CLAPHAM COMMON
Living Stones Working Group
Presentation #5
EPCM
22 November 2009
Longing for shelter, many are homeless
Longing for warmth, many are cold.
Make us your building, sheltering others,
Walls made of living stone Bernadette Farrell
1
Living Stones 22 November 2009
The last presentation was on 14 June 2009
What have the Living Stones Group been up to?
• We have updated the brief
• The design team is re-engaged
• The LSG has met 6 times since
• We have reported to the PCC
• We have met the DAC
• We have met the Clapham Soc.
• We have talked as a group
• We have listened
• And now we would like to
update the congregation.
Living Stones 22 November, 2009 2
The framework of projects
1. The Sanctuary A. Accessibility
2. The Chancel B. Sustainability
3. The Narthex C. Lighting
4. The Galleries D. Acoustics + AV
5. The Nave (Pews) E. Fire Safety
6. An Extension F. Storage
7. The Churchyard G. The Undercroft
PCC approval to proceed to January 2010 Tender Information and Summer 2010
Stage D Tender
Stage 1 works Autumn 2010
Fundraising Early 2010 onwards Major works on site January 2011 onwards
The above timescale has already been significantly revised and reflects the nature of the consultative
process within the church and the time commitments of the individuals involved in the project.
The input of the fundraising committee will be critical to the smooth progress of the projects.