Inverter
Distribution
System
Trafo
Step Up
Control
Panel &
Protection
Centralized
Inverter
Figure 4.7 illustrates the Inverter String array where single series circuit of Photovoltaic panels are connected in
series and string connected to single inverter and a single inverter for each string. Advantage of this
configuration is that the string inverter has a maximum power point tracking capabilities. Maximum Power
Point Tracking (MPPT) separately from each string of Photovoltaic used for reducing the loss of mismatch and
partial shadows so it can increase energy production. The weakness of this configuration is required more
inverter.
String 1
String 2
Ownership, installation, operation, reading and testing of revenue metering equipment must be in accordance
with SPLN or Electric Power Distribution Regulation (Chapter VIII Measurement rules).
4.6.3 TELEMETERING
If PLT EBT connected to a distribution system which operates at a voltage of 20 kV, Telemetering equipment
needed on PLT EBT facility which has capacity of 200 kW or more. PLN will only ask Telemetering, when
options with smaller adverse effects and more effective cost for the real time data provision is not available.
4.6.4 METERING LOCATION
Transaction metering equipment must be installed near Connecting Point, the location of where PLN receives
electrical power from PLT EBT. If the metering location is different from Connecting Point, the mechanism for
calculating energy losses must be negotiated and agreed between PLN and Developer, and noted in the PPA. In
the case of metering PLN must be located in a location which is owned by developer, developer must provide
proper location for all the metering equipment without any fees charged to PLN.
4.6.5 METERING COST
Developers have to bear all the required metering cost, including additional costs caused by the operation and
maintenance of metering equipment by PLN. Metering specifications must comply with SPLN or Electric
Power Distribution Regulation
4.7 COMMUNICATIONS REQUIREMENTS
PLT EBT with an installed capacity of less than 1 MW must have at least one communication channel such as a
telephone or radio, etc., which are used for communication between the PLT EBT and DCC PLN or other PLN
authorized Unit. If PLT EBT installed capacity greater than 1 MW, the PLT EBT should have at least provided
two communication channels for voice and data.
5. TESTING, CERTIFICATION AND COMMISSIONING
This chapter describes the requirements of the testing, certification and commissioning which only for
equipment and PLT EBT connection facilities. Testing, certification, and commissioning of renewable energy
generating units of proposed PLT is outside scope of the Guidelines.
Tests and described criteria in this chapter is taken from IEEE, IEC, UL and California Model Electric Rule 21
About power plant interconnection facilities along with Testing Standards, Certification and Equipment
Commissioning from ESDM and PLN validity.
Tests which are performed on the PLT EBT connection equipment include :
(i)
Type Test
(ii)
Production Test
(iii)
Commissioning Test
(iv)
Periodic Test
These test have to be done for checking compliance within technical standard described in Chapter 4, and then
to make sure that PLT- EBT equipment and parallel operation are not adverse to PLN Distribution System. Tests
carried out on assumption that PLT-EBT has low penetration level on PLN Distribution System. If the level of
penetration is PLT EBT increased in the future, it would require additional requirements and corresponding test
procedures.
This chapter also provides a connection device certification criteria on PLT EBT. Once the equipment is
certified with predetermined criteria, PLT EBT installation can be connected to the PLN Distribution System.
Unless specified in this Chapter that PLN do not need to repeat a design review or retest any certified
equipment.
connected to PLT EBT. Type test for abnormal frequency response should be based on nominal frequency 50 Hz
of electric power system as shown in Table 4.2.
The testing procedure should be able to measure connection equipment accurately for each protection and
control functions in accordance with the technical standards set out in Chapter 4. The testing procedure must be
agreed upon by the manufacturer and approved by PLN.
Table 5.1: Type Testing and Certification Requirements for Equipment Connection
Synchron
ous
generato
r
Inducti
on
Genera
tor
Inverter
Response to distribution
abnormal voltage
Response to distribution
abnormal frequency
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
-
x
x
x
-
x
x
-
Test Type
Anti-islanding
Loss of control circuit
Synchronization
Reset relay
Short Circuit
Power Factor
Connection integrity
Surge withstand
capability
Harmonic distortion
Flicker
Inrush current
DC injection
DC isolation
x
X: Required
O: Required for all self-excitation induction generator and
inverter which operates as a voltage source when connected
to Distribution System.
5. 3 PRODUCTION TEST
Production test conducted to verify the operation of manufactured connection equipment to be used in the field.
