ACERC/DOECE/2010-11/PTS/1
CHAPTER-1
INTRODUCTION:-
Shyam lal college chowk is located in the trans yamuna area. This foue arm
intersection is one of the major and most congested intersections. Presently, the intersection is
being controlled by traffic signals. The intersection being close to welcome metro station and
shyam lal college assumes special significance. Hence there is a great need for construction
of grade separator at shyam lal college chowk for free movement of traffic and pedestrians at
the intersection. The road no.57 is a major artery of the Trans yamuna road system. Large
volume of traffic flows on this road. There is free movement of traffic on 3 km shahdara
flyover on g.t road and shyam lal college chowk is located at a distance of400 m from
shahdara flyover which is a major bottleneck. The waiting time at signal goes up to 5-8
minutes. With the construction of grade separator, there would be free flow of traffic and
pedestrians. The construction of grade separator will also result in national saving in terms of
fuel, comfort to traffic and saving of valuable time and also reduces accidents substantially.
--- Flyover along g.t road at shyam lal college to ensure uninterrupted movement of straight
going traffic from old ISBT to U.P border.
---Underpass joining road no-57&65 to ensure free movement of traffic from road no-57 to
road no-65and vice-versa as road no-57 is main artery road of trans yamuna.
----------Rotary at surface level to allow free right turn
Three nos. foot over bridges to ensure risk free movement of pedestrians.
----U-turn underpass across road no-57 to ensure free right turn for slow moving vehicle
coming from Bihari colony..
ACERC/DOECE/2010-11/PTS/2
1.2-TECHNICAL DETAILS
--575 m long main flyover along g.t road (340 m viaduct. Typical span arrangement of
10*30+40 m, Dual carriageway of 9m in each direction) with superstructure of composite
steel construction with prefabricated steel I-girder
---Underpass from road no-57 to road no-65 having length 278m, dual carriageway of 7.5 m
in each direction, substructures with Diaphgram wall and desk slab.
---Rotary at surface for free movement of right turn.
--U-turn underpass across road no-57 having width 5.5m to facilitate right turn for small
vehicle coming from Bihari colony
---Two Nos. foot over bridges across G.T road at both ends of flyover and 1no. Across road
no-57. all the foot over bridges will have escalators.
---Total peak hour traffic at intersection 14,575PCU.
---Pier and pier caps shall be of aesthetically pleasing shape. Surface of fair-faced concrete
pier will have design patterns to enhanced aesthetics.
---Pile foundations passing through various sub-strata.
---Surface level roads of minimum 9m width on either side of flyover.
---Horticulture, Landscaping, electrical lighting and traffic signages.
: 93.82crores
---Tendered amount
a) Civil work
: 65,77.53.640/-
b) Electrical work
: 3, 30, 69,463/-
: october2009
ACERC/DOECE/2010-11/PTS/3
PARTICULARS
QUANTITY UNIT
2460
Mt
Structural steel
1931
Mt
Retaining wall
2281
Mt
2460
Cum
Dbm
2909
Cum
2607
Cum
2400
mtr
m-25,m-35,m- 15851
cum
ACERC/DOECE/2010-11/PTS/4
1.4-BRAINS BEHIND
1.PWD Team;
2.EVOLUTION by;
3.EXECUTION by;
M/S NAVAYUGA
ENGINEERS COMPANY LTD.
FIGURE-1
DRAWING PLAN OF FLYOVER
ACERC/DOECE/2010-11/PTS/5
CHAPTER-2
SCOPE OF WORK:ACERC/DOECE/2010-11/PTS/6
The scope of work for the Grade Separator project for improvement of traffic system is
defined in this chapter. The construction work of total scheme of grade separator is decided
to be taken up in various phases due to diversion of existing traffic.
ACERC/DOECE/2010-11/PTS/7
Phase I Shifting of utilities, removing all existing islands and footpaths, widening
existing roads except at the junction of GT road, Road No 57 and Road No 65 and
diverting the traffic onto the new pavement (as per dwg. No.: TD015).
Phase II Barricading of the central portion except at the junction of GT road, Road
No 57 and Road No 65 construction of Piled foundations and piers for the flyover (as
per dwg. No.: TD015).
