Вы находитесь на странице: 1из 38

Thursday,

April 27, 2006

Part III

Department of
Energy
Office of Energy Efficiency and
Renewable Energy

10 CFR Part 431


Energy Conservation Program: Test
Procedures for Distribution Transformers;
Final Rule
rmajette on PROD1PC67 with RULES3

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00001 Fmt 4717 Sfmt 4717 E:\FR\FM\27APR3.SGM 27APR3
24972 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

DEPARTMENT OF ENERGY Procedures for Distribution G. Review Under the Unfunded Mandates
Transformers, Docket No. EE–TP–98– Reform Act of 1995
Office of Energy Efficiency and 550, United States (U.S.) Department of H. Review Under the Treasury and General
Renewable Energy Government Appropriations Act of 1999
Energy, Energy Efficiency and
I. Review Under Executive Order 12630
Renewable Energy, Building J. Review Under the Treasury and General
10 CFR Part 431 Technologies Program, EE–2J, 1000 Government Appropriations Act, 2001
[Docket No. EE–TP–98–550] Independence Avenue, SW., K. Review Under Executive Order 13211
Washington, DC 20585–0121, (202) 586– L. Review Under Section 32 of the Federal
RIN 1904–AA85 9138, email: cyrus.nasseri@ee.doe.gov. Energy Administration Act of 1974
Francine Pinto, Esq., U.S. Department M. Congressional Notification
Energy Conservation Program: Test IV. Approval of the Office of the Secretary
of Energy, Office of General Counsel,
Procedures for Distribution
GC–72, 1000 Independence Avenue, I. Introduction
Transformers
SW., Washington, DC 20585–0121, (202)
AGENCY: Office of Energy Efficiency and 586–9507, email: A. Authority and Background
Renewable Energy, Department of Francine.Pinto@hq.doe.gov. Part C of Title III of the Energy Policy
Energy. and Conservation Act (EPCA) provides
SUPPLEMENTARY INFORMATION:
ACTION: Final rule. for an energy conservation program for
I. Introduction certain industrial equipment. (42 U.S.C.
SUMMARY: Pursuant to Sections A. Authority and Background 6311–6317) Section 346 of EPCA states
323(b)(10) and 346(a) of the Energy B. Summary of the Final Rule
that the Secretary of Energy (Secretary)
II. Discussion
Policy and Conservation Act, as must prescribe testing requirements and
A. General
amended, (EPCA or the Act), 42 U.S.C. B. Transformers Subject to the Test energy conservation standards for those
6293(b)(10) and 6317(a), the Department Procedure—Definition of Distribution ‘‘distribution transformers’’ for which
of Energy (DOE or the Department) Transformer the Secretary determines that standards
promulgates a rule prescribing test 1. General ‘‘would be technologically feasible and
procedures for measuring the energy 2. Incorporation and Definition of EPCA’s economically justified, and would result
efficiency of distribution transformers Exclusions—General in significant energy savings.’’ (42
under EPCA, definitions to delineate the 3. Specific EPCA Exclusions U.S.C. 6317(a)) The recent amendments
products covered by the test procedures, a. Transformers with Tap Ranges of 20
to EPCA set forth in the Energy Policy
Percent or More and Special Impedance
provisions (including a sampling plan) Act of 2005 (EPACT 2005), Pub. L. 109–
Transformers
manufacturers must use to implement b. Testing Transformers 58, accomplish the following for this
the test procedures, provisions to allow c. Grounding Transformers equipment: (1) Section 321(35) of EPCA
manufacturers to use calculation 4. Other Exclusions Considered now defines ‘‘distribution transformer’’
methods to determine the efficiency of 5. Rebuilt or Refurbished Distribution (42 U.S.C. 6291(35)), (2) Section
some of their models, and enforcement Transformers 323(b)(10) of EPCA provides that the
testing for distribution transformers. 6. Coverage of Liquid-Filled Transformers testing requirements ‘‘shall be based on
The Department will use the new test C. Test Procedure for Distribution the ‘Standard Test Method for
procedures in evaluating what energy Transformers
Measuring the Energy Consumption of
1. General Discussion
conservation standards are warranted Distribution Transformers’ prescribed
2. Specific Provisions of the Test Procedure
for distribution transformers other than a. Testing Harmonic Transformers by the National Electrical Manufacturers
the low-voltage dry-type. When DOE b. Determining Winding Temperatures Association (NEMA TP 2–1998).’’ (42
promulgates such standards, then the c. Test Set Neutrals U.S.C. 6293(b)(10)),1 and (3) section
test procedures and other provisions d. Losses from Auxiliary Devices 325(y) of EPCA prescribes minimum
adopted today will be used to determine e. Testing of Multiple Voltage Transformers efficiency levels for low-voltage dry-
the efficiencies and assess compliance f. Short-Circuiting Conductor Strap type distribution transformers (42 U.S.C.
of the transformers subject to these g. Revisions Suggested by NEMA in TP 2– 6295(y)).
standards. For low-voltage dry-type 2005 On October 22, 1997, the Department
h. Language Corrections as to Conversion
distribution transformers, the new issued a notice setting forth its
of the Resistance Measurement to the
standards prescribed for them in section Reference Temperature and Conducting determination (hereafter referred to as
325(y) of EPCA, 42 U.S.C. 6295(y), go the No-Load Loss Test the ‘‘Determination’’) that, based on the
into effect on January 1, 2007, and all D. Basic Model best information it had available, energy
of the provisions of today’s rule will 1. General Discussion conservation standards for electric
become applicable to those transformers 2. Definition of a Basic Model distribution transformers appeared to be
at that time. E. Manufacturer’s Determination of technologically feasible and
EFFECTIVE DATE: This final rule is Efficiency economically justified, and were likely
1. General Discussion to result in significant energy savings.
effective May 30, 2006, except for 2. Sampling Plan
§ 431.197(a)(4)(i), section 6.2(f) of 62 FR 54809.
3. Alternative Efficiency Determination
Appendix A and section 6.2(b) and (c) The Department subsequently began
Method (AEDM)
of Appendix A which contain F. Enforcement Procedures the process for its issuance of test
information collection requirements that III. Procedural Requirements procedures for distribution
have not been approved by the Office of A. Review Under Executive Order 12866 transformers. On February 10, 1998, the
Management and Budget (OMB). The B. Review Under the Regulatory Flexibility Department held a public workshop (the
Office of Energy Efficiency and Act of 1980 ‘‘1998 workshop’’) to discuss the
rmajette on PROD1PC67 with RULES3

Renewable Energy will publish a C. Review Under the Paperwork Reduction following issues: (a) Whether DOE
Act
document in the Federal Register D. Review Under the National 1 Section 323(b)(10)(B) also provides that the
announcing the effective date. Environmental Policy Act of 1969 Department may ‘‘review and revise’’ the test
FOR FURTHER INFORMATION CONTACT: E. Review Under Executive Order 13132 procedures established under that subparagraph.
Cyrus Nasseri, Project Manager, Test F. Review Under Executive Order 12988 (42 U.S.C. 6293(b)(10)(B))

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00002 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 24973

should adopt national and international proposed rule also included proposed (3) a new definition of ‘‘basic model’’
consensus standards as its test definitions of ‘‘distribution transformer’’ and a new sampling plan, to implement
procedures for determining the energy and related terms, of terms used in the the test procedures, (4) provisions to
efficiency of distribution transformers, test procedure provisions, and of ‘‘basic allow manufacturers to use calculation
(b) defining the transformers that the model.’’ It also proposed a sampling methods, instead of testing, to
test procedures will cover, (c) whether, plan for applying the test procedures to determine the efficiency of some of their
and to what extent, there is a burden on perform compliance testing. The models, and (5) enforcement
industry, especially on manufacturers, sampling approach was based on the procedures, including a testing protocol,
because of additional testing and data plan for compliance testing in 10 Code for distribution transformers. DOE held
processing, (d) the definition of ‘‘basic of Federal Regulations (CFR) Part 430, a public meeting on September 27,
model’’ for distribution transformers, (e) which contains energy efficiency 2004, on the SNOPR (the ‘‘2004 public
the sampling plan for units to be tested, requirements for consumer products, meeting’’) and received six written
(f) the selection of an energy but tailored to distribution transformers comments.
consumption measure for distribution and with a minimum sample size of five Concurrently with this rulemaking,
transformers, (g) the selection of units. The Department selected this the Department has evaluated the
reference temperatures, (h) the approach because it appeared to provide establishment of energy conservation
requirements for applying corrections to a satisfactory balance between assuring standards for distribution transformers.
measurement data, and (i) the the accuracy of efficiency ratings for On October 2, 2000, the Department
requirements for quality assurance in distribution transformers and made available a Framework Document
testing. The Department also gave minimizing the testing burden on for Distribution Transformer Energy
interested parties an opportunity to manufacturers. The Department also Conservation Standards Rulemaking,
submit written comments on these sought comment on three alternative which was the subject of a public
issues. compliance approaches for basic models workshop on November 1, 2000, and on
In 1998, the National Electrical produced in small numbers. which stakeholders submitted written
Manufacturers Association (NEMA) DOE held a public meeting on January comments before and after the
published ‘‘NEMA Standards 6, 1999, on the 1998 proposed rule and workshop. 65 FR 59761 (October 6,
Publication No. TP 2–1998, Standard received nine written comments. After 2000). Thereafter, the Department
Test Method for Measuring the Energy reviewing the oral and written visited manufacturers of distribution
Consumption of Distribution comments, DOE concluded that the transformers and posted on DOE’s
Transformers,’’ (NEMA TP 2–1998) a comments raised a number of significant website 3 several draft reports
publication that extracts and presents issues that required additional analysis. concerning the development of
pertinent parts of the current industry On June 23, 1999, the Department standards for these transformers. On the
standards for distribution transformer reopened the comment period on the same day that it published the SNOPR,
efficiency testing. NEMA TP 2–1998 1998 proposed rule, 64 FR 33431, (the DOE issued an Advance Notice of
also presents a weighted average ‘‘1999 reopening notice’’) to provide an Proposed Rulemaking (ANOPR) for
method to compute the energy opportunity for additional public distribution transformer standards. 69
efficiency of transformers, in order to comment on the following issues: (a) FR 45376 (July 29, 2004). Several of the
demonstrate compliance with the The suitability of NEMA TP 2–1998 for written comments DOE received in
efficiency levels in NEMA Standard TP adoption as the DOE test procedure; (b) response to the ANOPR address issues
1–1996 (NEMA TP 1).2 Comments the adequacy of stakeholder opportunity raised in the SNOPR, and the
received at the 1998 workshop, written to review NEMA TP 2–1998; (c) the Department has referenced them in the
comments associated with this transformers covered under the docket of this rulemaking and has
workshop, and NEMA TP 2–1998 definition of ‘‘distribution transformer;’’ considered them in formulating today’s
formed the basis for preparing the (d) the suitability of the definition of final rule.
November 12, 1998, Notice of Proposed ‘‘basic model’’ for the purpose of On October 18, 2005, the Department
Rulemaking (the ‘‘1998 proposed rule’’) grouping transformers to limit the test published a final rule to place in its
in this proceeding. 63 FR 63359. burden; and (e) the appropriateness of regulations the energy conservation
In the 1998 proposed rule, the the proposed sampling plan and a standards, and related definitions, that
Department proposed to adopt testing number of alternatives for Congress prescribed in EPACT 2005 for
methods that (1) it could use to evaluate demonstrating compliance. The certain consumer products and
distribution transformers during the Department received five comments in commercial and industrial equipment.
development of efficiency standards, response to the 1999 reopening notice. 70 FR 60407. The rule included the
and (2) manufacturers and DOE would On the basis of these comments, two definitions for ‘‘distribution
use to determine the efficiency of the additional comments it received transformer’’ and ‘‘low-voltage dry-type
transformers which the standards would subsequently, and its review of the distribution transformer,’’ and the
cover. DOE proposed to incorporate by issues raised by the 1998 proposed rule standards for low-voltage dry-type
reference as its test methods the and the 1999 reopening notice, the distribution transformers, that were
provisions from either the Institute of Department issued a supplemental contained in EPACT 2005. 10 CFR
Electrical and Electronics Engineers notice of proposed rulemaking sections 431.192 and 431.196. The
(IEEE) Standards C57.12.90–1993 and (SNOPR). 69 FR 45506 (July 29, 2004). Department put the provisions for all of
C57.12.91–1993 (using IEEE C57.12.00– In the SNOPR, DOE proposed to adopt the commercial and industrial products
1993 as an additional reference source), (1) a new ‘‘stand alone’’ test procedure covered by EPACT 2005, including
or NEMA TP 2–1998. The 1998 for distribution transformers, drafted by those for distribution transformers, in 10
the Department and consisting almost
rmajette on PROD1PC67 with RULES3

CFR Part 431. 70 FR 60414–18. In the


2 NEMA TP 1 contains suggested efficiency levels. entirely of test methods contained in prior Federal Register notices dealing
Its full name and title are ‘‘NEMA Standards NEMA TP 2–1998 and other existing
Publication No. TP 1–1996, Guide for Determining
Energy Efficiency for Distribution Transformers.’’
industry standards, (2) revised 3 http://www.eere.energy.gov/buildings/

NEMA TP 1 was updated in 2002, with definitions to establish which appliance_standards/commercial/


modifications to some of the efficiency levels. transformers the test procedure covers, dist_transformers.html

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00003 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
24974 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

with test procedures for distribution Today’s rule amends the definition of a single method for transformers in two
transformers, DOE had proposed adding ‘‘distribution transformer’’ that DOE or all three of these groups so long as
a new part 432 to include requirements recently adopted, 70 FR 60416, by the method is validated separately in
for distribution transformers. 63 FR adding capacity limits (the same ones each of the groups for which the
63376, 63369; 69 FR 45517, 45520. As the Department proposed in the manufacturer uses it. Today’s rule also
a result of DOE’s decision, in response SNOPR), making minor language and contains the enforcement procedures
to EPACT 2005, to incorporate format changes, and clarifying the proposed in the SNOPR, including a
provisions for distribution transformers exclusion of transformers with tap testing protocol, modified to be
into 10 CFR Part 431, today’s final rule ranges greater than 20 percent. As consistent with the revised compliance
places the new test procedures for this discussed below, today’s definition sampling plan tolerance. Finally, the
equipment in Subpart K to 10 CFR Part conforms to, and incorporates the Department is republishing in this rule,
431. relevant language from, the definition without substantive change, the
that EPACT 2005 added to EPCA. (42 standards for low-voltage dry-type
B. Summary of the Final Rule distribution transformers that it
U.S.C. 6291(35)) The Department’s
The test procedure in today’s rule is definition establishes which originally codified at 70 FR 70417.
based on the test methods contained in transformers the test procedure covers. Today’s rule contains a revised table
NEMA TP 2–1998 4 and IEEE Standards It uses the approach DOE proposed in that has a clearer, more appropriate
C57.12.90–1999 and C57.12.91–2001. the SNOPR—a broad definition with format than the table in the original
Initially, the Department will use the numerical criteria, but narrowed by the rule. The table also includes the
test procedure to evaluate distribution exclusion of specific types of reference conditions for the standards,
transformers for which it is currently transformers, many of which are not which DOE inadvertently omitted from
developing energy conservation commonly understood to be distribution the initial codification but which are
standards. When DOE promulgates such transformers. The numerical criteria essential elements of the standards, as
standards, the Department will then (except for the added capacity limits) set forth in Table 4–2 of NEMA TP 1–
require manufacturers to use the test and the exclusions are the same as those 2002, from which EPCA incorporates
procedure to determine compliance in EPCA’s new definition. They include the standards. (42 U.S.C. 6295(y))
with the standards and as a basis for virtually the same primary and II. Discussion
their efficiency representations for secondary voltage ranges the
covered transformers. The Department Department proposed in the SNOPR, A. General
would also use the test procedure in any most of the exclusions DOE proposed, Representatives of several
enforcement proceeding concerning and no additional exclusions. Today’s organizations attended the public
compliance with such standards and definition of distribution transformer, meeting on September 27, 2004,
related labeling requirements. In however, does not include the including trade associations (Copper
addition, the test procedures will exclusions of K-factor and harmonic Development Association, National
become mandatory for all of these mitigating distribution transformers, Electrical Manufacturers Association
purposes—compliance determination, which DOE proposed in the SNOPR but (NEMA), and National Rural Electric
representations and enforcement—for which are absent from the EPCA Cooperative Association), transformer
low-voltage dry-type distribution definition. Stakeholders will have the manufacturers (Acme Electric
transformers when standards go into opportunity in the energy conservation Corporation (ACME), ERMCO
effect for them, pursuant to 42 U.S.C. standards rulemaking to comment to the Distribution Transformers (ERMCO),
6295(y), on January 1, 2007. Department on whether standards Federal Pacific Transformer (Federal
The language of today’s rule sets forth should apply to these transformers. Pacific or FPT), Kuhlman Electric
all testing requirements, without Today’s rule contains several features Corporation, Pemco Corporation
reference to other sources, for designed to reduce the number of (Pemco), and Howard Industries, Inc.
determining the energy efficiency of transformers that manufacturers would (Howard Industries or Howard)), a core
distribution transformers. Measurement have to test. First, the Department steel manufacturer (AK Steel
of electric power consumed by the allows manufacturers to group models Corporation), electric utility companies
transformer is in the form of no-load into ‘‘basic models’’ for testing (Georgia Power Company and Ameren
and load losses. The rule specifies purposes, and defines ‘‘basic model’’ as Services), the Canadian Government
methods with which to measure the proposed in the SNOPR, with minor (Natural Resources Canada), the
temperature, current, voltage, extent of clarifications. Second, the rule includes National Institute of Standards and
distortion in voltage waveform, and the same type of compliance sampling Technology (NIST) of the U.S.
direct current resistance of the plan proposed in the SNOPR, except Department of Commerce, and private
windings. The rule also prescribes that the sampling plan tolerance is research/consulting entities (BB&F
provisions for calculating efficiency. based on a single-unit sample tolerance Associates, Lawrence Berkeley National
The testing methods are largely the (confidence limit) of eight percent, Laboratory, Merritt and Associates,
same as those proposed in the SNOPR, rather than the five percent DOE Navigant Consulting, Inc., and
with several clarifying changes and a proposed. And third, today’s rule allows Optimized Program Services, Inc.).
few changes to provide manufacturers manufacturers to use alternative NEMA also submitted a written
with greater flexibility. methods, other than testing, to statement in advance of the public
4 In September 2005, NEMA provided the
determine the efficiency of some basic meeting. Following the public meeting,
Department with its revised test procedure
models. The rule incorporates the ERMCO, Federal Pacific, Howard
document, TP 2–2005, which is similar to the rule SNOPR proposal except that Industries, Cooper Power Systems
rmajette on PROD1PC67 with RULES3

language in the SNOPR. The Department has treated manufacturers need not use a different (Cooper) and NEMA each submitted a
this submission as a comment on the SNOPR, has method for each of the following groups written statement. In addition, the
incorporated into today’s rule a number of the
changes that this revision made to the SNOPR’s rule
of distribution transformers: low-voltage Department received ten comments in
language, and addressed below the significant dry-type, medium-voltage dry-type, and its energy conservation standards
differences between the revision and the SNOPR. liquid-immersed. Manufacturers can use rulemaking that pertained to both the

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00004 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 24975

test procedure and the energy or ‘‘new’’ definition.) The EPCA maximum limits for primary and
conservation standards rulemakings. definition is similar in approach and secondary voltages, of 34.5 kilovolts and
Therefore, the Department cross- content to the definition proposed in the 600 volts, respectively, in the EPCA
referenced these comments from the SNOPR. It includes numerical criteria— definition have the practical effect of
energy conservation standards docket a maximum input voltage and frequency limiting transformers that meet the
(EE–RM/STD–00–550) to this that are similar to those in the SNOPR definition to those with a maximum
proceeding. The ten cross-referenced definition, and a maximum output capacity in the range of approximately
comments were submitted by Pemco, voltage that is identical—as well as a list 3750 to 5000 kVA, or possibly slightly
ERMCO, Harmonics Limited, NEMA, of excluded transformers that is quite higher. The voltage limits in the EPCA
Federal Pacific, HVOLT, Inc. (HVOLT), similar to the SNOPR’s list of excluded definition, however, subsume no lower
Oregon Department of Energy (ODOE), transformers. (The differences between limit on capacity.
Howard Industries, Power Quality EPCA’s list of exclusions and the It is unclear whether ‘‘distribution
International (PQI) and EMS SNOPR’s list are discussed below. transformer’’ as now defined in EPCA
International Consulting (EMS). Today’s rule adheres to the EPCA list.) and DOE’s regulations is, or can be,
The following summarizes the issues The new definition also authorizes DOE subject to capacity ranges other than the
addressed in the preamble of the to add to the list of exclusions any type just-mentioned upper limit. On the one
SNOPR and discusses in detail the of transformer that meets certain hand, the new definition includes no
points on which significant comments criteria. such capacity limitation, and it
were presented during and after the One significant difference exists, authorizes DOE to exclude from the
public meeting. however, between the numerical criteria definition, by rule, any transformer if it
in the EPCA and SNOPR definitions. No is designed for a special application, is
B. Transformers Subject to the Test capacity ranges are stated in the new unlikely to be used in a general purpose
Procedure—Definition of Distribution definition, whereas the SNOPR application, and significant energy
Transformer definition limits the term ‘‘distribution savings would not result from applying
1. General transformer’’ to liquid immersed units standards to it. (42 U.S.C.
with a capacity of 10 kVA to 2500 kVA, 6291(35)(B)(iii)) This suggests that
Although EPCA directed DOE to and dry-type units with a capacity of 15 unless, and until, DOE acts and
prescribe energy conservation standards kVA to 2500 kVA. (The Department has identifies capacity ranges that meet
and test procedures for certain been using a similar definition to these criteria, they are not part of the
‘‘distribution transformers’’ (42 U.S.C. delineate the transformers it is new definition of distribution
6317(a)), until recently the Act did not evaluating in the standards rulemaking. transformer. On the other hand, it is
define that term. Therefore, the 69 FR 45381–45384.) Transformers uncertain whether Congress intended to
Department undertook to adopt such a outside of these ranges are not typically regulate as distribution transformers
definition in this rulemaking. It used for electricity distribution, which units outside of the capacity ranges in
proposed a definition in the 1998 is the commonly understood function of the SNOPR, because few are used to
proposed rule, 63 FR 63362–63, 63369– a distribution transformer. The distribute electricity. In addition, at the
70, addressed the issue again in the Department received no adverse same time it enacted the new
1999 reopening notice, 64 FR 33432–34, comment on these proposed ranges. distribution transformer definition,
and proposed a substantially revised Moreover, NEMA agreed with the Congress also directed use of, and
definition in the SNOPR. 69 FR 45506. proposed lower capacity limit for dry- incorporated into EPCA, provisions of
That revised definition included type transformers, indicating that NEMA TP 2–1998 and NEMA TP
transformers meeting numerical criteria efficiency standards for transformers 1–2002, respectively (42 U.S.C.
as to primary and secondary voltage and with lower kVA ratings would fail to 6293(b)(10) and 6295(y)), both of which
capacity, and excluded specifically meet the criteria in section 346 of EPCA. apply only to transformers with capacity
listed types of transformers. 69 FR (NEMA, No. 39 at p. 2; Public Meeting ranges similar to those in the SNOPR
45509–10, 45520–22. The Department Transcript, No. 42.11 at p. 22) 5 But definition. Thus, Congress may have
designed that definition primarily to (1) notwithstanding the lack of any explicit intended to limit the term ‘‘distribution
encompass within ‘‘distribution capacity limits in the EPCA definition of transformer’’ to transformers within the
transformer’’ only those transformers distribution transformer, as a practical capacity ranges that normally
commonly understood to be distribution matter an upper capacity limit is characterize transformers that distribute
transformers, i.e. those made for the implicit in that definition. A electricity. If so, that would mean the
distribution of electricity, and (2) transformer’s capacity is to some extent Department’s authority to regulate the
exclude those distribution transformers tied to its primary (input) and secondary efficiency of transformers under 42
for which standards clearly would not (output) voltages. Therefore, the U.S.C. 6317 would be limited to
produce significant energy savings. 69 transformers within these capacity
FR 45509–10. 5 A notation in the form ‘‘NEMA, No. 39 at p. 2’’ ranges.
EPACT 2005 recently revised EPCA to identifies a written comment the Department has Given the inclusive language of
include a definition of ‘‘distribution received and has included in the docket of this EPCA’s definition of distribution
rulemaking. This particular notation refers to a
transformer’’ (42 U.S.C. 6291(35)), thus comment (1) by the National Electrical transformer, however, the Department is
filling the gap DOE had sought to fill Manufacturers Association (NEMA), (2) in not prepared at this point to infer that
with its own definition. As part of the document number 39 in the docket of this EPCA imposes this limitation. The
final rule mentioned above, to place in rulemaking (maintained in the Resource Room of Department also does not possess
the Building Technologies Program), and (3)
the CFR certain provisions prescribed in appearing on page 2 of document number 39.
information on whether transformers
EPACT 2005, the Department Likewise, ‘‘Public Meeting Transcript, No. 42.11 at outside of these ranges would meet the
rmajette on PROD1PC67 with RULES3

incorporated this new definition, almost p. 22,’’ for example, would refer to page 22 of the criteria in 42 U.S.C. 6291(35)(B)(iii),
verbatim, into 10 CFR section 431.192. transcript of the ‘‘Public Meeting on Test particularly the one on energy savings
Procedures for Distribution Transformers’’ held in
70 FR 60407, 60416–17. (In the Washington, DC, September 27, 2005, which is
from applying standards, for exclusion
paragraphs that follow, the new document number 42.11 in the docket of this from the definition of distribution
definition is referred to as the ‘‘EPCA’’ rulemaking. transformer. The standards rulemaking

