CHAPTER 1 GENERAL REQUIREMENTS...........3
SECTION 101 - TITLE, PURPOSE AND SCOPE......3
101.1 Title......................................................................3
101.2 Purpose................................................................3
101.3 Scope...................................................................3
101.4 Alternative Systems.............................................3
SECTION 102 - DEFINITIONS....................................3
SECTION 103 - CLASSIFICATION OF BUILDINGS4
103.1 Nature of Occupancy...........................................4
SECTION 104 - DESIGN REQUIREMENTS.............5
104.1 Strength Requirement..........................................5
104.2 Serviceability Requirement.................................5
104.2.1 General.........................................................5
104.3 Analysis...............................................................5
104.3.1 Stability Against Overturning.......................6
104.3.2 Self-Straining Forces....................................6
104.3.3 Anchorage.....................................................6
104.4 Foundation Investigation.....................................6
104.5 Design Review....................................................6
104. 6 Erection of Structural Framing...........................6
SECTION 105 - POSTING AND INSTRUMENTATION
1-1
1-2
1-3
108.2 Maintenance.....................................................14
108.3 Additions, Alterations or Repairs......................14
108.3.1 General.......................................................14
108.3.2 When Allowed by the Building Official.....14
108.3.3 Nonstructural..............................................15
108.3.4 Historic Buildings......................................15
108.4 Change in Use...................................................15
SECTION 109 - GRADING AND EARTHWORK..15
109.1 General..............................................................15
109.1.1 Scope..........................................................15
109.2 Definitions.........................................................15
109.3 Permits Required..............................................16
109.3.1 Permits Required........................................16
109.3.2 Exempted Work..........................................16
109.4 Hazards..............................................................17
109.5 Grading Permit Requirements...........................17
109.5.1 General.......................................................17
109.5.2 Grading Designation..................................17
109.5.3 Engineered Grading Requirements............17
109.5.4 Geotechnical Engineering Report..............18
109.5.5 Engineering Geology Report......................18
109.5.6 Regular Grading Requirements..................18
109.6 Grading Inspection............................................18
109.6.1 General.......................................................18
109.6.2 Civil Engineer.............................................18
109.6.3 Geotechnical Engineer................................18
109.6.4 Engineering Geologist................................18
109.6.5 Permittee.....................................................19
109.6.6 Building Official.........................................19
109.6.7 Notification of Noncompliance..................19
109.6.8 Transfer of Responsibility..........................19
109.7 Completion of Work..........................................19
109.7.1 Final Reports..............................................19
109.7.2 Notification of Completion........................19
CHAPTER 1 GENERAL
REQUIREMENTS
SECTION 101 - TITLE, PURPOSE
AND SCOPE
101.1 Title
These regulations shall be known as the National
Structural Code of the Philippines 6th Edition 2010,
may be cited as such and will be referred to herein as this
code."
101.2 Purpose
The purpose of this code is to provide minimum load
requirements for the design of buildings and other
National Structural Code of the Philippines 6th Edition Volume 1
1-4
Volume I
Volume II
Volume III
Volume IV
Volume V
1-5
Essential
Facilities
OCCUPANCY OR FUNCTION OF
STRUCTURE
Occupancies having surgery and emergency
treatment areas,
Fire and police stations,
Garages and shelters for emergency
vehicles and emergency aircraft,
Structures and shelters in
emergency preparedness centers,
Aviation control towers,
Structures and equipment in communication
centers and other facilities required for
emergency response,
Standby power-generating equipment for
Category I facilities,
Tanks or other structures containing
housing or supporting water or other
fire-suppression material or equipment
required for the protection of Category I,
II or III structures.
School buildings of more than one storey.
Hospitals and designated evacuation centers
1-6
II Hazardous
Facilities
III Special
Occupancy
Structures
OCCUPANCY OR FUNCTION OF
STRUCTURE
Occupancies and structures therein housing
or supporting toxic or explosive
chemicals or substances,
Non-building structures storing, supporting
or containing quantities of toxic or
explosive substances.
Single storey school buildings
Buildings with an assembly room with an
occupant capacity of 1,000 or more,
Educational buildings such as museums
libraries, auditorium etc with a capacity
of 300 or more students,
Buildings used for college or adult
education with a capacity of 500 or more
students,
Institutional buildings with 50 or more
incapacitated patients, but not included
in Category I,
Mental hospitals, sanitariums, jails, prison
and other buildings where personal liberties
of inmates are similarly restrained,
All structures with an occupancy 5,000 or
more persons,
Structures and equipment in powergenerating stations, and other public
utility facilities not included in Category
I or Category II above, and required for
continued operation.
IV Standard
Occupancy
Structures
V Miscellaneous
Structures
1-7
1-8
1-9
2.
3.
3.
4.
4.
5.
5.
6.
