Вы находитесь на странице: 1из 131

MTRD

ICT

MINISTRY OF
TRANSPORT
AND
INFRASTRUCTURE

STATE DEPARTMENT OF
INFRASTRUCTURE
MATERIALS TESTING AND RESEARCH
DIVISION(MTRD)

DETAILED INSPECTION OF BRIDGES


ALONG NAKURU-NYAHURURU-NYERI
MARUA ROAD(B5)
MTRD REPORT NO.1233
MAY,2015

CHIEF ENGINEER (MATERIALS )


P.O. BOX 11873-00400
NAIROBI

INTERNATIONAL CONSULTANTS
AND TECHNOCRATS(ICT) PVT LTD
A-8, GREEN PARK NEW DELHI
-110016, INDIA

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

1.0

ICT

INTRODUCTION

This bridge inspection report is in response to a request made by M/S


International Consultants and Technocrats (ICT) Pvt Ltd of A-8, Green Park
New Delhi -110016, and India to undertake inspection of structures along road
B5. This was done under the project: Consultancy Services for a Feasibility
Study, EIA, SIA and Detailed Designs Including Tender Documents for
Rehabilitation of Nakuru-Nyahururu-Nyeri Marua Road.

A total of seven structures had been targeted for detailed inspection as listed
below.
i. Bridge
ii. Bridge
iii. Bridge
iv. Bridge
v. Bridge
vi. Bridge
vii.Bridge

at
at
at
at
at
at
at

Km
Km
Km
Km
Km
Km
Km

60+030
84+520
93+380
102+510
125+670
142+450
173+120

This report contains a description of the structures, visual observations,


description of testing methods, test results for various parameters based on
different Non-Destructive Testing methods, conclusions and recommendations.
The report is factual and dwells mainly on the status of structural elements
and their material components.
The primary results of these inspections are given and the critical problems
have been highlighted.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

1.1

ICT

Scope of work

The scope of work as shown below involved testing of structural elements in


both the superstructures and substructures for each of the seven bridges for
several parameters using various Non-Destructive Testing methods.
Table 1: Scope of work
Item
no.

Structural

Parameters tested

Inspection details/methods

element
Appearance
Re-bar details
1

Abutments

Insitu Concrete strength


Quality, homogeneity and
internal defects of concrete
matrix
Deterioration status of the
concrete matrix
i. Corrosion
ii. Remaining effective
good covers
Crack profiling
i. Width
ii. Depth
iii. length

Piers
i. Wall type
ii. Column
type

Deck slab

Steel Girders

Carry out visual inspection


Carry out electromagnetic
tests
Carry out Schmidt hammer
tests
Carry out ultrasonic pulse
velocity tests
i.

Carry out
resistivity/half cell
potential tests
ii. Carry out carbonation
depth tests
i.

Use of crack width


microscope to measure
crack widths
ii. Carry out ultrasonic
tests to measure crack
depths

Ditto

Ditto

Ditto
Laminations
Corrosion

Ditto
Carry out ultrasonic tests
Carry out visual inspection
and ultrasonic thickness tests
Carry out ultrasonic tests
Carry out radiographic tests

Plate thicknesses
Continuity of critical welds
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

if any
5

3.0

Ancillary Fixtures
i. bearings
ii. expansion
gaps

Appearance

Carry out visual inspections

SUMMARY OF TEST RESULTS

Generally the findings from all the tests done indicate a lot of similarity for six
structures in terms of re-bar distribution for various structural elements,
cracking patterns, steel girder types ,numbers & sizes, type of ancillary fixtures
and concrete deterioration status.
The findings for bridge at km173+120 (at Marua) were different from those of
other structures.
Inspection results have been summarized for each structure and are presented
below.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

3.1

ICT

BRIDGE AT KM 60+030

This is a single span structure comprising a composite deck with 5 no. steel
beams, wall type RC abutments and wing walls.

Photo 1: A side view of bridge at km 60+030

3.1.1

ABUTMENTS

3.1.1.1

Visual Inspection

Two vertical cracks running full height were found on the Nyeri side abutment.
The cracks appear approximately midway between the beam supports at the
abutment cap. The crack widths vary from 0.8-1.4mm

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5


4050

2330

MTRD

ICT

Fig. 1: showing crack profiles for Nyeri side abutment

BRIDGE AT KM 60+030

Photo 2: a vertical crack on an abutment wall

One vertical crack was found on the Nyahururu side abutment. The crack
appearednear the inner RHS beam support at the abutment cap and
propagated the full height of the abutment wall. The maximum crack width
recorded was.1.0 mm

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5


4050

2330

MTRD

ICT

Fig. 1: showing crack profiles for Nyeri side abutment

3.1.1.2

Steel Reinforcement details for the Abutments

The reinforcement details as gathered through electromagnetic method revealed


the spacing of the reinforcement bars in the abutment walls on either side of
the bridge was not uniform in the vertical and horizontal directions, varying
between 400mm- 450mm and 380-450mm respectively . The vertical re-bars
were 25 mm diameter while the horizontal were 16 mm diameter.
BRIDGE AT KM 60+030
Steel Reinforcement details for the Abutments
The average covers were varying at different points on either abutment with the
lowest at 33 mm and the highest at 71 mm.

3.1.1.3

Concrete

strength,

quality

and

homogeneity

for

the

Abutments
The concrete strength as measured through rebound (Schmidt) hammer
method recorded strengths of between 44.0N/mm2 to 54.0N/mm2
The concrete matrix was generally homogeneous as revealed through ultrasonic
method except at locations where cracks appeared.
3.1.1.4

Crack depths for the Abutments

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

The crack depths were ultrasonically determined and found to be106mm at the
widest points.
3.1.1.5

Concrete Deterioration for the Abutments

Two methods were employed i.e. carbonation and resistivity potential to indicate
the level of deterioration of concrete.
The highest carbonation depth recorded was 6mm indicating a remaining good
cover of 27mm (least cover recorded was 33mm). This was an indication of low
level deterioration.
Probability of corrosion activity was insignificant as indicated by a high
resistivity potential of 111.4kcm.
3.1.2

DECK SLAB

3.1.2.1

Visual inspection of the Deck Slab

Deck slab thickness was 200mm.


There were several multi directional cracks appearing from the soffit of the
deck. The cracks were distributed all over the deck soffit.
Maximum crack width was 1mm.
3.1.2.2

Steel Reinforcement details of the Deck Slab

The reinforcement details as gathered through electromagnetic method revealed


that the distribution of the reinforcement bars in the deck slab was uniform
both in both longitudinal and transverse directions. The longitudinal re-bars
were 20 mm diameter at an average spacing of 400mm while the transverse
were 16 mm diameter at an average spacing of 300 mm. The average covers
were 50mm and 35mm for longitudinal re-bars and transverse re-bars
respectively.

3.1.2.3

Concrete strength, quality and homogeneity

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

The concrete strength as measured through rebound (Schmidt) hammer


method recorded an average strength of between 56N/mm2 62N/mm2
The concrete matrix was inhomogeneous as revealed through ultrasonic
method. This could be due to cracking on the deck slab soffit.
3.1.2.4

Crack depths

The crack depths were ultrasonically determined and found to be through


cracks
3.1.2.5

Concrete Deterioration of Deck Slab

Two methods were employed i.e. carbonation and resistivity potential to indicate
the level of deterioration of concrete.
The highest carbonation depth recorded was 6mm indicating a remaining good
cover of 29mm (least cover recorded was 35mm).This was an indication of low
level deterioration.
Deterioration in this case refers to chemical effects and not physical.
Probability of corrosion activity was insignificant as indicated by high resistivity
potential of 110.2

BRIDGE AT KM 60+030
3.1.4

WING WALLS

3.1.4.1

Visual Inspection of the Wing Walls

There were no visual structural defects on the wing walls


3.1.4.2

Steel Reinforcement Details for the Wing Walls

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

The reinforcement details as gathered through electromagnetic method revealed


the spacing of the reinforcement bars in the wing walls on either side of the
bridge not to be uniform in the vertical and horizontal directions, varying
between 380mm- 480mm and 390-470 mm respectively.
The vertical re-bars were 20 mm diameter while the horizontal were 16 mm.
The average covers were varying at different points on either side with the
lowest at 26 mm and the highest at 71 mm.

3.1.4.3

Concrete strength, quality and homogeneity for the wing

walls
The concrete strength as measured through rebound (Schmidt) hammer
method recorded an average strength of 58.0N/mm2
The concrete matrix was generally homogeneous as revealed through ultrasonic
method.
3.1.5

STEEL GIRDERS

3.1.5.1

Visual Inspection of Steel Girders

There were spots of paint peeling off from the bracings and beams.
The top flanges near the abutment supports had started to corrode as revealed
by red/brown colouration stains at the slab soffit joint. However the corrosion
was at an early stage without causing any significant reduction in thickness of
the steel plate.
There was accumulation of soil at the abutment caps which covered the bottom
flanges of the steel girders causing the paint to peel off resulting in early stages
of corrosion.
BRIDGE AT KM 60+030
Visual Inspection of Steel Girders
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

The bolts and nuts for all the joints were in good condition.
There were no critical welded joints.
3.1.5.2

Ultrasonic Thickness Tests for Steel Girders

There was no delaminating of the plates as determined ultrasonically. The


thicknesses for the flange and web plates were determined ultrasonically and
found to be uniform.
3.1.6

BEARINGS

The bearing type was elastomeric of approximate size 400x280x 30 mm and


was in good condition.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

3.2

ICT

BRIDGE AT KM 93+380

This is a single span structure comprising a composite deck with 5 no. steel
beams, wall type RC abutments and wing walls.

Photo 3: A side view of bridge at km 93+380

3.2.1

ABUTMENTS

3.2.1.1

Visual Inspection Abutments

There were four regularly spaced vertical cracks running full height on the
Nyeri side abutment. The cracks appeared approximately midway between the
beam supports at the abutment cap.

2600

1670

1880

1900

210

Fig 3: sketch showing the crack profiles on the Nyeri side abutment wall

The crack widths varied from 0.6-1mm.


DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

3.2

ICT

BRIDGE AT KM 93+380

Three regularly spaced vertical cracks running full height were found on the
Nyahururu side abutment. The cracks appeared approximately midway
between the beam supports for the inner LHS& RHS beams and the centre
beam.

3140

2650

2300

2000m

Fig 4: showing crack profiles for Nyahururu side abutment-measurement in mm

Photo 4: Showing a vertical crack on an abutment


DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

3.2.1.2

ICT

Steel Reinforcement details for the Abutments

The reinforcement details as gathered through electromagnetic method revealed


the distribution of the reinforcement bars in the abutment walls on either side
of the bridge to be uniform in the vertical and horizontal directions.

BRIDGE AT KM 93+380
Steel Reinforcement details for the Abutments
The vertical s re-bars were 25 mm diameter at an average spacing of 450mm
while the horizontal were 16 mm diameter at an average spacing of 450 mm.
The average covers were varying at different points on either abutment with the
lowest at 28 mm and highest at 66 mm.

3.2.1.3

Concrete

strength,

quality

and

homogeneity

for

the

Abutments
The concrete strength as measured through rebound (Schmidt) hammer
method recorded strengths between 40.0 N/mm2 to 60N/mm2 for six test
points.
The concrete matrix was generally homogeneous as revealed through ultrasonic
method except at locations where cracks appeared.
3.2.1.3

Crack depths

The crack depths were ultrasonically determined and found to be 61mm at the
widest points.
3.2.1.4

Concrete Deterioration for the Abutments

Two methods were employed i.e. carbonation and resistivity potential to indicate
the level of deterioration of concrete.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

The highest carbonation depth recorded was 5mm indicating a remaining good
cover of 23mm (least cover recorded was 28mm).This was an indication of low
level deterioration.
Probability of corrosion activity was insignificant as indicated by a high
resistivity potential of 110.6kcm.

BRIDGE AT KM 93+380
3.2.2

DECK SLAB

3.2.2.1

Visual inspection Of the Deck Slab

Deck slab thickness was 200mm.