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00005 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
24976 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

for distribution transformers, in which the beginning of the process of adopting this definition, with its
DOE would develop such information, evaluating standards for these capacity limitations, for the purpose of
and this test procedure rulemaking to a additional transformers. Neither DOE delineating the coverage of today’s rule,
slightly lesser extent, have focused nor stakeholders contemplated that the as well as the transformers that will be
almost entirely on transformers within standards rulemaking would cover these evaluated in the current standards
the capacity ranges. Thus, at the present additional transformers. To the contrary, rulemaking for distribution
time, DOE is proceeding on the premise as indicated above, interested parties transformers. The inclusion of the
that ‘‘distribution transformer’’ as had reached a consensus as to the capacity limitations in today’s
defined in EPCA includes transformers transformers to be covered in the definition does not mean that DOE has
outside the capacity ranges in the standards rulemaking, and expect that concluded that the EPCA definition of
SNOPR. DOE will now move as promptly as distribution transformer includes such
One option, therefore, would be for possible to promulgate standards for limitations. Rather, at some point after
the Department to retain this definition these transformers. completion of the current rulemakings
in its rules, not revise it in today’s rule, Another possibility would be for the as to distribution transformers, the
and apply it in any standards Department to attempt to preserve the Department intends to evaluate
rulemaking as well. That would have current scope of the standards and test transformers with larger and smaller
little or no impact on adoption of the procedure rulemakings by pursuing capacities than those included in
test procedures in today’s rule, but it exclusion from the definition of today’s definition, review how EPCA
might delay issuance of the rule. The distribution transformer, under 42 should be construed with regard to
Department believes that the test U.S.C. 6291(35)(B)(iii), of transformers those transformers, and decide what if
procedures as proposed in the SNOPR with capacities outside the ranges any action to take with regard to
and revised for inclusion in today’s rule specified in the SNOPR definition. This adoption of efficiency requirements for
would be valid for determining the too would delay the rulemakings. For such transformers. If DOE adopts
efficiency of transformers with DOE to gather relevant information and efficiency requirements for any of these
capacities up to the limits implicit in assess whether transformers above and transformers, it would amend the
EPCA’s definition, and below the lower below the SNOPR’s capacity ranges definition of ‘‘distribution transformer’’
end of the proposed ranges proposed in meet the criteria in 42 U.S.C. in its regulations accordingly.
the SNOPR. Nevertheless, because DOE 6291(35)(B)(iii), would be burdensome
Finally, the capacity limitations in
had not proposed to apply the test and time consuming. And if DOE
procedure to transformers with such determined exclusion of these today’s definition of ‘‘distribution
capacities, it would have to provide transformers to be warranted, it would transformer’’ will have no effect on the
some opportunity for public comment have to undertake additional existing requirements for low-voltage
on the applicability of the test rulemaking proceedings to achieve such dry-type distribution transformers.
procedure to those transformers. Doing exclusion. Moreover, if DOE were to EPCA sets forth a definition and
so could delay completion of this conclude that these transformers do not standards for this equipment, 42 U.S.C.
rulemaking. meet the criteria for exclusion, DOE 6291(38) and 6295(y), which DOE
The impact in the standards would be in essentially the same incorporated into its regulations at 10
rulemaking, of applying the EPCA position it is in now. CFR sections 431.192 and 431.196(a).
definition without capacity limits, The Department is determined to Because the definition states that a
would be much greater than the impact avoid further delays in the rulemakings ‘‘low-voltage dry-type distribution
of doing so in this test procedure on standards and test procedures for transformer’’ is a ‘‘distribution
rulemaking. Formulating standards for a distribution transformers. Therefore, it transformer’’ that meets certain criteria,
product involves developing an does not wish either to expand these the addition of capacity limits to the
understanding of, and evaluating, rulemakings to cover transformers definition of ‘‘distribution transformer’’
factors such as the nature of the outside the SNOPR’s capacity ranges, or could be read as affecting what
product, its market, the technical to pursue at this time exclusion of such constitutes a ‘‘low-voltage dry-type
feasibility of potential efficiency transformers from the definition of distribution transformer’’ under the
improvements, the manufacturing costs distribution transformer. Furthermore, regulation. As stated above, however,
of such improvements, the resulting the transformers within these capacity the maximum limits for primary and
energy savings, the cost of the improved ranges clearly are within the new EPCA secondary voltages of 34.5 kilovolts and
product(s) to purchasers, the impact of definition of distribution transformer, so 600 volts, respectively, in EPCA’s
efficiency standards on manufacturers the Department is authorized to pursue definition of ‘‘distribution transformer,’’
and utilities, and environmental and standards for them, and DOE believes in effect limit transformers that meet
employment impacts, as well as other there are ample grounds to conclude that definition to those with a maximum
factors unique to a particular product. that such standards are warranted under capacity of approximately 3750 to 5000
The Department has been engaged in the criteria of section 346(a) of EPCA, 42 kVA. Similarly, one of the criteria for a
such activities with respect to U.S.C. 6317(a). ‘‘low-voltage dry-type distribution
distribution transformers for over five For these reasons, § 431.192 of today’s transformer’’ is that its primary voltage
years, examining for the most part final rule modifies the EPCA definition not exceed 600 volts, 10 CFR section
products within the capacity ranges in of distribution transformer that was 431.192, which contemplates a
the SNOPR definition of distribution recently incorporated into the DOE rules secondary voltage much lower than 600
transformer. It is now developing by adding to it the kVA capacity volts. The obvious effect of this is that
proposed standards for these products. limitations in the SNOPR definition. a transformer will be a ‘‘low-voltage dry-
To expand that rulemaking now to This definition will not include, as it type distribution transformer’’ under the
rmajette on PROD1PC67 with RULES3

include transformers outside these could not, any transformers excluded regulations only if its maximum
ranges would impose a substantial from the EPCA definition, and today’s capacity is far less than 3750 kVA, and
burden on DOE, and would test procedure and any standards in all likelihood less than the 2500 kVA
substantially delay the rulemaking by rulemaking will not cover such maximum in today’s definition of
requiring that the Department go back to transformers. The Department is distribution transformer. In addition,

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00006 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 24977

EPCA and DOE rules prescribe specifically excluded transformers definitions are such that it would be
standards for low-voltage dry-type serves to describe those transformers, highly unlikely for a particular
distribution transformers only with and helps indicate the types of transformer to be both ‘‘sealed’’ and
kVA’s within the range of 15 to 1000, 42 transformers the statute authorizes DOE ‘‘nonventilated.’’ In the SNOPR, DOE
U.S.C. 6295(y) and 10 CFR section to exclude by rule. Therefore, because treated them as two separate exclusions
431.196(a), which are within the 15 to this provision does not actually from the term ‘‘distribution
2500 kVA range that today’s definition delineate excluded transformers, and in transformer,’’ as it believes is
of ‘‘distribution transformer’’ order to avoid confusion as to the appropriate. In light of the foregoing,
incorporates for dry-type transformers. function of this language, DOE in DOE construes EPCA as containing
For these reasons, the capacity today’s rule has amended section separate exclusions for sealed and
limitation in today’s definition of 431.192 by excluding it. nonventilated transformers, and today’s
‘‘distribution transformer’’ has no As just indicated, DOE incorporated rule so provides.
impact on the current DOE and EPCA into its definition of distribution The Department has also changed the
requirements for low-voltage dry-type transformer language from EPCA that format for the specific exclusions in
distribution transformers. authorizes DOE to add to the list of section 431.192 of today’s rule, and
excluded transformers. (42 U.S.C. adopted the approach in the SNOPR, by
2. Incorporation and Definition of 62912(35)(B)(iii); 70 FR 60416–17)
EPCA’s Exclusions—General placing the exclusions in a numbered
Because this language authorizes action list, rather than simply listing them
As indicated above, DOE incorporated by DOE and does not actually describe seriatim in a single paragraph. The
into its rules the new EPCA definition transformers that are not ‘‘distribution Department believes this will make the
of distribution transformer, including transformers,’’ upon further reflection rule easier to read and use.
the language listing specific types of the Department believes that the Finally, conforming to the approach
excluded transformers and authorizing language need not be included in the in EPCA, DOE’s recently adopted rule
DOE to add to that list. 70 FR 60416– definition in the DOE rules. Therefore, lists the 12 types of transformers it
17. Upon further review, the the Department has amended its excludes from the term ‘‘distribution
Department has decided to adopt in definition of ‘‘distribution transformer’’ transformer,’’ but contains no definition
Section 431.192 of today’s rule several by omitting this language from section for any of them. 70 FR 60416–17. In the
editorial, clarifying and format changes 431.92 of today’s rule. SNOPR, DOE proposed definitions for
to the language concerning the As to the specific exclusions, the the transformers it proposed to exclude.
exclusions. Department indicated when it adopted The Department believes such
To begin with, this language states the EPCA definition, 70 FR 60408, that definitions are warranted because they
that the term ‘‘distribution transformer’’ the definition uses incorrect terms in its help to clarify exactly which
does not include ‘‘a transformer that is exclusions of ‘‘Uninterruptible Power transformers are covered. Today’s rule
designed to be used in a special purpose System [UPS] transformer, impedance includes seven definitions drawn from
application and is unlikely to be used in transformer, * * * [and] sealed and IEEE standards, and five that DOE
general purpose applications, such as nonventilating transformer.’’ (42 U.S.C. developed based on industry catalogues,
[the list of specifically excluded 6291(35)(B)(ii)) In accordance with its practice and nomenclature. DOE
transformers]’’ (42 U.S.C. expressed intention to address such
6291(35)(B)(ii); 70 FR 60416–17) At first believes they represent a reasonable
minor drafting problems in future
reading, this language appears to construction of the EPCA exclusions.
rulemaking proceedings, where
exclude unspecified types of Except as indicated in the discussion
Congress has not already done so, 70 FR
transformers that meet the criteria just below of the definitions of special
60408, in today’s rule DOE is amending
quoted, and to introduce a list impedance, testing and grounding
its definition of distribution transformer
consisting of specific illustrations of the transformers, they are the same
to correct use of these terms. First, UPS
transformers excluded. However, the definitions DOE proposed in the
transformers are commonly referred to
very next paragraph of the definition SNOPR.
as ‘‘Uninterruptible Power Supply
states that DOE may, ‘‘by rule,’’ exclude transformers,’’ not ‘‘Uninterruptible 3. Specific EPCA Exclusions
‘‘any transformer not listed’’ which Power System transformers,’’ and
meets criteria that, in substantial part, a. Transformers With Tap Ranges of 20
therefore DOE adopts the former term in
are virtually identical to the criteria just Percent or More and Special Impedance
today’s rule. Second, every transformer
quoted. (42 U.S.C. 6291(35)(B)(iii); 70 Transformers
has an impedance, but only
FR 60416) If the definition were read as transformers with impedances outside EPCA and the Department’s recently
excluding any transformer, in addition of normal ranges, i.e., ‘‘special- adopted rule exclude from the
to those specifically listed, that met impedance’’ transformers, warrant definition of ‘‘distribution transformer’’
these criteria, this would obviate and exclusion from standards. The transformers with ‘‘multiple voltage
render null the provision authorizing Department had proposed to exclude taps, the highest of which equals at least
DOE to exclude additional transformers such transformers from its definition of 20 percent more than the lowest.’’ 42
that meet these criteria, but only distribution transformer in the SNOPR, U.S.C. 6291(35)(B)(i); 70 FR 60416. The
through rulemaking. The Department and NEMA excludes them from Department reads this language as
believes, however, that the soundest coverage of NEMA TP 1 and TP 2. excluding transformers with a tap range
construction of these provisions is that Therefore, DOE construes EPCA as of 20 percent or more. It is similar to the
transformers not specifically listed in excluding ‘‘special impedance’’ exclusion in the SNOPR of transformers
the definition can be excluded only transformers, and today’s rule with a tap range greater than 15 percent.
through a DOE rulemaking, thus substitutes that term for ‘‘impedance’’ in The language EPCA uses for this
rmajette on PROD1PC67 with RULES3

providing certainty as to which the list of exclusions. Third, IEEE exclusion, however, is ambiguous.
transformers are covered at any given standards define ‘‘sealed’’ transformers Each distribution transformer with
point in time. Use of the language separately from ‘‘nonventilated’’ multiple voltage taps has a nominal
quoted at the beginning of this transformers, treating them as two voltage at which it normally operates
paragraph to introduce the list of different types of transformers. The and other voltages (taps), typically

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00007 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
24978 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

above and below its nominal voltage at percent. In section 431.192 of today’s with ranges included in Howard’s
which it can also operate. The voltage rule, the Department has incorporated comments, which are more in line with
taps enable the transformer to be this interpretation into its regulations by ranges ANSI uses to delineate special
connected to distribution lines at these adding clarifying language to amend the impedance transformers and on which
other voltages. The tap range represents regulation containing this exclusion that most utility systems are based. (Howard,
the difference between the highest and it adapted from EPCA in 70 FR 60416. No. 55 at p. 3) For most kVA levels,
lowest voltage taps relative to the The Department also notes that EPCA DOE’s proposed ranges are broader than
nominal voltage, expressed as a includes this exclusion in a separate Howard’s. Hence, DOE’s ranges would
percentage. It is unclear whether, under paragraph, rather than in the list that result in exclusion of fewer
the EPCA exclusion, a transformer’s tap comprises the other exclusions from the transformers, by classifying fewer as
range is determined by computing the definition of ‘‘distribution transformer.’’ ‘‘special impedance.’’ In its revised test
percentage of the voltage difference (42 U.S.C. 6291(35)(B)(i)–(ii)) See 70 FR procedure document, NEMA TP 2–2005,
between its lowest and highest voltage 60416. To present this exclusion in the NEMA incorporated DOE’s proposed
taps relative to the voltage of the lower same format as the other exclusions, in normal impedance ranges. (NEMA, No.
tap, or, as the industry has traditionally section 431.192 of today’s rule the 60 Attachment 1 at pp. 5–6)
done, by adding the sum of the Department has added ‘‘Transformer The Department is concerned that
percentages by which the highest and with Tap Range of 20 percent or more’’ some transformers designed for
the lowest voltage taps deviate from the to the list of exclusions and defined that electricity distribution could be
nominal voltage. (The traditional term using the EPCA language that manufactured with impedances outside
industry method is equivalent to the contains the exclusion, modified as just normal ranges so that they would not be
percentage of the difference between the indicated. subject to otherwise applicable
lowest and highest voltage taps relative As indicated above, the Department efficiency standards. Such transformers
to the nominal voltage.) These two had proposed in the SNOPR to exclude could be less expensive to manufacture
approaches generally yield two different transformers with tap ranges greater than normal impedance transformers
results for tap range value for any given than 15 percent. 69 FR 45110, 45420– manufactured in compliance with the
transformer with multiple voltage taps. 22. Pemco, a manufacturer, expressed standards, and therefore could have a
For example, a 600-volt primary the concern that, if the Department competitive advantage over standards-
transformer with two 2.5-percent taps declines to adopt efficiency standards compliant distribution transformers. If
above and four 2.5-percent taps below for distribution transformers with a tap this occurred, it would subvert the
the nominal, with the highest tap being range of greater than 15 percent standards. At best, the manufacturer(s)
630 volts and the lowest 540 volts, (currently the standard tap range for low of such new, non-complying
voltage dry-type transformers), transformers would sell them in place of
would normally be referred to as having
manufacturers might begin producing complying products they would
a tap range of 15 percent (i.e., 6 times
transformers with a slightly larger tap otherwise have sold, and the product
2.5 percent, or 90 volts as a percentage
range, and such transformers would not would have a share of the market for
of 600 volts = 15 percent). Similarly, a
be covered by standards. (Pemco, No. 48 which DOE analysis demonstrated that
600-volt primary with three 2.5-percent
at p. 2) That could create a significant standards were technologically feasible
taps above and three 2.5-percent taps
loophole under the regulations. Since and economically justified. This would
below the nominal, with the highest tap
the 20-percent tap range is larger than reduce energy savings below the levels
being 645 volts and the lowest 555 volts,
the previously proposed 15-percent that standards under EPCA are designed
would also be referred to under the
range, exclusion of transformers with to achieve, and reduce the benefits
traditional industry approach as having tap ranges of at least 20 percent should transformer consumers and the public
a tap range of 15 percent. However, if reduce the risk that transformers with would realize from the standards. At
the tap percentages for these slightly larger tap ranges would be worst, to avoid significant losses of
transformers were calculated as a produced in order to avoid coverage. market share to the competing, non-
percentage of the voltage rating of the But that risk will not be completely complying transformer, other
lowest tap (540 volts and 555 volts in eliminated. manufacturers would be forced to
these examples), these two transformers The exclusion of special impedance produce the same type of non-
would have a tap range of 16.2 percent transformers, as provided in EPCA, as complying unit. In that case, all or most
and a 16.7 percent, respectively. recently incorporated by DOE into 10 of the benefit of standards could be lost.
The Department believes that EPCA’s CFR section 431.192, and as previously The Department believes that use of
exclusion of transformers with a tap proposed by DOE in the SNOPR, raises the impedance ranges in the proposed
range of 20 percent or more is best a similar issue. The issue is brought into rule, to delineate special impedance
construed as reflecting standard focus by DOE’s proposed definition for transformers, is a reasonable
industry practice, such that tap ranges these transformers in the SNOPR. The implementation of EPCA’s exclusion of
do not vary with the voltage rating of proposed definition specified a normal these transformers. This is the same
the lowest tap. Rather, tap range should impedance range for each standard kVA approach, discussed above, that EPCA
be calculated, and excluded rating, and stated that a ‘‘special- follows in its exclusion of transformers
transformers identified, based on the impedance transformer’’ would be any with non-standard tap ranges, in that
industry practice of calculating the transformer with an impedance outside only transformers that are considerably
transformer’s percent tap range relative the applicable range. Any such outside the normal ranges are excluded
to the nominal voltage of the transformer would not be a from coverage. To construe EPCA
transformer. Accordingly, the ‘‘distribution transformer’’ covered by otherwise, that is, to construe it as
Department interprets EPCA as the proposed rule. 69 FR 45510–11, excluding from coverage any
rmajette on PROD1PC67 with RULES3

excluding transformers from the 45520–22. No commenter objected to transformer that falls outside the
definition of ‘‘distribution transformer’’ this exclusion, and only one specifically current, standard normal impedance
when the aggregate of the transformer’s addressed it. Howard Industries ranges, could spawn a new generation of
highest to lowest tap voltages, relative to recommends that DOE replace its distribution transformers with
the nominal voltage, equals at least 20 proposed normal impedance ranges impedances outside these ranges, which

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00008 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 24979

would not be subject to Federal re-defining the relevant exclusions, and/ to consider further the exclusion of
efficiency standards and test or legislative action, is warranted. ‘‘instrument transformers’’ from today’s
procedures. As just mentioned, this definition of distribution transformer.
b. Testing Transformers
could subvert DOE’s energy efficiency
EPCA, and DOE’s recent rule, also c. Grounding Transformers
standards. NEMA’s inclusion of DOE’s
proposed impedance ranges in the exclude a ‘‘testing transformer’’ from the Finally, section 431.192 of today’s
revised TP 2 standard provided to the definition of distribution transformer, final rule contains a clarifying
Department, and the fact that only one 42 U.S.C. 6291(35)(B)(ii) and 70 FR modification to the SNOPR’s definition
commenter objected to them, indicate 60416, as does section 431.192 of of ‘‘grounding transformer.’’ That
they are a sound basis for delineating today’s rule. The Department proposed definition referred to ‘‘[a]n
the special impedance transformers that this exclusion in the SNOPR. 63 FR autotransformer with a zig-zag winding
are excluded from coverage under 63363; 69 FR 45510. No stakeholder arrangement.’’ 69 FR 45521. The
today’s rule and DOE’s efficiency commented on it, in response to either Department has since become aware
standards. Therefore, section 431.192 of the NOPR or SNOPR, except that in its that this language is internally
today’s rule retains the SNOPR’s revised TP 2–2005 document, NEMA inconsistent, because an
proposed definition of the ‘‘special- deleted the following sentence from the autotransformer with a zig-zag winding
impedance transformers’’ excluded from SNOPR’s proposed definition of ‘‘testing cannot be an autotransformer as defined
the term ‘‘distribution transformer.’’ transformer’’: ‘‘This type of transformer in the rule, nor does it meet industry’s
is also commonly known as an conventional understanding of the term.
The Department recognizes that this
Instrument Transformer.’’ (NEMA, No. The Department used the term
approach may not prevent attempts to
60 Attachment 1 at p. 7) An instrument autotransformer in the proposed
circumvent its efficiency requirements
transformer, however, is a type of grounding transformer definition to
through manufacture of distribution
transformer used for extending the describe a type of transformer that does
transformers that appear to, or do, fall
voltage and current ranges of measuring not have a separate physical secondary
just within this exclusion or the
and control instruments—such as winding (unlike a conventional
exclusion of transformers with tap
voltmeters, ammeters, wattmeters, and transformer). But although a three-phase
ranges of 20 percent or more. Such
relays—and is not the same as a testing autotransformer has three coils
transformers could conceivably be
transformer that supplies power to test constituting the primary winding only,
manufactured for use in standard electrical equipment. The Department and no separate secondary winding, a
applications to distribute electricity in recognizes that it erroneously included section of each primary coil is ‘‘tapped-
power distribution systems, but with this sentence in the SNOPR definition of off’’ to create, in effect, a secondary
efficiencies below those required by testing transformer and has deleted it winding. A grounding transformer,
DOE’s standards. Indeed, other from today’s rule. however, has only a primary winding,
exclusions from today’s definition of The Department believes that this and no secondary winding output. In
distribution transformer could also be error would not have lead stakeholders today’s rule, in the definition of
exploited to justify manufacture of to infer that DOE had proposed to ‘‘grounding transformer,’’ the
transformers, for standard distribution specifically exclude instrument Department has replaced the reference
applications, that do not meet DOE transformers from the definition of to an autotransformer with a reference
standards. The Department believes one ‘‘distribution transformer’’ in the to a transformer with a primary winding
such example may be the exclusion for SNOPR, for two reasons. First, the and no secondary winding.
drive (isolation) transformers. Such remainder of the proposed definition of
transformers can be similar to standard testing transformer clearly did not 4. Other Exclusions Considered
distribution transformers. A include instrument transformers, and The bulk of the comments on the
manufacturer might be able to produce second, contrary to the incorrect SNOPR’s definition of distribution
and market, for standard distribution sentence, testing transformers are not transformer advocated eliminating or
uses, a transformer that does not meet commonly known as instrument narrowing exclusions DOE had
DOE efficiency standards but that transformers. Nevertheless, to the extent proposed, or adding other exclusions.
clearly, or arguably meets, DOE’s the proposed rule may have been read EPACT 2005 incorporated none of these
definition of ‘‘drive (isolation) to specifically exclude instrument exclusions into EPCA.
transformer,’’ and claim that it is not a transformers, DOE believes such an In the SNOPR, DOE had proposed to
‘‘distribution transformer’’ as defined by exclusion is unnecessary and exclude both harmonic mitigating
DOE. unwarranted. The revised NEMA TP transformers and K-factor (also referred
The Department intends to strictly 2–2005 contains no such exclusion. to as ‘‘harmonic tolerating’’)
and narrowly construe the exclusions Moreover, an instrument transformer transformers at K–13 and higher, largely
from the definition of ‘‘distribution would be designed to handle less power based on its view that: (1) regulating
transformer.’’ It will also take than the lower capacity limits (10 kVA them would not save significant
appropriate steps, including for liquid-immersed and 15 kVA for dry- amounts of energy, and (2) they are
enforcement action if necessary, if any type) in today’s definition of sufficiently expensive that there is little
manufacturer or other party erroneously distribution transformer, unless it was risk they would be purchased in place
invokes one of the exclusions as a basis also designed to distribute electricity. In of more efficient transformers that
for marketing a transformer that is a the former case, the transformer would would be subject to standards. 69 FR
‘‘distribution transformer’’ under not be covered under today’s rule (or 45511, 45520–21. The Department also
today’s rule but does not meet DOE under the SNOPR) even absent a indicated its belief that few harmonic
standards. Moreover, to the extent specific exclusion, rendering an mitigating transformers would be
rmajette on PROD1PC67 with RULES3

transformers that do fall within the exclusion unnecessary. In the latter commonly understood to be distribution
exclusions begin to be marketed for case, it should be covered, and subject transformers. 69 FR 45511. No
standard distribution applications, or to DOE efficiency standards and test commenter advocated retention of either
find widespread use in such procedures, as a ‘‘distribution exclusion, and several supported
applications, DOE will examine whether transformer.’’ Hence, there is no reason eliminating or narrowing them.

