IQA for USAIDs Stabilization Program Activities in FATA and KP

Quality Assurance Plan - Annexure G

Annexure G

Quality Assurance Tests

Protocols to be followed with Construction Contractor (FWO) Staff


At present the construction contractor has set up material testing laboratories at Hathala on DIK-Tank
road, at Wana on Wana Shakai Makin road and at Miranshah on Bannu Miranshah Ghulam Khan
road. The laboratories are fully equipped to perform tests to ascertain the quality of road construction
materials for all components of road/bridges. HPK is in the process of setting up its material testing
laboratory in D.I. Khan and Bannu with USAID provided equipment to carry out independent
testing. Certain tests have to be performed at approved outsourced laboratories where such testing
facilities are not available at Construction Contractor or HPK laboratories. The following is expected
to be the distribution of testing which will be practiced in the field and laboratories. HPK staff will
collect samples during their field visits/inspections and conduct the tests at established frequency at
Construction Contractor, HPK and approved outsourced laboratories for the systematic monitoring to
ensure that the product is meeting the requirements that have been established for quality checks.
Non-destructive tests will be carried out on site. This will include the Schmidt Hammer and Ultra
pulse velocity tests where required.

30 April 2015

(1)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

Procedure for verifying the quality of material and works (Roads)

IQA Staff to coordinate with construction


contractor with respect to defined milestones to
facilitate visits by QA Monitors/Supervisor.

Co-ordination with construction contractor


on construction program

QA Monitors to check against design data


Checking 5 X-section/Km
Soil Classification1 per 5 Km or as / when required.
Compaction/FDT 2/km
CBR 1 per 10 km & Site Photos
(BASELINE MEASURE)

Earthworks- Removal of excess soil and


debris and the preparation of sub grade
for sub base laying.

Granular Sub Base and Agg. Base course


Selected inert well graded material to
form a level.

QA Monitors to undertake & record


Thickness Check
Sieve Analysis
required
Proctor Test
FDT/Compaction Test
required
CBR, Sand Equivalent
Los Angeles Abrasion value

Prime Coat- Mixture of Bitumen &


Kerosene to keep base course intact.

30 April 2015

1 per km
3/km or as
1 per 5Km
1 per 5Km

QA Monitors to undertake & record


Specification Check (i-e) wt/Area 1 per 3 Km

QA Monitors to ensure
Gradation of Aggregate
Thickness
Extraction Test
Sampling for stability

Wearing Course- Mixture of Bitumen, Fine


& coarse aggregate/ Asphalt.

Key Outputs during Construction:


Field Inspection Form
Bi weekly
Monthly Report

5/km
1 per 3 km or as

- Three copies
- Generated from South Office
- Generated by QA Manager

(2)

1 per Km
5 per Km
1 per 5Km
2 per Km

- (DI Khan)
- (Peshawar)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

Procedure for verifying the quality of material and works (Buildings)

Co-ordination with construction


contractor on construction
program

Foundation upto Plinth


level

Upto Walls bands


beams level

IQA Staff to coordinate with construction contractors with respect to


defined milestones to facilitate visits by QA Monitors/Supervisor.

QA Monitors to check against design data:


Width and depth of foundation 4 per building
Bearing capacity
1 for Foundations
Concrete Compressive Strength 1 Set for each grade of concrete
Reinforcement steel
Complete Physical tests for each size
of bar from stock.
Bricks/Blocks Strength
5 Bricks/ 10,000 or change of source /
as & when required.

QA Monitors to check against design data:


Bricks/Blocks Strength
5 Bricks/ 10,000
4 Blocks per 10,000
Masonry Mortar Ratio verification
Compressive strength as per requirement
Concrete Compressive Strength
1 Set for each grade of concrete for each part
of structure.
Reinforcement steel

Upto roof slab level

Finishing/Completion
Level

Complete Physical tests for each size of bar


from stock.