6.
106.4 Calculations
7.
8.
Explanation or definition of
abbreviations used in the drawings.
9.
106.4.1 General.
Calculations pertinent to the structural design of
structures and its component members shall be filed with
the design drawings.
symbols
and
2.
3.
3.
4.
4.
5.
5.
6.
6.
7.
7.
8.
2.
2.
1-10
2.
3.
4.
1-11
107.2 Definitions
The following terms are defined for use in this section:
CONTINUOUS STRUCTURAL INSPECTION is a
structural inspection where the structural inspector is on
the site at all times observing the work requiring
structural inspection.
PERIODIC STRUCTURAL INSPECTION is a
structural inspection where the inspections are made on a
periodic basis and satisfy the requirements of continuous
inspection, provided this periodic scheduled inspection is
performed as outlined in the inspection program prepared
by the structural engineer.
STRUCTURAL INSPECTION is the visual observation
by a structural engineer of a particular type of
construction work or operation for the purpose of
ensuring its general compliance to the approved plans and
specifications and the applicable workmanship provisions
of this code as well as overall construction safety at
various stages of construction.
STRUCTURAL OBSERVATION is the visual
observation of the structural system by the structural
engineer responsible for the design (see Section 107.9.2),
for its general conformance to the approved plans and
specifications, at significant construction stages and at
completion of the structural system.
Structural
107.4.1 Qualifications.
The structural inspector shall be a registered civil
engineer or a qualified person under the supervision of a
registered civil engineer who shall demonstrate
competence, to the satisfaction of the structural engineer,
for inspection of the particular type of construction or
operation requiring structural inspection.
107.4.2 Duties and Responsibilities.
The structural inspector shall observe the work assigned
for conformance to the approved design drawings and
specifications.
The structural inspector shall also verify that the as-built
drawings (see Section 106.5) pertaining to the work
assigned reflect the condition as constructed.
The structural inspector shall furnish inspection reports to
the building official, the structural engineer, and other
designated persons. All discrepancies shall be brought to
the immediate attention of the contractor for correction,
then, if uncorrected, to the proper design authority and to
the building official.
The structural inspector shall submit a final report duly
signed and sealed stating whether the work requiring
structural inspection was, to the best of the inspector's
knowledge, in conformance to the approved plans and
specifications and the applicable workmanship provisions
of this code.
1-12
Exception:
The structural inspector need not be present continuously
during placing of reinforcing steel and prestressing
tendons, provided the structural inspector has inspected
for conformance to the approved plans prior to the
closing of forms or the delivery of concrete to the jobsite.
107.5.5 Structural Welding.
107.5.5.1 General.
During the welding of any member or connection that is
designed to resist loads and forces required by this code.
2.
1.
3.
2.
4.
Exceptions:
1-13
Exception:
The structural inspections may be limited to an initial
inspection to check the deck surface and placement of
reinforcing steel. The structural inspector shall monitor
the preparation of compression test specimens during this
initial inspection.
107.5.10 Spray-Applied Fire-Resistive Materials.
During the application of spray-applied fire-resistive
materials..
107.5.11 Piling, Drilled Piers and Caissons.
During driving and load testing of piles and construction
of cast-in-place drilled piles or caissons. See Sections
107.5.1 and 107.5.4 for concrete and reinforcing steel
inspection.
107.5.12 Shotcrete.
During the taking of test specimens and placing of all
shotcrete.
Exception:
Exception:
107.5.7.2 General.
For fully grouted open-end hollow-unit masonry during
preparation and taking of any required prisms or test
specimens, at the start of laying units, after the placement
of reinforcing steel, grout space prior to each grouting
operation, and during all grouting operations.
Exception:
Structural inspection as required in Sections 107.5.7.1
and 107.5.7.2 need not be provided when design stresses
have been adjusted as specified in Chapter 7 to permit
noncontinuous inspection.
107.5.8 Reinforced Gypsum Concrete.
When cast-in-place Class B gypsum concrete is being
mixed and placed.
107.5.9 Insulating Concrete Fill.
During the application of insulating concrete fill when
used as part of a structural system.
1-14
107.7.4 Connections.
Every device used to connect prefabricated assemblies
shall be designed as required by this code and shall be
capable of developing the strength of the largest member
connected, except in the case of members forming part of
a structural frame designed as specified in Chapter 2.
Connections shall be capable of withstanding uplift forces
as specified in Chapter 2.
1.
2.
3.
107.7.6.1 Materials.
Materials and the assembly thereof shall be inspected to
determine compliance with this code. Every material shall
be graded, marked or labeled where required elsewhere in
this code.
107.7.6.2 Certificate.
A certificate of acceptance shall be furnished with every
prefabricated assembly, except where the assembly is
readily accessible to inspection at the site. The certificate
of acceptance shall certify that the assembly in question
has been inspected and meets all the requirements of this
code.
