Академический Документы
Профессиональный Документы
Культура Документы
Abstract
Many West Africa Offshore Fields are maturing and operators are completing secondary targets in their wells to
maintain the economic operation of their valuable assets. However, the capital expenditure associated to this kind
of interventions of critical importance. It follows that the selection of the right and most remunerative well activities
is crucial.
In the Kitina Field, offshore from Pointe Noire, Congo, deeper sands have been produced to economic depletion
and reservoir studies allowed the determination of alternative production intervals for production maintenance.
Large quantities of reserves can be found in low permeability, consolidated, formations as well as in very deep and
remote culminations.
From March 2007 to June 2007, the Kitina field production increased of 80% reaching a production level lost since
early 2004. This was achieved by infilling the Kitina South culmination with the long reach and ultra deep well KTMSM5 and via a massive multistage hydraulic fracturing campaign carried out on the three wells draining the low
permeability 3A reservoir. These represented the first applications in Congo of such technology. Eight hydraulic
propped fractures were placed in three re-completed, cased-hole wells in the with very encouraging production
improvements. A stabilized production increase ranging from 2 to 3 times was achieved.
The paper describes the unique reservoir modeling, operation geology, and drilling, completion and production
challenges encountered in the 2007 Kitina successful rejuvenation campaign. In particular, it focuses on the
successful multi-stage hydraulic fracture campaign carried out on four wells of the Kitina 3A reservoir from the
preliminary design and production forecast pre-job to the reservoir model history match and forecast phase postjob.
Introduction
The Kitina Marine, Congolese offshore field, has been discovered through the exploration well KTNM-1 in 1991.
Two appraisal wells were drilled later on which confirmed the discovery. The fields production starts up took place
in December 14th 1997 via 13 wells (8 oil producers and 5 potentially water injectors).
The Kitina field is composed by the following 5 levels:
3A limestone , sandstone with silty clay
2A Limestone: Oolitic Grainstone/Packstone, bioclastic with good intergranular porosity and intercalation
of sandstone with carbonate cement.
2A South Culmination: Oolitic Grainstone/Packstone, bioclastic with good intergranular porosity and
intercalation of sandstone with carbonate cement.
[OTC-19455]
Three reservoirs 2A, 1A and 1B were originally drained via a peripheral water injection scheme and a crestal gas
injection. The intial production rate of the field was around 50,000 BOPD (1997) thereafter a 10 years period drop
to 7,000 BOPD.
Due to the field depletion, some wells have been put under an artificial lift system, initially with ESP and now with
gaslift. In terms of recovery factor for each reservoir, it has been evaluated at about 15% for the 1B reservoir and
between 25-30% of 1A and 2A. As it could be noticed the potentiality of the field is still high. In order to start up a
rejuvenation process of the fields it has been decided to perform a full review of the field potentialities which ended
up by an ambitious plan made up as follow:
Optimize the recovery of the reservoir 3A (previously considered as marginal due to the low permeability
and low production rates of the 3 wells already completed) via a massive hydraulic fracturing campaign
Drill a long reach and ultra deep well (KTM-SM5) on the south Kitinas field structure in the level 2A, south
culmination.
Reservoir 3A
The evaluation of the productive potential of the reservoir 3A has been studied doing a correlation with a similar
sequence of an other field, Sounda Marine field, located 8km EST from Kitina. This level has been identified as
composed of silts with intercalation of sandstone and clays. The formation permeability to oil is ranging form 2 to 7
mD.
Three existing wells have been completed (KTM-W6ST, KTM-107 and KTM-111) in this reservoir from 2005 to
2006. Everyone was producing in natural flow but completed with gaslift mandrel in order to accelerate the well
clean up during the start up production phase. The reservoir 3A oil production potential, from those three wells, has
been of around 800 BOPD. At their steady-state flow, the oil production rate was as flow:
Subsequently the production rate of those three (3) wells progressively declined until heading to the non
economical plateau. In order to propose an in-depth solution to this production decline a study was carried out by
Eni Congo and Eni E&P with the aim to re-establish the reservoir 3A production to a viable economic level (more
than 1500 BOPD) without drilling new wells or performing heavy workover operations. Due to this operation
contraints and also linked to the ecomical aspect, only a rigless operation could be possible. Considering the fact
that the reservoir 3A is composed of soft sand, it has been proposed to study the hydraulic fracturation method.
Study results shown that a multi stage fracturation with a half length of 45 m would improve the production rate of
at least two times in steady state. Additional reserves increase to 3.7 Mbbl. The work over cost was optimized by
taking into consideration the presence of the Barraccuda a tender assited rig. The Net present value of each
intervention vary from 21M$ to 34 M$ with a pay out time ranging from 3 to 4 months.
