Вы находитесь на странице: 1из 5

572 A.

2d 1177 Page 2
240 N.J.Super. 162, 572 A.2d 1177
(Cite as: 240 N.J.Super. 162, 572 A.2d 1177)

ble party and advising it to consider whether it


Superior Court of New Jersey, wished to undertake the remedial investigation feasi-
Appellate Division. bility study, so that the one year in which the poten-
tially responsible party could file a claim against the
In the Matter of NLINDUSTRIES, INC. Spill Compensation Fund it did not begin to run when
Submitted Feb. 7, 1990. the letter was sent. N.J.S.A. 58:10-23.11k.
Decided April 17, 1990.
[3] Environmental Law 149E 451
Since the responsible party filed claim against New
Jersey Spill Compensation Fund, the Administrator 149E Environmental Law
rejected the claim and party appealed. The Superior 149EIX Hazardous Waste or Materials
Court, Appellate Division, Keefe, J.A.D., held that 149Ek450 Administrative Agencies and Pro-
claim was not timely. ceedings
149Ek451 k. In General. Most Cited Cases
Affirmed. (Formerly 199k25.5(9) Health and Environment)
Potentially responsible party was damaged and was
aware of its damage when it acceded to the Environ-
West Headnotes
mental Protection Agency proposal that it undertake
the remedial investigation and feasibility study and
[1] Environmental Law 149E 439 signed a consent order submitted by the EPA, and its
one year for seeking compensation from the Spill
149E Environmental Law Compensation Fund began to run at that time.
149EIX Hazardous Waste or Materials N.J.S.A. 58:10-23.11k.
149Ek436 Response and Cleanup; Liability
149Ek439 k. Remedial and Removal Ac- [4] Environmental Law 149E 451
tions in General; Cleanup Plans. Most Cited Cases
(Formerly 199k25.5(5.5) Health and Environ-
149E Environmental Law
ment)
149EIX Hazardous Waste or Materials
Contractor neither admits liability nor obtains any
149Ek450 Administrative Agencies and Pro-
benefits from entering into consent agreement with
ceedings
the Environmental Protection Agency to conduct
149Ek451 k. In General. Most Cited Cases
remedial investigation and feasibility study. Compre-
(Formerly 199k25.5(9) Health and Environment)
hensive Environmental Response, Compensation, and
Court has no authority to expand time limit for filing
Liability Act of 1980, § 104(a)(1), as amended, 42
claim with the Spill Compensation Fund.
U.S.C.A. § 9604(a)(1).
**1178*163 Hannoch & Weisman, for NLIndus-
tries, Inc. (A. Patrick Nucciarone, and Edward F.
[2] Environmental Law 149E 451 McTiernan, Roseland, on the brief).

149E Environmental Law Douglas S. Eakeley, Acting Atty. Gen. of N.J., for
149EIX Hazardous Waste or Materials respondent, New Jersey Dept. of Environmental Pro-
149Ek450 Administrative Agencies and Pro- tection (Mary C. Jacobson, Deputy Atty. Gen., of
ceedings counsel, Richard F. Engel, Deputy Atty. Gen., on the
149Ek451 k. In General. Most Cited Cases brief).
(Formerly 199k25.5(9) Health and Environment)
Potential responsible party was not damaged when it Before Judges KING, BAIME and KEEFE.
received letter from the Environmental Protection
Agency advising it that it was a potentially responsi-
The opinion of the court was delivered by

© 2010 Thomson Reuters. No Claim to Orig. US Gov. Works.


