44626 Federal Register / Vol. 70, No.

148 / Wednesday, August 3, 2005 / Notices

preparation of preliminary engineering DEPARTMENT OF ENERGY on March 1, 2005, Notice Issued: April
plans, and a study of environmental 5, 2005, Due Date: June 5, 2005.
impacts. Based on the results of these Federal Energy Regulatory l. Description of Project: The proposed
studies, the Applicant would decide Commission project using the Corps’ Red Rock Lake
whether to proceed with the preparation Dam and would consist of: (1) A
of a development application to Notice of Application Accepted for proposed intake structure, (2) three
construct and operate the project. Filing and Soliciting Comments, proposed 16-foot-diameter steel
Motions to Intervene, and Protests penstocks, (3) a proposed powerhouse
r. Comments, Protests, or Motions to
July 27, 2005. containing three generating units with a
Intervene—Anyone may submit
Take notice that the following total installed capacity of 36 megawatts,
comments, a protest, or a motion to
hydroelectric application has been filed (4) a proposed transmission line, and (5)
intervene in accordance with the
with the Commission and is available appurtenant facilities. The Red Rock
requirements of Rules of Practice and
for public inspection: Hydroelectric Development Company’s
Procedure, 18 CFR 385.210, .211, .214.
a. Type of Application: Competing project would have an average annual
In determining the appropriate action to
preliminary permit. generation of 110 gigawatt-hours.
take, the Commission will consider all m. Locations of Applications: A copy
protests or other comments filed, but b. Project No: 12600–000.
c. Date Filed: June 29, 2005. of the application is available for
only those who file a motion to inspection and reproduction at the
intervene in accordance with the d. Applicant: City of Ely, Iowa.
e. Name of Project: Red Rock Hydro Commission in the Public Reference
Commission’s Rules may become a Room, located at 888 First Street NE.,
Project.
party to the proceeding. Any comments, f. Location: The proposed project Room 2A, Washington DC 20426, or by
protests, or motions to intervene must would be located on the U.S. Army calling (202) 502–8371. This filing may
be received on or before the specified Corps of Engineer’s (Corps) existing Red also be viewed on the Commission’s
comment date for the particular Rock Dam, on the Des Moines River in Web site at http://www.ferc.gov using
application. Marion County, Iowa. the ‘‘eLibrary’’ link. Enter the docket
Comments, protests and interventions g. Filed Pursuant to: Federal Power number excluding the last three digits in
may be filed electronically via the Act, 16 U.S.C. 791(a)-825(r). the docket number field to access the
Internet in lieu of paper; see 18 CFR h. Applicant Contacts: Mayor, Dale A. document. For assistance, call toll-free
385.2001 (a)(1)(iii) and the instructions Stanek, City of Ely, Iowa, 1570 Rowley 1–866–208–3676 or e-mail
on the Commission’s Web site under ‘‘e- Street, Ely, IA 52227, (319) 848–3049 FERCOnlineSupport@ferc.gov. For TTY,
filing’’ link. The Commission strongly and Mr. Thomas J. Wilkinson, 1800 First call (202) 502–8659. A copy is also
encourages electronic filing. Avenue NE, 200 Wells Frago Bank available for inspection and
s. Filing and Service of Responsive Building, Cedar Rapids, IA 52402, (319) reproduction at the address in item h.
Documents—Any filings must bear in 364–0171. above.
i. FERC Contact: Mr. Robert Bell, n. Individuals desiring to be included
all capital letters the title
(202) 502–6062. on the Commission’s mailing list should
‘‘COMMENTS’’,
j. Deadline for Filing Motions to so indicate by writing to the Secretary
‘‘RECOMMENDATIONS FOR TERMS
Intervene, Protests and Comments: 30 of the Commission.
AND CONDITIONS’’, ‘‘PROTEST’’, or o. Proposed Scope of Studies under
days from the issuance date of this
‘‘MOTION TO INTERVENE’’, as Permit—A preliminary permit, if issued,
notice.
applicable, and the Project Number of All Documents (Original and Eight does not authorize construction. The
the particular application to which the Copies) Should be Filed With: Magalie term of the proposed preliminary permit
filing refers. Any of the above-named R. Salas, Secretary, Federal Energy would be 36 months. The work
documents must be filed by providing Regulatory Commission, 888 First proposed under the preliminary permit
the original and the number of copies Street, NE., Washington, DC 20426. would include economic analysis,
provided by the Commission’s Comments, protests, and interventions preparation of preliminary engineering
regulations to: The Secretary, Federal may be filed electronically via the plans, and a study of environmental
Energy Regulatory Commission, 888 Internet in lieu of paper; see 18 CFR impacts. Based on the results of these
First Street, NE., Washington, DC 20426. 385.2001(a)(1)(iii) and the instructions studies, the Applicant would decide
A copy of any motion to intervene must on the Commission’s Web site under the whether to proceed with the preparation
also be served upon each representative ‘‘e-Filing’’ link. The Commission of a development application to
of the Applicant specified in the strongly encourages electronic filings. construct and operate the project.
particular application. Please include the project number (P– p. Comments, Protests, or Motions to
t. Agency Comments—Federal, State, 12600–000) on any comments or Intervene—Anyone may submit
and local agencies are invited to file motions filed. comments, a protest, or a motion to
comments on the described application. The Commission’s Rules of Practice intervene in accordance with the
A copy of the application may be and Procedure require all intervenors requirements of Rules of Practice and
obtained by agencies directly from the filing documents with the Commission Procedure, 18 CFR 385.210, .211, .214.
Applicant. If an agency does not file to serve a copy of that document on In determining the appropriate action to
comments within the time specified for each person in the official service list take, the Commission will consider all
filing comments, it will be presumed to for the project. Further, if an intervenor protests or other comments filed, but
have no comments. One copy of an files comments or documents with the only those who file a motion to
agency’s comments must also be sent to Commission relating to the merits of an intervene in accordance with the
the Applicant’s representatives. issue that may affect the responsibilities Commission’s Rules may become a
of a particular resource agency, they party to the proceeding. Any comments,
Magalie R. Salas, protests, or motions to intervene must
must also serve a copy of the document
Secretary. on that resource agency. be received on or before the specified
[FR Doc. E5–4179 Filed 8–2–05; 8:45 am] k. Competing Application: Project No. comment date for the particular
BILLING CODE 6717–01–P 12576–000 and 12577, Date Filed: both application.