With those hypotheses, additional reserves 2P associated to the three interventions are of 3.7 Mbbls, as previously
mentioned, with 0.57 Mbbl in 2007 (see tabl.)
KBBL/AN
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
TOTAL [KBBL]
KTM-111ST
220
245
163
152
128
117
100
93
77
73
67
55
25
1515
KTM-W6ST2
200
240
128
124
98
80
72
58
53
42
35
30
15
1175
KTM-107ST
150
165
103
102
82
78
65
60
57
48
45
40
17
1012
TOTAL [KBBL]
570
650
394
378
308
275
237
211
187
163
147
125
57
3702
Tab.1 Increment of the annual production 2P associated to the hydraulic fracturations interventions respect to the
[Paper Number]
case Do Nothing
It has been noticed that 15-20% the reserves are already recoverable in 2007. The best productivity of the 3 wells
requires an acceleration of the recuperation during the contractual period with an increase of the reserves of the
estimated reservoir 3A like follows:
Reserve P1: + 1.5 Mbbl @ 20-06-2019 (end of the license)
Reserve P2: + 2.2 Mbbl @ 20-06-2019 (end of the license)
Reserve 2P: + 3.7 Mbbl @ 20-06-2019 (end of the license).
Below are summarize results of the study
Period 2007-2019
KTM-111ST
KTM-W6ST2
KTM-107ST
TOTAL
1.5
1.2
3.7
NPV [M$]
34.5
29.8
21.0
85.3
[OTC-19455]
interval and 91,528 lb of 20/40 ISP was placed into the middle perforated interval. The third fracture treatment was
placed three days later with 178,802 pounds of 20-40 ISP.
The third candidate well was KTM 107, this well also had three intervals but the lowermost perforations were close
to an Oil Water Contact so it was decided that the lowermost perforations would have a packer above the lower
perforations, the port opened, but the interval would not be fractured. Two factures were generated, the fracture of
the middle intervals occurred on June 9, 2007 and was performed as expected and placed the designed 99,000 lbs
of ISP into the middle interval. Eight days after the initial propped fracture, a mini-frac with a step down was
pumped. It was determined that the well was behaving normally and a pumping schedule was created. 133,000 lbs
of proppant was placed.
WELL NAME
num. frac
reservoir
permeability
Q oil
PRE-FRAC
[BOPD]
Q oil initial
POST FRAC
[BOPD]
Q oil steadystate
POST FRAC
[BOPD]
160
2100
(x 10)
600
(X3)
+ 400 BOPD
300
900
(x 3)
650
(X2)
+ 350 BOPD
130
1000
(x 7)
700
(X4)
+ 550 BOPD
KTM-W6
(3 fracs)
Kitina 3A
(10 md)
KTM-111
(3 fracs)
Kitina 3A
(10 md)
KTM-107
(2 fracs)
Kitina 3A
(10 md)
An overall steady-state increase (after 90 days) for these three wells from 600 to 1950 BOPD for a Fold of Increase (FOI) of
3.3 (+230%) (Figure1). A further production decline is expected. However, stabilization to a long term FOI of 2-2.5 is
foreseen.
2400
400
Kitina - Level 3A
2100
350
300
Qo
1500
250
FRAC
1200
200
900
150
600
100
300
50
0
Dec-04
Dec-05
Qo [BOPD]
Dec-06
GOR [Sm3/m3]
G O R /10 & W C
1800
0
Dec-07
WC [%]
[Paper Number]
An integrated study was done on the 2A level by ENI E&P and delivered to Eni Congo in May 2006.
The scope of the study was to perform the revision of the seismic of the reservoir, the structural interpretation, a
sedimentological study, the geochemistry and the study of the reservoir with a geological characterisation and
dynamic modalisation.
Concerning the reservoir study, the mains results are summarized in the following table.5 which the hydrocarbon in
place:
Level
sequence 2
OOIP [Mstb]
OGIP [MSm3]
2Aeq
11.89(*)
4850
2A3
21.73
2A4
5.41
2A5
21.14
TOTAL
48.28
4850
Table.5
Dynamic model
1) Construction of the dynamic model
The dynamic model has been constructed according to the hypothesis that levels 2A3 and 2A4 are in hydraulic
communication whereas the level 2A5 is separated.
The level L 2Aeq mineralised with condensate gas is completely separated from other levels.The southern
culmination of level 2A3 has a different hydraulic flow regime.
Therefore, four (4) balanced region are used in the field model
Data from RFT and DST have been used for the construction of the dynamic model.
2) History match
For the history match, production data from KTNSM3 have been used. The matched was obtained by adjusting the
aquifer parameters.