There were several multi directional cracks appearing from the soffit of the
deck. The cracks were distributed all over the deck soffit. There were two major
cracks that ran full width on each half of the Nyeri side and Nyahururu side of
the deck at approximatetly1500mm from the cross bracing. There were leakage
stains along these cracks, an indication that the cracks were through hence
the risk of exposure of re-bars to corrosion due to water ingress at the
locations. (See photos below)

Photo 5: showing a transverse crack on the deck of bridge at km 93+380


DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Photo 6: a closer view of the crack in photo 5 above

Maximum crack width was 1mm.

BRIDGE AT KM 93+380
3.2.2.2

Steel Reinforcement details for the Deck Slab

The reinforcement details as gathered through electromagnetic method revealed


that the distribution of the reinforcement bars in the deck slab was uniform
both in both longitudinal and transverse directions. The longitudinal re-bars
were 20 mm diameter at an average spacing of 400mm while the transverse
were 16 mm diameter at an average spacing of 300 mm. The average covers
were 50mm and 34mm for longitudinal re-bars and transverse re-bars
respectively.

3.2.2.3

Concrete strength, quality and homogeneity for the Deck Slab

The concrete strength as measured through rebound (Schmidt) hammer


method recorded an average strength of 55N/mm2 for three test locations.
The concrete matrix was inhomogeneous as revealed through ultrasonic
method. This was especially due to numerous multi directional cracks on the
deck slab soffit.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

3.2.2.4

ICT

Crack depths

The crack depths for the major transverse cracks were ultrasonically
determined and found to be through cracks at the widest points.
3.2.2.5

Concrete Deterioration

Two methods were employed i.e. carbonation and resistivity potential to indicate
the level of deterioration of concrete.
The highest carbonation depth recorded was 5mm indicating a remaining good
cover of 29mm (least cover recorded was 34mm).This was an indication of low
level deterioration.
Deterioration in this case refers to chemical effects, not physical.
Probability of corrosion activity was insignificant as indicated by a high
resistivity potential 108.6

BRIDGE AT KM 93+380
3.2.3

WING WALLS

Visual Inspection of the Wing Walls


There were no visible structural defects on the wing walls.
3.3.3.1

Steel Reinforcement Details

The reinforcement details as gathered through electromagnetic method revealed


the distribution of the reinforcement bars in the wing walls on either side of the
bridge to be uniform the vertical and horizontal directions.
The vertical re-bars were 220 mm diameter at an average spacing of 450mm
while the horizontal were 16 mm diameter at an average spacing of 350mm.
The average covers were varying at different points on either side with the
lowest at 37 mm and the highest at 68 mm.
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

3.2.3.2

Concrete strength, quality and homogeneity

The concrete strength as measured through rebound (Schmidt) hammer


method recorded strengths of between 58.0N/mm2 to 65N/mm2.
The concrete matrix was generally homogeneous as revealed through ultrasonic
method.
3.3.4

STEEL GIRDERS

3.2.4.1

Visual inspection of Steel Girders

There were spots of paint peeling off from the bracings and girders.
The top flanges near the abutments had started to corrode for approximately
700 mm length. However the corrosion was at an early stage without causing
any significant reduction in thickness of the steel plates.

Photo 1: showing spots of paint peeling off a bracing on bridge at km 93+380

BRIDGE AT KM 93+380
There was accumulation of soil at the abutment caps which covered the bottom
flanges of the steel girders causing the paint to peel off resulting in early stages
of corrosion.
The bolts and nuts for all the joints were in good condition.
There were no critical welded joints.
3.2.4.2

Thickness Tests for Girder Plates

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

There was no delaminating of the plates as determined ultrasonically. The


thicknesses for the flange and web plates were determined ultrasonically and
found to be uniform.
3.3.5

BEARINGS

The bearing type is elastomeric of approxsize400x280.30 while loaded and were


in good condition.

photo 8:showing a bridge bearing for bridge at km 93+380

3.3.6

OTHER BRIDGE FITTINGS

The guard rails were in good condition.

photo 2:showing guardrails for bridge at km 93+380

3.3

BRIDGE AT KM 84+520

This is a three span structure comprising a composite deck with 5 no. steel
girders for each span, wall type RC abutments, column type RC piers and wing
walls.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Photo 9:Showing the Approach for bridge at km 84+520

Photo 10: showing the soffit of bridge at km 84+520

3.3.1

ABUTMENTS

3.3.1.1

Visual Inspection of Abutments

Two vertical cracks running from mid way the height downwards were found on
the Nyahururu side abutment. The crack widths ranged between 0.6-1.0mm.

3000mm

3000m

Fig 5:showing crack profiles on the nyahururu side abutment

BRIDGE AT KM 84+520
One vertical crack running from mid-way the height downwards was found on
the Nyeri side abutment. The crack width was 0.8mm at the widest point.
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

3.3.1.2

ICT

Steel Reinforcement details for the Abutments

The reinforcement details as gathered through electromagnetic method revealed


the spacing of the reinforcement bars in the abutment walls on either side of
the bridge not to be uniform in the vertical and horizontal directions, varying
between 480mm- 520mm and 360-440mm respectively. The vertical re-bars
were 25 mm diameter while the horizontal were 16 mm diameter. The average
covers were varying at different points on either abutment with the lowest at 36
mm and the highest at 66mm.

3.3.1.3

Concrete

strength,

quality

and

homogeneity

for

the

Abutments
The concrete strength as measured through rebound (Schmidt) Hammer
method recorded average strengths of 50.0N/mm 2 and 54.0N/mm2 for the
Nyeri and Nyahururu sides respectively.
The concrete matrix was generally homogeneous as revealed through ultrasonic
method.
3.3.1.4

Crack depths for the abutment walls

The crack depths were ultrasonically determined and found to be 27 mm at the


widest points.
3.3.1.5

Concrete Deterioration

The highest carbonation depth recorded was 3 mm indicating a remaining good


cover of 29mm (least cover recorded was 32mm.This was an indication of low
level deterioration.
Probability of corrosion activity was insignificant as indicated by a high
resistivity potential of 111.6 kcm

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 84+520
3.3.2

DECK SLAB

3.3.2.1

Visual Inspection of the Deck Slab

Deck slab thickness was 200mm.


There were several multi directional cracks appearing from the soffit of the
deck. The cracks were distributed all over the deck soffit. There were two major
cracks that ran full width on each quarter of each span at approximately
1500mm from the transverse bracing. There were leakage stains along these
cracks, an indication that the cracks were through hence the risk of exposure
of re-bars to corrosion due to water ingress at the locations.Othermulti
directional cracks are distributed over the entire deck slab soffit.

Photo 11: showing a transverse crack on the deck slab of bridge at km 84+520

Maximum crack width was 1mm.


3.3.2.2

Steel Reinforcement Details for the Deck Slab

The reinforcement details as gathered through electromagnetic method revealed


the distribution of the reinforcement bars in the deck slab to be uniform in the
longitudinal and transverse directions. The longitudinal re-bars were 20 mm
diameter at an average spacing of 400mm while the transverse were 16 mm
diameter at an average spacing of 300 mm. The average covers were 45mm and
27mm for longitudinal re-bars and transverse re-bars respectively.
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 84+520
3.3.2.1

Concrete strength, quality and homogeneity for the Deck Slab

The concrete strength as measured through rebound (Schmidt) hammer


method recorded an average strength of 46N/mm2
The concrete matrix was inhomogeneous as revealed through ultrasonic
method. This could be attributed to numerous multi directional cracks on the
deck slab soffit.
3.3.2.2

Crack depths for the Deck Slab

The crack depths were ultrasonically and visually determined and found to
through at the widest points.
3.3.2.1

Concrete Deterioration for the Deck Slab

The highest carbonation depth recorded was 3mm indicating a remaining good
cover of 24mm (least cover recorded was 27 mm).This was an indication of low
level deterioration.
Deterioration in this case refers to chemical effects rather than physical.
Probability of corrosion activity was insignificant as indicated by a high
resistivity potential of 111.6.
3.3.3

WING WALLS

3.3.3.1

Visual Inspection of the Wing Walls

There were no visual structural defects on the wing walls.


3.3.3.2

Steel Reinforcement Details for the Wing Walls

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

The reinforcement details as gathered through electromagnetic method revealed


the spacing of the reinforcement bars in the wing walls on either side of the
bridge not to be uniform in the vertical and horizontal directions, varying
between 350mm- 470mm and 260-370mm respectively. The vertical re-bars
were 20 mm in diameter while the horizontal were 16 mm .The average covers
were varying at different points on either side with the lowest at 36 mm and
highest at 64 mm.
BRIDGE AT KM 84+520
3.3.3.3

Concrete Strength, Quality and Homogeneity of the Wing

Walls
The concrete strength as measured through rebound (Schmidt) hammer
method recorded an average strength of 55.0N/mm 2 and 54.0N/mm2 for Nyeri
and Nyahururu side respectively.
The concrete matrix was generally homogeneous as revealed through ultrasonic
method.
3.3.4 STEEL GIRDERS
3.3.4.1

Visual Inspection of Steel Girders

The girders were generally in good condition.


There were no critical welded joints along the entire length of the girders.
The bolts and nuts for all the joints were in good condition.
There were mud stains at the abutment support, causing early stages of
corrosion to the LHS girder near the abutment support for a length of
approximately 1m.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Photo 12:showing stains on a bottom flange of a steel girder for bridge at km 84+520

3.3.4.2

Ultrasonic Thickness Tests for Steel Girders

There was no delaminating of the plates as determined ultrasonically. The


thicknesses for the flange and web plates were determined ultrasonically and
found to be uniform.

BRIDGE AT KM 84+520
3.3.5

PIER COLUMNS

3.3.5.1

Visual Inspection of Pier Columns

The pier columns were generally in good condition.

Photo 13: showing part of a pier column for bridge at km 84+520

3.3.5.2

Steel Reinforcement details

There were 2 No. pier columns on either side of the river channel where the
central span is supported.
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

The columns sizes were 750x600mm.


The reinforcement details as gathered through electromagnetic method revealed
8 no.32mm diameter re-bars in each column. The average covers were varying
at different points on the faces of each column with the lowest at 40 mm and
highest at 70 mm.

3.3.5.3

Concrete strength, quality and homogeneity

The concrete strength as measured through rebound (Schmidt) hammer


method recorded average strengths of 55 N/mm 2 and 62 N/mm2 for Nyahururu
side and 48N/mm2 and 54.0N/mm2 for Nyeri side.
The concrete matrix was generally homogeneous as revealed through ultrasonic
method. The quality of concrete was also found to be good through direct
transmission mode of ultrasonic pulses where an average velocity of 4.2 km/s
was recorded.

BRIDGE AT KM 84+520
3.3.5.4

Concrete matrix Deterioration for pier columns

The highest carbonation depth recorded was 3 mm indicating a remaining good


cover of 37mm (least cover recorded was 40mm. This was an indication of low
level deterioration.
Probability of corrosion activity was insignificant as indicated by a high
resistivity potential of 111.6 kcm.
3.3.5.5

BEARINGS

The bearing type is elastomeric of approximate size400x280x30mm. They were


in good condition.
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Photo 14: Showing a bridge bearing for bridge at km 84+520

3.3.6

OTHER BRIDGE FITTINGS

The guard rails were in good condition.

photo 15:showing bridge fittings for bridge at km 84+52

3.4

BRIDGE AT KM 102+510

The structure comprises a composite deck with 5 no. steel beams, wall type RC
abutments and wing walls.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Photo 16: showing a side view of bridge at km 102+510

3.4.1

ABUTMENTS

3.4.1.1

Visual inspection for the Abutments

Four vertical cracks running from approximately quarter the height of the
abutment downwards were found on the Nyeri side abutment. The cracks
appeared along a line approximately midway between the beam supports at the
abutment cap. The crack widths varied from 0.4-1.2mm.

1
4
0

100
0

189
0

190
0

2800

Fig 6: sketch showing crack profiles for Nyeri side abutment for bridge at km 102+510

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Two vertical cracks from approximately mid height down wards were found on
the Nyahururu side abutment. The cracks appeared along a line approximately
midway between the two RHS beam supports and between the LHS and centre
beam supports.