Specific protection standards (set out in Chapter 4) allows adjustment of the set point, production test is done to
confirm the setting of the manufacturer of the specific requirements of the standard. In the Production Testing
assumed that the type test was to verify equipment connection suitability with protection standards. Therefore,
the production test only covers about :
(i)
Abnormal voltage response in distribution system,
(ii)
Abnormal frequency response in distribution systems, and
(iii)
The synchronization
This protection function test should be based on the settings and specifications of the manufacturer. Production
test can be done in a factory or being part of Commissioning Tests.
5. 4 COMMISSIONING TEST
5.4.1 GENERAL
The commissioning test must be performed after connection equipment is installed and ready to operate. The
purpose of commissioning tests is to verify that the connection of PLT EBT equipment has been fully euipped
and installed in accordance with the technical standards set out in Chapter 4. Accredited testing agency which
approved by PLN, must perform or directly supervise the commissioning test. Where the operation of the
connecting equipment is integrated and dependent on the operation of the Distribution System PLN,
commissioning test must be coordinated and approved by the DCC PLN or authorized PLN unit. if it is
required, DCC PLN or Authorized PLN Unit can witness the commissioning testing as described in this section.
Commissioning for the outside scope of connection equipment is regulated separately.
Testing agency must prepare a commissioning test report that contains results of all tests and list of last setting
equipment. Commissioning tests need to be repeated until the report is completed and approved by PLN.
5.4.2 TESTING PROCEDURE
Commissioning tests conducted by written procedure. The testing procedure is provided by the manufacturer
and must be approved by the owners of equipment and PLN. Writting procedure for commissioning tests report
should include:
Verification and Inspection
Test Functions in the Field
Function Test of a cease-to-energized
Unintentional islanding function tests, and
Test for revised settings
This procedure is summarized as follows:
5.4.2.1 VERIFICATION AND INSPECTION
a. Verify the connection and equipment installation in accordance to SPLN
b. Setting data used
c. Visual inspection of grounding system implementation according to SPLN
d. Visual inspection and verification of isolation device implementation, if necessary
e. Ensuring that the polarity, the load, and the CT and VT Ratio installation is correct and in accordance with
the design
f. Visual inspection, continuity test or insulation resistance test is done to ensure wiring and control are in
accordance with the manufacturer's drawings and requirements.
g. Connection device protection test with related breaker devices (for example, contactors or CB), Or, it can
be tested during production test to verify that the device is able to open when related breaker protection
devices work, as well as interlocking circuit test between protection devices and breakers if not tested
during Production Test
h. In the three-phase systems, phase sequence in PLT EBT and Distribution System should be inspected, and
it must be ensured both appropriate as it mounted
i. Ensure the functionality of all monitoring provisions as set out in Chapter 5.
5.4.2.2 FIELD FUNCTIONS TEST
Field Functions Test is a production test (included in 5.3) that has not been done at the factory, it must be done
in the field. Production test should be repeated for any change in software or hardware equipment, as required in
Section 5.3.
Several standard for recommended techniques and connection equipment testing in guidelines adopted or
modified from a standards or following international practices :
1. IEEE 1547-2003 (Revised 2008): Standard for Interconnecting Distributed Resources with
Electric Power Systems
2. IEEE 1547.1-2005:Standard Conformance Test Procedures for Equipment Interconnecting Distributed
Resources with Electric Power Systems
3. IEEE 1547.2-2008: Application Guide for IEEE 1547 Standard for Interconnecting Distributed
Resources with Electric Power System
4. IEEE 1547.3-2007: Guide for Monitoring, Information Exchange, and Control of Distributed
Resources Interconnected with Electric Power Systems
5. IEEE 519-1992: IEEE Recommended Practices and Requirements for Harmonic Control in Electric
Power Systems
6. IEC 62109-2: Safety of Power Converters for used in Photovoltaic Power Systems Particular
Requirements for Inverters
7. IEC 61727: Photovoltaic Systems Characteristics of the Utility Interface
8. IEC 62446: Grid Connected Photovoltaic Systems Minimum Requirements for System
Documentation,Commissioning Tests and Inspection
9. IEC 61000-3-7: Limits Assessment of Emission Limits for the Connection of Fluctuating Installations
for MV, HV, and EHV Power Systems
10. IEC 61000-4-15: Testing and Measurement Techniques Flicker Meter
11. IEC 61683: Photovoltaic System Power Conditioners Procedure for Measuring
Efficiency.