Phase III Construction of the superstructure for the viaduct spans, barricading the
obligatory portion and viaduct portion and construction of obligatory spans and
foundation and substructure for these viaducts, Barricading and construction of the
approach portion with R.E Walls and RCC retaining walls. (as per dwg. No.: TD016).
Construction of the central portion of the pedestrian subway shall be taken up in this
phase only.
Phase IV - Construction of the superstructures for the remaining viaducts and
construction of the busbays, all finishing works, landscaping and electrical works (as
per dwg no.: TD016).
Site clearance
Reinforced Earth wall construction and filling of backfill material and road work
ACERC/DOECE/2010-11/PTS/8
Cleaning of site
Thermoplastic lane marking on road surface and painting of railings and crash
barrier
2.4-Broad Scope
The work under pertains to construction of the following components:
1.Construction of Main Flyover at Keshav Chowk along GT Road Shahadra: The
work shall consist of construction of embankments with Reinforced Earth wall &
RCC retaining walls, concrete pavement, Steel-Concrete composite plate girder
superstructure with pile foundations, piers/abutments, deck slab, expansion joints,
bearings, crash barriers etc.
i)
ii)
iii)
Construction of 2 nos. of Foot Over Bridge on either end of the proposed Fly over
along GT Road: Construction of Prefabricated Steel-truss with cast-in situ deck
slab superstructure with open foundation on steel columns, deck slab, expansion
joints, bearings, development of aesthetics etc.
iv)
ACERC/DOECE/2010-11/PTS/9
v)
Constructions of surface level roads, traffic islands, work for Traffic signage etc.
vi)
vii)
viii)
ix)
x)
CHAPTER-3
MATERIALS AND TESTING
ACERC/DOECE/2010-11/PTS/10
3.1 CEMENT
Ordinary Portland Cement of 43 Grade and 53 Grade conforming to IS: 8112 and IS:12269
respectively was used.
TABLE-2
Dia. of Bar
(mm)
Weight
(Kg/m)
10
12
16
18
20
22
25
28
32
36
40
ACERC/DOECE/2010-11/PTS/11
IRC: 83 (Part III): POT, POT CUM PTFE, PIN and Metallic Guide Bearings shall form the
basis of bearing design. All the anchor sleeves, bolts, plates etc. shall be hot dip galvanized @
300 gm/m2.
FIGURE-2
Bearings used under steel girders
Black bolts, nuts and screws (Class 4.6) were in accordance with IS:1363 "Black
Hexagonal Bolts (6 mm to 39 mm ) with "Nuts and Black Hexagonal screws (6 mm
to 24 mm)".
FIGURE-3
Bolts used to join girders
3.7 Admixtures
Type of Admixtures : Retarding admixtures based on Lingosus-Phonates with due
consideration to clause 5.2 and 5.3 of IS:7861 were used. Admixtures generating hydrogen
and nitrogen etc. were used
3.9 Testing
All the tests were done in front of engineer in charge at site and few tests were done by
external laboratories as these tests were not possible to conduct at site laboratory as all the
steel tests were done by Delhi government laboratory of steel testing. A laboratory was set up
at site for the tests of materials such as concrete, water, bitumen, water and cement.
Tests were done depending as per demand. Some tests were monthly, some were done weekly
n some tests were done on daily basis.
---Tests were conducted at labs on site once and then send to other labs for tests and
conformation.
---Tests were conducted in front of pwd officers and samples were passed by them.
STEEL TESTS
1-steel is tested by the manufacturing company and test reports come along the steel with all
the details of desired tests. like-tensile strength
2-steel is also send to another lab for conformation tests
3-it is not possible to conduct test on steel at site.
