Вы находитесь на странице: 1из 68

Power Plant and Transmission System

Protection Coordination
Volts Per Hertz (24), Undervoltage (27), Overvoltage (59),
and Under/
Under/Overfrequency
Overfrequency (81) Protection
NERC Protection Coordination Webinar Series
June 23, 2010
Phil Tatro

Agenda
2

Technical Reference Document Overview


Objectives
Obj ti
Description of Protection Functions
Di
Discuss and
dD
Describe
ib S
System
t
E
Events
t th
thatt C
Could
ld C
Create
t
Conditions that Would Cause Operation of These
Functions
Detailed Coordination Information
Function 24 Volts Per Hertz Generator and Transformer
Protection
Function 27 Undervoltage for Generator, Plant Auxiliaries
System, High-Side Point of Common Coupling Protection
g Generator Protection
Function 59 Overvoltage
Function 81 Under/Overfrequency Turbine Generator
Protection

Agenda
3

What is Important
p
to Coordination
Settings that Protect the Generator
Time Coordination with UFLS and UVLS
Consideration of Islanding Conditions
Sufficient Studies

Question and Answer

Disclaimer
4

The information from this webcast is provided for


i f
informational
ti
l purposes only.
l A
An entity's
tit ' adherence
dh
tto th
the
examples contained within this presentation does not
constitute compliance with the NERC Compliance
Monitoring and Enforcement Program ("CMEP")
( CMEP )
requirements, NERC Reliability Standards, or any other
NERC rules. While the information included in this
material may provide some of the methodology that
NERC may use to assess compliance with the
requirements of certain Reliability Standards, this
material should not be treated as a substitute for the
R li bilit St
Reliability
Standard
d d or viewed
i
d as additional
dditi
lR
Reliability
li bilit
Standard requirements. In all cases, the entity should
rely on the language contained in the Reliability
Standard itself,
itself and not on the language contained in this
presentation, to determine compliance with the NERC
Reliability Standards.

Technical Reference Document Overview


5

Introduction and Background Blackout


Recommendation TR-22
SPCS
SPCSs
s Assignment

The Need for this Technical Reference


Document - History and Background:
August 14, 2003 Blackout
Subsequent Events

Technical Reference Document Overview


6

Support of PRC Standards


Benefits of Coordination:
To the Generator Owner
To the Transmission Owner
To the Planning Coordinator

Reliability of the Bulk Electric System and Power


Delivery to the Customer

Objective
7

Increase knowledge of recommended


generator protection for overexcitation,
undervoltage, overvoltage, underfrequency,
and overfrequency protection functions.
Facilitate improved coordination between
power plant and transmission system
protection for these specific
p
p
p
protection
functions.

Scope
8

Focus is on the reliability of the Bulk Electric


System.
This Technical Reference Document is
applicable to all generators, but concentrates on
synchronous
y
g
generators connected at 100-kV
and above.
Distributed Generation (DG) facilities connected
to distribution systems are outside the scope of
this document.

The Need for Overexcitation or


V/Hz
/ Protection Function 24
Overexcitation of a generator or any transformers connected to
the generator terminals will occur whenever the ratio of the voltage
to frequency (V/Hz) applied to the terminals of the equipment
exceeds 105% (generator base) for a generator; and 105%
(transformer base) at full load, 0.8 pf or 110% at no load at the
secondary terminals for a transformer
transformer.
Overexcitation causes saturation of the magnetic core of the
generator or connected transformers, and stray flux may be induced
in non
non-laminated
laminated components that are not designed to carry flux
flux.
Excessive flux may also cause excessive eddy currents in the
generator laminations that result in excessive voltages between
laminations This may cause severe overheating in the generator or
laminations.
transformer and eventual breakdown in insulation.
The field current in the generator could also be excessive.
IEEE C37.102-2006 Guide for AC
Generator Protection, Section 4.5.4

The Need for Generator Unit


Undervoltage
g Protection Function 27

For the generating unit, undervoltage protection that trips the unit is
rarely applied to generators.

It is frequently used as an interlock element for other protection function or


schemes, such as loss-of-field relay (40), distance relay (21), inadvertent
energizing relay (50/27), out-of-step relay (78), etc, where the abnormality
to be detected leads directly or indirectly to an undervoltage condition.

Generators are usually designed to operate continuously at a minimum


voltage of 95% of its rated voltage, while delivering rated power at rated
frequency.

Operating a generator with terminal voltage lower than 95% of its rated
voltage may result in undesirable effects such as reduction in stability limit,
import of excessive reactive power from the grid to which it is connected,
and malfunctioning of voltage sensitive devices and equipment.

