Вы находитесь на странице: 1из 3

Federal Register / Vol. 70, No.

206 / Wednesday, October 26, 2005 / Notices 61781

by the courts. City of Angoon v. Hodel, DATES: Comments concerning the scope Purpose and Need for Action
803 F.2d 1016, 1022 (9th Cir. 1986) and of the analysis must be received by The purpose of the proposed action is
Wisconsin Heritages, Inc. v. Harris, 490 November 28, 2005. The draft to bring the Hunter Reservoir dam into
F. Supp. 1334, 1338 (E.D. Wis. 1980). environmental impact statement is compliance with Colorado Dam Safety
Because of these court rulings, it is very expected in March 2006 and the final requirements and to enlarge the storage
important that those interested in this environmental impact statement is capacity of the reservoir so that UWCD
proposed action participate by the close expected in September 2006. can make beneficial use of its existing
of the 45-day comment period so that ADDRESSES: Send written comments to and conditional water rights in the Leon
substantive comments and objections Hunter Reservoir Project, Grand Valley Creek drainage basin.
are made available to the Forest Service Ranger district, 2777 Crossroads Blvd, The need for this combined action is
at a time when it can meaningfully Unit 1, Grand Junction, Colorado 81506. to afford UWCD the ability to address
consider them and respond to them in both the dam safety and water right use
FOR FURTHER INFORMATION CONTACT:
the final supplemental environmental aspects of their water facilities
impact statement. Carrie Surber, Team leader at
csurber@fs.fed.us or (970) 242–8211. management and responsibilities in a
To assist the Forest Service in manner that is environmentally,
identifying and considering issues and SUPPLEMENTARY INFORMATION: Ute Water
economically, and technically sound.
concerns on the proposed action, Conservancy District (UWCD) has
The dam safety issues at Hunter
comments on the draft EIS should be as decreed water rights for 110 acre-feet
Reservoir go back as far as 1964 when
specific as possible. It is also helpful if (AF) of storage in Hunter Reservoir
state inspection reports began to
comments refer to specific pages or located near the headwaters of Leon
identify safety concerns at the existing
chapters of the draft statement. Creek. Leon Creek is located on the
dam. These 1964 concerns and others
Comments may also address the northern slopes of the Grand Mesa, a
have continued to worsen to the extent
adequacy of the draft environmental prominent geologic feature in Mesa,
that actions to rectify dam safety
impact statement or the merits of the Delta and Gunnison Counties in western
problems must be addressed by UWCD
alternatives formulated and discussed in Colorado. The Hunter Reservoir project
to continue operations at Hunter
the statement. Reviewers may wish to location is located approximately 11
Reservoir.
refer to the Council on Environmental miles south of Vega Reservoir in Section UWCD needs include providing a
Quality Regulations for implementing 27, T. 11 S., R. 93 W. Sixth Principle continued supply of water to meet the
the procedural provisions of the Meridian, Mesa County, Colorado. public needs for a service area that is
National Environmental Policy Act at 40 UWCD also has conditional rights to experiencing continued and rapid
CFR 1503.3 in addressing these points. store 582.5 AF more water at the Hunter growth. As a public utility, UWCD has
Comments received, including the Reservoir location. In addition to the a responsibility to operate and manage
names and addresses of those who Hunter Reservoir water rights, UWCD its facilities with respect to feature
comment, will be considered part of the have conditional water rights for 5,650 demand with sound environmental and
public record on this proposed and will AF of storage at a Big Park site, also in economic management.
be available for public inspection. the Leon Creek drainage basin This proposed action will also meet
Authority: 40 CFR 1501.7 and 1508.22; downstream of Hunter Reservoir. UWCD the intent of the 2004 Memorandum of
Forest Service Handbook 1909.15, Section has determined that a new dam at the Understanding (MOU) between the
21. Big Park site would not be economically Rocky Mountain Region of the Forest
Dated: October 20, 2005. feasible for the volume of water they Service and the State of Colorado,
John D. Berry, would be allowed to store. UWCD which states, in part, that the State and
Forest Supervisor. desires to perfect its Big Park Forest Service agree to explore creative
conditional water rights at the Hunter ways to assure continued operation of
[FR Doc. 05–21340 Filed 10–25–05; 8:45 am]
Reservoir location by enlarging the water use facilities on NFS lands while
BILLING CODE 3410–11–M
existing dam and reservoir. protecting aquatic resources, that
Irrespective of UWCD’s storage and conflicts are best avoided by careful
DEPARTMENT OF AGRICULTURE conditional water right desires, the advance planning and a spirit of
Colorado Dam Safety Engineer is cooperation, and that reauthorization of
Forest Service requiring UWCD to make structural existing water facilities will be done in
improvements to the existing Hunter cooperation and collaboration with the
Rocky Mountain Region; Grand Mesa, Reservoir dam in order to keep using holders of the permits and with other
Uncompahgre and Gunnison National that facility to store water. parties such as local governments,
Forest; Mesa County, CO; Hunter UWCD would like to address both of tribes, and state and federal agencies, as
Reservoir Expansion Project these aspects of their water facility’s appropriate.
AGENCY: Forest Service, USDA. management and responsibilities by
enlarging the dam at Hunter Reservoir to Proposed Action
ACTION:Notice of intent to prepare an
environmental impact statement. both rectify dam safety concerns and The proposed action is to authorize
put their conditional water rights to Ute Water Conservancy District (UWCD)
SUMMARY: In order to provide additional beneficial use. to enlarge Hunter Reservoir and
water storage capacity for a growing The U.S.D.A Forest Service and the rehabilitate the dam to address safety
population in the Grand Junction Area, Army Corps of Engineers, as a requested issues. The construction necessary to
Ute Water Conservancy District (UWCD) cooperating agency, will prepare an accomplish these actions is expected to
is proposing to enlarge Hunter Reservoir Environmental Impact Statement (EIS) take two summer seasons due to the
while also addressing dam safety issues. addressing the environmental high elevation of the Hunter Reservoir
The existing reservoir is 16 surface consequences associated with site. UWCD would like to begin
acres. The proposed expanded reservoir rehabilitating the dam and enlarging the construction in the summer of 2007 and
would be approximately 80 surface reservoir at the Hunter Reservoir anticipates completion at the end of the
acres. location. summer in 2008.

