Академический Документы
Профессиональный Документы
Культура Документы
Energy
journal homepage: www.elsevier.com/locate/energy
DEIM e Department of Energy, Information Engineering and Mathematical Models, Universit di Palermo, Viale delle Scienze, Palermo, Italy
ENEA e Italian National Agency for New Technologies, Energy and Sustainable Economic Development, Portici, Italy
a r t i c l e i n f o
a b s t r a c t
Article history:
Received 21 May 2013
Received in revised form
22 November 2013
Accepted 23 November 2013
Available online xxx
The subject addressed in this paper is the denition of some strategies for the design and the optimaized
management of EES (Electrical Energy Storage) systems, for an existing islanded distribution network
supplying the Island of Pantelleria (Italy) in the Mediterranean Sea.
In the paper the authors have drawn interesting conclusions through the application of an efcient MO
(multi-objective) optimization algorithm, the NSGA-II, minimizing the energy losses in the grid, the total
electricity generation cost and the greenhouse gas emissions.
The results obtained for different installation scenarios of the EES are presented and discussed, putting
into evidence the technical, environmental and economical benets of using EES as well as the technical
issues connected to their installation into an existing distribution network.
The paper describes in details the second part of a feasibility study about the transition from a fuelbased traditional centralized electrical system to an active and smart renewables-based electrical
distribution system.
2013 Elsevier Ltd. All rights reserved.
Keywords:
Electric energy storage
GHG (greenhouse gas)
Energy losses
Islanded system
1. Introduction
In Ref. [1] a technical-economic feasibility study has been presented that, in line with the most recent trends in power systems
research [2e7], addresses the transformation of the electrical energy generation system supplying the MV/LV (Medium Voltage/
Low Voltage) distribution system in the Mediterranean island of
Pantelleria from a fossil fuel-based model to a distributed and
smart renewables-based one.
In particular, a set of scenarios, characterized by the presence of
RES (renewable energy sources) available in the island, have been
dened and a technical and economic analysis for these scenarios
has been carried out. The results of the simulations carried out have
highlighted the benets connected to the above described transformation, both in terms of costs and losses reduction and of quality
of the energy supply.
Based on the results drawn in Ref. [1], in this paper, a more
detailed technical assessment has been carried out, focusing the
649
650
Table 1
Distributed Generators in the test MV Network.
Typology
Rated power
[MW]
Yearly energy
production [MWh]
Node
Geothermal plant
PV plants
2.5
0.33 (total)
20,000
510
Waste-to-energy
plant
0.37
79
4, 5, 7, 8, 9, 12, 13, 32,
34, 35, 135, 144, 207
206
1600
Fig. 1. Simplied scheme of the MV network of the Island of Pantelleria, with the present DGs (Photovoltaic, Geothermal and Waste-to-Energy plants).
651
formulation and the optimization algorithm solving the management problem are described.
5. Formulation of the multi-objective optimization problem
With reference to a simulation time horizon of 24 h and in the
considered above described installation scenarios, the problem of
the management of the EES systems is that of the identication of
the set-points of the distributed generators and of the distributed
EES, in order to minimize the energy losses in the network, the total
generation costs and the GHG emissions, that are the objective
functions of the optimization problem.
The problem exposed is an EED (Environmental and Economical
Dispatch) non- linear multi-objective optimization problem with
constraints and has, in general, various solutions. Each solution is
characterized by different values of the objective functions.
The EED consists in the optimal dispatch of the energy generated by the power plants and generated/absorbed by the EES,
solving an Optimal Power Flow problem, given:
- the daily load prole in all the nodes of the network;
- the daily electrical energy production of all the RES-based
generators;
- the generation costs and the GHG emissions of all the traditional
dispatchable generators;
- the EES initial SOC (state-of-charge);
- the technical constraints for the thermal generator.
Considering that the simulation is done with a time-step of 1 h,
the analytical formulation of the optimization problem is the
following.
A N-bus isolated distribution system is considered with:
- Nx load or generation nodes with xed forecasted real and
reactive power demands or injections;
- NDG controllable distributed generation units.