12. IEC 61400 21: Measurement and Assessment of Power Quality Characteristics of Grid Connected
Wind Turbines
13. UL 1741: Inverters, Converters, Controllers and Interconnection System Equipment for Use with
Distributed Energy Resources
14. IEC 62116: Test Procedure for Islanding Prevention
15. California Electric Rule 21: Generation Facility Interconnection, California Public Utilities
Commission Decision 00-12-037, December 2000
16. Small Generator Interconnection Procedure, Federal Energy Regulatory Commission, July 2006
Appendix A: Application of PLT EBT Connection (For Power Plant Capacity no larger than 10 MW)
Instruction and General Information
The developer who plans to build PLT EBT (Renewable Energy Power Plant) and sell generated power to PLN
must submit a valid application for PLT EBT connection and parallel operated with PLN Distribution System.
Before delivering the application, developers are advised to understand about "Guidelines for connection
between PLT EBT and PLN Distribution System" (Guidelines). Developers are also advised to obtain
information about the closest connection point to PLN Distribution Systems, distribution feeder, and substation
to propose Connection Point. Developers have to fill about forms " Connection Planning Application for
Renewable Energy Power Plant" (Application) and submit to closest PLN Region or distribution for the
proposed PLT EBT. Submission does not include instructions and general information.
This application also requires certain documents, including, but not limited to, Pre-Feasibility Study Reports,
Environmental Studies and permits from local governments and other authorities to PLT EBT. This
information is required PLN Region or Distribution to conduct a review / study for determining the feasibility
of proposed connection and also recommend appropriate measures to ensure proposed connection and parallel
operation do not have a negative impact on safety, reliability and quality of PLN Power Distribution System.
This application is designed for small and medium PLT EBT (with installed capacity not greater than 10
MW) and is eligible to sell electricity to PLN at specified price in The Regulation of the Energy and Mineral
Resources Minister (ESDM), including Regulation No. 04 ESDM / 2012 on "Purchase Price of Electricity by
PT. PLN (Persero) from Small and Medium Scale PLT EBT or Excess Power ", Regulation No. 17 EMR / 2013
on "Purchase of Electricity by PT. PLN (Persero) from Photovoltaics Solar Power Generation", and Regulation
No. 19 EMR / 2013 on "Purchase of Electricity by PT. PLN (Persero) from Municipal Solid Waste-Based Power
Plants ", Regulation No. 12 EMR / 2014 regarding the "Power Purchase by PT. PLN (Persero) from
Hydroelectric Power Plants ". Regulation of Energy and Mineral Resources Minister are also arranged for small
and medium-scale of PLT EBT which connected to PLN 20 KV Distribution System or lower voltage levels.
Developers can choose Process whether " PLN Fast-Track Review " or "PLN Standards Review" in the
appropriate box of the application form. The proposed PLT EBT will be qualified PLN Fast-Track Review
Process, if it has an installed capacity as follows:
2 MW or less connected to 20 KV Distribution System in Java - Bali, or
200 KW or less connected to 20 KV Distribution System outside Java - Bali, or
30 KW or less connected to the Distribution System 400 V.
Developers can contact PLN Region or Distribution for more information about Application Form Filling.
Incomplete applications will be returned to Developer by PLN Region or distribution. All of the information in
the applications submitted will be kept confidential by PLN. A review / study by PLN Region or distribution
can only be done after the submitted application is complete and valid.
Appendix A: Application of PLT EBT Connection (For Power Plant Capacity no larger than 10 MW)
1. The Applicant who undersigned hereby request to connect the PLT EBT to PLN in accordance with
the Distribution System Code of Connection PLT EBT to PLN Distribution System for (mark on
one box):
Fast-Track Review Process
Standards Review Process
2. Application Connection is for (mark on one box)
Plan a new PLT EBT.
Installed Capacity additions or major modification to the existing PLT EBT.
3. COD date of proposed PLT EBT: ___________ (dd / mm / yr)
4. Does the developer already has permission from the Local Government (Permit Principle):
Yes
No
5. Principle Permit
Issued date : __________________________
Expiry date : __________________________
Number
: __________________________
6. Does the developer already has the Environmental Management Efforts Report (UKL) and
Environmental Monitoring (UPL) or Environmental Studies:
Yes
No
7. Does the developer already has the Environmental Permit for the project:
Yes
No
8. Does the developer already has Pre-Feasibility Study Report / Feasibility Study for proposed PLT
EBT:
Yes
No
9. Does the developer already has scaled drawing which show Plant Site and Connection point to PLN
Distribution System?
Yes
No
10. Does the developer already has One Line Diagram of the system:
Yes
No
Note: One line diagram should indicate installed equipment, including but not limited to generating units, stepup transformers, own use transformer, swiching tool, breakers, and necessary protective equipment. For
Photovoltaic Solar Power and Wind Energy, one line diagram should include distribution line which connect to
various generating units, capacitor banks for generating units, step-up transformers, power transformers and
capacitor banks on the proposed connection Point. One line diagram of the proposed PLT EBT with capacity
greater than 50 kW must be signed and stamped by a professional engineer (qualified professional engineer)
who qualify and be accepted by PLN.