VerDate Aug<31>2005 16:26 Oct 25, 2005 Jkt 208001 PO 00000 Frm 00005 Fmt 4703 Sfmt 4703 E:\FR\FM\26OCN1.SGM 26OCN1
61782 Federal Register / Vol. 70, No. 206 / Wednesday, October 26, 2005 / Notices

Dam reconstruction will be done by Lead and Cooperating Agencies acres of wetlands, 6 acres of littoral
raising the dam height to 26 feet, Lead Agency—USDA, Forest Service, zone, and 14 acres of existing
installing new outlet works, widening Grand Mesa , Uncompahgre and unvegetated reservoir bottom. The total
the crest of the dam, install new service Gunnison National Forest. acres of wetlands to be inundated are
and emergency spillways, rock rip- Cooperating Agency—U.S. Army about 38 acres. Some of these wetlands
rapping the dam embankments, and Corps of Engineers, Sacramento District, have the characteristics of peat forming
installing a seepage curtain at the foot Colorado/Gunnison Basin Regional wetlands, which could be fens. Fens in
of the dam toe. These actions would Office has been requested to participate these southern regions of the Rocky
increase storage capacity, improve flood as a cooperating agency. Mountains are considered rare and
surge capacity, and eliminate fill unique because of the plant
instability. These actions are expected Responsible Official communities often associated with such
to bring the reservoir into compliance The Responsible Official is Charles wetlands.
with the Colorado State Engineer’s Richmond, Forest Supervisor, Grand Soils and Water Resources: The access
Office for dam safety requirements. Mesa, Uncompahgre, and Gunnison road will require grading, leveling and
Road improvements would be needed National Forests, 2250 South Highway has 28 stream or wetland crossings.
on Forest Roads 262 and 280 to facilitate 50, Delta, Colorado 81416. Leon Creek would be diverted during
access by construction crews and to Nature of Decision To Be Made dam reconstruction activities and there
bring materials to the construction site. would be temporary increases in
Given the purpose and need, the sedimentation and erosion downstream
Both FR 262 and 280 are high-clearance Forest Supervisor will review the
roads not designed for passenger car in Leon Creek. On-site soils would be
proposed action, other alternatives and used for dam construction material.
travel. The type of improvements mitigation measures in order to make
envisioned for these access roads would Recreation: Proposed project activities
the following decisions:
include, but not limited to, grading, could cause increased recreation at the
• Whether or not to authorize the
leveling, stabilize and improve stream reservoir and to the Hunter Reservoir
enlargement of Hunter Reservoir and
crossings, relocation out of wetland area because of the improved access
conduct road reconstruction and other
areas, stabilize erosion from road runoff, conditions and the attraction of a larger
support activities to meet the stated
and gravel surfacing. Even with the reservoir. Improved access could also
purpose.
anticipated road improvements it is • If an action alternative is selected, change the recreational opportunity
unlikely that neither of these Forest under what conditions and by which spectrum for the area.
Roads would be deemed suitable for methods reservoir enlargement and Threatened/Endanged/Sensitive(TES)
passenger car travel, but would facilitate associated activities would be Species, Wildlife and Vegetation:
truck traffic necessary to move crews conducted. Proposed project activities could affect
and materials into the site. The Federal Land Policy and existing vegetation and wildlife habitat,