The vector X identifying the set-points of the controllable DG
units can be expressed as:
X x1 ; x2 ; .; xh ; .; x24
where the hth element, related to the hth hour of the day, is:
(1)
652
xh
g;h
(2)
g;h
O1 X
NDG
24 X
X
h1 i1
g;h
CPi $Pi $t
(3)
B. Energy losses
The second objective function O2 is the sum of the daily energy losses in all the branches of the MV network. Being Nb the
number of branches of the network and assumed that the current in each branch is constant in the elementary time interval
and equal to Iih , the objective function is formulated as it follows:
O2 X
Nb
24 X
X
h1 i1
3$Ri $Iih $t
(4)
6. The NSGA-II optimization algorithm
C. GHG emissions
The third objective function O3 is the sum of the GHG emish
sions of the traditional generators. Being Em;i
the quantity of
tons of gas produced during the hth hour by the ith generation
unit, the objective function is formulated as it follows:
O3 X
Nb
24 X
X
h1 i1
h
Em;i
(5)
g;h
g;h
Qj;min Qj
Pj;MAX
g
Qj;MAX
D. Constraints
The typical constraints are:
a)
Pj;min Pj
(6)
where:
g
g
- Pjg;h ; Pj;min
and Pj;MAX
respectively represent the active
production at the hth hour and the minimum and
maximum limits of active power at the jth DG unit;
g;h
g
g
- Qj ; Qj;min and Qj;MAX respectively represent the reactive
production at the hth and the minimum and maximum
limits of the reactive power at the jth DG unit.
b) power transfer limits in the network branches;
c) maximum and minimum limits for the voltage prole in the
nodes;
d) limits on the power exchanged by each EES system;
e) active and reactive power balancing between generators and
loads.
For a problem having multiple objective functions to be minimized (fj, j 1,.,m with m > 1) any two multidimensional solutions x1 and x2 of the optimization problem can have one or two
possibilities: one dominates the other or none dominates the other.
A solution x1 is said to dominate the other solution x2, if both the
following conditions are true:
the solution x1 is no worse than x2 in all objectives. This means
that fj(x1) fj(x2), for all j 1..m;
the solution x1 is strictly better than x2 in at least one objective.
This means that fj*(x1)<fj*(x2) for at least one j* {1.m}.
If no one of the above conditions is true, the solution x1 does not
dominate the solution x2.
It is also important to observe that the concept of optimality in
multiobjective optimization is related to a set of solutions, instead
than to a single one. This means that, generally, the problem has
multiple equivalent solutions and, therefore, it is possible to dene
Pareto local and global optimality for sets of solutions.
653
f2
0
i-1
CUBOID
i
i+1
1
f1
Here I[i].m refers to the mth objective function value of the ith
individual in the set I. It must be observed that the crowding distance is normalized along each direction of the objectives space.
i nj
654
95.75
95.6
95.55
GHG mission[ton]
95.7
95.65
95.5
95.45
95.4
6.82
4.905
6.8
4.91
6.78
Fig. 5. Monthly electric energy consumption of the Island of Pantelleria (data 2011).
6.74
4.92
6.72
4.925
costs[k]
95.75
GHG emission[ton]
4.915
6.76
95.7
95.65
95.6
95.55
95.5
95.45
95.4
6.82
4.905
6.8
4.91
6.78
4.915
6.76
6.74
4.92
6.72
4.925
costs[k]
Fig. 6. Average hourly electrical power demand for a working summer day (data 2011).
GHG emission[ton]
94.8
94.75
94.7
94.65
94.6
6.16
4.87
6.15
4.875
6.14
4.88
6.13
6.12
6.11
4.885
costs[k]
Fig. 10. Optimal Pareto set of solutions for the ST-LO strategy.
96
GHGemission[ton]
655
95.8
95.6
95.4
95.2
95
94.8
94.6
6.8
4.85
6.6
4.9
6.4
6.2
6
4.95
costs[k]
Fig. 11. Optimal Pareto set of solutions comparison for the three strategies.