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00009 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
24980 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

Supporting elimination of both application, and if significant energy constraints. (FPT, No. 52 at p. 2)
exclusions, NEMA stated that the savings would not result from applying Aligning with that comment, NEMA
exclusions could be used to avoid standards to it. (42 U.S.C. excludes mining transformers from its
efficiency standards. (NEMA, No. 39 at 6291(35)(B)(iii)) DOE previously relied revised test procedure, TP 2–2005.
p. 2 and No. 47 at p. 2; Public Meeting on general information to support the (NEMA, No. 60, Attachment 1 at p. 1
Transcript, No. 42.11 at p. 22; NEMA views expressed in the SNOPR that and p. 4) Pemco asserts the need for an
No. 51 at p. 2) The Oregon Department harmonic mitigating and K-factor exclusion for transformers subject to
of Energy raised doubts that these transformers would not be used for dimensional, physical or design
transformers would be unable to meet general purpose distribution constraints, such as height limits, low
standards and saw no rationale for applications, and that standards for temperature rise, special sound level
excluding them. (ODOE, No. 54 at p. 2) them would not save significant requirements, weight limits, and
Harmonics Limited believes the market amounts of energy. However, these suitability for high altitudes, which,
for them is large and growing, that use conclusions were somewhat negated by according to Pemco, render it physically
of K-rated transformers to circumvent the comments that these transformers impossible or cost-prohibitive for these
existing standards has resulted in could be sold in place of distribution transformers to meet an efficiency
greater energy consumption, and transformers that are subject to standard. (Pemco, No. 48 at p. 1) Pemco
harmonic transformers can both comply standards, and that their use is also states that an exclusion is needed
with standards and address harmonics increasingly common. Also, the for retrofit transformers that have to be
issues. (Harmonics Limited, No. 50 at p. Department is not aware of any more exactly the same as the ones they are
1) ACME and Pemco advocated concrete information or analyses that replacing. (Pemco, No. 48 at p. 1–2)
elimination of the exclusion for K-factor address whether standards for these Similarly, Howard Industries advocates
transformers (Public Meeting Transcript, transformers could save energy. Thus, an exclusion for retrofit transformers,
No. 42.11 at pp. 32–33; Pemco, No. 48 the Department now has no basis for particularly underground and subway
at p. 2), and EMS International excluding them under the new criteria style transformers, on the grounds that
Consulting, Inc. (EMS) advocated in section 42 U.S.C. 6291(35)(B)(iii). For they are subject to severe physical or
elimination of the exclusion for these reasons, DOE cannot conclude at electrical constraints, and would be
harmonic mitigating transformers. this point that harmonic mitigating or unable to also meet energy conservation
(EMS, No. 57 at p. 3) In addition, EMS K-factor transformers fail to meet the standards. (Public Meeting Transcript,
recommended that DOE cover K-rated new EPCA definition of ‘‘distribution No. 42.11 at p. 36; Howard, No. 55 at p.
transformers (up to a certain level which transformer.’’ 3) However, although NEMA views the
EMS did not specify), and Federal Concerning the issue of whether these lack of an exclusion for retrofit
Pacific recommended narrowing the transformers should be excluded from transformers as problematic, it did not
K-factor exclusion for transformers rated DOE’s definition of distribution advocate such an exclusion because it
up to 300 kVA and broadening it for transformer on the ground that energy has not formulated a definition or
transformers above 300 kVA, both on conservation standards for them would solution for this problem. (Public
grounds similar to those advanced by not meet the criteria in 42 U.S.C. Meeting Transcript, No. 42.11 at p. 35)
commenters who advocated its 6317(a)(1), as just set forth, there is In the SNOPR, DOE did not propose
elimination. (EMS, No. 57 at p. 2; FPT, insufficient basis to conclude that such to exclude any of the foregoing types of
No. 44 at pp. 2–3 and No. 52 at p. 2) standards would fail to save substantial transformers from its proposed
Based on these comments, and upon amounts of energy. Furthermore, definition of distribution transformer.
further review, DOE has concluded comments that harmonic mitigating and And as with K-factor and harmonic
there is not a sufficient basis at this K-factor transformers could be mitigating transformers, EPCA excludes
point to exclude harmonic mitigating or manufactured to be in compliance with none of them from its definition of
K-factor transformers from the applicable efficiency standards without distribution transformer. (42 U.S.C.
definition of distribution transformer. In excessive cost suggest that standards for 6291(35)(A) and (B)(i)-(ii)) Furthermore,
essence, the Department proposed in the this equipment might well be the commenters who supported these
SNOPR to exclude these transformers on economically justified. As with the additional exclusions have provided
the grounds that they are not issue of potential energy savings, the neither data as to the energy savings
‘‘distribution transformers,’’ and that Department is not aware of any concrete potential of standards for these
energy conservation standards for them information or analyses that suggest that transformers, nor information as to the
would fail to meet the EPCA criteria in standards for K-factor and harmonic likelihood they could be used in general
42 U.S.C. 6317(a)(1) because such mitigating transformers are not purpose applications, and the
standards would not save substantial economically justified. Thus, the Department is not aware of any concrete
amounts of energy and/or be Department believes there is insufficient information or analyses that address
economically justified. Concerning the basis to conclude at this point that these points. Therefore, the Department
first point, as discussed above, EPCA, as standards for these transformers would has no basis for excluding any of the
amended in EPACT 2005, now defines fail to meet the criteria in 42 U.S.C. transformers discussed in this paragraph
the term ‘‘distribution transformer.’’ 6317(a)(1). under section 321(35)(B)(iii) of EPCA.
Harmonic mitigating and K-factor Some commenters suggest adding (42 U.S.C. 6291(35)(B)(iii)) As to
transformers do not per se fail to meet other exclusions to the definition of whether these transformers satisfy the
the numerical criteria in this definition, distribution transformer. Federal Pacific criteria in 42 U.S.C. 6317(a)(1) for
nor are they in the definition’s list of recommends that mining transformers adopting test procedures and standards,
excluded transformers. (42 U.S.C. (transformers installed inside a mine, the commenters have provided broad
6291(35)(A) and (B)(i)–(ii)) inside equipment operated in a mine, or claims, but no technical or factual
rmajette on PROD1PC67 with RULES3

EPCA, as recently amended, now as a component of underground-digging evidence, that addresses this issue.
authorizes DOE, however, to exclude by or tunneling machinery) be excluded For these reasons, the Department has
rule any transformer if it is designed for from the application of standards, concluded that there is not a sufficient
a special application, if it is unlikely to because of their radically different loss basis at this point to exclude harmonic
be used in a general purpose characteristics and special dimensional mitigating or K-factor transformers, or

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00010 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 24981

transformers subject to dimensional, units is necessary to close a potential complex and burdensome task. By and
physical or design constraints loophole (EMS, No. 57 at p. 3; HVOLT, large, the Department believes EPCA
(including mining transformers), from No. 53 at p. 3), and ERMCO stated that indicates a Congressional intent that
today’s definition of distribution failure to cover rebuilt units might DOE focus on the market for new
transformer, and the definition does not enable end-users to avoid standards by products, and believes that this is where
exclude them. always rewinding failed units. (ERMCO, the largest energy savings can be
Rather, DOE will revisit the issues of No. 49 at p. 2) Manufacturers appeared achieved. For distribution transformers
whether, and to what extent, these to be concerned that the increased cost in particular, the Department
transformers should be subject to of new, standards-compliant understands that at present rebuilt
standards, and at what levels, during the transformers would cause some transformers are only a small part of the
standards rulemaking for distribution customers to either purchase rebuilt, market. Moreover, the core dimensions
transformers. As set forth in the instead of new, transformers or rebuild of existing units are fixed, whereas for
Determination notice, the Department existing transformers they already own. many newly manufactured transformers
can best address issues as to the The Oregon Department of Energy the dimensions of existing models could
technological feasibility, economic agreed that rebuilt transformers should be enlarged in order to allow their
justification and potential energy be required to meet new standards, efficiencies to increase. Therefore, at
savings of energy conservation indicating that high-quality rewinding least initially, any standard for rebuilt
standards in the standards rulemaking, practices can produce products that transformers would likely have to be
particularly during evaluation of would meet standards while poor lower than for comparable newly
proposed standard levels. 62 FR 54810. quality work can seriously degrade manufactured units, and given the
For many products, such as the types of performance. (ODOE, No. 54 at p. 2) current size of the refurbished
distribution transformers at issue here, Some commenters also advocated transformer market, it appears that
the question of whether standards are coverage of used and/or repaired significant energy savings could not be
warranted cannot adequately be distribution transformers. (Howard, No. achieved by adopting standards for
addressed without detailed information 55 at p. 3; EMS, No. 57 at p. 3) them.
and analysis. Once the Department has EPCA, in essence, seems to require For all of these reasons, the
decided to propose additional standard only new distribution transformers, that Department does not intend to apply its
levels for distribution transformers, and have not been sold to end users, to meet standards and test procedures to used,
has provided its analysis of the levels it Federal efficiency requirements. (42 repaired and rebuilt distribution
has considered in depth, stakeholders U.S.C. 6302, 6316(a) and 6317(a)(1)) transformers. Nevertheless, the
will have an opportunity to comment. Thus, DOE probably lacks authority to Department recognizes that there may
They can provide factual information require that used and repaired be some validity to the concerns raised
and analysis on issues such as whether transformers comply with its test by commenters about possible
the proposed standard levels, or other procedures and standards. The same substitution of rebuilt for new
levels, are warranted for particular may be true for rebuilt transformers, transformers. If conditions change—for
classes of transformers, including the although for them a genuine issue does example, if rebuilt transformers become
types just discussed. These comments exist as to DOE’s authority. Generally, a larger segment of the transformer
could also address whether some types EPCA provides that products, when market—DOE will reconsider its
of transformers should be completely or ‘‘manufactured,’’ are subject to decision not to subject them to energy
partially excluded from standards, efficiency standards. (42 U.S.C. 6295(b)– conservation requirements.
including, for example, whether a (i) and 6313) It is arguable, but by no
6. Coverage of Liquid-Filled
portion of K-factor transformers should means clear, that rebuilt transformers
Transformers
be excluded as advocated by Federal could be considered to be
Pacific. To the extent information ‘‘manufactured’’ again when they are Finally, Howard Industries suggested,
developed during the standards rebuilt, and therefore be classified as with regard to liquid-filled transformers,
rulemaking warrants exclusion of any new distribution transformers subject to that the utility, municipal, and co-op
type of transformers from coverage of DOE test procedures and standards. If, segment of the market not be subject to
the new standards (and test procedures), however, rebuilt products cannot be mandatory standards, because it already
the Department will modify its classified as newly manufactured, DOE uses life-cycle cost methods in
definition of ‘‘distribution transformer’’ would be subject to the same limitation purchasing products, and that only the
accordingly. on its authority to regulate them as commercial and industrial segment be
applies to used and repaired products. subject to such standards. (Howard, No.
5. Rebuilt or Refurbished Distribution 55 at p. 4) This is an interesting
In addition, contrary to the suggestion of
Transformers suggestion, but the Department believes
some commenters that DOE regulate the
The Department did not specifically efficiency of distribution transformers it is untenable because the distribution
address in the SNOPR whether today’s that their owners have re-wound, and transformers used in these two market
test procedure, as well as efficiency where the transformer is not re-sold, segments are not sufficiently different
standards for distribution transformers, EPCA provides authority to regulate from one another. If the Department
would apply to rebuilt distribution only products that are sold, imported or were to adopt efficiency requirements
transformers (i.e., units on which one or otherwise placed in commerce. (42 for transformers currently sold in one
more windings have been replaced), or U.S.C. 6291, 6311, and 6317(f)(1)) sector but not the other, DOE believes
to used or repaired distribution Throughout the history of its that the transformers it left unregulated
transformers. Nor does EPCA appliance efficiency program, DOE has would promptly find their way into the
specifically address this question. not sought to regulate used units that regulated market. The Department is
rmajette on PROD1PC67 with RULES3

Several commenters stated that the have been re-conditioned or rebuilt, or charged with prescribing test
requirements should apply to rebuilt have undergone major repairs. procedures and energy conservation
transformers, commonly referred to also Regulating this part of the market, standards for those distribution
as refurbished transformers. EMS and including the enforcement of efficiency transformers for which it determines
HVOLT stated that coverage of rebuilt requirements, could be an exceedingly standards are technologically feasible

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00011 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
24982 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

and economically justified and would proposed rule. 63 FR 63362. Nor did the In response to the SNOPR, several
result in significant energy savings. Department propose to incorporate the commenters requested that DOE rely on
Liquid-immersed distribution four IEEE standards by reference. As existing testing standards as much as
transformers sold into the utility, stated in the SNOPR, that would require possible, as it does for other products,
municipal and co-op segments of the users to consult several reference instead of adopting a new stand-alone
market are ‘‘distribution transformers’’ documents in order to construct the test test procedure. (FPT, No. 44 at p. 7;
as defined in section 321(35) of EPCA, procedure, whereas having a single Public Meeting Transcript, No. 42.11 at
and, because they clearly are designed reference test procedure would reduce pp. 49, 54–55) NEMA expressed
for general purpose applications, DOE the potential of misinterpreting testing concern that the Department’s proposal
could not exclude them under requirements and would enhance the differed significantly from the existing
paragraph (B)(iii) of that section. (42 convenience to users. In addition the testing methods (NEMA TP 2–1998 and
U.S.C. 6291(35)) Moreover, in October IEEE standards include test methods not IEEE), and asserted that industry
1997, the Department made a only for distribution transformers, but engineers would need to become experts
determination that energy conservation also for much larger power transformers in the new method, and that this could
standards for liquid-immersed that are not covered by the DOE test be a difficult, time consuming process.
distribution transformers would appear procedure. Nevertheless, the (Public Meeting Transcript, No. 42.11 at
to be technologically feasible and Department relied heavily on pp. 49–51, 53, 60) The Department
economically justified, and to result in techniques and methods from NEMA TP recognizes that there will be some
significant energy savings. 62 FR 54816. 2–1998 and the four IEEE standards in burden on manufacturers resulting from
For these reasons, today’s definition of developing the proposed test procedure today’s stand-alone test procedure. This
‘‘distribution transformer’’ does not and today’s final test procedure. burden, however, should be minimal.
exclude liquid-immersed transformers, EPACT 2005, which the President The test methods in the DOE test
nor any subset of these transformers signed into law on August 8, 2005, procedure are virtually identical to
destined for any particular end-user or amended EPCA in effect to direct the those in the TP 2–1998 and IEEE
market segment. Department to develop a test procedure standards, and require the same steps
for distribution transformers that is for determining losses and calculating
C. Test Procedure for Distribution ‘‘based on’’ NEMA TP 2–1998. (42 efficiency. Comments from stakeholders
Transformers U.S.C. 6293(b)(10)). In the SNOPR, DOE offered no specifics as to why use of the
1. General Discussion stated that it had ‘‘adapted virtually all DOE test procedure would be
The Department developed the test of the provisions of the [proposed ] test burdensome for manufacturers and
method in today’s final rule (Appendix procedure from NEMA TP 2[–1998] and identified no specific provisions in
A to Subpart K of Part 431) in order to the * * * four widely used IEEE DOE’s proposed test procedure that
have a single, primary reference that standards’’ just cited, and had used deviate from the TP 2–1998 or IEEE
would clearly set forth all testing NEMA TP 2–1998 to develop the standards. Furthermore, in NEMA’s
requirements for distribution proposed test procedure. 69 FR 45508. revised TP 2 document, TP 2–2005, the
transformers that may be covered by The Department did not receive any test method closely parallels the SNOPR
EPCA energy conservation standards. comments from stakeholders indicating rule language. (NEMA, No. 60,
Almost in its entirety, the test method that they took issue with these Attachment 1) This indicates that, upon
closely follows NEMA TP 2–1998 and statements. As stated above, today’s further reflection, NEMA believes use of
the following four widely used IEEE testing methods are largely the same as DOE’s proposed test procedure would
standards: (1) IEEE C57.12.90–1999, those proposed in the SNOPR. Thus, as not be burdensome for manufacturers.
‘‘IEEE Standard Test Code for Liquid- also set forth above, NEMA TP 2–1998 Federal Pacific states that
Immersed Distribution, Power and and the IEEE standards are the bases for manufacturers will still be required to
Regulating Transformers and IEEE these test methods. Indeed, because reference industry standards, in
Guide for Short Circuit Testing of NEMA TP 2–1998 is based on the IEEE addition to DOE standards. (FPT, No. 44
Distribution and Power Transformers,’’ standards, and represents an attempt to at p. 6) The Department believes that
(2) IEEE C57.12.91–2001, ‘‘IEEE incorporate them into a single due to the similarities between today’s
Standard Test Code for Dry-Type document, any test method that test procedure and the TP 2–1998 and
Distribution and Power Transformers,’’ incorporates the substance of these IEEE documents, a manufacturer
(3) IEEE C57.12.00–2000, ‘‘IEEE standards would conform to TP 2–1998. following the DOE test procedure would
Standard General Requirements for Furthermore, today’s test methods and also be consistent with NEMA TP 2–
Liquid-Immersed Distribution, Power those in NEMA TP 2–1998 are entirely 1998 and the IEEE test procedures.
and Regulating Transformers,’’ and (4) consistent with one another. For all of
IEEE C57.12.01–1998, ‘‘IEEE Standard these reasons, it can be fairly stated that methods, but NEMA TP 2–1998 appears to be the
today’s test procedure is ‘‘based on’’ only one that contains a sampling plan. Moreover,
General Requirements for Dry-Type for the reasons explained in the SNOPR, that
Distribution and Power Transformers NEMA TP 2–1998, within the meaning sampling plan is inconsistent with the standards
Including those with Solid Cast and/or of 42 U.S.C. 6293(b)(10), and satisfies and labeling requirements in EPCA for distribution
Resin Encapsulated Windings.’’ the Congressional intent that the DOE transformers, and with basic, long-standing
test procedure reflect the content of TP elements of DOE’s appliance efficiency program. 69
As discussed in the SNOPR, the DOE FR 45514. Congress gave no indication in enacting
did not propose to adopt NEMA TP 2.6 EPACT 2005 that it intended its mandate for use of
2–1998 verbatim as the DOE test method NEMA TP 2–1998 to change EPCA’s standards and
6 Although NEMA TP 2–1998 contains a sampling labeling requirements, or the structure of DOE’s
because of concerns about whether TP plan for establishing compliance with prescribed program, for this product. For these reasons, DOE
2–1998 was sufficiently clear, detailed efficiency levels, the compliance sampling plan in believes Congress intended to require that DOE’s
rmajette on PROD1PC67 with RULES3

and accurate to serve as the DOE test today’s rule, which is discussed in section II–E test methods for distribution transformers, but not
procedure. 69 FR 45508–09. The below, is not based on the plan in TP 2. EPACT its compliance sampling plan, be based on NEMA
2005 mandates that the Department use 12 industry TP 2–1998. Accordingly, the Department construes
Department had also identified or voluntary test procedures, each for a different 42 U.S.C. 6393(b)(10) as not affecting the content of
problems with the clarity and level of type of product, as the basis for DOE test its compliance sampling plan for distribution
detail in TP 2–1998 in the 1998 procedures for those products. All contain test transformers.

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00012 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 24983

Therefore, manufacturers would not The Department believes that such at p. 3) Federal Pacific stated that absent
have to take separate steps to assure action would be inappropriate. The an industry standard harmonic load
compliance with each test procedure. Department recognizes NEMA’s efforts profile, K=1 is the only available
Federal Pacific also asserts that a to revise TP 2 and appreciates NEMA’s method for consistently testing
stand-alone DOE test procedure may openness, including its submission of a transformers designed for harmonic
become a problem if IEEE, ANSI, or draft TP 2–200X document in March currents. (Public Meeting Transcript,
NEMA adopt changes to their standards 2005 (NEMA, No. 59 Attachment 1) and No. 42.11 at pp. 33–34) Federal Pacific
because the changes may have to be the final TP 2–2005 document in also commented that it uses K=1 to test
incorporated into the DOE test September 2005 (NEMA, No. 60 K-factor transformers when a customer
procedure. (FPT, No. 44 at pp. 6–7) This Attachment 1). These submissions have specifies a K-factor transformer but also
issue is not unique to transformers, and made a definite contribution to this wants it to meet TP 1 efficiency levels.
exists whether DOE has a stand-alone proceeding. As indicated elsewhere in (FPT, No. 44 at p. 2) When a harmonic
test procedure or incorporates by this preamble, these submissions transformer is tested with a linear load,
reference one or more industry identified changes that were needed in however, its measured losses are lower
standards, such as the IEEE test methods the proposed rule, and that DOE has than the losses it would experience
for transformers. The Department adopted in today’s final rule. These under non-linear loads. Therefore, the
regulates many other consumer changes include modification of the efficiency rating that results from testing
products and commercial equipment, all definition of load loss and several the transformer with a linear load will
of which have test procedures. Some of editorial changes. As also discussed in be higher than the actual efficiency of
these are DOE-developed, stand-alone this preamble, however, stakeholder the harmonic transformer during normal
test methods, and others incorporate by comments submitted in response to the operation (i.e., when the transformer is
reference industry standards. Even in SNOPR, as well as DOE’s own review, subject to non-linear loads).
the latter situations, no change to an have resulted in many other changes Nevertheless, as one commenter
industry standard becomes part of the that clarify and improve the proposed indicated, testing harmonic transformers
DOE test procedure unless and until the test procedure. These additional at linear loads does offer a straight-
Department adopts it. In the event of an changes include provisions for testing forward testing method that avoids over-
industry-consensus revision to the test harmonic transformers, clarification of complicating the issue. (FPT, No. 44 at
methods for distribution transformers, the language concerning test set p. 3, and No. 52 at p. 2) The Department
the Department would consider all neutrals, and an alternative to the believes that if its efficiency standards
petitions from manufacturers seeking to proposed method for providing short- become applicable to K-factor and
incorporate those changes into today’s circuiting conductors. None of the harmonic mitigating transformers, more
test procedure. additional changes are reflected in efficient harmonic transformers will be
In sum, the Department continues to NEMA’s final TP 2–2005 document. manufactured than if the standard did
believe that having a single, reference Moreover, TP 2–2005 contains a number not apply to them. DOE agrees with the
test procedure document would of changes from the SNOPR that should above comments, and therefore today’s
enhance the convenience to users and not be included in today’s final rule, final rule, in Section 4.1 of the test
reduce the potential for such as the exclusion of mining procedure, requires that manufacturers
misinterpretation of testing transformers. For these reasons, the test these transformers using
requirements. Today’s final rule adheres Department is not incorporating TP fundamental-frequency test current
to that approach rather than 2–2005 as its test procedure rule for (corresponding to a linear (K=1)) load.
incorporating provisions from the distribution transformers. That said, in
b. Determining Winding Temperatures
existing industry test procedures. the future, the Department would
Commenters did not disagree with the consider incorporating verbatim the Today’s test procedure expands the
Department’s decision not to adopt NEMA test method in TP 2 so long as options available to manufacturers for
NEMA TP 2–1998, without its substance conforms with the test determining the winding temperature of
modification, as the DOE test procedure. method then in effect. liquid immersed transformers. IEEE
In written comments and during the 2. Specific Provisions of the Test C.57.12.90–1999 provides that the
SNOPR public workshop meeting, Procedure temperature of windings of a liquid-
however, NEMA proposed that DOE, immersed transformer is assumed to be
NEMA and other stakeholders work a. Testing Harmonic Transformers the same as the temperature of the
together to reach a consensus on needed As discussed earlier in this notice, the liquid in which the windings are
revisions of TP 2, so that NEMA could Department proposed in the SNOPR to immersed. Adding specificity to this
revise it and DOE could then exclude both harmonic tolerating (K- approach, the Department proposed in
incorporate it by reference. (NEMA, No. factor) transformers with a K-factor of the SNOPR that the winding
39 at p. 1; Public Meeting Transcript, K–13 or greater and harmonic mitigating temperature of a liquid-immersed
No. 42.11 at pp. 22, 49–51, 53, 56–57) transformers from the definition of distribution transformer would be the
NEMA has now completed its revision distribution transformer, but today’s average of two temperature sensing
of TP 2, informing DOE that it obtained definition includes both of these types devices applied to the outside of the
approval from its membership and of transformers. Several stakeholders transformer tank, at top oil level and at
adopted TP 2–2005 on September 19, who recommended removal of the the bottom of the tank. Howard
2005. (NEMA did not indicate whether exemption for these transformers, also Industries questioned the accuracy of
other stakeholders were involved in this recommended that the test procedure this method for determining winding
process.) NEMA proposes that DOE should require testing using a linear temperatures, and recommended
rmajette on PROD1PC67 with RULES3

adopt the TP 2–2005 document as its load profile (K=1), namely, using the instead that DOE require direct
test procedure for distribution fundamental-frequency test current in (internal) top and bottom measurement
transformers, and reference it in the the measurement of load loss. (NEMA, of the liquid temperature to determine
final rule for such test procedures. No. 47 at p. 1; NEMA, No 51 at p. 1; winding temperature. (Howard, No. 45
(NEMA, No. 60 at p.1) HVOLT, No. 53 at pp. 2–3; PQI, No. 56 at p. 1)

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00013 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
24984 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