Concrete m-40
After 7 daysTABLE-3
Weight
Load
Strength
8255
910
40.44
8265
900
40.01
8280
930
41.33
8246
916
43.20
Weight
Load
Strength
8260
930
41.64
8320
1010
45.00
8150
1140
48.24
8400
1208
48.86
After 28 days
Concrete-m-40
TABLE-4
Concrete m-35
After 7-days
TABLE-5
ACERC/DOECE/2010-11/PTS/16
Weight
Load
Strength
8240
800
35.28
8215
830
37.09
8110
780
34.84
8202
820
36.25
Weight
Load
Strength
8360
900
40.10
8135
870
38.40
8275
1000
40.00
Concrete m-35
After 28 days
TABLE-6
CO
RSE
8215
780
37.09
AGGREGATE
10% Fine value
Size of aggregates-20mm
Source of aggr.-yamuna nagar
TABLE-7
ACERC/DOECE/2010-11/PTS/17
DESCRIPTION
SYM
Test no.1
Test no.2
10390
10390
Weight of mould+sample
14190
14215
Weight of sample
3800
3825
345
365
9.07
9.54
Weight of mould
Weight
of
gm
sample
passing D
9.305
X tonnes load
Load
required
for
10%
fines=14*X/Y+4
26.305 tonnes
263.05 K.N
BULK DENSITY
TABLE-8
ACERC/DOECE/2010-11/PTS/18
DESCRIPTION
SAMPLE-1
SAMPLE-2
9280
9280
metal measure(gm)
Weight of cylindrical metal B
31860
31805
22580
22535
14726
14726
measure (cc)
Bulk
1533.34
1530.29
measure
NOTATION
filled
with
aggregate(gm)
Weight of aggregate (B-A)
density
aggregate=C/D*1000 kg/m
Average bulk density kg/m
1531.815
Sym
Test no-1
Test no-2
Test no-3
724.6
724.6
724.6
1049.6
1054.6
1058.6
Weight of sample
325
330
334
46
42
48
14.15
12.72
14.39
(gm)
=13.59
CHAPTER-4
DECK SLAB
ACERC/DOECE/2010-11/PTS/19
4.1-General
The deck slabs of the flyover were constructed using the prestressing technique, so as to
make concrete strong in tension. The width of section is considerably reduced when
ptestressing is used. Less quantity of steel is used, but the technique is expensive than the
normal r.c.c pracities
Concrete used in span was of grade m-35
Steel girder were used at place of pre-casted slabs
Steel girders were of size 10m each and were joined with help of bolte and were made of size
30m
Shuttering was done on this girders only for casting slabs
Pile caps were used after setting up slabs between two sections of slabs
FIGURE-4
Steel girders used at place of pre-casted slabs
ACERC/DOECE/2010-11/PTS/20
Hydraulic jack
4.3-prestressing technology
This type of slab provides benefits of rapid construction, and improved structural
performance. The principal of working of pre-stressed slabs is the wires are used in place of
steel bars. These wires after concreting are pulled with the help of hydraulic jack and tension
is created in wires and is locked at the end preventing the wires not to slip back.
CHAPTER.5
ACERC/DOECE/2010-11/PTS/22
CRASH BARRIER
Crash barriers are made at the end of slabs on both the sides so as to control the accidents.
The crash barriers are made up with concrete ant at the top metal railing was used so as for
good appearance. The crash barriers were also fitted with system for electric work as pipes
were putted while construction so to pass the electric wires for road lights etc.
Crash barriers were constructed up to a height of 1m.
Crash barriers were on both side of a slab.
FIGURE-6
Crash barrier
FIGURE-7
Temperory form work done by welding on steel girders for crash barrier
ACERC/DOECE/2010-11/PTS/23
ACERC/DOECE/2010-11/PTS/24
CHAPTER.6
ROAD WORK:
6.4 LIME
Type of material: Lime for use as filler in bituminous mixes shall be commercial dry
lime, pre-slaked, and delivered to site in suitable packing. It shall have a purity of not
less than 80 per cent by weight of quick-lime (CaO) when tested in accordance with
IS:1514.
Storage of Lime: Lime shall be properly stored to avoid prolonged exposure to the
atmosphere and consequent carbonation.
6.5BITUMEN
1. Type of material : Bituminous materials shall be of the following two types, as
specified in the contract:
i
Bituminous emulsion
2. Polymer modified Bitumen: Polymer modified binder shall comply with the
requirements of IRC:SP-53-2002 and Elastomeric Thermoplastic Specifications.
The modifier shall be Styrene-Butadiene-Styrene, and the blending of the modifier
with bitumen shall be accomplished either in the refinery or an approved plant at
site capable of mixing the modifier and bitumen uniformly. The minimum content
of (SBS) Styrene-Butadiene-Styrene shall be 4% with appropriate sulphur content.