11. Does Developers already have a principles license of Local Government :
Yes
No
12. Developer Name: __________________________
13. Project Name: ______________________________
14. Holder of Principles License
Company Name : __________________________
Company owner : __________________________
15. Contact Person Project:
Owner Name: ____________________________________
Degree: _________________________________________
Postal Address: ___________________________________
___________________________________
Phone: _________________________________________
No. HP: ________________________________________
Fax: ___________________________________________
E-mail: _________________________________________
Authorized Representative (if different):
Name: ____________________________________
Degree: ____________________________________
Postal Address: ______________________________
______________________________
Phone: ____________________________________
No. HP: ____________________________________
Fax: _______________________________________
E-mail: ____________________________________
Engineering Design Consultants (Optional):
Company / Individual:
Name: ____________________________________
Postal Address: _____________________________
_____________________________
Phone: ____________________________________
No. HP: ____________________________________
Fax: _______________________________________
E-mail: ____________________________________
16. Location of the proposed PLT EBT:
Address: ____________________________________________
Administration Location: _______________________________
_______________________________
PLN Official office: __________________________________
GPS Coordinates: _____________________________________
17. Proposed Connecting Point Location to PLN Distribution System:
Address: ________________________________________
Administration Location : ___________________________
GPS Coordinates: _________________________________
a. Connection Voltage to PLN Distribution System: _______ kV
b. Does developer aware about Distribution System conditions (such as voltage fluctuations level of daily,
weekly, and annual, short circuit current level, interruption ammount per year and per week, distance to
the proposed Connecting Point) on proposed connection point:
Yes
No
18. Developer Status:
Is developers a PLN Regular customer at the moment :
If yes, PLN Account Number: _________________________________
Name of Account Holder *: _______________________________
(* must be the same name as Applicant)
19. PLT EBT Energy Sources:
Mini or Micro Hydro (Smaller than 1 MW)
Small scale hydro (1 up to10 MW)
Biomass
Biogas
Biofuel
Municipal waste-based plant
Gas Landfill
Solar Photovoltaic
Wind
Geothermal
Other, please specify: ____
20. General Information of Generation Facilities:
Power Type:
Synchronous
Induction
Inverter-Based
Number of Units: ____
Installed capacity of each unit: ____kW ____KVAR ____Voltage (V)
Generator Connected to:
Single Phase
Three phase
Proposed Installed Capacity: ____kW
c.
Delta
Star
Star grounding method is connected to the neutral point of the secondary windings:
Solid
d.
Ungrounded
Star
Star grounding method is connected to the neutral point of the primary winding:
Solid
Ungrounded
The term of PLN Voltage refers to connection voltage to PLN distribution system and PLT-EBT
Voltage refer to generator / inverter output voltage.
22. Circuit Breaker (PMT) (if any):
Manufacturers: _______ Type: ________ Current Rating: _____ Amps
Breaker Rating: _______ Trip Speed: ____ cycles
23. Relay Protection Splicing (if any)
Mention any functions and give Set Point (maximum and minimum) to any protection equipment or
software
24. Additional information for Synchronous Generator :
Short Circuit Duty information : for each generator, please provide reactance which is expressed in PU
units on Generator basis value :
Xd - Direct Axis Synchronous Reactance: __ pu
X ' D - Direct axis transient reactance: ___ pu
X "d - Direct axis subtransient reactance: ___ pu
X2 - Negative sequence reactance: ___ p.u.
Appendix B: Comparison of Requirements Engineering Guidelines and Rules Indonesia Electric Power
Distribution Electric Power Distribution Regulation issued by EMR in 2009 to establish general rules and
requirements for security, reliability and power quality of the power distribution system. The rules governing
the planning, operation, and connection of distribution system as well as the requirements of metering and
billing settlement. This rule was drawn up with a focus primarily on conventional power plants without any
special requirements for Renewable Energy Power Plant. Since then, a number of policies and government
regulations have made its laws to promote and accelerate the development of renewable energy PLT small and
medium scale.
These guidelines are based on Electric Power Distribution Regulation to provide
protection and control functionality requirements are more detailed and specific in order to ensure the
connection and parallel operation of PLT EBT does not adversely affect PLN Distribution System. Table B-1 is
the ratio of grafting techniques PLT EBT requirements set out in this Code and Electric Power Distribution
Regulation.