The Department understands that the Department recognizes the value of source can be used to test either a wye-
most common method in the being consistent with IEEE. However, or delta-wound transformer, and a
distribution transformer industry for the Department does not believe that for neutral deriving transformer is not
estimating the temperature of liquid distribution transformers, meeting both needed, and rarely if ever used, to
immersed windings is by using conditions is necessary. The IEEE obtain a neutral and ground. The
thermocouples attached to the exterior standard encompasses kVA ratings of Department has added language to
of the transformer tank, as proposed in transformers that are much larger (up to today’s final rule to make clear that the
the SNOPR. Furthermore, as also 500,000 kVA and larger) than those test procedure allows the use of wye-
proposed in the SNOPR, today’s rule covered by today’s final rule (no larger and delta-wound power source
requires that winding temperature be than 2,500 kVA). The Department transformers for testing, and only
measured only after certain conditions believes that for distribution requires use of a neutral deriving
have stabilized, which provides greater transformers, which are relatively small transformer in conjunction with a delta-
assurance that these external compared to many of the kVA ratings wound transformer.
measurements are a good estimate of the addressed by IEEE, manufacturers can Today’s final rule also contains a few
winding temperature. For these reasons, achieve accurate winding temperature editorial changes with respect to section
DOE believes Howard’s readings if one of these two conditions 4.3.3 of the SNOPR test procedure. First,
recommendation that DOE require is met. Therefore, the language in because the first sentence of that
direct top and bottom measurement of today’s final rule does not require that section, as proposed, concerned three-
the liquid could impose significant and both conditions be met. phase distribution transformers
unnecessary burdens on manufacturers. The Department has also made some generally and not merely test set
Nevertheless, the Department recognizes clarifying and editorial changes to the neutrals, DOE has now moved the
that such direct measurements would be language of section 3.2.2 in today’s rule, language to section 4.3.2. Second, the
at least as accurate as external which concerns determination of the remaining language of section 4.4.3 in
measurements, and that testers who winding temperature of dry-type the SNOPR related only to testing of
prefer to make direct measurements transformers. Section 5.2 of IEEE three-phase transformers, and therefore
should be allowed to do so. Therefore, C57.12.91–2001 allows for the it has been renumbered in today’s final
today’s final rule allows manufacturers determination of such winding rule as section 4.3.2.3 (part of Three-
to determine the winding temperature temperatures, for both ventilated and Phase Test Sets). Third, to improve
using either exterior tank measurements sealed units, through either direct clarity, the term ‘‘grounding
or direct liquid measurements. measurement or use of the ambient transformer’’ has replaced the term
The Department understands that temperature of the test area. The IEEE ‘‘neutral deriving transformer’’
testers normally make external tank standard permits the latter, however, throughout the test procedure. This is
temperature measurements using only under certain conditions. The because ‘‘grounding transformer’’ is
thermocouples that are designed to be Department intended to incorporate the more widely understood in the
thermally insulated from the IEEE approach in section 3.2.2 of the distribution transformer community as
surrounding environment. The use of test procedure in the SNOPR, but that referring to the type of transformer used
insulated thermocouples reduces error language appeared instead to permit use to create a grounded neutral for a delta-
in the temperature measurement, and of the ambient temperature only in wound transformer.
offers greater accuracy in determining determining the winding temperatures
d. Losses From Auxiliary Devices
the winding temperatures. Therefore, of sealed units, and to apply the
the Department has modified the conditions for use of ambient Sections 4.4.3.1 and 4.5.3.1 of the
language in proposed section 3.2.1 to temperature also to use of direct SNOPR test procedure required losses
clarify that these external temperature measurement. Section 3.2.2 of today’s attributable to test instrumentation to be
measurements must involve the use of final rule contains revised language that deducted from measured no-load and
insulated thermocouples. clearly incorporates the IEEE approach. load losses, respectively, in determining
In addition, proposed section 3.2.1 the total losses of a transformer.
would give manufacturers the choice of c. Test Set Neutrals Commenters suggested that the final
waiting to measure winding temperature Part 4.0 of the proposed test rule also require manufacturers, in
until either (a) the windings have been procedure set forth provisions for determining load losses, to exclude
under insulating liquid with no determining transformer losses, those losses attributable to auxiliary
excitation and no current in the including requirements for the test devices installed on a distribution
windings for four hours before the direct circuits and test sets used during transformer but which are separate from
current (dc) resistance is measured; or testing. Section 4.3.3 of the SNOPR the transformer, such as circuit breakers,
(b) the temperature of the insulating required use of a ‘‘four-wire, three- fuses, and switches, because such losses
liquid has stabilized, and the difference wattmeter test circuit,’’ and, for delta- are not related to losses from the
between the top and bottom temperature wound transformers, use of ‘‘a neutral transformer’s windings. (Howard, No.
does not exceed 5 °C. These conditions deriving transformer * * * to obtain 45 at p. 1, and No. 55 at p. 3; ERMCO,
each provide assurance that the neutral and ground.’’ Commenting on No. 49 at pp. 1–2) These commenters
temperature of the windings has this section, Howard Industries stated raise a valid concern, although today’s
stabilized when manufacturers measure that ‘‘[t]here are options for the design final rule permits, but does not require,
it. The Department took these two of the power source used to test the deduction or exclusion of auxiliary
conditions from IEEE C57.12.90–1999, distribution transformers,’’ and device losses from the measured load
which requires that both be met when recommended adding to this section the losses.
the tester measures the winding phrase ‘‘unless the source is WYE When a distribution transformer is
rmajette on PROD1PC67 with RULES3

temperature. Howard Industries connected.’’ (Howard, No. 45 at p. 2) equipped with auxiliary devices
commented that the DOE test procedure Although the Department does not agree (generally specified by the customer),
should also require that both be met, to with the change Howard recommended, these devices produce some energy
be consistent with the IEEE standard. this comment indicates a need to clarify losses, albeit relatively small in
(Howard, No. 45 at p. 2) The section 4.4.3. A wye-connected power comparison to the unit’s total losses.

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00014 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 24985

DOE anticipates that its efficiency this instrument. The Department has transformer in that class is designed to
standards would apply to distribution also made two other similar operate.
transformers without regard to whether modifications. The term ‘‘wattmeter’’ is Howard Industries commented that
auxiliary devices are installed. The replaced by ‘‘wattmeter voltage circuit’’ the efficiency measurement on series or
standards therefore would not govern because a wattmeter experiences losses multiple voltage transformers should
the efficiency of auxiliary devices, but through both its current and voltage always be based on the highest voltage
instead would apply to the performance circuits, but only losses from the voltage configuration. (Howard, No. 45 at p. 2;
of the basic transformer (the equipment circuit are part of measured transformer Howard, No. 55 at p. 3) The Department
to which the auxiliary devices are losses. The term ‘‘instrument is unable to accept this
added). Because the Department is transformer’’ is changed to ‘‘voltage recommendation, because a transformer
concerned that some manufacturers may transformer’’ because ‘‘instrument designed to operate at more than one
find it burdensome or problematic to transformer’’ refers to both current and nominal voltage would have to comply
exclude all or part of the losses voltage transformers, both of which with the standard at all voltage ratings.
attributable to auxiliary devices, each experience losses, and it is only losses Because the lowest voltage ratings
manufacturer will have the discretion to of the voltage transformer that are part would generally have the lowest
include or exclude some or all of the of measured transformer losses and efficiency ratings, to ensure that each
auxiliary-device losses in the should be deducted from the total multiple voltage transformer complies
determination of load losses. Although measured losses. None of these with the applicable standard at each
exclusion of all such losses would result revisions is a departure from the voltage at which it operates, the
in a more accurate efficiency rating for substance of the SNOPR. Rather they manufacturer would have to determine
the transformer being tested, inclusion improve the precision of the final rule the transformer’s efficiency by testing it
of such losses would understate the and reduce the risk of misinterpretation (or by calculating its efficiency using an
efficiency rating of the transformer, and or misapplication of the test procedure. AEDM), either at the voltage rating at
not circumvent any applicable standard. which the highest losses occur—
With respect to how to deduct the
The purchaser would be receiving a generally the lowest voltage—or at each
losses from auxiliary devices from the
slightly more efficient piece of voltage at which the transformer
measured load losses, one commenter
equipment than indicated by the rating. operates. Therefore, today’s final rule
suggested exclusion of the losses from
This approach is consistent with the requires the manufacturer to determine
auxiliary devices by removing the
Department’s regulations in other the basic model’s efficiency either at the
devices (Howard, No. 45 at p. 1), and
portions of its appliance standards voltage at which the highest losses
another suggested excluding the losses
program, which generally allow occur or at each voltage at which the
by deducting them from measured
manufacturers the discretion to rate transformer is rated to operate.
losses. (ERMCO, No. 49 at p. 2) Because
their products at efficiencies lower than f. Short-Circuiting Conductor Strap
the Department believes both
could be justified by test results. e.g., 10
approaches are sound, and would Section 4.5.2 of the SNOPR stated that
CFR section 430.24. It is also consistent
produce the same results, today’s final in the test for measuring load losses,
with the IEEE standards, which set forth
rule allows manufacturers the flexibility ‘‘[t]he conductors used to short-circuit
test methods for distribution
of using either one. the windings must have a cross-
transformers but do not require
exclusion of losses from accessories in e. Testing of Multiple Voltage sectional area equal to, or greater than,
measuring transformer losses. Transformers the corresponding transformer leads.’’
Today’s final rule also takes this same 69 FR 45530. Howard Industries
approach for instrumentation losses. For Today’s final rule also clarifies asserted that other methods exist for
the reasons just stated, the Department treatment of dual-or multiple-voltage providing short-circuiting conductors or
believes DOE’s test procedure should transformers under the Department’s their equivalent, and that the test
permit, but not require, (as proposed in test procedure. Distribution procedure should also permit
the SNOPR) that manufacturers deduct transformers can be designed with manufacturers to use any short
instrumentation losses from total losses multiple voltage ratings on the primary circuiting conductor that is ‘‘of
in determining transformer efficiencies. and/or secondary windings. Efficiency sufficient size to limit the tare watts to
This will allow manufacturers greater testing for these units can be less than 10 percent of the transformer
flexibility than was provided by the problematic because, for a given load losses.’’ (Howard, No. 45 at p. 2) In
SNOPR proposal, with no detriment to transformer and kVA rating, DOE industry parlance, ‘‘tare watts’’ are
the public or circumvention of any understands that each transformer will losses associated with the test set-up,
applicable standard. have two or more different efficiencies, and in this instance refer to losses in the
Therefore, section 4.5.3.1 of today’s i.e., one efficiency for each of its short-circuiting conductor. The short-
test procedure allows manufacturers to winding configurations. In other words, circuiting conductor losses incurred
exclude from measured load losses each multiple voltage transformer during testing are included in the
those losses attributable to auxiliary experiences different losses (and measured load losses for the transformer
devices, and sections 4.4.3.1 and 4.5.3.1 therefore different efficiencies) when being tested, but, as discussed above,
allow exclusion of losses attributable to operated at different voltages. This may be deducted from the measured
testing instruments from both no-load difference in losses is due to differences load losses. The Department’s proposed
and load losses. The Department has, in current associated with the voltage requirement of a cross sectional area
however, slightly modified the SNOPR configuration selected, and generally, equal to, or greater than, the
language in proposed sections 4.4.3.1 the lower voltage ratings will have the corresponding transformer leads is
and 4.5.3.1 that identified the sources of higher losses and therefore lower based on use of a simple, routine
rmajette on PROD1PC67 with RULES3

instrumentation losses. The final rule efficiency ratings. The Department method for short-circuiting the
omits the reference to ‘‘ammeter’’ intends, however, to have just one windings by means of the shortest
because, upon further consideration, standard level that would apply to all practical conductor between the
DOE now realizes that no measured transformers in a given class, regardless terminals of the transformer. The
transformer losses are attributable to of the voltage or voltages at which each Department believes this proposed

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00015 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
24986 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

requirement would limit the short- The language to implement this definition of ‘‘tolerances on measured
circuiting conductor losses to approach, however, varies slightly from losses’’ is therefore unnecessary.
approximately one to three percent of the language proposed by Howard As just indicated, Table 2–1 of NEMA
the transformer’s measured load losses. Industries. Howard’s proposed language TP 2–2005 contains an accuracy range
Howard’s recommended revision could be construed as permitting losses for frequency measurement of ± 0.5
contemplates allowing a less as great as 10 percent, even if a percent. (NEMA, No. 60 Attachment 1,
conventional approach, and would manufacturer uses the method p. 9) The Department has decided not to
allow losses in the short-circuiting strap prescribed in the SNOPR. The add such a provision to Table 2.1 of
to be as much as ten percent of the load Department sees no reason to allow that, today’s final rule, however, for the
losses. and believes losses of that magnitude following reasons. First, neither TP
The Department’s proposal generally should be permitted only if a 2–1998 nor the widely-used IEEE test
follows the approach taken in the manufacturer uses alternative methods. methods, which DOE used to develop
relevant IEEE standards. The IEEE today’s test procedure, contain an
standards are voluntary, however, and g. Revisions Suggested by NEMA in TP accuracy range for frequency
do not preclude manufacturers from 2–2005 measurement. Secondly, except in
using new, improved methods that do As stated above, NEMA prepared a unusual cases, it is not needed. When
not strictly adhere to those standards. revised version of NEMA TP 2–1998 power is supplied from the utility grid,
But incorporating the standards into and submitted it to the Department for frequency is very accurate and there is
DOE’s test procedure would make them review. (NEMA, No. 60 at p. 1) The no need to prescribe a frequency
mandatory and limit manufacturer Department compared this document, accuracy or require manufacturers to
flexibility to use such new methods. designated by NEMA as TP 2–2005 take steps to assure accuracy. The
The determination of losses in the (NEMA, No. 60 Attachment 1), with the Department would only require
short-circuiting strap is subject to errors, rule language proposed in the SNOPR to manufacturers to assure accuracy when
which will contribute to the overall identify all changes to the SNOPR’s the power supply is not synchronized
error in the determination of methods, procedures and language. For with an electric utility grid, and this is
transformer losses because the purposes of this final rule, DOE is addressed in sections 4.4.2 and 4.5.2 of
manufacturers can deduct the short- treating the differences that it identified the SNOPR. Thus, the Department has
circuiting losses from the measured load as written comments submitted by not added a frequency accuracy range to
losses in making their determination of NEMA on the SNOPR. The following Table 2.1.
total losses. DOE is concerned that discussion examines the significant Compared to the SNOPR, NEMA’s TP
increasing the permissible losses, as differences that DOE has not addressed 2–2005 contains slightly different and
proposed by Howard, might also elsewhere in this notice. longer definitions of ‘‘load’’ and ‘‘no-
increase the overall error—perhaps NEMA’s TP 2–2005 contains a load’’ loss. The SNOPR reads that
beyond acceptable limits—unless definition for ‘‘tolerances on measured ‘‘[l]oad loss means, for a distribution
appropriate care is exercised to losses’’ which was not provided in the transformer, those losses incident to a
determine the higher losses of the short- SNOPR and which reads: ‘‘Measured specified load carried by the
circuiting conductor. Today’s rule, values of electrical power, voltages, transformer, including losses in the
however, does not permit automatic currents, resistances, and temperature windings as well as stray losses in the
deduction of 10 percent or any other are used in the calculations of reported conducting parts of the transformer. It
fixed percent of losses denominated as data. To ensure sufficient accuracy in does not include no-load losses.’’
occurring in the short-circuiting the measured and calculated data, the NEMA’s revised TP 2–2005 reads ‘‘load
conductor or any other instrument or test system accuracy for each loss: The load losses of a transformer are
device. Instead, the rule provides that, measurement shall fall within the limits those losses incident to the carrying of
in determining measured load losses, specified in Table 4.’’ (NEMA, No. 60 a specified load by the transformer.
manufacturers may deduct only the Attachment 1, p. 8) The Department has Load losses include I2R loss in the
losses ‘‘attributable’’ to the short- not added this definition to the list of windings due to load and eddy currents;
circuiting conductor (as well as certain terms it is defining in the final rule stray losses due to leakage fluxes in the
other instruments and devices). Thus, because it believes such a definition windings, core clamps, and other parts,
the rule allows deduction only of actual would not further clarify or add and the loss due to circulating currents
losses, i.e., losses determined with a substance to the rule. Except for its (if any) in parallel windings, or in
reasonable degree of accuracy. range for frequency measurement parallel winding strands.’’ (NEMA, No.
Moreover, notwithstanding any increase accuracy, Table 2–1 7 of TP 2–2005 sets 60 Attachment 1, p. 4) The Department
in the amount of error that would be forth the same accuracy ranges as are has not modified its proposed definition
introduced by adoption of Howard’s contained in Table 2.1 in the SNOPR. of ‘‘load loss,’’ except by deleting the
proposal in today’s rule, the overall Moreover, section 2.0 of DOE’s test last sentence as NEMA did in TP
limit on the range of error for procedure states that ‘‘measurement 2–2005. The Department recognizes that
measurement of power losses remains at error will be limited to the values inclusion of this last sentence would
± 3 percent, as proposed in the SNOPR. shown in Table 2.1.’’ 69 FR 45524. The make the definition inaccurate, because
Thus, adoption of the proposal would Department believes these accuracy an insignificant amount of no-load loss
not have a significant effect on overall requirements for the measurement of is included in the measurement of load
results determined under the test losses are sufficient and clear, and a loss. Also, retention of this sentence
procedure. might incorrectly imply that
For these reasons, today’s rule allows 7 In the March 2005 draft of NEMA TP 2–200X, manufacturers should subtract this
manufacturers to use alternatives to the Table 4, Measurement Accuracy Requirements, was extremely small amount of no-load loss
rmajette on PROD1PC67 with RULES3

method specified in proposed section the correct citation. In preparing the final draft, from load-loss measurements, to
4.5.2(b) for providing short-circuiting Table 4 was re-labeled as Table 2–1, and all the determine load loss.
values remained the same. The language on page 8
conductors, so long as such alternatives of TP 2–2005 makes references to Table 4; however,
However, DOE believes that the
do not result in losses that are 10 this appears to be a typographical error as there is remainder of its proposed definition of
percent or more of the total load losses. no Table 4 in TP 2–2005. ‘‘load loss’’ is clear and not susceptible

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00016 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 24987

of misunderstanding, and its brevity is h. Language Corrections as to 69 FR 45530. Once again, DOE drew the
preferable to the approach in TP Conversion of the Resistance quoted language from IEEE standards,
2–2005. The description of the various Measurement to the Reference where it is included to accommodate
components of ‘‘load loss’’ in the NEMA Temperature and Conducting the No- testing as to characteristics other than
definition helps explain the causes of Load Loss Test efficiency, in situations where a
load loss, but neither alters nor clarifies Section 3.5 of DOE’s proposed test transformer includes special features
the definition or the requirements that procedure provided an equation for requested by a customer. Because this
the definition delineates. Such correcting measured resistance to the language has no application to
explanation generally is not included in resistance at the reference temperature. efficiency testing, and such testing must
rule language. 69 FR 45527. One of the terms of this always be conducted under the
Concerning the definition of ‘‘no-load equation, Tk, consists of a temperature conditions specified in proposed
loss,’’ the Department’s SNOPR reads: level for copper windings, another for paragraph (b), section 4.4.2(c) of today’s
‘‘[n]o-load loss means those losses that aluminum windings, and a third level final rule does not include this
are incident to the excitation of the ‘‘[w]here copper and aluminum language.
transformer.’’ NEMA’s revised TP 2 windings are employed in the same D. Basic Model
definition reads: ‘‘no-load (excitation) transformer.’’ However, a separate
loss: No-load (excitation) losses are resistance measurement is performed for 1. General Discussion
those losses that are incident to the each winding of a distribution Under the Department’s energy
excitation of the transformer. No-load transformer. Section 3.5 provides for conservation program, DOE has applied
(excitation) losses include core loss, adjustment of each such measurement, the ‘‘basic model’’ concept to alleviate
dielectric loss, conductor loss in the and each winding will be either copper burden on manufacturers, by reducing
winding due to excitation current, and or aluminum, but not both. Therefore, the amount of testing they must do to
conductor loss due to circulating the equation for adjusting the measured rate the efficiencies of their products.
current in parallel windings. These resistance need not, and should not, DOE’s intent is that a manufacturer
losses change with the excitation include a temperature level that would treat each group of its models
voltage.’’ Again, the Department contemplates the use of the two metals that have essentially identical energy
considers the SNOPR definition to be together, and in today’s final rule, the consumption characteristics as a ‘‘basic
clear and complete for the purposes of Department has deleted from section 3.5 model,’’ such that the manufacturer
this test procedure. As with its the language that includes such a would derive the efficiency rating for all
suggested definition of ‘‘load loss,’’ temperature level. models in the group from testing sample
NEMA’s definition of ‘‘no-load loss’’ Section 4.4.2 of the proposed test units of these models. All of the models
adds information, but its list of procedure concerns testing for no-load in the group would comprise the ‘‘basic
components is explanatory rather than losses. Proposed paragraph (b) of that model,’’ and they would all have the
substantive, and DOE has concerns section directed the tester to ‘‘[e]nergize same efficiency rating. The proposed
similar to those discussed for the ‘‘load not less than 25 percent’’ of either the definition of basic model for
loss’’ definition. For these reasons, the high voltage or low voltage winding. 69 distribution transformers implements
Department is not modifying, except as FR45530. The Department drew the 25 this approach by permitting
indicated, either the ‘‘no-load loss’’ or percent figure from section 8.2.3 of IEEE manufacturers to aggregate models that
the ‘‘load loss’’ definitions. C57.12.90–2001 and C57.12.91–2001, have the same energy consumption
NEMA TP 2–2005 introduces a which recommend energizing 100 characteristics, but not models with
definition of ambient temperature. percent of the winding in conducting different characteristics. Components of
(NEMA, No. 60 Attachment 1, p. 3) This this test, but allow as low as 25 percent. similar design can be substituted in a
definition appears to be derived from The IEEE standards allow the 25 percent basic model without requiring
the American Society of Heating, because they apply not only to additional testing if the represented
Refrigerating and Air-Conditioning distribution transformers but also to measures of energy consumption
Engineers (ASHRAE) Terminology of power transformers. Power transformers continue to satisfy applicable provisions
Heating, Ventilation, Air Conditioning, may require much higher voltages than for sampling and testing.
& Refrigeration (Second Edition) and are available in the power sources used
has several elements that apply to types in performing the no-load test. 2. Definition of a Basic Model
of transformers that are not distribution Distribution transformers, however, In the SNOPR, the Department
transformers. Therefore, it is not require much lower voltages, which can proposed a definition of ‘‘basic model’’
applicable to the Department’s test be accommodated by the available for distribution transformers that
procedure. Moreover, DOE believes that, power sources. Moreover, distribution included essentially the same criteria as
in the context of today’s final rule, transformers rarely have a 25-percent those contained in the definition
ambient temperature clearly refers to the voltage tap that would permit energizing proposed in the 1998 proposed rule,
room temperature in the location where a winding at 25 percent of its rated plus a requirement that the transformers
the measurements are being taken, as voltage, and DOE understands that included in the basic model ‘‘not have
DOE intends. For these reasons, the instead, in testing distribution any differentiating electrical, physical or
Department believes a definition of transformers for no-load losses, functional features that affect energy
ambient temperature is unnecessary in windings are energized to 100 percent of consumption.’’ DOE made several other
today’s rule. rated voltage. Hence, DOE has deleted modifications to the definition, and
Finally, NEMA TP 2–2005 contains a from today’s final rule the provision described these changes in the SNOPR.
number of editorial changes to the allowing testers to energize 25 percent 69 FR 45512–13.
rmajette on PROD1PC67 with RULES3

language in the SNOPR’s test methods. or more of a winding. NEMA commented that the SNOPR
The Department has incorporated Proposed paragraph (c) of section definition of ‘‘basic model’’ was too
several of these, such as edits in the first 4.4.2 required certain conditions with vague and needed clarification. (Public
paragraph of proposed section 6.1, in respect to voltage during the no-load Meeting Transcript, No. 42.11 at pp. 22–
today’s final rule. loss test, ‘‘unless otherwise specified.’’ 23) Specifically NEMA was concerned

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00017 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
24988 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

that the phrase added to the end of the produce numerous basic models. The either by testing it, or, under the
basic model definition ‘‘and do not have Department is aware, however, of no conditions set forth in the rule, by
any differentiating electrical, physical, reasonable way to aggregate models calculating the basic model’s efficiency
or functional features that affect energy with different energy consumption using an alternative efficiency
consumption’’ is unclear. (NEMA, No. characteristics, for purposes of testing, determination method (AEDM). Where
39 at p. 2) DOE believes that these that would produce an accurate the manufacturer uses an AEDM for a
general criteria for the creation of basic efficiency rating for each model basic model, it would not test units of
models are needed to allow included in the grouping. Today’s final the basic model to determine its
manufacturers the flexibility to create rule, however, will allow manufacturers efficiency for purposes of establishing
basic model groupings that reflect to rate the efficiency of many of their compliance with DOE requirements.
product features that affect energy transformers based on calculations 2. Sampling Plan
consumption. To address NEMA’s instead of testing, by using alternative
concern, DOE is modifying the efficiency determination methods. This The Department designed the
definition slightly to provide that should substantially alleviate any sampling plan in today’s final rule to
voltage and basic impulse insulation potential testing burden created by a provide a high probability that
level (BIL) rating are both examples of manufacturer’s producing large numbers manufacturers would find each basic
differentiating electrical features that of basic models. model to be in compliance with the
would cause transformer models to be In summary, DOE will slightly modify efficiency level at which it is
different basic models. DOE stated in the proposed definition of ‘‘basic manufactured, but without creating a
the preamble of the SNOPR that each of model’’ to explicitly provide that (1) significant probability that models
these features would be a differentiating voltage and BIL ratings are examples of would be found to meet levels higher
electrical characteristic, but the differentiating electrical features that than those at which they are
proposed definition itself did not would cause transformer models to be manufactured. The latter—‘‘false
include these examples. different basic models, and (2) each positives’’—would in effect create a
Additionally, NEMA noted it would basic model would comprise a group of regulatory loophole, by allowing
prefer that the rule contain a table of models of distribution transformers. transformer models manufactured at
basic models (NEMA, No. 39 at p. 2) or Otherwise, the proposed definition is efficiency levels below applicable
a tighter definition. (Public Meeting sound because its specific elements and standards to be rated as compliant with
Transcript, No. 42.11 at p. 37) DOE general criteria combine to allow the those standards. The Department’s goal
believes that creation of a table of basic grouping of models with similar energy for distribution transformers is to have
models would be impractical for several consumption characteristics without about a 97.5 percent probability that
reasons. First, there are literally allowing models with different tests on sample units of a basic model
thousands of possible designs for any characteristics to be included in the would verify or support an efficiency
one kVA rating and combination of core same group. rating for the model that is equal to or
steel and winding materials. Second, for less than the average efficiency of all
DOE to attempt to identify both the E. Manufacturer’s Determination of units of that model manufactured.
energy consumption profile of each Efficiency Stated alternatively, a basic model that
such combination of transformer is manufactured at or above its rated
1. General Discussion
features, as well as the combinations efficiency would have a probability of
that have common profiles, would be an During this rulemaking, NEMA not less than 97.5 percent of passing the
enormous undertaking. Third, to the advocated DOE adoption of the compliance demonstration test—i.e.,
extent that any significant number of sampling plan for compliance testing in being found in compliance with its
these possible transformer variations is NEMA TP 2–1998, which would allow rated value—based on test results using
not produced, either now or in the manufacturers to demonstrate the any sample size.
future, effort may be wasted. And compliance of aggregations of basic To accomplish this goal, DOE
fourth, DOE believes that neither it nor models, and the Department presented incorporated into its proposed sampling
industry can accurately anticipate all and solicited comment on several plan a one-sided statistical z-test, with
future design variations of distribution alternative approaches for a 97.5 percent confidence limit for
transformers. A table or other rigid demonstrating such aggregate average efficiency or power loss, which
definition, therefore, would (1) fail to compliance. For the reasons discussed manufacturers would apply to the test
provide for future designs, and/or (2) in the SNOPR, the Department chose results derived from testing sample
conflict with the rationale for using the not to propose adoption of either the units of a basic model. The 97.5 percent
‘‘basic model’’ construct, and (3) force NEMA TP 2–1998 sampling plan or an confidence limit in the one-sided z-test
future designs to be grouped with alternative approach allowing corresponds to 2s/√n, where s
models that do not share their energy aggregation. 69 FR 45513–15. represents the standard deviation of
consumption characteristics. As this last Instead, the Department has adopted units of distribution transformers, and n
point indicates, NEMA’s concern that both a sampling plan for compliance is the number of units, including one, in
the part of the definition quoted above testing, and provisions allowing use of the sample. Thus, for example, if a
could allow additional basic models at alternative methods (other than actual manufacturer tested a sample of only
a later date is misplaced. To the extent testing), for manufacturers to use to one unit of a basic model, and its
that the definition would allow creation determine the efficiency of individual measured power loss did not exceed the
of additional basic models that subsume basic models of distribution rated power loss of the basic model by
models with new energy consumption transformers. As proposed in the more than the amount representing two
characteristics, this indicates the SNOPR, today’s rule requires each standard deviations, the test would
rmajette on PROD1PC67 with RULES3

definition is sound rather than in need manufacturer to determine the confirm the validity of the rated
of alteration. efficiency of each of its basic models on efficiency. By way of further example, if
DOE recognizes that, given the large a one-time basis by testing, at least five the manufacturer tested a sample of
number of variations in distribution with compliance testing, and by rating more than one unit, the numerical value
transformer design, many manufacturers each of the remaining basic models for losses corresponding to the 97.5