Table 2
Mean values of the performance indexes of the network (objective functions) in the
base scenario.
Daily total generation
cost [kV]
Daily energy
losses [MWh]
Daily GHG
emissions [ton]
5.40
4.50
115
implemented at DEIM (Department of Energy, Information Engineering and Mathematics) and based on a code written on purpose,
varying size and location of the EES systems. Each Pareto front is
made of 200 individuals in 400 generations, crossover and mutation probabilities are 0.5 and 0.1 respectively. The results have been
averaged over a sample of Nr 30 runs which is considered to be a
meaningful sample.
8
6
4
2
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Fig. 12. Hourly electrical power production of the dispatchable generators (ST-PV: minimum generation cost solution).
Node_4
Node_32
2.5
Node_135
[MWh]
Node_144
1.5
1
0.5
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
h
Fig. 13. Daily prole of the state of charge (SOC) of the batteries (ST-PV: minimum generation cost solution).
656
8
6
4
2
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Fig. 14. Hourly electrical power production of the dispatchable generators (ST-PV: minimum GHG emission solution.
Node_4
2.5
Node_32
Node_135
Node_144
1.5
1
0.5
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Fig. 15. Daily prole of the state of charge (SOC) of the batteries (ST-PV: minimum GHG emission solution).
8
6
4
2
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
h
Fig. 16. Hourly electrical power production of the dispatchable generators (ST-VP: minimum generation cost solution).
Node_4
Node_32
2.5
Node_135
Node_144
1.5
1
0.5
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Fig. 17. Daily prole of the state of charge (SOC) of the batteries (ST-VP: minimum generation cost solution).
657
8
6
4
2
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Fig. 18. Hourly electrical power production of the dispatchable generators (ST-VP: minimum GHG emission solution).
Node_4
Node_32
2.5
Node_135
Node_144
1.5
1
0.5
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Fig. 19. Daily prole of the state of charge (SOC) of the batteries (ST-VP: minimum GHG emission solution).
8. Discussion
Simulations show that batteries have a notable potential to affect
the operation of distribution systems and that their operation is
characterized by no more than three charge/discharge cycles per day.
8
6
4
2
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Fig. 20. Hourly electrical power production of the dispatchable generators (ST-LO: minimum generation cost solution).
Node_4
Node_32
2.5
Node_135
Node_144
1.5
1
0.5
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Fig. 21. Daily prole of the state of charge (SOC) of the batteries (ST-LO: minimum generation cost solution).
658
8
6
4
2
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Fig. 22. Hourly electrical power production of the dispatchable generators (ST-LO: minimum GHG emission solution).
Node_4
Node_32
2.5
Node_135
Node_144
1.5
1
0.5
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Fig. 23. Daily prole of the state of charge (SOC) of the batteries (ST-LO: minimum GHG emission solution).
Table 3
Capacity of the batteries. ST-PV.
Node
Capacity [MWh]
4
32
135
144
0.93
0.75
1.18
2.43
Table 4
Capacity of the batteries. ST-VP.
Table 5
Capacity of the batteries. ST-LO.
Node
Capacity [MWh]
Node
Capacity [MWh]
3
24
131
199
1.9
1.16
1.16
0.95
2
9
15
144
3.2
0.8
0.5
0.65
Fig. 24. Voltage proles during the maximum load hour e Minimum cost solution.
Fig. 25. Voltage proles during the maximum load hour e Minimum GHG emissions solution.
Fig. 26. Voltage proles during the maximum load hour e Minimum energy losses solution.
659
660
Table 6
Maximum percentage voltage drop in the network.
Solution
Reference
scenario
ST-PV
ST-VP
ST-LO
8.46%
8.46%
8.44%
5.11%
5.11%
5.10%
2.77%
2.70%
2.77%
7.67%
7.61%
7.54%
Table 7
Number of nodes of the network where the voltage drops is higher than 7%.
