Вы находитесь на странице: 1из 1

An Introduction to PRINCE2

21

Corp..

Note: If the Project Board agrees with the Exception Report (if they agree with the recommended
options or one of the other options), they will request an Exception Plan, which will replace the
current Stage Plan and therefore allow the Project Manager to complete the current stage.

Direction

Directing a Project (DP)


Authorize a Stage
or Exception Plan

Give ad hoc
direction

Controlling a Stage (CS)

Guidance & advise

(SB) Managing a
Stage Boundary

Highlight Reports

End Stage Report


Next Stage Plan
or Exception Plan

Exception Report

Auth.
2 Proceed
Auth.next
stage

Co n tro llin g a S ta g e : Ou tp u ts
Authorize Project
Approved PID

Management

By Frank Turley
Management-Plaza.com

Corporate or Programme Management

Highlight Report
- Created by PM for Project Board
- Reports on Stage progress v Stage plan
- Tip: Think about the tip of an Iceberg
Exception Report
- Only created - out of tolerance,
- Describes issue & give suggestions
Input: Guidance & Advise
- At any time from Project Board

New WP

Delivery

Work Package
Work Package
Accept a WP

Work Package
Completed WP

Managing Product Delivery (MP)


Fig 3.16 Controlling a Stage outputs

Guidance and Advice


x
x

The project board can provide guidance and advice at any time during the project.
This can also be an answer to an issue/question that was perhaps raised by the Project
Manager in the Highlight Report.

3.15 CS: Project Manager Day to day activities


Before we move to the Managing a Stage Boundary process, let us look at the different activities
that are done by the Project Manager in the Controlling a Stage process.
There are eight activities in the Controlling a Stage process. They are divided into three parts that
also describe what the Project Manager does:
1.
2.
3.

Deal with Work Packages


Do Monitoring and Reporting
Deal with Issues

The Work Package activities are:


o Authorize a Work Package meaning assign and agree with the Team Manager so
that the Team Manager knows what to do and can create their team plan.
o Review Work Package Status check on work package progress, so read
Checkpoint reports and check the Quality Register.
o Receive Completed Work Packages which is to receive the completed products
back from the Team Manager and confirm that they have been quality-checked and
stored, as described in the configuration management document.

The Monitoring and Reporting activities are:


o Review the stage status Continually compare the stage status to the stage plan
checking if the stage is still on track and if anything is likely to affect this.

Management Plaza

Foundation Training Manual

Вам также может понравиться