572 A.2d 1177 Page 3
240 N.J.Super. 162, 572 A.2d 1177
(Cite as: 240 N.J.Super. 162, 572 A.2d 1177)

*164KEEFE, J.A.D.
c) The funds paid by NL, and all income thereon,
The issue presented is whether appellant, NLIndus- shall be separately maintained for a period of 10
tries, Inc. (NL), filed its claim for damages against years and shall be administered, invested and ex-
the New Jersey Spill Compensation Fund (Spill pended at the sole discretion of NJDEP to moni-
Fund) within one year of the discovery of damage as tor**1179 and remedy ground and/or surface water
required by N.J.S.A. 58:10-23.11k. The Spill Fund contamination as it nows (sic) exists at the Facility,
Administrator determined that the claim was not or as it may exist in the future, in any form and
timely filed. NL appeals from that determination. from any source, excluding the secured landfill lo-
Although we are not in full agreement with the Ad- cated at the Facility....
ministrator's analysis of the facts presented, we agree
with the conclusion reached by him and affirm. d) It is [the] intention of NJDEP and NL that pay-
ment of the funds ... shall constitute a liquidation
NL is the former owner of property located in and payment for all such monitoring and remedial
Pedricktown, New Jersey. During the time NL owned action, the performance of which may be necessary
the property it operated a secondary lead smelting or desirable in the future, and that NL shall have no
site there. Waste materials were generated at the site further duty or obligation with respect to any such
which included emission control dust, battery case monitoring or remedial action, except for that
material, lead smelting slag and battery acid. These ground water contamination which may emanate
materials were also stored at the site. from the secured landfill.... NJDEP forever releases
and discharges NL from any and all responsibility,
On October 6, 1982 NL entered into an Administra- obligation and liability relating to the performance
tive Consent Order (ACO) with the New Jersey De- of monitoring and remedial action respecting such
partment of Environmental Protection (DEP) wherein contamination, under all applicable laws, rules and
it agreed to take steps to remediate the hazardous regulations; NJDEP shall neither commence any
waste conditions that existed at the Pedricktown site action or proceeding against NL with respect
and to pay certain fines. thereto nor shall NJDEP take any action to initiate
the commencement of any action or proceeding by
The property was sold to National Smelting Com- any other entity against NL with respect thereto. In
pany of New Jersey, Inc. in 1983. In connection with the event the United States Environmental Protec-
that sale, an amendment to the ACO was entered into tion Agency shall require ground water remedial
on February 10, 1983 between representatives of the action at the Facility for those issues which are the
DEP, NL, National Smelting and Refining and Na- subject of this Paragraph (i.e. excluding ground
tional Smelting Company of New Jersey. water contamination emanating from the secured
landfill), NJDEP agrees to apply the aforedescribed
sum to the costs of such remedial action.
The Amended Administrative Consent Order
(AACO) provided that the original ACO remained in
effect and that NL had substantially complied with Although the United States Environmental Protection
the provisions of that order. The AACO recognized Agency (EPA) is mentioned in the AACO, it was not
that responsibility for compliance with the remainder a party to the order.
of the ACO was the responsibility of National Smelt-
ing Company of New Jersey, with the exception of After the AACO was executed by the parties, but
future “ground water contamination which might before July 31, 1985, National Smelting Company of
emanate from [an existing] secured landfill” which New Jersey declared bankruptcy. On that date, NL
remained NL's responsibility. NL agreed to pay the received a letter from the EPA informing it of the
DEP $600,000 in order to create a fund so *165 that EPA's intention to expend public funds for the inves-
the DEP could perform actions it deemed appropriate tigation of the Pedricktown property and advising NL
to monitor and remedy ground water and surface wa- of its potential liability for those costs pursuant to the
ter problems. Comprehensive Environmental Response, Compen-
sation, and Liability Act of 1980 (CERCLA), 42
The AACO states in part: U.S.C.A. §§ 9601-9675. The EPA's letter stated in

© 2010 Thomson Reuters. No Claim to Orig. US Gov. Works.