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00018 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 24989

percent confidence limit would tolerance on total loss. (Howard, No. 45 tolerances used in determining
decrease, and the precision of the at p. 2) efficiency is inappropriate.
determination of the average losses for Four commenters advocated a 12- Based on the information provided in
the basic model would increase. percent tolerance, which would equate comments, DOE now believes that 4
In developing the SNOPR, DOE had to three SDs of 4 percent. (Cooper, No. percent is the better SD to use, and that
information both to support a standard 46 at pp. 1–2; HVOLT, No. 53 at pp. 1– the available information supporting the
deviation (SD) for distribution 2; PQI, No. 56 at pp. 1–2; NEMA, No. 4 percent figure outweighs that
transformers of 2.7 percent and to 59 at p. 1, NEMA, No. 60, Attachment supporting the 2.7-percent SD. Two SDs
support one of 4 percent. Since the 1 at p. 34) This tolerance level would at 4 percent equates to an eight-percent
information in support of the 2.7 increase the compliance demonstration single unit tolerance, and results in a
percent level was slightly stronger, DOE probability to 99.9 percent, but would tolerance for the average efficiency of
based the confidence limit (or also allow for a significant probability of the sample of units tested of 8/√n
‘‘tolerance’’) 8 in the SNOPR sampling false positives. For example, a basic percent. Increasing the tolerance from
plan on the SD of 2.7 percent. 69 FR model designed with losses 2 percent 5/√n percent to 8/√n percent increases
45515. Two SDs of 2.7 percent above its rated value would have a 99.4- the probability of demonstrating
correspond to a tolerance for the average percent probability of being found to compliance of a product manufactured
efficiency of the sample of units tested have an efficiency at or above its rated at the applicable standard level from
of 5/√n percent. (Most commenters who level if the sample size is one, and about 89 percent to about 98 percent,
commented on the sampling plan would have a 97-percent probability of without introducing a significant
tolerance level addressed it as a straight being found to have such an efficiency probability that a product manufactured
numerical amount, although in actuality if the sample size is five. In addition, a below the standard level would be
the proposed tolerance is a tolerance 12-percent tolerance would be found in compliance. This assumes that
that depends on the size of the sample inconsistent with the much smaller the variability of units of the basic
of units tested, and is 5/√n percent. The tolerance, for rejection of single units, in model being tested have a standard
commenters may have used straight existing IEEE standards. For these deviation of 4 percent. The probability
numerical amounts because application reasons, the Department is not of a significant false positive—finding a
of the expression 5/√n percent to a incorporating the 12-percent tolerance model in compliance with its rated
sample size of one would always result level into its sampling plan. efficiency where on average the units of
in a flat five-percent tolerance.) Three of the commenters advocating that model as manufactured actually
The Department received several the 12-percent tolerance for compliance experience a power loss 2-percent larger
comments stating that its proposed testing based their position in part on than the rated loss—is approximately 93
tolerance was too stringent, and should the assertion that DOE’s rule for electric percent for a sample of one unit and 81
be relaxed. NEMA notes that the motors allows a 20-percent ‘‘test percent for a sample of five units. Both
Department’s equation relating the tolerance band.’’ (Cooper, No. 46 at p. 2; probabilities, especially the second one,
average efficiency of the sample and the HVOLT, No. 53 at p. 2; PQI, No. 56 at are sufficiently low that a manufacturer
represented efficiency assumes a tighter p. 2) The tolerance to which they refer would not risk producing a product
performance probability distribution in the electric motors rule is not with power losses 2 percent or more
function than is achievable in practice, applicable to distribution transformers above the losses at which it seeks to rate
particularly for small manufacturers. for two reasons. First, the 20-percent the product. Thus, today’s final rule
(NEMA, No. 47 at p. 3; NEMA, No. 51 tolerance in the motors rule applies increases the tolerance from 5/√n
at p. 3) during testing that occurs in percent to 8/√n percent.
Four commenters requested that the enforcement proceedings. The rule uses Several manufacturers submitted
tolerance for individual units be relaxed this tolerance to determine the adequacy comments asking that DOE confirm that
from the SNOPR proposal of five of the size of the test sample used in the they have the option of testing all
percent to eight percent. (ERMCO, No. proceeding, following testing of the transformers of a basic model or some
43 at p. 2; FPT, No. 44 at p. 6; Howard, initial sample, and determination of the basic models. (Public Meeting
sample’s mean, standard deviation, and Transcript, No. 42.11 at p. 22; NEMA,
No. 45 at p. 2; EMS, No. 57 at p. 3)
standard error. This 20-percent No. 39 at p. 2) One stakeholder
Federal Pacific commented that use of a
tolerance has no relevance to requested clarification that if it chooses
five-percent tolerance is too stringent
compliance testing. Second, application to test 100 percent of its production, it
given the variability of transformer
of a particular tolerance with respect to would not have to use the sampling
losses, particularly the variability of no-
efficiency and losses for electric motors plan or an AEDM (alternative efficiency
load losses. (FPT, No. 44 at p. 6) EMS
does not indicate the appropriate determination method). (Public Meeting
and ERMCO recommend that the
tolerance for distribution transformers. Transcript, No. 42.11 at p. 65) NEMA
tolerance should be eight percent to be
Induction motors have a similarity to also requested clarification on the
consistent with IEEE/ANSI C57.12.00
transformers in that their stator and number of samples that would have to
and NEMA TP 2. (EMS, No. 57 at p. 3; rotor windings are akin somewhat to the be tested if the sample size is small.
ERMCO, No. 43 at p. 2) Howard primary and secondary windings of a (Public Meeting Transcript, No. 42.11 at
Industries also recommended that the transformer. However, at that point the p. 67)
minimum acceptable efficiency level similarity ends. A transformer has no As indicated above, once efficiency
calculation be based on an eight-percent moving parts in normal operation standards for distribution transformers
8 The precise statistics term ‘‘confidence limit’’ is
whereas a motor’s main feature is the have gone into effect, today’s rule will
frequently replaced in engineering applications by
spinning of the rotor, a mechanical require each manufacturer to rate the
a more general term ‘‘tolerance.’’ In the preceding process which in itself absorbs efficiency of each of its basic models on
rmajette on PROD1PC67 with RULES3

discussion, DOE used the precise term to explain considerable energy. Thus, motors, in a one-time basis. The rating would
the basis of the tolerance in the SNOPR’s proposed addition to having electrical power enable the manufacturer to establish
sampling plan for compliance testing. The
Department will use the term ‘‘tolerance’’ in the
losses, also have mechanical losses. that the basic model complies with the
discussion that follows, particularly because all of Consequently the comparison of motors applicable standard, and provide the
those who commented on this issue used this term. and transformers when discussing basis for any energy representations

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00019 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
24990 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

(e.g., labeling and certification) required containing the validation requirement, rule. Thus to substantiate a single global
by DOE. 69 FR 45514. The Department however, the final rule (in section AEDM that would apply to the entire
intended in its SNOPR proposal, and 431.197(a)(2)(i)) also precludes a range of distribution transformers (all
wishes to confirm with respect to manufacturer from applying an AEDM three groups), a manufacturer would
today’s rule, that where a manufacturer to a basic model unless ‘‘the AEDM has have to test not fewer than 15 basic
arrives at this rating through testing, been derived from a mathematical models (a total of at least 75 units), and
rather than use of an AEDM, the model that represents the electrical it would have to test at least 10 basic
sampling plan would permit the characteristics of that basic model.’’ models (a total of at least 50 units) to
manufacturer to test 100 percent of the Thus, apart from any testing to validate substantiate an AEDM that would apply
units available for testing. The language the accuracy of an AEDM, this language to two groups. DOE believes this
of section 431.194(b)(2) of the final rule will require each AEDM to represent amount of testing to validate the AEDM
has been modified to make this clear. any unique or custom-designed is sufficient.
Thus, where manufacturers have on electrical characteristics of any basic The SNOPR also included a
hand more than five units of a basic model to which it applies. DOE believes requirement that manufacturers
model at the time they do compliance that this provision satisfactorily ‘‘periodically’’ verify each AEDM that
testing to rate the basic model, or addresses Howard’s concern that DOE they use. 69 FR 45523. Howard
produce more than five over a six- require AEDMs to reflect the particular Industries recommended that the
month period, they would have the characteristics of the transformers to Department change ‘‘periodically’’ to
discretion to rate the basic model based which they apply. ‘‘annually.’’ (Howard, No. 45 at p. 3, and
on testing either all of the units or a The Department believes that to No. 55 at p. 3) The Department
sample of at least five units. In addition, require each AEDM to be validated considered this proposal, but decided
the final rule clearly requires based on testing of 75 basic models, or that annual verification of an AEDM,
compliance testing of 100 percent of the some other number larger than five, which could include testing, could be
units for basic models for which a would create undue burden. The unduly burdensome on manufacturers.
manufacturer produces five or fewer foregoing is particularly true because
The Department has also decided,
units during a six-month period. DOE understands that manufacturers
however, largely because of the
None of the provisions in today’s rule use design models and software to
particular circumstances of the
would prevent a manufacturer from design their distribution transformers,
distribution transformer industry, to
doing continuous testing of 100 percent and DOE believes that most AEDMs
eliminate the periodic verification
of the units it produces in order to meet would be derived from, or consist of,
requirement from today’s final rule.
contractual obligations to report to its such models and software. Since these
Many distribution transformer
customers the losses, efficiency or other design tools would have validity
manufacturers already engage in
energy consumption characteristics of independent of the AEDM
continuous testing—sometimes by
each individual unit it sells to them. substantiation required by DOE
Nor does the Department anticipate that regulations, extensive testing to testing 100 percent of their units—to
provisions it may adopt, for assuring substantiate the validity of AEDMs assure that the actual performance,
compliance with energy conservation appears to be unnecessary. including efficiency, of their products
standards and for manufacturer Section 432.12(a)(2)(iii) of the conforms to the manufacturer’s design
representations (e.g., labeling) as to proposed rule restricted the use of each software and representations to
efficiency, would prevent manufacturers AEDM to one of the following groups of customers. In addition, other provisions
from testing all of their units in order to distribution transformers: low-voltage of today’s final rule authorize DOE to
meet such obligations. dry-type transformers, medium-voltage obtain information from manufacturers
dry-type transformers, and liquid- concerning their use of AEDMs, and to
3. Alternative Efficiency Determination immersed transformers. 69 FR 45522. require a manufacturer to do sample
Method (AEDM) Upon further review, the Department testing or take other steps. Thus, DOE
Under the proposed rule, a believes that this provision is too now believes that mandatory, periodic,
manufacturer would have to validate restrictive, and that manufacturers subsequent verification of AEDMs for
each AEDM it uses based on test data for should be permitted to use a single distribution transformers is
at least five basic models, derived by AEDM for distribution transformers in unwarranted.
testing at least five units of each of these two or all three of these groups, so long F. Enforcement Procedures
basic models. 69 FR 45522. Taken as the manufacturer validates the AEDM
together, these provisions would require separately for each group. The The SNOPR included proposed
testing of at least 25 units to validate an Department is aware of no reason why enforcement procedures, including a
AEDM. Howard Industries commented it should limit use of each AEDM to sampling plan and other provisions for
that five basic models is too small a transformers in one of these groups, if enforcement testing. 69 FR 45415–17,
sample to adequately represent all the the AEDM can validly predict the 45523–23, 45533–34. The Department
different kVA/voltages/BIL efficiency for transformers in more than based the proposed procedures on
requirements when validating an AEDM one group. Accordingly, today’s final enforcement provisions in 10 CFR Part
and recommended that DOE require 75 rule allows a single AEDM to apply to 430, which apply when DOE examines
models to be tested to validate an two or all three of these groupings. See whether a basic model of a covered
AEDM. (Howard, No. 45 at p. 3, and No. 10 CFR section 431.197(a)(2) of the rule. product complies with efficiency
55 at p. 3) Howard also asserted that five The rule also requires that the requirements set forth in those parts.
basic models was too low a number to manufacturer validate each AEDM The SNOPR’s enforcement sampling
verify that the AEDM would accurately separately for each group—i.e., low- plan was based on the plan in Part 430,
rmajette on PROD1PC67 with RULES3

predict the efficiency of all liquid- voltage dry-type, medium-voltage dry- but was developed specifically for
immersed transformers. It stated that type, and liquid-immersed—for which it distribution transformers. It allows
transformers vary considerably, with a uses the AEDM, based on test data for testing of small sample sizes and applies
large number of design options. five basic models from such group. 10 only to energy efficiency testing,
(Howard, No. 58 at p. 1) In addition to CFR section 431.197(a)(2)(iii) of the whereas the Part 430 plan contemplates

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00020 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 24991

larger sample sizes and covers energy calculations. (FPT, No. 44 at p. 6) As General Counsel’s Web site: http://
use testing. explained in the SNOPR, the statistical www.gc.doe.gov.
NEMA requested clarification on methods used in those calculations were The Department reviewed today’s
when the process of enforcement based on well-established statistical final rule under the provisions of the
commences. (Public Meeting Transcript, methods for obtaining a confidence Regulatory Flexibility Act and the
No. 42.11 at p. 73) The Department interval on a mean. 69 FR 45516. Hence, procedures and policies published on
initiates the enforcement process when the Department believes these February 19, 2003, and certified in the
it receives information, either from a calculations can be understood by any SNOPR that the proposed rule would
third party or other source, indicating statistician. In addition, a complete not impose a significant economic
that a manufacturer’s units may not be explanation is set forth in NIST impact on a substantial number of small
in compliance with the national Technical Note 1456, Operating entities. 69 FR 45517. As indicated in
standard. Initially, DOE seeks to meet Characteristics of the Proposed section I-A above, when it issued the
with the manufacturer and review its Sampling Plans for Testing Distribution SNOPR DOE was concurrently pursuing
underlying test data as to the models in Transformers, May 2004, which has a rulemaking to develop energy
question. DOE would commence been placed in the docket for this conservation standards for low-voltage
enforcement testing procedures if these rulemaking and is publicly available at dry type, medium-voltage dry type and
steps do not resolve identified http://www.eere.energy.gov/buildings/ liquid immersed distribution
compliance issues. appliance_standards/commercial/ transformers. The Department explained
The Department also received dist_transformers.html. On the other in the SNOPR that, unless and until
comments relating to enforcement as to hand, it would be very burdensome for DOE adoption of such standards, no
stock units and imported units. Cooper DOE to develop and include in this entities, small or large, would be
sought clarification on application of notice a detailed explanation, in required to comply with today’s final
efficiency standards to units in stock layman’s terms, of the statistics and rule. 69 FR 45517. Once the Department
when standards take effect, and to operation of these equations. adopted standards, however, the rule
foreign manufacturers. (Cooper, No. 46 Furthermore, these equations will be would become binding on, and could
at p. 2) Traditionally, new DOE used by DOE, and would not be applied have an economic impact on, small
standards for a product have applied to by manufacturers. For these reasons, the entities which manufacture the
units manufactured after a certain date, Department has concluded that the type distribution transformers subject to the
or, in the case of foreign-manufactured of explanation Federal Pacific requests standards. But the nature and extent of
units, imported after that date. See, e.g., is unwarranted, and would add little such impact, if any, could not be
42 U.S.C. 6291, 6295, 6311 and 6313. useful information to the record of this assessed until the Department has
The Department anticipates that this rulemaking. promulgated the standards. The
will also be the case for distribution Department stated in the SNOPR that, in
transformers. Therefore, the efficiency III. Procedural Requirements light of these circumstances, at an
levels would not apply to units in a appropriate point in conjunction with
A. Review Under Executive Order 12866
domestic manufacturer’s stock prior to the standards rulemaking, it will
the date standards become applicable, The Office of Information and conduct further review under the
or to units imported prior to that date. Regulatory Affairs of the Office of Regulatory Flexibility Act. The
In all other respects, DOE anticipates Management and Budget (OMB) has Department received no comments on
that the same requirements and determined that today’s regulatory this issue in response to the SNOPR.
enforcement provisions that apply to action is not a ‘‘significant regulatory For medium-voltage dry-type and
domestic units will also apply to action’’ under Executive Order 12866, liquid immersed distribution
imported units. In addition, however, ‘‘Regulatory Planning and Review,’’ 58 transformers, DOE is continuing to
imported units are subject to the FR 51735 (October 4, 1993). pursue its standards-development
provisions of 42 U.S.C. 6301 of EPCA, Accordingly, this action was not subject rulemaking and the circumstances
concerning importation of products to review under the Executive Order. described in the SNOPR still exist.
subject to EPCA requirements. B. Review Under the Regulatory
Therefore, after considering the
HVOLT commented that the potential impact of this final rule on
Flexibility Act of 1980
Department should require that the small entities that manufacture these
efficiency of any foreign-built The Regulatory Flexibility Act (5 transformers, DOE affirms the
transformer be verified by a third party U.S.C. 601 et seq.) requires preparation certification that this rule will not have
before it can be sold in the U.S. of an initial regulatory flexibility a significant economic impact on a
(HVOLT, No. 53 at p. 3) The Department analysis for any rule that by law must substantial number of these small
believes that this issue is outside the be proposed for public comment, unless entities.
scope of this rulemaking. Today’s final the agency certifies that the rule, if Low-voltage dry-type distribution
rule does not address the DOE promulgated, will not have a significant transformers, however, are no longer
administrative framework for economic impact on a substantial included in DOE’s rulemaking on
manufacturers to follow to demonstrate number of small entities. As required by energy conservation standards for
compliance with distribution Executive Order 13272, Proper distribution transformers. Instead,
transformer energy conservation Consideration of Small Entities in EPCA, as amended in EPACT 20005,
standards. The Department will likely Agency Rulemaking, 67 FR 53461 now specifies minimum standards for
address such requirements in (August 16, 2002), DOE published all such transformers manufactured after
conjunction with the standards procedures and policies on February 19, January 1, 2007, 42 U.S.C. 6295(y), and
rulemaking. 2003, to ensure that the potential the Department has incorporated those
rmajette on PROD1PC67 with RULES3

The SNOPR enforcement sampling impacts of its rules on small entities are standards into its regulations. 10 CFR
plan contained several calculation properly considered during the section 431.196. Because today’s rule
equations. 69 FR 45533. Federal Pacific rulemaking process. 68 FR 7990. The will apply to all distribution
requested further explanation and Department has made its procedures transformers that become subject to
examples of the enforcement and policies available on the Office of standards, as of January 1, 2007, the rule

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00021 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
24992 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

would become binding on all only part of the process that could number of its basic models a
manufacturers, small and large, of low- impose a significant burden on manufacturer must rate through actual
voltage dry-type distribution manufacturers. For all of these reasons testing and how may units of each it
transformers. Consequently, under the the Department concludes that the must test, (2) prescribes a detailed
Regulatory Flexibility Act, the enforcement provisions in today’s rule method for testing each unit, and (3)
Department must assess the economic will not have a significant impact on a provides for use of alternative efficiency
impact of this rule on small substantial number of entities, whether determination methods for transformers
manufacturers of these transformers. small or large. that manufacturers do not rate through
Small businesses, as defined by the As to the methods for manufacturers testing. See Section 431.193 and
Small Business Administration (SBA) to rate the efficiencies of low-voltage 431.197 of the attached rule. As to
for the distribution transformer dry-type distribution transformers, DOE whether today’s method for testing each
manufacturing industry, are notes initially that requirements for unit is more burdensome than NEMA
manufacturing enterprises with 750 testing and rating these transformers are TP 2–1998, the two are nearly identical
employees or fewer. The Department already implicit in EPCA. Specifically, except that the Department’s method
estimates that, of a total of to comply with EPCA’s efficiency adds technical detail, clarifying
approximately 55 manufacturers of low- standards for low-voltage dry-type language, and editorial improvements.
voltage dry-type distribution distribution transformers, 42 U.S.C. Thus, the DOE method is no more
transformers, about 45 are small 6295(y), manufacturers will have to burdensome, and may alleviate burden
businesses under the SBA definition. In determine the efficiencies of any such because it reduces the need for
today’s rule, the enforcement provisions transformers they produce. This manufacturers to do background work to
and the methods manufacturers must necessarily entails the use of testing and provide missing details and clarify
use to rate its products could potentially rating methods, and if DOE does not ambiguous provisions.
impose burdens on these small prescribe such methods, manufacturers
Nor does today’s test method impose
manufacturers. But DOE has examined would still be subject to the burden of
significantly, if any, more burden than
these aspects of the rule and determined using such tools. In addition, as noted
other methods a small manufacturer
that they will not have a significant above, EPCA requires DOE to prescribe
might reasonably use to comply with
economic impact on a substantial testing requirements for any
the EPACT standards for low-voltage
number of small manufacturers of low- transformers subject to standards, and
dry-type transformers. A manufacturer
voltage dry-type distribution states that these requirements ‘‘shall be
transformers. based on’’ NEMA TP 2–1998. 42 U.S.C. might choose to use NEMA TP 2–1998,
As to the enforcement provisions, 6293(b)(10) and 6317(a). Although these which as just indicated is no more
they require DOE to first attempt to provisions allow the Department burdensome than today’s method, or
resolve a transformer’s possible non- substantial discretion in prescribing a NEMA TP 2–2005, which is almost
compliance with EPCA requirements by test method for distribution word-for-word the same as the SNOPR’s
reviewing available information and transformers, they indicate that EPCA test method and which varies little from
meeting with the manufacturer. Then, if contemplates that the DOE method today’s rule. A manufacturer might also
necessary, DOE must test sample units likely would impose burdens equivalent craft a test method from the standards
of the allegedly non-complying basic or similar to those imposed by NEMA of accepted engineering practice as set
model(s) to determine whether they TP 2–1998. Thus, today’s rule itself has forth in IEEE standards. On the one
comply. See Section 431.198 of the an impact on small manufacturers only hand, except for the requirements as to
attached rule. Only provisions that to the extent it imposes an incremental equipment calibration in today’s rule,
come into play once DOE invokes burden beyond what they would be the test method in the rule is the
testing—specifically, manufacturers required to do to comply with EPCA’s equivalent to the method in the four
must provide and ship sample units to standards or NEMA TP 2–1998. relevant IEEE standards. On the other
DOE and must retain all units in the This is significant under the hand, DOE believes it is possible that
batch sample until a final determination Regulatory Flexibility Act because the small manufacturers might each be able
of compliance or non-compliance, and Act applies only where the agency’s rule to modify the details of the IEEE test
manufacturers may conduct additional has a significant impact on small method so as to best fit its products. As
testing at their own expense if the DOE entities. It does not apply to a rule if the a result its costs of testing needed to
testing indicates non-compliance— agency certifies that ‘‘the rule will not comply with the EPACT efficiency
could impose a significant burden on * * * have a significant impact on a standards, i.e., implicit in the EPACT
manufacturers. substantial number of small entities.’’ 5 requirements, could be lower than the
None of the enforcement provisions U.S.C. 605(a) (Emphasis added). Thus, cost of testing under the test method in
imposes on-going duties on the Act does not apply, for example, today’s rule. The Department believes
manufacturers. They apply only when where the agency merely incorporates that such savings would not be
an issue of compliance is raised, which statutory requirements into its rules, or significant, and to some extent would be
at this point is speculative. Indeed, even adopts the equivalent of statutory offset by the resources a small
when they are invoked as to a particular requirements without adding any manufacturer would have to expend to
manufacturer, they will only apply to significant impact on small entities. In research and develop such a customized
the specific basic model(s) at issue. such instances, it is the statutory test method. Today’s method does
Moreover, these types of enforcement requirements, and not the agency’s rule, include requirements to calibrate
provisions have been in place for DOE’s that could have an impact on small equipment and maintain records of such
program for appliance energy entities. The Department therefore calibrations, which are not explicitly
conservation standards for more than 15 examines in the following paragraphs included in the IEEE standards. But to
rmajette on PROD1PC67 with RULES3

years, and the Department has whether today’s rule imposes any achieve the accuracy levels required
commenced the process at most two or burdens on small entities beyond those under these standards, a manufacturer
three times a year. In every instance it imposed by EPCA. would have to engage in some
has resolved the matter without In prescribing efficiency rating calibration effort. In any event, DOE
proceeding to enforcement testing, the methods, today’s rule (1) addresses the estimates that today’s rule would