This effect
Thi
ff t h
however iis a ffunction
ti off titime. If applied,
li d the
th undervoltage
d
lt
protection is generally connected to alarm and not trip the unit, so that
the operator can take appropriate action to remedy the undervoltage
condition (if possible).
IEEE C37.102-2006 Guide for AC
Generator Protection, Section 4.5.7

10

The Need for Generating Plant Auxiliary Power


Systems Undervoltage Protection Function 27

This function is used to protect auxiliary system equipment from severe


undervoltage conditions that would have serious consequences, such as
auxiliaryy motors stalling
g or voltage
g collapse
p for the g
generating
g unit(s).
( )

When the voltage level of the auxiliary system reaches the undervoltage
set-point, this protection may initiate any one or a combination of the
following actions:

Al
Alarming.
i

Automatic transfer to alternative power supply.

Starting of emergency generator(s).

Tripping the generating unit,


unit if necessary.
necessary

This function also protects the integrity of the power supply to safety related
buses applied to support the reactor of nuclear power plants. In these
applications two undervoltage thresholds are utilized:

The first undervoltage (UV) level (function 27SB1) initiates auxiliary load
transfers to an alternative power supply.

The second UV level (function 27SB2) initiates a unit trip. (See section 3.3.4 for
further details)

11

The Need for Undervoltage Relays Applied


at the Point of Common Coupling Function 27

The function of these relays is to alarm that an


undervoltage condition is occurring on the
transmission system and that the operator
should be on a heightened state of awareness,
matching this alarm with others that may be
occurring
i within
ithi th
the plant.
l t

12

The Need for Generator Unit


Overvoltage
g Protection Function 59

Generator overvoltage may occur without necessarily exceeding the V/Hz


limits of the machine. In general, this is a problem associated with hydro
generators, where upon load rejection, the overspeed may exceed 200% of
normal.

Protection for generator overvoltage is provided with a frequencycompensated (or frequency-insensitive) overvoltage relay.
relay The relay should
have both an instantaneous unit and a time-delay unit with an inverse time
characteristic. The instantaneous unit is generally set to pick up at 130% to
150% voltage while the inverse time unit is set to pick up at about 110% of
normal voltage. Two definite time-delayy relays
y can also be applied.
IEEE C37.102-2006 Guide for AC
Generator Protection, Section 4.5.6

Overvoltage protection is necessary for preventing an insulation break-down from a


sustained overvoltage. The generator insulation system is capable of operating at
105 percent overvoltage continuously.

g above 105 p
percent normally
y should not occur for a g
generator
Sustained overvoltage
with a healthy voltage regulator, but may be caused by the following contingencies:
(1) defective automatic voltage regulator (AVR) operation, (2) manual operation w/o
AVR, and (3) sudden load loss.

13

The Need for Generator Unit Under and


Overfrequency
q
y Protection Function 81

14

Mismatch between load and generation may be caused by a variety of


system disturbances and/or operating conditions. However, of primary
concern is the system disturbance caused by a major loss of generation that
produces system separation and severe overloading on the remaining
system generators.

Under this condition, the system frequency will decay and the generators
may be
b subjected
bj t d tto prolonged
l
d operation
ti att reduced
d
d ffrequency and
d th
there
exists the possibility of operation at reduced frequency for sufficient time to
damage steam or gas turbine generators.

Full- or partial-load rejection


j
may
y be caused by
y clearing
g of system
y
faults or
by over-shedding of load during a major system disturbance. Load rejection
will cause the generator to overspeed and operate at some frequency
above normal.

In g
general,, underfrequency
q
y operation
p
of a turbine g
generator is more critical
than overfrequency operation since the operator does not have the option of
control action.

IEEE C37.102-2006 Guide for AC


Generator Protection, Section 4.5.8

Relay OneOne-Line Showing All Generator Protection


and Identifying Functions 24, 27, 59, and 81

15

87U
87T

51T

87G

50BF

24
24

27
27

59
59

81
81
51TG

59GN/
27TH

21

32

40

46

50/27

51V

78

System Events that Could Cause Undesired


Operation of These Protection Functions

Fault Conditions
Loss of Critical Lines
Loss of Critical Units
Events such as August
g
14,, 2003 Blackout
System Islanding Conditions

16

General Data Exchange Requirements


Generator Owner Data and Information
The following general information must be exchanged in addition to
relay settings to facilitate coordination
coordination, where applicable:
Relay scheme descriptions
Generator off nominal frequency operating limits
CT and
d VT/CCVT configurations
fi
ti
Main transformer connection configuration
Main transformer tap position(s) and impedance (positive and zero
sequence) and neutral grounding impedances
High voltage transmission line impedances (positive and zero
sequence) and mutual coupled impedances (zero sequence)
Generator impedances (saturated and unsaturated reactances that
include direct and quadrature axis, negative and zero sequence
impedances and their associated time constants)
Documentation showing the function of all protective elements listed
above

17

General Data Exchange Requirements


Transmission or Distribution Owner Data and Information
The following general information must be exchanged in addition to
relay settings to facilitate coordination
coordination, where applicable:
Relay scheme descriptions
Regional Reliability Organizations off-nominal frequency plan
CT and VT/CCVT configurations
Any transformer connection configuration with transformer tap
position(s) and impedance (positive and zero sequence) and neutral
grounding impedances
High voltage transmission line impedances (positive and zero
sequence) and mutual coupled impedances (zero sequence)
Documentation showing
g the function of all p
protective elements
Results of fault study or short circuit model
Results of stability study
Communication-aided
Communication aided schemes

18

Detailed Coordination Information for


Functions 24,, 27,, 59,, and 81
Detailed coordination information is presented
under seven headings, as appropriate, for each
function in the document.
The following slides present a section-by-section
summaryy for Functions 24,, 27,, 59,, and 81.