QA Monitors to ensure:
Thickness of slab, concrete cover to Reinforcement
Concrete Compressive Strength
1 Set for each grade of concrete
Reinforcement steel
Complete Physical tests for each size of
bar from stock

QA Monitors to ensure;
Surface Finishing, Painting, Joinery and Electrification works.

Key Outputs during Construction:


Field Inspection Form
- Three copies
Bi weekly
- Generated from North Office - (Swat)
Monthly Report
- Generated by QA Manager
- (Peshawar)

30 April 2015

(3)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

Proposed IQA Process (Power Sector)


Pre-construction Process (Power)

Master Design program.


Master Construction Program

IQA Team to review all documentation.


Review shall include checks on Design
standards adopted, Cost estimates,
Construction drawings and Specifications
meet the regulatory requirements. The
IQA process shall be based on the
detailed Construction program with
regard to a key performance indicator
been linked to the percentage completion
of the works. The construction schedule
shall form the baseline measure.
(BASELINE & OPERATIONAL
MEASURE)

Procurement program.
Information release schedules

(2)Soil Investigations.
(3)Design Basis & Standards.
(4)Detailed Construction Drawings.
(5)Final Bills of Quantities
(6)Final Cost Estimates & PC-1
(7)Final Technical Specifications
(8)Phase 1 Scope of works

Testing/Inspection of material in
manufacturing premises C.E design
NTDC/C.E M.I PEPCO and witnessed
by IQA Representatives.

QA Monitors/supervisor will be deployed to


ascertain the As is situation prior to
construction. Data collection shall include:
1. Existing distribution lines & conditions
2. Existing Grid stations & Conditions

KEY OUTPUTS:
A pre-construction as is report (attached) that
shall form a fundamental part of the Baseline
Measure.

30 April 2015

(4)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

Procedure for verifying the quality of material and works Grid station & Transmission Lines
(Power)

IQA Staff to coordinate with construction contractor/


FATA Secretariat with respect to defined milestones to
facilitate visits by QA Monitors/Supervisor.

Co-ordination with Construction contractor


on construction program

QA Monitor/Supervisor to check the work against the


approved drawings and start on site.
( BASELINE MEASURE)

Earthworks- Removal of excess soil and


debris and the preparation for sub base
laying for foundation.

QA Monitor/Supervisor & QA Manager to check


the Material Schedule, prior to order placement.

Electrical Material procurement Schedule

Material Placement of shipping order


(Approved by Design NTDC/Material
Inspection PEPCO

QA Monitor/Supervisor to check the date of order


placement.

QA Monitor/Supervisor to check and witness


Material Type against original order placement.
QA Monitor to check the Inspection Certificate.

Receipt of Material on site.

QA Monitors/Supervisor to check that the Electrical


Materials been Installed on site as per the approved
drawings & Certifications by (Chief Engineer
Design (NTDC) PEPCO Lahore).

Installation on site

Testing & Commissioning

Key Outputs during Construction:


Field Inspection Form
Bi weekly Progress Report
Monthly Progress Report

30 April 2015

- Three copies
- Generated from South & North Office (DIK and Swat)
- Generated by QA Manager
- (Peshawar)

(5)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

Procedure for verifying the quality of material and works (Grid Station)

IQA Staff to coordinate with construction contractor /


FATA Secretariat with respect to defined milestones to
facilitate visits by QA Monitors/Supervisor.

Co-ordination with Construction contractor


on construction program

QA Monitors/Supervisor to check the work against the


approved drawings and undertake independent level and
geometrical checks.
(BASELINE MEASURE)

Possession of Site. Site survey check. Soil


Testing, Levelling

Excavation of main unit Foundations.


Excavation of Power Transformer Foundations
Excavation of Cable laying foundations.

QA Monitors/Supervisor to check depth of


excavations arrange soil sample for testing at DIK
Peshawar University

Installation of Power Transformer


Installation of Current Transformer
Installation of potential Transformer

QA Monitors/Supervisor to check Transformer


types against specifications and drawings.