The selected cases of the production forecast are as follow:
a) Do nothing
b) New infilling well (KTNSM5)
c) New infilling well + water injector
d) New infilling well multi lateral
[OTC-19455]
Reserves @ 01-01-2022
[Mbbls]
R.F.
[%]
a) Do nothing
5.65
11.7
b) KTNSM5
7.48
15.5
c) KTNSM5 + WI
8.24
17.1
d) Bi-drain
7.64
15.8
e) Bi-drain + WI
9.00
18.7
8.26
17.1
Case
Table.6
The balance between the economic and the RF associated to the intervention proposed showed that it was more
advantageous to drill and put in production the well KTNSM5. The expected production trend is presented in the
following graphs.
[Paper Number]
DATE:
SINGLE COMPLETION
VERTICAL
ICGP
OHGP
ARPO 20 / C
DEVIATED
[tons]
Top:
[m]
7''
Bottom:
[m]
Density:
75
100
Casing
125
Model type
I.D.
Depth
14.33
Actual
500
-lbs.
lbs.
HYDRAULIC PERMANENT
1000
COMPLETION STRING
Tubing
lb/ft
3-1/2
2-7/8''
9.30
6.50
Bottom (m)
L-80
L-80
53,5
29
CSG/LIN OD
TOP AT mt
SHOE AT mt
CEM UP mt
7'' @
4800 m
LINER HANGER :
LINER HANGER :
CASINGS CHARACTERISTICS
STEEL
L-80
L-80
THRD
AMS28
BTC
6175
lbf/ft
D mm
53,5
29
#
Steel Gr.
S.V
Down to
247
250
5015
L-80
L-80
-ftlbs
REF
LINER HANGER :
Nom. O.D.
1500
API 5A-2
Tools
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
ID
OD
4.06
4.06
2.99
2.99
2.99
2.99
2.81
2.99
2.44
2.44
2.44
2.35
2.44
2.44
2.44
2.35
2.44
2.44
2.44
2.35
13.37
4.50
3.50
3.50
3.50
3.50
5.00
3.50
3.90
2.875
2.875
4.75
2.875
3.50
2.875
4.75
2.875
3.50
2.875
4.75
2.44
2.44
2.44
2.44
4.78
4.75
2.99
2.99
2.99
2.50
2.99
2.99
2.99
DEPTH
14.33
14.66
A
15.13
16.54
242.50
245.39
247.37
248.78
B
249.89
987.46
988.10
990.16
990.83
C
2024.40
2025.03
2027.08
2027.85
2819.88
2820.52
2822.58
2.875 2823.35
2.875 4511.57
2.875 4513.46
3.90 4514.33
7.00 4515.03 PKR
8.28 4516.89
4518.77 9-5/8''
4519.07
3.50 4520.53 LNR HGR
3.50 5734.41
3.50 5736.38 SHOE
5736.97
3.50 5738.42 7''-29 #
3.50
5741.35
5750.70
2000
GLM
990,16
GLM
2027,08
2500
GLM
9-5/8''
SHOE
3000
3500
4000
4500
4516.89
SC-2PAH
5000
5500
4546
H
00
00
00
00
LNR HGR
PERFORATED DEPTH
2822.58
Thread
HYD-CS
HYD-CS
MAKE UP TORQUE :
PRODUCTION CASING
Top (mMD)
50
SIZE
TYPE
lb/ft
GUNS OD
TYPE OF CHARGE
SHOOT DENSITY
Manufact.
25
Plan
TUBING HANGER
WELL HEAD
9-5/8"
7"
5''
Packer
Nom. O.D.
DESCRIPTION
TO m
Time (Days)
[kg/l]
BARRACUDA
X-MAS TREE
BONNET
BACK PRESSURE VALVE
OD NOM
KTSM5
Time vs Depth
ESP
Filtered
WELL HEAD
9-5/8" AMS
BTC
7"
SELECTIVE
[in]
GENERAL INFORMATIONS
Nom OD Thd
12J5B9011
Account
HORIZONTAL
40/60
[tons]
[y/n]
no
DRILLING PERIOD
RIG USED
RT/TIE DOWN
WELL HEAD RATING
TOTAL DEPTH
TOP CMT (COLLAR)
BRIDGE PLUG
ANNULUS FLUID
BTM CHECKED ON
GEOG COORD LAT
GEOG COORD LONG
KITINA SM-5
WELL NAME
String weight up
Make up report
KITINA
FIELD NAME
Eni Congo
Affiliate Company
GROUP
0000
0000
4800
6000
LINER
6500
5744
5808
6175
NOTES :
NOTA BENE = COTES GAS LIFT MANDREL
1 G L MAND KICK-OFF VALVE ORIF 8/64 '' OP,PRES DE 94,2 A 96,2 BARS
2 G L MAND KICK-OFF VALVE ORIF 8/64 '' OP,PRES DE 92 A 94 BARS
3 G L MAND GAS LIFT VALVE ORIF 14/64 ''
Rig Supervisor
N.MARCHAL/H.MANTINOU
DEPTH
A
B
C
Super Intendant
FRANCOIS POUNGA
Actual production
Oil rate
WC
Forecasted production
[OTC-19455]
CONCLUSION
50000
Qo [BOPD]
45000
FIELD OF KITINA
40000
35000
Qo
30000
Production increased of
5000 bopd
25000
20000
15000
10000
5000
0
dc-97
dc-98
dc-99
dc-00
dc-01
dc-02
dc-03
dc-04
dc-05
dc-06
Qo [BOPD]
Acknowledgements
The authors wish to thank the Eni Congo management, its different technical departments for permission and
encouraging the implementation the project.