572 A.2d 1177 Page 4
240 N.J.Super. 162, 572 A.2d 1177
(Cite as: 240 N.J.Super. 162, 572 A.2d 1177)

part:
On April 8, 1986 the EPA extended the deadline for
EPA will immediately move forward with the reme- signing its Order to April 21, 1986.
dial investigation and feasibility studies (RI/FS)
unless you notify EPA in writing BY NO LATER On April 21, 1986 an official of NL signed the Ad-
THAN AUGUST 16, 1985 of your intent to under- ministrative Consent Order as proposed by the EPA.
take the RI/FS. The order outlined the scope and procedures for a
remedial investigation and feasibility study at the
*166 In the months which followed the EPA letter, a Pedricktown site. The order was executed by the re-
series of discussions and exchange of correspondence gional administrator of the EPA on April 25, 1986.
took place between NL, EPA and DEP. Those dis- The EPA forwarded the executed order to NL on
cussions focused on NL's liability for costs associated April 28, 1986, advising it that the order was effec-
with a proposed EPA Administrative Consent Order tive on April 30, 1986. The *167 effective date was
and, more specifically, whether the DEP would re- important because NL was required to perform cer-
lease all or some of the $600,000 which it was hold- tain tasks within 90 days of the effective date.
ing pursuant to the AACO to help fund the RI/FS.
Although the record is not completely clear as to the On April 24, 1987 NL mailed its claim for damages
exact date, NL states in its appellate brief that “DEP against the Spill Fund to the Administrator. NL's re-
ultimately declined to apply any of those funds to the quest for money from the Spill Fund was denied on
RI/FS.” FN1 February 17, 1989 as being untimely. This denial was
followed by an Amplified Damage Claim Denial that
FN1. NL's brief refers to a letter contained explained that at the most N.L.'s claim was approxi-
in the appendix from DEP to NL dated Feb- mately one year and six days late, and at the least its
ruary 20, 1986. claim was six days late. The Administrator deter-
mined that NL discovered its damage as early as July
By February 21, 1986 the EPA became insistent that 31, 1985, the date the EPA mailed its notification
NL decide whether it was or was not going to sign letter to NL, or as late as April 21, 1986, the date NL
the EPA's proposed consent order. In the letter dated signed the EPA Administrative Consent Order.
March 21, 1986 addressed to NL, the EPA's regional
counsel stated: The New Jersey Spill Fund “may be used for six pur-
poses: (1) to finance governmental cleanup of haz-
The RI/FS needs to get started and EPA cannot de- ardous waste sites; (2) to reimburse third parties for
bate indefinitely the merits of the language of the cleanup costs; (3) to compensate third parties for
proposed Order with NL. NL has had an adequate damage resulting from hazardous substance dis-
opportunity to express its views, and EPA has at- charges; (4) to pay personnel and equipment costs;
tempted to accommodate NL's legitimate concerns (5) to administer the fund itself; and (6) to conduct
in the revised versions of the Order. research.” Exxon Corp. v. Hunt, 475 U.S. 355, 375,
106 S.Ct. 1103, 1116, 89 L.Ed.2d 364 (1986). It is for
As I told you in our meeting on March 19, 1986, NL the third stated purpose that NL intended to make
now needs to decide whether it will sign the EPA application to the Spill Fund. N.J.S.A. 58:10-23.11g.
Order and perform the RI/FS. Since we have al- However, any such claim “shall be filed with the ad-
ready received many comments from NL, EPA will ministrator not later than 1 year after the date of dis-
at this time only entertain minor revisions to the covery of damage....” N.J.S.A. 58:10-23.11k. The
February 21, draft of the Order, and any suggested application is made on forms provided by the Admin-
revision received by EPA after March 28 will not istrator for such purpose. Id.
be considered. If NL wishes to perform the **1180
RI/FS, it must sign an EPA-approved Order by no In this case, the form filed by NL with the Adminis-
later than April 15, 1986 and deliver the signed trator revealed that NL's claimed damage was for the
Order to EPA by that date. These two deadlines cost of the RI/FS study and for any further remedia-
are, of course, the ones I informed you of on March tion liability expense that may result from the RI/FS
19. study. The Administrator made a specific finding as

© 2010 Thomson Reuters. No Claim to Orig. US Gov. Works.


572 A.2d 1177 Page 5
240 N.J.Super. 162, 572 A.2d 1177
(Cite as: 240 N.J.Super. 162, 572 A.2d 1177)

to the damage being claimed by NL in his Amplified question. [Id.]


Damage Claim Denial.
[2] Thus, it would appear that a consent agreement to
Specifically, Claimant (NL) is seeking compensation perform a RI/FS study is conceptual in nature and a
for its percentage of the costs of a Remedial Inves- response action contractor does not sustain damage,
tigation and Feasibility Study (RI/FS) which re- i.e., incur costs for *169 the study, until it agrees to
sulted from complying with an Administrative Or- perform it. We find no provision in CERCLA which
der of Consent entered into with the *168 U.S. En- permits the EPA to direct a potentially responsible
vironmental Protection Agency. The amount of this party to perform a RI/FS without the party's consent.
FN2
claim is unspecified. Thus, as a matter of law, NL was not damaged on
July 30, 1985 when it received the letter from the
Given the nature of the damage claimed by NL, the EPA advising NL that it was a “potentially responsi-
Administrator was required to determine when the ble party” and inviting NL to consider whether it
damage was incurred and the date on which NL wished to undertake the RI/FS study.
learned of it. The Administrator selected alternative
dates of July 30, 1985 and April 21, 1986. FN2. Of course once liability is established
pursuant to the statute, a responsible party is
[1] We disagree with the Administrator's reliance on liable for all costs of removal or remediation
the EPA letter of July 30, 1985 as the date on which and any other costs of response incurred as a
NL learned that it was damaged by reason of the dis- result thereof. 42 U.S.C.A. § 9607(a).
charge of hazardous waste. The disagreement stems
from our understanding of CERCLA. Under [3] On the other hand, it is clear that NL was dam-
CERCLA when there is a discharge or substantial aged and was aware of its damage on April 21, 1986
threat of discharge of any hazardous substance, pol- when it ultimately acceded to the EPA proposal and
lutant or contaminant into the environment which signed the consent order in the form submitted by the
presents an imminent and substantial danger to the EPA. The letter of transmittal from the EPA to NL
public health or welfare, the EPA is authorized to act. with reference to that consent order, dated April 8,
One of the actions that it may take is to allow the 1986, makes it clear that no further room for negotia-
“owner or operator of the facility” or “any other re- tion was available. NL was required to execute the
sponsible party” to “conduct the remedial investiga- order by April 21, 1986 or forfeit its right to conduct
tion, or conduct the feasibility study in accordance the study. Therefore, contrary to NL's argument, the
with section 9622 of this title.” However, the EPA execution of the consent order by the EPA on April
may not delegate the RI/FS study to such third parties 25th and the designation of the effective date of April
until there is a determination that the party is “quali- 30, 1986 has no bearing on the date on which NL
fied to conduct the RI/FS”. 42 U.S.C.A. § 9604(a)(1). incurred damage or the date on which it discovered
An **1181 owner, operator, or other responsible such damage.
party who undertakes to do a RI/FS study upon
agreement with the EPA is known as a “response In Woodland Private Study Group v. State. of New
action contractor” or a “potentially responsible Jersey, Dep't of Envtl. Protection, 616 F.Supp. 794
party.” Id. It is clear from the statute that such a con- (D.N.J.1985), vacated and remanded with instruc-
tractor neither admits liability nor obtains any benefit tions to dismiss as moot, 846 F.2d 921 (3d Cir.1988),
from entering into such a consent agreement with the only reported case addressing interpretation of the
EPA. The Act provides. statute in question, the court found that the date on
which plaintiff discovered its damage was March 5,
In no event shall a potentially responsible party be 1985. That was the date on which the DEP issued two
subject to a lesser standard of liability, receive directives to members of the plaintiff group and oth-
preferential treatment, or in any other way, whether ers requiring that they pay the DEP a total of
direct or indirect, benefit from any such arrange- $880,000 within seven days of receipt of the direc-
ments as a response action contractor, or as a per- tives for the purpose of funding the costs of a RI/FS.
son hired or retained by such a response action Almost two years prior to that date, plaintiff had
contractor, with respect to the release or facility in *170 entered into negotiations with the DEP concern-