Installation of remaining proprietary


elements

QA Monitor/Supervisor to check remaining


electrical components against certifications.

Laying of control & Power Cables


Laying of 132kV Bus Bar

Connecting all equipments in the switchyard


QA Monitors/Supervisor to check that the
Electrical Materials been Installed on site as per the
approved drawings & Certifications and carry out
independent verifications & testing.

Testing and earthing of all equipment

Key Outputs during Construction:


Field Inspection Form
Bi weekly Progress Report
Monthly Progress Report

30 April 2015

- Three copies
- Generated from South & North Office (DIK and Swat)
- Generated by QA Manager
(Peshawar)

(6)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

Procedure for verifying the quality of material and works (Transmission Line)

Coordination with Construction


contractor on construction program.

Possession of site. Site survey check


Soil testing leveling

Excavation of tower foundation and


concreting of stubs

IQA Staff to coordinate with construction


contractor/ FATA Secretariat with respect to
defined milestones to facilitate visits by QA
Monitors/Supervisor.

QA Monitors/Supervisor to check the work


against the approved drawings and
undertake independent level and geometrical
checks

QA Monitors/Supervisor to check the depth


of excavations arrange soil sample for
testing at DIK/Peshawar University

Erection of towers

Laying/sagging of conductor on
towers

QA Monitors/Supervisor to check electrical


components of transmission line against
specifications.

Jump ring and installation of


dampers

Testing/commission of transmission
line

Key Outputs during Construction:


Field Inspection Form
Bi weekly
Progress
30 April
2015 Report
Monthly Progress Report

QA Monitors/Supervisor to check that the


Electrical Material been installed on site as
per the approved drawings & Certifications
and carry out independent verification &
Testing.

- Three copies
- Generated from
Swat) Pakistan
(7) South & North Office - (DIK andHalcrow
- Generated by QA Manager
- (Peshawar)

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

Procedure for verifying the quality of material and works (Rehabilitation 11kV/33kV)

IQA Staff to coordinate with construction


contractor (FWO) with respect to defined
milestones to facilitate visits by QA
Monitors/Supervisor.

Co-ordination with construction


contractor on Construction Program

Site survey and dismantle/Removal of


damaged items.

QA Monitors/Supervisor to check the work


against the approved drawings and
undertake independent level and
geometrical checks

Possession of site and


excavation/Concreting of HT/LT pole
foundations.

QA Monitors/Supervisor to check depth of


excavations arrange soil sample for testing
at DIK/Peshawar University

Installation of transformers and


remaining proprietary elements.

QA Monitors/Supervisor to check
transformer types against specifications and
drawings.

Connecting/Jumpering of transformers
and conductors.

QA Monitors/Supervisor to check
remaining electrical components against
certifications.

Earthing/Testing and energization of all


equipments.

Key Outputs during Construction:


Field Inspection Form
Bi weekly Progress Report
Monthly Progress Report

30 April 2015

QA Monitors/Supervisor to check that the


Electrical Materials been installed on site
as per the approved drawings &
Certifications and carry out independent
verifications & testing

- Three copies
- Generated from South & North Office - (DIK and Swat)
- Generated by QA Manager
- (Peshawar)

(8)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

Non Compliance Monitoring Process

QA Field Monitor identifies non-compliance either in


Design or Construction. Non-compliance is noted in
Field Inspection form.
(BASELINE MEASURE)

Ongoing construction

QA Monitors re-checks the rectified work.

Filed Offices
QA Monitors verbally informs and hands over a
copy of Field Inspection form to QA Engineer. QA
Engineer reports to QA Manager.

Instruction given to site and remedial works


carried out

PESHAWAR PROJECT OFFICE


QA Manager reviews report & analyses the noncompliance and forwards to construction
contractor and COP.