Solution
Reference
scenario
ST-PV
ST-VP
ST-LO
23
23
23
0
0
0
0
0
0
16
16
15
Fig. 27. Simplied scheme of the MV network of the Island of Pantelleria, with the DGs and the EES systems for the ST-VP scenario.
661
Fig. 28. Control system layout for the optimal management system (only DG units are represented).
objective functions, for the three different examined scenarios (STPV, ST-VP and ST-LO), the results obtained demonstrate that it is not
possible to individuate only one optimal solution but a set of
numerous equivalent solutions.
In the ST-LO scenario, the minimum reduction of energy losses
but the maximum reduction of generation cost and GHG emission
is obtained. At the same time, this strategy is not able to give
sensible improvements to the voltage prole.
In the ST-PV scenario, the voltage drop signicantly reduces in
the most disadvantaged nodes but, on the contrary, it rises in the
other nodes. However, in the complex, the mean voltage prole is
generally improved. Moreover it appears the less convenient
among the three examined strategies.
Finally, the ST-VP scenario appears as the most suitable for the
operation of the network, with signicant advantageous effects on
the voltage prole and intermediate values for the objective
functions.
The scheme of the MV network, with the distributed generators
and the batteries for the ST-VP scenario is reported in Fig. 27.
Future works on the topic will address the following issues:
the identication of the branches whose section should be
increased in order to reduce energy losses;
the identication of the most suitable EES technology to be
installed in the Island of Pantelleria.
Acknowledgments
The study presented has been realized by a collaboration between ENEA, the Italian National Agency for New Technologies,
Energy and Sustainable Economic Development, and the DEIM
(Department of Energy, Information Engineering and Mathematics)
of the University of Palermo within the project Advanced Energy
Storage Systems nanced by the Italian Minister for the Economic
Development, through the program RdS (Research on the Electric
System), thanks to the data provided by S.MED.E. PANTELLERIA
S.p.a., the society that manages the production and distribution of
the electric energy in the island of Pantelleria.
References
[1] Cosentino V, Favuzza S, Graditi G, Ippolito MG, Massaro F, Riva Sanseverino E,
et al. Smart renewable generation for an islanded system. Technical and
economic issues of future scenarios. Energy 2012;39(1):196e204.
[2] Zhang X, Ruoshui W, Molin H, Martinot E. A study of the role played by
renewable energies in Chinas sustainable energy supply. Energy 2010;35:
4392e9.
662
[3] Blumsack S, Fernandez A. Ready or not, here comes the smart grid! Energy
2012;37:61e8.
[4] stergaard PA. Comparing electricity, heat and biogas storages impacts on
renewable energy integration. Energy 2012;37:255e62.
[5] Lund H, Andersen AN, stergaard PA, Vad Mathiesen B, Connolly D. From
electricity smart grids to smart energy systems e a market operation based
approach and understanding. Energy 2012;42:96e102.
[6] Tarroja B, Mueller F, Eichman JD, Samuelsen S. Metrics for evaluating the
impacts of intermittent renewable generation on utility load-balancing. Energy 2012;42:546e62.
[7] Lin S, Chen J. Distributed optimal power ow for smart grid transmission
system with renewable energy sources. Energy 2013;56:184e92.
[8] Deb K, Agrawal S, Pratap A, Meyarivan TA. Fast elitist non-dominated sorting
genetic algorithm for multi-objective optimization: NSGA-II. Parallel problem
solving from nature VI; 2000.
[9] Riva Sanseverino E, Ippolito MG, Zizzo G, Graditi G. Optimal set points regulation of distributed generation units in micro-grids under islanded operation.
In: Proceedings ISIE conference, Italy 2007.
[10] Campoccia A, Riva Sanseverino E, Zizzo G. Considering safety issues in minimum losses reconguration for MV distribution networks. Eur Transac Electr
Power (ETEP) 2009;19(5):642e54.
[11] Campoccia A, Dusonchet L, Telaretti E, Zizzo G. Comparative analysis of
different supporting measures for the production of electrical energy by solar
PV and wind systems: four representative European cases. Sol Energy
2009;83(3):287e97.