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00022 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 24993

require only about one week of staff would allow a manufacturer to do less record-keeping requirements that must
time to satisfy the calibration than 20 percent of the testing that would be approved by the OMB pursuant to
requirements in the first year the rule is otherwise be required. the Paperwork Reduction Act before the
operative, and about two days a year For all of these reasons, the manufacturers may be required to
thereafter. For the foregoing reasons, the Department certifies that today’s final comply with them. Section
Department concludes that, although rule would not have a significant 431.197(a)(4)(i) would require
today’s test method might impose economic impact on a substantial manufacturers of distribution
modest burdens on small manufacturers number of small entities. Accordingly, transformers to have records as to
of low-voltage dry-type distribution DOE has not prepared a regulatory alternative efficiency determination
transformers, these burdens are not flexibility analysis for this rulemaking. methods available for DOE inspection;
significant. DOE has transmitted the certification section 6.2 of Appendix A would
However, the final rule’s provisions as and supporting statement of factual require maintenance of calibration
to the amount of testing required to rate basis to the Chief Counsel for Advocacy records. As a result, concurrent with or
distribution transformer efficiencies are of the Small Business Administration shortly after publication of today’s rule,
clearly far less burdensome to small for review pursuant to 5 U.S.C. 605(b). the Department will issue a notice
manufacturers than methodologies seeking public comment under the
C. Review Under the Paperwork
currently in use. The rule requires each Paperwork Reduction Act, with respect
Reduction Act
manufacturer to test at least five basic to these manufacturers, on the record-
models. For each such model, the As indicated in the SNOPR, today’s keeping requirements in today’s rule.
manufacturer must test the lesser of all final rule contains certain record- After considering any public comments
units manufactured over a 180 day keeping requirements. 69 FR 45517. The received in response to that notice, DOE
period or five units, and must rate the situation with respect to the Paperwork will submit the proposed collection of
basic model’s efficiency by applying a Reduction Act (44 U.S.C. 3501 et seq.) information to OMB for approval
formula to the test results. The rule also is similar to that described in Section pursuant to 44 U.S.C. 3507.
allows use of AEDMs to rate the III.B. with respect to the Regulatory An agency may not conduct or
remaining basic models. The IEEE Flexibility Act. For the reasons stated sponsor, and a person is not required to
standards contain no provision for there, unless and until the Department respond to a collection of information
sampling, or for use of AEDMs, in rating requires manufacturers to comply with unless it displays a currently valid OMB
the efficiency of distribution energy conservation standards for control number. As stated in the
transformers. Moreover, DOE medium-voltage and liquid immersed ‘‘EFFECTIVE DATE’’ line of this notice
understands that, under current distribution transformers, no of final rulemaking, the information
practice, where a manufacturer must manufacturer of those products would collection requirements in
rate a low-voltage dry-type transformer’s be required to comply with these § 431.197(a)(4)(i) and section 6.2(b) and
losses—the equivalent of efficiency record-keeping provisions. Therefore, (c) of Appendix A will not become
determination—typically it will test all today’s rule would not impose on those effective until OMB approves them. The
units and rate them based on their manufacturers any new reporting Department will publish a document in
average efficiency. Although, as requirements requiring clearance by the Federal Register advising low-
explained below in footnote 6, EPCA OMB under the Paperwork Reduction voltage dry-type manufacturers of their
does not direct DOE to use the sampling Act. The Department recognizes, effective date. That document also will
regimen in NEMA TP 2–1998, that is a however, as also set forth in the SNOPR, display the OMB control number.
methodology a manufacturer might use that if it adopts standards for those
to determine whether its low-voltage distribution transformers, once the D. Review Under the National
dry-type transformers comply with standards become operative Environmental Policy Act of 1969
EPCA’s standards. NEMA TP 2–1998’s manufacturers will become subject to DOE has determined that this rule
sampling plan provides that, over a 180- the record-keeping requirements in falls into a class of actions that are
day period, either all units today’s rule, and possibly additional categorically excluded from review
manufactured be tested, or that five or reporting and/or record-keeping under the National Environmental
more units per month be tested, thus requirements. 69 FR 45517. Policy Act of 1969 (42 U.S.C. 4321 et
requiring approximately six times as We received no comments on this seq.) and the Department’s
much testing as today’s rule. It also issue. For medium-voltage and liquid implementing regulations at 10 CFR part
contains no provision for rating immersed distribution transformers, the 1021. Specifically, this rule establishing
transformer efficiencies through use of Department intends, as stated in the test procedures will not affect the
AEDMs. As explained in the SNOPR, 69 SNOPR, to comply with the Paperwork quality or distribution of energy and,
FR 45514–15, NEMA TP 2–1998 clearly Reduction Act with respect to the will not result in any environmental
requires considerably more testing that record-keeping requirements in today’s impacts, and, therefore, is covered by
today’s final rule (which requires the rule at the appropriate point in the Categorical Exclusion in paragraph
same amount of testing as DOE’s conjunction with the standards A6 to subpart D, 10 CFR part 1021.
proposal in the SNOPR). development rulemaking. Accordingly, neither an environmental
Insofar as the final rule’s reduction in Since the publication of the SNOPR, assessment nor an environmental
testing burden results from the use of however, the Department has adopted impact statement is required.
AEDMs, however, this benefit is not standards prescribed by EPCA for low-
without cost. The Department estimates voltage dry-type distribution E. Review Under Executive Order 13132
that a manufacturer would have to incur transformers. When these standards Executive Order 13132, ‘‘Federalism,’’
approximately three to six weeks of become operative on January 1, 2007, 64 FR 43255 (August 4, 1999), imposes
rmajette on PROD1PC67 with RULES3

engineering staff time to develop a valid manufacturers of those products will be certain requirements on agencies
AEDM, and approximately two weeks of required to comply with the record- formulating and implementing policies
staff time to administer and maintain keeping provisions in today’s rule. or regulations that preempt State law or
the AEDM(s) thereafter. The Department Therefore, as to these manufacturers that have federalism implications. The
estimates, however, that use of AEDMs today’s final rule contains certain Executive Order requires agencies to

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00023 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
24994 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

examine the constitutional and statutory G. Review Under the Unfunded Amendment to the United States
authority supporting any action that Mandates Reform Act of 1995 Constitution.
would limit the policymaking discretion Title II of the Unfunded Mandates
of the States and carefully assess the J. Review Under the Treasury and
Reform Act of 1995 (UMRA) (Pub. L. General Government Appropriations
necessity for such actions. The 104–4) requires each Federal agency to
Executive Order also requires agencies Act, 2001
assess the effects of Federal regulatory
to have an accountable process to actions on State, local, and Tribal Section 515 of the Treasury and
ensure meaningful and timely input by governments and the private sector. For General Government Appropriations
State and local officials in the a proposed regulatory action likely to Act, 2001 (44 U.S.C. 3516 note) provides
development of regulatory policies that result in a rule that may cause the for agencies to review most
have federalism implications. On March expenditure by State, local, and Tribal disseminations of information to the
14, 2000, DOE published a statement of governments, in the aggregate, or by the public under guidelines established by
policy describing the intergovernmental private sector of $100 million or more each agency pursuant to general
consultation process it will follow in the in any one year (adjusted annually for guidelines issued by OMB. OMB’s
development of such regulations 65 FR inflation), section 202 of UMRA requires guidelines were published at 67 FR
13735. DOE has examined today’s final a Federal agency to publish a written 8452 (February 22, 2002), and DOE’s
rule and has determined that it does not statement that estimates the resulting guidelines were published at 67 FR
preempt State law and does not have a costs, benefits, and other effects on the
62446 (October 7, 2002). The
substantial direct effect on the States, on national economy. (2 U.S.C. 1532(a), (b))
Department has reviewed today’s final
the relationship between the national The UMRA also requires a Federal
rule under the OMB and DOE guidelines
government and the States, or on the agency to develop an effective process
distribution of power and to permit timely input by elected and has concluded that it is consistent
responsibilities among the various officers of State, local, and Tribal with applicable policies in those
levels of government. No further action governments on a proposed ‘‘significant guidelines.
is required by Executive Order 13132. intergovernmental mandate,’’ and K. Review Under Executive Order 13211
requires an agency plan for giving notice
F. Review Under Executive Order 12988 and opportunity for timely input to Executive Order 13211, ‘‘Actions
With respect to the review of existing potentially affected small governments Concerning Regulations That
regulations and the promulgation of before establishing any requirements Significantly Affect Energy Supply,
new regulations, section 3(a) of that might significantly or uniquely Distribution, or Use,’’ 66 FR 28355 (May
Executive Order 12988, ‘‘Civil Justice affect small governments. On March 18, 22, 2001) requires Federal agencies to
1997, DOE published a statement of prepare and submit to the Office of
Reform’’ (61 FR 4729, February 7, 1996),
policy on its process for Information and Regulatory Affairs
imposes on Federal agencies the general
intergovernmental consultation under (OIRA), Office of Management and
duty to adhere to the following
UMRA. 62 FR 12820 (also available at Budget, a Statement of Energy Effects for
requirements: (1) Eliminate drafting
http://www.gc.doe.gov). Today’s rule any proposed significant energy action.
errors and ambiguity; (2) write
does not contain any Federal mandate A ‘‘significant energy action’’ is defined
regulations to minimize litigation; and
likely to result in an aggregate as any action by an agency that
(3) provide a clear legal standard for
expenditure of $100 million or more in promulgated or is expected to lead to
affected conduct rather than a general
any year, so these requirements under
standard and promote simplification promulgation of a final rule, and that:
the Unfunded Mandates Reform Act do
and burden reduction. Section 3(b) of (1) Is a significant regulatory action
not apply.
Executive Order 12988 specifically under Executive Order 12866, or any
requires that Executive agencies make H. Review Under the Treasury and successor order; and (2) is likely to have
every reasonable effort to ensure that the General Government Appropriations a significant adverse effect on the
regulation: (1) Clearly specifies the Act of 1999 supply, distribution, or use of energy, or
preemptive effect, if any; (2) clearly Section 654 of the Treasury and (3) is designated by the Administrator of
specifies any effect on existing Federal General Government Appropriations OIRA as a significant energy action. For
law or regulation; (3) provides a clear Act, 1999 (Pub. L. 105–277) requires any proposed significant energy action,
legal standard for affected conduct Federal agencies to issue a Family the agency must give a detailed
while promoting simplification and Policymaking Assessment for any rule statement of any adverse effects on
burden reduction; (4) specifies the that may affect family well-being. This energy supply, distribution, or use
retroactive effect, if any; (5) adequately rule would not have any impact on the should the proposal be implemented,
defines key terms; and (6) addresses autonomy or integrity of the family as and of reasonable alternatives to the
other important issues affecting clarity an institution. Accordingly, DOE has action and their expected benefits on
and general draftsmanship under any concluded that it is not necessary to energy supply, distribution, and use.
guidelines issued by the Attorney prepare a Family Policymaking
General. Section 3(c) of Executive Order This final rule is not a significant
Assessment.
12988 requires Executive agencies to regulatory action under Executive Order
review regulations in light of applicable I. Review Under Executive Order 12630 12866 or any successor order. In
standards in section 3(a) and section The Department has determined, addition, it is not likely to have a
3(b) to determine whether they are met under Executive Order 12630, significant adverse effect on the supply,
or it is unreasonable to meet one or ‘‘Governmental Actions and Interference distribution, or use of energy, nor has it
rmajette on PROD1PC67 with RULES3

more of them. DOE has completed the with Constitutionally Protected Property been designated by the Administrator of
required review and determined that, to Rights,’’ 53 FR 8859 (March 18, 1988), OIRA as a significant energy action.
the extent permitted by law, this rule that this regulation would not result in Thus, DOE has not prepared a Statement
meets the relevant standards of any takings which might require of Energy Effects.
Executive Order 12988. compensation under the Fifth

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00024 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 24995

L. Review Under Section 32 of the ■ 2. Section 431.191 is revised to read differentiating electrical features that
Federal Energy Administration Act of as follows: affect energy consumption.
1974 Distribution transformer means a
§ 431.191 Purpose and scope. transformer that—
Under Section 301 of the Department This subpart contains energy
of Energy Organization Act (Pub. L. 95– (1) Has an input voltage of 34.5 kV or
conservation requirements for less;
91), the Department must comply with
distribution transformers, pursuant to (2) Has an output voltage of 600 V or
Section 32 of the Federal Energy
Parts B and C of Title III of the Energy less;
Administration Act of 1974 (FEAA), as
Policy and Conservation Act, as (3) Is rated for operation at a
amended by the Federal Energy
amended, 42 U.S.C. 6291–6317. frequency of 60 Hz; and
Administration Authorization Act of
1977. (15 U.S.C. 788) The Department ■ 3. Section 431.192 is amended by: (4) Has a capacity of 10 kVA to 2500
■ a. Revising the Section heading. kVA for liquid-immersed units and 15
indicated in the SNOPR that Section 32
■ b. Adding introductory language. kVA to 2500 kVA for dry-type units; but
applies to the portion of today’s rule
■ c. Adding in alphabetical order (5) The term ‘‘distribution
that incorporates testing methods
contained in five commercial standards, definitions of ‘‘autotransformer,’’ ‘‘basic transformer’’ does not include a
requiring consultation with the Attorney model,’’ ‘‘drive (isolation) transformer,’’ transformer that is an—
General and the Chairman of the Federal ‘‘efficiency,’’ ‘‘excitation current or no- (i) Autotransformer;
Trade Commission concerning the load current,’’ ‘‘grounding transformer,’’ (ii) Drive (isolation) transformer;
impact of these standards on ‘‘liquid-immersed distribution (iii) Grounding transformer;
competition. 69 FR 45506, 45519 (July transformer,’’ ‘‘load loss,’’ ‘‘machine- (iv) Machine-tool (control)
29, 2004). tool (control) transformer,’’ ‘‘medium- transformer;
Since publication of the SNOPR, DOE voltage dry-type distribution (v) Nonventilated transformer;
has reviewed this requirement for transformer,’’ ‘‘no-load loss,’’ (vi) Rectifier transformer;
consultation as it applies to this final ‘‘nonventilated transformer,’’ ‘‘phase (vii) Regulating transformer;
rule. While DOE now believes that such angle,’’ ‘‘phase angle correction,’’ (viii) Sealed transformer;
‘‘phase angle error,’’ ‘‘rectifier (ix) Special-impedance transformer;
consultation is not necessarily required
transformer,’’ ‘‘reference temperature,’’ (x) Testing transformer;
for this rule, since DOE stated in the
‘‘regulating transformer,’’ ‘‘sealed (xi) Transformer with tap range of 20
SNOPR that it would submit it for
transformer,’’ ‘‘special-impedance percent or more;
consultation under Section 32, it has
transformer,’’ ‘‘temperature correction,’’ (xii) Uninterruptible power supply
done so. Neither the Attorney General
‘‘test current,’’ ‘‘test frequency,’’ ‘‘test transformer; or
nor the Chairman of the Federal Trade
voltage,’’ ‘‘testing transformer,’’ ‘‘total (xiii) Welding transformer.
Commission has recommended against
loss,’’ ‘‘transformer with tap range of 20 Drive (isolation) transformer means a
incorporation of these standards.
percent or more,’’ ‘‘uninterruptible transformer that:
M. Congressional Notification power supply transformer,’’ ‘‘waveform (1) Isolates an electric motor from the
As required by 5 U.S.C. 801, DOE will correction,’’ and ‘‘welding transformer.’’ line;
report to Congress on the promulgation ■ d. Revising the definition of (2) Accommodates the added loads of
of this rule prior to its effective date. ‘‘distribution transformer.’’ drive-created harmonics; and
The report will state that it has been The revision and additions read as (3) Is designed to withstand the
determined that the rule is not a ‘‘major follows: additional mechanical stresses resulting
rule’’ as defined by 5 U.S.C. 804(2). from an alternating current adjustable
§ 431.192 Definitions. frequency motor drive or a direct
IV. Approval of the Office of the The following definitions apply for current motor drive.
Secretary purposes of this subpart: Efficiency means the ratio of the
The Secretary of Energy has approved Autotransformer means a transformer useful power output to the total power
publication of this final rule. that: input.
(1) Has one physical winding that Excitation current or no-load current
List of Subjects in 10 CFR Part 431 consists of a series winding part and a means the current that flows in any
Administrative practice and common winding part; winding used to excite the transformer
procedure, Distribution transformers, (2) Has no isolation between its when all other windings are open-
Energy conservation. primary and secondary circuits; and circuited.
Issued in Washington, DC, on March 28, (3) During step-down operation, has a Grounding transformer means a three-
2006. primary voltage that is equal to the total phase transformer intended primarily to
Douglas L. Faulkner, of the series and common winding provide a neutral point for system-
Acting Assistant Secretary, Energy Efficiency voltages, and a secondary voltage that is grounding purposes, either by means of:
and Renewable Energy. equal to the common winding voltage. (1) A grounded wye primary winding
Basic model means a group of models and a delta secondary winding; or
■ For the reasons set forth in the
of distribution transformers (2) A transformer with its primary
preamble, Part 431 of Chapter II of Title
manufactured by a single manufacturer, winding in a zig-zag winding
10, Code of Federal Regulations, is
amended as set forth below. that have the same insulation type (i.e., arrangement, and with no secondary
liquid-immersed or dry-type), have the winding.
PART 431—ENERGY EFFICIENCY same number of phases (i.e., single or Liquid-immersed distribution
PROGRAM FOR CERTAIN three), have the same standard kVA transformer means a distribution
COMMERCIAL AND INDUSTRIAL rating, and do not have any transformer in which the core and coil
rmajette on PROD1PC67 with RULES3

EQUIPMENT differentiating electrical, physical or assembly is immersed in an insulating


functional features that affect energy liquid.
■ 1. The authority citation for Part 431 consumption. Differences in voltage and Load loss means, for a distribution
continues to read as follows: differences in basic impulse insulation transformer, those losses incident to a
Authority: 42 U.S.C. 6291–6317. level (BIL) rating are examples of specified load carried by the

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00025 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
24996 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

transformer, including losses in the Phase angle means the angle between transformers, at 35 percent load and 50
windings as well as stray losses in the two phasors, where the two phasors percent load, respectively. It is the
conducting parts of the transformer. represent progressions of periodic temperature at which the transformer
* * * * * waves of either: losses must be determined, and to
(1) Two voltages; which such losses must be corrected if
Machine-tool (control) transformer (2) Two currents; or testing is done at a different point.
means a transformer that is equipped (3) A voltage and a current of an (These temperatures are specified in the
with a fuse or other over-current alternating current circuit. test method in Appendix A to this part.)
protection device, and is generally used Phase angle correction means the
for the operation of a solenoid, Regulating transformer means a
adjustment (correction) of measurement
contactor, relay, portable tool, or transformer that varies the voltage, the
data to negate the effects of phase angle
localized lighting. phase angle, or both voltage and phase
error.
Phase angle error means incorrect angle, of an output circuit and
Medium-voltage dry-type distribution compensates for fluctuation of load and
transformer means a distribution displacement of the phase angle,
introduced by the components of the input voltage, phase angle or both
transformer in which the core and coil voltage and phase angle.
assembly is immersed in a gaseous or test equipment.
Rectifier transformer means a Sealed transformer means a
dry-compound insulating medium, and transformer designed to remain
which has a rated primary voltage transformer that operates at the
fundamental frequency of an hermetically sealed under specified
between 601 V and 34.5 kV. conditions of temperature and pressure.
alternating-current system and that is
No-load loss means those losses that designed to have one or more output Special-impedance transformer
are incident to the excitation of the windings connected to a rectifier. means any transformer built to operate
transformer. Reference temperature means 20 °C at an impedance outside of the normal
Nonventilated transformer means a for no-load loss, 55 °C for load loss of impedance range for that transformer’s
transformer constructed so as to prevent liquid-immersed distribution kVA rating. The normal impedance
external air circulation through the coils transformers at 50 percent load, and 75 range for each kVA rating for liquid-
of the transformer while operating at °C for load loss of both low-voltage and immersed and dry-type transformers is
zero gauge pressure. medium-voltage dry-type distribution shown in Tables 1 and 2, respectively.

TABLE 1.—NORMAL IMPEDANCE RANGES FOR LIQUID-IMMERSED TRANSFORMERS


Single-phase transformers Three-phase transformers

Impedance Impedance
kVA kVA
(%) (%)

10 ................................................................................................................................................. 1.0–4.5 15 1.0–4.5


15 ................................................................................................................................................. 1.0–4.5 30 1.0–4.5
25 ................................................................................................................................................. 1.0–4.5 45 1.0–4.5
37.5 .............................................................................................................................................. 1.0–4.5 75 1.0–5.0
50 ................................................................................................................................................. 1.5–4.5 112.5 1.2–6.0
75 ................................................................................................................................................. 1.5–4.5 150 1.2–6.0
100 ............................................................................................................................................... 1.5–4.5 225 1.2–6.0
167 ............................................................................................................................................... 1.5–4.5 300 1.2–6.0
250 ............................................................................................................................................... 1.5–6.0 500 1.5–7.0
333 ............................................................................................................................................... 1.5–6.0 750 5.0–7.5
500 ............................................................................................................................................... 1.5–7.0 1000 5.0–7.5
667 ............................................................................................................................................... 5.0–7.5 1500 5.0–7.5
833 ............................................................................................................................................... 5.0–7.5 2000 5.0–7.5
2500 5.0–7.5

TABLE 2.—NORMAL IMPEDANCE RANGES FOR DRY-TYPE TRANSFORMERS


Single-phase transformers Three-phase transformers

Impedance Impedance
kVA kVA
(%) (%)

15 ................................................................................................................................................. 1.5–6.0 15 1.5–6.0


25 ................................................................................................................................................. 1.5–6.0 30 1.5–6.0
37.5 .............................................................................................................................................. 1.5–6.0 45 1.5–6.0
50 ................................................................................................................................................. 1.5–6.0 75 1.5–6.0
75 ................................................................................................................................................. 2.0–7.0 112.5 1.5–6.0
100 ............................................................................................................................................... 2.0–7.0 150 1.5–6.0
167 ............................................................................................................................................... 2.5–8.0 225 3.0–7.0
250 ............................................................................................................................................... 3.5–8.0 300 3.0–7.0
333 ............................................................................................................................................... 3.5–8.0 500 4.5–8.0
rmajette on PROD1PC67 with RULES3

500 ............................................................................................................................................... 3.5–8.0 750 5.0–8.0


667 ............................................................................................................................................... 5.0–8.0 1000 5.0–8.0
833 ............................................................................................................................................... 5.0–8.0 1500 5.0–8.0
2000 5.0–8.0
2500 5.0–8.0

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00026 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 24997

Temperature correction means the Total loss means the sum of the no- sinusoidal, to a value(s) that would have
mathematical correction(s) of load loss and the load loss for a been obtained with a sinusoidal voltage.
measurement data, obtained when a transformer. Welding transformer means a
transformer is tested at a temperature * * * * * transformer designed for use in arc
that is different from the reference welding equipment or resistance
Transformer with tap range of 20 welding equipment.
temperature, to the value(s) that would percent or more means a transformer
have been obtained if the transformer ■ 4. Section 431.193 is added to subpart
with multiple voltage taps, the highest
had been tested at the reference of which equals at least 20 percent more K, under the heading ‘‘Test Procedures,’’
temperature. than the lowest, computed based on the to read as follows:
Test current means the current of the sum of the deviations of the voltages of Test Procedures
electrical power supplied to the these taps from the transformer’s
nominal voltage. § 431.193 Test procedures for measuring
transformer under test.
energy consumption of distribution
Test frequency means the frequency of Uninterruptible power supply transformers.
the electrical power supplied to the transformer means a transformer that The test procedures for measuring the
transformer under test. supplies power to an uninterruptible energy efficiency of distribution
power system, which in turn supplies transformers for purposes of EPCA are
Test voltage means the voltage of the power to loads that are sensitive to
electrical power supplied to the specified in Appendix A to this subpart.
power failure, power sags, over voltage,
transformer under test. ■ 5. Section 431.196 is amended in
switching transients, line noise, and
Testing transformer means a other power quality factors. paragraph (a) by revising the table to
transformer used in a circuit to produce read as follows:
Waveform correction means the
a specific voltage or current for the adjustment(s) (mathematical § 431.196 Energy conservation standards
purpose of testing electrical equipment. correction(s)) of measurement data and their effective dates.
obtained with a test voltage that is non- (a) * * *

Single phase Three phase

Efficiency Efficiency
kVA kVA
(%) 1 (%) 1

15 ................................................................................................................................................. 97.7 15 97.0


25 ................................................................................................................................................. 98.0 30 97.5
37.5 .............................................................................................................................................. 98.2 45 97.7
50 ................................................................................................................................................. 98.3 75 98.0
75 ................................................................................................................................................. 98.5 112.5 98.2
100 ............................................................................................................................................... 98.6 150 98.3
167 ............................................................................................................................................... 98.7 225 98.5
250 ............................................................................................................................................... 98.8 300 98.6
333 ............................................................................................................................................... 98.9 500 98.7
750 98.8
1000 98.9
1 Efficiencies are determined at the following reference conditions: (1) for no-load losses, at the temperature of 20 °C, and (2) for load-losses,
at the temperature of 75 °C and 35 percent of nameplate load.
(Source: Table 4–2 of National Electrical Manufacturers Association (NEMA) Standard TP–1–2002, ‘‘Guide for Determining Energy Efficiency
for Distribution Transformers.’’)