Most earthen materials needed for Management Act gives the Forest including TES such as Canada lynx,
construction would be obtained on site. Service the authority to issue or deny boreal toad and bald eagle.
Rock riprap would come from a authorizations for water storage Fisheries: Proposed project activities,
rockslide area at the site. Dam facilities. The Forest Service is also especially during construction, could
embankment material would come from required to protect and manage natural affect existing fisheries in the reservoir
spillway construction and blanket cutoff resources. and Leon Creek. The long-term effects
construction. Road surface gravels and on downstream fisheries and in-lake
Scoping Process
filter drain materials (crushed rock) as fisheries have the potential to improve
Initial scoping was conducted for this because there could be decreased
well as cement would be delivered to
proposal during August 2005. Letters potential for winter-kill in the reservoir
the site. Concrete would be mixed and
inviting comments on the proposal were and if in-stream flow provisions can be
poured on site.
sent to parties known to be interested. incorporated into the reservoir
Possible Alternatives A news release was issued and operations.
published in the Grand Junction Daily Transportation: Proposed project
Alternative 1: See proposed action Sentinel on Saturday May 28, 2005.
above. activities could affect National Forest
Also, a legal notice was run in that same System Roads. NFSR 280 and 262 are
Alternative 2: Under this alternative newspaper on Friday May 27, 2005. currently rough four-wheel drive roads
only dam safety issues would be Seven letters were received in response. that will need to be upgraded to allow
corrected and Hunter Reservoir would An initial set of issues, listed below, access for crews, equipment and
not be enlarged. were identified from reading the materials. Even with improvements, it is
Alternative 3: A new storage facility response to scoping, from working with unlikely passenger cars could access
would be constructed at another site federal agencies, including the Corps of Hunter Reservoir. Lack of annual
within the Leon Creek drainage basin or Engineers, and from Forest Service and maintenance would allow these roads to
some other adjacent drainage nearby. consultant analysis. degrade to current conditions.
Alternative 4: (No action) Under this Preliminary Issues Range: Proposed project activities
alternative, Hunter Reservoir would not The following issues have been could affect grazing capacity in the Leon
be enlarged nor dam safety issues identified as preliminary issues to be Creek Grazing Allotment. More water
corrected. This alternative is required by carried through the analysis: would be available over a longer period
NEPA to be presented as a baseline to Wetlands: Based on wetland if the proposed action is approved but
consider the environmental effects of delineation by WestWater Engineering there would be a loss of wetland grasses
action alternatives. In the event the in October 2005, the following wetland and forbs that are currently utilized as
action alternatives were found to be classification categories will be below forage for livestock.
unacceptable, this alternative could be high water elevation of the proposed Other issues may be identified
selected. enlarged reservoir: approximately 32 through the scoping process.

VerDate Aug<31>2005 16:26 Oct 25, 2005 Jkt 208001 PO 00000 Frm 00006 Fmt 4703 Sfmt 4703 E:\FR\FM\26OCN1.SGM 26OCN1
Federal Register / Vol. 70, No. 206 / Wednesday, October 26, 2005 / Notices 61783