ACERC/DOECE/2010-11/PTS/26
The bitumen of required grade as specified conforming to IS:73-1992 with upto date
amendments and other relevant codes from the manufactuers of repute like Indian Oil
Corporation Ltd, Hindustan Petroleum Corporation Ltd. and Bharat Petroleum
Corporation Ltd. as approved by Ministry of Petroleum, Govt. of India and holding
licence to use ISI certificates mark for their products.
6.6 ROAD WORK (FLEXIBLE PAVEMENT)
TABLE-10
PROFORMA FOR THE BITUMEN REGISTER RECEIPT
--------------------------------------------------------------------------------------------------------Date of
Qty
Receipt
Received Total
Issue
4
Issued
5
Total
Issued
--------------------------------------------------------------------------------------------------------_____________________________________________________________________
--------------------------------------------------------------------------------------------------------Item of
Appx. Qty.
Theoretical requirement
work of
of work
Which issued
done on each
Remarks of
AE/AEE
Ex. Eng.
The 500mm thick of the sub-grade shall be compacted to achieve at least 97% of
MDD at OMC.
6.8 GRANULAR SUB-BASE COURSE
This work shall consist of laying and compacting well-graded material on prepared
sub-grade in accordance with the requirements of these Specifications. The material
shall be laid in one or more layers as sub-base or lower sub-base and upper sub-base
(termed as sub-base hereinafter) as necessary according to lines, grades and crosssections shown on the drawings or as directed by the Engineer-in-Charge.
The granular sub-base (GSB) material shall be closed graded of grading I and III,
conforming to the requirements of clause 401 and table 400-1 of MORTH,
Specifications for Road and Bridge Works (4th Revision 2001).
6.9 WET MIX MACADAM BASE COURSE
The work shall consist of laying and compacting clean, crushed, graded aggregate and
granular material premixed with water, to a dense mass on a prepared subgrade/subbase/base or existing pavement as the case may be in accordance with the
requirements of these specifications. The material shall be laid in one or more layers
as necessary to lines, grade and cross section shown on the approved drawings or as
directed by the Engineer-in-charge. The laying of WMM layer shall be done using
paver only.
The wet mix macadam base course shall satisfy the requirements of clause 406 of
MORTH, Specifications for Road and Bridge Works. (4th revision 2001)
The contractor shall have to necessarily deploy self-propelled paver with electronic
sensor having suitable hydraulically operated screeds capable of spreading, tamping
and finishing the mix true to the specified lines, grades and cross sections of the road.
The paver finisher shall have the following essential features :
ACERC/DOECE/2010-11/PTS/28
i)
ii)
iii)
iv)
The screed shall have tamping and vibrating arrangement for initial
compaction to the layer as it is spread without rutting or otherwise marring the
surface. It shall have adjustable amplitude and variable frequency.
v)
vi)
The paver shall be fitted with an electronic sensing device for automatic
leveling and profile control within the specified tolerances.
vii)
viii)
The paver shall be capable of laying 2.5 to 4.0 m width in service road and
4.0 to 7.0m width on main carriageway as per site requirement.
ix)
x)
The contractor shall have to necessarily deploy the road rollers, for BM, DBM
& BC for their compaction as per relevant MORT&H specifications.
Mix shall be prepared in a computerized hot mix plant of adequate capacity and
capable of yielding a mix of proper and uniform quality with thoroughly coated
aggregate. Hot Mix Plant shall be preferably of batch mix type with electronic load
sensor device. The requirement of clause 504.3.4 of MoRT&H Specifications for
Road and Bridge Works (Fourth Revision) 2001 shall be strictly adhered to.
6.11 PRIME COAT
ACERC/DOECE/2010-11/PTS/29
The work shall consists of the application of a single coat of low viscosity liquid
bituminous material to a porous granular surface preparatory to the superimposition of
bituminous mix material. The work shall execute in accordance with clause 502 and
sub clause there to of MoRT&H Specifications for Road and Bridge Works (Fourth
Revision) 2001.
The emulsified bitumen for prime coat shall be medium setting conforming to
IS:8887-1995. The bitumen emulsion shall be brought at site in one lot in sealed
drums and shall be got verified and checked by the representative of Engineer-inCharge before its use. After priming coat the road can be opened to the traffic as
directed by the engineer in charge.