CONSTRUCTION CONTRACTORS
Construction Contractor receives written
instruction from USAID/Clients for
rectification.

USAID COR
USAID initiates instruction to FATA
Secretariat / PaRRSA and informs clients
rectification of defects.

30 April 2015

PESHAWAR PROJECT OFFICE


COP checks non-compliance report for onward
submission to USAID COR.

(9)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

G-1

QA Tests for Roads


Specified Tests

Frequency
Proctor test
Sieve analysis

Earth works

FDT

CBR

to be done in site lab (1 per 5 Km or as required)


to be done in site lab (1 per 10 Km)

Proctor test

to be done in site lab ( I per Km)

Sieve analysis

to be done in site lab ( I per 3 Km)

FDT

to be done in site lab ( 3 per Km)

CBR, Sand
equivalent

to be done in site lab (1 per 10Km or as required)

Los Angeles
abrasion value

to be done in site lab if equipment is available (1


test for 10 Km or as required)

Grade of
bitumen

Min 1 test for one road project

Sampling for
stability

one sample per 5 Km.

Gradation of
aggregates

as above

Spray rate
Bitumen / Asphalt

to be done in site lab ( I per 5 Km or as required)


2 per KM

Soil
Classification

Granular Subbase & Agg. Base


course

to be done in site lab ( I per 5 Km)

Temperature

For each work day


During each work day

Soundness test of to be done in site lab if equipment is available (1 ~


aggregates
2 tests for each road project)

30 April 2015

Los Angeles
abrasion value

to be done in site lab if equipment is available (1 ~


2 tests for each source of material)

Coring from
pavement for
thickness and
compaction

Four samples per km

(10)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

Specified Tests

Frequency
Compressive
Strength
(Cylinder)

Concrete

After 10 , 30 & 50 Cu.m for column, wall and large


pours or minimum one set for each grade of
concrete as and when required.

Slump Test
Hourly
Bricks

Strength,
5 bricks / 10,000
Absorption, Size

Blocks
Strength,
4 blocks / 10,000
Absorption, Size
Masonry Mortar
Compressive
Strength
Steel

From plaster/brick laying, Monthly

Complete
For each size of bar from source / shipment.
physical test
(Bend,
elongation%,
yield & Ultimate
strength)

Structures
X-drainage (Culvert/Cause way)
B/walls
R/walls
Side drain
Gabions / Protection works
Pavement Marking / studs
Sign boards
Guard Rail

Foundation
checking
(Ht & Width)
Masonry work
measurement

3 per Km
2 per Km.
2 per Km
3 per Km
2 per each location

Design
conformity /
specification

02 Location per km
Every 10th sign board
Every 5th Guard Rail

Location of Laboratories for Testing


Component

Tests

Conducted by

Laboratory

Proctor test

Halcrow/Constr
uction
Contractor joint

Construction
Contractor

Sieve Analysis

Halcrow/
Construction
Contractor joint

Construction
Contractor
/Halcrow

Earth Work

30 April 2015

(11)

Field

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

FDT

Halcrow/
Construction
Contractor joint

Field

Classification

Halcrow/
Construction
Contractor joint

Field

CBR

Halcrow/
Construction
Contractor joint

Construction
Contractor
/Halcrow

Proctor test

Halcrow/
Construction
Contractor joint

Construction
Contractor

Sieve Analysis

Halcrow/
Construction
Contractor joint

Construction
Contractor
/Halcrow

FDT

Halcrow/
Construction
Contractor joint

CBR, Sand
equivalent

Halcrow/
Construction
Contractor joint

FWO/Halcrow

Los Angeles
Abrasion value

Halcrow/
Construction
Contractor joint

Construction
Contractor Lab

Grade of
Bitumen

UET
Peshawar/Taxila

Out Source Lab

Sampling for
Stability

Halcrow/
Construction
Contractor joint

Construction
Contractor
/Halcrow

Gradation of
Aggregates

Halcrow/
Construction
Contractor joint

Construction
Contractor
/Halcrow

Spray rates

Halcrow/
Construction
Contractor joint

Field

Temperature

Halcrow

Field

Soundness test
of aggregate

Halcrow/
Construction
Contractor joint

Construction
Contractor Lab

Los Angeles
abrasion value

Halcrow/
Construction
Contractor joint

Construction
Contractor Lab

Coring from
pavement for

Halcrow/
Construction
Contractor Joint

Granular Sub-base &


Aggregate. Base course

Bitumen Asphalt

30 April 2015

(12)