© 2010 Thomson Reuters. No Claim to Orig. US Gov. Works.


572 A.2d 1177 Page 6
240 N.J.Super. 162, 572 A.2d 1177
(Cite as: 240 N.J.Super. 162, 572 A.2d 1177)

ing the nature of the RI/FS for the site in question and ity to expand the time limit contained in the statute.
the extent of the DEP's control over the study. In We have in the past upheld the dismissal of a claim
short, negotiations ultimately broke down resulting in for failure to comply with the statute of limitation
the directive of March 5, 1985. Thus, despite plain- where the complaint was filed only one day after the
tiff's knowledge that it was considered to be a poten- running of the statutory period. Leake v. Bullock, 104
tially responsible party for the clean-up costs as early N.J.Super. 309, 250 A.2d 27 (App.Div.1969). See
as August, 1983 and despite the fact that plaintiff also Cwiklinski v. Burton, 217 N.J.Super. 506, 526
offered to undertake the RI/FS study on its own A.2d 271 (App.Div.1987).
terms, the court found that plaintiff was not damaged
until March 5, 1985. In arriving at that conclusion, Affirmed.
the court reasoned that it was not until the March 5,
1985 directive that plaintiff was “officially assured” N.J.Super.A.D.,1990.
that a claim would be filed against it for the cost of Matter of NL Industries, Inc.
the studies. 240 N.J.Super. 162, 572 A.2d 1177

The DEP argues that the July 31, 1985 letter from the END OF DOCUMENT
EPA to NL “is just like a directive.” We disagree
with that analysis. As noted earlier, the July, 1985
letter issued by the EPA to NL was pursuant to 42
U.S.C.A. § 9604(a). The letter was not a directive at
all similar to the DEP directive in Woodland. Rather,
it invited NL to undertake the cost of the RI/FS study
as a way of mitigating any possible liability for clean-
up costs it might ultimately incur. This invitation by
the EPA resulted in protracted**1182 negotiations
which ultimately broke down, resulting in the EPA
issuing a non-negotiable consent order which NL was
required to sign if it wished to undertake the RI/FS
study.

It would appear from Woodland that the DEP took


the position that the one-year statute of limitation did
not begin to run during the period of negotiations
between plaintiff and DEP concerning the RI/FS
study. Woodland, 616 F.Supp. at 803. We cannot
understand how, under similar circumstances, the
DEP can take a different position in this case. The
event in the subject case which is comparable to the
DEP directive in the Woodland case is NL's capitula-
tion to the EPA demand that it sign the proposed con-
sent order with no further changes. As indicated ear-
lier, that did not occur until April 21, 1986.

[4] In view of our decision that the date of discovery


of damage in this case was April 21, 1986, it is un-
necessary for us *171 to decide whether NL's claim
was “filed” with the Administrator on April 24, 1987
when NL forwarded the claim by certified mail, or
April 27, 1987 the date on which the DEP received
the form. In either event, NL filed its claim beyond
the one-year statute of limitation. We have no author-

© 2010 Thomson Reuters. No Claim to Orig. US Gov. Works.

Вам также может понравиться