6.12 TACK COAT
The work shall consist of application of single coat of low viscosity liquid bituminous
material to an existing road surface preparatory to another bituminous construction
over it. The binder used for tack coat shall be bitumen of suitable grade as specified in
nomenclature of item.
a) The emulsified bitumen for tack coat on road shall be medium setting (MS) type
conforming to IS: 8887-1995. The bitumen emulsion shall be brought at site in one lot
in sealed drums and shall be got verified and checked by the representative of
Engineer-in-Charge before its use. The work shall be done strictly in accordance with
clause 503 and sub-clauses thereto of MORT&H specifications for Roads & Bridges
work (Fourth Revision), 2001.
b) Cleaning and Preparation of the Surface: The surface on which the tack coat is to be
applied shall be clean and free from dust, dirt and any extraneous material and be
otherwise prepared in accordance with the requirements of clause 501.8 and 902 of
MORT&H Specifications for Road and Bridge Works (Fourth Revision). Immediately
before the application or the tack coat, the surface shall be swept clean with a
mechanical broom and high pressure jet or by other means as directed by the
Engineer-in-Charge.
6.13 BITUMINOUS MACADAM
The work shall consists of constructing a single layer of specified compacted
ACERC/DOECE/2010-11/PTS/30
Material
i)
Bitumen
Aggregate
ACERC/DOECE/2010-11/PTS/31
Material
i) Bitumen
Bitumen shall confirm to grade and quantity as specified in nomenclature of item.
ii)Aggregate
Aggregate shall consist of crushed stone aggregate confirming to grading and
specification as laid down in sub-clause-507.2.2 to 507.2.5 of MoRT&H
Specifications for Road and Bridge Works (Fourth Revision) 2001. The grading shall
conform to grading of Table 500-10/
iii)Filler
Filler shall consist of hydrated lime of grade & specification conforming to clause
507.2.4 of MORT&H Specification for Roads & Bridges.
The contract unit rate for the Dense Bituminous Macadam shall be payment in full for
carrying out all the required operations as specified, and shall include, but not
necessarily limited to all component listed in 501.8.8.2 (i) to (xi) as MORT&H
Specifications for Road and Bridge Works (Fourth Revision) 2001. The rate shall
include the provision of bitumen in mix design @ 5.0% by weight of total mix with
provision that variation of quantity on minus side shall be recovered @ Rs 25,200/per M.T. of bitumen less use as per design mix. However, no extra payment would be
admissible for use of extra bitumen if the variation is on higher side i.e. beyond 5% of
weight of total mix.
6.15 BITUMINOUS CONCRETE
The work shall consist of constructing a single layer of specified compacted thickness
of bituminous concrete consisting of crushed stone aggregate mixed with bituminous
binder to serve as wearing course laid immediately after mixing on a previously
prepared base in accordance with the requirements of specifications as laid down in
clause 509 and sub-clauses thereto of MORT&H Specifications for Road and Bridge
Works (Fourth Revision) 2001 and as directed by Engineer-in-Charge.
Material
i)
ii)
Aggregate
ACERC/DOECE/2010-11/PTS/32
Filler
Filler shall consist of hydrated lime of grade & specification conforming to clause
509.2.4 of MORT&H Specification for Roads & Bridges(4th revision 2001).
iv)
Rate
The contract unit rate for the Dense Bituminous Concrete using modified bitumen
(PMB-40) shall be payment in full for carrying out all the required operations as
specified, and shall include, but not necessarily limited to all component listed in
501.8.8.2 (i) to (xi) of MORT&H Specifications for Road and Bridge Works
(Fourth Revision) 2001. The rate shall cover the provision of modified bitumen
(PMB-40) in mix design @ 5.5% by weight of total mix with provision that
variation of quantity on minus side shall be recovered @ Rs. 31,800/- per M.T. of
modified bitumen, less used as per design mix. However, no extra payment would
be admissible for use of extra modified bitumen if the variation is on higher side
i.e. beyond 5.5% of weight of total mix.