19

Document Format Seven SubSub-Sections


for Each Protection Function

Purpose

Coordination of Generator and Transmission System

Faults

Loadability

Other Conditions, Where Applicable

Considerations and Issues

Coordination Procedure

Test Procedure for Validation

Setting Considerations

Examples

Proper Coordination

Improper Coordination

Summary of Detailed Data Required for Coordination of the Protection


F
Function
i

Table of Data and Information that Must be Exchanged

20

Volts Per Hertz Function 24


21

Purpose
Prevent damage to generators and connected transformers that
may occur when the excitation (V/Hz) applied exceeds the
equipment capability.
Generator: 105% on the generator base
Transformer: 105% on the transformer base at full load, 0.8 pf or
110% at no load at the secondary terminals.

Overexcitation
O
it ti may resultlt in:
i
Saturation of the magnetic core.
Stray flux induced in non-laminated components that are not
d i
designed
d tto carry flflux.
Excessive eddy currents in the generator laminations resulting in
excessive voltages between laminations, severe overheating, and
eventual breakdown in insulation.
Excessive field current in the generator.

Coordination of Generator and


Transmission System
y
Function 24
Faults
There are no coordination issues for system faults for
this function.

Loadability
Th
There are no coordination
di ti issues
i
related
l t d to
t loadability
l d bilit
for this function.

22

Coordination of Generator and


Transmission System
y
Function 24
Other Operating Conditions
Coordination between generating plant overexcitation
protection and the transmission system is necessary
for off-nominal
off nominal frequency events
events.
Coordination is necessary to allow the UFLS program
to arrest frequency decline and recover frequency to
a sustainable operating condition.
Uncoordinated tripping of generation by overexcitation
protection will exacerbate the unbalance between load and
generation.
This may result in tripping of more load than necessary, or in
the worst case, system collapse if the resulting imbalance
exceeds the design basis of the UFLS program.

23

Considerations and Issues Function 24


24

Overexcitation withstand limit characteristics of


generators and transformers should be requested from
the equipment manufacturer whenever possible.
Abnormal system voltage during UFLS events is not
uncommon.
Particularly when such events occur during heavy load
conditions when reactive sources are dispatched to meet
reactive power demand.
Under such conditions restoring a balance between load and
generation to recover system frequency may be insufficient to
control excitation to acceptable levels.
Additional coordination with voltage control devices may be
required (e.g. to remove shunt capacitor banks or connect shunt
reactors).

Coordination Procedure Function 24


25

The following data and information exchange steps should be taken


b the
by
h G
Generator O
Owner and
d Pl
Planning
i C
Coordinator.
di
N
Note that
h iin
cases where the generator step-up transformer is owned by the
Transmission Owner, the Transmission Owner would have the same
responsibility as the Generator Owner.
Step 1 Generator Owner provides Settings, Time Delays, and
Protection Characteristics to the Planning Coordinator for both the
Generator and Generator Step-up
Step up Transformer.
Step 2 The Generator Owner and Planning Coordinator confirm
that the Protection settings coordinate with operation of the UFLS
program.
Step 3 The Planning Coordinator performs studies to verify
coordination.

Setting Procedure Function 24


26

Plot the V/Hz withstand capability curves of the GSU transformer


and generator.
Plot the overexcitation (V/Hz) protection characteristic on the same
graph.
Ch
Check
k proper coordination
di ti b
between
t
th
the relay
l characteristic
h
t i ti curves
and timing settings of excitation control limiter(s).
Short time excursions beyond the overexcitation limit should not cause
the protection system to trip the generator.
generator
The excitation control system limiter should act first to reduce excitation
to prevent equipment damage.
Th
The generator
t protection
t ti mustt be
b sett to
t operate
t slower
l
than
th the
th
excitation limiter, but fast enough to protect the equipment should the
excitation limiter fail.
Protection system tripping times are generally long enough so that
coordination with exciter response is not a problem.

Setting Procedure Function 24


27

Coordination between the overexcitation protection and the UFLS


program design
d i can b
be validated
lid d only
l through
h
h a stability
bili study.
d
The overexcitation protection should be modeled in the study
Or

Excitation should be monitored for comparison against tripping


characteristics (at all buses at which overexcitation protection is utilized)

In a limited number of cases, conditions may exist for which


coordination cannot be achieved for every generating unit.
Coordination may be deemed acceptable if tripping does not cascade
and is limited to a small amount of generation (as a percentage of the
load in the affected portion of the system).
Protection models should be added to system models for any units for
which coordination cannot be obtained.