2
0
0
0
4300mm

2600mm

Fig 6: sketch showing crack profiles for Nyahururu side abutment for bridge at km 102+510

Photo 17: showing a vertical crack on an abutment wall for bridge at km 102+510

There was scouring of the Nyeri side abutment bottom level up to 1400mm
high reducing the re-bar covers along this line which is mostly submerged
when water levels are high.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Photo 19: showing a scoured surface at the bottom of the abutment for bridge at km
102+510

BRIDGE AT KM 102+510
3.4.1.2

Steel Reinforcement details for the Abutments

The reinforcement details as gathered through electromagnetic method revealed


the distribution of the reinforcement bars in the abutment walls on either side
of the bridge to be uniform in the vertical and horizontal directions. The
vertical re-bars were 25 mm in diameter at an average spacing of 450mm while
the horizontal were 16 mm diameter at an average spacing of 400mm. The
average covers were varying at different points on either abutment with the
lowest at 26 mm and highest at 60 mm.

3.4.1.3

Concrete

strength,

quality

and

homogeneity

for

the

Abutments
The concrete strength as measured through rebound (Schmidt) hammer
method recorded strengths of between 40.0 N/mm2 to 59.0N/mm2.
The concrete matrix was generally homogeneous as revealed through ultrasonic
method except at locations where cracks appeared.
3.4.1.4

Crack depths

The crack depths were ultrasonically determined and found to be 42 mm at the


widest points.
3.4.1.5

Concrete Deterioration for the abutments

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

The highest carbonation depth recorded was 4mm indicating a remaining good
cover of 22mm (least cover recorded was 26mm), see table ... for calculation of
balance of carbonation depth).This was an indication of low level deterioration.
Probability of corrosion activity was insignificant as indicated by a high
resistivity potential of 110.8.

BRIDGE AT KM 102+510
3.4.2

DECK SLAB

3.4.2.1

Visual inspection of the Deck

Deck slab thickness was 200mm.


There were several multi directional cracks appearing from the soffit of the
deck. The cracks were distributed all over the deck soffit. There were two major
cracks that ran full width on either half of the Nyeri side and Nyahururu side
of the deck at approx1, 500 mm from the transverse bracing. There were
leakage stains along these cracks, an indication that the cracks were through
hence the risk of exposure of re-bars to corrosion due to water ingress at the
locations. (See photos below).

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Photo 20: showing cracks on the deck slab of bridge at km 102+510

Maximum crack width was 0.8 mm.


3.4.2.2

Steel Reinforcement details for the Deck Slab

The reinforcement details gathered through electromagnetic method revealed


that the distribution of the reinforcement bars in the deck slab to be uniform in
the longitudinal and transverse directions. The longitudinal re-bars were 20
mm in diameter at an average spacing of 400mm while the transverse were 16
mm diameter at an average spacing of 300 mm. The average covers were 45 mm
and 60mm for longitudinal and transverse re-bars respectively.
3.4.2.3

Concrete strength, quality and homogeneity for the Deck Slab

The concrete strength measured through rebound (Schmidt) hammer method


recorded an average strength of 55.5N/mm2.
The concrete matrix was inhomogeneous as revealed through ultrasonic
method. This could be attributed to numerous multi directional cracks on the
deck slab soffit.
3.4.2.4

Crack depths

The crack depths were ultrasonically determined and found to be 42mm at the
widest points.
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

3.4.2.5

ICT

Concrete Deterioration

The highest carbonation depth recorded was 5mm indicating a remaining good
cover of 40mm (least cover recorded was 45mm). This was an indication of no
deterioration.
Probability of corrosion activity was insignificant as indicated by a high
resistivity potential of 110.8 kcm.
3.4.3

WING WALLS

3.4.3.1

Visual Inspection of Wing Walls

There were no visible structural defects on the wing walls


3.4.3.1 Steel Reinforcement Details for wing walls
The reinforcement details gathered through electromagnetic method revealed
the distribution of the reinforcement bars in the wing walls on either side of the
bridge to be uniform in the vertical and horizontal directions. The vertical rebars were 20 mm diameter at an average spacing of 500mm while the
horizontal were 16 mm diameter at an average spacing of 400mm. The average
covers were varying at different points on either side with the lowest at 29 mm
and highest at 55 mm.

BRIDGE AT KM 102+510
3.4.3.2

Concrete strength, quality and homogeneity for Wing Walls

The concrete strength as measured through rebound (Schmidt) hammer


method recorded strengths between of 49.0N/mm2 to 60.0N/mm2.
The concrete matrix was generally homogeneous as revealed through ultrasonic
method.
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

3.4.4

STEEL GIRDERS

3.4.4.1

Visual

There were spots of paint peeling off on the bracings and beams

Photo 21: showing a point where paint has peeled off a bottom flange plate of a girder for bridge at km
102+510

There was accumulation of soil at the abutment caps which covered the bottom
flanges of the steel girders causing the paint to peel off resulting in early stages
of corrosion.
The bolts and nuts for all the joints were in good condition.
There were no critical welded joints.
3.4.4.2

Ultrasonic Plate Thickness Tests for Steel Girders

There was no delaminating of the plates as determined ultrasonically. The


thicknesses for the flange and web plates were determined ultrasonically and
found to be uniform.

BRIDGE AT KM 102+510
3.4.4.3

BEARINGS

The bearing type was elastomeric of approximate size300x280.30 and were in


good condition.
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

3.4.4.4

ICT

OTHER BRIDGE FITTINGS

The guard rails were intact and in good condition.

Photo 22: showing the guardrails for bridge at km 102+510

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

3.5

ICT

BRIDGE AT KM 125+670

This is a three span structure comprising a composite deck with 5 no. steel
girders which are continuous through the three spans, wall type RC
abutments, and wall type RC piers .There were no wing walls-gabion boxes had
been used instead.

Photo 3: A side view of bridge at km 125+670

3.5.1

ABUTMENTS

3.5.2

Visual Inspection of Abutments

The abutments could not be accessed due to protection works (stone pitching)
3.5.3

DECK SLAB

3.5.3.1

Visual inspection of the Deck Slab

Deck slab thickness was 200mm.


There were numerous (dense) multi directional cracks appearing from the soffit
of the deck. The cracks were distributed all over the deck soffit. There were two
major cracks that ran full width on each quarter of the span at the transverse
bracings.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

There were leakage stains along these cracks, an indication that the cracks
were through hence the risk of exposure of re-bars to corrosion due to water
ingress at the locations.(see photos below)

Photo 23: showing cracks on the deck slab of bridge at km 125+670

Vibrations could be felt midspan upon movement of vehicles on the deck.


Maximum crack width was 1mm.
3.5.3.2

Steel Reinforcement details for the deck slab

The reinforcement details gathered through electromagnetic method revealed


that the distribution of the reinforcement bars in the deck slab to be uniform in
the longitudinal and transverse directions. The longitudinal re-bars were 20
mm in diameter at an average spacing of 400mm while the transverse were 12
mm diameter at an average spacing of 300 mm. The average covers were 25mm
and 45 mm for longitudinal and transverse re-bars respectively.

3.5.3.3

Concrete strength, quality and homogeneity for the Deck Slab

The concrete strength measured through rebound (Schmidt) hammer method


recorded a strength ranging between 40N/mm2 to 46.0N/mm2.
The concrete matrix was slightly inhomogeneous as revealed through
ultrasonic method. This could be attributed to cracks on the deck slab soffit.
3.5.3.4

Crack depths for the Deck Slab

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

The crack depths were ultrasonically and visually determined and found to be
through cracks at the widest points.

BRIDGE AT KM 125+670
3.5.3.5

Concrete Deterioration for the Deck Slab

The highest carbonation depth recorded was 4mm indicating a remaining good
cover of 21mm (least cover recorded was 25 mm).This was an indication of low
level deterioration.
Probability of corrosion activity was insignificant as indicated by a high
resistivity potential of 112.3.
3.5.4

PIER WALLS

3.5.4.1

Visual inspection of the Pier Walls

There were two vertical cracks on the Nyeri side pier wall.
The protection works near the bases of the pier walls and for the Nyeri side
back fill were damaged.
The walls thicknesses were 600mm.

3.5.4.2

Steel Reinforcement Details for the Pier Walls

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

The reinforcement details gathered through electromagnetic method revealed


the spacing of the reinforcement bars in the pier walls on either side of the
bridge to be uniform the vertical and horizontal directions at 300 and 450 mm
respectively. The vertical re-bars were 25 mm in diameter while the horizontal
were 16 mm .The average covers were varying at different points on either side
with the lowest at 40 mm and the highest at 67 mm.

BRIDGE AT KM 125+670
3.5.4.3

Concrete Strength, Quality and Homogeneity of the pier walls

The concrete strength measured through rebound (Schmidt) hammer method


recorded an average strength of 51.0N/mm 2and 53.0 N/mm2 for Nyeri and
Nyahururu side respectively.
The concrete matrix was generally homogeneous as revealed through ultrasonic
method. Direct transmission of ultrasonic pulses gave an average ultrasonic
velocity of 4.3 km/s, an indication of good quality concrete.
3.5.5

STEEL GIRDERS

3.5.5.1

Visual Inspection of Steel Girders

The paint had peeled off the bottom flanges of the steel girders near the
abutment supports.

Photo 24: showing paint peeling off the bottom flange and web pates
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Three bracings-two on Nyeri side and one on Nyahururu side-were missing,


probably stolen. The beams were reachable near the abutments making it easy
for vandals to remove bolts and steal the bracings.

Photo 25: Showing a missing bracing on bridge at km 125+670

There were no critical welded joints along the entire length of the girders.
The bolts and nuts for all the joints were in good condition.
BRIDGE AT KM 125+670
3.5.6

BEARINGS

The bearings were elastomeric measuring 400x280x 30 mm and were in good


condition.

Photo 26: Showing a bridge bearing for bridge at km 125+670

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

3.6

ICT

BRIDGE AT KM 142+450(NEAR MWEIGA TOWNSHIP)

The structure comprises a composite deck with 5 no. steel beams, wall type RC
abutments and wing walls.

Photo 27: showing a side view of bridge at km 142+450

3.6.1

ABUTMENTS

3.6.1.1

Visual inspection of the Abutments

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Three vertical cracks running mid-way the height from the abutment cap were
found on the Nyahururu side abutment. One of the cracks appeared
approximately midway between the two RHS beam supports while the other
one propagated from the centre beam support at the abutment cap downwards.

Photo 28: Showing a vertical crack on the abutment wall for bridge at km 142+450

The maximum crack width was 1.1 mm

BRIDGE AT KM 142+450(NEAR MWEIGA TOWNSHIP)


3.6.1.2

Steel Reinforcement details for the Abutments

The reinforcement details gathered through electromagnetic method revealed


the distribution of the reinforcement bars in the abutment walls on either side
of the bridge to be uniform in the vertical and horizontal directions. The
vertical re-bars were 25 mm in diameter at an average spacing of 450mm while
the horizontal were 16 mm diameter at an average spacing of 400 mm. The
average covers were varying at different points on either abutment wall with
the lowest at 27 mm and highest at 67 mm.

3.6.1.3

Concrete

strength,

quality

and

Abutments

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

homogeneity

for

The

MTRD

ICT

The concrete strength measured through rebound (Schmidt) hammer method


recorded strengths of between 54 N/mm2 to 64 N/mm2.
The concrete matrix was homogeneous except for LHS of Nyahururu side,
though with no visible defects on the surface. This infers the likelihood of
internal defects within the concrete matrix at the tested location.
3.6.1.4

Crack depths

The crack depths were ultrasonically determined and found to be 42mm at the
widest points.
3.6.1.5

Concrete Deterioration

The highest carbonation depth recorded was 7mm indicating a remaining good
cover of 20mm (least cover recorded was 27mm).This was an indication of low
level deterioration.
Probability of corrosion activity was insignificant as indicated by high resistivity
potential 111.5.

BRIDGE AT KM 142+450(NEAR MWEIGA TOWNSHIP)


3.6.2

DECK SLAB

3.6.2.1

Visual inspection of the deck slab

Deck slab thickness was 200mm.


There were longitudinal cracks propagating from both Nyeri side and
Nyahururu side towards the middle of the span.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Photo 29: showing longitudinal cracks on the deck of bridge at km 142+450

There were also other multi directional cracks distributed on the deck slab
soffit.
Maximum crack width was 1.0mm.
There was lime like substance on the surface of the deck slab soffit which
appeared prominently along the location of the re-bars forming a similar
pattern to that of the re-bars layout.