6.16 COMPACTION
The degree of compaction for the various bituminous layers shall be established by
taking CORE from the laid bituminous layer. The bill of the contractor shall be paid
only if the same qualifies as per the specifications / requirements. Sand replacement
method for verifying the degree of compaction of laid bituminous layers will not be
allowed
6.17 C.C. KERB STONES
Procurement
ACERC/DOECE/2010-11/PTS/33
Pre-cast C.C. kerb stones conforming to M-35 grade of concrete and size as
mentioned in the nomenclature of items, shall be procured only from reputed
manufacturer approved by Engineer-in-Charge. The plant/ factory to be approved by
the Engineer in Charge shall strictly adhere to following norms before supply is
entrusted to them:
(i) The mix shall be prepared in batch mix plant only.
(ii) The plant shall remain open to inspection at any time for above lot.
(iii) A suitable vibrating and curing mechanism shall be maintained to ensure the
quality as desired.
(iv) Minimum grade of concrete shall be M-35 i.e. compressive characteristic
strength of concrete at 28 days shall not be less than 35 N/mm2.
(v) Proper Logo of manufacture shall be engraved on each kerb stone.
(vi) The contractor shall provide original challan / voucher as a proof of having the
material purchased from the approved manufacturer. The original challan/voucher
shall be returned after verification and making necessary endorsement.
Laying
Before laying at site compressive strength test in accordance with specifications shall
be mandatory. Laying shall be as per specifications and direction of Engineer-inCharge.
Sampling And Testing
The contractor shall have to obtain and furnish test certificates issued by
manufacture to the Engineer-in-Charge in respect of material purchased by
him. However, sample shall be collected, at discretion of Engineer-in-Charge
and got tested as per relevant B.I.S. Codes and specifications from the
laboratory provided by him.
The contractor shall supply, free of cost, the required samples of kerb stones
for testing. Cost of tests shall also be borne by the contractor.
In case the test results reveal that the kerb stones procured by the contractor do
not conform to the relevant B.I.S. Codes and specifications, the same lot shall
stand rejected and the contractor shall have to remove that material from site at
ACERC/DOECE/2010-11/PTS/34
his own cost within a weeks time of written order from Engineer-in-Charge to
do so.
For the execution of any items of work where any incidental work is actually
required but not specifically stated in the tender, it is to be understood that the
rate quoted by the contractor shall cover such charges also and nothing extra
on account of such incidental charges, if any, shall be paid.
executing all aspects of the work related to inserts and embedments, including
tolerances, primers, galvanizing etc. so that the final assembly of the concrete
elements can meet satisfactorily the requirements intended in the structure.
Void Former In Concrete
The corrugated spiral tubes void formers shall be of galvanised steel 0.7mm (min)
strips with 4-ply spiral lock seal which runs on the external side manufactured by
specialised agencies using high precision machines. Various matching tube fitting like
slip joint couplings, end blockers etc. and other support systems shall be as per
supplier details. The void formers shall be procured form any of the suppliers listed in
Annexure-A
CHAPTER-7
DIAPHGRAM WALL
ACERC/DOECE/2010-11/PTS/35
7.1
BENDING OF REINFORCEMENT
Bending of reinforcement shall be done as per bar bending schedule to be prepared and
got approved by the contractor from Engineer-in-Charge or his authorised
representative prior to commencement of work. The bar cutting and bending for 16mm
and above diameters shall be done on bar cutting and bending machine only.
PLACING OF REINFORCEMENT
Reinforcement left projecting from newly placed concrete shall be supported in such a
way that there is no sag or risk of damage to the newly placed concrete. The projecting
bars that are likely to be exposed for a long time shall be protected by a coat of neat
cement wash. These shall be thoroughly cleaned and wire brushed before depositing
fresh concrete around it. No reinforcement bar shall remain exposed or projecting out
of the concrete surface. These shall be removed or treated in a manner as directed by
Engineer-in-Charge. The unwanted projected reinforcement bars shall be cut below the
finished surface and the cut end painted with epoxy paint. Thereafter the surface shall
be repaired to match the colour, texture or pattern of adjoining concrete to the
satisfaction of Engineer-in-Charge.
.