Field

Field

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

thickness &
compaction

Concrete

Steel

Compressive
Strength
(Cylinder
/Cube)

Halcrow/
Construction
Contractor joint

Slump test

Halcrow

Strength,
Absorption
(Bricks)

Halcrow/
Construction
Contractor joint

Size (Bricks)

Halcrow/
Construction
Contractor joint

Strength,
Absorption
(Blocks)

Halcrow/
Construction
Contractor joint

Size (Blocks)

Halcrow/
Construction
Contractor joint

Compressive
Strength of
masonry mortar

Halcrow/
Construction
Contractor joint

Complete
Physical test (%
elongation,
bend, yield and
ultimate
strength)

Construction
Contractor /Out
Source
Field
Construction
Contractor /Out
Source
Field
Construction
Contractor /Out
Source
Field
Construction
Contractor /Out
Source

Out Source Lab

In addition the job mix formula for asphalt concrete will be carried out jointly at the Construction
Contractor laboratory. The tests related to the mix design will be supervised jointly and approved by
the material engineer/technician of Construction Contractor and Halcrow.
The concrete mix design if required by the specification will be conducted jointly by the Halcrow and
Construction Contractor staff and approved by the material engineer/technicians.
If in case the material tested at the different laboratories yield results which differ in respect of
meeting the specification then, it is recommended to jointly test the material to arrive at a conclusion
of either accepting or rejecting the material.
It is highly recommended to conduct the field test by Halcrow jointly with Construction Contractor
staff.
It will be difficult at this stage to ascertain the exact percentage of testing to be carried out at
Halcrow or Construction Contractor and outsource laboratories as Halcrow will mostly be spot
checking the test in the field and at the laboratory. It is envisaged that about 25% of the testing
should be carried out independently at the Halcrow laboratories.
30 April 2015

(13)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

G-2

QA Tests for Buildings and Other Works

The works being executed in the North region (Malakand) shall be controlled from Swat office
and a central laboratory established at Swat.
Material

Test

Test Method

Frequency

Soil
Soil and graded materials

Classification
MDD
Field Density
Moisture content
Gradation
Plasticity Index
Bearing Capacity

AASHTO M-145
AASHTO T-180
AASHTO T-191
ASTM C-566
ASTM C-136
AASHTO T-90
ASTM D1194

As per
requirement
As per
requirement
As per
requirement
As per
requirement
As per
requirement
As per
requirement
Once for
foundations

Coarse Aggregate

Gradation
Water Absorption & Sp.Gr.
L. A. Abrasion
Soundness (Na2So4)
Flat & Elongated particles
Clay lumps & Friable part.
Unit Weight
Material finer # 200 sieve

ASTM C-136
ASTM C-127
ASTM C-131
ASTM C-88
ASTM D-4791
ASTM C-142
ASTM C-29
ASTM C-117

From built
stock as per
requirement
Monthly
As per
requirement
After 3months
Monthly
As per
requirement
As per
requirement
As per
requirement

Fine Aggregate

30 April 2015

Gradation with F.M.