* * * * * manufacturer must determine the model’s efficiency either at the voltage


■ 6. Sections 431.197 through 431.198 efficiency of each basic model of at which the highest losses occur or at
are added to subpart K, under the distribution transformer either by each voltage at which the transformer is
heading ‘‘Compliance and testing, in accordance with § 431.193 of rated to operate.
Enforcement,’’ to read as follows: this part and paragraphs (b)(2) and (b)(3) (2) Alternative efficiency
of this section, or by application of an determination method. A manufacturer
Compliance and Enforcement alternative efficiency determination may apply an AEDM to a basic model
§ 431.197 Manufacturer’s determination of method (AEDM) that meets the pursuant to paragraph (a)(1) of this
efficiency for distribution transformers. requirements of paragraphs (a)(2) and section only if:
When a manufacturer or other party (a)(3) of this section; provided, however, (i) The AEDM has been derived from
(both of which this section refers to as that a manufacturer may use an AEDM a mathematical model that represents
a ‘‘manufacturer’’) determines the to determine the efficiency of one or the electrical characteristics of that basic
efficiency of a distribution transformer more of its untested basic models only model;
in order to comply with an obligation if it determines the efficiency of at least (ii) The AEDM is based on
imposed on it by or pursuant to Part C five of its other basic models (selected engineering and statistical analysis,
of Title III of EPCA, 42 U.S.C. 6311– in accordance with paragraph (b)(1) of computer simulation or modeling, or
6317, this section applies. This section this section) through actual testing. For other analytic evaluation of performance
rmajette on PROD1PC67 with RULES3

does not apply to enforcement testing each basic model of distribution data; and
conducted pursuant to § 431.198 of this transformer that has a configuration of (iii) The manufacturer has
part. windings which allows for more than substantiated the AEDM, in accordance
(a) Methods used to determine one nominal rated voltage, the with paragraph (a)(3) of this section, by
efficiency—(1) General requirements. A manufacturer must determine the basic applying it to, and testing, at least five

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00027 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
24998 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

other basic models of the same type, i.e., models selected by the Department, or 100
low-voltage dry-type distribution a combination of the foregoing. X≥
transformers, medium-voltage dry-type  0.08   100 
(b) Additional testing requirements— 1 + 1 +  − 1
distribution transformers, or liquid- (1) Selection of basic models for testing  n   RE 
immersed distribution transformers. if an AEDM is to be applied. (i) A
(3) Substantiation of an alternative manufacturer must select basic models where RE is the represented efficiency.
efficiency determination method. Before for testing in accordance with the § 431.198 Enforcement testing for
using an AEDM, the manufacturer must following criteria: distribution transformers.
substantiate the AEDM’s accuracy and
(A) Two of the basic models must be (a) Test notice. Upon receiving
reliability as follows:
(i) Apply the AEDM to at least five of among the five basic models with the information in writing, concerning the
the manufacturer’s basic models that highest unit volumes of production by energy performance of a particular
have been selected for testing in the manufacturer in the prior year, or distribution transformer sold by a
accordance with paragraph (b)(1) of this during the prior 12-calendar-month particular manufacturer or private
section, and calculate the power loss for period beginning in 2003,1 whichever is labeler, which indicates that the
each of these basic models; later; transformer may not be in compliance
(ii) Test at least five units of each of (B) No two basic models should have with the applicable energy efficiency
these basic models in accordance with the same combination of power and standard, or upon undertaking to
the applicable test procedure and voltage ratings; and ascertain the accuracy of the efficiency
paragraph (b)(2) of this section, and (C) At least one basic model should be rating on the nameplate or in marketing
determine the power loss for each of single-phase and at least one should be materials for a distribution transformer,
these basic models; three-phase. disclosed pursuant to this part, the
(iii) The predicted total power loss for Department may conduct testing of that
(ii) In any instance where it is
each of these basic models, calculated equipment under this subpart by means
impossible for a manufacturer to select
by applying the AEDM pursuant to of a test notice addressed to the
basic models for testing in accordance
paragraph (a)(3)(i) of this section, must manufacturer in accordance with the
with all of these criteria, the criteria
be within plus or minus five percent of following requirements:
shall be given priority in the order in
the mean total power loss determined (1) The test notice procedure will only
which they are listed. Within the limits
from the testing of that basic model be followed after the Department has
imposed by the criteria, basic models
pursuant to paragraph (a)(3)(ii) of this examined the underlying test data (or,
shall be selected randomly.
section; and where appropriate, data as to use of an
(iv) Calculate for each of these basic (2) Selection of units for testing within AEDM) provided by the manufacturer
models the percentage that its power a basic model. For each basic model a and after the manufacturer has been
loss calculated pursuant to paragraph manufacturer selects for testing, it shall offered the opportunity to meet with the
(a)(3)(i) is of its power loss determined select and test units as follows: Department to verify, as applicable,
from testing pursuant to paragraph (i) If the manufacturer would produce compliance with the applicable
(a)(3)(ii), compute the average of these five or fewer units of a basic model over efficiency standard, or the accuracy of
percentages, and that calculated average a reasonable period of time labeling information, or both. In
power loss, expressed as a percentage of (approximately 180 days), then it must addition, where compliance of a basic
the average power loss determined from test each unit. However, a manufacturer model was certified based on an AEDM,
testing, must be no less than 97 percent may not use a basic model with a the Department shall have the discretion
and no greater than 103 percent. sample size of fewer than five units to to pursue the provisions of
(4) Subsequent verification of an substantiate an AEDM pursuant to § 431.197(a)(4)(ii) prior to invoking the
AEDM. (i) Each manufacturer that has paragraph (a)(3) of this section. test notice procedure. The Department
used an AEDM under this section shall (ii) If the manufacturer produces more shall be permitted to observe any
have available for inspection by the than five units over such period of time, reverification procedures undertaken
Department of Energy records showing: it must either test all such units or select pursuant to this subpart, and to inspect
The method or methods used; the a sample of at least five units at random the results of such reverification.
mathematical model, the engineering or and test them. Any such sample shall be (2) The Department will mail or
statistical analysis, computer simulation comprised of production units of the deliver the test notice to the plant
or modeling, and other analytic basic model, or units that are manager or other responsible official, as
evaluation of performance data on representative of such production units. designated by the manufacturer.
which the AEDM is based; complete test (3) Applying results of testing. In a test (3) The test notice will specify the
data, product information, and related of compliance with a represented basic model(s) to be selected for testing,
information that the manufacturer has efficiency, the average efficiency of the the method of selecting the test sample,
generated or acquired pursuant to sample, X̄, which is defined by the date and time at which testing shall
paragraph (a)(3) of this section; and the be initiated, the date by which testing is
calculations used to determine the 1 n scheduled to be completed and the
efficiency and total power losses of each
basic model to which the AEDM was
X= ∑ Xi
n i =1
facility at which testing will be
conducted. The test notice may also
applied. provide for situations in which a
(ii) If requested by the Department, where Xi is the measured efficiency of specified basic model is unavailable for
the manufacturer shall conduct unit i and n is the number of units testing, and may include alternative
tested, must satisfy the condition:
ER27AP06.001</MATH>

simulations to predict the performance basic models. The specified basic model
rmajette on PROD1PC67 with RULES3

of particular basic models of may be one either that the manufacturer


1 When identifying these five basic models, any
distribution transformers specified by has rated by actual testing or that it has
basic model that does not comply with Federal
the Department, analyses of previous energy conservation standards for distribution rated by the use of an AEDM.
simulations conducted by the transformers that may be in effect shall be excluded (4) The Department may require in the
ER27AP06.000</MATH>

manufacturer, sample testing of basic from consideration. test notice that the manufacturer shall

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00028 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 24999

ship at its expense a reasonable number applicable energy efficiency standard, Department conduct additional testing
of units of each basic model specified in shall be based on the testing conducted of the basic model according to
such test notice to a testing laboratory in accordance with the statistical procedures set forth in Appendix B of
designated by the Department. The sampling procedures set forth in this subpart and the test procedures
number of units of each basic model Appendix B of this subpart and the test specified for distribution transformers.
specified in a test notice shall not procedures specified for distribution (2) All units tested under this
exceed twenty (20). transformers. paragraph (f) shall be selected and
(5) Except as required or provided in (d) Test unit selection. The tested in accordance with the provisions
paragraphs (a)(6) or (a)(7) of this section, Department shall select a batch, a batch given in paragraphs (a)(9), (b), (d) and
initially the Department will test five sample, and test units from the batch (e) of this section.
units. sample in accordance with the (3) The manufacturer shall bear the
(6) Except as provided in paragraph following provisions of this paragraph cost of all testing conducted under this
(a)(7) of this section, if fewer than five and the conditions specified in the test paragraph (f).
units of a basic model are available for notice. (4) The manufacturer shall cease
testing when the manufacturer receives (1) The batch may be subdivided by distribution of the basic model tested
the test notice, then the Department utilizing criteria under the provisions of this paragraph
(i) DOE will test the available unit(s); specified in the test notice. from the time the manufacturer elects to
or (2) The Department will then exercise the option provided in this
(ii) If one or more other units of the randomly select a batch sample of up to paragraph until the basic model is
basic model are expected to become 20 units from one or more subdivided determined to be in compliance. The
available within six months, DOE may groups within the batch. The Department may seek civil penalties for
instead, at its discretion, test either: manufacturer shall keep on hand all all units distributed during such period.
(A) The available unit(s) and one or units in the batch sample until such (5) If the additional testing results in
more of the other units that time as the basic model is determined a determination of compliance, a notice
subsequently become available (up to a to be in compliance or non-compliance. of allowance to resume distribution
maximum of twenty); or (3) The Department will randomly shall be issued by the Department.
(B) Up to twenty of the other units select individual test units comprising ■ 7. Appendices A and B are added to
that subsequently become available. the test sample from the batch sample. subpart K, to read as follows:
(7) Notwithstanding paragraphs (a)(5) (4) All random selection shall be
and (a)(6) of this section, if testing of the achieved by sequentially numbering all Appendix A to Subpart K of Part 431—
available or subsequently available units of the units in a batch sample and then Uniform Test Method for Measuring the
of a basic model would be impractical, using a table of random numbers to Energy Consumption of Distribution
as for example where a basic model is select the units to be tested. Transformers
very large, has unusual testing (e) Test unit preparation. (1) Prior to 1.0 Definitions.
requirements, or has limited production, and during the testing, a test unit The definitions contained in §§ 431.2 and
the Department may in its discretion selected in accordance with paragraph 431.192 are applicable to this Appendix A.
decide to base the determination of (d) of this section shall not be prepared,
modified, or adjusted in any manner 2.0 Accuracy Requirements.
compliance on the testing of fewer than
the available number of units, if the unless such preparation, modification, (a) Equipment and methods for loss
or adjustment is allowed by the measurement shall be sufficiently accurate
manufacturer so requests and
applicable Department of Energy test that measurement error will be limited to the
demonstrates that the criteria of this values shown in Table 2.1.
paragraph are met. procedure.
(8) When testing units under (2) No quality control, testing, or
assembly procedures shall be performed
TABLE 2.1.—TEST SYSTEM ACCURACY
paragraphs (a)(5), (a)(6), or (a)(7) of this
on a test unit, or any parts and sub- REQUIREMENTS FOR EACH MEAS-
section, DOE shall perform the
assemblies thereof, that is not performed URED QUANTITY
following number of tests:
(i) If DOE tests four or more units, it during the production and assembly of
all other units included in the basic Test system
will test each unit once; Measured quantity accuracy
(ii) If DOE tests two or three units, it model.
will test each unit twice; or (3) A test unit shall be considered Power Losses ........... ± 3.0%
(iii) If DOE tests one unit, it will test defective if such unit is inoperative or Voltage ...................... ± 0.5%
that unit four times. is found to be in noncompliance due to Current ...................... ± 0.5%
(9) Within five working days of the failure of the unit to operate according Resistance ................ ± 0.5%
time the units are selected, the to the manufacturer’s design and Temperature .............. ± 1.0 °C
manufacturer shall ship the specified operating instructions. Defective units,
test units of the basic model to the including those damaged due to (b) Only instrument transformers meeting
the 0.3 metering accuracy class, or better,
testing laboratory. shipping or handling, shall be reported may be used under this test method.
(b) Testing laboratory. Whenever the immediately to the Department. The
Department conducts enforcement Department shall authorize testing of an 3.0 Resistance Measurements
testing at a designated laboratory in additional unit on a case-by-case basis. 3.1 General Considerations
accordance with a test notice under this (f) Testing at manufacturer’s option. (a) Measure or establish the winding
section, the resulting test data shall (1) If a manufacturer’s basic model is temperature at the time of the winding
constitute official test data for that basic determined to be in noncompliance resistance measurement.
with the applicable energy performance (b) Measure the direct current resistance
model. Such test data will be used by
rmajette on PROD1PC67 with RULES3

(Rdc) of transformer windings by one of the


the Department to make a determination standard at the conclusion of methods outlined in section 3.3. The
of compliance or noncompliance. Department testing in accordance with methods of section 3.5 must be used to
(c) Sampling. The determination that the sampling plan specified in correct load losses to the applicable reference
a manufacturer’s basic model complies Appendix B of this subpart, the temperature from the temperature at which
with its labeled efficiency, or the manufacturer may request that the they are measured. Observe precautions

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00029 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
25000 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

while taking measurements, such as those in (a) The windings have been under (4) Neither voltage nor current has been
section 3.4, in order to maintain insulating liquid with no excitation and no applied to the unit under test for 24 hours.
measurement uncertainty limits specified in current in the windings for four hours before In addition, increase this initial 24 hour
Table 2.1. the dc resistance is measured; or period by any added amount of time
3.2 Temperature Determination of (b) The temperature of the insulating liquid necessary for the temperature of the
Windings and Pre-conditions for Resistance has stabilized, and the difference between the
Measurement. transformer windings to stabilize at the level
top and bottom temperature does not exceed
Make temperature measurements in 5 °C. of the ambient temperature. However, this
protected areas where the air temperature is 3.2.2 Dry-Type Distribution Transformers. additional amount of time need not exceed
stable and there are no drafts. Determine the Record the winding temperature (Tdc) of 24 hours.
winding temperature (Tdc) for liquid- dry-type transformers as either of the 3.3 Resistance Measurement Methods.
immersed and dry-type distribution following: Make resistance measurements using either
transformers by the methods described in (a) For ventilated dry-type units, use the the resistance bridge method, the voltmeter-
sections 3.2.1 and 3.2.2, respectively. average of readings of four or more ammeter method or a resistance meter. In
3.2.1 Liquid-Immersed Distribution thermometers, thermocouples, or other each instance when this Uniform Test
Transformers. suitable temperature sensors inserted within Method is used to test more than one unit of
3.2.1.1 Methods the coils. Place the sensing points of the
a basic model to determine the efficiency of
measuring devices as close as possible to the
Record the winding temperature (Tdc) of that basic model, the resistance of the units
winding conductors. For sealed units, such
liquid-immersed transformers as the average being tested may be determined from making
as epoxy-coated or epoxy-encapsulated units,
of either of the following: resistance measurements on only one of the
use the average of four or more temperature
(a) The measurements from two
sensors located on the enclosure and/or units.
temperature sensing devices (for example,
thermocouples) applied to the outside of the cover, as close to different parts of the 3.3.1 Resistance Bridge Methods.
transformer tank and thermally insulated winding assemblies as possible; or If the resistance bridge method is selected,
from the surrounding environment, with one (b) For both ventilated and sealed units, use either the Wheatstone or Kelvin bridge
located at the level of the oil and the other use the ambient temperature of the test area, circuit (or the equivalent of either).
located near the tank bottom or at the lower under the following conditions:
(1) All internal temperatures measured by 3.3.1.1 Wheatstone Bridge
radiator header if applicable; or
(b) The measurements from two the internal temperature sensors must not (a) This bridge is best suited for measuring
temperature sensing devices immersed in the differ from the test area ambient temperature resistances larger than ten ohms. A schematic
transformer liquid, with one located directly by more than 2 °C. diagram of a Wheatstone bridge with a
above the winding and other located directly (2) Enclosure surface temperatures for
representative transformer under test is
below the winding. sealed units must not differ from the test area
ambient temperature by more than 2 °C. shown in Figure 3.1.
3.2.1.2 Conditions (3) Test area ambient temperature should
Make this determination under either of not have changed by more than 3 °C for 3
the following conditions: hours before the test.

Where: have a provision for resistance Vdc is a source of dc voltage for supplying the
Rdc is the resistance of the transformer adjustment, power to the Wheatstone Bridge.
winding being measured, Rt is a resistor for reducing the time constant (b) In the measurement process, turn on the
of the circuit,
rmajette on PROD1PC67 with RULES3

Rs is a standard resistor having the resistance source (Vdc), and adjust the resistance ratio
Rs, D is a null detector, which may be either a (Ra/Rb) to produce zero signal at the detector
Ra, Rb are two precision resistors with micro ammeter or microvoltmeter or (D). Determine the winding resistance by
resistance values Ra and Rb , equivalent instrument for observing that using equation 3–1 as follows:
respectively; at least one resistor must no signal is present when the bridge is
ER27AP06.002</GPH>

balanced, and

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00030 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 25001

R dc = R s ( R a /R b ) ( 3-1) 3.3.1.2 Kelvin Bridge for measuring resistances of ten ohms and
(a) This bridge separates the resistance of smaller. A schematic diagram of a Kelvin
the connecting conductors to the transformer bridge with a representative transformer
winding being measured from the resistance under test is shown in Figure 3.2.
of the winding, and therefore is best suited

(b) The Kelvin Bridge has seven of the Determine the winding resistance by using to the transformer terminals and the standard
same type of components as in the equation 3–2 as follows: resistor, thus eliminating voltage drops from
Wheatstone Bridge. It has two more resistors the measurement in the current-carrying
than the Wheatstone bridge, Ra1 and Rb1. At R dc = R s ( R a /R b ) ( 3-2 ) , leads as represented by Rd.
least one of these resistors must have 3.3.2 Voltmeter-Ammeter Method.
adjustable resistance. In the measurement as with the Wheatstone bridge, with an (a) Employ the voltmeter-ammeter method
process, the source is turned on, two additional condition that: only if the rated current of the winding is
resistance ratios (Ra/Rb) and (Ra1/Rb1) are greater than one ampere and the test current
adjusted to be equal, and then the two ratios ( R a /R b ) = ( R a1/R b1 ) ( 3-3) is limited to 15 percent of the winding
are adjusted together to balance the bridge current. Connect the transformer winding
(c) The Kelvin bridge provides two sets of
producing zero signal at the detector. under test to the circuit shown in Figure 3.3.
leads, current-carrying and voltage-sensing,

ER27AP06.007</GPH>
ER27AP06.006</MATH>
ER27AP06.004</GPH> ER27AP06.005</MATH>
rmajette on PROD1PC67 with RULES3

Where: A is an ammeter or a voltmeter-shunt V is a voltmeter with sensitivity in the


combination for measuring the current millivolt range for measuring the voltage
ER27AP06.003</MATH>

(Imdc) in the transformer winding,

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00031 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
25002 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

(Vmdc) applied to the transformer (b) The accurate reading of resistance Rdc measured quantities will need correction for
winding, may be facilitated by shortening the time instrumentation losses and may need
Rdc is the resistance of the transformer constant. This is done by introducing a corrections for known phase angle errors in
winding being measured, resistor Rt in series with the winding under measuring equipment and for the waveform
Rt is a resistor for reducing the time constant test in both the bridge and voltmeter- distortion in the test voltage. Any power loss
of the circuit, and ammeter circuits as shown in Figures 3.1 to not measured at the applicable reference
Vdc is a source of dc voltage for supplying 3.3. The relationship for the time constant is: temperature must be adjusted to that
power to the measuring circuit. reference temperature. The measured load
(b) To perform the measurement, turn on Tc = ( L tc /R tc ) ( 3-5) loss must also be adjusted to a specified
the source to produce current no larger than output loading level if not measured at the
15 percent of the rated current for the Where: specified output loading level. Test
winding. Wait until the current and voltage Tc is the time constant in seconds, distribution transformers designed for
readings have stabilized and then take Ltc is the total magnetizing and leakage harmonic currents using a sinusoidal
simultaneous readings of voltage and current. inductance of the winding under test, in waveform (k=1).
Determine the winding resistance Rdc by henries, and 4.2 Measurement of Power Losses.
using equation 3–4 as follows: Rtc is the total resistance in ohms, consisting 4.2.1 No-Load Loss.
of Rt in series with the winding Measure the no-load loss and apply
R dc = ( Vmdc /I mdc ) ( 3-4 ) resistance Rdc and the resistance Rs of the corrections as described in section 4.4, using
standard resistor in the bridge circuit. the appropriate test set as described in
Where: (c) Because Rtc is in the denominator of the section 4.3.
Vmdc is the voltage measured by the voltmeter expression for the time constant, increasing 4.2.2 Load Loss.
V, and the resistance Rtc will decrease the time Measure the load loss and apply
Imdc is the current measured by the ammeter constant. If the time constant in a given test corrections as described in section 4.5, using
A. circuit is too long for the resistance readings the appropriate test set as described in
(c) As shown in Figure 3.3, separate to be stable, then a higher resistance can be section 4.3.
current and voltage leads must be brought to substituted for the existing Rtc, and 4.3 Test Sets.
the transformer terminals. (This eliminates successive replacements can be made until (a) The same test set may be used for both
the errors due to lead and contact resistance.) adequate stability is reached. the no-load loss and load loss measurements
3.3.3 Resistance Meters. 3.5 Conversion of Resistance provided the range of the test set
Resistance meters may be based on Measurements. encompasses the test requirements of both
voltmeter-ammeter, or resistance bridge, or (a) Resistance measurements must be tests. Calibrate the test set to national
some other operating principle. Any meter corrected, from the temperature at which the standards to meet the tolerances in Table 2.1
used to measure a transformer’s winding winding resistance measurements were in section 2.0. In addition, the wattmeter,
resistance must have specifications for made, to the reference temperature. As current measuring system and voltage
resistance range, current range, and ability to specified in these test procedures, the measuring system must be calibrated
measure highly inductive resistors that cover reference temperature for liquid-immersed separately if the overall test set calibration is
the characteristics of the transformer being transformers loaded at 50 percent of the rated outside the tolerance as specified in section
tested. Also the meter’s specifications for load is 55 °C. For medium-voltage, dry-type 2.0 or the individual phase angle error
accuracy must meet the applicable criteria of transformers loaded at 50 percent of the rated exceeds the values specified in section 4.5.3.
Table 2.1 in section 2.0. load, and for low-voltage, dry-type (b) A test set based on the wattmeter-
3.4 Precautions in Measuring Winding transformers loaded at 35 percent of the rated voltmeter-ammeter principle may be used to
Resistance. load, the reference temperature is 75 °C. measure the power loss and the applied
3.4.1 Required actions. (b) Correct the measured resistance to the voltage and current of a transformer where
The following guidelines must be observed resistance at the reference temperature using the transformer’s test current and voltage are
when making resistance measurements: equation 3–6 as follows: within the measurement capability of the
(a) Use separate current and voltage leads measuring instruments. Current and voltage
when measuring small (< 10 ohms) R ts = R dc ( Ts + Tk ) / ( Tdc + Tk )  ( 3-6 ) transformers, known collectively as
resistance. instrument transformers, or other scaling
(b) Use null detectors in bridge circuits, Where: devices such as resistive or capacitive
and measuring instruments in voltmeter- Rts is the resistance at the reference dividers for voltage, may be used in the
ammeter circuits, that have sensitivity and temperature, Ts, above circumstance, and must be used
resolution sufficient to enable observation of Rdc is the measured resistance at temperature, together with instruments to measure
at least 0.1 percent change in the measured Tdc, current, voltage, or power where the current
resistance. Ts is the reference temperature in °C, or voltage of the transformer under test
(c) Maintain the dc test current at or below Tdc is the temperature at which resistance exceeds the measurement capability of such
15 percent of the rated winding current. was measured in °C, and instruments. Thus, a test set may include a
(d) Inclusion of a stabilizing resistor Rt (see Tk is 234.5 °C for copper or 225 °C for combination of measuring instruments and
section 3.4.2) will require higher source aluminum. instrument transformers (or other scaling
voltage. devices), so long as the current or voltage of
(e) Disconnect the null detector (if a bridge 4.0 Loss Measurement the transformer under test does not exceed
circuit is used) and voltmeter from the circuit 4.1 General Considerations. the measurement capability of any of the
before the current is switched off, and switch The efficiency of a transformer is instruments.
off current by a suitable insulated switch. computed from the total transformer losses, 4.3.1 Single-Phase Test Sets.
3.4.2 Guideline for Time Constant. which are determined from the measured Use these for testing single-phase
(a) The following guideline is suggested for value of the no-load loss and load loss power distribution transformers.
ER27AP06.010</GPH>

the tester as a means to facilitate the components. Each of these two power loss 4.3.1.1 Without Instrument Transformers.
measurement of resistance in accordance components is measured separately using test (a) A single-phase test set without an
with the accuracy requirements of section sets that are identical, except that shorting instrument transformer is shown in Figure
2.0: straps are added for the load-loss test. The 4.1.
ER27AP06.009</GPH>
rmajette on PROD1PC67 with RULES3

ER27AP06.008</GPH>

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00032 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 25003

Where: A is an rms ammeter used to measure test measurements the primary winding is
W is a wattmeter used to measure Pnm and current, especially Ilm, the load loss connected to the test set. Use the average-
Plm, the no-load and load loss power, current, and sensing voltmeter, Vav, only in no-load loss
respectively, (SC) is a conductor for providing a short- measurements.
Vrms is a true root-mean-square (rms) circuit across the output windings for the
4.3.1.2 With Instrument Transformers.
voltmeter used to measure Vr(nm) and Vlm, load loss measurements.
A single-phase test set with instrument
the rms test voltages in no-load and load (b) Either the primary or the secondary
transformers is shown in Figure 4.2. This
loss measurements, respectively, winding can be connected to the test set.
Vav is an average sensing voltmeter, However, more compatible voltage and circuit has the same four measuring
calibrated to indicate rms voltage for current levels for the measuring instruments instruments as that in Figure 4.1. The current
sinusoidal waveforms and used to are available if for no-load loss measurements and voltage transformers, designated as (CT)
measure Va(nm), the average voltage in no- the secondary (low voltage) winding is and (VT), respectively, are added.
load loss measurements, connected to the test set, and for load loss