Example - Proper Coordination


Function 24

28

Transformer
Generator

130

Inverse Time Curve


Definite Time

125
Percentage V/Hz

Series5

120
115

Definite Time
Pickup

110
Inverse Time
Pickup

105
100
0.01

0.1

10

Operating Time in Minutes

100

Example - Proper Coordination


Function 24

Bus Excitation (V/Hz)


Bus Voltage

Bus Frequency

29

Summary of Protection Functions


Required
q
for Coordination Function 24
Table2Excerpt Function24ProtectionCoordinationConsiderations

GeneratorProtection
Function

24 Volts/Hz

TTransmissionSystemProtection
i i S t
P t ti
Functions

UFLSProgram
UFLSdesignisgenerallytheresponsibility
ofthePlanningCoordinator

SystemConcerns

GeneratorV/Hzprotectioncharacteristicsshallbedetermined
Generator
V/Hz protection characteristics shall be determined
andberecognizedinthedevelopmentofanyUFLSprogramfor
allrequiredvoltageconditions.TheGeneratorOwner(andthe
TransmissionOwnerwhentheGSUtransformerisownedbythe
TransmissionOwner)exchangeinformationofV/Hzsetpoints and
UFLSsetpoints withthePlanningCoordinator

CoordinatewiththeV/HzwithstandcapabilityandV/Hzlimiterin
Coordinate
with the V/Hz withstand capability and V/Hz limiter in
theexcitationcontrolsystemofthegenerator

CoordinatewithV/Hzconditionsduringislanding(highvoltage
withlowfrequencysystemconditionsthatmayrequiresystem
mitigationactions)

RegionalUFLSprogramdesignmustbecoordinatedwiththese
settings.

Islandingissues(highvoltageandlowfrequency)mayrequire
planningstudiesandrequirereactiveelementmitigation
strategies

Settingsshouldbeusedforplanningandsystemstudieseither
throughexplicitmodelingofthefunction,orthroughmonitoring
through
explicit modeling of the function, or through monitoring
voltageandfrequencyperformanceattherelaylocationinthe
stabilityprogramandapplyingengineeringjudgment

30

Protection Function Data and Information


Exchange
g Required
q
for Coordination Function 24

Table3Excerpt Function24DatatobeExchangedBetweenEntities

GeneratorOwner

Theoverexcitationprotection
characteristics,includingtimedelaysand
relaylocation,forthegeneratorandthe
GSUtransformer(ifownedbythe
Generator Owner)
GeneratorOwner)

TransmissionOwner

Theoverexcitationprotectioncharacteristicsforthe
GSUtransformer(ifownedbytheTransmission
Owner)

PlanningCoordinator

Feedbackonproblemsfoundbetween
overexcitation settingsandUFLSprograms

31

Undervoltage Protection Function 27


32

G
System

GSU

27

27

Alarm

Figure 3.3.1.1 Typical Unit


Generator Undervoltage Scheme
Point of
Common
Coupling

Backup
Power
Supply

Power
P
Plant
Station
Service

Trasfer
Switch

Auxiliary

GSU

System
G

System
y
G

GSU

27

Figure 3.3.3.1 Undervoltage


Relay Applied at the Point of
Common Coupling

Figure 3.3.2.1 Generating Plant


Auxiliary Power System
Undervoltage Protection Scheme

Undervoltage Protection Function 27


33

1. Purpose of Generator Unit Function 27


Undervoltage alarms are used as an indicator of possible
abnormal operating conditions on hydro, fossil, combustion and
nuclear units, such as excitation problems and thermal issues
within the unit.
Note that each type of unit (hydro, fossil, nuclear, combustion, and
renewable) has different abnormal operating issues relating to
system undervoltage.

IEEE C37.102 IEEE Guide for AC Generator Protection does


not recommend use of the 27 function for tripping,
pp g but only
y to
alarm to alert operators to abnormal conditions that require
operator intervention.
Manufacturers recommend operator action up to and including
reduction in unit output rather than a unit trip.

Undervoltage Protection Function 27


34

2. Purpose
p
of Function 27 on the Generator Auxiliary
y
System
These relays are used to protect auxiliary system equipment
f
from
severe undervoltage
d
lt
conditions
diti
that
th t would
ld have
h
serious
i
consequences, such as auxiliary motors stalling or voltage
collapse for the generating unit(s).
These relays initiate alarming, automatic transfer to an
alternative power supply, starting of emergency generator(s), or,
if necessary, generator tripping.

3. Purpose of Function 27 at Point of Common Coupling


These relays are used to alert the operator that an undervoltage
condition is occurring on the transmission system.