Photo 30: showing lime stains on the deck soffit

BRIDGE AT KM 142+450(NEAR MWEIGA TOWNSHIP)


3.6.2.3

Steel Reinforcement details for the Deck Slab

The reinforcement details gathered through electromagnetic method revealed


the distribution of the reinforcement bars in the deck slab to be uniform in the
longitudinal and transverse directions. The longitudinal re-bars were 20 mm
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

diameter at an average spacing of 400mm while the transverse were 12 mm


diameter at an average spacing of 300 mm. The average covers were 45mm and
33 mm for longitudinal and transverse re-bars respectively.

3.6.2.4

Concrete strength, quality and homogeneity for the Deck Slab

The concrete strength as measured through rebound (Schmidt) hammer


method recorded an average strength of 53.3N/mm 2 (see details at various
point in table no....)
3.6.2.5

Crack depths

The crack depths were ultrasonically determined and found to be 65 mm at the


widest points.
3.6.2.6

Concrete Deterioration

Two methods were employed i.e. carbonation and resistivity potential to indicate
the level of deterioration of concrete.
The highest carbonation depth recorded was 6mm indicating a remaining good
cover of 27mm .This was an indication of low level deterioration.
Probability of corrosion activity was insignificant as indicated by high resistivity
potential of 111.3.

BRIDGE AT KM 142+450(NEAR MWEIGA TOWNSHIP)


DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

3.6.3

WING WALLS

3.6.3.1

Visual inspection of the Wing Walls

There were no visual structural defects on the wing walls


3.6.3.2

Steel Reinforcement Details for the Wing Walls

The reinforcement details gathered through electromagnetic method revealed


the spacing of the reinforcement bars in the abutment walls on either side of
the bridge not to be uniform in both vertical and horizontal directions varying
between 300mm- 450mm and 400-450mm respectively. The vertical re-bars
were 20 mm diameter while the horizontal were 16 mm diameter the average
covers were varying at different points on either abutment with the lowest at 40
mm and the highest at 68 mm.

3.6.3.3

Concrete strength, quality and homogeneity for the wing

walls
The concrete strength measured through rebound (Schmidt) hammer method
recorded strengths between 55.0N/mm2 to 62.0 N/mm2.
The concrete matrix was slightly inhomogeneous as revealed through
ultrasonic method.
3.6.4

STEEL GIRDERS

3.6.4.1

Visual inspection of Steel Girders

There were spots of paint peeling off on the beams signalling early stages of
corrosion. The LHS girder had a large spot where paint had peeled off on the
bottom flange.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Photo 31: showing spots of paint peeling off from the steel girders

BRIDGE AT KM 142+450(NEAR MWEIGA TOWNSHIP)


There was accumulation of soil at the abutment caps covering the bottom
flanges of the steel girders causing the paint to peel off resulting in early stages
of corrosion.
The bolts and nuts for the joints were in good condition.
There were no critical welded joints.
3.6.4.2

Thickness tests

There was no delaminating of the plates as determined ultrasonically. The


thicknesses for the flange and web plates were determined ultrasonically and
found to be uniform.
3.6.5

BEARINGS

The bearing type was elastomeric of size 400x280x 30 mm and was in good
condition.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Photo 32:showing a bridge bearing for bridge at km 142+450

3.7

BRIDGE AT KM 173+120(MARUA)

This is a three span structure comprising a composite deck with 4 no. steel
girders for each span, column type RC abutments and column type RC piers

Photo 33: a side view of bridge at km 173+120

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

3.7.1

ABUTMENTS

3.7.2

Visual Inspection of the abutments

The abutments could not be accessed due to gabion box protection works

Photo34: showing gabion boxes which prevented access to the abutment columns

3.7.3

DECK SLAB

3.7.2.1

Visual Inspection of the Deck Slab

The deck slab is in good condition. No structural defects were visible

BRIDGE AT KM 173+120(MARUA)
3.7.2.2

Steel Reinforcement details for the Deck Slab

The reinforcement details gathered through electromagnetic method revealed


that the distribution of the reinforcement bars in the deck slab to be uniform in
the longitudinal and transverse directions.
The longitudinal re-bars were 16 mm diameter at an average spacing of 150mm
while the transverse were 12 mm diameter at an average spacing of 130 mm.
The average covers were 20 mm and 10mm for longitudinal re-bars and
transverse re-bars respectively.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

3.7.2.3

ICT

Concrete strength, quality and homogeneity for the Deck Slab

The concrete strength measured through rebound (Schmidt) hammer method


recorded an average strength of between 30.0 N/mm2 and 55.0 N/mm2.
The concrete matrix was slightly inhomogeneous as revealed through
ultrasonic method.
3.7.2.4

Concrete Deterioration of the Deck Slab

The highest carbonation depth recorded was 3mm indicating a remaining good
cover of 4mm (least cover recorded was 6 mm).This was an indication of high
level deterioration. It should be noted that the little balance of effective good
cover is contributed to by small initial covers and not due to deep carbonation.
Probability of corrosion activity was insignificant as indicated by a high
resistivity potential of 111.4kcm.
3.7.3

STEEL GIRDERS

3.7.3.1

Visual inspection of steel girders

The girders were generally in good condition along the spans.


There was accumulation of soil through the expansion joint at the abutment
caps which upon removal revealed a serious corrosion attack for the bottom
flanges, mounting bolts, anchor plates and stiffening plates at the abutment
caps supports.
BRIDGE AT KM 173+120(MARUA)
The Nyeri side girders mounting bolts, stiffener plates and the anchor plates
were severely corroded and had started to peel off. See photos below.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Photo 35: showing corrode mounting bolt and bottom flange plate

Photo 36: showing a corroded mounting bolts and a stiffening plate.

Photo 37: showing corroded mounting bolt ,nut ,bottom flange plate and stiffener plate.
Notice the peel off

BRIDGE AT KM 173+120(MARUA)
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Corrosion at early stages was also observed at the mid span joints.
See photo below

Photo 38: showing corrosion at early stages at the midspan joint

3.7.4

PIER COLUMNS

3.7.4.1

Visual inspection of pier columns

The pier columns are generally in good condition.

Photo 39: showing a column pier for bridge at km 173+120

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 173+120(MARUA)
3.7.4.2

Steel Reinforcement details for Pier Columns

There were 4 No. pier columns on either side of the river channel where the
central span is suspended.
The columns sizes were 450x600mm.
The reinforcement details as gathered through electromagnetic method revealed
8 No.32mm diameter re-bars in each column. The average covers were varying
at different points on the faces of the columns with the lowest at 18mm and
highest at 36 mm.The links were spaced at 250mm.

3.7.4.3

Concrete strength, quality and homogeneity for Pier Columns

The concrete strength measured through rebound (Schmidt) hammer method


recorded average strengths of 32 N/mm2 and 45 N/mm2 for Nyeri side and
43.0N/mm2 and 55.0N/mm2 for Karatina side.
The concrete matrix was generally homogeneous as revealed through ultrasonic
method. The quality of concrete was also found to be good through direct
transmission of mode of ultrasonic method where an average ultrasonic pulse
velocity of 4.4 km/s was recorded.
3.7.4.4

Concrete Deterioration for Pier Columns

The highest carbonation depth recorded was 6 mm indicating a remaining good


cover of 12mm (least cover recorded was 18mm).This was an indication of
medium level deterioration.
Probability of corrosion activity was insignificant as indicated by a high
resistivity potential of 111.4 kcm.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

3.7.4.5

ICT

BEARINGS

The bearing type was found to be steel plate laminations which had started to
corrode.

photo 40& 41:showing laminated metallic bearing on the Nyeri side abutment cap support

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

4.0

ICT

CONCLUSIONS

From the results obtained, the following conclusions can be made:


i. There is severe cracking of the deck slabs
ii. The steel girders for the structures except bridge at km 173+120 are in
good condition but may need repainting.
iii. The concrete strengths recorded for the structural elements are
structurally okay.
iv. The concrete covers for the abutments and wing walls vary considerably
at different points on these structural elements.
v. The danger of re-bar corrosion is minimal except at locations where the
crack depths are greater than the concrete covers where water can get to
the re-bars.
vi. There is adequate effective good cover for steel reinforcement barscarbonation effect is minimal except forbridge at km 173+120 deck slab.
vii.The bearings for the structures are in good condition-except for bridge at
km 173+120
viii.
The deck slab forbridge at km 173+120 is in good condition
ix. The steel girders for bridge at km 173+120(Marua Bridge) are damaged
by corrosion at the abutment capsupport. This is the same case with the
mounting bolts and anchor plates-immediate attention is needed.

5.0

RECOMMENDATIONS

1) An action plan is needed to address the following


i. Cracking on the deck slabs and abutments
ii. Damaged protection works for bridge at km125+670
iii. Vandalism and theft of bracings for bridge at km 125+670
iv. Lime accumulation for bridge at km 142+450.
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

v. Severe corrosion of anchor plates, mounting bolts and bottom flange


edges at the abutment caps for bridge at km 173+120
vi. Damage or lack of bearings for bridge at km 173+120
2) Development of a periodic inspection plan to monitor any further
deterioration or performance of any rehabilitation worksthat may be
implemented in response to no.1 above.
3) The custodians of the structuresshould maintain proper records for the
structures in future to enable comparison of status during inspection
and original design requirements.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

6.0

ICT

TESTS DONE

Seven tests were done namely:


i) Visual Inspection to ascertain the extent of wear and tear of the
structure.
ii) Ultrasonic Test to determine the homogeneity, quality, and
internal defects in the concrete matrix.
iii) Ultrasonic test to determine steel plate thicknesses and test for
delamination.
iv) Electromagnetic Test to establish the steel reinforcement details
for reinforced concrete.
v) Schmidt Hammer Test to determine the concrete strength insitu.
vi) Carbonation test to determine the effective good cover to the
reinforcement.
vii)

Resistivity potential to determine the probability of corrosion

of the re-bars.
4.1

Test Method Principles

4.1.1 Visual Inspection


Visual Inspection is used in maintenance of facilities, inspection of
equipment and structures using either or all of human senses such as
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

vision, hearing, touch and smell. Visual Inspection typically means


inspection using human senses and/or any non-specialized inspection
equipment.

4.1.2

Schmidt Hammer Test

This method is based on the principle that the rebound of an elastic


mass depends on the hardness of the surface that it strikes. The
rebound number obtained from the Schmidt Hammer is correlated with
concrete cube crushing strength, whose calibration curves for 7 days and
28 days curing periods are contained in the digital instrument

4.1.3

Electromagnetic Test

This method is employed for locating steel in concrete using an


Electromagnetic Covermeter.

The principle method

of

test is by

electromagnetic induction. When a probe carrying an alternating field is


brought close to steel, eddy magnetic fields are generated by the steel,
which reduces the primary field of the probe. At maximum induction
level depicted by audio signals and reduction in minimum cover
measurement, the location and orientation of a reinforcement bar can be
established. After appropriate calibration, the technique is used to
determine concrete cover, location and diameter of reinforcement bars
(when reinforcement bars are parallel to the surface of the probe).
Normally, closely packed reinforcement bars influence the accuracy of
this method while determining the bar size. The accuracy of the method
employed for bar size determination is 2mm.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

4.1.4 Ultrasonic Pulse velocity Test


The velocity of ultrasonic pulses traveling through a solid material
depends on the density and the elastic properties of that material.
Ultrasonic pulse velocity testing using low frequency pulses of 54 kHz is
employed as a Non Destructive testing technique to determine the quality
and homogeneity of concrete. This is given by the velocity at which the
pulses will travel through the concrete. Regions of cracks or damaged
material will have a corresponding reduction in the pulse velocity due to
their high acoustic impedance.

In this case two modes of transmission were employed namely:


a) Direct transmission to determine the pulse velocity in km/s
hence the quality of concrete.
b)

Indirect transmission method was employed to determine the


homogeneity of concrete. A straight line graph of transit time
against distance indicates a homogeneous concrete

matrix.

Deviations from the straight line are indications of inhomogeneity.