4.3.2 Three-Phase Test Sets. (a) A three-phase test set without devices as shown. As an alternative, the
Use these for testing three-phase instrument transformers is shown in Figure entire instrumentation system of a three-
distribution transformers. Use in a four-wire, 4.3. This test set is essentially the same phase test set without transformers may
three-wattmeter test circuit. circuit shown in Figure 4.1 repeated three consist of a multi-function analyzer.
4.3.2.1 Without Instrument Transformers. times, and the instruments are individual
ER27AP06.012</GPH>
rmajette on PROD1PC67 with RULES3

ER27AP06.011</GPH>

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00033 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
25004 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

(b) Either group of windings, the primary Therefore a provision must be made to must be made to switch the voltmeters for
or the secondary, can be connected in wye switch the voltmeters for line-to-neutral line-to-neutral and line-to-line measurements
or delta configuration. If both groups of measurements for wye-connected windings as in section 4.3.2.1. The voltage sensors
windings are connected in the wye and for line-to-line measurements for delta- (‘‘coils’’) of the wattmeters must always be
configuration for the no-load test, the neutral connected windings. connected in the line-to-neutral
of the winding connected to the test set must 4.3.2.2 With Instrument Transformers.
be connected to the neutral of the source to A three-phase test set with instrument configuration.
provide a return path for the neutral current. transformers is shown in Figure 4.4. This test
(c) In the no-load loss measurement, the set is essentially the same circuit shown in
voltage on the winding must be measured. Figure 4.2 repeated three times. Provision

ER27AP06.014</GPH>
rmajette on PROD1PC67 with RULES3

ER27AP06.013</GPH>

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00034 Fmt 4701 Sfmt 4725 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 25005

4.3.2.3 Test Set Neutrals. 4.4.3.2 Correction for Non-Sinusoidal 4.5 Load Losses: Measurement and
If the power source in the test circuit is Applied Voltage. Calculations.
wye-connected, ground the neutral. If the (a) The measured value of no-load loss 4.5.1 General Considerations.
power source in the test circuit is delta- must be corrected to a sinusoidal voltage, (a) The load losses of a transformer are
connected, use a grounding transformer to except when waveform distortion in the test those losses incident to a specified load
obtain neutral and ground for the test. voltage causes the magnitude of the carried by the transformer. Load losses
4.4 No-Load Losses: Measurement and correction to be less than 1 percent. In such consist of ohmic loss in the windings due to
Calculations. a case, no correction is required. the load current and stray losses due to the
4.4.1 General Considerations. (b) To make a correction where the eddy currents induced by the leakage flux in
Measurement corrections are permitted but distortion requires a correction of 5 percent the windings, core clamps, magnetic shields,
not required for instrumentation losses and or less, use equation 4–1. If the distortion tank walls, and other conducting parts. The
for losses from auxiliary devices. requires a correction to be greater than 5 ohmic loss of a transformer varies directly
Measurement corrections are required: percent, improve the test voltage and re-test. with temperature, whereas the stray losses
(a) When the waveform of the applied Repeat until the distortion requires a vary inversely with temperature.
voltage is non-sinusoidal; and correction of 5 percent or less. (b) For a transformer with a tap changer,
(b) When the core temperature or liquid (c) Determine the no-load losses of the conduct the test at the rated current and
temperature is outside the 20 °C ± 10 °C transformer corrected for sine-wave basis rated-voltage tap position. For a transformer
range. from the measured value by using equation that has a configuration of windings which
4.4.2 No-Load Loss Test. 4–1 as follows: allows for more than one nominal rated
(a) The purpose of the no-load loss test is voltage, determine its load losses either in
to measure no-load losses at a specified Pnm the winding configuration in which the
excitation voltage and a specified frequency. Pncl = ( 4-1) highest losses occur or in each winding
The no-load loss determination must be P1 + kP2 configuration in which the transformer can
based on a sine-wave voltage corrected to the operate.
reference temperature. Connect either of the Where:
4.5.2 Tests for Measuring Load Losses.
transformer windings, primary or secondary, Pncl is the no-load loss corrected to a sine- (a) Connect the transformer with either the
to the appropriate test set of Figures 4.1 to wave basis at the temperature (Tnm) at high-voltage or low-voltage windings to the
4.4, giving consideration to section which no-load loss is measured,
appropriate test set. Then short-circuit the
4.4.2(a)(2). Leave the unconnected winding(s) Pnm is the measured no-load loss at
winding that was not connected to the test
open circuited. Apply the rated voltage at temperature Tnm,
set. Apply a voltage at the rated frequency (of
rated frequency, as measured by the average- P1 is the per unit hysteresis loss,
the transformer under test) to the connected
sensing voltmeter, to the transformer. Take P2 is the per unit eddy-current loss,
windings to produce the rated current in the
the readings of the wattmeter(s) and the P1 + P2 = 1,
transformer. Take the readings of the
average-sensing and true rms voltmeters.
wattmeter(s), the ammeters(s), and rms
Observe the following precautions: 2
(1) Voltmeter connections. When  Vr ( nm )  voltmeter(s).
correcting to a sine-wave basis using the k=  , (b) Regardless of the test set selected, the
 Va ( nm )  following preparatory requirements must be
average-voltmeter method, the voltmeter   satisfied for accurate test results:
connections must be such that the waveform
applied to the voltmeters is the same as the Vr(nm) is the test voltage measured by rms (1) Determine the temperature of the
waveform across the energized windings. voltmeter, and windings using the applicable method in
(2) Energized windings. Energize either the Va(nm) is the test voltage measured by average- section 3.2.1 or section 3.2.2.
high voltage or the low voltage winding of voltage voltmeter. (2) The conductors used to short-circuit the
the transformer under test. (d) The two loss components (P1 and P2) windings must have a cross-sectional area
(3) Voltage and frequency. The no-load loss are assumed equal in value, each assigned a equal to, or greater than, the corresponding
test must be conducted with rated voltage value of 0.5 per unit, unless the actual transformer leads, or, if the tester uses a
impressed across the transformer terminals measurement-based values of hysteresis and different method to short-circuit the
using a voltage source at a frequency equal eddy-current losses are available (in per unit windings, the losses in the short-circuiting
to the rated frequency of the transformer form), in which case the actual conductor assembly must be less than 10
under test. measurements apply. percent of the transformer’s load losses.
(b) Adjust the voltage to the specified value 4.4.3.3 Correction of No-Load Loss to (3) When the tester uses a power supply
as indicated by the average-sensing Reference Temperature. that is not synchronized with an electric
voltmeter. Record the values of rms voltage, After correcting the measured no-load loss utility grid, such as a dc/ac motor-generator
rms current, electrical power, and average for waveform distortion, correct the loss to set, follow the provisions of the ‘‘Note’’ in
voltage as close to simultaneously as the reference temperature of 20 °C. If the no- section 4.4.2.
possible. For a three-phase transformer, take load loss measurements were made between 4.5.3 Corrections.
all of the readings on one phase before 10 °C and 30 °C, this correction is not 4.5.3.1 Correction for Losses from
proceeding to the next, and record the required. If the correction to reference Instrumentation and Auxiliary Devices.
average of the three rms voltmeter readings temperature is applied, then the core 4.5.3.1.1 Instrumentation Losses.
as the rms voltage value. temperature of the transformer during no- Measured losses attributable to the
Note: When the tester uses a power supply load loss measurement (Tnm) must be voltmeters, wattmeter voltage circuit and
that is not synchronized with an electric determined within ± 10 °C of the true average short-circuiting conductor (SC), and to the
utility grid, such as a dc/ac motor-generator core temperature. Correct the no-load loss to voltage transformers if they are used, may be
set, check the frequency and maintain it the reference temperature by using equation deducted from the total load losses measured
within ±0.5 percent of the rated frequency of 4–2 as follows: during testing.
ER27AP06.017</MATH>

the transformer under test. A power source 4.5.3.1.2 Losses from Auxiliary Devices.
that is directly connected to, or synchronized Pnc = Pncl 1 + 0.00065 ( Tnm − Tnr )  ( 4-2 ) Measured losses attributable to auxiliary
with, an electric utility grid need not be devices (e.g., circuit breakers, fuses,
monitored for frequency. Where: switches) installed in the transformer, if any,
4.4.3 Corrections. Pnc is the no-load losses corrected for that are not part of the winding and core
4.4.3.1 Correction for Instrumentation waveform distortion and then to the assembly, may be excluded from load losses
ER27AP06.016</MATH>
rmajette on PROD1PC67 with RULES3

Losses. reference temperature of 20 °C, measured during testing. To exclude these


Measured losses attributable to the Pnc1 is the no-load losses, corrected for losses, either (1) measure transformer losses
voltmeters and wattmeter voltage circuit, and waveform distortion, at temperature Tnm, without the auxiliary devices by removing or
to voltage transformers if they are used, may Tnm is the core temperature during the by-passing them, or (2) measure transformer
be deducted from the total no-load losses measurement of no-load losses, and losses with the auxiliary devices connected,
ER27AP06.015</MATH>

measured during testing. Tnr is the reference temperature, 20 °C. determine the losses associated with the

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00035 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
25006 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

auxiliary devices, and deduct these losses per unit correction, bn, obtained by using (c) If the correction for phase angle errors
from the load losses measured during testing. equation 4–3 as follows: is to be applied, first examine the total
4.5.3.2 Correction for Phase Angle Errors. system phase angle (bw ¥ bv + bc). Where the
(a) Corrections for phase angle errors are Vlm Ilm ( βw − βv + βc ) sin φ total system phase angle is equal to or less
not required if the instrumentation is βn = ( 4-3) than ±12 milliradians (±41 minutes), use
calibrated over the entire range of power
p lm either equation 4–4 or 4–5 to correct the
factors and phase angle errors. Otherwise, (b) The correction must be applied if bn is measured load loss power for phase angle
determine whether to correct for phase angle outside the limits of ±0.01. If bn is within the errors, and where the total system phase
errors from the magnitude of the normalized limits of ±0.01, the correction is permitted angle exceeds ±12 milliradians (±41 minutes)
but not required. use equation 4–5, as follows:

Plcl = Plm − Vlm Ilm ( βw − βv + βc ) sin φ ( 4-4 )

Plcl = Vlm Ilm cos ( φ + βw − βv + βc ) ( 4-5) is the measured phase angle between Vlm and
Ilm,
(e) The instrumentation phase angle errors
used in the correction equations must be
(d) The symbols in this section (4.5.3.2) bw is the phase angle error (in radians) of the specific for the test conditions involved.
have the following meanings: wattmeter; the error is positive if the 4.5.3.3 Temperature Correction of Load
phase angle between the voltage and Loss.
Plc1 is the corrected wattmeter reading for
current phasors as sensed by the (a) When the measurement of load loss is
phase angle errors, wattmeter is smaller than the true phase
Plm is the actual wattmeter reading, made at a temperature Tlm that is different
angle, thus effectively increasing the
Vlm is the measured voltage at the measured power, from the reference temperature, use the
transformer winding, bv is the phase angle error (in radians) of the procedure summarized in the equations 4–6
Ilm is the measured rms current in the voltage transformer; the error is positive to 4–10 to correct the measured load loss to
transformer winding, if the secondary voltage leads the the reference temperature. The symbols used
primary voltage, and in these equations are defined at the end of
bc is the phase angle error (in radians) of the this section.
Plm
φ = cos −1 current transformer; the error is positive if (b) Calculate the ohmic loss (Pe) by using
Vlm Ilm the secondary current leads the primary equation 4–6 as follows:
current.

Pe = Pe( p ) + Pe(s )

ER27AP06.025</MATH>
Tk ( p ) + Tlm Tk (s ) + Tlm
= Ilm
2
( p ) R dc ( p ) + Ilm
2
( s ) R dc ( s )
Tk ( p ) + Tdc Tk (s ) + Tdc
 Tk ( p ) + Tlm  N1  Tk (s ) + Tlm 
2

ER27AP06.024</MATH>
= Ilm
2
(p)  R dc ( p )
+   R  ( 4-6 )
 Tk ( p ) + Tdc  N 2  dc(s ) Tk (s ) + Tdc 

(c) Obtain the stray loss by subtracting the (d) Correct the ohmic and stray losses to

ER27AP06.023</MATH>
calculated ohmic loss from the measured the reference temperature for the load loss by
load loss, by using equation 4–7 as follows: using equations 4–8 and 4–9, respectively, as
follows:
Ps = Plc1 − Pe ( 4-7 )

ER27AP06.022</MATH>
Tk ( p ) + Tlr Tk (s ) + Tlr
Per = Pe( p ) + Pe(s )
Tk ( p ) + Tlm Tk (s ) + Tlm
ER27AP06.021</MATH>

 Tk ( p ) + Tlr  N1  2 Tk (s ) + Tlr 
= Ilm
2
(p)  R dc ( p )
+   R dc(s )  ( 4-8)
 Tk ( p ) + Tdc  N 2  Tk (s ) + Tdc 

ER27AP06.020</MATH>

Tk + Tlm (e) Add the ohmic and stray losses, temperature, by using equation 4–10 as
Psr = ( Plc1 − Pe ) ( 4-9 ) corrected to the reference temperature, to follows:
Tk + Tlr
ER27AP06.019</MATH>

give the load loss, Plc2, at the reference


rmajette on PROD1PC67 with RULES3

ER27AP06.018</MATH>

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00036 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations 25007

Plc 2 = Per + Psr

 Tk ( p ) + Tlr  N1  2 Tk (s ) + Tlr 
= Ilm
2
(p)  R dc ( p )
+   R dc(s ) 
 Tk ( p ) + Tdc  N 2  Tk (s ) + Tdc 

  Tk ( p ) + Tlm  N1  2 Tk (s ) + Tlm   Tk + Tlm



+ Plc1 − Ilm ( p )  R dc( p )
2
+   R dc(s )  ( 4-10 )
  Tk ( p ) + Tdc  N 2  Tk (s ) + Tdc   Tk + Tlr
  

(f) The symbols in this section (4.5.3.3) 5.0 Determining the Efficiency Value of the Pts is as described and calculated in section
have the following meanings: Transformer 5.2.
Ilm(p) is the primary current in amperes, This section presents the equations to use 5.4 Significant Figures in Power Loss and
Ilm(s) is the secondary current in amperes, in determining the efficiency value of the Efficiency Data.
Pe is the ohmic loss in the transformer in transformer at the required reference In measured and calculated data, retain
enough significant figures to provide at least
watts at the temperature Tlm, conditions and at the specified loading level.
1 percent resolution in power loss data and
Pe(p) is the ohmic loss in watts in the primary The details of measurements are described in
0.01 percent resolution in efficiency data.
winding at the temperature Tlm, sections 3.0 and 4.0. For a transformer that
Pe(s) is the ohmic loss in watts in the has a configuration of windings which allows 6.0 Test Equipment Calibration and
secondary winding at the temperature for more than one nominal rated voltage, Certification
Tlm, determine its efficiency either at the voltage Maintain and calibrate test equipment and
Per is the ohmic loss in watts corrected to the at which the highest losses occur or at each measuring instruments, maintain calibration
reference temperature, voltage at which the transformer is rated to records, and perform other test and
Plc1 is the measured load loss in watts, operate. measurement quality assurance procedures
corrected for phase angle error, at the 5.1 Output Loading Level Adjustment. according to the following sections. The
temperature Tlm, If the output loading level for energy calibration of the test set must confirm the
Plc2 is the load loss at the reference efficiency is different from the level at which accuracy of the test set to that specified in
the load loss power measurements were section 2.0, Table 2.1.
temperature,
made, then adjust the corrected load loss 6.1 Test Equipment.
Ps is the stray loss in watts at the temperature
power, Plc2, by using equation 5–1 as follows: The party performing the tests shall
Tlm,
Psr is the stray loss in watts corrected to the control, calibrate and maintain measuring
P  and test equipment, whether or not it owns
reference temperature,
Rdc(p) is the measured dc primary winding Plc = Plc 2  os  = Plc 2 L2 ( 5-1) the equipment, has the equipment on loan,
resistance in ohms,  Por  or the equipment is provided by another
party. Equipment shall be used in a manner
Rdc(s) is the measured dc secondary winding Where: which assures that measurement uncertainty
resistance in ohms, Plc is the adjusted load loss power to the is known and is consistent with the required
Tk is the critical temperature in degrees specified energy efficiency load level, measurement capability.
Celsius for the material of the Plc2 is as calculated in section 4.5.3.3, 6.2 Calibration and Certification.
transformer windings. Where copper is Por is the rated transformer apparent power The party performing the tests must:
used in both primary and secondary (name plate), (a) Identify the measurements to be made,
windings, Tk is 234.5 °C; where Pos is the specified energy efficiency load the accuracy required (section 2.0) and select
aluminum is used in both primary and level, where , and Pos = PorL2, and the appropriate measurement and test
secondary windings, Tk is 225 °C; where L is the per unit load level, e.g., if the load equipment;
both copper and aluminum are used in level is 50 percent then ‘‘L’’ will be 0.5. (b) At prescribed intervals, or prior to use,
the same transformer, the value of 229 °C 5.2 Total Loss Power Calculation. identify, check and calibrate, if needed, all
is used for Tk, Calculate the corrected total loss power by measuring and test equipment systems or
Tk(p) is the critical temperature in degrees using equation 5–2 as follows: devices that affect test accuracy, against
Celsius for the material of the primary certified equipment having a known valid
winding: 234.5 °C if copper and 225 °C relationship to nationally recognized
if aluminum,
Pts = Pnc + Plc ( 5-2 ) standards; where no such standards exist, the
Tk(s) is the critical temperature in degrees Where: basis used for calibration must be
documented;
ER27AP06.030</MATH>
Celsius for the material of the secondary Pts is the corrected total loss power adjusted
winding: 234.5 °C if copper and 225 °C (c) Establish, document and maintain
for the transformer output loading calibration procedures, including details of
if aluminum, specified by the standard,
Tlm is the temperature in degrees Celsius at equipment type, identification number,
Pnc is as calculated in section 4.4.3.3, and location, frequency of checks, check method,
which the load loss is measured, Plc is as calculated in section 5.1.
Tlr is the reference temperature for the load acceptance criteria and action to be taken
ER27AP06.029</MATH>

5.3 Energy Efficiency Calculation. when results are unsatisfactory;


loss in degrees Celsius,
Calculate efficiency (h) in percent at (d) Ensure that the measuring and test
Tdc is the temperature in degrees Celsius at specified energy efficiency load level, Pos, by equipment is capable of the accuracy and
which the resistance values are using equation 5–3 as follows: precision necessary, taking into account the
measured, and
voltage, current and power factor of the
N1/N2 is the ratio of the number of turns in
 Pos  transformer under test;
ER27AP06.028</MATH>

η = 100  ( 5-3)
rmajette on PROD1PC67 with RULES3

the primary winding (N1) to the number


 (e) Identify measuring and test equipment
of turns in the secondary winding (N2);
for a primary winding with taps, N1 is
 Pos + Pts  with a suitable indicator or approved
identification record to show the calibration
the number of turns used when the Where: status;
voltage applied to the primary winding Pos is as described and calculated in section (f) Maintain calibration records for
ER27AP06.026</MATH>

is the rated primary voltage. 5.1, and measuring and test equipment;

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00037 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3
25008 Federal Register / Vol. 71, No. 81 / Thursday, April 27, 2006 / Rules and Regulations

(g) Assess and document the validity of the test is to determine compliance with the Step 10. Compute the standard error
previous test results when measuring and test labeled efficiency value. (SE(X̄2)) of the mean efficiency of the n1 and
equipment is found to be out of calibration; Step 6. Compute the lower control limit n2 tests in the combined first and second
(h) Ensure that the environmental (LCL1) for the mean of the first sample by samples by using equation 8 as follows:
conditions are suitable for the calibrations, using equation 5 as follows:
measurements and tests being carried out; S1
(i) Ensure that the handling, preservation
LCL1 = SSD ( m1 ) − tSE ( X1 ) (5) SE ( X 2 ) = (8)
and storage of measuring and test equipment n1 + n 2
is such that the accuracy and fitness for use where t is the 2.5th percentile of a t-
is maintained; and (Note that S1 is the value obtained above in
distribution for a sample size of n1, which
(j) Safeguard measuring and test facilities, yields a 97.5 percent confidence level for a Step 3.)
including both test hardware and test one-tailed t-test. Step 11. Set the lower control limit (LCL2)
software, from adjustments which would Step 7. Compare the mean of the first to,
invalidate the calibration setting. sample (X̄1) with the lower control limit
Appendix B to Subpart K of Part 431—
(LCL1) to determine one of the following:
(i) If the mean of the first sample is below
LCL 2 = SSD ( m1 ) − tSE ( X 2 ) (9)
Sampling Plan for Enforcement Testing the lower control limit, then the basic model where t has the value obtained in Step 5 and
Step 1. The number of units in the sample is in non-compliance and testing is at an end. SSD(m1) is sample size discount from Step 5.
(m1) shall be in accordance with (ii) If the mean is equal to or greater than
Compare the combined sample mean (X̄2) to
§§ 431.198(a)(4), 431.198(a)(5), 431.198(a)(6) the lower control limit, no final
the lower control limit (LCL2) to find one of
and 431.198(a)(7) and shall not be greater determination of compliance or non-
compliance can be made; proceed to Step 8. the following:
than twenty. The number of tests in the first
Step 8. Determine the recommended (i) If the mean of the combined sample (X̄2)
sample (n1) shall be in accordance with
sample size (n) by using equation 6 as is less than the lower control limit (LCL2), the
§ 431.198(a)(8) and shall be not fewer than
follows: basic model is in non-compliance and testing
four.
Step 2. Compute the mean (X̄i) of the is at an end.

ER27AP06.040</MATH>
 tS (108 − 0.08RE ) 
2 (ii) If the mean of the combined sample
measured energy performance of the n1 tests
in the first sample by using equation 1 as n= 1  (6) (X̄2) is equal to or greater than the lower
follows:  RE ( 8 − 0.08RE )  control limit (LCL2), the basic model is in
compliance and testing is at an end.
where S1 and t have the values used in Steps
1 n1 Manufacturer-Option Testing
∑ Xi (1) 3 and 6, respectively. The factor

ER27AP06.039</MATH>
X1 =
n1 i =1 If a determination of non-compliance is
108 − 0.08RE made in Steps 6, 7 or 11, above, the
where Xi is the measured efficiency of test i.
RE ( 8 − 0.08RE )
manufacturer may request that additional
Step 3. Compute the sample standard testing be conducted, in accordance with the
deviation (S1) of the measured efficiency of following procedures.

ER27AP06.038</MATH>
is based on an 8-percent tolerance in the total
the n1 tests in the first sample by using power loss. Step A. The manufacturer requests that an
equation 2 as follows: additional number, n3, of units be tested,
Given the value of n, determine one of the
following: with n3 chosen such that n1+n2+n3 does not
n1 (i) If the value of n is less than or equal exceed 20.
∑(X − X1 )
2
to n1 and if the mean energy efficiency of the Step B. Compute the mean efficiency,

ER27AP06.037</MATH>
i
S1 = i =1
( 2) first sample (X̄1) is equal to or greater than standard error, and lower control limit of the
n1 − 1 the lower control limit (LCL1), the basic new combined sample in accordance with
model is in compliance and testing is at an the procedures prescribed in Steps 8, 9, and
Step 4. Compute the standard error end. 10, above.
(SE(X̄1)) of the mean efficiency of the first (ii) If the value of n is greater than n1, and Step C. Compare the mean performance of

ER27AP06.036</MATH>
sample by using equation 3 as follows: no additional units are available for testing, the new combined sample to the lower
testing is at an end and the basic model is control limit (LCL2) to determine one of the
S1 in non-compliance. If the value of n is greater
SE ( X1 ) =
following:
( 3) than n1, and additional units are available for
testing, select a second sample n2. The size
(a) If the new combined sample mean is
n1 equal to or greater than the lower control
of the n2 sample is determined to be the

ER27AP06.035</MATH>
Step 5. Compute the sample size discount smallest integer equal to or greater than the limit, the basic model is in compliance and
(SSD(m1)) by using equation 4 as follows: difference n–n1. If the value of n2 so testing is at an end.
calculated is greater than 20–n1, set n2 equal (b) If the new combined sample mean is
to 20–n1. less than the lower control limit and the
100
SSD ( m1 ) = ( 4) Step 9. After testing the n2 sample, value of n1+n2+n3 is less than 20, the
 .08   100  compute the combined mean (X̄2) of the manufacturer may request that additional ER27AP06.034</MATH>
1 + 1 +  − 1 measured energy performance of the n1 and units be tested. The total of all units tested
 m1   RE 
 n2 tests of the combined first and second may not exceed 20. Steps A, B,and C are then
samples by using equation 7 as follows: repeated.
where m1 is the number of units in the
(c) Otherwise, the basic model is
sample, and RE is the applicable EPCA n1 + n 2 determined to be in non-compliance.
ER27AP06.033</MATH>

1
efficiency when the test is to determine
compliance with the applicable statutory X2 =
n1 + n 2
∑X
i =1
i (7) [FR Doc. 06–3165 Filed 4–26–06; 8:45 am]
standard, or is the labeled efficiency when BILLING CODE 6450–01–P
ER27AP06.032</MATH>
rmajette on PROD1PC67 with RULES3

ER27AP06.031</MATH>

VerDate Aug<31>2005 15:25 Apr 26, 2006 Jkt 208001 PO 00000 Frm 00038 Fmt 4701 Sfmt 4700 E:\FR\FM\27APR3.SGM 27APR3

Вам также может понравиться