Coordination of Generator and


Transmission System
y
Function 27
Faults
The undervoltage function should never trip for a transmission
system fault condition.
The p
protection should be set to coordinate with the longest
g
clearing time and reclosing times for faults on transmission
system elements connected to the high-side bus.

Loadability
The preferred method is to alarm only.
If the undervoltage function is used to trip the unit
unit, the
undervoltage function should not trip the generator for a
recoverable system event.
D
Defined
fi d as a sustained
t i d ttransmission
i i system
t
voltage
lt
att th
the hi
high-side
h id
of the generator step-up transformer of 0.85 per unit.

35

Coordination of Generator and


Transmission System
y
Function 27
Considerations and Issues
Loss of generating units due to tripping by undervoltage
protection or operator action during a system fault or recoverable
system event must be avoided
avoided.
If undervoltage tripping is applied on the generator and an
Undervoltage Load Shedding (UVLS) program is used in the
t
transmission
i i system,
t
th
the UVLS sett points
i t and
d time
ti
delays
d l
mustt
be coordinated with the generator undervoltage protection.
The generator set points should be modeled in system studies to
verify coordination.
A simple relay-to-relay setting coordination is inadequate due to
differences in voltage between the generator terminals and
transmission or distribution buses where the UVLS protection is
implemented.

36

Coordination Procedure Function 27


37

Alarm
IEEE C37.102
C37 102 IEEE Guide for AC Generator Protection does not
recommend use of the 27 function for tripping, but only to alarm to alert
operators to take necessary actions.
Undervoltage element (function 27) calculation:
V27 = 90% of Vnominal = 0.9 x 120 V = 108 V with a 10 second time delay to
prevent nuisance alarms (per IEEE standard C37.102).

Tripping (not recommended)


CAUTION: If the Generator Owner uses the 27 function for tripping, the
following condition must be met at a minimum:
Time delay of the undervoltage element trip must be longer than the greater
of the local or remote backup clearing times for all transmission elements
connected
t d tto the
th high-side
hi h id b
bus, b
butt nott lless th
than 10 seconds.
d

Undervoltage element (function 27) calculation:


V27 = 87% of Vnominal = 0.87 x 120 V = 104 V with a coordinated time delay
N
Note:
t A
An 87 percentt sett point
i t was selected
l t db
because th
the power plant
l t iis nott
capable of continued operation at this voltage level, and it allows for a
reasonable margin for extreme system contingencies.

Example Function 27
38

Proper
p Coordination
If the undervoltage function is set to trip the generator:
The threshold setting is below 90 percent at the generator terminals,
and
An adequate time delay is applied to allow system recovery above
this level.

Improper Coordination
If the undervoltage function is set to trip the generator:
A threshold setting at or above 90 percent at the generator
terminals, and/or
Inadequate time delay to allow system recovery .

Summary of Protection Functions


Required
q
for Coordination Function 27
Table2Excerpt Function27(Gen.Prot.)ProtectionCoordinationConsiderations
GeneratorProtection
Function

TransmissionSystemProtectionFunctions

27 GeneratorUnit
UndervoltageProtection
**ShouldNotBeSetto
Trip,AlarmOnly**
Iffunction27trippingis
ff
usedforanunmanned
facility thesettingsmust
coordinatewiththe
stressedsystemconditionof
0.85perunitvoltageand
time delays set to allow for
timedelayssettoallowfor
clearingofsystemfaultsby
transmissionsystem
protection,including
breakerfailuretimes.

21
27ifapplicable
87B
87T
50BF
Longesttimedelayfortransmissionsystem
protection to clear a fault
protectiontoclearafault

SystemConcerns

Mustnottripprematurelyforarecoverableextremesystem
eventwithlowvoltageorsystemfaultconditions
t ith l
lt
t
f lt
diti

UVLSsetpoints andcoordinationifapplicable

Settingsshouldbeusedforplanningandsystemstudies
eitherthroughexplicitmodelingofthefunction,orthrough
monitoringvoltageperformanceattherelaylocationinthe
stabilityprogramandapplyingengineeringjudgment

Mustcoordinatewithtransmissionlinereclosing

39

Protection Function Data and Information


Exchange
g Required
q
for Coordination Function 27

Table3Excerpt Function27(Gen.Prot.)DatatobeExchangedBetweenEntities

G
GeneratorOwner
t O

Relaysettings:Undervoltagesetpointifapplicable,
includingtimedelays,atthegeneratorterminals

T
TransmissionOwner
i i O

Timedelayoftransmissionsystemprotection

Pl
PlanningCoordinator
i C di t

Feedbackonproblemsfoundin
coordinatingwithstressedvoltage
conditionstudiesandifapplicable,UVLS
studies

40

Summary of Protection Functions


Required
q
for Coordination Function 27
Table2Excerpt Function27(PlantAux.)ProtectionCoordinationConsiderations

GeneratorProtection
Function

27 PlantAuxiliary
27
Plant Auxiliary
Undervoltage
IfTrippingisused the
correctsetpointand
adequatetimedelaysoit
doesnottripforsystem
faultsandrecoverable
extremesystemevents