4.1.5

Carbonation Test.

The drilling method is used to determine the depth of carbonation. The


drilled out material at prescribed depth is then analyzed for carbonation
using phenolphthalein reagent. Presence of carbonation is depicted by no
color change while the color changes to pink in the absence of
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

carbonation.
A deterioration degree is judged based on the balance of carbonation
depth as shown in the table below.
Based on this table, the degree of reinforcement corrosion is None for
the results of tests having more than 30 mm depth for the balance of
carbonation depth.
Table 2: Evaluation of Carbonation Depth
Degree of
reinforcement
corrosion
High
T < 0 mm
Large
Medium
0 mm T < 10 mm
Medium
Low
10 mm T < 30 mm
Low
None
30 mm T
None
Note: Balance of Carbonation Depth = Cover Carbonation Depth
Deterioration
degree

Balance of
Carbonation Depth

4.1.6 Reinforcement Corrosion Investigation (Resistivity potential


method)
The time at which corrosion of steel may commence and the rate at
which it may proceed is dependent upon the properties of the cement
paste and the permeability of the concrete. Since the electrical
conductivity of concrete is an electrolysis process, which takes place by
ionic movement in the aqueous pore solution of the cement matrix, it
follows that a highly permeable concrete will have a high conductivity
and low electrical resistance.

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

The knowledge of the electrical resistance of concrete can provide a


measure of the possible corrosion of steel embedded in it as shown below
Table 3: Resistivity Level vs Possible Corrosion Rate
Resistivity Level(k ohm cm)
<5
5-10
10-20
>20

Possible Corrosion Rate


Very high
high
moderate to low
insignificant

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

DETAILED RESULTS DATA SHEETS

BRIDGE AT KM 60+030
ABUTMENTS
Electromagnetic test results for the abutments
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Abutment
Test Element/Location

LHS
At
abutme
nt cap

Centre
RHS

A1 Nyeri
Side

LHS
Along
the
middle
line

Centre
RHS
LHS

At
abutme
nt cap

Centre
RHS

A2
Nyahururu
Side

LHS
Along
the
middle
line

Centre
RHS

Re-bar spacing

Average

Re-bar size

wall

(mm)

covers

(mm)

Thickness

Vertical:350
Horizontal:400
Vertical:450
Horizontal:400
Horizontal:480
Horizontal: 400
Vertical:350
Horizontal:450
Vertical:450
Horizontal:400
Horizontal:480
Horizontal: 400
Vertical:450
Horizontal:500
Vertical:400
Horizontal:470
Horizontal:380
Horizontal:450
Vertical:450
Horizontal:420
Vertical:400
Horizontal:400
Horizontal:400
Horizontal:400

(mm)
Vertical:45
Horizontal:65
Vertical:42
Horizontal:63
Vertical: 35
Horizontal:60
Vertical:45
Horizontal:60
Vertical:36
Horizontal:60
Vertical: 35
Horizontal:60
Vertical:45
Horizontal:75
Vertical:35
Horizontal:65
Vertical: 61
Horizontal:33
Vertical: 52
Horizontal:66
Vertical:38
Horizontal:73
Vertical: 33
Horizontal:71

Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical: 25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical: 25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical: 25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16

(mm)

700

Schmidt Hammer Test Results for the Abutments


Average concrete strength
(N/mm2)

Test Element/Location

At abutment cap
A1 Nyeri Side
Along the middle
line
At abutment cap
A2 Nyahururu
Side

Along the middle


line

LHS
Centre
RHS
LHS
Centre
RHS
LHS
Centre
RHS
LHS
Centre
RHS

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

49.5
53.1
53.1
41.3
44.1
44.0
54.0
48.0
44.0
48.0
43.0
45.0

MTRD

ICT

BRIDGE AT KM 60+030
Ultrasonic Pulse Velocity Results for the Abutments
Test Element/Location

Homogeneity of concrete matrix

LHS
Centre
RHS
LHS
Centre
RHS
LHS
Centre
RHS
LHS
Centre
RHS

A1 Nyeri Side

A2 Nyahururu
Side

Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous

Carbonation Test Results for the Abutments


Test

Carbonation

Least cover

Balance of

Element/Location

depth

recorded

carbonation depth

(mm)

(mm)

(mm)

A1-Nyeri side

35

29

A2-Nyahururu side

33

27

Remarks

Low
deterioration
degree

Resistivity Test Results for the Abutments


Resistivity

Test
Element/Location

Remarks

(kcm)

A1-Nyeri side

111.3

A2-Nyahururu side

111.5

Probability of corrosion is
insignificant

Crack Profiles for the Abutments


Test
Element/Locatio

Crack

Crack length

Crack width

Crack depth

no.

(mm)

(mm)

(mm)

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Cr.1
A1-Nyeri side
A2-Nyahururu
side

Cr.2
Cr.1

Full height of the


abutment wall
Full height of the
abutment wall
Full height of the
abutment wall

1.4

160

0.8

76

0.8

70

BRIDGE AT KM 60+030
DECK SLAB
Electromagnetic Test Results for the Deck Slab
Deck slab
Test Location

DS1-Nyeri Side
DS3-Nyahururu
side

Re-bar spacing

Average covers

Re-bar size

Thickness

(mm)

(mm)

(mm)

(mm)

Longitudinal:400
Transverse:300
Longitudinal:400
Transverse:300

Longitudinal:50
Transverse:35
Longitudinal:55
Transverse:37

Longitudinal:20
Transverse:16
Longitudinal:20
Transverse:16

250

Schmidt hammer Test Results for the Deck Slab


Average concrete strength
Test Location

(N/mm2)

DS1-Nyeri Side

56.1

DS2 Mid Span

59.6

DS3-Nyahururu side
62.0

Ultrasonic Pulse Velocity Results for the Deck Slab


Test Element/Location

Homogeneity of concrete matrix

DS1-Nyeri Side

Not homogenous-transmission of ultrasonic pulses not


consistent

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

DS2-Nyahururu side

Not homogenous-transmission of ultrasonic pulses not


consistent

Carbonation Test Results for the Deck Slab


Test
Element/Locatio

Carbonation

Least cover

Balance of

depth

recorded

carbonation

(mm)

(mm)

depth

Remarks

(mm)
DS1-Nyeri Side

35

29

DS3-Nyahururu
side

37

31

Low
deterioratio
n degree

BRIDGE AT KM 60+030
DECK SLAB
Resistivity Test Results for the Deck Slab
Resistivity

Test
Element/Locatio

Remarks

(kcm)

111.2

DS1-Nyeri Side
DS2-Nyahururu
side

Probability of corrosion is
insignificant

109.1

Crack profiles For the Deck Slab


Test
Element/Locatio

Crack
no.

Crack length
(mm)

Crack width
(mm)

Crack depth
(mm)

9.9-Full width
9.9-Full width

1.0
1.0

Through crack
Through crack

DS1-Nyeri side
DS3-Nyahururu
side

Cr.1
Cr.1

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

WING WALLS
Electromagnetic Test Results for the Wing Walls
Test Element/Location

LHS

Nyeri Side
Nyahururu
Side

LHS

Re-bar spacing

Average

Re-bar size

(mm)

covers

(mm)

Vertical:380
Horizontal:460
Vertical:480
Horizontal:470

(mm)
Vertical:39
Horizontal:53
Vertical:45
Horizontal:60

Vertical:20
Horizontal:16
Vertical:20
Horizontal:16

Schmidt Hammer Test Results for the Wing Walls


Average concrete strength
(N/mm2)

Test Element/Location
Nyeri Side

Nyahururu Side

LHS

56.0

LHS

60.0

Ultrasonic Pulse Velocity Results for the Wing Walls


Test Element/Location

Homogeneity of concrete
matrix

Nyeri Side

LHS

Nyahururu Side

LHS

Homogeneous

BRIDGE AT KM 60+030
Carbonation Test Results for the Wing Walls
Test
Element/Locatio
n

Carbonation

Least cover

Balance of

depth

recorded

carbonation

(mm)

(mm)

depth

Remarks

(mm)
Nyeri side
Nyahururu side

26

20

31

25

Resistivity test results for the Wing Walls


DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Low
deterioratio
n degree

MTRD

ICT

Test

Resistivity

Element/Locatio

(kcm)

Remarks

Nyeri side
Nyahururu side

110.2
108.2

Probability of corrosion is
insignificant

BRIDGE AT KM 60+030
STEEL GIRDERS
Ultrasonic Tests for Plate Thickness & Lamination for steel girders
Steel Girder

Section Dimensions

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Continuity Across

MTRD

ICT

No.

SG1 LHS

(mm)

Plate Thickness

6
0
0

No Delamination

22.5

13.8

SG2 LHS

6
0
0

No Delamination

22.7

13.7

Steel Girder

Section Dimensions

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Continuity Across

MTRD

ICT

No.

SG3 Centre

(mm)

Plate Thickness

6
0
0

No Delamination

22.6

14.5

SG2 RHS

6
0
0

No Delamination

22.4

14.0

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 60+030
STEEL GIRDERS
Ultrasonic Tests for Plate Thickness & Lamination for steel girders
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

SG1 RHS

6
0
0

No Delamination

22.5

14.0

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 84+520-NDARAGWA
ABUTMENTS
Electromagnetic test results for the abutments
Abutment
Test Element/Location

Re-bar

Average

Re-bar size

wall

spacing

covers

(mm)

Thicknes

(mm)

(mm)

Vertical:500
Horizontal:450
Vertical:470
Horizontal:370
Vertical:480
Horizontal:360
Vertical:500
Horizontal:400
Vertical:520
Horizontal:400
Vertical:480
Horizontal:400
Vertical:450
Horizontal:400
Vertical:400
Horizontal:440
Vertical:500
Horizontal:400
Vertical:450
Horizontal:380
Vertical:400
Horizontal:450
Vertical:500
Horizontal:400

Vertical:45
Horizontal:66
Vertical:40
Horizontal:60
Vertical:36
Horizontal:54
Vertical:40
Horizontal:60
Vertical:40
Horizontal:60
Vertical:37
Horizontal:60
Vertical:45
Horizontal:65
Vertical:37
Horizontal:60
Vertical:35
Horizontal:60
Vertical:40
Horizontal:65
Vertical:36
Horizontal:60
Vertical:36
Horizontal:60

s
(mm)

LHS
At
abutment
cap

Centre
RHS

A1 Nyeri
Side

LHS
Along the
middle
line

Centre
RHS
LHS

At
abutment
cap

Centre
RHS

A2
Nyahururu
Side

LHS
Along the
middle
line

Centre
RHS

Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16

770

770

Schmidt Hammer Test Results for the Abutments


Average concrete strength
Test Element/Location
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

(N/mm2)

MTRD

ICT

LHS
Centre
RHS
LHS
Centre
RHS
LHS
Centre
RHS
LHS
Centre
RHS

At abutment cap
A1 Nyeri Side
Along the middle
line
At abutment cap
A2 Nyahururu
Side

Along the middle


line

51.7
41.1
54.9
54.1
48.8
53.8
48.1
55.7
52.5
57.6
53.3
54.9

BRIDGE AT KM 84+520
Ultrasonic Pulse Velocity Results for the Abutments
Test Element/Location

Homogeneity of concrete matrix

LHS
Centre
RHS
LHS
Centre
RHS
LHS
Centre
RHS
LHS
Centre
RHS

A1 Nyeri Side

A2 Nyahururu
Side

Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous

Carbonation Test Results for the Abutments


Test
Element/Location

A1-Nyeri side
A2-Nyahururu
side

Carbonation

Least

Balance of

Remarks/deterioration

depth

cover

carbonation

degree

(mm)

recorded

depth

(mm)

(mm)

32

29

Low

36

33

None

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Resistivity Test Results for the Abutments


Resistivity

Test
Element/Location

Remarks

(kcm)
111.7

A1-Nyeri side
A2-Nyahururu side

Probability of corrosion is
insignificant

111.5

Crack Profiles for the Abutments


Test
Element/Locatio

Crack

Crack length

Crack width

Crack depth

no.