We would also like to thank everyone who has contributed to the said project with their constructive comments.
[Paper Number]
References
1. Bagzis, J.M., et al: Optimized Hydraulic Fracturing Improves Oil Production in the NDola Field, Offshore
Angola, SPE 49108 presented at the 1998 Annual Technical Conference and Exhibition held in New Orleans,
LA, USA, 27-30, September 1998.
2. Barba, R.E. and Shook, R.A.: Post Frac Evaluation of Multiple Fracture Treatments Using the Completion
Efficiency Concept, SPE 90483 presented at the 2004 Annual Technical Conference and Exhibition held in
Houston, TX, USA, 26-29, February 2004.
3. Butter, M., East, L, and Kuvshinov, I.: Post Frac Evaluation of Multiple Fracture Treatments Using the
Completion Efficiency Concept, SPE 102633 presented at the 2006 SPE Russian Oil and Gas Technical
Conference and Exhibition held in Moscow, Russia, 3-6, October 2006.
4. Internal Documents.
5. Jain, S. et al, Case Study from 12 Successful Years of High Temperature Fracturing in Bach Ho Field
Offshore Vietnam, SPE 106712 presented at the 2007 SPE Production and Operations Symposium held in
Oklahoma City, OK, USA, 31 March 3 April, 2007.
6. Lietard, O., Ayoub, J., Pearson A.,: Hydraulic Fracturing of Horizontal Wells: An Update of Design and
Execution Guidelines, SPE 37122 presented at the 2nd International Three-Day Conference and Exhibition on
Horizontal Well Technology held in Calgary, Alberta, Canada, 18-20, November 1998.
7. Lohoefer, D., Athans, J. and Seale, R.: New Barnett Shale Horizontal Completion Lowers Cost and Improves
Efficiency, SPE 103046 presented at the 2006 Annual Technical Conference and Exhibition held in San
Antonio, TX, USA, 24-27, September 2006.
8. Neumann, L.F., et al: Case Study of Multiple Hydraulic Fracture Completion in a Subsea Horizontal Well,
Campos Basin, SPE 98277 presented at the 2006 SPE International Symposium and Exhibition on Formation
Damage Control held in Lafayette, LA, USA, 15-17, February 2006.
9. Rodrigues, V.F., et al: First Applications of a Multiple Fracturing in Noncemented Horizontal Offshore Wells,
SPE 94583 presented at the SPE Latin American and Caribbean Petroleum Engineering Conference held in
Rio de Janeiro, Brazil, 20-23, June 2005.
10. Rodrigues, V.F., et al: Horizontal Well Completion and Stimulation Techniques A Review With Emphasis on
Low-Permeability Carbonates, SPE 108075 presented at the SPE Latin American and Caribbean Petroleum
Engineering Conference held in Buenos Aires, Argentina, 15-18, April 2007.
11. Seale, R., Athans, J. and Themig, D.: An Effective Horizontal Well Completion and Stimulation System, SPE
101230 presented at the 2006 Abu Dhabi International Petroleum Exhibition and Conference held in Abu
Dhabi, UAE, 5-8, November 2006.
12. Seale, R., Donaldson, J. and Athans, J.: Multistage Fracturing System: Improving Operational Efficiency and
Production, SPE 104557 presented at the 2006 Eastern Regional Meeting held in Canton, OH, USA, 11-13,
October 2006.
13. Seale, R., Themig D. and Athans, J.: Effective Stimulation of Horizontal Wells - A New Completion Method,
SPE 106357 presented at the 2006 SPE Technical Symposium of Saudi Arabia Section held in Dhahran,
Saudi Arabia, 21-23, May 2006.
14. D. Baldini, L.Riccobon, A. Baioni, Drilling and completion program of KTMSM5 (Eni Congo).