107.7.6.3 Certifying Agency.
To be acceptable under this code, every certificate of
approval shall be made by a recognized certifying body or
agency.
Exception:
Continuous inspection will not be required during
prefabrication if the approved agency certifies to the
construction and furnishes evidence of compliance.
1-15
107.8.2.2 General.
Partial penetration groove welds when used in column
splices shall be tested either by ultrasonic testing or
radiography when required by the plans and
specifications. For partial penetration groove welds when
used in column splices, with an effective throat less than
20 mm thick, nondestructive testing is not required; for
this welding, continuous structural inspection is required.
107.8.2.3 General.
Base metal thicker than 40 mm, when subjected to
through-thickness weld shrinkage strains, shall be
ultrasonically inspected for discontinuities directly behind
such welds after joint completion.
Any material discontinuities shall be accepted or rejected
on the basis of the defect rating in accordance with the
(larger reflector) criteria of approved national standards.
107.8.3 Others.
The structural engineer may accept or require in place
non-destructive testing of concrete or other materials and
assemblies to supplement or replace conventional tests.
Exceptions:
1.
2.
3.
4.
2.
3.
1-16
2.
3.
4.
108.3.3 Nonstructural.
Nonstructural alterations or repairs to an existing building
or structure are permitted to be made of the same
materials of which the building or structure is constructed,
provided that they do not adversely affect any structural
member or the fire-resistance rating of any part of the
building or structure.
108.3.4 Historic Buildings.
Repairs, alterations and additions necessary for the
preservation, restoration, rehabilitation or continued use
2.
3.
1-17
109.1.1 Scope.
The provisions of this section apply to grading,
excavation and earthwork construction, including fills and
enbankments.
109.2 Definitions
The following terms are defined for use in this section:
1-18
Cemetery graves;
4.
5.
6.
7.
8.
9.
2.
permit shall be obtained for each site, and may cover both
excavations and fills.
109.5.2 Grading Designation.
Grading in excess of 4,000 m3 shall be performed in
accordance with the approved grading plan prepared by a
civil engineer, and shall be designated as "engineered
grading." Grading involving less than 4,000 m3 shall be
designated "regular grading" unless the permittee chooses
to have the grading performed as engineered grading, or
the building official determines that special conditions or
unusual hazards exist, in which case grading shall
conform to the requirements for engineered grading.
109.5.3 Engineered Grading Requirements.
Application for a grading permit shall be accompanied by
two sets of plans and specifications, and supporting data
consisting of a geotechnical engineering report and
engineering geology report. Additionally, the application
shall state the estimated quantities of work involved. The
plans and specifications shall be prepared and signed by
the civil engineer licensed to prepare such plans or
specifications when required by the building official.
Specifications shall contain information covering
construction and material requirements. Plans shall be
drawn to scale upon substantial paper or cloth and shall be
of sufficient clarity to indicate the nature and extent of the
work proposed and show in detail that they will conform
to the provisions of this code and all relevant laws,
ordinances, rules and regulations. The first sheet of each
set of plans shall give location of the work, the name and
address of the owner, and the person by whom they were
prepared.
The plans shall include the following information:
1.
2.
3.
4.
5.
1-19
7.
2.
1-20
3.
109.6.5 Permittee.
The permittee shall be responsible for the work to be
performed in accordance with the approved plans and
specifications and in conformance with the provisions of
this code, and the permittee shall engage consultants, as
may be necessary, to provide professional inspection on a
timely basis. The permittee shall act as a coordinator
between the consultants, the contractor and the building
official. In the event of changed conditions, the permittee
shall be responsible for informing the building official of
such change and shall provide revised plans for approval.
109.6.6 Building Official.
The building official shall inspect the project at the
various stages of work requiring approval to determine
that adequate control is being exercised by the
professional consultants.
109.6.7 Notification of Noncompliance.
If, in the course of fulfilling their respective duties under
this chapter, the civil engineer, the geotechnical engineer
or the engineering geologist finds that the work is not
being done in conformance with this chapter or the
approved grading plans, the discrepancies shall be
reported immediately in writing to the permittee and to
the building official.
109.6.8 Transfer of Responsibility.
If the civil engineer, the geotechnical engineer, or the
engineering geologist of record is changed during
grading, the work shall be stopped until the replacement
has agreed in writing to accept their responsibility within
the area of technical competence for approval upon
completion of the work. It shall be the duty of the
permittee to notify the building official in writing of such
change prior to the recommencement of such grading.
109.7 Completion of Work
109.7.1 Final Reports.
Upon completion of the rough grading work and at the
final completion of the work, the following reports and
drawings and supplements thereto are required for
engineered grading or when professional inspection is
performed for regular grading, as applicable:
1.
3.
4.
1-21