TransmissionSystemProtection
Functions

21
27ifapplicable
87B
87T
50BF
Longesttimedelayfortransmissionsystem
protection to clear a fault
protectiontoclearafault

SystemConcerns

Coordinatetheauxiliarybusprotectionandcontrolwhen
connecteddirectlytotheHighVoltagesystem

GeneratorOwnertovalidatetheproperoperationof
Generator
Owner to validate the proper operation of
auxiliarysystemat8085percentvoltage.Theundervoltage
tripsettingispreferredat80percent

GeneratorOwnersvalidatetheproperoperationofauxiliary
systemat0.80.85perunitvoltage

Settingsshouldbeusedforplanningandsystemstudies
eitherthroughexplicitmodelingofthefunction,orthrough
monitoringvoltageperformanceattherelaylocationinthe
stabilityprogramandapplyingengineeringjudgment

41

Protection Function Data and Information


Exchange
g Required
q
for Coordination Function 27

Table3Excerpt Function27(PlantAux.)DatatobeExchangedBetweenEntities

GeneratorOwner

Relaysettings:Undervoltagesetpointif
applicable,includingtimedelays,atthe
powerplantauxiliarybus

TransmissionOwner

Timedelayoftransmissionsystemprotection

PlanningCoordinator

Feedbackonproblemsfoundin
coordinatingwithstressedvoltage
conditionstudies,andifapplicable,UVLS
studies

42

Summary of Protection Functions


Required
q
for Coordination Function 27

Table2Excerpt Function27(PlantHVSystemSide)ProtectionCoordinationConsiderations

GeneratorProtection
Function

TransmissionSystemProtectionFunctions

27 PlantHighVoltage
systemsideundervoltage

21
27ifapplicable
87B
87T
50BF
Longesttimedelayfortransmissionsystem
protectiontoclearafault

SystemConcerns

Mustnottripprematurelyforarecoverableextremesystem
eventwithlowvoltageorsystemfaultconditions

UVLSsetpoints andcoordinationifapplicable

Settingsshouldbeusedforplanningandsystemstudies
eitherthroughexplicitmodelingofthefunction,orthrough
monitoringvoltageperformanceattherelaylocationinthe
stabilityprogramandapplyingengineeringjudgment

43

Protection Function Data and Information


Exchange
c a ge Required
equ ed for
o Coo
Coordination
d at o Function
u ct o 27

Table3Excerpt Function27(PlantHVSystemSide)DatatobeExchangedBetweenEntities

GeneratorOwner

Relaysettings:Undervoltagesetpointif
applicable,includingtimedelays,athigh
pp
g
y
g
sidebus

TransmissionOwner

y
y
p
Timedelayoftransmissionsystemprotection

PlanningCoordinator

Feedbackonproblemsfoundincoordinating
withstressedvoltageconditionstudiesandif
g
applicable,UVLSstudies

44

Overvoltage Protection Function 59


45

Purpose
Prevent an insulation breakdown from a sustained overvoltage
condition.

59
GSU

Insulation of
Stator
Windings

Surge
Arrester
Surge
Capacitor

Coordination of Generator and


Transmission System
y
Function 59
Faults
There are no coordination requirements for system faults given
the high voltage set point and long delay; tens of seconds or
longer.
longer

Loadability
Coordination for extreme system events resulting in overvoltage
should be considered when a trip threshold is utilized at 1.1 per
unit nominal voltage.
E
Even when
h significant
i ifi
t ttrip
i d
delay
l iis applied
li d ((e.g. 10 seconds
d or
longer).

For credible contingencies where overvoltage may occur,


available voltage control should be coordinated with the trip time
setting on the generator.

46

Coordination of Generator and


Transmission System
y
Function 59
Considerations and Issues
Function 59 protection is mainly provided for the generator stator
winding insulation.
Surge arrestors protect the stator from overvoltages caused by
lightning, impulses, and inrush.
The 59 function provides backup protection for these hazards.

Wh
When the
th generator
t voltage
lt
regulator
l t is
i operating
ti normally
ll and
d
keeps the generator terminal voltage within 105 percent of
nominal, there are no system coordination issues.
Pl
Planners and
d operational
ti
l planners
l
need
d tto understand
d t db
both
th th
the
performance of the voltage regulator and the overvoltage relay
settings when studying extended-time, overvoltage system
conditions.

47

Coordination Procedure Function 59


48

Setting Considerations
Two types of relays of (or elements) are commonly
used on a g
generator p
protection.
An instantaneous function (59I), applied at 130 150 percent
of nominal voltage.
A time delayed function (59T), applied at about 110 percent
of nominal voltage.