Water Absorption & Sp.Gr.
Organic Impurities
Unit Weight
Material finer # 200 sieve

(14)

ASTM C-131
ASTM C-128
ASTM C-40
ASTM C-29
ASTM C-117

From built
stock as per
requirement
Monthly
As per
requirement
As per
requirement
As per
requirement

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

Material
Concrete

Clay Bricks
Blocks

Test

Test Method

Compressive Strength
(Cylinder)

ASTM C-39

Slump Test
Strength, Absorption, Size
Strength, Absorption, Size
Compressive Strength

ASTM C-143
ASTM C-67
ASTM C-140
ASTM C-109

Masonry Mortar

Frequency
After 5, 10 ,
30 & 50 Cu.m
for column,
wall and
large pours or
minimum one
set for each
grade of
concrete or as
required.
During
concreting (as
required)
5 bricks /
10,000
4 blocks /
10,000
From plaster
or brick
laying,
Monthly

Water

Chlorides, Sulphates,
pH.,TDS

AASHTO T-26

once for
source

Cement

Physical tests

ASTM C-150

(Mill Test
certificate)

Reinforcement steel

Complete physical tests


(bend, % elongation, yield
and ultimate strengths)

ASTM A-615

For each size


of bar from
source.

Piping works

Pressure test
Leakage test

ASTM C-828
ASTM C-828

As per
requirement
As per
requirement

Electric cables

30 April 2015

Specify testing and


commissioning

(15)

For each
source / as
per
requirement

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

G-3

QA

Tests for Power

11kV / 33kV Distribution Systems


Material

Specified Routine Lab Tests


a) Complete structures

HT and LT Structure

Rabbit Conductor
ACSR , Al-Aluminum
Conductor ACC and
GSL Wire

Frequency
Once before pre
shipment from
Manufacture Premises

Verification of dimensions, weights and


Transverse load test.
b) On members

-do-

Tensile strength Test , Elongation Test , Bend Test


, Embrittlement Test , Hardness Test and Yield
Strength Test.
c) Galvanizing

-do-

Weight , uniformity and Adherence of zinc


coating
a) Aluminum

-do-

Verification of Diameter, Weight, Breaking load of


single strand, Tensile strength, Resistivity test,
Wrapping and DCR of single wire and complete
strand.
b) Steel (For ACSR Only)

-do-

Verification of Diameter, Tensile strength,


Elongation, Wrapping, Lay Ratio Test Adherence,
Uniformity and Adherence of Zn coating.
c) Complete conductor

-do-

Breaking load and unit weight

-do-

-do-

-do-

-do-do-

d) Transformer oil tests

Transformers 11 and 33
/ 0.415kV
25, 50 , 100 and 200
KVA

Steel cross arm ,Pin


steel , Tension Clamp ,

30 April 2015

Checking Specific gravity, Viscosity, Flash Point,


Acidity value, Dielectric Strength and Pour Point.

-do-

e) Routine tests
Polarity and Phase relationship, Load and No
Load test, Losses test, Induced voltage test and
over voltage withstand test, Tank pressure test,
Bird test and Paint thickness test, Turn Ratio and
Transformer resistance test.

-do-

Verification of dimension and weight, Tensile Test


and Yield Strength, Elongation and Embrittlement

-do-

(16)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

Eye Nut , D-Shackle ,


Earthling Unit , Stay
Rod , PG Connector ,
Misc Material.

test. Mechanical Test: (Lead should not loose or


separate at 1000Kg load.)
a) Galvanizing

-do-

Weight of Zn, uniformity, Adherence and bend


test.

-do-

Compressive Strength (Cylinder)


Concrete
Gradation of Course and Fine Aggregate

G-4

1 test per 5 HT and LT


foundations.
As per requirement

132kV Transmission Line


Material

Specified Routine Lab Tests


Verification of weights ,UTS ,Elongation ,Bend
test , chemical analysis test ,Embrittlement ,
Yield Strength and Thermal Shock Test.

Frequency
Once before pre shipment
from Manufacture
Premises.

