme - The System Design Challenge

Autotransformer System

AUTOTRANSFORMER

1.5 I

0.5 I

CONTACT WIRE

2I

0.5 I

0.5 I

0.5 I

RAIL

0.5 I

0.5 I

AUXILIARY FEEDER

FEEDER
STATION

24-July-2014 / 14

Railway Electrification Programme - The System Design Challenge

Autotransformer System

24-July-2014 / 15

Railway Electrification Programme - The System Design Challenge

AT / BT Impedance Profile

10

MPTSC
ATS

ATS

SATS

FS

ATS

ATS

ATFS / FS

-10

FS

ATS

ATS

MPATS

TSC

TSC

MPTSC
TSC

TSC

MPTSC
TSC
SATS

ATS

ATS

TSC

8
MPATS

Impedance [ohms]

10

MPTSC

12

0
-60

-50

-40

-30

-20

20

30

40

50

60

Distance [km]

24-July-2014 / 16

Railway Electrification Programme - The System Design Challenge

Challenge 2

24-July-2014 / 17

Railway Electrification Programme - The System Design Challenge

Energy Risk
Supply shortage leading to Brownouts
Electricity price rise

24-July-2014 / 18

Railway Electrification Programme - The System Design Challenge

Enablers
Largest single consumer of electricity in UK

Asset portfolio comparable to DNO

Opportunities in new technology and utilisation of our networks

24-July-2014 / 19

Railway Electrification Programme - The System Design Challenge

System Design

24-July-2014 / 20

Railway Electrification Programme - The System Design Challenge

Traction Power Modelling


Assessment of the impact of future
services on existing and proposed
infrastructure

Propose and analyse electrification


enhancements

Strategic view

24-July-2014 / 21

Railway Electrification Programme - The System Design Challenge

Technical Requirements
Technical Specifications for Interoperability

Bulk supply point assessment

Negative Phase Sequence

Equipment loading assessment

Voltage regulation

Rail potentials and induced voltages

Energy loss

24-July-2014 / 22

Railway Electrification Programme - The System Design Challenge

Example Compliance Outputs


From Western Route Traction
Power System Strategy

24-July-2014 / 23

Railway Electrification Programme - The System Design Challenge

Didcot GSP Feeding Area


- Simplified to support slides which follow

24-July-2014 / 24

Railway Electrification Programme - The System Design Challenge

Demand Analysis Didcot Morning Peak


- GSP transformer naturally cooled ONAN rating 80 MVA

Transformer utilisation
compliant.
Analysis supports capacity
headroom definition.

24-July-2014 / 25

Railway Electrification Programme - The System Design Challenge

Voltage Analysis Train Scatter Plot


- Minimum voltage compliance limit 19 kV [EN 50119:2009]

Train pantograph voltages


compliant.
Voltage decays away from
supply point, with the
largest voltage drop at
extremities of feeding
area. This places a limit
on how far a supply point
can feed since train
performance deteriorates
at lower voltages.

24-July-2014 / 26

Railway Electrification Programme - The System Design Challenge

Earth Potential Analysis


- Load conditions compliance limit 60 V [EN 50122-1]

Safe touch potentials on


rails compliant.
Jump in rail voltages is
because Didcot is the
point where the railway
changes from four tracks
to two tracks, hence larger
rail impedance.

24-July-2014 / 27

Railway Electrification Programme - The System Design Challenge

Electromagnetic Induction Analysis


- Fault conditions compliance limit 645 V [EN 50122-1] for safe touch potentials

Safe touch potentials on


lineside cables compliant.
Again jump in voltages is
because Didcot is the
point where the railway
changes from four tracks
to two tracks, hence larger
rail impedance.

24-July-2014 / 28

Railway Electrification Programme - The System Design Challenge

Fault Analysis
- Nominal fault level is 300 MVA (12 kA) [Network Rail Policy]

washing line appearance


is a result of lower
impedance at intermediate
autotransformer sites due
to paralleling.

24-July-2014 / 29

Railway Electrification Programme - The System Design Challenge

Energy Loss
- Portion of active power provided by GSP not transferred to train pantographs

Supports whole life cost


assessment of system.

24-July-2014 / 30

Railway Electrification Programme - The System Design Challenge

Electromagnetic Induction

24-July-2014 / 31

Railway Electrification Programme - The System Design Challenge

Return Screen Conductor

24-July-2014 / 32

Railway Electrification Programme - The System Design Challenge

Challenge 3

24-July-2014 / 33

Railway Electrification Programme - The System Design Challenge

Technical Complexity Whilst Delivering


Efficiencies
Distributed demand and power generation that is constantly moving
around network

Modelling is detailed and takes time

24-July-2014 / 34

Railway Electrification Programme - The System Design Challenge

Enablers
Need tools that well suited to future planning and option analysis

Traction Power Supply Strategies

Technological innovation

24-July-2014 / 35

Railway Electrification Programme - The System Design Challenge

Why are we moving to TPSS approach?

To identify better whole life cost options that may span multiple
control periods.
To move away from project by project timetable specific TP
enhancements.
To demonstrate to the regulator that our power projects are aligned to
the future needs of the railway.
To allow the Energy industry to have a better understanding of our
future energy needs.
To develop the fundamental system design early to allow projects to
focus on delivering and implementing the detailed design.
24-July-2014 / 36

Railway Electrification Programme - The System Design Challenge

Integrated Protection & Control (IPC)


Intelligent Electronic Device (IED)
Hardware

Communication

A typical device is shown which uses a


microprocessor to perform protection and control
functions .

IEC 61850
A standard architecture for communication
networks and systems in substations.

Marshalling
Rugged Ethernet Switch
A typical device (harden for use within a railway
substation environment) is shown which directs
Ethernet network traffic.
24-July-2014 / 37

Railway Electrification Programme - The System Design Challenge

IPC Development Suite

24-July-2014 / 38

Railway Electrification Programme - The System Design Challenge

Summary
1.

Biggest rail electrification programme for a generation

2.

Challenges ahead

3.

Exciting opportunities to make a difference in system design

24-July-2014 / 39

Вам также может понравиться