Академический Документы
Профессиональный Документы
Культура Документы
Arrow diagrams
consist of arrows and nodes plus letters and numbers for labeling and calculation
purposes
Key Steps in Critical Path Method Project Planning
1. Specify activities
2. Establish Activity Sequence
3. Produce network diagram
4. Estimate the completion time for each activity
5. Identify the critical path (longest path through the network)
6. Update the CPM diagram as the project progresses
1. Specify Activities
* Based on the work breakdown structure (WBS), produce a list of all the activities in
the project.
* This listing will be used as the basis for additional sequence and duration
information.
2. Establish Activity Sequence
Determine the correct sequence of the tasks. Do this by asking three questions for
each task:
i. Which tasks must happen before this one can begin?
ii. Which tasks can be done at the same time as this one?
iii. Which tasks should happen immediately after this one?
It can be useful to create a table with four columns:-prior tasks, this task,
simultaneous tasks, following tasks.
3. Produce Network Diagram
Once the activities and their sequencing have been defined, the CPM diagram can be
drawn. CPM originally was developed as an activity on node (AON) network. Now
computers and planning software such as Primavera are used to produce the
Network Diagram. however the principles of AON networks should be understood.
4. Determine Activity Durations
Determine a reasonable time required to complete each activity based on metrics,
past experience or the estimates of knowledgeable persons. It is important to record
how the estimated durations were derived and from what source of information. the
Critical Path Method is a deterministic model that does not take into account
variation in the completion time, so only one number is used for an activity's time
estimate.
5. Identify the Critical Path
Determine the following four parameters for each activity:
i. ES - earliest start time
The earliest time at which the activity can start given that its precedent activities
must be completed first.
ii. EF - earliest finish time
Equal to the earliest start time for the activity plus the time required to complete the
activity.
iii. LF - latest finish time
The latest time at which the activity can be completed without delaying the project.
iv. LS - latest start time
Equal to the latest finish time minus the time required to complete the activity.
The Float (slack time) for an activity is the time between its earliest and latest start
time, or between its earliest and latest finish time. Float is the amount of time that
an activity can be delayed past its earliest start or earliest finish without delaying the
project.
The critical path is the longest-duration path through the network. The activities that
lie on the critical path cannot be delayed without delaying the project. The critical
path is the path through the project network in which none of the activities have
float, that is, the path for which ES=LS and EF=LF for all activities in the path.
To accelerate the project it is necessary to reduce the total time required for the
activities in the critical path.
6. Update the CPM diagram
Update the CPM diagram as the project progresses. The task completion times will be
known and the network diagram can be updated to include this information. A new
critical path can emerge, and structural changes may be made in the network if
project requirements change. This is a key element in managing the project and
fundamental aspect of Change Management.
Your example
Your
ne Critical Activities
Activities are critical when:
1.Early Event Time & Late Event Time are the same
2.ES and LS & EF and LF time are the same
Applying these rules to our example the Critical Path is as follows:
Determi
SSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSSS
To calculate the total float for a Precedence Diagram, subtract the Early Finish Time from the Late
Finish Time.
Once this is accomplished for every activity, then the float calculation portion of the schedule is
complete. The diagram below show the location for the total float and provide an example of a small
schedule with completed total float calculation.
an example diagram that includes total float for a slightly more complex sequence of activities is
shown below. You may notice that the path of activities with the least float (i.e. zero float) is Activity
B and Activity D. These two activities are on the critical path for this small project.
Typically the Late Finish Time for the last activity will be set to the project completion date. If the
float is positive then the critical path may be delayed without running the project past the
completion date. If the float is equal to zero, then any delay to the critical path will result in a delay
to the project. Negative float identifies a critical path that is behind schedule.