Galvanizing
Thickness , weight and uniformity of zinc
coating and Impact Test.
ACSR Lynx Conductor
and 9mm Earthwire

Dimension , weight , TST , Lay ratio , DCR of


single and complete ,breaking load test,
wrapping test, Elongation ,Weight , adherence
and uniformity of Zn coating.

-do-

Dimensional test, Temperature cycle,


Mechanical breaking, Porosity, Galvanizing, Oil
puncture voltage and operation test.

-do-

Hardware
(ST-L , SF-9, MS-9 , SB
vibration Dampers , PG
Clamp and Misc)

Breaking Load, Elongation, unit weight,


verification of dimensions, TST, Galvanizing test
and Zn coating thickness.

-do-

Tower Footing
Resistance

Measuring tower footing Resistance TFR

Disc Insulators

Compressive Strength (Cylinder /cube)


Concrete

30 April 2015

Checking earth resistance


of each Tower.
1 test per 5 Tower

Gradation of Coarse and Fine Aggregate

As per requirement

Slump test

As per requirement

(17)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

G-5

132kV Grid Station

Material

Specified Routine Lab Tests

Frequency

a) On Power Transformer

Power Transformer with


Auxiliary control panel

Measurement of insulation resistance of


windings , Voltage ratio and phase
displacement , winding resistance (HV &
LV) , Capacitance and Dissipation factor of
insulation of T/F and bushings ,No load loss
& current , short circuit impedance & load
loss (ONAN&ONAF) , separate source
voltage withstand test, induced over-voltage
withstand test & measurement of partial
discharge , OLTC functional tests AND
lightning impulse voltage withstand test.
a) Oil Tests

Once before pre


shipment from
Manufacture
Premises.

Viscosity, Pour point, acidity value, Moisture


content, Dielectric Dissipation factor,
Interfacial tension and dielectric strength.
b) Auxiliary Control Panel Functional Tests
11KV Switchgear Panels
(Incoming, Outgoing, Bus
Coupler & Capacitor Bank Panel)

AC/DC Auxiliary Panel


Line Control Panel CP-30
Transformer Control Panel CP-50

I. Line Relay Panel RP-3


II. Transformer Relay Panel RP-4
30 April 2015

Visual Inspection & Dimensions,


Electrical operation tests, (Ampere,
voltage, Pf, Energy meter), Indication
Lights, Push buttons, continuity of earth.
Trip Circuit Supervision, O/C, S/C, E/F,
Back up E/F, Capacitor Un-balanced
protection, under & over voltage Relays.
Load break switches Mechanical
performance, Mechanical Interlocking.
Power frequency withstand Voltage test
(Auxiliary circuit) 2KV for one minute to
Auxiliary circuit.
Power frequency withstand Voltage test
(Main circuit) 36KV for one minute to
Main Circuit
Insulation test of VCB Vacuum Tube and
resistance of Main circuit and
Verification of Interchangeability of
Components & Mechanical operation
test.

-do-

Applied 2KV across Auxiliary Circuit for 1


minute, General and functional Tests on AC
and DC portion

-do-

Applied 2KV across Auxiliary Circuit for 1


minute, General Tests, Functional Tests on
Panel, Functional Tests on Tripping &

-do-

(18)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

Supervision, Distance Relay, O/C & E/F


Relays.
95 mm Copper Conductor,
Al-Aluminum Conductor 600
mm
Earth wire 7/3 (9mm Dia)

Measuring Diameter , Breaking Load ,


Elongation , Lay ratio , Resistance and Unit
weight , TST , Zinc coating ,Uniformity , and
adherence.

-do-

Thickness of insulation, sheath, Diameter of


single wire, elongation of conductor, TST and
elongation of PVC sheath and insulation
before and after ageing.
Hot deformation of PVC insulation and
sheath.
Heat Shock, cold bend test, Color fastness
test, Resistance to burning test, Water
absorption and loss of mass for a PVC
insulation/sheath.
Insulation resistance, copper tape resistance
and DC resistance of copper conductor.