Permits or Licenses Required chapters of the draft statement. electronic comments to: comments-
Department of the Army Permit (404 Comments may also address the pacificnorthwest-umatilla@fs.fed.us.
permit) for dam fill. Obtained by the adequacy of the draft environmental FOR FURTHER INFORMATION CONTACT:
U.S. Army Corps of Engineers. impact statement or the merits of the Dean Millett, Project Team Leader,
Special Use Permit from the U.S. alternatives formulated and discussed in Pomeroy Ranger District, 71 West Main
Forest Service. the statement. Reviewers may wish to Street, Pomeroy, WA 99347, phone
refer to the Council on Environmental (509) 843–1891. e-mail:
Comments Requested Quality Regulations for implementing dmillett@fs.fed.us.
This notice of intent initiates the the procedural provisions of the
SUPPLEMENTARY INFORMATION:
scoping process that guides the National Environmental Policy Act at 40 Purpose and Need. The purpose and
development of the environmental CFR 1503.3 in addressing these points. need of the School Fires Salvage
impact statement. (Authority: 40 CFR 1501.7 and 1508.22; Recovery Project includes: (1) Recovery
Forest Service Handbook 1909.15, Section of the economic value of a portion of
Early Notice of Importance of Public 21)
Participation in Subsequent dead and dying trees consistent with
Environmental Review Dated: October 18, 2005. protection of other resource values; and
Charles S. Richmond, (2) Improving public safety within the
A draft environmental impact Forest Supervisor. fire area by removing potential hazard
statement will be prepared for comment. trees along open forest travel routes,
[FR Doc. 05–21335 Filed 10–25–05; 8:45 am]
The comment period on the draft developed recreation sites, and
BILLING CODE 3410–11–P
environmental impact statement will be administrative sites.
45 days from the date the Proposed Action. This action includes
Environmental Protection Agency DEPARTMENT OF AGRICULTURE salvage of dead and dying trees from
publishes the notice of availability in approximately 10,000 acres and removal
the Federal Register. Comments Forest Service of potential hazard trees for public
received, including the names and safety along open forest travel routes,
addresses of those who comment, will Umatilla National Forest, Columbia and developed recreation sites, and
be considered part of the public record Garfield Counties, WA School Fire administrative sites. Salvage harvest
on this proposal and will be available Salvage Recovery Project methods would include ground based,
for public inspection. skyline, and helicopter yarding systems.
The Forest Service believes, at this AGENCY: Forest Service, USDA.
Ground based systems would not be
early stage, it is important to give ACTION:Notice of intent to prepare an used on sustained slopes greater than 30
reviewers notice of several court rulings environmental impact statement. percent. To facilitate haul some existing
related to public participation in the classified roads would be reconstructed
SUMMARY: The USDA Forest Service will
environmental review process. First, and about 15 miles of temporary roads
prepare an environmental impact
reviewers of draft environmental impact would be constructed. No new classified
statement (EIS) to disclose
statements must structure their road construction is proposed and all
environmental effects on a proposed
participation in the environmental temporary roads would be closed or
action to recover the economic value of
review of the proposal so that it is decommissioned after project activities
dead and dying trees damaged in the
meaningful and alerts an agency to the are completed. No commercial harvest
School Fire, and remove potential
reviewer’s position and contentions. or road construction is proposed within
hazard trees from open forest travel
Vermont Yankee Nuclear Power Corp. v. the Willow Spring Inventoried Roadless
routes, developed recreation sites, and
NRDC, 435 U.S. 519, 553 (1978). Also, Area. Tree planting is proposed in
administrative sites within North Patit
environmental objections that could be salvage harvest areas where there is
Creek, Little Tucannon River,
raised at the draft environmental impact insufficient seed source to ensure
Cummings Creek, Tumalum Creek,
statement stage but that are not raised natural regeneration in a timely manner.
Headwaters of Tucannon River, and
until after completion of the final Some areas would have sub-
Pataha Creek subwatersheds. School
environmental impact statement may be merchantable trees felled prior to
Fire, located 12 miles south of Pomeroy,
waived or dismissed by the courts. City planting, and these areas would be
Washington, burned approximately
of Angoon v. Hodel, 803 F.2d 1016, broadcast burned to reduce excessive
52,000 acres across mixed ownership in
1022 (9th Cir. 1986) and Wisconsin fuel loading before planting. Forest Plan
August 2005, of that approximately
Heritages Inc. v. Harris, 409 F. Supp. amendments would be included as
27,000 acres were on National Forest
1334, 1338 (E.D. Wis. 1980). Because of needed.
System Lands administered by Pomeroy
these court rulings, it is very important Possible Alternatives. Alternatives
Ranger District, Umatilla National
that those interested in this proposed will include the proposed action, no
Forest.
action participate by the close of the 45 action, and additional alternatives that
day comment period so that substantive DATES: Comments concerning the scope respond to issues generated during the
comments and objections are made of the analysis must be received by scoping process. The agency will give
available to the Forest Service at the November 28, 2005. The Draft EIS is notice of the full environmental analysis
time when it can meaningfully consider expected to be filed with the and decision-making process so
them and respond to them in the final Environmental Protection Agency (EPA) interested and affected people may
environmental impact statement. and be available to the public for review participate and contribute to the final
To assist the Forest Service in by April 2006. The Final EIS is decision.
identifying and considering issues and scheduled to be completed by July 2006. Scoping. Public participation will be
concerns on the proposed action, ADDRESSES: Send written comments to especially important at several points
comments on the draft environmental the Responsible Official, Kevin D. during the analysis, beginning with the
impact statement should be as specific Martin, Forest Supervisor, Umatilla scoping process (40 CFR 1501.7). Initial
as possible. It is also helpful if National Forest, 2517 S.W. Hailey scoping began with the project listed in
comments refer to specific pages or Avenue, Pendleton, OR 97801. Send the 2005 Fall Edition of the Umatilla

VerDate Aug<31>2005 16:26 Oct 25, 2005 Jkt 208001 PO 00000 Frm 00007 Fmt 4703 Sfmt 4703 E:\FR\FM\26OCN1.SGM 26OCN1

Вам также может понравиться