Example Function 59
49

Proper
p Coordination
The following is an example of setting the 59T and 59I element
time delays.
Step 1 Vnominal = (20,000V) (120/20,000) = 120V
Step 2 59T = 105% of 110% of Vnominal = 1.05 x 1.10 x 120V
=139V
139V (=1.155
( 1.155 pu), with a time delay of 10 seconds or longer.
Step 3 59I =105% of 130% of Vnominal = 1.05 x 1.30 x 120V
=184V (=1.365 pu)

Improper Coordination
A threshold setting lower than 110 percent voltage at the
generator terminals and/or an inadeq
inadequate
ate time dela
delay.

Example Function 59
50

Figure 3.11.3 Typical Example Load Rejection Data for Voltage


Regulator Response Time

Figure 3.11.3 is a typical load rejection response curve of a voltage


regulator for an example of a hydro turbine generator.
The regulator causes the generator to operate back near nominal
voltage in about two seconds
seconds, well before any action by the overvoltage
protection.

Summary of Protection Functions


Required
q
for Coordination Function 59

Table2Excerpt Function59ProtectionCoordinationConsiderations

GeneratorProtection
Function

TransmissionSystemProtectionFunctions

SystemConcerns

59 Overvoltage

59(whenapplicable)

Settingsshouldbeusedforplanningandsystemstudieseither
throughexplicitmodelingofthefunction,orthrough
monitoring voltage performance at the relay location in the
monitoringvoltageperformanceattherelaylocationinthe
stabilityprogramandapplyingengineeringjudgment

51

Protection Function Data and Information


Exchange
c a ge Required
equ ed for
o Coo
Coordination
d at o Function
u ct o 59

Table3Excerpt Function59DatatobeExchangedBetweenEntities

GeneratorOwner

TransmissionOwner

Relaysettings:settingandcharacteristics,
includingtimedelaysettingorinversetime
characteristic,atthegeneratorterminals

Pickupandtimedelayinformationofeach59function
appliedforsystemprotection

PlanningCoordinator

None

52

Overfrequency and Underfrequency


Generator Protection Function 81
Purpose
Protect the turbine against
g
the p
potential impacts
p
of operating
p
g
at off-nominal frequency.

Figure 3.14.1 Typical Location of Generator Frequency


Relays and Load Shedding Relays Requiring Coordination

53

Coordination of Generator and


Transmission System
y
Function 81
Faults
There are no coordination issues for system faults for
this function.

Loadability
Th
There are no coordination
di ti issues
i
related
l t d to
t loadability
l d bilit
for this function.

54

Coordination of Generator and


Transmission System
y
Function 81
Other Operating Conditions
Coordination is necessary to allow the UFLS program to stabilize
frequency at a sustainable operating condition.
Generator UF protection and the UFLS program must be
coordinated to permit load shedding to arrest frequency decline
and recover frequency to a sustainable operating condition.
If this is not possible, most regions require accounting for unit
tripping in UFLS design assessments and require UFLS program
modifications such as arming additional "compensating"
compensating load
shedding.

Generator OF protection and the UFLS program must be


prevent g
generator tripping
pp g due to frequency
q
y
coordinated to p
overshoot.
It is important to note that the coordination is not a relay-to-relay
coordination in the traditional sense; rather it is coordination
between the generator prime mover capabilities
capabilities, the over and
underfrequency protection, and the UFLS program and
transmission system design.

55

Coordination of Generator and


Transmission System
y
Function 81
Considerations and Issues
G
Generator
t off-nominal
ff
i l ffrequency protection
t ti should
h ld b
be
coordinated with the governor settings.
Ensure that protection does not trip the unit for a condition from
which the governor could restore the unit to an acceptable operating
condition.

Turbine limits should be obtained from the turbine manufacturer


in order to properly set the over and underfrequency protection.
protection
When it is necessary to apply underfrequency protection, settings
must consider turbine limits that account for both frequency and
time at frequency.

In some plant designs, critical station service load may be


supplied from a motor-generator (M-G) set.
When frequency protection is located on the load side of the M-G
set, the protection settings must account for the frequency
difference between the system and the load.

56

Coordination of Generator and


Transmission System
y
Function 81

57

Considerations and Issues (cont.)


Note that generator frequency protection is not coordinated
directly with the UFLS relay settings:
S
Subsequent
bseq ent to the UFLS program operating to shed load
load, a time
delay will exist before frequency decline is arrested and recovery
begins.
This time delay,
delay as well as the rate at which frequency recovers
recovers, is a
function of the physical characteristics of the system including types
of load, generating unit inertia, and governing response.

It is important to understand the protection function limitations


limitations.
Some relays are blocked automatically if the system frequency or
voltage is outside the range of relay specifications, while other
relays remain in
in-service
service but are subject to misoperations
misoperations.