(mm)

(mm)

(mm)

Cr.1
Cr.1
Cr.2

2000
1500
1500

0.8
1.0
0.6

25
27
22

A1-Nyeri side
A2-Nyahururu
side

BRIDGE AT KM 84+520
DECK SLAB
Electromagnetic Test Results for the Deck Slab
Deck slab
Test Location

DS1-Nyeri Side
DS3-Nyahururu
side

Re-bar spacing

Average covers

Re-bar size

Thickness

(mm)

(mm)

(mm)

(mm)

Longitudinal:400
Transverse:300
Longitudinal:400
Transverse:300

Longitudinal:45
Transverse:27
Longitudinal:45
Transverse:34

Longitudinal:20
Transverse:16
Longitudinal:20
Transverse:16

Schmidt hammer Test Results for the Deck Slab


Average concrete strength
Test Location

(N/mm2)

DS1-Nyeri Side

46.0

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

220

MTRD

ICT

DS2-Nyahururu side

47.9

Ultrasonic Pulse Velocity Results for the Deck Slab


Test Element/Location

Homogeneity of concrete matrix


Slightly inhomogeneous

DS1-Nyeri Side
DS2-Nyahururu side

Slightly inhomogeneous

Carbonation Test Results for the Deck Slab


Test

Carbonation

Least cover

Balance of

Remarks/degree

Element/Locatio

depth

recorded

carbonation

of deterioration

(mm)

(mm)

depth
(mm)

DS1-Nyeri Side

24

21

low

DS2-Nyahururu
side

33

30

low

BRIDGE AT KM 84+520
DECK SLAB
Resistivity Test Results for the Deck Slab
Test

Resistivity

Element/Locatio

(kcm)

Remarks

DS1-Nyeri Side

110.7

DS3-Nyahururu
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Probability of corrosion is
insignificant

MTRD

ICT

side

110.9

Crack Profiles for the Deck Slab


Test
Element/Locatio
n

DS1-Nyeri side
DS2-Nyahururu
side

Crack

Crack length

Crack width

Crack depth

no.

(mm)

(mm)

(mm)

Cr.1
Cr.2
Cr.1
Cr.2

Full
Full
Full
Full

width
width
width
width

1.2
1.0
1.2
1.2

Through cracks

WING WALLS
Electromagnetic Test Results for the Wing Walls
Re-bar spacing

Average

(mm)

covers

Re-bar size

Vertical:470
Horizontal:450
Vertical:350
Horizontal:260,370

(mm)
Vertical:40
Horizontal:61
Vertical:60
Horizontal:75

(mm)
Vertical:20
Horizontal:16
Vertical:20
Horizontal:16

Test Element/Location

Nyeri Side

RHS

Nyahururu Side

LHS

Schmidt Hammer Test Results for the Wing Walls


Average concrete strength
(N/mm2)

Test Element/Location
RHS

56.4

LHS

54.0

LHS

53.9

RHS

55.0

Nyeri Side

Nyahururu
Side

BRIDGE AT KM 84+520
Ultrasonic Pulse Velocity Results for the Wing Walls
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Test Element/Location

Homogeneity of concrete matrix

LHS

Homogeneous

RHS

Homogeneous

LHS

Homogeneous

RHS

Homogeneous

Nyeri Side

Nyahururu Side

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 84+520
STEEL GIRDERS
Ultrasonic Tests for Plate Thickness & Lamination
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

SG1 LHS

6
0
0

No Delamination

23.5

14.2

SG2 LHS

6
0
0

No Delamination

23.7

14.2

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 84+520
STEEL GIRDERS
Ultrasonic Tests for Plate Thickness & Lamination
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

SG3 Centre

ICT

6
0
0

No Delamination

22.6

14.3

SG2 RHS

6
0
0

No Delamination

22.3

14.1

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 84+520
STEEL GIRDERS
Ultrasonic Tests for Plate Thickness & Lamination

Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

SG1 RHS

6
0
0

No Delamination

22.4

13.9

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 84+520
PIER COLUMNS
Electromagnetic Test Results for the Pier Columns
Test element

Column Size(mm),

/location

No. & Arrangement of re-bars

Re-bar

Average

Link

size

covers

Details

(mm)

(mm)

(mm)

Side A:50
Side B:63
Side C:70
Side D:55

size:10
Spacing:300

A
20
0

200

PC 1-Nyeri
side
LHS

75
0

25
0

D
D
B

25
0

600

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

32

MTRD

ICT

A
200

PC 2-Nyeri
side
RHS

20
0
75
0

25
0

D
D

32

Side A:53
Side B:56
Side C:56
Side D:50

size:10
Spacing:300

25
0

600

BRIDGE AT KM 84+520
Test element

Column Size(mm),

Re-bar

Average

Link

/location

No. & Arrangement of re-bars

size

covers

Details

(mm)

(mm)

(mm)

Side A:58
Side B:56
Side C:51
Side D:60

size:10
Spacing:300

A
20
0

PC 1Nyahururu
side
LHS

20
0

75
0

28
0

D
D
B
28
0

600
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

32

MTRD

ICT

A
20
0

20

PC 1Nyahururu
side
LHS

75
0

2
5
0

D
D

Side A:55
Side B:56
Side C:50
Side D:50

32

B
25
0

600

BRIDGE AT KM 84+520
Schmidt Hammer Test Results for the Pier Columns
Average concrete strength
Test Element/Location

(N/mm2)

RHS

55.0

LHS

61.6

Nyeri Side
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

size:10
Spacing:300

MTRD

ICT

Nyahururu
Side

LHS

48.0

RHS

54.0

Ultrasonic Pulse Velocity Results for the Pier Columns for homogeneity
Test Element/Location

Homogeneity of concrete matrix

LHS

Homogeneous

Nyeri Side

RHS

Homogeneous

Nyahururu Side

LHS

Homogeneous
Homogeneous
RHS

Ultrasonic Pulse Velocity Results for the Pier Columns for quality of concrete
Test Element/Location

Transit time
(s)

Pulse velocity
Distance

(km/s)

(mm)

LHS

144

600

4.16

RHS

148

600

4.05

LHS

137

600

4.40

RHS

142

600

4.22

Nyeri Side

Nyahururu Side

remarks

Good quality
concrete

Carbonation Test Results for the Pier Columns


Test
Element/Locatio
n

Nyeri side
Nyahururu side

Carbonation

Least

Balance of

Remarks/deterioration

depth

cover

carbonation

degree

(mm)

recorded

depth

(mm)

(mm)

49

46

40

37

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

None

MTRD

ICT

BRIDGE AT KM 84+520
Resistivity Test Results for the Pier Columns
Test
Element/Locatio
n

Resistivity

Remarks

(kcm)

111.6
Nyeri side
Nyahururu side

Probability of corrosion is
insignificant
111.6

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 93+380
ABUTMENTS
Electromagnetic Test Results for the Abutments
Abutment
Test Element/Location

LHS
At
abutment
cap

Centre
RHS

A1 Nyeri
Side

LHS
Along the
middle
line

Centre
RHS
LHS

At
abutment
cap

Centre
RHS

A2
Nyahururu
Side

LHS
Along the
middle
line

Centre
RHS

Re-bar

Average

Re-bar size

wall

spacing

covers

(mm)

Thickness

(mm)
Vertical:450
Horizontal:400
Vertical:450
Horizontal:500
vertical:450
Horizontal:440
Vertical:450
Horizontal:400
Vertical:450
Horizontal:400
Vertical :450
Horizontal:420
Vertical:430
Horizontal:400
Vertical:440
Horizontal:400
Vertical :450
Horizontal:400
Vertical:450
Horizontal:400
Vertical:440
Horizontal:400
Vertical :450
Horizontal:400

(mm)
Vertical:30
Horizontal:55
Vertical:32
Horizontal:55
Vertical:40
Horizontal:65
Vertical:40
Horizontal:70
Vertical:36
Horizontal:50
Vertical:40
Horizontal:65
Vertical:28
Horizontal:55
Vertical:35
Horizontal:60
Vertical:54
Horizontal:72
Vertical:30
Horizontal:55
Vertical:30
Horizontal:55
Vertical:40
Horizontal:66

Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16

Schmidt Hammer Test Results for the Abutments

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

(mm)

700

700

MTRD

ICT

Average concrete strength


(N/mm2)

Test Element/Location
LHS
Centre
RHS
LHS
Centre
RHS
LHS
Centre
RHS
LHS
Centre
RHS

At abutment cap
A1 Nyeri Side
Along the middle
line
At abutment cap
A2 Nyahururu
Side

Along the middle


line

45.5
60.3
43.2
57.6
43.8
44.2
40.1
58.7
48.2
51.1
56.2
45.8

BRIDGE AT KM 93+380
ABUTMENTS
Ultrasonic Pulse Velocity Results for the Abutments
Test Element/Location

Homogeneity of concrete
matrix
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous

LHS
Centre
RHS
RHS
LHS
Centre
RHS
Centre
RHS

A1 Nyeri Side

A2 Nyahururu Side

Carbonation Test Results for the Abutments


Test
Element/Location

A1-Nyeri side
A2-Nyahururu
side

Carbonation

Least

Balance of

Remarks/deterioration

depth

cover

carbonation

degree

(mm)

recorded

depth

(mm)

(mm)

30

25

Low

28

23

Low

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Resistivity Test Results for the Abutments


Resistivity

Test
Element/Location

Remarks

(kcm)
110.8

A1-Nyeri side
A2-Nyahururu side

Probability of corrosion is
insignificant

110.4

Crack Profiles for the Abutments


Test
Element/Locatio
n

Crack

Crack length

Crack width

Crack depth

no.

(mm)

(mm)

(mm)

1.0

61

1.0

60

0.8

48

0.6

40

Cr.1
A1-Nyeri side
Cr.2
Cr.3
Cr.4

Full height of
abutment wall
Full height of
abutment wall
Full height of
abutment wall
Full height of
abutment wall

BRIDGE AT KM 93+380
Crack Profiles for the Abutments
Test
Element/Locatio
n

Crack

Crack length

Crack width

Crack depth

no.

(mm)

(mm)

(mm)

Cr.1
A2-Nyahururu
side

Cr.2
Cr,3

Full height of
abutment wall
Full height of
abutment wall
Full height of
abutment wall

DECK SLAB
Electromagnetic Test Results for the Deck Slab
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

1.0
55
1.0

41

0.6

33

MTRD

ICT

Deck slab
Test Location

Re-bar spacing

Average covers

Re-bar size

Thickness

DS2 Mid Span

(mm)
Longitudinal:400
Transverse:300
Longitudinal:400
Transverse:300

(mm)
Longitudinal:54
Transverse:34
Longitudinal:35
Transverse:50

(mm)
Longitudinal:20
Transverse:16
Longitudinal:20
Transverse:16

DS3-Nyahururu
side

Longitudinal:400
Transverse:300

Longitudinal:34
Transverse:48

Longitudinal:20
Transverse:16

DS1-Nyeri Side

(mm)

200

Schmidt Hammer Test Results for the Deck Slab


Average concrete strength
Test Location

(N/mm2)

DS1-Nyeri Side

54.5

DS2 Mid Span

56.6

DS3-Nyahururu side

56.1

Ultrasonic Pulse Velocity Results for the Deck Slab


Test Element/Location

Homogeneity of concrete matrix


Homogeneous

DS1-Nyeri Side
Homogeneous
DS2 Mid Span
DS3-Nyahururu side

Homogeneous

BRIDGE AT KM 93+380
Carbonation Test Results for the Deck Slab
Test
Element/Locatio
n

Carbonation

Least cover

Balance of

Remarks/degree

depth

recorded

carbonation

of deterioration

(mm)

(mm)

depth
(mm)

DS1-Nyeri Side
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

34

29

DS2 Mid Span

35

30

DS3-Nyahururu
side

34

29

Low

DECK SLAB
Resistivity Test Results for the Deck Slab
Resistivity

Test
Element/Locatio

Remarks

(kcm)

DS1-Nyeri Side

106.8

DS2 Mid Span

108.8

DS3-Nyahururu
side

110.2

Probability of corrosion is
insignificant

Crack profiles For the Deck Slab


Test
Element/Locatio
n

DS1-Nyeri side
DS3-Nyahururu
side

Crack

Crack length

Crack width

Crack depth

no.