VerDate jul<14>2003 15:22 Aug 02, 2005 Jkt 205001 PO 00000 Frm 00074 Fmt 4703 Sfmt 4703 E:\FR\FM\03AUN1.SGM 03AUN1
Federal Register / Vol. 70, No. 148 / Wednesday, August 3, 2005 / Notices 44627

q. Filing and Service of Responsive d. Applicant: Greybull Valley application for preliminary permit for a
Documents—Any filings must bear in Irrigation District. proposed project must submit the
all capital letters the title e. Name of Project: Lower Sunshine competing application itself, or a notice
‘‘COMMENTS’’, ‘‘NOTICE OF INTENT Project. of intent to file such an application, to
TO FILE COMPETING APPLICATION’’, f. Location: On Greybull River, in Park the Commission on or before the
‘‘COMPETING APPLICATION’’, County, Wyoming. The dam is own by specified comment date for the
‘‘PROTEST’’, or ‘‘MOTION TO the applicant. particular application (see 18 CFR 4.36).
INTERVENE’’, as applicable, and the g. Filed Pursuant to: Federal Power Submission of a timely notice of intent
Project Number of the particular Act, 16 U.S.C. 791(a)–825(r). allows an interested person to file the
application to which the filing refers. h. Applicant Contact: Mr. William B. competing preliminary permit
Any of the above-named documents Schlenker, Greybull Valley Irrigation application no later than 30 days after
must be filed by providing the original District, P.O. Box 44, Emblem, WY the specified comment date for the
and the number of copies provided by 82422–0044, (307) 762–3555. particular application. A competing
the Commission’s regulations to: The i. FERC Contact: Robert Bell, (202) preliminary permit application must
Secretary, Federal Energy Regulatory 502–6062. conform with 18 CFR 4.30(b) and 4.36.
Commission, 888 First Street, NE., j. Deadline for Filing Comments, o. Competing Development
Washington, DC 20426. An additional Protests, and Motions to Intervene: 60 Application—Any qualified
copy must be sent to Director, Division days from the issuance date of this development applicant desiring to file a
of Hydropower Administration and notice. competing development application
All documents (original and eight must submit to the Commission, on or
Compliance, Federal Energy Regulatory
copies) should be filed with Magalie R. before a specified comment date for the
Commission, at the above-mentioned
Salas, Secretary, Federal Energy particular application, either a
address. A copy of any notice of intent,
Regulatory Commission, 888 First competing development application or a
competing application or motion to
Street, NE., Washington, DC 20426. notice of intent to file such an
intervene must also be served upon each
Please include the project number (P– application. Submission of a timely
representative of the Applicant
12604–000) an any comments, protests, notice of intent to file a development
specified in the particular application.
or motions filed. application allows an interested person
Comments, protests and interventions k. Description of Project: The
may be filed electronically via the to file the competing application no
proposed project would consist of; (1) later than 120 days after the specified
Internet in lieu of paper; see 18 CFR An existing 178-foot-high, 1660-foot-
385.2001(a)(1)(iii) and the instructions comment date for the particular
long earthfill dam, (2) an existing application. A competing license
on the Commission’s Web site under the impoundment having a surface area of
‘‘e-Filing’’ link. The Commission application must conform with 18 CFR
1,049 acres, with a storage capacity of 4.30(b) and 4.36.
