Академический Документы
Профессиональный Документы
Культура Документы
Power Transformers
Bushing
LTC
LTC
Control
Cabinet
Cooler
Main Tank
Cooler
INTRODUCTION
Commissioning versus Maintenance Testing
Main Transformer Protection:
Restrained Phase Differential
High Set Phase Differential
Ground Differential
INTRODUCTION
Topics:
Transformer Differential Boundary Test
(Commissioning)
Ground Differential Sensitivity Test
(Commissioning/Maintenance)
Secondary Transformer Protection
Harmonic Restraint for Transformer Inrush
(Maintenance)
1965
1975-
1982
1983-
1988
Number
% of Total
Number
% of Total
Number
% of Total
134
51
615
55
144
37
Tap changer
failures
49
19
231
21
85
22
Bushing failures
41
15
114
10
42
11
Terminal board
failures
19
71
13
24
12
72
101
26
262
100
1127
100
389
100
Winding failures
Core failures
Miscellaneous
Total
Commissioning
Common Practice:
Test all numerical relay settings
verify settings properly entered
Easily facilitated using computer
automate test set & store results
Hundreds of tests are possible
numerical relays have many settings
Commissioning
Final Goal
Ensure the transformer is properly protected for the
particular application
46
RG
E
+
46
RG
ZT
I2
46
ZT
ZT
3RG
I1
Y
Y
87
* Simulate Through Current
Differential Characteristic
Operating Equations
Differential Characteristic
Id
% = Y *100%
X
Y
Minimum
Pickup
(per unit)
Ir
Differential Characteristic
Id
Minimum
Pickup
Ir
Matrix
[]
Id
Ir
[ ][]
1 -1 *
I1
I2
Inverted Matrix
[]
I1
I2
[ ][]
1
- 1
Id
Ir
Differential Characteristic
Test Current Equations
Differential Characteristic
Test Points
Minimum Pickup = 0.2 per unit
Id
Slope = 28.6%
4
3
1
Minimum
Pickup
Ir
Differential Characteristic
Test Points (Per Unit)
Id
Ir
I1
I2
0.2
0.3
0.4
0.2
0.2
0.7
0.8
0.6
0.4
1.4
1.6
1.2
0.6
2.0
2.3
1.7
TABLE 1
I1
Y
Y
87
* Simulate Through Current
DAB WINDING
IA1relay = IA1/TAP1
WYE WINDING
IB1relay = IB1/TAP1
IC1relay = IB1/TAP1
MVA#
TAP# =
kV#LL*CTR#*SQRT(3)
Id
Ir
I1
I2
0.2
0.7
0.8
0.6
IA1test = 0.8*TAP1
IA2test = 0.6*TAP2*SQRT(3)
As an example, if we have a two winding transformer with Y/Delta-AC connection (or YD1)
with Y-Y cts. This will be equivalent to case 2 with a 30o phase shift.
A
1:
0O
C
3:
60O
B
7:
180O
A
B
9:
240O
A
11:
300O
C
0 1 0
I ' ABC = 0 0 1 I ABC
1 0 0
A
2:
30O
C
4:
90O
5:
120O
B
1 0 0
I ' ABC = 0 1 0 I ABC
0 0 1
0 0 1
I ' ABC = 1 0 0 I ABC
0 1 0
1 0 0
I ' ABC = 0 1 0 I ABC
0 0 1
0 1 0
I ' ABC = 0 0 1 I ABC
1 0 0
0 0 1
I ' ABC = 1 0 0 I ABC
0 1 0
C
6:
150O
B
1 1 0
1
I ' ABC = 0 1 1 I ABC
3
1 0 1
0 1 1
1
I ' ABC = 1 0 1 I ABC
3
1 1 0
1 0 1
1
I ' ABC = 1 1 0 I ABC
3
0 1 1
A
B
8:
210O
B
10:
270O
A
12:
330O
1 1 0
1
I ' ABC = 0 1 1 I ABC
3
1 0 1
0 1 1
1
I ' ABC = 1 0 1 I ABC
3
1 1 0
1 0 1
1
I ' ABC = 1 1 0 I ABC
3
0 1 1
External
IG
I0
-90o
Fault Resistance
140
120
100
80
60
40
20
0
0
20
40
60
80
Source Impedance
IG = 200 mA
IG = 500 mA
IG = 1 Amp
100
120
IG
Directional Element
INTERNAL
EXTERNAL
IG2
IOP
CTCF*3I0(2)
New Pickup = 1.0 Amps
24 Overexcitation (V/Hz)
46 Negative-Sequence Overcurrent
49 Winding Overload
50 Instantaneous Phase Overcurrent (per winding)
50G Instantaneous Ground Overcurrent (per winding)
50N Instantaneous Neutral Overcurrent (per winding)
51 Inverse Time Phase Overcurrent (per winding)
51G Inverse Time Ground Overcurrent (per winding)
51N Inverse Time Neutral Overcurrent (per winding)
59G Ground Overvoltage (Ungrounded Windings)
63 Sudden Pressure
Causes of Overexcitation
Generating Plants
Excitation system runaway
Sudden loss of load
Operational issues (reduced frequency)
Static starts
Pumped hydro starting
Rotor warming
Transmission Systems
Voltage and Reactive Support Control Failures
Capacitor banks ON when they should be OFF
Shunt reactors OFF when they should be ON
Near-end breaker failures resulting in voltage
rise on line (Ferranti effect)
Runaway LTCs
Ferranti Effect
10-20 MVAR
30-40 MVAR
Overexcitation Curves
W3
delta
345 kV
230 kV
wye
W1
wye
W2
Z HM + Z HL Z ML
2
ZM =
Z HM + Z ML Z HL
2
ZL =
Z HL + Z ML Z HM
2
TAP2 =
= 4.18
= 3.77
Ieven =
2
(I2
2 1/2
I4 )
CONCLUSIONS
CONCLUSIONS
Transformer Differential Boundary Test
(Commissioning)
Ground Differential Sensitivity Test
(Commissioning/Maintenance)
Harmonic Restraint for Transformer Inrush
(Maintenance)
QUESTIONS ?