(mm)

(mm)

(mm)

11600-full width
11600-full width

1.0
1.0

Cr.1
Cr.1

Through crack
Through crack

WING WALLS
Electromagnetic Test Results for the Wing Walls
Test Element/Location

Nyeri Side

Nyahururu Side

Re-bar spacing

Average covers

Re-bar size

(mm)

(mm)

(mm)

LHS

Vertical:450
Horizontal:350

Vertical:37
Horizontal:60

Vertical:20
Horizontal:16

RHS

Vertical:450
Horizontal:350

Vertical:45
Horizontal:68

Vertical:20
Horizontal:16

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 93+380
Schmidt Hammer Test Results for the Wing Walls
Average concrete strength
(N/mm2)

Test Element/Location
Nyeri Side

Nyahururu Side

LHS

57.9

RHS

57.7

RHS

65.0

LHS

60.2

Ultrasonic Pulse Velocity Results for the Wing Walls


Test Element/Location

Homogeneity of concrete matrix


Homogeneous

LHS
Homogeneous

Nyeri Side
RHS

Homogeneous
Nyahururu Side

LHS
Homogeneous
RHS

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 93+380
STEEL GIRDERS
Ultrasonic Tests for Plate Thickness & Lamination
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

SG1 LHS

6
0
0

No Delamination

22.1

14.2

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

SG2 LHS

6
0
0

No Delamination

22.0

14.2

BRIDGE AT KM 93+380
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

SG3 Centre

ICT

6
0
0

No Delamination

22.5

14.0

SG2 RHS

6
0
0

No Delamination

22.4

14.2

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 93+380
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

SG1 RHS

6
0
0

No Delamination

22.1

14.0

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 102+510
ABUTMENTS
Electromagnetic Test Results for the Abutments
Test Element/Location

Re-bar spacing

Average

Re-bar size

Abutment wall

(mm)

covers

(mm)

Thickness

(mm)
LHS
A1 Nyeri Side

Centre
RHS
LHS
Centre

A2
Nyahururu
Side

RHS

Vertical:450
Horizontal:400
Vertical:450
Horizontal:400
vertical:450
Horizontal:400
Vertical:450
Horizontal:400
Vertical:450
Horizontal:400
vertical:450
Horizontal:400

(mm)

Vertical:45
Horizontal:60
Vertical:40
Horizontal:50
Vertical:26
Horizontal:57
Vertical:40
Horizontal:55
Vertical:37
Horizontal:51
Vertical:30
Horizontal:55

Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16

Schmidt Hammer Test Results for the Abutments


Average concrete strength
Test Element/Location

A1 Nyeri Side
Side A2
Nyahururu

LHS
Centre
RHS
LHS
Centre
RHS

ABUTMENTS
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

(N/mm2)
59.1
57.7
51.0
40.8
52.4
55.8

MTRD

ICT

Ultrasonic Pulse Velocity Results for the Abutments


Test Element/Location

Homogeneity of concrete
matrix
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous

LHS
Centre
RHS
LHS
Centre
RHS

A1 Nyeri Side

A2 Nyahururu Side

BRIDGE AT KM 102+510
Carbonation Test Results for the Abutments
Test

Carbonation

Least

Balance of

Remarks/deterioration

Element/Location

depth

cover

carbonation

degree

(mm)

recorded

depth

(mm)

(mm)

Low
A1-Nyeri side
A2-Nyahururu
side

26

22

30

26

Low

Resistivity Test Results for the Abutments


Test

Resistivity

Element/Location

(kcm)

Remarks

110.8
A1-Nyeri side

Probability of corrosion is
insignificant

A2-Nyahururu side

110.8

Crack Profiles for the Abutments


Test

Crack

Crack length

Crack width

Crack depth

Element/Locatio

no.

(mm)

(mm)

(mm)

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

A1-Nyeri side

A2-Nyahururu
side

Cr.1
Cr.2
Cr.3
Cr.4
Cr.1
Cr.2

1400
1400
1400
1400
2000
2000

0.4
0.7
1.2
1.2
0.8
1.0

20
33
42
40
35
38

DECK SLAB
Electromagnetic Test Results for the Deck Slab
Deck slab
Test Location

DS1-Nyeri Side

Re-bar spacing

Average covers

Re-bar size

Thickness

(mm)

(mm)

(mm)

(mm)

DS2 Mid Span

Longitudinal:400
Transverse:300
Longitudinal:400
Transverse:300

Longitudinal:45
Transverse:30
Longitudinal:45
Transverse:60

Longitudinal:20
Transverse:16
Longitudinal:20
Transverse:16

DS3-Nyahururu
side

Longitudinal:400
Transverse:300

Longitudinal:33
Transverse:45

Longitudinal:20
Transverse:16

BRIDGE AT KM 102+510
Schmidt hammer Test Results for the Deck Slab
Average concrete strength
Test Location

(N/mm2)

DS1-Nyeri Side

55.4

DS2 Mid Span

57.7

DS3-Nyahururu side
54.6

Ultrasonic Pulse Velocity Results for the Deck Slab


Test Element/Location

Homogeneity of concrete matrix

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

200

MTRD

ICT

Inhomogeneous
DS1-Nyeri Side
Inhomogeneous
DS2 Mid Span
DS3-Nyahururu side

Inhomogeneous

Carbonation Test Results for the Deck Slab


Test

Carbonation

Least

Balance of

Remarks/deterioration

Element/Locatio

depth

cover

carbonation

degree

(mm)

recorded

depth

(mm)

(mm)

DS1-Nyeri Side

30

25

DS2 Mid Span

45

40

DS3-Nyahururu
side

Low
None
None

33

28

DECK SLAB
Resistivity Test Results for the Deck Slab
Test

Resistivity

Element/Locatio

(kcm)

Remarks

110.8

DS1-Nyeri Side

Probability of corrosion is
insignificant

110.8

DS2 Mid Span

110.8

DS3-Nyahururu
side

BRIDGE AT KM 102+510
Crack profiles For the Deck Slab
Test
Element/Locatio
n

DS1-Nyeri side

Crack

Crack length

Crack width

Crack depth

no.

(mm)

(mm)

(mm)

Full width of the


deck

0.8

Through

Cr.1

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

DS3-Nyahururu
side

Cr.1

Full width of the


deck

0.8

Through

WING WALLS
Electromagnetic Test Results for the Wing Walls
Re-bar spacing

Average

Re-bar size

(mm)

covers

(mm)

(mm)
Vertical: 29
Horizontal:50
Vertical: 35
Horizontal:55

Vertical: 20
Horizontal:16
Vertical: 20
Horizontal:16

Test Element/Location

Nyeri Side

RHS

Nyahururu Side

LHS

Vertical:500
Horizontal:400
Vertical:500
Horizontal:450

Schmidt Hammer Test Results for the Wing Walls


Average concrete strength
(N/mm2)
59.1

Test Element/Location
RHS

60.1

Nyeri Side
LHS

48.8
Nyahururu
Side

LHS
55.8
RHS

Ultrasonic Pulse Velocity Results for the Wing Walls


Test Element/Location

Homogeneity of concrete matrix

LHS

Homogeneous

Nyeri Side

RHS

Homogeneous

Nyahururu Side

LHS

Homogeneous
Homogeneous
RHS

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 102+510
STEEL GIRDERS
Ultrasonic Tests for Plate Thickness & Lamination
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

SG1 LHS

6
0
0

No Delamination

22.5

14.0

SG2 LHS

6
0
0

No Delamination

22.7

14.1

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 102+510
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

SG3 Centre

6
0
0

No Delamination

21.9

14.3

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

SG2 RHS

6
0
0

No Delamination

22.1

14.1

BRIDGE AT KM 102+510
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

6
0
0

No Delamination

SG1 RHS

22.4

14.0

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 125+670
DECK SLAB
Electromagnetic Test Results for the Deck Slab
Deck slab
Test Location

DS1-Nyeri Side

Re-bar spacing

Average covers

Re-bar size

Thickness

(mm)

(mm)

(mm)

(mm)

DS2 Mid Span

Longitudinal:400
Transverse:300
Longitudinal:400
Transverse:300

Longitudinal:45
Transverse:32
Longitudinal:45
Transverse:25

Longitudinal:20
Transverse:12
Longitudinal:20
Transverse:12

DS3-Nyahururu
side

Longitudinal:400
Transverse:300

Longitudinal:51
Transverse:38

Longitudinal:20
Transverse:12

200

Schmidt Hammer Test Results for the Deck Slab


Average concrete strength
Test Location

(N/mm2)

DS1-Nyeri Side

40.2

DS2 Mid Span

43.4

DS3-Nyahururu side
46.5

Ultrasonic Pulse Velocity Results for the Deck Slab


Test Element/Location

Homogeneity of concrete matrix


Inhomogeneous

DS1-Nyeri Side
Inhomogeneous
DS2 Mid Span
DS3-Nyahururu side

Inhomogeneous

Carbonation Test Results for the Deck Slab


Test
Element/Locatio
n

Carbonation

Least

Balance of

Remarks/deterioration

depth

cover

carbonation

degree

(mm)

recorded

depth

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

(mm)

(mm)
Low

DS1-Nyeri Side

25

21
None

DS2-Nyahururu
side

38

34

BRIDGE AT KM 102+510
DECK SLAB
Resistivity Test Results for the Deck Slab
Test

Resistivity

Element/Locatio

(kcm)

Remarks

112.3

DS1-Nyeri Side
DS2 Mid Span

118.8

DS2-Nyahururu
side

110.8

Probability of corrosion is
insignificant

Crack Profiles for the Deck Slab


Test
Element/Locatio
n

DS1-Nyeri side

Crack

Crack length

Crack width

Crack depth

no.

(mm)

(mm)

(mm)

Cr.1
Cr.2

DS2-Mid span

Cr.1
Cr.2

DS3-Nyahururu
side

Cr.1
Cr.2

Full width
deck
Full width
deck
Full width
deck
Full width
deck
Full width
deck
Full width
deck

of the

1.0

of

1.0

of

0.8

of

1.0

of

1.0

of

1.0

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Through cracks

MTRD

ICT

BRIDGE AT KM 102+510
STEEL GIRDERS
Ultrasonic Tests for Plate Thickness & Lamination
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

SG1 LHS

6
0
0

No Delamination

23.0

13.6

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

SG2 LHS

6
0
0

No Delamination

22.5

13.5

BRIDGE AT KM 102+510
Ultrasonic Tests for Plate Thickness & Lamination
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

SG3 Centre

ICT

6
0
0

No Delamination

22.5

13.2

SG2 RHS

6
0
0

No Delamination

21.5

13.4

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 102+510
Ultrasonic Tests for Plate Thickness & Lamination
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

SG1 RHS

6
0
0

No Delamination

22.4

13.7

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 102+510
PIER WALLS
Electromagnetic Test Results for the Pier Walls
Re-bar spacing

Average

Re-bar size

Pier wall

(mm)

covers

(mm)

Thickness

Test Element/Location

Nyeri Side

Vertical:300
Horizontal:450
Vertical:300
Horizontal:450
Vertical:300
Horizontal:450
Vertical:300
Horizontal:450
Vertical:300
Horizontal:450
Vertical:300
Horizontal:450

RHS
Centre
LHS

Nyahururu
Side

LHS
Centre
RHS

(mm)
Vertical: 53
Horizontal:67
Vertical: 48
Horizontal:69
Vertical:55
Horizontal:67
Vertical: 42
Horizontal:57
Vertical: 52
Horizontal:66
Vertical:50
Horizontal:64

(mm)
Vertical:25
Horizontal:16
Vertical: 25
Horizontal:16
Vertical:25
Horizontal:16
Vertical: 25
Horizontal:16
Vertical: 25
Horizontal:16
Vertical:25
Horizontal:16

Schmidt Hammer Test Results for the Pier Walls


Average concrete strength
Test Element/Location

Nyeri Side

Nyahururu
Side

(N/mm2)

RHS

50.0

Centre

52.4

LHS

51.0

LHS

53.8

Centre

56.4
48.1

RHS
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

600

MTRD

ICT

Ultrasonic Pulse Velocity Results for the Pier Walls


Test Element/Location

Nyeri Side

Homogeneity of concrete matrix

LHS

Homogeneous

Centre

Homogeneous

RHS

Homogeneous
Homogeneous

LHS
Homogeneous

Nyahururu Side
Centre

Homogeneous
RHS

BRIDGE AT KM 102+510
Ultrasonic Pulse Velocity Results for the Pier walls for quality of concrete
Test Element/Location