strongly encourages electronic filings 58,750 acre-feet and normal water p. Notice of Intent—A notice of intent
r. Agency Comments—Federal, state, surface elevation of 5,100 feet mean sea must specify the exact name, business
and local agencies are invited to file level, (3) an existing powerhouse address, and telephone number of the
comments on the described application. containing two generating units having prospective applicant, and must include
A copy of the application may be a total installed capacity of 5.50 an unequivocal statement of intent to
obtained by agencies directly from the megawatts, (4) a proposed 1,700-foot- submit, if such an application may be
Applicant. If an agency does not file long, 25 kilovolt transmission line, and filed, either a preliminary permit
comments within the time specified for (5) appurtenant facilities. The project application or a development
filing comments, it will be presumed to would have an annual generation of application (specify which type of
have no comments. One copy of an 12.4 gigawatt-hours that would be sold application). A notice of intent must be
agency’s comments must also be sent to to a local utility. served on the applicant(s) named in this
the Applicant’s representatives. l. Locations of Applications: A copy of public notice.
Magalie R. Salas, the application is available for q. Proposed Scope of Studies under
Secretary. inspection and reproduction at the Permit—A preliminary permit, if issued,
Commission in the Public Reference does not authorize construction. The
[FR Doc. E5–4182 Filed 8–2–05; 8:45 am]
Room, located at 888 First Street NE., term of the proposed preliminary permit
BILLING CODE 6717–01–P
Room 2A, Washington, DC 20426, or by would be 36 months. The work
calling (202) 502–8371. This filing may proposed under the preliminary permit
also be viewed on the Commission’s would include economic analysis,
DEPARTMENT OF ENERGY
Web site at http://www.ferc.gov using preparation of preliminary engineering
Federal Energy Regulatory the ‘‘eLibrary’’ link. Enter the docket plans, and a study of environmental
Commission number excluding the last three digits in impacts. Based on the results of these
the docket number field to access the studies, the Applicant would decide
Notice of Application Accepted for document. For assistance, call toll-free whether to proceed with the preparation
Filing and Soliciting Motions to 1–866–208–3676 or e-mail of a development application to
Intervene, Protests, and Comments FERCOnlineSupport@ferc.gov. For TTY, construct and operate the project.
call (202) 502–8659. A copy is also r. Comments, Protests, or Motions to
July 27, 2005. Intervene—Anyone may submit
available for inspection and
Take notice that the following reproduction at the address in item h. comments, a protest, or a motion to
hydroelectric application has been filed above. intervene in accordance with the
with the Commission and is available m. Individuals desiring to be included requirements of Rules of Practice and
for public inspection: on the Commission’s mailing list should Procedure, 18 CFR 385.210, .211, .214.
a. Type of Application: Preliminary so indicate by writing to the Secretary In determining the appropriate action to
permit. of the Commission. take, the Commission will consider all
b. Project No.: 12604–000. n. Competing Preliminary Permit— protests or other comments filed, but
c. Date Filed: May 27, 2005. Anyone desiring to file a competing only those who file a motion to

VerDate jul<14>2003 15:22 Aug 02, 2005 Jkt 205001 PO 00000 Frm 00075 Fmt 4703 Sfmt 4703 E:\FR\FM\03AUN1.SGM 03AUN1

Вам также может понравиться