-do-

120mm 3 core power cables


500mm Single core Power cables

Verification of dimensions, power frequency


voltage test Conductor resistance test , Heat
Shock test , Behavior of low temperature test,
Flame test, Heat deformation of PVC sheath ,
DC resistance of copper conductor ,
Resistivity of semi conducting screens

-do-

Battery charger

Visual inspection , Dielectric strength test ,


Properties of smoothing circuit , Checking of
protective devices , Properties of current
limiter , Noise level test and Checking of
alarms

-do-

12 m Beam
13.1 m Column
13.1 m Earth Mast

Yield load, Breaking load , Yield stress


Ultimate stress , Elongation, Bend test

-do-

Average speed of opening and closing,


Opening and closing synchronism between
plates, closing & Opening time.

-do-

I. 2.5mm 4 core control cables


II. 2.5mm 8 core control cables
III. 2.5mm 16 core control
cables
IV. 6mm2 4 core control cables

11kV Structure 4m Long and


substation connectors.

I. 132kV Circuit Breaker


II. 132kV Line / Bus
Disconnector

Mechanical Operation Test


Switching Operation opening and closing
voltage. Motor charging time and normal
working voltage.

30 April 2015

(19)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

Dielectric test of main circuit, Aux & control


circuit.
Alarm and Lock pressure of SF6 gas.
132kV Surge Arrestor

Residual voltage test at nominal discharge


current , Power frequency reference voltage
test ,Partial discharge test and Verification of
Terminal Markings

-do-

132kV Transformer
Current Transformer and 132kV
Line Current Transformer.

Measurement of Capacitance and dielectric


dissipation factor ,Test of short-time power
frequency withstand voltage,
Partial discharge measurement(B)

-do-

a)

Error Test
Error of Metering /Protection
Winding

Ratio Error
Phase Displacement Error
132kV Voltage Transformer

Verification of Terminal Markings ,


Measurement of DC resistance ,
Measurement of capacitance and dielectric
dissipation factor , Induced withstand
voltage test , Measurement of Excitation and
Partial discharge measurement

To be performed in
the Manufacture
Lab

Concrete

Compressive Strength (Cylinder)

After 5, 10, 30 & 50


Cu.m for column,
wall and large
pours or minimum
one set for each
grade or as
required.

Gradation of Course and Fine Aggregate

As per requirement

Slump Test

During concreting
(As per
requirement)

Masonry Mortar

Compressive Strength

Cement

Physical Test

Bricks / Blocks

Water Absorption , size , Compressive


strength

Reinforcement steel

Complete physical tests (bend, % elongation,


yield and ultimate strengths)

30 April 2015

(20)

Plaster or Brick
laying (As per
requirement)
Mill Test certificate
5 bricks / 10,000
4 blocks / 10,000
For each size of bar
from source.

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

G6 Water (Irrigation/Dams)
Specified Tests

Frequency
X-Sect

3 No.

Soil
Earth works
3 Nos.
Classification
(Excavation of foundations and abutments)
Concrete
3 Nos.
Tests
Foundation
treatment & grouting
Embankment completion in layers from
bottom to crest

Spillway & intake Structure

Irrigation Channels

30 April 2015

Concrete
Test

3 Nos.

Compaction

3Nos per Meter of compacted fill

Thickness

3Nos per Meter of compacted fill

Gradation

3Nos per Meter of compacted fill

Soil
Classification

3 Nos per structure

Concrete

After 5, 10, 30 & 50 Cu.m for column, wall


and large pours or minimum one set for
each grade or as required.

Masonry

03 Nos. per 5m

X Section

03 Nos. per km

Concrete

After 5, 10, 30 & 50 Cu.m for column, wall


and large pours or minimum one set for
each grade or as required.

(21)

Halcrow Pakistan

IQA for USAIDs Stabilization Program Activities in FATA and KP


Quality Assurance Plan - Annexure G

30 April 2015

(22)