Transit time

Distance

Pulse velocity

(s)

(mm)

(km/s)
4.5
4.3

Nyeri Side

LHS

133

600

Nyahururu Side

LHS

139

600

Remarks

Good quality
concrete

Carbonation Test Results for the Pier Walls


Test

Carbonation

Least

Balance of

Remarks/deterioration

Element/Locatio

depth

cover

carbonation

degree

(mm)

recorded

depth

(mm)

(mm)

None
Nyeri side

48

40
None

Nyahururu side

42

38

Resistivity Test Results for the Pier Walls


Test

Resistivity

Element/Location

(kcm)

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Remarks

MTRD

ICT

Nyeri side

111.3

Nyahururu side

112.3

Probability of corrosion is
insignificant

BRIDGE AT KM 142+450
ABUTMENTS
Electromagnetic Test Results for the Abutments
Test Element/Location

Re-bar spacing

Average

Re-bar size

Abutment wall

(mm)

covers

(mm)

Thickness

(mm)
LHS
A1 Nyeri Side

Centre
RHS
LHS

A2
Nyahururu
Side

Centre
RHS

Vertical:450
Horizontal:400
Vertical:450
Horizontal:400
vertical:450
Horizontal:400
Vertical:450
Horizontal:400
Vertical:430
Horizontal:420
vertical:450
Horizontal:400

Vertical:27
Horizontal:50
Vertical:27
Horizontal:50
Vertical:26
Horizontal:57
Vertical:42
Horizontal:60
Vertical:36
Horizontal:55
Vertical:41
Horizontal:67

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

(mm)
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16
Vertical:25
Horizontal:16

900

900

MTRD

ICT

Schmidt Hammer Test Results for the Abutments


Average concrete strength
(N/mm2)

Test Element/Location
LHS
Centre
RHS
LHS
Centre
RHS

A1 Nyeri Side
Side A2
Nyahururu

60.8
64.8
63.9
60.7
60.9
54.6

ABUTMENTS
Ultrasonic Pulse Velocity Results for the Abutments
Test Element/Location

Homogeneity of concrete
matrix
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous
Homogeneous

LHS
Centre
RHS
LHS
Centre
RHS

A1 Nyeri Side

A2 Nyahururu Side

BRIDGE AT KM 142+450
Carbonation Test Results for the Abutments
Test

Carbonation

Least

Balance of

Remarks/deterioration

Element/Location

depth

cover

carbonation

degree

(mm)

recorded

depth

(mm)

(mm)

Low
A1-Nyeri side
A2-Nyahururu
side

26

19

30

23

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Low

MTRD

ICT

Resistivity Test Results for the Abutments


Test

Resistivity

Element/Location

(kcm)

Remarks

111.8
A1-Nyeri side

Probability of corrosion is
insignificant

A2-Nyahururu side

111.3

Crack Profiles for the Abutments


Test

Crack

Crack length

Crack width

Crack depth

Element/Locatio

no.

(mm)

(mm)

(mm)

Cr.1
Cr.2
Cr.3

3500
3500
2000

1.2
1.2
1.0

41
42
30

A1-Nyeri side

DECK SLAB
Electromagnetic Test Results for the Deck Slab
Test Location

Re-bar spacing

Average covers

Re-bar size

Deck slab

(mm)

(mm)

(mm)

Thickness
(mm)

DS1-Nyeri Side

DS2 Mid Span

Longitudinal:400
Transverse:300
Longitudinal:400
Transverse:300

Longitudinal:41
Transverse:29
Longitudinal:47
Transverse:33

Longitudinal:20
Transverse:12
Longitudinal:20
Transverse:12

DS3-Nyahururu
side

Longitudinal:400
Transverse:300

Longitudinal:45
Transverse:30

Longitudinal:20
Transverse:12

BRIDGE AT KM 142+450
Schmidt hammer Test Results for the Deck Slab
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

200

MTRD

ICT

Average concrete strength


Test Location

(N/mm2)

DS1-Nyeri Side

53.3
52.1

DS2 Mid Span


DS3-Nyahururu side

48.8

Ultrasonic Pulse Velocity Results for the Deck Slab


Test Element/Location

Homogeneity of concrete matrix


Inhomogeneous

DS1-Nyeri Side
Inhomogeneous
DS2 Mid Span
DS3-Nyahururu side

Inhomogeneous

Carbonation Test Results for the Deck Slab


Test
Element/Locatio
n

Carbonation

Least

Balance of

Remarks/deterioration

depth

cover

carbonation

degree

(mm)

recorded

depth

(mm)

(mm)

DS1-Nyeri Side

6.0

29

23

Low

DS3-Nyahururu
side

6.0

30

24

Low

DECK SLAB
Resistivity Test Results for the Deck Slab
Test

Resistivity

Element/Locatio

(kcm)

Remarks

DS1-Nyeri Side

110.0

DS2 Mid Span

111.3

DS3-Nyahururu
side

111.1

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Probability of corrosion is
insignificant

MTRD

ICT

BRIDGE AT KM 142+450
WING WALLS
Electromagnetic Test Results for the Wing Walls
Test Element/Location
LHS
Nyeri Side
Nyahururu Side

LHS

Re-bar spacing

Average covers

Re-bar size

(mm)
Vertical:300
Horizontal:300
Vertical:450
Horizontal:450

(mm)
Vertical:68
Horizontal:45
Vertical:33
Horizontal:45

(mm)
Vertical:20
Horizontal:6
Vertical:20
Horizontal:16

Schmidt Hammer Test Results for the Wing Walls


Average concrete strength
(N/mm2)

Test Element/Location
RHS

59.4

LHS

62.0

LHS

53.2

RHS

55.0

Nyeri Side

Nyahururu
Side

Ultrasonic Pulse Velocity Results for the Wing Walls


Test Element/Location

Homogeneity of concrete matrix

LHS

Homogeneous

Nyeri Side

RHS

Homogeneous

Nyahururu Side

LHS

Homogeneous

RHS

Homogeneous

Carbonation Test Results for the Wing Walls


Test

Carbonation

Least

Balance of

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Remarks/deterioration

MTRD

ICT

Element/Locatio
n

Nyeri side
Nyahururu side

depth

cover

carbonation

degree

(mm)

recorded

depth

(mm)

(mm)

33

28

Low

45

38

None

BRIDGE AT KM 142+450
Resistivity test results for the Wing Walls
Test
Element/Locatio
n

Resistivity

Remarks

(kcm)

110.0
Nyeri side
Nyahururu side

111.5

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Probability of corrosion is
insignificant

MTRD

ICT

BRIDGE AT KM 142+450
STEEL GIRDERS
Ultrasonic Tests for Plate Thickness & Lamination
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

SG1 LHS

6
0
0

No Delamination

25

15.0

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

SG2 LHS

ICT

6
0
0

No Delamination

25

14.5

BRIDGE AT KM 142+450
Ultrasonic Tests for Plate Thickness & Lamination
DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

SG3 Centre

60
0

No Delamination

23.2

14.3

SG2 RHS

60
0

No Delamination

23.5

14.5

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 142+450
Ultrasonic Tests for Plate Thickness & Lamination
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

SG1 RHS

6
0
0

No Delamination

22.4

14.0

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

BRIDGE AT KM 173+120
DECK SLAB
Electromagnetic Test Results for the Deck Slab
Deck slab
Test Location

Re-bar spacing

Average covers

Re-bar size

Thickness

(mm)

(mm)

(mm)

(mm)

DS1-Nyeri Side
RHS
DS2 Nyeri Side
Centre

Longitudinal:150
Transverse:130
Longitudinal:150
Transverse:120

Longitudinal:20
Transverse:10
Longitudinal:20
Transverse:12

Longitudinal:16
Transverse:12
Longitudinal:16
Transverse:12

DS3-Nyeri Side
LHS

Longitudinal:150
Transverse:130

Longitudinal:20
Transverse:10

Longitudinal:16
Transverse:12

Schmidt hammer Test Results for the Deck Slab


Average concrete strength
Test Location

(N/mm2)

DS1-Nyeri Side LHS

30.7

DS1-Nyeri Side Centre

40.4

DS1-Nyeri Side RHS

55.2

DS2-Karatina side LHS

52.1

DS2-Karatina side Centre

51.3

DS2-Karatina side RHS

40.6

Ultrasonic Pulse Velocity Results for the Deck Slab


DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

Test Element/Location

Homogeneity of concrete matrix

DS1-Nyeri Side
RHS

Slightly Inhomogeneous

DS2 Nyeri Side Centre

Slightly Inhomogeneous
Slightly Inhomogeneous

DS3-Nyeri Side LHS

Carbonation Test Results for the Deck Slab


Test

Carbonation

Least

Balance of

Remarks/Deterioration

Element/Locatio

depth

cover

carbonation

degree

(mm)

recorded

depth

(mm)

(mm)

10

DS1-Nyeri Side

High

BRIDGE AT KM 173+120
DECK SLAB
Resistivity Test Results for the Deck Slab
Test

Resistivity

Element/Locatio

(kcm)

Remarks

n
DS1-Nyeri Side

111.4

Probability of corrosion is
insignificant

PIER COLUMNS
Test element

Column Size(mm),

/location

No.& Arrangement of re-bars

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Re-bar

Average

Link

size

covers

Details

(mm)

(mm)

(mm)

MTRD

ICT

AA
350

PC 1-Nyeri
side
LHS

60
0
50
0

32

Side A:53
Side B:23
Side C:26
Side D:36

size:10
Spacing:250

Side A:20
Side B:18
Side C:25
Side D:22

size:10
Spacing:250

450

C
AA
350

PC 2-Nyeri
side
LHS

60
0
50
0

32

450

BRIDGE AT KM 173+120
PIER COLUMNS
Test element

Column Size(mm),

Re-bar

Average

Link

/location

No.& Arrangement of re-bars

size

covers

Details

(mm)

(mm)

(mm)

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

AA
350

PC 1-Nyeri
side
RHS

60
0
50
0

32

Side A:31
Side B:32
Side C:24
Side D:30

size:10
Spacing:250

Side A:35
Side B:30
Side C:36
Side D:25

size:10
Spacing:250

450

C
AA
350

PC 2-Nyeri
side
RHS

60
0
50
0

450

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

32

MTRD

ICT

BRIDGE AT KM 173+120
Schmidt Hammer Test Results for the Pier Columns
Average concrete strength
(N/mm2)

Test Element/Location
PC1LHS

45.0

PC2LHS

32.0

PC1RHS

41.8

PC2RHS

45.0

PC1LHS

43.0

PC2LHS

50.0

PC1RHS

52.1

PC2RHS

55.0

Nyeri Side

Karatina
Side

Carbonation Test Results for the Pier Columns


Test Element/Location

Carbonation

Least

Balance of

Remarks/

depth

cover

carbonatio

deterioration

(mm)

recorded

n depth

degree

(mm)

(mm)

PC1LHS

23

17

Low

PC2LHS

18

12

Low

PC1RHS

24

18

Low

PC2RHS

25

19

Low

Nyeri side

Resistivity test results for the Pier Columns


Test Element/Location

Resistivity

Remarks

(kcm)
Nyeri side

PC2
RHS

111.4

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Probability of corrosion is
insignificant

MTRD

ICT

BRIDGE AT KM 173+120
STEEL GIRDERS
Ultrasonic Tests for Plate Thickness & Lamination
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

SG1 LHS

8
7
0

No Delamination

24

17.0

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

ICT

SG2 LHS

8
7
0

No Delamination

23

16.5

BRIDGE AT KM 173+120
Ultrasonic Tests for Plate Thickness & Lamination
Steel Girder

Section Dimensions

Continuity Across

No.

(mm)

Plate Thickness

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

MTRD

SG3 Centre

ICT

87
0

No Delamination

23.5

16.5

SG2 RHS

60
0

No Delamination

22.5

16.0

DETAILED INSPECTION REPORT FOR BRIDGES ALONG ROAD B5

Вам также может понравиться