[12] Campoccia A, Dusonchet E, Telaretti L, Zizzo G. Financial measures for supporting wind power systems in Europe: a comparison between green tags and
feedin tariffs. In: SPEEDAM conference, Italy 2008.
[13] Fouquet D, Johansson TB. European renewable energy policy at crossroads e
focus on electricity support mechanisms. Energy Policy 2008;36:4079e92.
[14] Yamamoto Y. Pricing electricity from residential photovoltaic systems: a
comparison of feed-in tariffs, net metering, and net purchase and sale. Sol
Energy 2012;86:2678e85.
[15] Sarasa-Maestro CJ, Dufo-Lopez R, Bernal-Agustin JL. Photovoltaic remuneration policies in the European Union. Energy Policy 2013;55:317e28.
[16] Gutermuth PG. Regulatory and institutional measures by the state to enhance
the deployment of renewable energies: German experiences. Sol Energy
2000;69(3):205e13.
[17] Erge T, Hoffman VU, Kiefer K. The German experience with grid-connected
PV-systems. Sol Energy 2001;70(6):479e87.
[18] Di Dio V, Miceli R, Rando C, Zizzo G. Dynamics photovoltaic generators: technical
aspects and economical valuation. In: SPEEDAM conference, Italy 2010.
[19] Cipriani G, Di Dio V, La Manna D, Massaro F, Miceli R, Zizzo G. Economic
analysis on dynamic photovoltaic systems in new Italian feed in tariffs
context. In: ICCEP conference, Italy 2013.
[20] Dusonchet L, Graditi G, Ippolito MG, Telaretti E, Zizzo G. An optimal operating
strategy for combined RESebased generators and electric storage systems for
load shifting applications. In: Proceedings IEEE conference on power engineering, energy and electrical drives, Turkey 2013.
[21] Directive 2009/28/EC of the European Parliament and of the Council of 23
April 2009 on the promotion of the use of energy from renewable sources and
amending and subsequently repealing Directives 2001/77/EC and 2003/30/EC.
[22] Chen H, Cong TN, Yang W, Tan C, Li Y, Ding Y. Progress in electrical energy
storage system: a critical review. Prog Nat Sci 2009;19:291e312.
[23] Daz-Gonzlez F, Sumper A, Gomis-Bellmunt O, Villafla-Robles R. A review
of energy storage technologies for wind power applications. Renew Sustain
Energy Rev 2012;16:2154e71.
[24] Evans A, Strezov V, Evans TJ. Assessment of utility energy storage options for
increased renewable energy penetration. Renew Sustain Energy Rev 2012;16:
4141e7.
[25] Hittinger E, Whitacre JF, Apt J. What properties of grid energy storage are
most valuable? J Power Source 2012;206:436e49.
[26] Beaudin M, Zareipour H, Schellenberglabe A, Rosehart W. Energy storage for
mitigating the variability of renewable electricity sources: an updated review.
Energy Sustain Dev 2010;14:302e14.
[27] Nielsen TK, Bouley D. How data centre management software improves
planning and cuts operational costs. APC White Paper; 2013. p. 107.
[28] Xu Y, Singh C. Adequacy and economy analysis of distribution systems integrated with electric energy storage and renewable energy resources. IEEE
Transac Power Sys 2012;27(4):2332e41.
[29] Korpaas M, Holen AT, Hildrum R. Operation and sizing of energy storage for
wind power plants in a market system. Electr Power Energy Sys 2003;25:
599e606.
[30] Italian Standard CEI 0-16. Reference technical rules for the connection of
active and passive consumers to the HV and MV electrical networks of distribution Company.
[31] Italian Standard CEI 0-21. Reference technical rules for the connection of
active and passive consumers to the LV electrical networks of distribution
Company.
[32] Srivastava AK, Kumar AA, Schulz NN. Impact of distributed generations with
energy storage devices on the electric grid. IEEE Sys J 2012;6(1):110e7.