Coordination Procedure Function 81


58

Step 1 Planning Coordinator provides the regional


underfrequency load shedding and generator off
off-nominal
nominal frequency
protection setting criteria.
Step 2 Generator Owner and Planning Coordinator verify that the
generator off-nominal
off nominal frequency protection is set to coordinate with
the regional UFLS program design and generator off-nominal
frequency protection setting criteria.
Step 3 If coordination cannot be achieved without compromising
protection
t ti off the
th generating
ti unit,
it th
the Pl
Planning
i C
Coordinator
di t performs
f
studies to assess the impact on the UFLS program design and
identify modifications, if necessary, to accommodate the generator
protection setting while ensuring the UFLS program continues to
meett its
it design
d i objectives.
bj ti

Example Function 81
59

Proper
p Coordination
The following Figure 3.14.3 illustrates an example of how
generator protection settings are coordinated with the turbine
p
y and the underfrequency
q
yp
protection setting
g limits for
capability
generating units.
In this example the protection setting must be set above the
green curve which defines the turbine capability
g
p
yp
provided by
y the
manufacturer and on or below the red curve that defines the
applicable generator underfrequency protection setting limits.
In this example the protection is set with an instantaneous trip
threshold at 57.7 Hz and a time delayed threshold setting at 58.5
Hz with a definite time delay of 60 seconds. Both settings
coordinate in this example.

Example Function 81
60

60

59.5

58.5

Fre
equency (Hz)

59

58

57 5
57.5

0.1

10

100

1000

57
10000

Time (sec)
Generator Capability

Generator UF Protection Limit

Generator Protection Setting-Inst

Generator Protection Setting-TD

Figure 3.14.3 Generator Underfrequency Protection Setting Example

Summary of Protection Functions


Required
q
for Coordination Function 81
Table2Excerpt
p
Functions81U/81OProtectionCoordinationConsiderations
/

GeneratorProtection
Function

81U Underfrequency
81O Overfrequency

TransmissionSystemProtectionFunctions

81U
81O
Note:UFLSdesignisgenerallythe
responsibilityofthePlanningCoordinator

SystemConcerns

Coordination with system UFLS setpoints andtimedelay


CoordinationwithsystemUFLSsetpoints
and time delay
(typicallyachievedthroughcompliancewithregionalfrequency
standardsforgenerators)

Meetunderfrequency overfrequency requirements

Autorestartofdistributedgenerationsuchaswindgeneration
duringoverfrequency conditions

Settingsshouldbeusedforplanningandsystemstudieseither
throughexplicitmodelingofthefunction,orthrough
monitoringfrequencyperformanceattherelaylocationinthe
stabilityprogramandapplyingengineeringjudgment

61

Protection Function Data and Information


Exchange
c a ge Required
equ ed for
o Coo
Coordination
d at o Function
u ct o 8
81

Table3Excerpt Functions81U/81ODatatobeExchangedBetweenEntities

GeneratorOwner

Relay settings and time delays


Relaysettingsandtimedelays

TransmissionOwner

None

PlanningCoordinator

Feedbackonproblemsfoundbetween
underfrequency settingsandUFLSprograms

62

What is Important to Coordination


63

Settings
g That Protect the Generator
Time Coordination with UFLS and UVLS
Islanding Conditions
Sufficient Studies

Settings that Protect the Generator


64

The g
generator p
protection set-points
p
are described in the
IEEE Guide for AC Generator Protection (C37.102) for
Functions 24, 27, 59, and 81.
The times to trip or alarm are adjusted based on the
specific generator and application limits as well as
coordination with system functions and schemes
schemes.
Examples of these were given in the presentation, but
again,
g , specific
p
settings
g need to be determined by
y the
entities.

Time Coordination with UFLS and UVLS


65

Coordination of g
generator p
protection with UFLS and
UVLS programs is essential to surviving extreme
operating conditions from which the system is capable of
recovering.
recovering
As noted, coordination is not a typical relay-to-relay
coordination.
coordination
System studies are required to verify coordination
between the g
generator p
protection,, the UFLS and UVLS
program settings, and the system response to severe
events.

Consideration of Islanding Conditions


66

The protection must be set to avoid unnecessary tripping for worst


case survivable
i bl conditions:
di i
Operation of transmission equipment within continuous and emergency
thermal and voltage limits
Recovery from a stressed system voltage condition for an extreme
system event i.e. 0.85 pu voltage at the system high side of the
generator step-up transformer
Stable power
po er swings
s ings
Transient frequency and voltage conditions for which UFLS and UVLS
programs are designed to permit system recovery

When coordination cannot be achieved without compromising


protection of the generator, the generator protection setting must be
accounted for in system studies.

Sufficient Studies
67

The Planning
g Coordinator must study
y a number of
operating conditions sufficient to bound the worst case.
Assess sensitivity of generator and system response to:
System load level
Generator loading (both active and reactive power)
Commitment and dispatch of other generators
System operating states (N-0, N-1, . . .)

The most limiting operating condition may vary among


protective functions or even for different settings for a
single protective function
function.

68

Question & Answer


Q
Contact:
Phil Tatro
Senior Engineer, System Analysis
and Reliability Initiatives
phil.tatro@nerc.net
hil t t @
t
508.612.1158

Вам также может понравиться