BAR SPLICES
The location of joints in continuous reinforcing bars, not shown in drawings, shall be
submitted to the Engineer-in-Charge for acceptance. If nothing contrary has been
ACERC/DOECE/2010-11/PTS/36
specified, the number of bars to be joined in any cross section shall not exceed onethird of the total.
ii)
iii)
iv)
v)
The level of drilling mud shall be maintained at least 1.5m above the contemporary
ground water level. The bentonite slurry shall not be allowed to be discharged into
any nallah/drain or on the ground. The waste slurry shall be removed by
tanker/vehicles as directed by Engineer-in-Charge. In order to avoid collapse of
upper soft soil into the borehole, temporary liner of thickness not less than 6 mm shall
be provided up to at least 5 m from the existing ground level. The liner shall be
provided by hydraulically operated mechanism. After concreting of pile the liner shall
be extracted by vibrators or jacking.
ACERC/DOECE/2010-11/PTS/37
The tremie pipes and funnel shall be filled with concrete and lifted 15 cm above the
bottom of the hole before releasing the concrete column in order to facilitate flushing
it out. The concrete levels in the tremie shall be checked for every few feet in order to
note the difference, if any, between the theoretical quantity that should have been
placed and actual quantity that has gone in. This serves when fixing the position of
over cut during pouring.
In case the actual quantity of concrete poured in the Dwall hole is less than 90%
of the theoretical quantity of concrete for the Dwall, the Dwall shall be
subjected to rejection.
The diameter of tremie pipe shall be 200mm minimum and the funnel should be
capable of holding 0.4 cum of concrete.
Following rules were strictly observed during the tremie method, cited above
i)
ii)
The concrete shall be coherently rich in cement and having slump in the range
of 150mm to 200mm.
iii)
iv)
The tremie shall be large enough in order to cater for the size of aggregates
thereby allowing a smooth uninterrupted flow of concrete. For instance, a
tremie of 200 mm diameter shall suffice the requirements with 20 mm
aggregate. The tremie should be of robust construction conforming to the
approved standards.
ACERC/DOECE/2010-11/PTS/38
v)
The first charge of concrete shall be placed with a sliding plug pushed down
the tube ahead of it to prevent mixing of concrete and water/bentonite slurry.
However, the plug shall not be left in the concrete as a lump.
vi)
The tremie pipe shall always penetrate deep enough (at least 1m) into the
concrete with an adequate margin of safety against accidental withdrawal.
vii)
The pile shall be concreted wholly by tremie and the method of deposition
shall not be changed part way up the pile in order to prevent the latency from
being entrapped within the dwall
viii) The tremie shall essentially be water-tight in order to avoid mixing of bore
fluid with the concrete.
ix)
x)
Normally the concreting of the dwall shall be uninterrupted. In case, under the
unavoidable circumstances, the operation has to suspend for a period of 6 hours
maximum the tremie shall not be taken out of concrete. Instead it shall be raised and
lowered slowly from time to time which would prevent the concrete around the tremie
from setting. Concreting should be resumed by introducing a little richer concrete (5%
additional cement) with a higher slump for easy displacement of the partly set
concrete.
FIGURE-12
Tremie method
ACERC/DOECE/2010-11/PTS/39
ACERC/DOECE/2010-11/PTS/40
FIGURE-10
Dwall steel web placing
ACERC/DOECE/2010-11/PTS/43
FIGURE-12
Placing complition
FIGURE-13
Crab of dwall machine
ACERC/DOECE/2010-11/PTS/44
Figure-14
Shuttering on girders for slab
ACERC/DOECE/2010-11/PTS/45
Figure-15
Casting of slab
ACERC/DOECE/2010-11/PTS/46
Figure-16
ACERC/DOECE/2010-11/PTS/47
Figure-17
ACERC/DOECE/2010-11/PTS/48
Concrete plant
Figure-18
ACERC/DOECE/2010-11/PTS/49
ACERC/DOECE/2010-11/PTS/50
CONCLUSION
ACERC/DOECE/2010-11/PTS/51
LIST OF REFERENCE
1. Guidance provided by the pwd officer, supervisor & other staff member
2. IS 456:2000
Indian Standard
PLAIN AND REINFORCED CONCRETE CODE OF PRATICE
3. BOOKS:(a)
R.C.C
B.C.PUNMIA
(b)
CONCRETE M.S.SHETTY
(c)
ACERC/DOECE/2010-11/PTS/52