[33] Lund H. Renewable energy strategies for sustainable development. Energy
2007;32:912e9.
[34] Ippolito MG, Telaretti E, Zizzo G, Graditi G. A new device for the control and
the connection to the grid of combined RES-based generators and electric
storage systems. In: Proceedings ICCEP conference, Italy 2013.
[35] Yukita K, Ichiyanagi K, Goto Y, Hirose K. A study of electric power quality
using storage system in distributed generation. In: Proceeding EPQU conference, Spain 2007.
[36] Masaud TM, Lee K, Sen PK. An overview of energy storage technologies in
electric power systems: what is the future?. In: Int. Proceedings of North
American power symposium (NAPS), USA 2010.
[37] Joseph A, Shahidehpour M. Battery storage systems in electric power systems.
In: Proceedings IEEE power engineering society general meeting, USA 2006.
[38] Zhang X, Tan SC, Li G, Li J, Feng Z. Components sizing of hybrid energy systems
via the optimization of power dispatch simulations. Energy 2013;52:165e72.
[39] Lo Prete C, Hobbs BF, Norman CS, Cano-Andrade S, Fuentes A, von
Spakovsky MR, et al. Sustainability and reliability assessment of microgrids in
a regional electricity market. Energy 2012;41:192e202.
[40] Riva Sanseverino E, Di Silvestre ML, Zizzo G, Gallea R, Quang NN. A selfadapting approach for forecast-less scheduling of electrical energy storage
systems in a liberalized energy market. Energies 2013;6:5738e59.
[41] Hobbs BF, Rijkers FAM. Modeling strategic generator behavior with conjectured transmission price responses in a mixed transmission pricing systemI:
formulation. IEEE Transac Power Sys 2004;19(2):707e17.
[42] Benvindo RPJ, Cossi AM, Mantovani JRS. Multiobjective short-term planning of
electric power distribution systems using NSGA-II. J Control Auto Electr Sys
2013; April 06:1e14.
[43] Tomoiag
a B, Chindris M, Sumper A, Sudria-Andreu A, Villafala-Robles R.
Pareto optimal reconguration of power distribution systems using a Genetic
algorithm based on NSGA-II. Energies 2013;6(3):1439e55.
[44] Xianchao H, Taylor GA. Service restoration of distribution systems based on
NSGA-II. In: Universities power Engineering conference (UPEC) 2010. 45th
Aug. 31 2010-Sept. 3 2010.
[45] Buoro D, Casisi M, De Nardi A, Pinamonti P, Reini P. Multicriteria optimization
of a distributed energy supply system for an industrial area. Energy 2013;58:
128e37.
[46] Saraswat A, Saini A, Saxena AK. A novel multi-zone reactive power market
settlement model: a pareto-optimization approach. Energy 2013;51:85e100.
[47] zyna S, Temurtas H, Durmus B, Kuvat G. Charged system search algorithm
for emission constrained economic power dispatch problem. Energy 2012;46:
420e30.
[48] Zangeneh A, Jadid S, Rahimi-Kian A. A fuzzy environmental-technicaleconomic model for distributed generation planning. Energy 2011;36:
3437e45.
[49] Soroudi A. Robust optimization based self scheduling of hydro-thermal genco
in smart grids. Energy 2013;61:262e71.
[50] Kozio1 J, Czubala J. An optimisation strategy using probabilistic and heuristic
input data for fuel feeding boilers with regard to the trading effects of CO2
allowances. Energy 2013;62:82e7.
[51] Wu S, Yu Z, Feng X, Liu G, Deng C, Chu KH. Optimization of renery hydrogen
distribution systems considering the number of compressors. Energy
2013;62:185e95.
[52] Graditi G, Ippolito MG, Riva Sanseverino E, Zizzo G. Robust multi-objective
optimal dispatch of distributed energy resources in micro-grids. In: Proceedings IEEE power tech 2011.
[53] JRC European Commission. Photovoltaic Geographical Information system
(PVGIS). Available at: http://re.jrc.ec.europa.eu/pvgis.